Al Ain Water Distribution Network 
Building/Structure Planning Model 
Hydraulic 
Analysis 
Material 
tal/Approval 
TRANSCO Approval for Hydraulic Analysis 
Main Pumps Material Submittal 
Pump House Valves Material Approval 
MV Motor-Phase Shift Transformer-VFD Material 
Submittal 
Pump House Valves Material Submittal 
MV Motor-Phase Shift Transformer-VFD Material 
33 KV Switch Gear Material Submittal 
33 KV Switch Gear Material Approval 
SS=0 Dys 
Cooling Water System for 
Pump/Motors Material Submittal 
Submit 
Design G.A Drawings M 
General Arrangement Drawing of Pump House- 
Elec.Building-Transformer Approval 
General Arrangement Drawing of 33 KV 
Switch Gear Approval 
Design & Engineering for Pump House (Incl. 
Approvals) 
Design & Engineering for Electrical Building 
(Incl. Approvals) 
Design & Engineering for Transformer 
Foundation (Incl. Approvals) 
Excavation Of Pump House Excavation Of Electrical Building Excavation Of Transformers Boxs 
FS=106 Dys 
Design & Engineering for 33 KV Substation 
(Incl. Approvals) 
Excavation Of Substation Building 
SS=0 Dys 
Design & Engineering for Utility Building (Incl. 
Approvals ) 
Excavation Of Utility Building 
Design & Engineering for WQM Building 
(Incl. Approvals) 
Excavation Of WQM Building 
General Arrangement Drawing of Pump House- 
Elec.Building-Transformer Submital 
Motor Transformer Approval 
General Arrangement Drawing of 33 KV 
Switch Gear Submittal 
SS=0 Dys 
SS=0 Dys 
SS=0 Dys 
Cooling Water System for 
Pump/Motors Material Approval 
Civil Work 
Formation Level and Compaction 
Test 
Casting of Blinding and Curing 
Laying Water Proofing 
Casting Screed Over Water 
Proofing&Curing 
Reinf.Steel,Shuttering Works and 
Casting Foundation 
Formation Level and Compaction 
Test 
Casting of Blinding and Curing 
Laying Water Proofing 
Casting Screed Over Water 
Proofing&Curing 
Reinf.Steel,Shuttering Works and 
Casting Foundation 
FS=55 Days 
Formation Level and Compaction 
Test 
Casting of Blinding and Curing 
Laying Water Proofing 
Casting Screed Over Water 
Proofing&Curing 
Reinf.Steel,Shuttering Works and 
Casting Foundation 
Formation Level and Compaction 
Test 
Casting of Blinding and Curing 
Laying Water Proofing 
Casting Screed Over Water 
Proofing&Curing 
Reinf.Steel,Shuttering Works and 
Casting Foundation 
SS=150 Dys 
Formation Level and Compaction 
Test 
Casting of Blinding and Curing 
Laying Water Proofing 
Casting Screed Over Water 
Proofing&Curing 
Reinf.Steel,Shuttering Works and 
Casting Foundation 
Formation Level and Compaction 
Test 
Casting of Blinding and Curing 
Laying Water Proofing 
Casting Screed Over Water 
Proofing&Curing 
Reinf.Steel,Shuttering Works and 
Casting Foundation 
SS=90 Dys 
C 
& 
P ks 
Programme 
Reinf.Steel,Shuttering Works and 
Casting of Walls,Columns 
Reinforcement Steel, Shuttering 
and Casting for Ground Slab 
Reinforcement Steel, Shuttering 
and Casting for Columns 
Supply and Erection of Metal 
Roofing System 
Reinf.Steel,Shuttering Works and 
Casting of Walls,Columns 
Reinforcement Steel, Shuttering 
and Casting for Ground Slab 
Reinforcement Steel, Shuttering and 
Casting for Columns and Staircase 
Reinforcement Steel, Shuttering 
and Casting for Roof and Parapet 
Reinf.Steel,Shuttering Works and 
Casting of Walls, 
Reinf.Steel,Shuttering Works and 
Casting of Walls,Columns 
Reinforcement Steel, Shuttering and 
Casting for Columns and Staircase 
Reinforcement Steel, Shuttering 
and Casting for Roof and Parapet 
Reinforcement Steel, Shuttering 
and Casting for Columns and 
Staircase 
Reinforcement Steel, Shuttering 
and Casting for Roof and Parapet 
Reinforcement Steel, Shuttering 
and Casting for Columns and 
Staircase 
Reinforcement Steel, Shuttering 
and Casting for Roof and Parapet 
Arch 
MEP 
Work 
See The Overall Implementation File : AARC Planning Model Page 1 of 2 Printed on : 12/21/2009 at 6:16 PM
Hydr.-Surge Analysis 
Al Ain Water Distribution Network 
Building/Structure Planning Model 
Hydr.-Surge 
Analysis 
Material 
mital/App. 
TRANSCO Approval for Surge Vessel Analysis TRANSCO Approval for Hydraulic Analysis 
Surge Vessels Material Submittal Air Compressor Material Submittal Pump House Valves Material Submittal Pump House Pipes Material Submittal 
Design Subm 
M 
Surge Vessels Material Approval Air Compressor Material Approval 
Design & Engineering for Surge Vessel 
Foundation (Incl. Approvals) 
Design & Engineering for Air Compressor 
Shelter Foundation (Incl. Approvals) 
Design & Engineering for Valve Chambers 
(Incl. Approvals) 
Excavation Of Surge Vessel Air Compressors Foundation 
Excavation Of Transformers Boxs 
Pump House Valves Material Approval Pump House Pipes Material Approval 
Excavation Of Pump House 
SS=150 Dys 
Installation of External Pipes and Valves 
SS=30 Dys 
Air Compressors Foundation 
Civil Work 
Formation Level and Compaction 
Test 
Casting of Blinding and Curing 
Laying Water Proofing 
Casting Screed Over Water 
Proofing&Curing 
Reinf.Steel,Shuttering Works and 
Casting Foundation 
Formation Level and Compaction 
Test 
Casting of Blinding and Curing 
Laying Water Proofing 
Casting Protection Screed Over 
Water Proofing System 
Reinf Steel,Shuttering and Casting 
f B Sl b 
Arch & MEP 
Works 
of Base Slab 
Reinf Steel,Shuttering and Casting 
of Wall Shaft 
Supply and Erection of Roof Slab 
,Including Vent Pipes,Ladders,… 
See The Overall Implementation Programme 
File : AARC Planning Model Page 2 of 2 Printed on : 12/21/2009 at 6:16 PM

Building-Structure Planning Model

  • 1.
    Al Ain WaterDistribution Network Building/Structure Planning Model Hydraulic Analysis Material tal/Approval TRANSCO Approval for Hydraulic Analysis Main Pumps Material Submittal Pump House Valves Material Approval MV Motor-Phase Shift Transformer-VFD Material Submittal Pump House Valves Material Submittal MV Motor-Phase Shift Transformer-VFD Material 33 KV Switch Gear Material Submittal 33 KV Switch Gear Material Approval SS=0 Dys Cooling Water System for Pump/Motors Material Submittal Submit Design G.A Drawings M General Arrangement Drawing of Pump House- Elec.Building-Transformer Approval General Arrangement Drawing of 33 KV Switch Gear Approval Design & Engineering for Pump House (Incl. Approvals) Design & Engineering for Electrical Building (Incl. Approvals) Design & Engineering for Transformer Foundation (Incl. Approvals) Excavation Of Pump House Excavation Of Electrical Building Excavation Of Transformers Boxs FS=106 Dys Design & Engineering for 33 KV Substation (Incl. Approvals) Excavation Of Substation Building SS=0 Dys Design & Engineering for Utility Building (Incl. Approvals ) Excavation Of Utility Building Design & Engineering for WQM Building (Incl. Approvals) Excavation Of WQM Building General Arrangement Drawing of Pump House- Elec.Building-Transformer Submital Motor Transformer Approval General Arrangement Drawing of 33 KV Switch Gear Submittal SS=0 Dys SS=0 Dys SS=0 Dys Cooling Water System for Pump/Motors Material Approval Civil Work Formation Level and Compaction Test Casting of Blinding and Curing Laying Water Proofing Casting Screed Over Water Proofing&Curing Reinf.Steel,Shuttering Works and Casting Foundation Formation Level and Compaction Test Casting of Blinding and Curing Laying Water Proofing Casting Screed Over Water Proofing&Curing Reinf.Steel,Shuttering Works and Casting Foundation FS=55 Days Formation Level and Compaction Test Casting of Blinding and Curing Laying Water Proofing Casting Screed Over Water Proofing&Curing Reinf.Steel,Shuttering Works and Casting Foundation Formation Level and Compaction Test Casting of Blinding and Curing Laying Water Proofing Casting Screed Over Water Proofing&Curing Reinf.Steel,Shuttering Works and Casting Foundation SS=150 Dys Formation Level and Compaction Test Casting of Blinding and Curing Laying Water Proofing Casting Screed Over Water Proofing&Curing Reinf.Steel,Shuttering Works and Casting Foundation Formation Level and Compaction Test Casting of Blinding and Curing Laying Water Proofing Casting Screed Over Water Proofing&Curing Reinf.Steel,Shuttering Works and Casting Foundation SS=90 Dys C & P ks Programme Reinf.Steel,Shuttering Works and Casting of Walls,Columns Reinforcement Steel, Shuttering and Casting for Ground Slab Reinforcement Steel, Shuttering and Casting for Columns Supply and Erection of Metal Roofing System Reinf.Steel,Shuttering Works and Casting of Walls,Columns Reinforcement Steel, Shuttering and Casting for Ground Slab Reinforcement Steel, Shuttering and Casting for Columns and Staircase Reinforcement Steel, Shuttering and Casting for Roof and Parapet Reinf.Steel,Shuttering Works and Casting of Walls, Reinf.Steel,Shuttering Works and Casting of Walls,Columns Reinforcement Steel, Shuttering and Casting for Columns and Staircase Reinforcement Steel, Shuttering and Casting for Roof and Parapet Reinforcement Steel, Shuttering and Casting for Columns and Staircase Reinforcement Steel, Shuttering and Casting for Roof and Parapet Reinforcement Steel, Shuttering and Casting for Columns and Staircase Reinforcement Steel, Shuttering and Casting for Roof and Parapet Arch MEP Work See The Overall Implementation File : AARC Planning Model Page 1 of 2 Printed on : 12/21/2009 at 6:16 PM
  • 2.
    Hydr.-Surge Analysis AlAin Water Distribution Network Building/Structure Planning Model Hydr.-Surge Analysis Material mital/App. TRANSCO Approval for Surge Vessel Analysis TRANSCO Approval for Hydraulic Analysis Surge Vessels Material Submittal Air Compressor Material Submittal Pump House Valves Material Submittal Pump House Pipes Material Submittal Design Subm M Surge Vessels Material Approval Air Compressor Material Approval Design & Engineering for Surge Vessel Foundation (Incl. Approvals) Design & Engineering for Air Compressor Shelter Foundation (Incl. Approvals) Design & Engineering for Valve Chambers (Incl. Approvals) Excavation Of Surge Vessel Air Compressors Foundation Excavation Of Transformers Boxs Pump House Valves Material Approval Pump House Pipes Material Approval Excavation Of Pump House SS=150 Dys Installation of External Pipes and Valves SS=30 Dys Air Compressors Foundation Civil Work Formation Level and Compaction Test Casting of Blinding and Curing Laying Water Proofing Casting Screed Over Water Proofing&Curing Reinf.Steel,Shuttering Works and Casting Foundation Formation Level and Compaction Test Casting of Blinding and Curing Laying Water Proofing Casting Protection Screed Over Water Proofing System Reinf Steel,Shuttering and Casting f B Sl b Arch & MEP Works of Base Slab Reinf Steel,Shuttering and Casting of Wall Shaft Supply and Erection of Roof Slab ,Including Vent Pipes,Ladders,… See The Overall Implementation Programme File : AARC Planning Model Page 2 of 2 Printed on : 12/21/2009 at 6:16 PM