SlideShare a Scribd company logo
Quiz.1
1. Which process formally authorizes the project?
a. Receive project approval
b. Identify Project Manager
c. Develop preliminary project statement
d. Develop project charter
e. Develop project management plan
2. Scope management is involved in which two project management lifecycle processes:
a) Initiation and planning.
b) Planning, monitoring, and control.
c) Planning and closured.
d) Selection and planning
3. The following components are involved in scope management planning: (T/F)
a) Collect scope requirements;
b) Define the scope;
c) Create WBS;
d) Verify scope;
e) Control scope
Given a project with the following characteristics, answer the following questions:
 You are the project manager of a project to build fancy birdhouses.
 You are to build two birdhouses a month for 12 months.
 Each birdhouse is planned to cost $100.
 Your project is scheduled to last for 12 months.
 It is the beginning of month 10.
 You have built 20 birdhouses and your CPI is .9091.
4. How is the project performing?
A. Over budget and ahead of schedule
B. Under budget and ahead of schedule
C. Over budget and behind schedule
D. Under budget and behind schedule.
Subject Marks Time
Project M&C and Evaluation Management 10 30 (Minutes)
Explanation:
CPI is .9091, and the CPI formula = EV/AC. CPI less than 1 means that we aren’t getting
the project Actual cost estimation, so it is over budget.
5. What is the actual cost of the project right now?
A. $1800
B. $2000
C. $2200
D. $2400
Explanation:
 CPI = EV/AC
 .9091 = 2000/AC
 AC(.9091) = 2000
 Actual Cost = 2200
6. Assuming that the COST variance experienced so far in the project will continue, how much
more money will it take to complete the project?
A. $400
B. $440
C. $2800
D. $2840
Explanation:
 Budget At Completion = 2 birdhouses per month x 12 months x $100 per birdhouse
 BAC = $2400
 Estimation To Complete = BAC/CPI – AC
 ETC = 2400/.9091 – 2200
 ETC = 440
7. If the variance experienced so far were to stop, what is the project’s estimate at completion?
A. $2400
B. $2440
C. $2600
D. $2800
Explanation:
 Estimate At Completion = AC + BAC – EV
 EAC = 2200 + 2400 – 2000
 EAC = $2600
8. What is the project’s TCPI using the project’s budget at completion?
A. .5
B. 1
C. 1.5
D. 2
Explanation:
 TCPI = (BAC – EV)/(BAC – AC)
 TCPI = (2400 – 2000) / (2400 – 2200) = 400/200
 TCPI = 2
9. Senior management wants to the percentage of the project that is complete. What should
you report?
A. 75%
B. 83%
C. 92%
D. 95%
Explanation:
percentage of the project = EV/BAC x 100
percentage of the project = 2000/2400 x 100
percentage of the project = 83%
10. Imagine if instead of 10 months and costing $2200, the project was in month three and
costing $4000. What formula might you use for BAC?
A. [(BAC – EV) / (CPI * SPI)] + AC
B. new bottom-up estimate
C. AC + new ETC
D. AC + BAC – EV
Explanation:
If you find that your estimates are wrong at the beginning of a project, it is best to develop a
new estimate to complete and then add that to your actual costs.

More Related Content

What's hot

Cost-based Query Optimization in Apache Phoenix using Apache Calcite
Cost-based Query Optimization in Apache Phoenix using Apache CalciteCost-based Query Optimization in Apache Phoenix using Apache Calcite
Cost-based Query Optimization in Apache Phoenix using Apache Calcite
Julian Hyde
 
Internals of Speeding up PySpark with Arrow
 Internals of Speeding up PySpark with Arrow Internals of Speeding up PySpark with Arrow
Internals of Speeding up PySpark with Arrow
Databricks
 
Procter & Gamble
Procter & GambleProcter & Gamble
How to Build a Product Roadmap by Walmart Senior Product Manager
How to Build a Product Roadmap by Walmart Senior Product ManagerHow to Build a Product Roadmap by Walmart Senior Product Manager
How to Build a Product Roadmap by Walmart Senior Product Manager
Product School
 
Kafka Summit SF 2017 - Kafka Connect Best Practices – Advice from the Field
Kafka Summit SF 2017 - Kafka Connect Best Practices – Advice from the FieldKafka Summit SF 2017 - Kafka Connect Best Practices – Advice from the Field
Kafka Summit SF 2017 - Kafka Connect Best Practices – Advice from the Field
confluent
 
The Startup Lifecycle (Presented by CEI and friends)
The Startup Lifecycle (Presented by CEI and friends)The Startup Lifecycle (Presented by CEI and friends)
The Startup Lifecycle (Presented by CEI and friends)
Center For Entrepreneurial Innovation
 
Intro to Product Management
Intro to Product Management Intro to Product Management
Intro to Product Management
Ria Sankar
 
Hadoop Meetup Jan 2019 - Dynamometer and a Case Study in NameNode GC
Hadoop Meetup Jan 2019 - Dynamometer and a Case Study in NameNode GCHadoop Meetup Jan 2019 - Dynamometer and a Case Study in NameNode GC
Hadoop Meetup Jan 2019 - Dynamometer and a Case Study in NameNode GC
Erik Krogen
 
敏捷开发全景视图(流程、方法和最佳实践)
敏捷开发全景视图(流程、方法和最佳实践)敏捷开发全景视图(流程、方法和最佳实践)
敏捷开发全景视图(流程、方法和最佳实践)
Weijun Zhong
 
Blue Ocean Story (BOS) Canvas for Cirque du Soleil: Rapidly Translate Great B...
Blue Ocean Story (BOS) Canvas for Cirque du Soleil: Rapidly Translate Great B...Blue Ocean Story (BOS) Canvas for Cirque du Soleil: Rapidly Translate Great B...
Blue Ocean Story (BOS) Canvas for Cirque du Soleil: Rapidly Translate Great B...
Rod King, Ph.D.
 
700 Queries Per Second with Updates: Spark As A Real-Time Web Service
700 Queries Per Second with Updates: Spark As A Real-Time Web Service700 Queries Per Second with Updates: Spark As A Real-Time Web Service
700 Queries Per Second with Updates: Spark As A Real-Time Web Service
Spark Summit
 
From Pandas to Koalas: Reducing Time-To-Insight for Virgin Hyperloop's Data
From Pandas to Koalas: Reducing Time-To-Insight for Virgin Hyperloop's DataFrom Pandas to Koalas: Reducing Time-To-Insight for Virgin Hyperloop's Data
From Pandas to Koalas: Reducing Time-To-Insight for Virgin Hyperloop's Data
Databricks
 
Consistency in UX Design
Consistency in UX DesignConsistency in UX Design
Consistency in UX Design
Remy Rey De Barros
 
Optimizing Performance in Rust for Low-Latency Database Drivers
Optimizing Performance in Rust for Low-Latency Database DriversOptimizing Performance in Rust for Low-Latency Database Drivers
Optimizing Performance in Rust for Low-Latency Database Drivers
ScyllaDB
 
Oracle SQLcl: Formatting your Query Results
Oracle SQLcl: Formatting your Query ResultsOracle SQLcl: Formatting your Query Results
Oracle SQLcl: Formatting your Query Results
Jeff Smith
 
Agile Product Development Playbook - Popular Tools and Techniques
Agile Product Development Playbook - Popular Tools and TechniquesAgile Product Development Playbook - Popular Tools and Techniques
Agile Product Development Playbook - Popular Tools and Techniques
Andy Birds
 
Kafka Summit NYC 2017 - Data Processing at LinkedIn with Apache Kafka
Kafka Summit NYC 2017 - Data Processing at LinkedIn with Apache KafkaKafka Summit NYC 2017 - Data Processing at LinkedIn with Apache Kafka
Kafka Summit NYC 2017 - Data Processing at LinkedIn with Apache Kafka
confluent
 
Educators guide jan 2014
Educators guide jan 2014Educators guide jan 2014
Educators guide jan 2014
Stanford University
 
Digital Impact: From Systems of Record to Systems of Engagement
Digital Impact: From Systems of Record to Systems of EngagementDigital Impact: From Systems of Record to Systems of Engagement
Digital Impact: From Systems of Record to Systems of Engagement
Geoffrey Moore
 
From AWS Data Pipeline to Airflow - managing data pipelines in Nielsen Market...
From AWS Data Pipeline to Airflow - managing data pipelines in Nielsen Market...From AWS Data Pipeline to Airflow - managing data pipelines in Nielsen Market...
From AWS Data Pipeline to Airflow - managing data pipelines in Nielsen Market...
Itai Yaffe
 

What's hot (20)

Cost-based Query Optimization in Apache Phoenix using Apache Calcite
Cost-based Query Optimization in Apache Phoenix using Apache CalciteCost-based Query Optimization in Apache Phoenix using Apache Calcite
Cost-based Query Optimization in Apache Phoenix using Apache Calcite
 
Internals of Speeding up PySpark with Arrow
 Internals of Speeding up PySpark with Arrow Internals of Speeding up PySpark with Arrow
Internals of Speeding up PySpark with Arrow
 
Procter & Gamble
Procter & GambleProcter & Gamble
Procter & Gamble
 
How to Build a Product Roadmap by Walmart Senior Product Manager
How to Build a Product Roadmap by Walmart Senior Product ManagerHow to Build a Product Roadmap by Walmart Senior Product Manager
How to Build a Product Roadmap by Walmart Senior Product Manager
 
Kafka Summit SF 2017 - Kafka Connect Best Practices – Advice from the Field
Kafka Summit SF 2017 - Kafka Connect Best Practices – Advice from the FieldKafka Summit SF 2017 - Kafka Connect Best Practices – Advice from the Field
Kafka Summit SF 2017 - Kafka Connect Best Practices – Advice from the Field
 
The Startup Lifecycle (Presented by CEI and friends)
The Startup Lifecycle (Presented by CEI and friends)The Startup Lifecycle (Presented by CEI and friends)
The Startup Lifecycle (Presented by CEI and friends)
 
Intro to Product Management
Intro to Product Management Intro to Product Management
Intro to Product Management
 
Hadoop Meetup Jan 2019 - Dynamometer and a Case Study in NameNode GC
Hadoop Meetup Jan 2019 - Dynamometer and a Case Study in NameNode GCHadoop Meetup Jan 2019 - Dynamometer and a Case Study in NameNode GC
Hadoop Meetup Jan 2019 - Dynamometer and a Case Study in NameNode GC
 
敏捷开发全景视图(流程、方法和最佳实践)
敏捷开发全景视图(流程、方法和最佳实践)敏捷开发全景视图(流程、方法和最佳实践)
敏捷开发全景视图(流程、方法和最佳实践)
 
Blue Ocean Story (BOS) Canvas for Cirque du Soleil: Rapidly Translate Great B...
Blue Ocean Story (BOS) Canvas for Cirque du Soleil: Rapidly Translate Great B...Blue Ocean Story (BOS) Canvas for Cirque du Soleil: Rapidly Translate Great B...
Blue Ocean Story (BOS) Canvas for Cirque du Soleil: Rapidly Translate Great B...
 
700 Queries Per Second with Updates: Spark As A Real-Time Web Service
700 Queries Per Second with Updates: Spark As A Real-Time Web Service700 Queries Per Second with Updates: Spark As A Real-Time Web Service
700 Queries Per Second with Updates: Spark As A Real-Time Web Service
 
From Pandas to Koalas: Reducing Time-To-Insight for Virgin Hyperloop's Data
From Pandas to Koalas: Reducing Time-To-Insight for Virgin Hyperloop's DataFrom Pandas to Koalas: Reducing Time-To-Insight for Virgin Hyperloop's Data
From Pandas to Koalas: Reducing Time-To-Insight for Virgin Hyperloop's Data
 
Consistency in UX Design
Consistency in UX DesignConsistency in UX Design
Consistency in UX Design
 
Optimizing Performance in Rust for Low-Latency Database Drivers
Optimizing Performance in Rust for Low-Latency Database DriversOptimizing Performance in Rust for Low-Latency Database Drivers
Optimizing Performance in Rust for Low-Latency Database Drivers
 
Oracle SQLcl: Formatting your Query Results
Oracle SQLcl: Formatting your Query ResultsOracle SQLcl: Formatting your Query Results
Oracle SQLcl: Formatting your Query Results
 
Agile Product Development Playbook - Popular Tools and Techniques
Agile Product Development Playbook - Popular Tools and TechniquesAgile Product Development Playbook - Popular Tools and Techniques
Agile Product Development Playbook - Popular Tools and Techniques
 
Kafka Summit NYC 2017 - Data Processing at LinkedIn with Apache Kafka
Kafka Summit NYC 2017 - Data Processing at LinkedIn with Apache KafkaKafka Summit NYC 2017 - Data Processing at LinkedIn with Apache Kafka
Kafka Summit NYC 2017 - Data Processing at LinkedIn with Apache Kafka
 
Educators guide jan 2014
Educators guide jan 2014Educators guide jan 2014
Educators guide jan 2014
 
Digital Impact: From Systems of Record to Systems of Engagement
Digital Impact: From Systems of Record to Systems of EngagementDigital Impact: From Systems of Record to Systems of Engagement
Digital Impact: From Systems of Record to Systems of Engagement
 
From AWS Data Pipeline to Airflow - managing data pipelines in Nielsen Market...
From AWS Data Pipeline to Airflow - managing data pipelines in Nielsen Market...From AWS Data Pipeline to Airflow - managing data pipelines in Nielsen Market...
From AWS Data Pipeline to Airflow - managing data pipelines in Nielsen Market...
 

Similar to Quiz 2-mspm iii1 03-398192-009

Earned Value Management Project Analysis
Earned Value Management Project Analysis Earned Value Management Project Analysis
Earned Value Management Project Analysis
Roger H. Mandel
 
Mark blum ubc tool box execution - powerpoint presentation
Mark blum   ubc tool box execution - powerpoint presentationMark blum   ubc tool box execution - powerpoint presentation
Mark blum ubc tool box execution - powerpoint presentation
CDN_Irony
 
Session 10 4th edition PMP
Session   10 4th edition PMPSession   10 4th edition PMP
Session 10 4th edition PMP
محمد عصمت عبد الرازق
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docx
sagarlesley
 
Earned Value Management - Project Controls - Schedule Only.pptx
Earned Value Management - Project Controls - Schedule Only.pptxEarned Value Management - Project Controls - Schedule Only.pptx
Earned Value Management - Project Controls - Schedule Only.pptx
ssuser5fc1e7
 
07 pmp cost management exam
07 pmp cost management exam07 pmp cost management exam
07 pmp cost management exam
Jamil Faraj , PMP
 
1. A key objective of change control in configuration management i.docx
1. A key objective of change control in configuration management i.docx1. A key objective of change control in configuration management i.docx
1. A key objective of change control in configuration management i.docx
dorishigh
 
Pmp cost chapter 7
Pmp cost chapter 7Pmp cost chapter 7
Pmp cost chapter 7
Ahmed Elshaboury,PMP,LEED GA
 
Network diagram problems
Network diagram problemsNetwork diagram problems
Network diagram problems
Subhra Mishra
 
ACCT 212 entire course new
ACCT 212  entire course newACCT 212  entire course new
ACCT 212 entire course new
olivergeorg
 
75985278 sample-questions-of-capital-budgeting
75985278 sample-questions-of-capital-budgeting75985278 sample-questions-of-capital-budgeting
75985278 sample-questions-of-capital-budgeting
varsha nihanth lade
 
1440 pmp exam question bank
1440 pmp exam question bank1440 pmp exam question bank
1440 pmp exam question bank
Baskar El
 
Killexam
KillexamKillexam
Killexam
Tomas Vileikis
 
Killexam
KillexamKillexam
Killexam
Tomas Vileikis
 
FIN 610 Midterm ExamInstructions Write your name on your exam.docx
FIN 610 Midterm ExamInstructions Write your name on your exam.docxFIN 610 Midterm ExamInstructions Write your name on your exam.docx
FIN 610 Midterm ExamInstructions Write your name on your exam.docx
RAJU852744
 
UNIT-2.pptx
UNIT-2.pptxUNIT-2.pptx
UNIT-2.pptx
Raja Manyam
 
1.1. Provide the definitions for resource loading and resource.docx
1.1. Provide the definitions for resource loading and resource.docx1.1. Provide the definitions for resource loading and resource.docx
1.1. Provide the definitions for resource loading and resource.docx
jackiewalcutt
 
Devry proj 586 final exam set 2 new
Devry proj 586 final exam set 2 newDevry proj 586 final exam set 2 new
Devry proj 586 final exam set 2 new
uopassignment
 
Pppl evms training_02
Pppl evms training_02Pppl evms training_02
Pppl evms training_02
apocalypto1
 
Devry proj 586 final exam set 3 new
Devry proj 586 final exam set 3 newDevry proj 586 final exam set 3 new
Devry proj 586 final exam set 3 new
uopassignment
 

Similar to Quiz 2-mspm iii1 03-398192-009 (20)

Earned Value Management Project Analysis
Earned Value Management Project Analysis Earned Value Management Project Analysis
Earned Value Management Project Analysis
 
Mark blum ubc tool box execution - powerpoint presentation
Mark blum   ubc tool box execution - powerpoint presentationMark blum   ubc tool box execution - powerpoint presentation
Mark blum ubc tool box execution - powerpoint presentation
 
Session 10 4th edition PMP
Session   10 4th edition PMPSession   10 4th edition PMP
Session 10 4th edition PMP
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docx
 
Earned Value Management - Project Controls - Schedule Only.pptx
Earned Value Management - Project Controls - Schedule Only.pptxEarned Value Management - Project Controls - Schedule Only.pptx
Earned Value Management - Project Controls - Schedule Only.pptx
 
07 pmp cost management exam
07 pmp cost management exam07 pmp cost management exam
07 pmp cost management exam
 
1. A key objective of change control in configuration management i.docx
1. A key objective of change control in configuration management i.docx1. A key objective of change control in configuration management i.docx
1. A key objective of change control in configuration management i.docx
 
Pmp cost chapter 7
Pmp cost chapter 7Pmp cost chapter 7
Pmp cost chapter 7
 
Network diagram problems
Network diagram problemsNetwork diagram problems
Network diagram problems
 
ACCT 212 entire course new
ACCT 212  entire course newACCT 212  entire course new
ACCT 212 entire course new
 
75985278 sample-questions-of-capital-budgeting
75985278 sample-questions-of-capital-budgeting75985278 sample-questions-of-capital-budgeting
75985278 sample-questions-of-capital-budgeting
 
1440 pmp exam question bank
1440 pmp exam question bank1440 pmp exam question bank
1440 pmp exam question bank
 
Killexam
KillexamKillexam
Killexam
 
Killexam
KillexamKillexam
Killexam
 
FIN 610 Midterm ExamInstructions Write your name on your exam.docx
FIN 610 Midterm ExamInstructions Write your name on your exam.docxFIN 610 Midterm ExamInstructions Write your name on your exam.docx
FIN 610 Midterm ExamInstructions Write your name on your exam.docx
 
UNIT-2.pptx
UNIT-2.pptxUNIT-2.pptx
UNIT-2.pptx
 
1.1. Provide the definitions for resource loading and resource.docx
1.1. Provide the definitions for resource loading and resource.docx1.1. Provide the definitions for resource loading and resource.docx
1.1. Provide the definitions for resource loading and resource.docx
 
Devry proj 586 final exam set 2 new
Devry proj 586 final exam set 2 newDevry proj 586 final exam set 2 new
Devry proj 586 final exam set 2 new
 
Pppl evms training_02
Pppl evms training_02Pppl evms training_02
Pppl evms training_02
 
Devry proj 586 final exam set 3 new
Devry proj 586 final exam set 3 newDevry proj 586 final exam set 3 new
Devry proj 586 final exam set 3 new
 

Recently uploaded

Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
IJECEIAES
 
Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
heavyhaig
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
MDSABBIROJJAMANPAYEL
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
IJECEIAES
 
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
ihlasbinance2003
 
Question paper of renewable energy sources
Question paper of renewable energy sourcesQuestion paper of renewable energy sources
Question paper of renewable energy sources
mahammadsalmanmech
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
kandramariana6
 
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
University of Maribor
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
SyedAbiiAzazi1
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
Victor Morales
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
gerogepatton
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
Hitesh Mohapatra
 
Wearable antenna for antenna applications
Wearable antenna for antenna applicationsWearable antenna for antenna applications
Wearable antenna for antenna applications
Madhumitha Jayaram
 
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
MIGUELANGEL966976
 
CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
rpskprasana
 
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptxML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
JamalHussainArman
 
PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
anoopmanoharan2
 
Exception Handling notes in java exception
Exception Handling notes in java exceptionException Handling notes in java exception
Exception Handling notes in java exception
Ratnakar Mikkili
 
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
awadeshbabu
 
Series of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.pptSeries of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.ppt
PauloRodrigues104553
 

Recently uploaded (20)

Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
 
Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
 
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
 
Question paper of renewable energy sources
Question paper of renewable energy sourcesQuestion paper of renewable energy sources
Question paper of renewable energy sources
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
 
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
 
Wearable antenna for antenna applications
Wearable antenna for antenna applicationsWearable antenna for antenna applications
Wearable antenna for antenna applications
 
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
 
CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
 
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptxML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
 
PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
 
Exception Handling notes in java exception
Exception Handling notes in java exceptionException Handling notes in java exception
Exception Handling notes in java exception
 
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
 
Series of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.pptSeries of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.ppt
 

Quiz 2-mspm iii1 03-398192-009

  • 1. Quiz.1 1. Which process formally authorizes the project? a. Receive project approval b. Identify Project Manager c. Develop preliminary project statement d. Develop project charter e. Develop project management plan 2. Scope management is involved in which two project management lifecycle processes: a) Initiation and planning. b) Planning, monitoring, and control. c) Planning and closured. d) Selection and planning 3. The following components are involved in scope management planning: (T/F) a) Collect scope requirements; b) Define the scope; c) Create WBS; d) Verify scope; e) Control scope Given a project with the following characteristics, answer the following questions:  You are the project manager of a project to build fancy birdhouses.  You are to build two birdhouses a month for 12 months.  Each birdhouse is planned to cost $100.  Your project is scheduled to last for 12 months.  It is the beginning of month 10.  You have built 20 birdhouses and your CPI is .9091. 4. How is the project performing? A. Over budget and ahead of schedule B. Under budget and ahead of schedule C. Over budget and behind schedule D. Under budget and behind schedule. Subject Marks Time Project M&C and Evaluation Management 10 30 (Minutes)
  • 2. Explanation: CPI is .9091, and the CPI formula = EV/AC. CPI less than 1 means that we aren’t getting the project Actual cost estimation, so it is over budget. 5. What is the actual cost of the project right now? A. $1800 B. $2000 C. $2200 D. $2400 Explanation:  CPI = EV/AC  .9091 = 2000/AC  AC(.9091) = 2000  Actual Cost = 2200 6. Assuming that the COST variance experienced so far in the project will continue, how much more money will it take to complete the project? A. $400 B. $440 C. $2800 D. $2840 Explanation:  Budget At Completion = 2 birdhouses per month x 12 months x $100 per birdhouse  BAC = $2400  Estimation To Complete = BAC/CPI – AC
  • 3.  ETC = 2400/.9091 – 2200  ETC = 440 7. If the variance experienced so far were to stop, what is the project’s estimate at completion? A. $2400 B. $2440 C. $2600 D. $2800 Explanation:  Estimate At Completion = AC + BAC – EV  EAC = 2200 + 2400 – 2000  EAC = $2600 8. What is the project’s TCPI using the project’s budget at completion? A. .5 B. 1 C. 1.5 D. 2 Explanation:  TCPI = (BAC – EV)/(BAC – AC)  TCPI = (2400 – 2000) / (2400 – 2200) = 400/200  TCPI = 2 9. Senior management wants to the percentage of the project that is complete. What should you report? A. 75% B. 83%
  • 4. C. 92% D. 95% Explanation: percentage of the project = EV/BAC x 100 percentage of the project = 2000/2400 x 100 percentage of the project = 83% 10. Imagine if instead of 10 months and costing $2200, the project was in month three and costing $4000. What formula might you use for BAC? A. [(BAC – EV) / (CPI * SPI)] + AC B. new bottom-up estimate C. AC + new ETC D. AC + BAC – EV Explanation: If you find that your estimates are wrong at the beginning of a project, it is best to develop a new estimate to complete and then add that to your actual costs.