The document discusses cost estimation and control for projects. It outlines inputs, techniques, and outputs for estimating costs, developing a cost baseline and budget, and controlling costs using earned value management. Key steps include determining the project scope and work breakdown structure, developing cost estimates, setting a budget, and monitoring performance to track cost and schedule variance and forecast estimates to completion. The goal is to deliver the project according to the approved scope within the allocated time and funds.
A short presentation I did in simple words, aimed at explaining time driven activity based costing and how it fits in a performance management framework to a new audience
A short presentation I did in simple words, aimed at explaining time driven activity based costing and how it fits in a performance management framework to a new audience
Activity based costing is considered to be useful only for Manufacturing Organizations whereas reality is that it is equally usefull to Service providers
Earned schedule role in performance reporting and other important delay indicators.
Video: https://www.youtube.com/watch?v=FbA6RWB1gDM&feature=youtu.be
The full course: https://www.luqmanacademy.com/course?course=project-control-using-evm_399sl6015424f8aba9
Video: https://twitter.com/magedkom/status/1354678096683618305?s=20
Program Management 2.0: Work Breakdown StructureJohn Carter
From a course titled Program Management 2.0, this presentation pulls together a suite of tools for creating a Work Breakdown Structure - which is very helpful for tracking the true project a project is making. It lends itself to also communicate the earned value of a project - so teams and managers can see what is done, and what is left to do.
In many organizations, bottom up estimation of software development projects is still the way to go. Management feels that top-down (parametric) estimation models require too much effort and cost. In this presentation, a random selection of 10 bids are analyzed and the bottom-up estimates and top-down estimates are compared with regard to accuracy and effort spend.
Activity based costing is considered to be useful only for Manufacturing Organizations whereas reality is that it is equally usefull to Service providers
Earned schedule role in performance reporting and other important delay indicators.
Video: https://www.youtube.com/watch?v=FbA6RWB1gDM&feature=youtu.be
The full course: https://www.luqmanacademy.com/course?course=project-control-using-evm_399sl6015424f8aba9
Video: https://twitter.com/magedkom/status/1354678096683618305?s=20
Program Management 2.0: Work Breakdown StructureJohn Carter
From a course titled Program Management 2.0, this presentation pulls together a suite of tools for creating a Work Breakdown Structure - which is very helpful for tracking the true project a project is making. It lends itself to also communicate the earned value of a project - so teams and managers can see what is done, and what is left to do.
In many organizations, bottom up estimation of software development projects is still the way to go. Management feels that top-down (parametric) estimation models require too much effort and cost. In this presentation, a random selection of 10 bids are analyzed and the bottom-up estimates and top-down estimates are compared with regard to accuracy and effort spend.
لمشاهدة ملفات الفيديو
https://www.youtube.com/watch?v=gKbK6kCp7G0&list=PL0CTRdzzWSMuvJ9nKHzyxGAYCapJMQ8_Y&index=15
للمتابعة في جروب المذاكرة
https://www.facebook.com/groups/PMP.SG
6. Outputs :
Inputs : Technique: 1. Work performance
measurements
1. Earned Value 2. Budget forecasts .
1. Project Management
Management plan 3. Change request .
2.Forecasting
2. Project funding 4. Project plan update
requirements . 3. Performance
review . 5. Project document
3. Work update
performance 4,5,6
6. Organizational
information
process assets updates
4. OPA
7. Primary Data Points
Budget At Completion (BAC)
PV = BAC * % of planned work.
EV = BAC * % of Actual work
AC is the actual cost
8. Problem: A project has a budget of £10M and schedule for 10 months. It is
assumed that the total budget will be spent equally each month until the 10th
month is reached. After 2 months the project manager finds that only 5% of
the work is finished and a total of £1M spent.
PV = £2M
EV = £10M * 0.05 = £0.5M
AV = £1M
CV = EV-AC = 0.5-1 = -0.5M
SV = EV-PV = 0.5-2 = -1.5 months
CPI = EV/AC = 0.5/1 = 0.5
SPI = EV/PV = 0.5/2 = 0.25
EAC = BAC/CPI = 10/0.5 = £20M
ETC = (BAC-EV) / CPI = (10-0.5)/0.5 = £19M
TTC= (BAC-EV) / SPI= (10-0.5)/0.25 = 38 Months
This project will take TOTAL £20M (19+1) and 40 (38+2) Months to complete.