SlideShare a Scribd company logo
By : Ahmed Zein
MBA E-Business
Eng_ahmedzein@yahoo.com
1. Cost Estimation .


2. Determine Budget .


3. Control Costs .
Outputs :
Inputs :                    Techniques                         1.   Activity cost
1. Scope baseline           1. Expert Judgment                      estimates
(scope                      2. Analogous                       2.   Basis of
statement+ wbs)                estimation                           estimation
2. Schedule                 3. Vendor bid                      3.   project
                            analysis                                document
3.HR plan                                                           update
                            4.
4. Risk register
                            5,6,7,8,9
5. E E F
6. O P A

                                      1000 $$



                                                 50000 $$


                    1500$

                                                     3000 $$




                            2000 $$
Technique:            Outputs :
Inputs :            1. Cost               1. Cost baseline
1. Activity cost    aggregation           2. Project funding
estimates           2. Reserve analysis      requirements
2. Basis of         3. Expert             3. Project
estimation .        judgment                 document
3. Scope baseline   4. Historical            Update .
4. schedule         information
5. Calendar         5. Funding limit
6. Contracts        reconciliation
7. OPA
Outputs :

Inputs :             Technique:        1. Work performance
                                          measurements
                     1. Earned Value   2. Budget forecasts .
1. Project              Management
Management plan                        3. Change request .
                     2.Forecasting
2. Project funding                     4. Project plan update
requirements .       3. Performance
                     review .          5. Project document
3. Work                                   update
performance          4,5,6
                                       6. Organizational
information
                                          process assets updates
4. OPA
Primary Data Points
Budget At Completion (BAC)
PV = BAC * % of planned work.
EV = BAC * % of Actual work
AC is the actual cost
Problem: A project has a budget of £10M and schedule for 10 months. It is
assumed that the total budget will be spent equally each month until the 10th
month is reached. After 2 months the project manager finds that only 5% of
the work is finished and a total of £1M spent.

PV = £2M
EV = £10M * 0.05 = £0.5M
AV = £1M
CV = EV-AC = 0.5-1 = -0.5M
SV = EV-PV = 0.5-2 = -1.5 months
CPI = EV/AC = 0.5/1 = 0.5
SPI = EV/PV = 0.5/2 = 0.25
EAC = BAC/CPI = 10/0.5 = £20M

ETC = (BAC-EV) / CPI = (10-0.5)/0.5 = £19M
TTC= (BAC-EV) / SPI= (10-0.5)/0.25 = 38 Months
This project will take TOTAL £20M (19+1) and 40 (38+2) Months to complete.

More Related Content

Viewers also liked

methods, techniques and system of costing
methods, techniques and system of costingmethods, techniques and system of costing
methods, techniques and system of costing
kunalaggarwal2007
 
Unit 9 costing methods
Unit 9 costing methodsUnit 9 costing methods
Unit 9 costing methodsRyk Ramos
 
Activity Based Costing
Activity Based CostingActivity Based Costing
Activity Based Costing
Vikas Gupta
 
Cost & Management Accounting Techniques
Cost & Management Accounting TechniquesCost & Management Accounting Techniques
Cost & Management Accounting Techniques
Stroke Keys
 
TIME DRIVEN ACTIVITY BASED COSTING
TIME DRIVEN ACTIVITY BASED COSTINGTIME DRIVEN ACTIVITY BASED COSTING
TIME DRIVEN ACTIVITY BASED COSTING
Else Kuipers
 
Activity based costing
Activity based costingActivity based costing
Activity based costing
sachdevkkapil
 

Viewers also liked (7)

methods, techniques and system of costing
methods, techniques and system of costingmethods, techniques and system of costing
methods, techniques and system of costing
 
Unit 9 costing methods
Unit 9 costing methodsUnit 9 costing methods
Unit 9 costing methods
 
Activity Based Costing
Activity Based CostingActivity Based Costing
Activity Based Costing
 
Cost & Management Accounting Techniques
Cost & Management Accounting TechniquesCost & Management Accounting Techniques
Cost & Management Accounting Techniques
 
TIME DRIVEN ACTIVITY BASED COSTING
TIME DRIVEN ACTIVITY BASED COSTINGTIME DRIVEN ACTIVITY BASED COSTING
TIME DRIVEN ACTIVITY BASED COSTING
 
Activity-Based Costing System
Activity-Based Costing SystemActivity-Based Costing System
Activity-Based Costing System
 
Activity based costing
Activity based costingActivity based costing
Activity based costing
 

Similar to Pmi project cost managment

ادارة تكلفة المشروع
ادارة تكلفة المشروع ادارة تكلفة المشروع
ادارة تكلفة المشروع
Mohamed Dahi
 
Chapter 07
Chapter 07Chapter 07
Chapter 07
KareemBullard1
 
Intro to PM.ppt
Intro to PM.pptIntro to PM.ppt
Intro to PM.ppt
Chandrabhan Seniya
 
Topic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdfTopic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdf
HuyNguyen657394
 
Vanessa.jeff
Vanessa.jeffVanessa.jeff
Vanessa.jeffNASAPMC
 
project time management
 project time management project time management
project time management
Hira Atiq
 
Flow of PMBOK 4th Edition in English - Black and White
Flow of PMBOK 4th Edition in English - Black and WhiteFlow of PMBOK 4th Edition in English - Black and White
Flow of PMBOK 4th Edition in English - Black and White
Ricardo Viana Vargas
 
Flow of PMBOK 4th Edition in English - Color
Flow of PMBOK 4th Edition in English - ColorFlow of PMBOK 4th Edition in English - Color
Flow of PMBOK 4th Edition in English - Color
Ricardo Viana Vargas
 
Performing against the wall - SPI after completion
Performing against the wall - SPI after completionPerforming against the wall - SPI after completion
Performing against the wall - SPI after completion
M Maged Hegazy, LLM, MBA, CCP, P3O
 
PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7
Muzette Charles, PMP
 
CCI PM Processes (within PMP Process Groups and Knowledge Areas)
CCI PM Processes (within PMP Process Groups and Knowledge Areas)CCI PM Processes (within PMP Process Groups and Knowledge Areas)
CCI PM Processes (within PMP Process Groups and Knowledge Areas)Pamela Garrett
 
07 projectcostmanagement
07 projectcostmanagement07 projectcostmanagement
07 projectcostmanagement
Dhamo daran
 
Program Management 2.0: Work Breakdown Structure
Program Management 2.0: Work Breakdown StructureProgram Management 2.0: Work Breakdown Structure
Program Management 2.0: Work Breakdown Structure
John Carter
 
Van heeringen estimate faster, cheaper, better
Van heeringen   estimate faster, cheaper, betterVan heeringen   estimate faster, cheaper, better
Van heeringen estimate faster, cheaper, better
Harold van Heeringen
 
6- PMP Training - Cost Management
6- PMP Training - Cost Management6- PMP Training - Cost Management
6- PMP Training - Cost Management
Qais Ur Rehman Rasooli, PMP
 
07.cost management updated
07.cost management updated07.cost management updated
07.cost management updatedShraddha PMP
 
I tt-o of pmp processes.5th ed
I tt-o of pmp processes.5th edI tt-o of pmp processes.5th ed
I tt-o of pmp processes.5th edElMazagangy
 
Thomas.a.greathouse.r
Thomas.a.greathouse.rThomas.a.greathouse.r
Thomas.a.greathouse.rNASAPMC
 
day 3 PMP.pptx
day 3 PMP.pptxday 3 PMP.pptx
day 3 PMP.pptx
AhmedKayed6
 
PMP Preparation - 07 Cost Management
PMP Preparation - 07 Cost ManagementPMP Preparation - 07 Cost Management
PMP Preparation - 07 Cost Management
Mohamed ElSaadany, PMP, CCP, PMI-RMP, SCE-PE
 

Similar to Pmi project cost managment (20)

ادارة تكلفة المشروع
ادارة تكلفة المشروع ادارة تكلفة المشروع
ادارة تكلفة المشروع
 
Chapter 07
Chapter 07Chapter 07
Chapter 07
 
Intro to PM.ppt
Intro to PM.pptIntro to PM.ppt
Intro to PM.ppt
 
Topic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdfTopic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdf
 
Vanessa.jeff
Vanessa.jeffVanessa.jeff
Vanessa.jeff
 
project time management
 project time management project time management
project time management
 
Flow of PMBOK 4th Edition in English - Black and White
Flow of PMBOK 4th Edition in English - Black and WhiteFlow of PMBOK 4th Edition in English - Black and White
Flow of PMBOK 4th Edition in English - Black and White
 
Flow of PMBOK 4th Edition in English - Color
Flow of PMBOK 4th Edition in English - ColorFlow of PMBOK 4th Edition in English - Color
Flow of PMBOK 4th Edition in English - Color
 
Performing against the wall - SPI after completion
Performing against the wall - SPI after completionPerforming against the wall - SPI after completion
Performing against the wall - SPI after completion
 
PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7
 
CCI PM Processes (within PMP Process Groups and Knowledge Areas)
CCI PM Processes (within PMP Process Groups and Knowledge Areas)CCI PM Processes (within PMP Process Groups and Knowledge Areas)
CCI PM Processes (within PMP Process Groups and Knowledge Areas)
 
07 projectcostmanagement
07 projectcostmanagement07 projectcostmanagement
07 projectcostmanagement
 
Program Management 2.0: Work Breakdown Structure
Program Management 2.0: Work Breakdown StructureProgram Management 2.0: Work Breakdown Structure
Program Management 2.0: Work Breakdown Structure
 
Van heeringen estimate faster, cheaper, better
Van heeringen   estimate faster, cheaper, betterVan heeringen   estimate faster, cheaper, better
Van heeringen estimate faster, cheaper, better
 
6- PMP Training - Cost Management
6- PMP Training - Cost Management6- PMP Training - Cost Management
6- PMP Training - Cost Management
 
07.cost management updated
07.cost management updated07.cost management updated
07.cost management updated
 
I tt-o of pmp processes.5th ed
I tt-o of pmp processes.5th edI tt-o of pmp processes.5th ed
I tt-o of pmp processes.5th ed
 
Thomas.a.greathouse.r
Thomas.a.greathouse.rThomas.a.greathouse.r
Thomas.a.greathouse.r
 
day 3 PMP.pptx
day 3 PMP.pptxday 3 PMP.pptx
day 3 PMP.pptx
 
PMP Preparation - 07 Cost Management
PMP Preparation - 07 Cost ManagementPMP Preparation - 07 Cost Management
PMP Preparation - 07 Cost Management
 

Pmi project cost managment

  • 1. By : Ahmed Zein MBA E-Business Eng_ahmedzein@yahoo.com
  • 2. 1. Cost Estimation . 2. Determine Budget . 3. Control Costs .
  • 3. Outputs : Inputs : Techniques 1. Activity cost 1. Scope baseline 1. Expert Judgment estimates (scope 2. Analogous 2. Basis of statement+ wbs) estimation estimation 2. Schedule 3. Vendor bid 3. project analysis document 3.HR plan update 4. 4. Risk register 5,6,7,8,9 5. E E F 6. O P A 1000 $$ 50000 $$ 1500$ 3000 $$ 2000 $$
  • 4. Technique: Outputs : Inputs : 1. Cost 1. Cost baseline 1. Activity cost aggregation 2. Project funding estimates 2. Reserve analysis requirements 2. Basis of 3. Expert 3. Project estimation . judgment document 3. Scope baseline 4. Historical Update . 4. schedule information 5. Calendar 5. Funding limit 6. Contracts reconciliation 7. OPA
  • 5.
  • 6. Outputs : Inputs : Technique: 1. Work performance measurements 1. Earned Value 2. Budget forecasts . 1. Project Management Management plan 3. Change request . 2.Forecasting 2. Project funding 4. Project plan update requirements . 3. Performance review . 5. Project document 3. Work update performance 4,5,6 6. Organizational information process assets updates 4. OPA
  • 7. Primary Data Points Budget At Completion (BAC) PV = BAC * % of planned work. EV = BAC * % of Actual work AC is the actual cost
  • 8. Problem: A project has a budget of £10M and schedule for 10 months. It is assumed that the total budget will be spent equally each month until the 10th month is reached. After 2 months the project manager finds that only 5% of the work is finished and a total of £1M spent. PV = £2M EV = £10M * 0.05 = £0.5M AV = £1M CV = EV-AC = 0.5-1 = -0.5M SV = EV-PV = 0.5-2 = -1.5 months CPI = EV/AC = 0.5/1 = 0.5 SPI = EV/PV = 0.5/2 = 0.25 EAC = BAC/CPI = 10/0.5 = £20M ETC = (BAC-EV) / CPI = (10-0.5)/0.5 = £19M TTC= (BAC-EV) / SPI= (10-0.5)/0.25 = 38 Months This project will take TOTAL £20M (19+1) and 40 (38+2) Months to complete.