1. Strategic Allocation of Ressources
in Wind Energy Projects
to Improve Project Parameters
Cotanum GmbH
Solutions for
Europe´s Clean Energy Future
2. Overview Major Topics
Shorter Project Development Phases
Efficient use of Finances
Overview
time/costs
Period I Period II Costs Phase I
Plan
Costs Phase I
real
Project Berlin B8 4 month 9 month 136 Mio € 167 Mio €
Project Stuttgart
NG
6 month 10
month
83 Mio € 116 mio €
Project Frankfurt
north
7 month 8 month 101 Mio € 107 Mio €
Project Neckar II 8 month open 76 Mio € open
Project Hamburg
N4
open open 83 Mio € open
Project 25
Project 28
Project 29
3. Mission
Target: Reduce Time for Development and
Installation about 30%
Cut Project Costs by 25%
Clear Structure and better forecasting for
Investors (Phase II and CM)
4. Situation
Projets take 12....19 Month for Phases I and II
Deviation in Cost plan/FC is significant
→ Investors are reluctant to invest financial
ressources
→ Project members have few control on scedule and
therefore poor planning
→ this increases Costs !!
→ this delays Projects !!
5. Status A
Status of A- and D-application is poor
Control of planning and production factors is
insufficient
Prognosis fail in 78 % of all projects (10% or
more deviation)
Costs/Planning poor and not applicable
Project management fails
Feedback Loop inconsistent
6. Status B
Proposal CM-3 for Phase I : worked out in
Jan 2016 by Cotanum GmbH for Client
Agreement of Shareholders and
Management of Holding obtained
Proposal accepted in Jan. 2016
Proposal for Phase II in progress (see S23)
Action Plan 2016/2018 in preparation
(by Cotanum GmbH, Germany)
7. Further Steps
Agreement to keep Update Information (see S12)
Scedule of complete Project published
Project Results Phase II to be presented by Cotanum
GmbH in Late Summer 2016
Transfer of project results to USA: end 2016
Transfer of project results to China: end2016/2017