Analysis of Productivity in Construction
Hari.P1
, Thirumurugan.S2
1
Construction Engineering and Management, Sona College of Technology, India
2
Assistant Professor, Civil Engineering Department, Sona College of Technology, India
Abstract: Construction is the world’s largest cash flowing industry. The successful completion of any construction
project within budget and time is depends on skill of planning manager and control and monitor system of the
construction site. The productivity tracking is one of the effective recent methods to control the project workflow
with available resource. This paper shows how the project should be monitor by productivity of site with the help
of Earned value analysis method. The data which going to analyzed in this paper is real site data and given by
respective planning manager for education purpose. The major activity deals the entire site productivity and
overall performance is taken into consideration. The result of this analysis shows the deviation of planned and
actual work done of activity in site and warning sign to project manager from cost overrun and suggestions to
improve productivity in site. It is possible to predict the exact scenario of construction site by this analysis before
any major occurrence of loss.
Keywords: Site management, Earned value analysis, Monitoring, Productivity, Progress management.
I. INTRODUCTION
India is the developing country and its economy highly depends on Construction industry. Productivity is one of the
critical factors which affect the overall performance of any construction site. It is directly proportional to cost savings and
probability of project. There is no standard definition for productivity for construction operations. In general terms,
construction productivity can be defined as association between an input and an output. Productivity measurement at
construction site enables companies to monitor their expected performance of the project against their site performance.
Construction productivity at site level can be grouped under major activities whose can affect entire construction the
project. The Earned value analysis is one of the best methods among all monitoring method of construction. The project
becomes out of control when there is no control action taken at right place. This analysis method gives current and future
state of project.
OBJECTIVES:
1. To Measure the productivity of the construction site by Earned value analysis.
2. To Provide suggestions and recommendations to increase productivity of the construction site.
II. TYPES OF PRODUCTIVITY
1. Single factor productivity:
Productivity calculated for the single activity like reinforcement, Formwork, Concrete is known as Single factor
productivity.
2. Multi factor productivity:
Productivity calculated for more than one activity like labour and equipment or material and equipment and concrete is
called as Multi factor productivity.
ISSN 2393-8471
International Journal of Recent Research in Civil and Mechanical Engineering (IJRRCME)
Vol. 4, Issue 1, pp: (6-14), Month: April 2017 – September 2017, Available at: www.paperpublications.org
Page | 7
Paper Publications
3. Total factor productivity:
Productivity calculations which include all the activity on the construction site is called as total factor productivity.
In this paper we are taken into consideration only single factor productivity
III. EARNED VALUE ANALYSIS
Earned Value Analysis (EVA) is a method of measuring performance .Earned value is a program management technique
that uses work progress to indicate what will happen in the future (Bhosekar & Vyas, 2012). EVA is a three dimensional
approach and is based on planned value (PV), Earned value (EV) and actual cost (AC). It proves the earn value of a
completed work and compares it with actual cost and planned cost to determine the project performance and forecast its
future trends. EVA is also described as an integrated, indirect or remote monitoring technique for the complex interaction
of time and cost parameters to provide the performance measurement of a whole project. It is an effective and useful
project tool that helps the client and as well as contractor to assess the project performance.
IV. DATA COLLECTED FOR ANALYSIS
The analysis for productivity of site needs field data about project. These are the basic data should be collected from the
site.
1. Monthly actual work done of the activity from progress report
2. Daily progress report
3. Monthly certified bills
After data collection EVA technique used to predict current state of project and expected future progress of the project to
avoid deviation from the planned value of activity and increase productivity.
V. MEASUREMENT OF PRODUCTIVITY
Productivity for individual projects can be measured upon project completion or during construction. In this analysis we
using simple equation used by the construction industry development board [CIDB] Singapore to compute the monthly
productivity of the individual projects. The Input and Output values are planned quantity and actual quantity for the
period of a month. We can calculate any kind of activity whose input and output value are known.
Productivity = Input/Output
VI. CASE STUDY
In order to achieve the objectives, data was collected from the construction site. This case study is a resort construction in
konkan coastal region of India. The list of important items about project is,
 Type of contract ‘Cost plus’
 Total cost of contract is 66 cores
 Duration of the contract 24 months
The scope of the project is complete finishing of building civil work as per architectural and structural drawing. The
project is already delayed due to low productivity.
As it is cost plus type of contract, delay of major activities make impact on the project and productivity of the project.
Below table 1.1 shows planned and executed quantity of the all activity. The monthly executed quantity taken from
monthly progress report of the site.
ISSN 2393-8471
International Journal of Recent Research in Civil and Mechanical Engineering (IJRRCME)
Vol. 4, Issue 1, pp: (6-14), Month: April 2017 – September 2017, Available at: www.paperpublications.org
Page | 8
Paper Publications
VII. RESULT AND DISCUSSION
Table 1.1 Planned and Executed quantity of activities for the month February, March, and April 2016
S.no Description Unit Feb-16 Mar-16 Apr-16
Planned Executed Planned Executed Planned Executed
1 Earthwork m3 1100.00 488.8 2000.00 0 2470.30 0
2 Rubble soling m3 276.00 255.5 214.47 96.6 214.47 0
3 PCC m3 168.00 93.93 103.00 28.5 128.14 9.9
4 Plum concrete m3 75.00 20.24 150.00 5 260.00 10.2
5 Anti-termite m2 500.00 10 63.00 0 400.00 0
6 RCC m3 248.76 199.8 533.91 140.45 429.49 156.3
7 Reinforcement MT 22.00 24 49.00 16 43.00 14
8 Formwork m2 909.20 1238.9 3138.70 193.41 3656.04 727.1
10 Masonry work m2 1300.00 942.19 2300.00 76.67 4001.71 1304.32
11 Wall finishes m2 1420.00 1299 4350.00 133.33 1064.28 627.86
Table 1.2 Planned and Executed quantity of activities for the month of May, June and July 2016
S.n
o
Description Unit May-16 Jun-16 Jul-16
Planned Executed Planned Executed Planned Executed
1 Earthwork m3 3000.00 0 3000.00 144.58 0.00 0
2 Rubble soling m3 104.76 0 104.76 4.88 66.12 49.93
3 PCC m3 52.50 16.3 52.50 13.9 40.00 59.2
4 Plum concrete m3 207.64 42.82 207.64 96.95 60.00 175.53
5 Anti-termite m2 0.00 0 0.00 0 0.00 0
6 RCC m3 445.58 246.99 0.00 87.35 166.96 262.86
7 Reinforcement MT 34.24 8.72 0.00 10.13 17.68 19.08
8 Formwork m2 3248.40 599.52 0.00 818.16 923.06 1064.1
10 Masonry work m2 3000.00 295.95 379.25 374.44 851.08 376.43
11 Wall finishes m2 4050.00 638.24 500.00 1118.82 3533.16 985.46
Table 1.3 Planned and Executed quantity of activities for the month of August, September and October 2016
S.no Description Unit Aug-16 Sep-16 Oct-16
Planned Executed Planned Executed Planned Executed
1 Earthwork m3 0.00 0 0.00 0 0.00 0
2 Rubble soling m3 66.11 73.74 0.00 30.97 14.66 7
3 PCC m3 40.56 13.2 40.00 12.6 13.79 19.8
4 Plum concrete m3 42.36 2.57 60.00 8.5 26.21 93.7
5 Anti-termite m2 0.00 0 0.00 0 400.00 0
6 RCC m3 203.70 33.78 278.49 80.01 400.75 68.84
7 Reinforcement MT 7.82 5.11 3.54 11.7 43.88 7.72
8 Formwork m2 965.45 259.23 1031.33 250.89 1790.68 507.39
10 Masonry work m2 851.08 82.62 774.42 158.83 1684.65 55.47
11 Wall finishes m2 3533.16 298.65 3533.16 754.57 4273.21 88.79
ISSN 2393-8471
International Journal of Recent Research in Civil and Mechanical Engineering (IJRRCME)
Vol. 4, Issue 1, pp: (6-14), Month: April 2017 – September 2017, Available at: www.paperpublications.org
Page | 9
Paper Publications
Table 1.4 Planned and Executed quantity of activities for the month of November, December and January 2016
S.no Description Unit Nov-15 Dec-15 Jan-16
Planned Executed Planned Executed Planned Executed
1 Earthwork m3 0.00 0 0.00 0 0.00 0
2 Rubble soling m3 11.66 9.9 1.76 0 0.00 0
3 PCC m3 13.79 0.9 12.29 16.6 1.59 1.6
4 Plum concrete m3 26.21 0 70.00 53.3 30.00 0
5 Anti-termite m2 0.00 0 0.00 0 0.00 0
6 RCC m3 400.75 27.81 160.17 49.97 110.00 38.51
7 Reinforcement MT 23.88 7.48 13.95 9.16 9.46 1.14
8 Formwork m2 838.14 529.14 863.86 328.79 538.76 74.48
10 Masonry work m2 918.56 523.19 685.42 743.31 273.43 113.97
11 Wall finishes m2 4273.21 582.42 4128.09 963.48 1377.13 226.58
Table 1.5 Productivity of activities for the month of February 2016 to January 2017
S.no Description Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
1 Earthwork 44.44 0.00 0.00 0.00 4.82 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2 Rubble soling 92.57 45.04 0.00 0.00 4.66 75.51 111.54 100.00 47.75 84.91 0.00 0.00
3 PCC 55.91 27.67 7.73 31.05 26.48 148.00 32.54 31.50 143.58 6.53 135.07 100.63
4 Plum concrete 26.99 3.33 3.92 20.62 46.69 292.55 6.07 14.17 357.50 0.00 76.14 0.00
5 Anti-termite 2.00 0.00 0.00 0.00 100.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6 RCC 80.32 26.31 36.39 55.43 100.00 157.44 16.58 28.73 17.18 6.94 31.20 35.01
7 Reinforcement 109.09 32.65 32.56 25.47 100.00 107.92 65.35 330.51 17.59 31.32 65.66 12.05
8 Formwork 136.26 6.16 19.89 18.46 100.00 115.28 26.85 24.33 28.34 63.13 38.06 13.82
9 Masonry work 72.48 3.33 32.59 9.87 98.73 44.23 9.71 20.51 3.29 56.96 108.45 41.68
10 Wall finishes 91.48 3.07 58.99 15.76 223.76 27.89 8.45 21.36 2.08 13.63 23.34 16.45
Graph 1.1 Productivity of Earthwork for the month of February 2016 to January 2017
ISSN 2393-8471
International Journal of Recent Research in Civil and Mechanical Engineering (IJRRCME)
Vol. 4, Issue 1, pp: (6-14), Month: April 2017 – September 2017, Available at: www.paperpublications.org
Page | 10
Paper Publications
Graph 1.2 Productivity of Rubble soling for the month of February 2016 to January 2017
Graph 1.3 Productivity of PCC for the month of February 2016 to January 2017
Graph 1.4 Productivity of Plum concrete for the month of February 2016 to January 2017
ISSN 2393-8471
International Journal of Recent Research in Civil and Mechanical Engineering (IJRRCME)
Vol. 4, Issue 1, pp: (6-14), Month: April 2017 – September 2017, Available at: www.paperpublications.org
Page | 11
Paper Publications
Graph 1.5 Productivity of Anti-termite for the month of February 2016 to January 2017
Graph 1.6 Productivity of RCC for the month of February 2016 to January 2017
Graph 1.7 Productivity of Reinforcement for the month of February 2016 to January 2017
ISSN 2393-8471
International Journal of Recent Research in Civil and Mechanical Engineering (IJRRCME)
Vol. 4, Issue 1, pp: (6-14), Month: April 2017 – September 2017, Available at: www.paperpublications.org
Page | 12
Paper Publications
Graph 1.8 Productivity of formwork for the month of February 2016 to January 2017
Graph 1.9 Productivity of masonry work for the month of February 2016 to January 2017
Graph 1.10 Productivity of Wall finishes for the month of February 2016 to January 2017
ISSN 2393-8471
International Journal of Recent Research in Civil and Mechanical Engineering (IJRRCME)
Vol. 4, Issue 1, pp: (6-14), Month: April 2017 – September 2017, Available at: www.paperpublications.org
Page | 13
Paper Publications
VIII. CONCLUSION
Project is already delayed due to low productivity. From the graph 1.1 to 1.10 shows the productivity of all activities for
the month February 2016 to January 2017. The expected productivity is 100 % from the site management but it is not
achieved frequently. Maximum productivity of the site is 357.5 % that is plum concrete at October 2016 since the activity
has high scope at site. Minimum productivity of the site is 2 % that is anti-termite treatment since no scope at February
2016. The Following table 1.6 shows maximum and minimum productivity of activities for the month of February 2016
to January 2017.
Table 1.6 shows maximum and minimum productivity of activities for the month of February 2016 to January 2017.
S.no Description Maximum Minimum
1 Earthwork 44.44 0
2 Rubble soling 111.54 0
3 PCC 148.00 6.53
4 Plum concrete 357.50 0
5 Anti-termite 100 0
6 RCC 157.44 6.94
7 Reinforcement 330.51 12.05
8 Formwork 136.26 6.16
9 Masonry work 108.45 3.29
10 Wall finishes 223.76 2.08
IX. SUGGESTION AND RECOMMENDATIONS
From the result of table 1.5 and table 1.6 the analyst concludes improper planning definitely reduces the productivity so
while planning the planning manager should consider the previous month planned and achieved quantity for the activity
and the reason submitted by site person for not achieved the target quantity. Site conditions and manpower availability
also gives major impact on planning. The substantial recommendations for productivity improvement at site are,
 Appointing potential planning manager
 Use updated and effective planning technique
 Consider site condition and pervious month productivity data while planning for upcoming month
 Conduct Weekly meeting
 Effective record keeping
 Direct inspection of site by planning manager
 Increase involvement site person in planning
 Consider suggestions of site persons in planning
 Allocate Incentive, extra wages for successful target achievement
REFERENCES
[1] Varma Santosh and Apte (2014) Productivity in Building Construction, IOSR-JMCE Volume 10, Issue 5
[2] Pramod M, Phaniraj and Srinivasan (2014) Monitoring System for Project Cost Control in Construction Industry,
[3] International Journal of Engineering Research & Technology (IJERT) ISSN: 2278-0181 Vol. 3 Issue 7, July – 2014
[4] Mohd Faris Khamidi and Waris Ali Khan and Arazi Idrus (2011) The Cost Monitoring of Construction Projects
Through
ISSN 2393-8471
International Journal of Recent Research in Civil and Mechanical Engineering (IJRRCME)
Vol. 4, Issue 1, pp: (6-14), Month: April 2017 – September 2017, Available at: www.paperpublications.org
Page | 14
Paper Publications
[5] Earned Value Analysis International Conference on Economics and Finance Research IPEDR vol.4
[6] Mostafa E. Shehata and Khaled M. El-Gohary (2011) Towards improving construction labor productivity and
projects’ Performance Alexandria Engineering journal vol 50, 321-330
[7] Syed Ali Dilawer (2014) Control the loss of labor productivity IJCSER volume 2, Issue 1, pp: 104-110
[8] Thiyagu.C and M.Dheenadhayalan (2016) Construction labor productivity and its improvement IRJET volume : 02
issue : 08
[9] Vaishant Gupta (2014) Improvement of construction labor productivity in chambal region IJRET Volume : 3 Issus:
10
[10] Yogendrakumar (2013) Productivity Analysis of Small Construction Projects in India Asaian journal of Applied
sciences,
[11] Sudam Chavan and Hemant Salunkhe (2016) A study on labor productivity in construction industry IJER volume no
5, issue Special 1 pp: 247-249.
[12] Shreyash Raut and Karan Sawant (2013) Effect of Project Cost and Time Monitoring on Progress of Construction
Project IJRET,Volume :02 Issue:12

More Related Content

Similar to Analysis of Productivity in Construction

EJMCM_Volume 7_Issue 4_Pages 310-318.pdf
EJMCM_Volume 7_Issue 4_Pages 310-318.pdfEJMCM_Volume 7_Issue 4_Pages 310-318.pdf
EJMCM_Volume 7_Issue 4_Pages 310-318.pdfkripeshdubey1
 
Research study on Optimization of Cost and Duration with Line of Balance by U...
Research study on Optimization of Cost and Duration with Line of Balance by U...Research study on Optimization of Cost and Duration with Line of Balance by U...
Research study on Optimization of Cost and Duration with Line of Balance by U...IRJET Journal
 
Vocational training report l&t
Vocational training report l&tVocational training report l&t
Vocational training report l&tNishant Pandey
 
Scheduling and Financial Analysis of a High Rise Building
Scheduling and Financial Analysis of a High Rise BuildingScheduling and Financial Analysis of a High Rise Building
Scheduling and Financial Analysis of a High Rise Buildingiosrjce
 
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET Journal
 
Evaluate the effective resource management through pert analysis
Evaluate the effective resource management through pert analysisEvaluate the effective resource management through pert analysis
Evaluate the effective resource management through pert analysiseSAT Publishing House
 
Construction project scheduling and quality control
Construction project scheduling and quality controlConstruction project scheduling and quality control
Construction project scheduling and quality controlmonishkumark
 
FINAL_PRESENTATION_2022_labour Productivity_Biprendra.pptx
FINAL_PRESENTATION_2022_labour Productivity_Biprendra.pptxFINAL_PRESENTATION_2022_labour Productivity_Biprendra.pptx
FINAL_PRESENTATION_2022_labour Productivity_Biprendra.pptxKaushalKumar522651
 
IRJET- Optimization of Time and Cost of Building Construction using Fast ...
IRJET-  	  Optimization of Time and Cost of Building Construction using Fast ...IRJET-  	  Optimization of Time and Cost of Building Construction using Fast ...
IRJET- Optimization of Time and Cost of Building Construction using Fast ...IRJET Journal
 
Application of last planner system
Application of last planner systemApplication of last planner system
Application of last planner systemAnshi Verma
 
Tracking and Management of Construction Projects using Primavera
Tracking and Management of Construction Projects using PrimaveraTracking and Management of Construction Projects using Primavera
Tracking and Management of Construction Projects using PrimaveraIRJET Journal
 
Estimation and Evaluation of G+3 Residential Building
Estimation and Evaluation of G+3 Residential BuildingEstimation and Evaluation of G+3 Residential Building
Estimation and Evaluation of G+3 Residential Buildingvivatechijri
 
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...IRJET Journal
 
Effect of project cost and time monitoring on
Effect of project cost and time monitoring onEffect of project cost and time monitoring on
Effect of project cost and time monitoring oneSAT Publishing House
 
Effect of project cost and time monitoring on progress of construction projct
Effect of project cost and time monitoring on progress of construction projctEffect of project cost and time monitoring on progress of construction projct
Effect of project cost and time monitoring on progress of construction projcteSAT Journals
 
Analysis and Design of Commercial Building using ETABS
Analysis and Design of Commercial Building using ETABSAnalysis and Design of Commercial Building using ETABS
Analysis and Design of Commercial Building using ETABSIRJET Journal
 
Developing an effective workflow module for productivity analysis using stati...
Developing an effective workflow module for productivity analysis using stati...Developing an effective workflow module for productivity analysis using stati...
Developing an effective workflow module for productivity analysis using stati...eSAT Journals
 
Time Cost Trade Off
Time Cost Trade OffTime Cost Trade Off
Time Cost Trade Offssuserfe1b72
 

Similar to Analysis of Productivity in Construction (20)

EJMCM_Volume 7_Issue 4_Pages 310-318.pdf
EJMCM_Volume 7_Issue 4_Pages 310-318.pdfEJMCM_Volume 7_Issue 4_Pages 310-318.pdf
EJMCM_Volume 7_Issue 4_Pages 310-318.pdf
 
Research study on Optimization of Cost and Duration with Line of Balance by U...
Research study on Optimization of Cost and Duration with Line of Balance by U...Research study on Optimization of Cost and Duration with Line of Balance by U...
Research study on Optimization of Cost and Duration with Line of Balance by U...
 
Vocational training report l&t
Vocational training report l&tVocational training report l&t
Vocational training report l&t
 
A012610106
A012610106A012610106
A012610106
 
Scheduling and Financial Analysis of a High Rise Building
Scheduling and Financial Analysis of a High Rise BuildingScheduling and Financial Analysis of a High Rise Building
Scheduling and Financial Analysis of a High Rise Building
 
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
 
Evaluate the effective resource management through pert analysis
Evaluate the effective resource management through pert analysisEvaluate the effective resource management through pert analysis
Evaluate the effective resource management through pert analysis
 
Construction project scheduling and quality control
Construction project scheduling and quality controlConstruction project scheduling and quality control
Construction project scheduling and quality control
 
FINAL_PRESENTATION_2022_labour Productivity_Biprendra.pptx
FINAL_PRESENTATION_2022_labour Productivity_Biprendra.pptxFINAL_PRESENTATION_2022_labour Productivity_Biprendra.pptx
FINAL_PRESENTATION_2022_labour Productivity_Biprendra.pptx
 
IRJET- Optimization of Time and Cost of Building Construction using Fast ...
IRJET-  	  Optimization of Time and Cost of Building Construction using Fast ...IRJET-  	  Optimization of Time and Cost of Building Construction using Fast ...
IRJET- Optimization of Time and Cost of Building Construction using Fast ...
 
Application of last planner system
Application of last planner systemApplication of last planner system
Application of last planner system
 
Tracking and Management of Construction Projects using Primavera
Tracking and Management of Construction Projects using PrimaveraTracking and Management of Construction Projects using Primavera
Tracking and Management of Construction Projects using Primavera
 
Estimation and Evaluation of G+3 Residential Building
Estimation and Evaluation of G+3 Residential BuildingEstimation and Evaluation of G+3 Residential Building
Estimation and Evaluation of G+3 Residential Building
 
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...
 
Effect of project cost and time monitoring on
Effect of project cost and time monitoring onEffect of project cost and time monitoring on
Effect of project cost and time monitoring on
 
Effect of project cost and time monitoring on progress of construction projct
Effect of project cost and time monitoring on progress of construction projctEffect of project cost and time monitoring on progress of construction projct
Effect of project cost and time monitoring on progress of construction projct
 
Analysis and Design of Commercial Building using ETABS
Analysis and Design of Commercial Building using ETABSAnalysis and Design of Commercial Building using ETABS
Analysis and Design of Commercial Building using ETABS
 
Developing an effective workflow module for productivity analysis using stati...
Developing an effective workflow module for productivity analysis using stati...Developing an effective workflow module for productivity analysis using stati...
Developing an effective workflow module for productivity analysis using stati...
 
20320140503025
2032014050302520320140503025
20320140503025
 
Time Cost Trade Off
Time Cost Trade OffTime Cost Trade Off
Time Cost Trade Off
 

Recently uploaded

Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...121011101441
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...Chandu841456
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)Dr SOUNDIRARAJ N
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptSAURABHKUMAR892774
 

Recently uploaded (20)

Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.ppt
 

Analysis of Productivity in Construction

  • 1. ISSN 2393-8471 International Journal of Recent Research in Civil and Mechanical Engineering (IJRRCME) Vol. 4, Issue 1, pp: (6-14), Month: April 2017 – September 2017, Available at: www.paperpublications.org Page | 6 Paper Publications Analysis of Productivity in Construction Hari.P1 , Thirumurugan.S2 1 Construction Engineering and Management, Sona College of Technology, India 2 Assistant Professor, Civil Engineering Department, Sona College of Technology, India Abstract: Construction is the world’s largest cash flowing industry. The successful completion of any construction project within budget and time is depends on skill of planning manager and control and monitor system of the construction site. The productivity tracking is one of the effective recent methods to control the project workflow with available resource. This paper shows how the project should be monitor by productivity of site with the help of Earned value analysis method. The data which going to analyzed in this paper is real site data and given by respective planning manager for education purpose. The major activity deals the entire site productivity and overall performance is taken into consideration. The result of this analysis shows the deviation of planned and actual work done of activity in site and warning sign to project manager from cost overrun and suggestions to improve productivity in site. It is possible to predict the exact scenario of construction site by this analysis before any major occurrence of loss. Keywords: Site management, Earned value analysis, Monitoring, Productivity, Progress management. I. INTRODUCTION India is the developing country and its economy highly depends on Construction industry. Productivity is one of the critical factors which affect the overall performance of any construction site. It is directly proportional to cost savings and probability of project. There is no standard definition for productivity for construction operations. In general terms, construction productivity can be defined as association between an input and an output. Productivity measurement at construction site enables companies to monitor their expected performance of the project against their site performance. Construction productivity at site level can be grouped under major activities whose can affect entire construction the project. The Earned value analysis is one of the best methods among all monitoring method of construction. The project becomes out of control when there is no control action taken at right place. This analysis method gives current and future state of project. OBJECTIVES: 1. To Measure the productivity of the construction site by Earned value analysis. 2. To Provide suggestions and recommendations to increase productivity of the construction site. II. TYPES OF PRODUCTIVITY 1. Single factor productivity: Productivity calculated for the single activity like reinforcement, Formwork, Concrete is known as Single factor productivity. 2. Multi factor productivity: Productivity calculated for more than one activity like labour and equipment or material and equipment and concrete is called as Multi factor productivity.
  • 2. ISSN 2393-8471 International Journal of Recent Research in Civil and Mechanical Engineering (IJRRCME) Vol. 4, Issue 1, pp: (6-14), Month: April 2017 – September 2017, Available at: www.paperpublications.org Page | 7 Paper Publications 3. Total factor productivity: Productivity calculations which include all the activity on the construction site is called as total factor productivity. In this paper we are taken into consideration only single factor productivity III. EARNED VALUE ANALYSIS Earned Value Analysis (EVA) is a method of measuring performance .Earned value is a program management technique that uses work progress to indicate what will happen in the future (Bhosekar & Vyas, 2012). EVA is a three dimensional approach and is based on planned value (PV), Earned value (EV) and actual cost (AC). It proves the earn value of a completed work and compares it with actual cost and planned cost to determine the project performance and forecast its future trends. EVA is also described as an integrated, indirect or remote monitoring technique for the complex interaction of time and cost parameters to provide the performance measurement of a whole project. It is an effective and useful project tool that helps the client and as well as contractor to assess the project performance. IV. DATA COLLECTED FOR ANALYSIS The analysis for productivity of site needs field data about project. These are the basic data should be collected from the site. 1. Monthly actual work done of the activity from progress report 2. Daily progress report 3. Monthly certified bills After data collection EVA technique used to predict current state of project and expected future progress of the project to avoid deviation from the planned value of activity and increase productivity. V. MEASUREMENT OF PRODUCTIVITY Productivity for individual projects can be measured upon project completion or during construction. In this analysis we using simple equation used by the construction industry development board [CIDB] Singapore to compute the monthly productivity of the individual projects. The Input and Output values are planned quantity and actual quantity for the period of a month. We can calculate any kind of activity whose input and output value are known. Productivity = Input/Output VI. CASE STUDY In order to achieve the objectives, data was collected from the construction site. This case study is a resort construction in konkan coastal region of India. The list of important items about project is,  Type of contract ‘Cost plus’  Total cost of contract is 66 cores  Duration of the contract 24 months The scope of the project is complete finishing of building civil work as per architectural and structural drawing. The project is already delayed due to low productivity. As it is cost plus type of contract, delay of major activities make impact on the project and productivity of the project. Below table 1.1 shows planned and executed quantity of the all activity. The monthly executed quantity taken from monthly progress report of the site.
  • 3. ISSN 2393-8471 International Journal of Recent Research in Civil and Mechanical Engineering (IJRRCME) Vol. 4, Issue 1, pp: (6-14), Month: April 2017 – September 2017, Available at: www.paperpublications.org Page | 8 Paper Publications VII. RESULT AND DISCUSSION Table 1.1 Planned and Executed quantity of activities for the month February, March, and April 2016 S.no Description Unit Feb-16 Mar-16 Apr-16 Planned Executed Planned Executed Planned Executed 1 Earthwork m3 1100.00 488.8 2000.00 0 2470.30 0 2 Rubble soling m3 276.00 255.5 214.47 96.6 214.47 0 3 PCC m3 168.00 93.93 103.00 28.5 128.14 9.9 4 Plum concrete m3 75.00 20.24 150.00 5 260.00 10.2 5 Anti-termite m2 500.00 10 63.00 0 400.00 0 6 RCC m3 248.76 199.8 533.91 140.45 429.49 156.3 7 Reinforcement MT 22.00 24 49.00 16 43.00 14 8 Formwork m2 909.20 1238.9 3138.70 193.41 3656.04 727.1 10 Masonry work m2 1300.00 942.19 2300.00 76.67 4001.71 1304.32 11 Wall finishes m2 1420.00 1299 4350.00 133.33 1064.28 627.86 Table 1.2 Planned and Executed quantity of activities for the month of May, June and July 2016 S.n o Description Unit May-16 Jun-16 Jul-16 Planned Executed Planned Executed Planned Executed 1 Earthwork m3 3000.00 0 3000.00 144.58 0.00 0 2 Rubble soling m3 104.76 0 104.76 4.88 66.12 49.93 3 PCC m3 52.50 16.3 52.50 13.9 40.00 59.2 4 Plum concrete m3 207.64 42.82 207.64 96.95 60.00 175.53 5 Anti-termite m2 0.00 0 0.00 0 0.00 0 6 RCC m3 445.58 246.99 0.00 87.35 166.96 262.86 7 Reinforcement MT 34.24 8.72 0.00 10.13 17.68 19.08 8 Formwork m2 3248.40 599.52 0.00 818.16 923.06 1064.1 10 Masonry work m2 3000.00 295.95 379.25 374.44 851.08 376.43 11 Wall finishes m2 4050.00 638.24 500.00 1118.82 3533.16 985.46 Table 1.3 Planned and Executed quantity of activities for the month of August, September and October 2016 S.no Description Unit Aug-16 Sep-16 Oct-16 Planned Executed Planned Executed Planned Executed 1 Earthwork m3 0.00 0 0.00 0 0.00 0 2 Rubble soling m3 66.11 73.74 0.00 30.97 14.66 7 3 PCC m3 40.56 13.2 40.00 12.6 13.79 19.8 4 Plum concrete m3 42.36 2.57 60.00 8.5 26.21 93.7 5 Anti-termite m2 0.00 0 0.00 0 400.00 0 6 RCC m3 203.70 33.78 278.49 80.01 400.75 68.84 7 Reinforcement MT 7.82 5.11 3.54 11.7 43.88 7.72 8 Formwork m2 965.45 259.23 1031.33 250.89 1790.68 507.39 10 Masonry work m2 851.08 82.62 774.42 158.83 1684.65 55.47 11 Wall finishes m2 3533.16 298.65 3533.16 754.57 4273.21 88.79
  • 4. ISSN 2393-8471 International Journal of Recent Research in Civil and Mechanical Engineering (IJRRCME) Vol. 4, Issue 1, pp: (6-14), Month: April 2017 – September 2017, Available at: www.paperpublications.org Page | 9 Paper Publications Table 1.4 Planned and Executed quantity of activities for the month of November, December and January 2016 S.no Description Unit Nov-15 Dec-15 Jan-16 Planned Executed Planned Executed Planned Executed 1 Earthwork m3 0.00 0 0.00 0 0.00 0 2 Rubble soling m3 11.66 9.9 1.76 0 0.00 0 3 PCC m3 13.79 0.9 12.29 16.6 1.59 1.6 4 Plum concrete m3 26.21 0 70.00 53.3 30.00 0 5 Anti-termite m2 0.00 0 0.00 0 0.00 0 6 RCC m3 400.75 27.81 160.17 49.97 110.00 38.51 7 Reinforcement MT 23.88 7.48 13.95 9.16 9.46 1.14 8 Formwork m2 838.14 529.14 863.86 328.79 538.76 74.48 10 Masonry work m2 918.56 523.19 685.42 743.31 273.43 113.97 11 Wall finishes m2 4273.21 582.42 4128.09 963.48 1377.13 226.58 Table 1.5 Productivity of activities for the month of February 2016 to January 2017 S.no Description Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan 1 Earthwork 44.44 0.00 0.00 0.00 4.82 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2 Rubble soling 92.57 45.04 0.00 0.00 4.66 75.51 111.54 100.00 47.75 84.91 0.00 0.00 3 PCC 55.91 27.67 7.73 31.05 26.48 148.00 32.54 31.50 143.58 6.53 135.07 100.63 4 Plum concrete 26.99 3.33 3.92 20.62 46.69 292.55 6.07 14.17 357.50 0.00 76.14 0.00 5 Anti-termite 2.00 0.00 0.00 0.00 100.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6 RCC 80.32 26.31 36.39 55.43 100.00 157.44 16.58 28.73 17.18 6.94 31.20 35.01 7 Reinforcement 109.09 32.65 32.56 25.47 100.00 107.92 65.35 330.51 17.59 31.32 65.66 12.05 8 Formwork 136.26 6.16 19.89 18.46 100.00 115.28 26.85 24.33 28.34 63.13 38.06 13.82 9 Masonry work 72.48 3.33 32.59 9.87 98.73 44.23 9.71 20.51 3.29 56.96 108.45 41.68 10 Wall finishes 91.48 3.07 58.99 15.76 223.76 27.89 8.45 21.36 2.08 13.63 23.34 16.45 Graph 1.1 Productivity of Earthwork for the month of February 2016 to January 2017
  • 5. ISSN 2393-8471 International Journal of Recent Research in Civil and Mechanical Engineering (IJRRCME) Vol. 4, Issue 1, pp: (6-14), Month: April 2017 – September 2017, Available at: www.paperpublications.org Page | 10 Paper Publications Graph 1.2 Productivity of Rubble soling for the month of February 2016 to January 2017 Graph 1.3 Productivity of PCC for the month of February 2016 to January 2017 Graph 1.4 Productivity of Plum concrete for the month of February 2016 to January 2017
  • 6. ISSN 2393-8471 International Journal of Recent Research in Civil and Mechanical Engineering (IJRRCME) Vol. 4, Issue 1, pp: (6-14), Month: April 2017 – September 2017, Available at: www.paperpublications.org Page | 11 Paper Publications Graph 1.5 Productivity of Anti-termite for the month of February 2016 to January 2017 Graph 1.6 Productivity of RCC for the month of February 2016 to January 2017 Graph 1.7 Productivity of Reinforcement for the month of February 2016 to January 2017
  • 7. ISSN 2393-8471 International Journal of Recent Research in Civil and Mechanical Engineering (IJRRCME) Vol. 4, Issue 1, pp: (6-14), Month: April 2017 – September 2017, Available at: www.paperpublications.org Page | 12 Paper Publications Graph 1.8 Productivity of formwork for the month of February 2016 to January 2017 Graph 1.9 Productivity of masonry work for the month of February 2016 to January 2017 Graph 1.10 Productivity of Wall finishes for the month of February 2016 to January 2017
  • 8. ISSN 2393-8471 International Journal of Recent Research in Civil and Mechanical Engineering (IJRRCME) Vol. 4, Issue 1, pp: (6-14), Month: April 2017 – September 2017, Available at: www.paperpublications.org Page | 13 Paper Publications VIII. CONCLUSION Project is already delayed due to low productivity. From the graph 1.1 to 1.10 shows the productivity of all activities for the month February 2016 to January 2017. The expected productivity is 100 % from the site management but it is not achieved frequently. Maximum productivity of the site is 357.5 % that is plum concrete at October 2016 since the activity has high scope at site. Minimum productivity of the site is 2 % that is anti-termite treatment since no scope at February 2016. The Following table 1.6 shows maximum and minimum productivity of activities for the month of February 2016 to January 2017. Table 1.6 shows maximum and minimum productivity of activities for the month of February 2016 to January 2017. S.no Description Maximum Minimum 1 Earthwork 44.44 0 2 Rubble soling 111.54 0 3 PCC 148.00 6.53 4 Plum concrete 357.50 0 5 Anti-termite 100 0 6 RCC 157.44 6.94 7 Reinforcement 330.51 12.05 8 Formwork 136.26 6.16 9 Masonry work 108.45 3.29 10 Wall finishes 223.76 2.08 IX. SUGGESTION AND RECOMMENDATIONS From the result of table 1.5 and table 1.6 the analyst concludes improper planning definitely reduces the productivity so while planning the planning manager should consider the previous month planned and achieved quantity for the activity and the reason submitted by site person for not achieved the target quantity. Site conditions and manpower availability also gives major impact on planning. The substantial recommendations for productivity improvement at site are,  Appointing potential planning manager  Use updated and effective planning technique  Consider site condition and pervious month productivity data while planning for upcoming month  Conduct Weekly meeting  Effective record keeping  Direct inspection of site by planning manager  Increase involvement site person in planning  Consider suggestions of site persons in planning  Allocate Incentive, extra wages for successful target achievement REFERENCES [1] Varma Santosh and Apte (2014) Productivity in Building Construction, IOSR-JMCE Volume 10, Issue 5 [2] Pramod M, Phaniraj and Srinivasan (2014) Monitoring System for Project Cost Control in Construction Industry, [3] International Journal of Engineering Research & Technology (IJERT) ISSN: 2278-0181 Vol. 3 Issue 7, July – 2014 [4] Mohd Faris Khamidi and Waris Ali Khan and Arazi Idrus (2011) The Cost Monitoring of Construction Projects Through
  • 9. ISSN 2393-8471 International Journal of Recent Research in Civil and Mechanical Engineering (IJRRCME) Vol. 4, Issue 1, pp: (6-14), Month: April 2017 – September 2017, Available at: www.paperpublications.org Page | 14 Paper Publications [5] Earned Value Analysis International Conference on Economics and Finance Research IPEDR vol.4 [6] Mostafa E. Shehata and Khaled M. El-Gohary (2011) Towards improving construction labor productivity and projects’ Performance Alexandria Engineering journal vol 50, 321-330 [7] Syed Ali Dilawer (2014) Control the loss of labor productivity IJCSER volume 2, Issue 1, pp: 104-110 [8] Thiyagu.C and M.Dheenadhayalan (2016) Construction labor productivity and its improvement IRJET volume : 02 issue : 08 [9] Vaishant Gupta (2014) Improvement of construction labor productivity in chambal region IJRET Volume : 3 Issus: 10 [10] Yogendrakumar (2013) Productivity Analysis of Small Construction Projects in India Asaian journal of Applied sciences, [11] Sudam Chavan and Hemant Salunkhe (2016) A study on labor productivity in construction industry IJER volume no 5, issue Special 1 pp: 247-249. [12] Shreyash Raut and Karan Sawant (2013) Effect of Project Cost and Time Monitoring on Progress of Construction Project IJRET,Volume :02 Issue:12