This document contains progress information for a construction project for Al Rajhi Bank. It shows: 1) The actual monthly and cumulative percentage progress achieved compared to the planned recovery progress curve and original planned progress curve. The actual progress achieved to date is 60.85% while the recovery planned progress to date is 37.96%. 2) Tables with the monthly planned percentage, actual percentage earned, and cumulative percentages for both the earned and planned progress based on the original and recovery baselines. 3) A chart showing the overall progress S-curve with lines for the actual cumulative percentage completed, recovery planned progress, and original planned progress.