M/S P&R INFRAPROJECTS LTD
QUIET OFFICE NO 7, 1ST AND 2ND FLOOR
CHANDIGARH, 160035
INTRODUCTION TO PROJECT
LOCATION MALHIPUR ,SHAHIBPUR KAMAL
DISTT.BEGUSARAI ,BIHAR INDIA
PROJECT SUPER STRUCTURE OF RAIL CUM ROAD
BRIDGE PROJECT OVER RIVER GANGA
PRINCEPLE EMPOLOYER EAST CENTRAL RAILWAY (ECR)
CONTRACTOR BRETHWET BURN JOSOPH (BBJ)
SUB-CONTRACTOR GAMMON INDIA LTD.
SUB-SUB CONTRACTOR P&R INFRA PROJECTS LTD.
TOTAL AWARDED SPANS 125 MTR LONG X 14 NOS .32 MTRS LONG X 1
NO.
TOTAL DIMENSION OF AWARDED
BRIDGE
1782 MTRS LONG ,12.25 MTRS WIDE & 18.5MTR
HIGHT
TOTAL QTY. OF STEEL INVOLVED 28000 MT(APROX)
WT.OF A SINGLE SPAN 1866 MT(APROX)
TOTAL NO.OF PANNELS IN A SPAN 16 NOS (116.625 MT EACH)
CONTRACTUAL VALUE OF 120 CR.(INR) FABRICATION & ERECTION.
INTRODUCTION TO PROJECT
SR NO. TOTAL NO. OF PRINCIPLE MEMBERS IN 1 SPAN QUANTITY
1 BOTTOM CHORD 32
2 BOTTOM CROSS GIRDER 17
3 BOTTOM LATERAL BRACING 16
4 BOX DIAGONAL 12
5 BRAKING BRACING 8
6 END RAKER 4
7 END VERTICAL 4
8 KNEE BRACING 6
9 LOWER DIAGONAL 24
10 MIDDLE CROSS GIRDER 17
11 MIDDLE HORIZONTAL 32
12 PORTAL BRACING 2
13 RAIL STINGER BRACING 16
14 RAIL STRINGER 32
15 ROAD STINGER 80
INTRODUCTION TO PROJECT
SR. NO. TOTAL NO. OF PRINCIPLE MEMBERS IN 1 SPAN QUANTITY
1 LOWER DIAGONAL 24
2 MIDDLE CROSS GIRDER 17
3 MIDDLE HORIZONTAL 32
4 PORTAL BRACING 2
5 RAIL STINGER BRACING 16
6 RAIL STRINGER 32
7 ROAD STINGER 80
8 TOP CHORD 28
9 TOP CROSS GIRDER 15
10 TOP LATERAL BRACING 14
11 UPPER DIAGONAL 24
12 VERTICAL POST 34
PHYSICAL PROGRESSS OF SITE
AS ON DATE 31.07.12
SR.NO JOB DISCRIPTION WORK DONE
1 CUTTING 13,640.859 MT
2 FITUP 12,063.466 MT
3 WELDING 11,679.465 MT
4 DRILLING 10,698.97 MT
5 INSPECTION 9230.42 MT
6 PAINTING 6726.98 MT
7 ERECTION 5150.49 MT
8 RIVETING 2,39,341 NOS
FINANCIAL PROGRES OF SITE
AS ON DATE 31.07.12
1 TOTAL GROSS BILL CLAIMED
2 TOATL GROSS BILL CERTIFIED FROM M/S
GIL
3 TOATL BILL PAID
4 WCT RECOVERED
5 TDS RECOVERED
6 OTHER RECOVERIES
7 BALANCE DUE
8 EXTRA CLAIM
MACHINERY AND EQUIPMENT
SR.NO. ITEM CAPACITY QUANTITY
1 AMERICAN CRANE 9260 125 TON 1 NOS
2 TATA 655 CRANE 45 TON 1 NOS
3 DERRIK CRANE 25 MT AT 25 M
RADIUS
02 NOS
4 HYDRA ESCORT 07 NOS
5 TATA TAILOR 02 NOS
6 ELECTRIC TROLLEY AT ERECTIN 02 NOS
7 DEEP LORRY 10 SET
MACHINERY AND EQUIPMENT
SR.
NO.
EQUIPMENTS QUANTITY CAPACITY
1 ARC WELDING MACHINE 19 NOS 400 Amp
2 SAW WELDING MACHINE FIDDER
(OUTER)
05 NOS
3 SAW WELDING MACHINE FIDDER (INNER) 02 NOS
4 MIG WELDING MACHINE 09 NOS
5 MOTHER OVEN 09 NOS
6 BLOWER MACHINE 07 NOS
7 CARRY OVEN 05 NOS
MACHINERY AND EQUIPMENT
SR.NO EQUIPMENTS QUANTITY CAPACITY
1 PUG CUTTING MACHINE 15 NOS
2 RADIAL DRILL MACHINE 11 NOS
3 RADIAL DRILL MACHINE 03 NOS
4 GANTRY CRANE 01 SET 45 MT
5 D.G. SETS TOATL CAPACITY 01 NOS
6 END MILLING MACHINE 01 NOS
7 CNC CUTTING MACHINE 01 NOS
8 H-BEAM ASSEMBLER 01 NOS
9 FLANGE STRAIGHTNOR 01 NOS
10 PLATE STAGIHTINING PRESS 01 NOS
11 LATHE MACHINE 01 NOS
MACHINERY AND EQUIPMENT
SR. NO. ITEM QUANTITY
1 AIR COMPRESSOR (DIESEL) 10 NOS
2 AIR COMPRESSOR (ELECTRIC 02 NOS
3 MAGNETIC DRILL MACHINE 26 NOS
4 GRINDING MACHINE 24 NOS
5 OIL CUT DRILL MACHINE 01 NOS
6 HYDRAULLIC JACK OF DIFFERENT CAPACITY 18 NOS
7 JACKS OF DIFFERENT CAPACITY 26 NOS
8 TRAVSE JACK 750 TON 04 NOS
9 HYDRAULLIC PUMP 12NOS 12 NOS
10 BAREL PUMP 03 NOS
11 POWER PACK 04 NOS
12 Ff 2 MACHINE 02 NOS
13 HOOPER 04 NOS
MACHINERY AND EQUIPMENT
SR. NO. ITEM QUANTITY
1 CHAIN PULLY BLOCK 17 NOS
2 Pp ROPE PULLY 22 NOS
3 STEEL WIRE ROPE PULLKY 3 LINE 04 NOS
4 RACHET 10 NOS
5 CONTAINER 01 NOS
6 HAND WINCH MACHINE 02 NOS
7 ELECTRIC WINCH MACHINE 01 NOS
8 TURN BUCLKLE 33 NOS
9 HOOK CHOOK MACHINE 08 NOS
10 D SHACKLE 136 NOS
11 GREASSE GUN 05 NOS
MACHINERY AND EQUIPMENT
SR. NO. ITEM QUANTITY
1 METALIZING GUN 06 NOS
2 PLATE CATCHER ( VERTICAL 11 NOS
3 PLATE CATCHER ( HORIZONTAL 08 NOS
4 RIVETING GUN 29 NOS
5 RIMMER MACHINE 13 NOS
6 IMPACT WRENCH- 14 NOS
7 TORQUE WRENCH 09 NOS
8 MULTIPLY TORQUE WRENCH 06 NOS
9 WEB SLING 02 NOS
10 DOLLY MACHINE 28 NOS
11 RIVET BUSTER 07 NOS
12 SCREW LONG JACK 03 NOS
13 PENCIL GRINDING MACHINE 04 NOS
14 JIM SCREW 01 NOS
15 ROCKET JACK 04 NOS
16 WINCH MOTOR WITH TWO HANDLE 02 NOS
17 FIRE EXTINGUSHIER 08 NOS
PLATE STACKING YARD
 PLATE ARE KEPT THICKNESS WISE AND GRADE
WISE AND WILL BE ISSUED ON ISSUE SLIP FROM
STORES ON APPROVAL OF PLANING ENGINEER.
PLATE MARKING
 MARKING OF PLATES IS BEING DONE AS PER
CUTTING PLAN APPROVED BY PLANING ENGINEER
PLATE CUTTING
 AFTER MARKING INSPECTION AS PER CUTTING
PLAN WILL BE CHECKED THEN ONLY CUTTING
WILL BE CARRIED OUT
PLATE GRINDING
FITUP MEMBER IS BEING CARRIED OUT AS
PER B1-2001
BOTTOM CHORD FITUP BOTTOM CHORD FITUP COMPLETE
FITUP OF BOX DIAPHARAGMI GIRDER FITUP
WELDING OF MEMBERS
3 TYPES OF WELDING CONSUMBLES ARE
BEING USED FOR SAW.
1 :W1 & F1 FOR IS – 2062 E-250.
2: W2 & F2 FOR IS -2062 E-350.
3: W4 & F4 FOR IS – 2062 E-450. MIG WELDING
MIG WELDING OF VERTICLE POST
TACK WELD BY SMAW
MEMBER DESTORTION CONTROL
DISTORTION CONTROL OF END X
GIRDER
DISTORTION CONTROL OF END
RACKER
DISTORTION CONTROL OF ST.PLATE FOR FITUP OF BOTTOM CHORD.
MARKING FOR DRILLING
MARKING OF BOTTOM CHORD FOR DRILLING WITH BODY JIG.
DRILLING OF MEMBER
DRILLING OF GUSSET BY RADILL DRILLING OF BOX DIAGONAL
DRILLING OF BOTTOM CHORD
DRILLING OF MID.HORIZONTAL
ULTRASONIC TESTING OF N-CROSS
GIRDER OF SPAN 4
ULTRASONIC TESTING
INSPECTION BY GIL ,BBJ,ECR
INSPECION OF VERTICAL POST WITH GIL ,BBJ,ECR & PLANT DEPO.
SAND BLASTING
SAND BLASTING OF BLB SA-2.1/2 SAND BLASTING OF DIAGONAL SA-2.1/2
METALIZING
METTALIZING OF ROAD STRINGER
INSPECTION OF DFT BY ELCOMETER
PAINTING
PAINTING OF MEMBERS BY SPRAY GUN
FINESHED MATERIAL
MEMBERS READY FOR ASSEMBLY
MEMBER ASSEMBLY FOR
ERECTION
ASSEMBLY OF END VERTICLE IN PROGRESS FOR ERECTION
ASSEMBLED MEMBER BEING READY FOR YARD RIVETING FOR ERECTION
DISPATCH TO ERECTION SITE
DISPATCH OF END RACKER TO ERECTION SITE
MEMBER LOADING FOR ERECTION
 MEMBER ARE LOADED FOR ERECTION POINT
THROUGH AMERICAN CRANE 125 TON TO
TROLLEY FOR ERECTION
LIFTING OF MEMBER LOADING POINT
LIFTING OF MEMBER FOR ERECTIONERECTION POINT
MEMBER TRANSPORTATION FROM
LOADING POINT TO ERECTION POINT
 MEMBER ARE TRANSPORTED THROUGH
TROLLEY TO ERECTION POINT FOR ERECTION
TRANSPORTATION OF MEMBER TO ERECTION POINT BY MANNUAL TROLEY
LIFTING OF MEMBER FOR ERECTION
LIFTING OF MEMBER FOR
ERECTION
 MEMBER IS LIFTED TROUGH DERRIK CRANE FOR
ERECTION AT ERECTION PIOINT
ERECTION OF MEMBER IN PROGRESS
ERECTED MEMBER
TRAVERSE JACK 750 MT CAP.FOR
LIGTING OF SPAN
RIVETING AT ERECTION SITE
RIVETING OF JOINTS IN PROGRESS AT ERECTION FRONT
RIVETED JOINT
ACHIEVEMENTS
 FABRICATION OF 9500 MT IN JUST 10
MONTHS
 SUCCESSFUL LANDING OF 3 SPANS
 TIMELY ERECTION OF TWO NO.DERICK
CRANES
 WELDING QUALITY APPRICIATED BY C.E
(ECR)
 HOLE MATCHING APPRICIATED BY C.E
(ECR)
HURDLES
 LOCAL INTERFERANCE
 SHORTAGE OF STEEL
 ADMINISTRATION PROBLEMS
 CASH FLOW
 MAINTANENCE OF EQUIEPMENTS
WITH OUT FUNDS
 NON CO-OPERATION OF M/S GIL.
 WRONG DEPLOYMENT OF
CONTRACTORS
SAFETY DAY
FLAG HOISTING FOR SAFETY DAY SAFETY SPEECH BY DGM
PRIZE DISTRIBUTION BY DGM FOR SAFETY DAY CLOSING CERMONEY
ENVIRNOMENTAL DAY
PLANTATION BY HONERABLE M.D ON ENVIRNOMENTAL DAY
TEAM P&R AT SITE
WITH
THANKS
AND
REGARDS
MR. R.S. YADAV (G.M.)
MR. AFROZ KAPRA (D.G.M)
AND
TEAM P&R MUNGER SITE
M/S P&R INFRAPROJECT
LTD MUNGER

More Related Content

What's hot

Method aluminum door & window
Method aluminum door & windowMethod aluminum door & window
Method aluminum door & windowMinh Bui Si
 
Manufacturing of crankshaft
Manufacturing of crankshaftManufacturing of crankshaft
Manufacturing of crankshaftSaddamQureshi
 
Harlem Park Building Design Project
Harlem Park Building Design ProjectHarlem Park Building Design Project
Harlem Park Building Design ProjectEd Guerra, P.E.
 
Engineering constructionmethodsguidelinescbs(2)
Engineering constructionmethodsguidelinescbs(2)Engineering constructionmethodsguidelinescbs(2)
Engineering constructionmethodsguidelinescbs(2)Devinder Chawla
 
Concrete method rev02
Concrete method rev02Concrete method rev02
Concrete method rev02Minh Bui Si
 
14325 connels house drafting (1)
14325 connels house drafting (1)14325 connels house drafting (1)
14325 connels house drafting (1)Yousef Riad
 
Method statement for repair of concrete surface
Method statement for repair of concrete surfaceMethod statement for repair of concrete surface
Method statement for repair of concrete surfaceMinh Bui Si
 
Crankshaft Manufacturing Project report
Crankshaft Manufacturing Project report Crankshaft Manufacturing Project report
Crankshaft Manufacturing Project report Omar Amen
 
Reducing The Vibration Level Of The Blast Fan
Reducing The Vibration Level Of The Blast FanReducing The Vibration Level Of The Blast Fan
Reducing The Vibration Level Of The Blast Fanharlandmachacon
 
abermain.firestation
abermain.firestationabermain.firestation
abermain.firestationYousef Riad
 
Method statement painting
Method statement painting Method statement painting
Method statement painting Daniel SLSA CLA
 
Air lock-rotary
Air lock-rotaryAir lock-rotary
Air lock-rotarymkpq pasha
 
IRJET- Design and Finite Element Analysis of Fabricated Panama Chock with 225...
IRJET- Design and Finite Element Analysis of Fabricated Panama Chock with 225...IRJET- Design and Finite Element Analysis of Fabricated Panama Chock with 225...
IRJET- Design and Finite Element Analysis of Fabricated Panama Chock with 225...IRJET Journal
 
Rubber moulded and bridge bearing pads by ameenji rubber private limited, Sec...
Rubber moulded and bridge bearing pads by ameenji rubber private limited, Sec...Rubber moulded and bridge bearing pads by ameenji rubber private limited, Sec...
Rubber moulded and bridge bearing pads by ameenji rubber private limited, Sec...IndiaMART InterMESH Limited
 
2 cm-ms-bld-012 - roof fan & natural ventilator
2   cm-ms-bld-012 - roof fan & natural ventilator2   cm-ms-bld-012 - roof fan & natural ventilator
2 cm-ms-bld-012 - roof fan & natural ventilatorMinh Bui Si
 

What's hot (19)

Method aluminum door & window
Method aluminum door & windowMethod aluminum door & window
Method aluminum door & window
 
Manufacturing of crankshaft
Manufacturing of crankshaftManufacturing of crankshaft
Manufacturing of crankshaft
 
Harlem Park Building Design Project
Harlem Park Building Design ProjectHarlem Park Building Design Project
Harlem Park Building Design Project
 
Engineering constructionmethodsguidelinescbs(2)
Engineering constructionmethodsguidelinescbs(2)Engineering constructionmethodsguidelinescbs(2)
Engineering constructionmethodsguidelinescbs(2)
 
Concrete method rev02
Concrete method rev02Concrete method rev02
Concrete method rev02
 
Rcc design handbook
Rcc design  handbookRcc design  handbook
Rcc design handbook
 
14325 connels house drafting (1)
14325 connels house drafting (1)14325 connels house drafting (1)
14325 connels house drafting (1)
 
Method statement for repair of concrete surface
Method statement for repair of concrete surfaceMethod statement for repair of concrete surface
Method statement for repair of concrete surface
 
Crankshaft Manufacturing Project report
Crankshaft Manufacturing Project report Crankshaft Manufacturing Project report
Crankshaft Manufacturing Project report
 
Column & beam
Column & beamColumn & beam
Column & beam
 
Reducing The Vibration Level Of The Blast Fan
Reducing The Vibration Level Of The Blast FanReducing The Vibration Level Of The Blast Fan
Reducing The Vibration Level Of The Blast Fan
 
abermain.firestation
abermain.firestationabermain.firestation
abermain.firestation
 
Method statement painting
Method statement painting Method statement painting
Method statement painting
 
Casting yard
Casting yardCasting yard
Casting yard
 
Air lock-rotary
Air lock-rotaryAir lock-rotary
Air lock-rotary
 
CASE STUDY OF WAKOTA BRIDGE
CASE STUDY OF WAKOTA BRIDGECASE STUDY OF WAKOTA BRIDGE
CASE STUDY OF WAKOTA BRIDGE
 
IRJET- Design and Finite Element Analysis of Fabricated Panama Chock with 225...
IRJET- Design and Finite Element Analysis of Fabricated Panama Chock with 225...IRJET- Design and Finite Element Analysis of Fabricated Panama Chock with 225...
IRJET- Design and Finite Element Analysis of Fabricated Panama Chock with 225...
 
Rubber moulded and bridge bearing pads by ameenji rubber private limited, Sec...
Rubber moulded and bridge bearing pads by ameenji rubber private limited, Sec...Rubber moulded and bridge bearing pads by ameenji rubber private limited, Sec...
Rubber moulded and bridge bearing pads by ameenji rubber private limited, Sec...
 
2 cm-ms-bld-012 - roof fan & natural ventilator
2   cm-ms-bld-012 - roof fan & natural ventilator2   cm-ms-bld-012 - roof fan & natural ventilator
2 cm-ms-bld-012 - roof fan & natural ventilator
 

Viewers also liked

Presentation on steel, fabrication & erection Munger Ganga Bridge
Presentation on steel, fabrication & erection  Munger Ganga BridgePresentation on steel, fabrication & erection  Munger Ganga Bridge
Presentation on steel, fabrication & erection Munger Ganga BridgeAshish Kumar Yadav
 
Safety month celebration at Munger Ganga Bridge, North End
Safety month celebration at Munger Ganga Bridge, North EndSafety month celebration at Munger Ganga Bridge, North End
Safety month celebration at Munger Ganga Bridge, North EndAshish Kumar Yadav
 
Corporate presentation of P & R Infraprojects Ltd
Corporate presentation of P & R Infraprojects LtdCorporate presentation of P & R Infraprojects Ltd
Corporate presentation of P & R Infraprojects LtdAshish Kumar Yadav
 
Rail and Road Over Rail Bridge
Rail and Road Over Rail BridgeRail and Road Over Rail Bridge
Rail and Road Over Rail BridgeKorutla Harish
 
Inspection and assembly of Open web Girder
Inspection and assembly of Open web GirderInspection and assembly of Open web Girder
Inspection and assembly of Open web GirderAshish Kumar Yadav
 
Munger rail cum road bridge
Munger rail cum road bridgeMunger rail cum road bridge
Munger rail cum road bridgejaiveer singh
 
PPT On Bridge Construction
PPT On Bridge ConstructionPPT On Bridge Construction
PPT On Bridge ConstructionRobin Nirwal
 

Viewers also liked (7)

Presentation on steel, fabrication & erection Munger Ganga Bridge
Presentation on steel, fabrication & erection  Munger Ganga BridgePresentation on steel, fabrication & erection  Munger Ganga Bridge
Presentation on steel, fabrication & erection Munger Ganga Bridge
 
Safety month celebration at Munger Ganga Bridge, North End
Safety month celebration at Munger Ganga Bridge, North EndSafety month celebration at Munger Ganga Bridge, North End
Safety month celebration at Munger Ganga Bridge, North End
 
Corporate presentation of P & R Infraprojects Ltd
Corporate presentation of P & R Infraprojects LtdCorporate presentation of P & R Infraprojects Ltd
Corporate presentation of P & R Infraprojects Ltd
 
Rail and Road Over Rail Bridge
Rail and Road Over Rail BridgeRail and Road Over Rail Bridge
Rail and Road Over Rail Bridge
 
Inspection and assembly of Open web Girder
Inspection and assembly of Open web GirderInspection and assembly of Open web Girder
Inspection and assembly of Open web Girder
 
Munger rail cum road bridge
Munger rail cum road bridgeMunger rail cum road bridge
Munger rail cum road bridge
 
PPT On Bridge Construction
PPT On Bridge ConstructionPPT On Bridge Construction
PPT On Bridge Construction
 

Similar to Rail cum Road Bridge across the Ganga near Munger

WEATHER STRIPPING
WEATHER STRIPPINGWEATHER STRIPPING
WEATHER STRIPPINGKNCwoder
 
15RDM01-2016-Academy Utility Plan
15RDM01-2016-Academy Utility Plan15RDM01-2016-Academy Utility Plan
15RDM01-2016-Academy Utility PlanKevin Stober
 
LIFTING PLAN FLARE-KRB.pdf
LIFTING PLAN FLARE-KRB.pdfLIFTING PLAN FLARE-KRB.pdf
LIFTING PLAN FLARE-KRB.pdfNanangArief2
 
LDavis_work_examples
LDavis_work_examplesLDavis_work_examples
LDavis_work_examplesLoren Davis
 
MISSION STATMENT 2015
MISSION STATMENT 2015MISSION STATMENT 2015
MISSION STATMENT 2015Alauddin Alam
 
Newcast Die Casting
Newcast Die CastingNewcast Die Casting
Newcast Die Castingnr_blore
 
IFA (8999) 16-478196-R.0-Imp
IFA (8999) 16-478196-R.0-ImpIFA (8999) 16-478196-R.0-Imp
IFA (8999) 16-478196-R.0-ImpJay Fraley
 
20200116 tvn3- onesheet of piling works-rv5
20200116  tvn3- onesheet of piling works-rv520200116  tvn3- onesheet of piling works-rv5
20200116 tvn3- onesheet of piling works-rv5Thang234
 
02 QUALITY CONTROL TEST REPORTS FORMATS
02 QUALITY CONTROL TEST REPORTS FORMATS02 QUALITY CONTROL TEST REPORTS FORMATS
02 QUALITY CONTROL TEST REPORTS FORMATSMary Calkins
 
LeanValueStreamOrg-wKanban-FeketeIstvanPic
LeanValueStreamOrg-wKanban-FeketeIstvanPicLeanValueStreamOrg-wKanban-FeketeIstvanPic
LeanValueStreamOrg-wKanban-FeketeIstvanPicIstvan Fekete
 
API-653 Tank Inspection Sample Report
API-653 Tank Inspection Sample ReportAPI-653 Tank Inspection Sample Report
API-653 Tank Inspection Sample ReportAllison Thompson
 
MAIN CANOPY BAJAJ HR(22.09.2016)
MAIN CANOPY BAJAJ HR(22.09.2016)MAIN CANOPY BAJAJ HR(22.09.2016)
MAIN CANOPY BAJAJ HR(22.09.2016)sufiyan shaikh
 
Ahmed Al Balawi-Sea Water Cooling System For Jubail 2
Ahmed Al Balawi-Sea Water Cooling System For Jubail 2Ahmed Al Balawi-Sea Water Cooling System For Jubail 2
Ahmed Al Balawi-Sea Water Cooling System For Jubail 2syed abdul wahab
 
INDUSTRIAL TRAINING REPORT BY ShRiDhAR KaDaM
INDUSTRIAL TRAINING REPORT BY ShRiDhAR KaDaMINDUSTRIAL TRAINING REPORT BY ShRiDhAR KaDaM
INDUSTRIAL TRAINING REPORT BY ShRiDhAR KaDaMshridharthecyberdude
 

Similar to Rail cum Road Bridge across the Ganga near Munger (20)

Connecting Bridge
Connecting BridgeConnecting Bridge
Connecting Bridge
 
Lot information
Lot informationLot information
Lot information
 
3D Drawing Samples
3D Drawing Samples3D Drawing Samples
3D Drawing Samples
 
WEATHER STRIPPING
WEATHER STRIPPINGWEATHER STRIPPING
WEATHER STRIPPING
 
15RDM01-2016-Academy Utility Plan
15RDM01-2016-Academy Utility Plan15RDM01-2016-Academy Utility Plan
15RDM01-2016-Academy Utility Plan
 
LIFTING PLAN FLARE-KRB.pdf
LIFTING PLAN FLARE-KRB.pdfLIFTING PLAN FLARE-KRB.pdf
LIFTING PLAN FLARE-KRB.pdf
 
254815797-PLANOS-Estandares.pdf
254815797-PLANOS-Estandares.pdf254815797-PLANOS-Estandares.pdf
254815797-PLANOS-Estandares.pdf
 
Generator maintenance
Generator maintenance Generator maintenance
Generator maintenance
 
LDavis_work_examples
LDavis_work_examplesLDavis_work_examples
LDavis_work_examples
 
MISSION STATMENT 2015
MISSION STATMENT 2015MISSION STATMENT 2015
MISSION STATMENT 2015
 
Newcast Die Casting
Newcast Die CastingNewcast Die Casting
Newcast Die Casting
 
IFA (8999) 16-478196-R.0-Imp
IFA (8999) 16-478196-R.0-ImpIFA (8999) 16-478196-R.0-Imp
IFA (8999) 16-478196-R.0-Imp
 
20200116 tvn3- onesheet of piling works-rv5
20200116  tvn3- onesheet of piling works-rv520200116  tvn3- onesheet of piling works-rv5
20200116 tvn3- onesheet of piling works-rv5
 
02 QUALITY CONTROL TEST REPORTS FORMATS
02 QUALITY CONTROL TEST REPORTS FORMATS02 QUALITY CONTROL TEST REPORTS FORMATS
02 QUALITY CONTROL TEST REPORTS FORMATS
 
LeanValueStreamOrg-wKanban-FeketeIstvanPic
LeanValueStreamOrg-wKanban-FeketeIstvanPicLeanValueStreamOrg-wKanban-FeketeIstvanPic
LeanValueStreamOrg-wKanban-FeketeIstvanPic
 
API-653 Tank Inspection Sample Report
API-653 Tank Inspection Sample ReportAPI-653 Tank Inspection Sample Report
API-653 Tank Inspection Sample Report
 
MAIN CANOPY BAJAJ HR(22.09.2016)
MAIN CANOPY BAJAJ HR(22.09.2016)MAIN CANOPY BAJAJ HR(22.09.2016)
MAIN CANOPY BAJAJ HR(22.09.2016)
 
GA-01.pdf
GA-01.pdfGA-01.pdf
GA-01.pdf
 
Ahmed Al Balawi-Sea Water Cooling System For Jubail 2
Ahmed Al Balawi-Sea Water Cooling System For Jubail 2Ahmed Al Balawi-Sea Water Cooling System For Jubail 2
Ahmed Al Balawi-Sea Water Cooling System For Jubail 2
 
INDUSTRIAL TRAINING REPORT BY ShRiDhAR KaDaM
INDUSTRIAL TRAINING REPORT BY ShRiDhAR KaDaMINDUSTRIAL TRAINING REPORT BY ShRiDhAR KaDaM
INDUSTRIAL TRAINING REPORT BY ShRiDhAR KaDaM
 

More from Ashish Kumar Yadav

More from Ashish Kumar Yadav (6)

Dobra Chanthi HMV Suspension Bridge Project
Dobra Chanthi HMV Suspension Bridge ProjectDobra Chanthi HMV Suspension Bridge Project
Dobra Chanthi HMV Suspension Bridge Project
 
Dobra Chanthi Suspension bridge Project
Dobra Chanthi Suspension bridge ProjectDobra Chanthi Suspension bridge Project
Dobra Chanthi Suspension bridge Project
 
P & R Brochure
P & R BrochureP & R Brochure
P & R Brochure
 
P&r group ppt
P&r group pptP&r group ppt
P&r group ppt
 
Hira
HiraHira
Hira
 
Presentation for safety month celebration 2012
Presentation for safety month celebration 2012Presentation for safety month celebration 2012
Presentation for safety month celebration 2012
 

Recently uploaded

Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxRoyAbrique
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdfssuser54595a
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppCeline George
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17Celine George
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxOH TEIK BIN
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionSafetyChain Software
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentInMediaRes1
 

Recently uploaded (20)

Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
 
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website App
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptx
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
Staff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSDStaff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSD
 
9953330565 Low Rate Call Girls In Rohini Delhi NCR
9953330565 Low Rate Call Girls In Rohini  Delhi NCR9953330565 Low Rate Call Girls In Rohini  Delhi NCR
9953330565 Low Rate Call Girls In Rohini Delhi NCR
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory Inspection
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media Component
 

Rail cum Road Bridge across the Ganga near Munger

  • 1. M/S P&R INFRAPROJECTS LTD QUIET OFFICE NO 7, 1ST AND 2ND FLOOR CHANDIGARH, 160035
  • 2. INTRODUCTION TO PROJECT LOCATION MALHIPUR ,SHAHIBPUR KAMAL DISTT.BEGUSARAI ,BIHAR INDIA PROJECT SUPER STRUCTURE OF RAIL CUM ROAD BRIDGE PROJECT OVER RIVER GANGA PRINCEPLE EMPOLOYER EAST CENTRAL RAILWAY (ECR) CONTRACTOR BRETHWET BURN JOSOPH (BBJ) SUB-CONTRACTOR GAMMON INDIA LTD. SUB-SUB CONTRACTOR P&R INFRA PROJECTS LTD. TOTAL AWARDED SPANS 125 MTR LONG X 14 NOS .32 MTRS LONG X 1 NO. TOTAL DIMENSION OF AWARDED BRIDGE 1782 MTRS LONG ,12.25 MTRS WIDE & 18.5MTR HIGHT TOTAL QTY. OF STEEL INVOLVED 28000 MT(APROX) WT.OF A SINGLE SPAN 1866 MT(APROX) TOTAL NO.OF PANNELS IN A SPAN 16 NOS (116.625 MT EACH) CONTRACTUAL VALUE OF 120 CR.(INR) FABRICATION & ERECTION.
  • 3. INTRODUCTION TO PROJECT SR NO. TOTAL NO. OF PRINCIPLE MEMBERS IN 1 SPAN QUANTITY 1 BOTTOM CHORD 32 2 BOTTOM CROSS GIRDER 17 3 BOTTOM LATERAL BRACING 16 4 BOX DIAGONAL 12 5 BRAKING BRACING 8 6 END RAKER 4 7 END VERTICAL 4 8 KNEE BRACING 6 9 LOWER DIAGONAL 24 10 MIDDLE CROSS GIRDER 17 11 MIDDLE HORIZONTAL 32 12 PORTAL BRACING 2 13 RAIL STINGER BRACING 16 14 RAIL STRINGER 32 15 ROAD STINGER 80
  • 4. INTRODUCTION TO PROJECT SR. NO. TOTAL NO. OF PRINCIPLE MEMBERS IN 1 SPAN QUANTITY 1 LOWER DIAGONAL 24 2 MIDDLE CROSS GIRDER 17 3 MIDDLE HORIZONTAL 32 4 PORTAL BRACING 2 5 RAIL STINGER BRACING 16 6 RAIL STRINGER 32 7 ROAD STINGER 80 8 TOP CHORD 28 9 TOP CROSS GIRDER 15 10 TOP LATERAL BRACING 14 11 UPPER DIAGONAL 24 12 VERTICAL POST 34
  • 5. PHYSICAL PROGRESSS OF SITE AS ON DATE 31.07.12 SR.NO JOB DISCRIPTION WORK DONE 1 CUTTING 13,640.859 MT 2 FITUP 12,063.466 MT 3 WELDING 11,679.465 MT 4 DRILLING 10,698.97 MT 5 INSPECTION 9230.42 MT 6 PAINTING 6726.98 MT 7 ERECTION 5150.49 MT 8 RIVETING 2,39,341 NOS
  • 6. FINANCIAL PROGRES OF SITE AS ON DATE 31.07.12 1 TOTAL GROSS BILL CLAIMED 2 TOATL GROSS BILL CERTIFIED FROM M/S GIL 3 TOATL BILL PAID 4 WCT RECOVERED 5 TDS RECOVERED 6 OTHER RECOVERIES 7 BALANCE DUE 8 EXTRA CLAIM
  • 7. MACHINERY AND EQUIPMENT SR.NO. ITEM CAPACITY QUANTITY 1 AMERICAN CRANE 9260 125 TON 1 NOS 2 TATA 655 CRANE 45 TON 1 NOS 3 DERRIK CRANE 25 MT AT 25 M RADIUS 02 NOS 4 HYDRA ESCORT 07 NOS 5 TATA TAILOR 02 NOS 6 ELECTRIC TROLLEY AT ERECTIN 02 NOS 7 DEEP LORRY 10 SET
  • 8. MACHINERY AND EQUIPMENT SR. NO. EQUIPMENTS QUANTITY CAPACITY 1 ARC WELDING MACHINE 19 NOS 400 Amp 2 SAW WELDING MACHINE FIDDER (OUTER) 05 NOS 3 SAW WELDING MACHINE FIDDER (INNER) 02 NOS 4 MIG WELDING MACHINE 09 NOS 5 MOTHER OVEN 09 NOS 6 BLOWER MACHINE 07 NOS 7 CARRY OVEN 05 NOS
  • 9. MACHINERY AND EQUIPMENT SR.NO EQUIPMENTS QUANTITY CAPACITY 1 PUG CUTTING MACHINE 15 NOS 2 RADIAL DRILL MACHINE 11 NOS 3 RADIAL DRILL MACHINE 03 NOS 4 GANTRY CRANE 01 SET 45 MT 5 D.G. SETS TOATL CAPACITY 01 NOS 6 END MILLING MACHINE 01 NOS 7 CNC CUTTING MACHINE 01 NOS 8 H-BEAM ASSEMBLER 01 NOS 9 FLANGE STRAIGHTNOR 01 NOS 10 PLATE STAGIHTINING PRESS 01 NOS 11 LATHE MACHINE 01 NOS
  • 10. MACHINERY AND EQUIPMENT SR. NO. ITEM QUANTITY 1 AIR COMPRESSOR (DIESEL) 10 NOS 2 AIR COMPRESSOR (ELECTRIC 02 NOS 3 MAGNETIC DRILL MACHINE 26 NOS 4 GRINDING MACHINE 24 NOS 5 OIL CUT DRILL MACHINE 01 NOS 6 HYDRAULLIC JACK OF DIFFERENT CAPACITY 18 NOS 7 JACKS OF DIFFERENT CAPACITY 26 NOS 8 TRAVSE JACK 750 TON 04 NOS 9 HYDRAULLIC PUMP 12NOS 12 NOS 10 BAREL PUMP 03 NOS 11 POWER PACK 04 NOS 12 Ff 2 MACHINE 02 NOS 13 HOOPER 04 NOS
  • 11. MACHINERY AND EQUIPMENT SR. NO. ITEM QUANTITY 1 CHAIN PULLY BLOCK 17 NOS 2 Pp ROPE PULLY 22 NOS 3 STEEL WIRE ROPE PULLKY 3 LINE 04 NOS 4 RACHET 10 NOS 5 CONTAINER 01 NOS 6 HAND WINCH MACHINE 02 NOS 7 ELECTRIC WINCH MACHINE 01 NOS 8 TURN BUCLKLE 33 NOS 9 HOOK CHOOK MACHINE 08 NOS 10 D SHACKLE 136 NOS 11 GREASSE GUN 05 NOS
  • 12. MACHINERY AND EQUIPMENT SR. NO. ITEM QUANTITY 1 METALIZING GUN 06 NOS 2 PLATE CATCHER ( VERTICAL 11 NOS 3 PLATE CATCHER ( HORIZONTAL 08 NOS 4 RIVETING GUN 29 NOS 5 RIMMER MACHINE 13 NOS 6 IMPACT WRENCH- 14 NOS 7 TORQUE WRENCH 09 NOS 8 MULTIPLY TORQUE WRENCH 06 NOS 9 WEB SLING 02 NOS 10 DOLLY MACHINE 28 NOS 11 RIVET BUSTER 07 NOS 12 SCREW LONG JACK 03 NOS 13 PENCIL GRINDING MACHINE 04 NOS 14 JIM SCREW 01 NOS 15 ROCKET JACK 04 NOS 16 WINCH MOTOR WITH TWO HANDLE 02 NOS 17 FIRE EXTINGUSHIER 08 NOS
  • 13. PLATE STACKING YARD  PLATE ARE KEPT THICKNESS WISE AND GRADE WISE AND WILL BE ISSUED ON ISSUE SLIP FROM STORES ON APPROVAL OF PLANING ENGINEER.
  • 14. PLATE MARKING  MARKING OF PLATES IS BEING DONE AS PER CUTTING PLAN APPROVED BY PLANING ENGINEER
  • 15. PLATE CUTTING  AFTER MARKING INSPECTION AS PER CUTTING PLAN WILL BE CHECKED THEN ONLY CUTTING WILL BE CARRIED OUT
  • 17. FITUP MEMBER IS BEING CARRIED OUT AS PER B1-2001 BOTTOM CHORD FITUP BOTTOM CHORD FITUP COMPLETE FITUP OF BOX DIAPHARAGMI GIRDER FITUP
  • 18. WELDING OF MEMBERS 3 TYPES OF WELDING CONSUMBLES ARE BEING USED FOR SAW. 1 :W1 & F1 FOR IS – 2062 E-250. 2: W2 & F2 FOR IS -2062 E-350. 3: W4 & F4 FOR IS – 2062 E-450. MIG WELDING MIG WELDING OF VERTICLE POST TACK WELD BY SMAW
  • 19. MEMBER DESTORTION CONTROL DISTORTION CONTROL OF END X GIRDER DISTORTION CONTROL OF END RACKER DISTORTION CONTROL OF ST.PLATE FOR FITUP OF BOTTOM CHORD.
  • 20. MARKING FOR DRILLING MARKING OF BOTTOM CHORD FOR DRILLING WITH BODY JIG.
  • 21. DRILLING OF MEMBER DRILLING OF GUSSET BY RADILL DRILLING OF BOX DIAGONAL DRILLING OF BOTTOM CHORD DRILLING OF MID.HORIZONTAL
  • 22. ULTRASONIC TESTING OF N-CROSS GIRDER OF SPAN 4 ULTRASONIC TESTING
  • 23. INSPECTION BY GIL ,BBJ,ECR INSPECION OF VERTICAL POST WITH GIL ,BBJ,ECR & PLANT DEPO.
  • 24. SAND BLASTING SAND BLASTING OF BLB SA-2.1/2 SAND BLASTING OF DIAGONAL SA-2.1/2
  • 25. METALIZING METTALIZING OF ROAD STRINGER INSPECTION OF DFT BY ELCOMETER
  • 28. MEMBER ASSEMBLY FOR ERECTION ASSEMBLY OF END VERTICLE IN PROGRESS FOR ERECTION ASSEMBLED MEMBER BEING READY FOR YARD RIVETING FOR ERECTION
  • 29. DISPATCH TO ERECTION SITE DISPATCH OF END RACKER TO ERECTION SITE
  • 30. MEMBER LOADING FOR ERECTION  MEMBER ARE LOADED FOR ERECTION POINT THROUGH AMERICAN CRANE 125 TON TO TROLLEY FOR ERECTION LIFTING OF MEMBER LOADING POINT LIFTING OF MEMBER FOR ERECTIONERECTION POINT
  • 31. MEMBER TRANSPORTATION FROM LOADING POINT TO ERECTION POINT  MEMBER ARE TRANSPORTED THROUGH TROLLEY TO ERECTION POINT FOR ERECTION TRANSPORTATION OF MEMBER TO ERECTION POINT BY MANNUAL TROLEY LIFTING OF MEMBER FOR ERECTION
  • 32. LIFTING OF MEMBER FOR ERECTION  MEMBER IS LIFTED TROUGH DERRIK CRANE FOR ERECTION AT ERECTION PIOINT ERECTION OF MEMBER IN PROGRESS ERECTED MEMBER TRAVERSE JACK 750 MT CAP.FOR LIGTING OF SPAN
  • 33. RIVETING AT ERECTION SITE RIVETING OF JOINTS IN PROGRESS AT ERECTION FRONT RIVETED JOINT
  • 34. ACHIEVEMENTS  FABRICATION OF 9500 MT IN JUST 10 MONTHS  SUCCESSFUL LANDING OF 3 SPANS  TIMELY ERECTION OF TWO NO.DERICK CRANES  WELDING QUALITY APPRICIATED BY C.E (ECR)  HOLE MATCHING APPRICIATED BY C.E (ECR)
  • 35. HURDLES  LOCAL INTERFERANCE  SHORTAGE OF STEEL  ADMINISTRATION PROBLEMS  CASH FLOW  MAINTANENCE OF EQUIEPMENTS WITH OUT FUNDS  NON CO-OPERATION OF M/S GIL.  WRONG DEPLOYMENT OF CONTRACTORS
  • 36. SAFETY DAY FLAG HOISTING FOR SAFETY DAY SAFETY SPEECH BY DGM PRIZE DISTRIBUTION BY DGM FOR SAFETY DAY CLOSING CERMONEY
  • 37. ENVIRNOMENTAL DAY PLANTATION BY HONERABLE M.D ON ENVIRNOMENTAL DAY
  • 38. TEAM P&R AT SITE
  • 39. WITH THANKS AND REGARDS MR. R.S. YADAV (G.M.) MR. AFROZ KAPRA (D.G.M) AND TEAM P&R MUNGER SITE M/S P&R INFRAPROJECT LTD MUNGER