Agenda
1. Introduction to OPM
2. OPM3 framework from PMI®
3. OPM3 assessment exercise
4. Maturity Assessment Process
5. Alternative frameworks
 CMMI, IVI IT-CMF, Kerzner KPM3
6. Summary of options
7. Benefits
8. References & More Information
9. Discussion
(Short questions during program, and discussion at the end)
3
1. Introduction to OPM (not OPM3)
Gartner survey of 130 organizations:
“What is the top success criterion for your projects?”
Note that
alignment is
#1 at 29%.
Cost, budget,
scope (triple
constraint)
total to only
40%.
Reference (1) PMI standard presentation on OPM3
4
1. Introduction to OPM.
OPM = Organizational Project Management:
OPM:The alignment and systematic
management of projects,
programs and portfolios to
achieve strategic organizational
goals
Reference (2) Ginger Levin general slides © Ginger Levin, 2011
Does your organization use OPM?
Or does the “squeaky wheel get
the grease” ?
5
2. OPM3 framework from PMI®
PMI® recognized a need and created “Organizational
Project Management Maturity Model” (OPM3)
 2003 First Edition of OPM3 standard
 2008 Second Edition; alignment with other PMI®
standards
 OPM3 acceptance level has been low, is being
addressed:
 Newer versions of software are not buggy, as earlier ones were
 OPM3 standard being rewritten in more business-friendly terms
 PMI® is promoting OPM3 more heavily
6
2. OPM3 framework from PMI®
Library of PMI® Global Standards
1. Foundational Standards
 Project Management (PMBOK®)
 Program Management
 Portfolio Management
 Organizational Project Management (OPM3)
2. Practice Standards and Frameworks
 (7) exist, including: Risk; Scheduling; WBS
3. Foundational Extensions
 (2) exist; PMBOK® for construction, government
See: http://www.pmi.org/PMBOK-Guide-and-Standards/Standards-Library-of-PMI-Global-Standards.aspx
7
2. OPM3 framework from PMI®
OPM3 Best Practice concepts, 488 total:
(A) Domain processes x 4 improvement stages
 Project (42 processes) x 4 = 168 Best Practices
 Program (47 processes) x 4 = 188 Best Practices
 Portfolio (14 processes) x 4 = 56 Best Practices
(B) Organizational Enablers (76)
Total: 168 + 188 + 56 + 76 = 488 Best Practices
8
2. OPM3 framework from PMI®
OPM3 Best Practice concepts, 488 total:
(A) Domain processes x 4 improvement stages
 Four Process Improvement Stages, SMCI:
 Standardize = Consistent, documented,
communicated
 Measure = Identify & measure: inputs,
characteristics, results
 Control = Control plan is developed and
implemented
 Improve = Identify problems, implement sustainable
improvements
9
2. OPM3 framework from PMI®
OPM3 Best Practice concepts, 488 total:
(A) Domain processes x 4 improvement stages
 Example process: Develop Project Charter
 Standardized ?
 Measured ?
 Controlled ?
 Improve ?
10
2. OPM3 framework from PMI® .
(B) OPM3 - Organizational Enablers
 Facilitate implementation and sustainability
 22 groups, with 76 total OE items. Examples:
 PMIS and Knowledge Management
 7365: Project Management Information System
 7375: Intellectual Capital Reuse
 5660: Manage Portfolio Value
 Resource Allocation
 5220: Provide Competent Organizational PM Resources
 1590: Record Project Resource Assignments
11
3. OPM3 Assessment Exercise
Group exercise:
Review lists of OPM3 BestPractices…
See separate documents with Best Practices lists,
and with survey of PMINEO chapter meeting
attendees on PMBOK practice standardization.
12
4. Maturity Assessment Process
OPM3 assessment options
 Self-assessment using online tools.
 Simpler tool (Yes/No questions) for roughly $1,000
 Benchmark against other companies
 Hire certified assessor
 Assessor uses more robust toolset
 Low end: $15-20K, 2-3 weeks total, single site
 Higher: multiple months, $100K, international scope
 Can limit scope (ex: Portfolio, or “Standardize”)
13
4. Maturity Assessment Process.
Common steps, with OPM3 or most frameworks:
1) Obtain organizational commitment; hold a kickoff meeting
2) Review organizational documents (ex: policies)
3) Review sample program and project documents
4) Distribute questionnaires
5) Conduct interviews
6) Analyze results
7) Report results and recommendations for improvement
8) Determine when to reassess
Reference (3) Ginger Levin, “Maturity Models”
14
5. Alternative Frameworks
5.1) CMMI = Capability Maturity Model Integration
5.2) IT-CMF from IVI (Innovation Value Institute)
5.3) Kerzner Project Management Maturity Model
Local notes:
Rockwell Automation has been considering OPM3 as a
standard
Progressive is considering a combination of OPM3
and IT-CMF from IVI
15
5.1) CMMI
 CMMI = Capability Maturity Model Integration
 One of the best known maturity models
 CMMI replaced CMM (developed from 1987 - 1997)
 CMMI:
 A Process Improvement Approach
 Identify strengths and weaknesses
 Assessment leads to overall maturity ranking of 1, 2, 3, 4, or 5
 Plan process changes to address weaknesses
References: (4) CMMI site, (5) Wikipedia
16
5.1) CMMI
 Most organizations start in CMMI at level 1 or 2
 Growth to level 3 (govmt contracts) can take a few years
17
5.1) CMMI.
CMMI currently addresses three areas of interest:
1. Product and service Development (CMMI-DEV),
2. Service establishment, management, and delivery —
(CMMI-SVC)
3. Product and service acquisition — (CMMI-ACQ).
The CMMI model mostly deals with what processes should
be implemented, and not so much with how they can be
implemented.
18
5.2) IT-CMF from IVI
IVI = Innovation Value Institute
 A global consortium of industry, government, non-profit,
and academic organizations, established in 2006
 Goal: define standard for managing IT for business value
 Includes Intel, Ernst & Young, Google, Microsoft, SAP
IT-CMF = IT Capability Maturity Framework
 An assessment framework for total IT business value
 Portfolio/Program/Project are components of total scope
Reference: (7) Managing IT for Business Value
19
5.2) IT-CMF from IVI
20
5.2) IT-CMF from IVI
21
5.2) IT-CMF from IVI.
 Levels of membership exist, for education, assessment,
mentoring
 Full adoption journey covers 12-24 months, including
education, assessment, review, new practices
 Options include self-help with online tools, IVI staff,
consulting organizations
22
5.3) Kerzner PM3
Perform self-assessment using an online tool:
 Each participant answers 183 multiple choice questions
 Generate a score for your organization & Project Managers
 Benchmark your scores against your industry and overall
 Create a list of actionable recommendations
Focus is on Project Management and PMBOK
List price is $95 per person, with volume discounts
23
5.3) Kerzner PM3
24
5.3) Kerzner PM3.
Level 1: common language.
“Definition of Scope Management is...”
Level 2: common processes.
“Our executives have demonstrated a willingness to change….“
Level 3: singular methodology.
“My company actively uses the following processes….”
Level 4: benchmarking.
“Benchmarking has found companies with tighter cost controls…“
Level 5: continuous improvement.
“Methodology improvements have pushed us closer to customers….“
25
6. Summary of Options.
Option Notes
OPM3 • Scope: Portfolio/Program/Project management, for IT or other
• Uses Best Practices; does not provide summary score
CMMI • Scope: Development, Service, Acquisition processes
• Uses 5 levels of progressive maturity
• Summary level scores well-known (ex: “3” for govmt contracts)
IT-CMF
of IVI
• Scope: IT, overall, including projects and operations
• Addresses 32 process areas, in four groupings
• Note that IVI is seeking to collaborate with CMMI
KPM3 • Scope: Project Management and PMBOK
• Uses 5 generally progressive levels of maturity
• Can be done on self-help basis, at low cost, w optional consulting
26
7. Benefits.
CMMI site has published results of projects
 Costs: Siemens reduced cost of quality from 45% to 30% in 3 years
 Schedule: GM improved percent of milestones met from 50% to
85%
 Productivity: Warner Robbins reduced effort to deliver test program
sets by 25%
 Quality: Siemens reduced defect density an average of 71% in 3
technical areas
 Customer Satisfaction: Northrup Grumman received 98% of
customer award fees
 ROI: Accenture experienced 5 to 1 ROI for quality activities
Reference: (4), CMMI site, page http://www.sei.cmu.edu/cmmi/why/benefits/. See published appraisal results.
27
8. References & More Information
References
(1) OPM3 standard presentation slides from PMI
(2) Ginger Levin, certified OPM3 consultant; engagement slides
Gin;evin@AOL.com, http://www.linkedin.com/in/gingerlevin
(3) Ginger Levin, “Maturity Models” chapter for book by Dr. Rodney
Turner
(4) CMMI website (http://www.sei.cmu.edu/cmmi/)
(5) CMMI on Wikipedia (http://en.wikipedia.org/wiki/CMMI)
(6) “Managing IT for Business Value” the Boston Consulting Group, for
IVI and IT-CMF
(7) Claudia Baca, OPM3 committee, certified consultant
cmbaca@att.net , http://www.linkedin.com/pub/claudia-baca/5/105/455
(8) Kerzner PM3 from www.iil.com/kpm3
(9) “Capability Immaturity Model”, Schorsch, Nexus, 1996
(10) OPM3 standard from PMI 2nd Edition, 2008
28
8. References & More Information.
More Information
a) PMI “Community of Practice” for OPM
Free membership; newsletters; webinars
See: http://opm.vc.pmi.org/
b) IVI, Innovation Value Institute
See: http://ivi.nuim.ie/
See also Boston Consulting Group at: http://www.bcg.com/
c) ESI International
Training, assessment, support, for Portfolio//ProgramProject Mgmt.
See: http://www.esi-intl.com/
d) OPM3 and other standards publications are available for on-line
viewing for PMI members, on PMI.org
29
9. Discussion
1. Standing Ovation
2. Discussion
30

More Related Content

What's hot

PMO Presentation
PMO PresentationPMO Presentation
PMO PresentationTURKI , PMP
 
Pmp exam questions
Pmp exam questionsPmp exam questions
Pmp exam questions
Zubair Choudhary
 
Complete Online PMP Study Training Material for PMP Exam Provided Free for PM...
Complete Online PMP Study Training Material for PMP Exam Provided Free for PM...Complete Online PMP Study Training Material for PMP Exam Provided Free for PM...
Complete Online PMP Study Training Material for PMP Exam Provided Free for PM...
GlobalSkillup
 
Organizational project maturity model (opm3)
Organizational project maturity model (opm3)Organizational project maturity model (opm3)
Organizational project maturity model (opm3)
Daniele Pinto
 
Project scope and requirements management
Project scope and requirements managementProject scope and requirements management
Project scope and requirements management
tictactoe123
 
PMP Certification - An Overview 2021
PMP Certification - An Overview 2021PMP Certification - An Overview 2021
PMP Certification - An Overview 2021
Muhammad Jahan Zeb Khan P.Eng., PMP, MCP
 
PMP Exam Prep_sample slides
PMP Exam Prep_sample slidesPMP Exam Prep_sample slides
PMP Exam Prep_sample slides
Wilber Tuttleman
 
Instructor Slides - PMP/CAPM PMBOK 6th Edition
Instructor Slides - PMP/CAPM PMBOK 6th EditionInstructor Slides - PMP/CAPM PMBOK 6th Edition
Instructor Slides - PMP/CAPM PMBOK 6th Edition
Mnbianchi
 
PMP Chapter 1 of 6 introduction (Based on PMBOK 6th edition)
PMP Chapter 1 of 6  introduction (Based on PMBOK 6th edition)PMP Chapter 1 of 6  introduction (Based on PMBOK 6th edition)
PMP Chapter 1 of 6 introduction (Based on PMBOK 6th edition)
Shamil Habet
 
PMBOK® Guide Processes Flow – 6th Edition
PMBOK® Guide Processes Flow – 6th EditionPMBOK® Guide Processes Flow – 6th Edition
PMBOK® Guide Processes Flow – 6th Edition
Ricardo Viana Vargas
 
PMBOK® Guide Processes Flow – 6th Edition (Simplified version)
PMBOK® Guide Processes Flow – 6th Edition (Simplified version)PMBOK® Guide Processes Flow – 6th Edition (Simplified version)
PMBOK® Guide Processes Flow – 6th Edition (Simplified version)
Ricardo Viana Vargas
 
Project Management Professional PMI-PMP Based on PMBOK 6th Edition
Project Management Professional PMI-PMP Based on PMBOK 6th EditionProject Management Professional PMI-PMP Based on PMBOK 6th Edition
Project Management Professional PMI-PMP Based on PMBOK 6th Edition
John Khateeb
 
PMP® Exam Questions and Answers 2019 | PMP Exam Preparation | PMP® Exam Train...
PMP® Exam Questions and Answers 2019 | PMP Exam Preparation | PMP® Exam Train...PMP® Exam Questions and Answers 2019 | PMP Exam Preparation | PMP® Exam Train...
PMP® Exam Questions and Answers 2019 | PMP Exam Preparation | PMP® Exam Train...
Edureka!
 
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
Anand Bobade
 
PMP Chap 4 - Project Integration Management - Part1
PMP Chap 4 - Project Integration Management - Part1PMP Chap 4 - Project Integration Management - Part1
PMP Chap 4 - Project Integration Management - Part1
Anand Bobade
 
Opm3™ Knowledge Foundation
Opm3™ Knowledge FoundationOpm3™ Knowledge Foundation
Opm3™ Knowledge Foundation
Huong Hoang, PMP®, CSM®
 
Project Scope Management,PMP Chapter 5,PMBOK,PMP Exam Preparation training
Project Scope Management,PMP Chapter 5,PMBOK,PMP Exam Preparation trainingProject Scope Management,PMP Chapter 5,PMBOK,PMP Exam Preparation training
Project Scope Management,PMP Chapter 5,PMBOK,PMP Exam Preparation training
JustAcademy
 
Pmp study-notes
Pmp study-notesPmp study-notes
Pmp study-notes
Krishna Murthy RVN
 
PMBOK® Guide Sixth Edition | Project Management Certification | PMP® Certific...
PMBOK® Guide Sixth Edition | Project Management Certification | PMP® Certific...PMBOK® Guide Sixth Edition | Project Management Certification | PMP® Certific...
PMBOK® Guide Sixth Edition | Project Management Certification | PMP® Certific...
Edureka!
 

What's hot (20)

PMO Presentation
PMO PresentationPMO Presentation
PMO Presentation
 
Pmp exam questions
Pmp exam questionsPmp exam questions
Pmp exam questions
 
Complete Online PMP Study Training Material for PMP Exam Provided Free for PM...
Complete Online PMP Study Training Material for PMP Exam Provided Free for PM...Complete Online PMP Study Training Material for PMP Exam Provided Free for PM...
Complete Online PMP Study Training Material for PMP Exam Provided Free for PM...
 
Organizational project maturity model (opm3)
Organizational project maturity model (opm3)Organizational project maturity model (opm3)
Organizational project maturity model (opm3)
 
Project scope and requirements management
Project scope and requirements managementProject scope and requirements management
Project scope and requirements management
 
PMP Certification - An Overview 2021
PMP Certification - An Overview 2021PMP Certification - An Overview 2021
PMP Certification - An Overview 2021
 
PMP Exam Prep_sample slides
PMP Exam Prep_sample slidesPMP Exam Prep_sample slides
PMP Exam Prep_sample slides
 
Instructor Slides - PMP/CAPM PMBOK 6th Edition
Instructor Slides - PMP/CAPM PMBOK 6th EditionInstructor Slides - PMP/CAPM PMBOK 6th Edition
Instructor Slides - PMP/CAPM PMBOK 6th Edition
 
PMP Chapter 1 of 6 introduction (Based on PMBOK 6th edition)
PMP Chapter 1 of 6  introduction (Based on PMBOK 6th edition)PMP Chapter 1 of 6  introduction (Based on PMBOK 6th edition)
PMP Chapter 1 of 6 introduction (Based on PMBOK 6th edition)
 
PMBOK® Guide Processes Flow – 6th Edition
PMBOK® Guide Processes Flow – 6th EditionPMBOK® Guide Processes Flow – 6th Edition
PMBOK® Guide Processes Flow – 6th Edition
 
PMO-Framework
PMO-FrameworkPMO-Framework
PMO-Framework
 
PMBOK® Guide Processes Flow – 6th Edition (Simplified version)
PMBOK® Guide Processes Flow – 6th Edition (Simplified version)PMBOK® Guide Processes Flow – 6th Edition (Simplified version)
PMBOK® Guide Processes Flow – 6th Edition (Simplified version)
 
Project Management Professional PMI-PMP Based on PMBOK 6th Edition
Project Management Professional PMI-PMP Based on PMBOK 6th EditionProject Management Professional PMI-PMP Based on PMBOK 6th Edition
Project Management Professional PMI-PMP Based on PMBOK 6th Edition
 
PMP® Exam Questions and Answers 2019 | PMP Exam Preparation | PMP® Exam Train...
PMP® Exam Questions and Answers 2019 | PMP Exam Preparation | PMP® Exam Train...PMP® Exam Questions and Answers 2019 | PMP Exam Preparation | PMP® Exam Train...
PMP® Exam Questions and Answers 2019 | PMP Exam Preparation | PMP® Exam Train...
 
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
 
PMP Chap 4 - Project Integration Management - Part1
PMP Chap 4 - Project Integration Management - Part1PMP Chap 4 - Project Integration Management - Part1
PMP Chap 4 - Project Integration Management - Part1
 
Opm3™ Knowledge Foundation
Opm3™ Knowledge FoundationOpm3™ Knowledge Foundation
Opm3™ Knowledge Foundation
 
Project Scope Management,PMP Chapter 5,PMBOK,PMP Exam Preparation training
Project Scope Management,PMP Chapter 5,PMBOK,PMP Exam Preparation trainingProject Scope Management,PMP Chapter 5,PMBOK,PMP Exam Preparation training
Project Scope Management,PMP Chapter 5,PMBOK,PMP Exam Preparation training
 
Pmp study-notes
Pmp study-notesPmp study-notes
Pmp study-notes
 
PMBOK® Guide Sixth Edition | Project Management Certification | PMP® Certific...
PMBOK® Guide Sixth Edition | Project Management Certification | PMP® Certific...PMBOK® Guide Sixth Edition | Project Management Certification | PMP® Certific...
PMBOK® Guide Sixth Edition | Project Management Certification | PMP® Certific...
 

Similar to PMINEO_2012_03_OPM3_Organizational_PM_Maturity

Pmi, Opm3 And Cmmi Assessment Overview
Pmi, Opm3 And Cmmi Assessment OverviewPmi, Opm3 And Cmmi Assessment Overview
Pmi, Opm3 And Cmmi Assessment OverviewAlan McSweeney
 
Cmmi
CmmiCmmi
Cmmi
bht all
 
CMMI for Development Workshop
CMMI for Development WorkshopCMMI for Development Workshop
CMMI for Development Workshop
Sherif Salah
 
Introduction to CMMI-DEV v1.3 - Day 1
Introduction to CMMI-DEV v1.3  - Day 1Introduction to CMMI-DEV v1.3  - Day 1
Introduction to CMMI-DEV v1.3 - Day 1
Sherif Salah, MBA, ITIL, CMMI, MCSA, TQM
 
9.process improvement chapter 9
9.process improvement chapter 99.process improvement chapter 9
9.process improvement chapter 9
Warui Maina
 
QAI - Cmmi Overview - Induction ppt
QAI - Cmmi Overview - Induction pptQAI - Cmmi Overview - Induction ppt
QAI - Cmmi Overview - Induction pptQAIites
 
CMMI and Agile
CMMI and AgileCMMI and Agile
CMMI and Agile
Glen Alleman
 
CH-2.1 Conceptualizing and Initializing the IT Project.ppt
CH-2.1 Conceptualizing and Initializing the IT Project.pptCH-2.1 Conceptualizing and Initializing the IT Project.ppt
CH-2.1 Conceptualizing and Initializing the IT Project.ppt
amanuel236786
 
Kivanc Kanturk Swe550 Fall2010 Capability Maturity Model Integration (Cmmi)
Kivanc Kanturk Swe550 Fall2010 Capability Maturity Model Integration (Cmmi)Kivanc Kanturk Swe550 Fall2010 Capability Maturity Model Integration (Cmmi)
Kivanc Kanturk Swe550 Fall2010 Capability Maturity Model Integration (Cmmi)
Kivanc Kanturk
 
COBIT®5 - Assessor
COBIT®5 - AssessorCOBIT®5 - Assessor
The True Costs and Benefits of CMMI Level 5
The True Costs and Benefits of CMMI Level 5The True Costs and Benefits of CMMI Level 5
The True Costs and Benefits of CMMI Level 5
rhefner
 
Project Management Framework
Project Management FrameworkProject Management Framework
Project Management Framework
Rahul Sudame
 
Applicability of CMMI for Small to Medium Enterprises
Applicability of CMMI for Small to Medium EnterprisesApplicability of CMMI for Small to Medium Enterprises
Applicability of CMMI for Small to Medium Enterprises
rhefner
 
Business Case4 Process Improvement
Business Case4 Process ImprovementBusiness Case4 Process Improvement
Business Case4 Process Improvement
Al Bennett
 
scribd.vdownloaders.com_day-6-quality.pdf
scribd.vdownloaders.com_day-6-quality.pdfscribd.vdownloaders.com_day-6-quality.pdf
scribd.vdownloaders.com_day-6-quality.pdf
AbdullahSamy6
 
Leading a Lean Implementation
Leading a Lean ImplementationLeading a Lean Implementation
Leading a Lean Implementation
Life Cycle Engineering
 
CMMI V1.3
CMMI V1.3CMMI V1.3
CMMI V1.3
Coupons Fantasy
 
Lean pilots by Mariya Breyter from Dun & Bradstreet
Lean pilots by Mariya Breyter from Dun & BradstreetLean pilots by Mariya Breyter from Dun & Bradstreet
Lean pilots by Mariya Breyter from Dun & Bradstreet
Institut Lean France
 
presentations_Day 3 & 4-Capability Maturity Model Integration (CMMI).pptx
presentations_Day 3 & 4-Capability Maturity Model Integration (CMMI).pptxpresentations_Day 3 & 4-Capability Maturity Model Integration (CMMI).pptx
presentations_Day 3 & 4-Capability Maturity Model Integration (CMMI).pptx
BenjaminFamili
 
Slides 2015 for contact 2
Slides 2015 for contact 2Slides 2015 for contact 2
Slides 2015 for contact 2
YourhighnessJordaan
 

Similar to PMINEO_2012_03_OPM3_Organizational_PM_Maturity (20)

Pmi, Opm3 And Cmmi Assessment Overview
Pmi, Opm3 And Cmmi Assessment OverviewPmi, Opm3 And Cmmi Assessment Overview
Pmi, Opm3 And Cmmi Assessment Overview
 
Cmmi
CmmiCmmi
Cmmi
 
CMMI for Development Workshop
CMMI for Development WorkshopCMMI for Development Workshop
CMMI for Development Workshop
 
Introduction to CMMI-DEV v1.3 - Day 1
Introduction to CMMI-DEV v1.3  - Day 1Introduction to CMMI-DEV v1.3  - Day 1
Introduction to CMMI-DEV v1.3 - Day 1
 
9.process improvement chapter 9
9.process improvement chapter 99.process improvement chapter 9
9.process improvement chapter 9
 
QAI - Cmmi Overview - Induction ppt
QAI - Cmmi Overview - Induction pptQAI - Cmmi Overview - Induction ppt
QAI - Cmmi Overview - Induction ppt
 
CMMI and Agile
CMMI and AgileCMMI and Agile
CMMI and Agile
 
CH-2.1 Conceptualizing and Initializing the IT Project.ppt
CH-2.1 Conceptualizing and Initializing the IT Project.pptCH-2.1 Conceptualizing and Initializing the IT Project.ppt
CH-2.1 Conceptualizing and Initializing the IT Project.ppt
 
Kivanc Kanturk Swe550 Fall2010 Capability Maturity Model Integration (Cmmi)
Kivanc Kanturk Swe550 Fall2010 Capability Maturity Model Integration (Cmmi)Kivanc Kanturk Swe550 Fall2010 Capability Maturity Model Integration (Cmmi)
Kivanc Kanturk Swe550 Fall2010 Capability Maturity Model Integration (Cmmi)
 
COBIT®5 - Assessor
COBIT®5 - AssessorCOBIT®5 - Assessor
COBIT®5 - Assessor
 
The True Costs and Benefits of CMMI Level 5
The True Costs and Benefits of CMMI Level 5The True Costs and Benefits of CMMI Level 5
The True Costs and Benefits of CMMI Level 5
 
Project Management Framework
Project Management FrameworkProject Management Framework
Project Management Framework
 
Applicability of CMMI for Small to Medium Enterprises
Applicability of CMMI for Small to Medium EnterprisesApplicability of CMMI for Small to Medium Enterprises
Applicability of CMMI for Small to Medium Enterprises
 
Business Case4 Process Improvement
Business Case4 Process ImprovementBusiness Case4 Process Improvement
Business Case4 Process Improvement
 
scribd.vdownloaders.com_day-6-quality.pdf
scribd.vdownloaders.com_day-6-quality.pdfscribd.vdownloaders.com_day-6-quality.pdf
scribd.vdownloaders.com_day-6-quality.pdf
 
Leading a Lean Implementation
Leading a Lean ImplementationLeading a Lean Implementation
Leading a Lean Implementation
 
CMMI V1.3
CMMI V1.3CMMI V1.3
CMMI V1.3
 
Lean pilots by Mariya Breyter from Dun & Bradstreet
Lean pilots by Mariya Breyter from Dun & BradstreetLean pilots by Mariya Breyter from Dun & Bradstreet
Lean pilots by Mariya Breyter from Dun & Bradstreet
 
presentations_Day 3 & 4-Capability Maturity Model Integration (CMMI).pptx
presentations_Day 3 & 4-Capability Maturity Model Integration (CMMI).pptxpresentations_Day 3 & 4-Capability Maturity Model Integration (CMMI).pptx
presentations_Day 3 & 4-Capability Maturity Model Integration (CMMI).pptx
 
Slides 2015 for contact 2
Slides 2015 for contact 2Slides 2015 for contact 2
Slides 2015 for contact 2
 

PMINEO_2012_03_OPM3_Organizational_PM_Maturity

  • 1. 1 Organizational Project Management (OPM), With a focus on OPM3 PMINEO Chapter meeting March 15, 2012 Presented by Bob Zoller, PMP Email: RLZoller@gmail.com See notes in “Notes Page” view
  • 2. 2 Agenda 1. Introduction to OPM 2. OPM3 framework from PMI® 3. OPM3 assessment exercise 4. Maturity Assessment Process 5. Alternative frameworks  CMMI, IVI IT-CMF, Kerzner KPM3 6. Summary of options 7. Benefits 8. References & More Information 9. Discussion (Short questions during program, and discussion at the end)
  • 3. 3 1. Introduction to OPM (not OPM3) Gartner survey of 130 organizations: “What is the top success criterion for your projects?” Note that alignment is #1 at 29%. Cost, budget, scope (triple constraint) total to only 40%. Reference (1) PMI standard presentation on OPM3
  • 4. 4 1. Introduction to OPM. OPM = Organizational Project Management: OPM:The alignment and systematic management of projects, programs and portfolios to achieve strategic organizational goals Reference (2) Ginger Levin general slides © Ginger Levin, 2011 Does your organization use OPM? Or does the “squeaky wheel get the grease” ?
  • 5. 5 2. OPM3 framework from PMI® PMI® recognized a need and created “Organizational Project Management Maturity Model” (OPM3)  2003 First Edition of OPM3 standard  2008 Second Edition; alignment with other PMI® standards  OPM3 acceptance level has been low, is being addressed:  Newer versions of software are not buggy, as earlier ones were  OPM3 standard being rewritten in more business-friendly terms  PMI® is promoting OPM3 more heavily
  • 6. 6 2. OPM3 framework from PMI® Library of PMI® Global Standards 1. Foundational Standards  Project Management (PMBOK®)  Program Management  Portfolio Management  Organizational Project Management (OPM3) 2. Practice Standards and Frameworks  (7) exist, including: Risk; Scheduling; WBS 3. Foundational Extensions  (2) exist; PMBOK® for construction, government See: http://www.pmi.org/PMBOK-Guide-and-Standards/Standards-Library-of-PMI-Global-Standards.aspx
  • 7. 7 2. OPM3 framework from PMI® OPM3 Best Practice concepts, 488 total: (A) Domain processes x 4 improvement stages  Project (42 processes) x 4 = 168 Best Practices  Program (47 processes) x 4 = 188 Best Practices  Portfolio (14 processes) x 4 = 56 Best Practices (B) Organizational Enablers (76) Total: 168 + 188 + 56 + 76 = 488 Best Practices
  • 8. 8 2. OPM3 framework from PMI® OPM3 Best Practice concepts, 488 total: (A) Domain processes x 4 improvement stages  Four Process Improvement Stages, SMCI:  Standardize = Consistent, documented, communicated  Measure = Identify & measure: inputs, characteristics, results  Control = Control plan is developed and implemented  Improve = Identify problems, implement sustainable improvements
  • 9. 9 2. OPM3 framework from PMI® OPM3 Best Practice concepts, 488 total: (A) Domain processes x 4 improvement stages  Example process: Develop Project Charter  Standardized ?  Measured ?  Controlled ?  Improve ?
  • 10. 10 2. OPM3 framework from PMI® . (B) OPM3 - Organizational Enablers  Facilitate implementation and sustainability  22 groups, with 76 total OE items. Examples:  PMIS and Knowledge Management  7365: Project Management Information System  7375: Intellectual Capital Reuse  5660: Manage Portfolio Value  Resource Allocation  5220: Provide Competent Organizational PM Resources  1590: Record Project Resource Assignments
  • 11. 11 3. OPM3 Assessment Exercise Group exercise: Review lists of OPM3 BestPractices… See separate documents with Best Practices lists, and with survey of PMINEO chapter meeting attendees on PMBOK practice standardization.
  • 12. 12 4. Maturity Assessment Process OPM3 assessment options  Self-assessment using online tools.  Simpler tool (Yes/No questions) for roughly $1,000  Benchmark against other companies  Hire certified assessor  Assessor uses more robust toolset  Low end: $15-20K, 2-3 weeks total, single site  Higher: multiple months, $100K, international scope  Can limit scope (ex: Portfolio, or “Standardize”)
  • 13. 13 4. Maturity Assessment Process. Common steps, with OPM3 or most frameworks: 1) Obtain organizational commitment; hold a kickoff meeting 2) Review organizational documents (ex: policies) 3) Review sample program and project documents 4) Distribute questionnaires 5) Conduct interviews 6) Analyze results 7) Report results and recommendations for improvement 8) Determine when to reassess Reference (3) Ginger Levin, “Maturity Models”
  • 14. 14 5. Alternative Frameworks 5.1) CMMI = Capability Maturity Model Integration 5.2) IT-CMF from IVI (Innovation Value Institute) 5.3) Kerzner Project Management Maturity Model Local notes: Rockwell Automation has been considering OPM3 as a standard Progressive is considering a combination of OPM3 and IT-CMF from IVI
  • 15. 15 5.1) CMMI  CMMI = Capability Maturity Model Integration  One of the best known maturity models  CMMI replaced CMM (developed from 1987 - 1997)  CMMI:  A Process Improvement Approach  Identify strengths and weaknesses  Assessment leads to overall maturity ranking of 1, 2, 3, 4, or 5  Plan process changes to address weaknesses References: (4) CMMI site, (5) Wikipedia
  • 16. 16 5.1) CMMI  Most organizations start in CMMI at level 1 or 2  Growth to level 3 (govmt contracts) can take a few years
  • 17. 17 5.1) CMMI. CMMI currently addresses three areas of interest: 1. Product and service Development (CMMI-DEV), 2. Service establishment, management, and delivery — (CMMI-SVC) 3. Product and service acquisition — (CMMI-ACQ). The CMMI model mostly deals with what processes should be implemented, and not so much with how they can be implemented.
  • 18. 18 5.2) IT-CMF from IVI IVI = Innovation Value Institute  A global consortium of industry, government, non-profit, and academic organizations, established in 2006  Goal: define standard for managing IT for business value  Includes Intel, Ernst & Young, Google, Microsoft, SAP IT-CMF = IT Capability Maturity Framework  An assessment framework for total IT business value  Portfolio/Program/Project are components of total scope Reference: (7) Managing IT for Business Value
  • 21. 21 5.2) IT-CMF from IVI.  Levels of membership exist, for education, assessment, mentoring  Full adoption journey covers 12-24 months, including education, assessment, review, new practices  Options include self-help with online tools, IVI staff, consulting organizations
  • 22. 22 5.3) Kerzner PM3 Perform self-assessment using an online tool:  Each participant answers 183 multiple choice questions  Generate a score for your organization & Project Managers  Benchmark your scores against your industry and overall  Create a list of actionable recommendations Focus is on Project Management and PMBOK List price is $95 per person, with volume discounts
  • 24. 24 5.3) Kerzner PM3. Level 1: common language. “Definition of Scope Management is...” Level 2: common processes. “Our executives have demonstrated a willingness to change….“ Level 3: singular methodology. “My company actively uses the following processes….” Level 4: benchmarking. “Benchmarking has found companies with tighter cost controls…“ Level 5: continuous improvement. “Methodology improvements have pushed us closer to customers….“
  • 25. 25 6. Summary of Options. Option Notes OPM3 • Scope: Portfolio/Program/Project management, for IT or other • Uses Best Practices; does not provide summary score CMMI • Scope: Development, Service, Acquisition processes • Uses 5 levels of progressive maturity • Summary level scores well-known (ex: “3” for govmt contracts) IT-CMF of IVI • Scope: IT, overall, including projects and operations • Addresses 32 process areas, in four groupings • Note that IVI is seeking to collaborate with CMMI KPM3 • Scope: Project Management and PMBOK • Uses 5 generally progressive levels of maturity • Can be done on self-help basis, at low cost, w optional consulting
  • 26. 26 7. Benefits. CMMI site has published results of projects  Costs: Siemens reduced cost of quality from 45% to 30% in 3 years  Schedule: GM improved percent of milestones met from 50% to 85%  Productivity: Warner Robbins reduced effort to deliver test program sets by 25%  Quality: Siemens reduced defect density an average of 71% in 3 technical areas  Customer Satisfaction: Northrup Grumman received 98% of customer award fees  ROI: Accenture experienced 5 to 1 ROI for quality activities Reference: (4), CMMI site, page http://www.sei.cmu.edu/cmmi/why/benefits/. See published appraisal results.
  • 27. 27 8. References & More Information References (1) OPM3 standard presentation slides from PMI (2) Ginger Levin, certified OPM3 consultant; engagement slides Gin;evin@AOL.com, http://www.linkedin.com/in/gingerlevin (3) Ginger Levin, “Maturity Models” chapter for book by Dr. Rodney Turner (4) CMMI website (http://www.sei.cmu.edu/cmmi/) (5) CMMI on Wikipedia (http://en.wikipedia.org/wiki/CMMI) (6) “Managing IT for Business Value” the Boston Consulting Group, for IVI and IT-CMF (7) Claudia Baca, OPM3 committee, certified consultant cmbaca@att.net , http://www.linkedin.com/pub/claudia-baca/5/105/455 (8) Kerzner PM3 from www.iil.com/kpm3 (9) “Capability Immaturity Model”, Schorsch, Nexus, 1996 (10) OPM3 standard from PMI 2nd Edition, 2008
  • 28. 28 8. References & More Information. More Information a) PMI “Community of Practice” for OPM Free membership; newsletters; webinars See: http://opm.vc.pmi.org/ b) IVI, Innovation Value Institute See: http://ivi.nuim.ie/ See also Boston Consulting Group at: http://www.bcg.com/ c) ESI International Training, assessment, support, for Portfolio//ProgramProject Mgmt. See: http://www.esi-intl.com/ d) OPM3 and other standards publications are available for on-line viewing for PMI members, on PMI.org
  • 29. 29 9. Discussion 1. Standing Ovation 2. Discussion