SlideShare a Scribd company logo
1 of 1
Download to read offline
Getting FIT
with REA Presenter: Leah Deveaux, BES EA Specialist
On September 24, 2009 the Ontario government proclaimed the Green Energy and Green Economy
Act (GEEA).This piece of legislation introduced several monumental changes to the Ontario renewable
power market including replacing of the Renewable Energy Standard Offer Program (RESOP) with the
newly created Feed-inTariff (FIT) program and replacing the Environmental Assessment (O.Reg116/01)
process with the Renewable Energy Approval (REA) process.
Changes to
Permitting and Procurement
How do FIT and REA
Timelines work together?
The FIT program created milestones that a developer is
required to meet in order to maintain its contract, such as
a minimum three years to commissioning and a Notice
to Proceed (NTP) period no less than six months prior
to the COD of a project. A completed REA is required for
NTP.The REA also has a guaranteed review time of six
months provided the application is complete, ensures an
expedient review. Other agencies also have expedited
review times based on the COD of the project.
How the new regime
has changed development
As can be seen in the above diagram, the FIT and
REA have changed the way in which project work is
completed. Under the old process much of the design
work was left until after the EA was completed.The REA
requires much of this civil work to be part of the final
submission.
What Gaps are left in the process?
•	 Lack of federal coordination
•	 Agency confirmation letters required prior to
publication of REA draft documents
•	 Development processes may be out of synch with the
REA process (i.e.Timing of detailed design work)
•	 Concerns regarding agency review times
Conclusions
The changes stemming from the GEEA of September 24, 2009 have been positive. While the REA process and the FIT
process are still in their infancies they show positive changes to systems which were ailing.The development process
is adapting to the increased information requirements during the permitting stage; however, the increased consultation
component is one of the more challenging adjustments. Readily available digital information has allowed local residents
and land owners to independently review and assess the impacts of new renewable energy developments.This
ability to better understand the effect on their lands is a significant change that requires the most adjustment by those
undertaking the development process.

More Related Content

What's hot

A New Bureau…A New Mission: PA DEP Bureau of Conservation and Restoration Mov...
A New Bureau…A New Mission: PA DEP Bureau of Conservation and Restoration Mov...A New Bureau…A New Mission: PA DEP Bureau of Conservation and Restoration Mov...
A New Bureau…A New Mission: PA DEP Bureau of Conservation and Restoration Mov...Michael Hewitt, GISP
 
2016_06_15 Clean Energy Fund 101
2016_06_15 Clean Energy Fund 1012016_06_15 Clean Energy Fund 101
2016_06_15 Clean Energy Fund 101Neil Webb
 
CCXG Forum, March 2021, Lydia Cavasin
CCXG Forum, March 2021, Lydia CavasinCCXG Forum, March 2021, Lydia Cavasin
CCXG Forum, March 2021, Lydia CavasinOECD Environment
 
CCXG Forum, March 2021, Jae Jung
CCXG Forum, March 2021, Jae JungCCXG Forum, March 2021, Jae Jung
CCXG Forum, March 2021, Jae JungOECD Environment
 
David sholk cpa resume
David sholk cpa resumeDavid sholk cpa resume
David sholk cpa resumedsholk
 
Project Clean Lake, Appendix 3 Green Infrastructure Anticipated Co-Benefits A...
Project Clean Lake, Appendix 3 Green Infrastructure Anticipated Co-Benefits A...Project Clean Lake, Appendix 3 Green Infrastructure Anticipated Co-Benefits A...
Project Clean Lake, Appendix 3 Green Infrastructure Anticipated Co-Benefits A...Northeast Ohio Regional Sewer District
 
Environment clearance mandatory for real estate projects
Environment clearance mandatory for real estate projectsEnvironment clearance mandatory for real estate projects
Environment clearance mandatory for real estate projectsProperty Document Verification
 
CCXG Forum, September 2021, MJ Mace
CCXG Forum, September 2021, MJ MaceCCXG Forum, September 2021, MJ Mace
CCXG Forum, September 2021, MJ MaceOECD Environment
 
Slide Presentation For Eecbg For Steering Committee
Slide Presentation For Eecbg For Steering CommitteeSlide Presentation For Eecbg For Steering Committee
Slide Presentation For Eecbg For Steering CommitteeKim Mitchell
 
CBEC - GST - Registration Amendment
CBEC - GST - Registration AmendmentCBEC - GST - Registration Amendment
CBEC - GST - Registration Amendmentgst-trichy
 
session 6 indicative targets
session 6 indicative targetssession 6 indicative targets
session 6 indicative targetsRCREEE
 

What's hot (17)

A New Bureau…A New Mission: PA DEP Bureau of Conservation and Restoration Mov...
A New Bureau…A New Mission: PA DEP Bureau of Conservation and Restoration Mov...A New Bureau…A New Mission: PA DEP Bureau of Conservation and Restoration Mov...
A New Bureau…A New Mission: PA DEP Bureau of Conservation and Restoration Mov...
 
2016_06_15 Clean Energy Fund 101
2016_06_15 Clean Energy Fund 1012016_06_15 Clean Energy Fund 101
2016_06_15 Clean Energy Fund 101
 
CCXG Forum, March 2021, Lydia Cavasin
CCXG Forum, March 2021, Lydia CavasinCCXG Forum, March 2021, Lydia Cavasin
CCXG Forum, March 2021, Lydia Cavasin
 
CCXG Forum, March 2021, Jae Jung
CCXG Forum, March 2021, Jae JungCCXG Forum, March 2021, Jae Jung
CCXG Forum, March 2021, Jae Jung
 
David sholk cpa resume
David sholk cpa resumeDavid sholk cpa resume
David sholk cpa resume
 
Project Clean Lake, Appendix 3 Green Infrastructure Anticipated Co-Benefits A...
Project Clean Lake, Appendix 3 Green Infrastructure Anticipated Co-Benefits A...Project Clean Lake, Appendix 3 Green Infrastructure Anticipated Co-Benefits A...
Project Clean Lake, Appendix 3 Green Infrastructure Anticipated Co-Benefits A...
 
3.UAEGH_2013
3.UAEGH_20133.UAEGH_2013
3.UAEGH_2013
 
The Commercial Energy Codes Support Program
The Commercial Energy Codes Support ProgramThe Commercial Energy Codes Support Program
The Commercial Energy Codes Support Program
 
NIPA annual conference 2019
NIPA annual conference 2019NIPA annual conference 2019
NIPA annual conference 2019
 
30.UNEP_Kuwait
30.UNEP_Kuwait30.UNEP_Kuwait
30.UNEP_Kuwait
 
Environment clearance mandatory for real estate projects
Environment clearance mandatory for real estate projectsEnvironment clearance mandatory for real estate projects
Environment clearance mandatory for real estate projects
 
CCXG Forum, September 2021, MJ Mace
CCXG Forum, September 2021, MJ MaceCCXG Forum, September 2021, MJ Mace
CCXG Forum, September 2021, MJ Mace
 
Eia 2020
Eia 2020 Eia 2020
Eia 2020
 
Municipal Energy Program Applicant Workshop
Municipal Energy Program Applicant WorkshopMunicipal Energy Program Applicant Workshop
Municipal Energy Program Applicant Workshop
 
Slide Presentation For Eecbg For Steering Committee
Slide Presentation For Eecbg For Steering CommitteeSlide Presentation For Eecbg For Steering Committee
Slide Presentation For Eecbg For Steering Committee
 
CBEC - GST - Registration Amendment
CBEC - GST - Registration AmendmentCBEC - GST - Registration Amendment
CBEC - GST - Registration Amendment
 
session 6 indicative targets
session 6 indicative targetssession 6 indicative targets
session 6 indicative targets
 

Viewers also liked

Managing Technical & Project Risks on Small Renewable Energy Projects (...
Managing Technical & Project Risks on Small Renewable Energy Projects (...Managing Technical & Project Risks on Small Renewable Energy Projects (...
Managing Technical & Project Risks on Small Renewable Energy Projects (...mtingle
 
Wind Farms: Underperformance Fears –Avoid Overcompensating
Wind Farms:  Underperformance Fears –Avoid OvercompensatingWind Farms:  Underperformance Fears –Avoid Overcompensating
Wind Farms: Underperformance Fears –Avoid Overcompensatingmtingle
 
Wind Sector Building a Business Strategy Our Lessons Learned
Wind Sector Building a Business Strategy Our Lessons LearnedWind Sector Building a Business Strategy Our Lessons Learned
Wind Sector Building a Business Strategy Our Lessons Learnedmtingle
 
Can Wea Supply Chain Final June 10, 2010
Can Wea Supply Chain Final June 10, 2010Can Wea Supply Chain Final June 10, 2010
Can Wea Supply Chain Final June 10, 2010mtingle
 
A case study in offshore wind farm project management
A case study in offshore wind farm project managementA case study in offshore wind farm project management
A case study in offshore wind farm project managementmtingle
 
Job description loan analyst - VEDC
Job description loan analyst - VEDCJob description loan analyst - VEDC
Job description loan analyst - VEDCTravis Vaughan
 
Douglas County Schools app
Douglas County Schools appDouglas County Schools app
Douglas County Schools appHealthONE - HCA
 
Efecto de sonido en el ser humano
Efecto de sonido en el ser humanoEfecto de sonido en el ser humano
Efecto de sonido en el ser humanoAngie Dhm
 
DLSC ARTMUSIC - Personal Artworks by Suarez
DLSC ARTMUSIC - Personal Artworks by SuarezDLSC ARTMUSIC - Personal Artworks by Suarez
DLSC ARTMUSIC - Personal Artworks by SuarezAntonio Sikat Suarez
 
A resource allocation scheme for scalable video multicast in wi max relay net...
A resource allocation scheme for scalable video multicast in wi max relay net...A resource allocation scheme for scalable video multicast in wi max relay net...
A resource allocation scheme for scalable video multicast in wi max relay net...Ecwaytechnoz
 
Digital Edu Hyundai Award
Digital Edu Hyundai AwardDigital Edu Hyundai Award
Digital Edu Hyundai Awarddesainstore
 
Preakness stakes 2013
Preakness stakes 2013Preakness stakes 2013
Preakness stakes 2013Joe Duffy
 
WQD2011 - KAIZEN - EMAL - HRSG-22 underperforming
WQD2011 - KAIZEN - EMAL - HRSG-22 underperformingWQD2011 - KAIZEN - EMAL - HRSG-22 underperforming
WQD2011 - KAIZEN - EMAL - HRSG-22 underperformingDubai Quality Group
 
Socialmediaperformancemeasurementandbusinessimpactjune2010 100615145909-phpapp01
Socialmediaperformancemeasurementandbusinessimpactjune2010 100615145909-phpapp01Socialmediaperformancemeasurementandbusinessimpactjune2010 100615145909-phpapp01
Socialmediaperformancemeasurementandbusinessimpactjune2010 100615145909-phpapp01Federico Smanio
 
Things I have learned in my life so far in advertising
Things I have learned in my life so far in advertisingThings I have learned in my life so far in advertising
Things I have learned in my life so far in advertisingContagious Tribe
 

Viewers also liked (19)

Managing Technical & Project Risks on Small Renewable Energy Projects (...
Managing Technical & Project Risks on Small Renewable Energy Projects (...Managing Technical & Project Risks on Small Renewable Energy Projects (...
Managing Technical & Project Risks on Small Renewable Energy Projects (...
 
Wind Farms: Underperformance Fears –Avoid Overcompensating
Wind Farms:  Underperformance Fears –Avoid OvercompensatingWind Farms:  Underperformance Fears –Avoid Overcompensating
Wind Farms: Underperformance Fears –Avoid Overcompensating
 
Wind Sector Building a Business Strategy Our Lessons Learned
Wind Sector Building a Business Strategy Our Lessons LearnedWind Sector Building a Business Strategy Our Lessons Learned
Wind Sector Building a Business Strategy Our Lessons Learned
 
Can Wea Supply Chain Final June 10, 2010
Can Wea Supply Chain Final June 10, 2010Can Wea Supply Chain Final June 10, 2010
Can Wea Supply Chain Final June 10, 2010
 
A case study in offshore wind farm project management
A case study in offshore wind farm project managementA case study in offshore wind farm project management
A case study in offshore wind farm project management
 
Job description loan analyst - VEDC
Job description loan analyst - VEDCJob description loan analyst - VEDC
Job description loan analyst - VEDC
 
Ppp cronograma
Ppp cronogramaPpp cronograma
Ppp cronograma
 
Douglas County Schools app
Douglas County Schools appDouglas County Schools app
Douglas County Schools app
 
Efecto de sonido en el ser humano
Efecto de sonido en el ser humanoEfecto de sonido en el ser humano
Efecto de sonido en el ser humano
 
Timber flooring
Timber flooringTimber flooring
Timber flooring
 
Que son Las Wikis
Que son Las WikisQue son Las Wikis
Que son Las Wikis
 
DLSC ARTMUSIC - Personal Artworks by Suarez
DLSC ARTMUSIC - Personal Artworks by SuarezDLSC ARTMUSIC - Personal Artworks by Suarez
DLSC ARTMUSIC - Personal Artworks by Suarez
 
A resource allocation scheme for scalable video multicast in wi max relay net...
A resource allocation scheme for scalable video multicast in wi max relay net...A resource allocation scheme for scalable video multicast in wi max relay net...
A resource allocation scheme for scalable video multicast in wi max relay net...
 
Digital Edu Hyundai Award
Digital Edu Hyundai AwardDigital Edu Hyundai Award
Digital Edu Hyundai Award
 
Preakness stakes 2013
Preakness stakes 2013Preakness stakes 2013
Preakness stakes 2013
 
WQD2011 - KAIZEN - EMAL - HRSG-22 underperforming
WQD2011 - KAIZEN - EMAL - HRSG-22 underperformingWQD2011 - KAIZEN - EMAL - HRSG-22 underperforming
WQD2011 - KAIZEN - EMAL - HRSG-22 underperforming
 
Socialmediaperformancemeasurementandbusinessimpactjune2010 100615145909-phpapp01
Socialmediaperformancemeasurementandbusinessimpactjune2010 100615145909-phpapp01Socialmediaperformancemeasurementandbusinessimpactjune2010 100615145909-phpapp01
Socialmediaperformancemeasurementandbusinessimpactjune2010 100615145909-phpapp01
 
3165
31653165
3165
 
Things I have learned in my life so far in advertising
Things I have learned in my life so far in advertisingThings I have learned in my life so far in advertising
Things I have learned in my life so far in advertising
 

Similar to CanweaHandout LD v1

DTE Energy Year End 2014 Earnings Conference Call Slide Deck
DTE Energy Year End 2014 Earnings Conference Call Slide DeckDTE Energy Year End 2014 Earnings Conference Call Slide Deck
DTE Energy Year End 2014 Earnings Conference Call Slide DeckMarcellus Drilling News
 
A2 - Industry leadership in setting best practice
A2 - Industry leadership in setting best practiceA2 - Industry leadership in setting best practice
A2 - Industry leadership in setting best practiceIceland Geothermal
 
Real Estate Regulatory & Development Act
Real Estate Regulatory & Development ActReal Estate Regulatory & Development Act
Real Estate Regulatory & Development ActUmesh Shinde
 
Breaking the Gridlock in Marine Renewables
Breaking the Gridlock in Marine RenewablesBreaking the Gridlock in Marine Renewables
Breaking the Gridlock in Marine RenewablesCarolyn Elefant
 
Breaking the Gridlock in Marine Renewable Energy Development
Breaking the Gridlock in Marine Renewable Energy DevelopmentBreaking the Gridlock in Marine Renewable Energy Development
Breaking the Gridlock in Marine Renewable Energy DevelopmentCarolyn Elefant
 
NiSource 2Q14 Supplement Slide Presentation
NiSource 2Q14 Supplement Slide PresentationNiSource 2Q14 Supplement Slide Presentation
NiSource 2Q14 Supplement Slide PresentationMarcellus Drilling News
 
Zimmerman.marybeth
Zimmerman.marybethZimmerman.marybeth
Zimmerman.marybethNASAPMC
 
RE-DELAYS: Documenting and analising the cost of regulatory delays
RE-DELAYS: Documenting and analising the cost of regulatory delaysRE-DELAYS: Documenting and analising the cost of regulatory delays
RE-DELAYS: Documenting and analising the cost of regulatory delaysIEA_RETD
 
ARTBA Comments on FHWA/FTA Environmental Review Process Guidance
ARTBA Comments on FHWA/FTA Environmental Review Process Guidance  ARTBA Comments on FHWA/FTA Environmental Review Process Guidance
ARTBA Comments on FHWA/FTA Environmental Review Process Guidance artba
 
Overview of the Permitting Requirements for LNG Projects in British Columbia
Overview of the Permitting Requirements for LNG Projects in British ColumbiaOverview of the Permitting Requirements for LNG Projects in British Columbia
Overview of the Permitting Requirements for LNG Projects in British ColumbiaBlake, Cassels & Graydon LLP
 
Results from minnesota’s existing building commissioning program
Results from minnesota’s existing building commissioning programResults from minnesota’s existing building commissioning program
Results from minnesota’s existing building commissioning programCenter for Energy and Environment
 
Regulatory Update: Introduction to Bill 135 and Environmental Policies Impact...
Regulatory Update: Introduction to Bill 135 and Environmental Policies Impact...Regulatory Update: Introduction to Bill 135 and Environmental Policies Impact...
Regulatory Update: Introduction to Bill 135 and Environmental Policies Impact...Enercare Inc.
 
Wci Stakeholder Update For January 12 2012
Wci Stakeholder Update For January 12 2012Wci Stakeholder Update For January 12 2012
Wci Stakeholder Update For January 12 2012Nellson LLC
 
Plan Making Reforms Implementation Consultation Presentation Aug 2023
	Plan Making Reforms Implementation Consultation Presentation Aug 2023	Plan Making Reforms Implementation Consultation Presentation Aug 2023
Plan Making Reforms Implementation Consultation Presentation Aug 2023mhutttch
 
IAQM AGM 2015 - Stephen Moorcroft, Defra's draft plans to improve air quality
IAQM AGM 2015 - Stephen Moorcroft, Defra's draft plans to improve air qualityIAQM AGM 2015 - Stephen Moorcroft, Defra's draft plans to improve air quality
IAQM AGM 2015 - Stephen Moorcroft, Defra's draft plans to improve air qualityIES / IAQM
 
Streamlining Approval Procedure for Real Estate Projects (SAPREP) - 19 sept '14
Streamlining Approval Procedure for Real Estate Projects (SAPREP) -  19 sept '14Streamlining Approval Procedure for Real Estate Projects (SAPREP) -  19 sept '14
Streamlining Approval Procedure for Real Estate Projects (SAPREP) - 19 sept '14Competition Advisory Services (India) LLP
 
.integrysgroup 02/26/2009_slides
.integrysgroup  02/26/2009_slides.integrysgroup  02/26/2009_slides
.integrysgroup 02/26/2009_slidesfinance26
 
The Australian Taxation Office change program – lessons about IT procurement
The Australian Taxation Office change program – lessons about IT procurementThe Australian Taxation Office change program – lessons about IT procurement
The Australian Taxation Office change program – lessons about IT procurementTom Augustsson CPA
 

Similar to CanweaHandout LD v1 (20)

DTE Energy Year End 2014 Earnings Conference Call Slide Deck
DTE Energy Year End 2014 Earnings Conference Call Slide DeckDTE Energy Year End 2014 Earnings Conference Call Slide Deck
DTE Energy Year End 2014 Earnings Conference Call Slide Deck
 
A2 - Industry leadership in setting best practice
A2 - Industry leadership in setting best practiceA2 - Industry leadership in setting best practice
A2 - Industry leadership in setting best practice
 
Real Estate Regulatory & Development Act
Real Estate Regulatory & Development ActReal Estate Regulatory & Development Act
Real Estate Regulatory & Development Act
 
Breaking the Gridlock in Marine Renewables
Breaking the Gridlock in Marine RenewablesBreaking the Gridlock in Marine Renewables
Breaking the Gridlock in Marine Renewables
 
Breaking the Gridlock in Marine Renewable Energy Development
Breaking the Gridlock in Marine Renewable Energy DevelopmentBreaking the Gridlock in Marine Renewable Energy Development
Breaking the Gridlock in Marine Renewable Energy Development
 
NiSource 2Q14 Supplement Slide Presentation
NiSource 2Q14 Supplement Slide PresentationNiSource 2Q14 Supplement Slide Presentation
NiSource 2Q14 Supplement Slide Presentation
 
Zimmerman.marybeth
Zimmerman.marybethZimmerman.marybeth
Zimmerman.marybeth
 
RE-DELAYS: Documenting and analising the cost of regulatory delays
RE-DELAYS: Documenting and analising the cost of regulatory delaysRE-DELAYS: Documenting and analising the cost of regulatory delays
RE-DELAYS: Documenting and analising the cost of regulatory delays
 
ARTBA Comments on FHWA/FTA Environmental Review Process Guidance
ARTBA Comments on FHWA/FTA Environmental Review Process Guidance  ARTBA Comments on FHWA/FTA Environmental Review Process Guidance
ARTBA Comments on FHWA/FTA Environmental Review Process Guidance
 
Overview of the Permitting Requirements for LNG Projects in British Columbia
Overview of the Permitting Requirements for LNG Projects in British ColumbiaOverview of the Permitting Requirements for LNG Projects in British Columbia
Overview of the Permitting Requirements for LNG Projects in British Columbia
 
Results from minnesota’s existing building commissioning program
Results from minnesota’s existing building commissioning programResults from minnesota’s existing building commissioning program
Results from minnesota’s existing building commissioning program
 
Regulatory Update: Introduction to Bill 135 and Environmental Policies Impact...
Regulatory Update: Introduction to Bill 135 and Environmental Policies Impact...Regulatory Update: Introduction to Bill 135 and Environmental Policies Impact...
Regulatory Update: Introduction to Bill 135 and Environmental Policies Impact...
 
Wci Stakeholder Update For January 12 2012
Wci Stakeholder Update For January 12 2012Wci Stakeholder Update For January 12 2012
Wci Stakeholder Update For January 12 2012
 
Plan Making Reforms Implementation Consultation Presentation Aug 2023
	Plan Making Reforms Implementation Consultation Presentation Aug 2023	Plan Making Reforms Implementation Consultation Presentation Aug 2023
Plan Making Reforms Implementation Consultation Presentation Aug 2023
 
IAQM AGM 2015 - Stephen Moorcroft, Defra's draft plans to improve air quality
IAQM AGM 2015 - Stephen Moorcroft, Defra's draft plans to improve air qualityIAQM AGM 2015 - Stephen Moorcroft, Defra's draft plans to improve air quality
IAQM AGM 2015 - Stephen Moorcroft, Defra's draft plans to improve air quality
 
Frank Gorke, Massachusetts Department of Energy Resources
Frank Gorke, Massachusetts Department of Energy ResourcesFrank Gorke, Massachusetts Department of Energy Resources
Frank Gorke, Massachusetts Department of Energy Resources
 
Hillsborough County's Major Building Repairs and Maintenance Program
Hillsborough County's Major Building Repairs and Maintenance ProgramHillsborough County's Major Building Repairs and Maintenance Program
Hillsborough County's Major Building Repairs and Maintenance Program
 
Streamlining Approval Procedure for Real Estate Projects (SAPREP) - 19 sept '14
Streamlining Approval Procedure for Real Estate Projects (SAPREP) -  19 sept '14Streamlining Approval Procedure for Real Estate Projects (SAPREP) -  19 sept '14
Streamlining Approval Procedure for Real Estate Projects (SAPREP) - 19 sept '14
 
.integrysgroup 02/26/2009_slides
.integrysgroup  02/26/2009_slides.integrysgroup  02/26/2009_slides
.integrysgroup 02/26/2009_slides
 
The Australian Taxation Office change program – lessons about IT procurement
The Australian Taxation Office change program – lessons about IT procurementThe Australian Taxation Office change program – lessons about IT procurement
The Australian Taxation Office change program – lessons about IT procurement
 

CanweaHandout LD v1

  • 1. Getting FIT with REA Presenter: Leah Deveaux, BES EA Specialist On September 24, 2009 the Ontario government proclaimed the Green Energy and Green Economy Act (GEEA).This piece of legislation introduced several monumental changes to the Ontario renewable power market including replacing of the Renewable Energy Standard Offer Program (RESOP) with the newly created Feed-inTariff (FIT) program and replacing the Environmental Assessment (O.Reg116/01) process with the Renewable Energy Approval (REA) process. Changes to Permitting and Procurement How do FIT and REA Timelines work together? The FIT program created milestones that a developer is required to meet in order to maintain its contract, such as a minimum three years to commissioning and a Notice to Proceed (NTP) period no less than six months prior to the COD of a project. A completed REA is required for NTP.The REA also has a guaranteed review time of six months provided the application is complete, ensures an expedient review. Other agencies also have expedited review times based on the COD of the project. How the new regime has changed development As can be seen in the above diagram, the FIT and REA have changed the way in which project work is completed. Under the old process much of the design work was left until after the EA was completed.The REA requires much of this civil work to be part of the final submission. What Gaps are left in the process? • Lack of federal coordination • Agency confirmation letters required prior to publication of REA draft documents • Development processes may be out of synch with the REA process (i.e.Timing of detailed design work) • Concerns regarding agency review times Conclusions The changes stemming from the GEEA of September 24, 2009 have been positive. While the REA process and the FIT process are still in their infancies they show positive changes to systems which were ailing.The development process is adapting to the increased information requirements during the permitting stage; however, the increased consultation component is one of the more challenging adjustments. Readily available digital information has allowed local residents and land owners to independently review and assess the impacts of new renewable energy developments.This ability to better understand the effect on their lands is a significant change that requires the most adjustment by those undertaking the development process.