This document discusses the differences between P6 Professional and P6 EPPM functionality in Oracle Primavera P6 version 8.2. Key functionality such as import/export files and manual resource curve editing are only available in P6 Professional. Dashboards, portfolio views, and issues tracking are only in the web-based P6 EPPM. The hosted demonstration provides examples of useful web functionality like the team member mobile app.
P6 EPPM Functionality
Not Available in P6 Pro
Don McNatty, PSP
Certified P6 Trainer/Consultant
Business Process Outsourcing
2.
Thank you forjoining today’s technical webinar
• Mute – all call in phones are automatically muted in
order to preserve the quality of the audio for all
attendees.
• Questions – during the session, questions can be
submitted through the Questions Box on the right side
of the screen . We will try to address your questions
at the end of the presentation, time permitting.
• Follow up – all registrants will receive an Excel file
listing all questions and responses along with a link to
the recorded webinar.
2
3.
Safe Harbor
• Thestatements made in this technical presentation
are based on our current knowledge of the tools.
• Our statements should not be construed to be an
official “Oracle perspective”, but are intended to be
the sharing of technical and user knowledge gained
as we explore new paths and technologies, usually in
advance of our clients.
• Our statements should not be construed as in conflict
with any Oracle statement, as the Oracle statement is
likely made based on more current knowledge than is
available to us.
3
4.
2 5 +years experience
with Primavera
Services and Products
Project Support
Oracle
Oracle Certified Oracle Certified Services –
Primavera Support
Training Implementation administrators,
Software
schedulers
Managed Hosting through MLM Project Services
Primavera Portfolios, P6(web), P6 Pro,
Hard Dollar, Acumen, Fuse, Ecosys,
Contract Management, BI Publisher,
Prism, G2
Documents, Risk
Subscription based software solutions
Primavera applications on a monthly fee
dmcnatty@drmcnatty.com
Tel. 877.367.7990 4
5.
Agenda
Overview ofP6 Functionality in
Best Application
EPPM and client (Pro) but not
Environments
Professional 8.2 in web
Hosted Most useful web Functionality in web
DEMONSTRATION only functionality but not in client
Summary of
Differences
Where to get Help? Questions
between web and
Pro
5
6.
Overview of P6EPPM and Professional 8.2
P6 EPPM 8.2 was released the end of December 2011.
With 8.2, Oracle has added some new update functionality in the web and P6 Pro
returns to a single Windows environment for both the standalone P6 Pro and the
“P6 Windows client”.
This new configuration resolves issues many schedulers have with “delegating”
update inputs.
8.2 also improves the deployment of 8.2 (web).
8.2 also supports running P6 Pro off-line
6
7.
Best Application Environments
P6 EPPM (Web) P6 Professional
• You are a casual schedule • If you use your scheduling tool
user (update periodically) every day, if you consider
• You need P6 Analytics yourself to be a “professional
• You participate, manage or scheduler” (makes a living
collaborate on projects creating, updating, reviewing
through Issues, Risks, Notes and analyzing schedules).
or Workflows. • If you manage schedules with
• You have advanced Resource more than a few hundred
Management Needs activities per project.
• You want to manage Portfolios • You need to work with
of Projects schedules off-line.
7
Functionality in client(Pro) not in web
Import/export XER, P3, MPP, XLS
Time Scaled Logic Diagrams
Line Numbering
Partial Baseline Updates
Reflection Projects
Global Changes
Manually model Resource Curves (Future Period Edits)
Internal and unlimited ability to create new reports and modify existing reports
9
10.
Functionality in webnot in client
• User setup and administration (when P6 Pro is linked)
• Project level, formula driven custom fields
• Administer Issue Codes and Forms
• Administer Resource and Role Teams
• Templates
• Full function Risk Register
• Schedule Checker
• Preview Schedule Changes
• Email links to Activity Views
• Workflows and Document Control (versioning)
• Advanced Portfolio and Resource Management
• Dashboards and Alerts
10
11.
Most useful webonly functionality
Dashboards
Portfolio views
Issues
Risk Register
Schedule Checker
Team Member
Formula Driven Custom Fields
Template Projects
Resource Overload Notification
Web (BI Publisher) Reporting
11
Summary of Differencesbetween Web & Pro
P6 EPPM (web) provides P6 Professional (client)
an environment for team provides “best in class”
collaboration, visibility to functionality that
the latest performance professional schedulers
and transparency down to expect from Primavera.
the lowest level of detail.
P6 EPPM is a great When P6 Pro is linked to a
solution for dispersed P6 EPPM (web) database
project teams that you have the best of both
supports a variety of roles worlds including the ability
from the most casual to for the schedulers to work
providing a repository for off-line when needed.
the most detailed.
16.
Where to Gethelp
Questions on Questions on Questions on this
pricing and Training and presentation
deployment Implementation
Support
Peter Smith Dan Beck, Don McNatty
+1 949 297 4057 +1 716 597 4094 dmcnatty@drmcnatty.com
17.
Upcoming Events
AACE International’s 56th
Annual Meeting
July 8-11 in San Antonio
Booth 205 & 207
18.
Questions?
Don McNatty
Principal Consultant
T. (877) 367-7990 x4053
E. dmcnatty@drmcnatty.com
W. www.drmcnatty.com
32
Editor's Notes
#14 P6 Team Member App Benefits:P6 Team Member App enables users to easily update status directly from their personal devices into the P6 database. CAPABILITIES: Get assignments, Give updates, E-mail, Approval steps, Intelligently Integrated, Native iOS app