This document contains a progress report for elevator works at the Anantara Palm Jumeirah and Tiara Residences project for the period ending January 26, 2008. It shows the planned, early, late, and actual monthly and accumulated percentages of progress. By the end of January 2008, the early progress was at 88.3% of the total plan, the late progress was at 86.03% of the plan, and the actual completed work was 8.43% of the plan. The overall progress curve indicates that installation was mostly on or ahead of schedule according to the early progress line, with some delays as shown in the late progress line.