SlideShare a Scribd company logo
1 of 35
OPTIMIZATION OF AN AUTONOMOUS
VEHICLE DISPATCH SYSTEM IN AN
UNDERGROUND MINE
OBJECTIVES
 Develop a simulation to accurately simulate the
movement and other activities of autonomous
vehicles in an underground mine.
 Determine evaluation criteria to optimize the
dispatch strategies
 Develop and implement dispatch strategies with the
evaluation criteria in mind
 Evaluate the improvement (if any) obtained by
implementing the dispatch strategies, as compared
to the baseline strategy
INTRODUCTION
 The project deals with the optimization of
autonomous vehicle dispatch system for a block
cave mine.
DRAW
POINT TRANSFER
POINT
CRUSHER
DSPATCH SYSTEM
LITERATURE REVIEW:
NEED FOR AUTOMATION IN UNDERGROUND MINE
 Conventional mining method for dispatching rely on
intuition of supervisor.
 Hazardous environment of underground mines and
increase death rates
 Mismanagement due to improper supervision
 With autonomous vehicles an operator can be in a
control room safely above ground, and production
efficiency could increase
NEED FOR OPTIMIZATION OF AUTONOMOUS
VEHICLE
 Draw point hang-ups
 Vehicle breakdowns.
 Trucks shutdowns
 Frequent crusher shutdowns
 Mismanagement in workings.
 Pressure of increased productivity
MINING AUTOMATION
 Type of mining automation: computer-aided
mining (CAM) and telerobotic mining (TRM).
 Communication network connecting all the parts
of the automated system for real-time monitoring
and control
 Information and data acquisition system (local
sensors on vehicles, central database etc.).
 Computerized database with open access for
mine planning, control and maintenance systems.
VEHICLE DISPATCH SYSTEM IN MINING
 Objective is to control a certain number of vehicles
to complete tasks.
 AGVs follow fixed routes
 Active area in a mine is constantly shifting
 Communication with satellite is inhibited
 Sensors could be the possible solution..
METHODOLOGY-OPTIMIZATION OF
AUTONOMOUS VEHICLE
Parameter consider for formation of strategy:-
 Controllable parameter
 Vehicles speed
 Direction of movement
 Number of vehicle in the system
 Fixed parameter
 Maximum acceleration
 Maximum speed
 Fuel consumption
 Capacity of crusher
 Capacity of vehicle
METHODOLOGY-OPTIMIZATION OF
AUTONOMOUS VEHICLE
 Optimization of autonomous vehicles can be done
in two ways:-
 Collision avoidance strategies
 Strategies for dispatch system
COLLISION AVOIDANCE STRATEGIES
STRATEGICALY PARAMETERS FOR LHD
DISPATCHING
STRATEGICAL PARAMETERS FOR TRUCK
DISPATCHING
SIMULATION MODEL
 The goal of the simulation is to model the real-life
system of vehicles in an underground mine as close
as possible.
 Active area in mine will shift with time.
 In a real-life system however, a lot of unpredictable
factors play a role,but these factors are very hard,
and sometimes impossible, to model accurately.
 Thus stress is laid to develop the simplest model
that is adequate to determine the desired outcome.
ASSUMPTIONS
 The active area that is simulated consists of 7 tunnels with 15
drawpoints on both sides of each tunnel
 Secondary blasting, in a specific tunnel, is done when 55% or
more of the drawpoints in that tunnel are inactive due to
hangups, or drawpoint has been inactive for more than 3
days.
 During secondary blasting the tunnel is closed for production
until all the drawpoints are active again. There is also a
waiting period, of about 60 minutes, after blasting before
production vehicles can re-enter the specific tunnel
 The crusher is switched off if it stays empty for more than 12
minutes
 Limit on the amount of ore that can be drawn daily is 200mm
of solid rock per day.
LHD PARAMETER
PARAMETER MINIMUM TYPICAL MAXIMUM
Bucket load 9 ton
fuel tank 450 ltrs
Load delay 0.5 minutes 0.6 minutes 0.75 minutes
Off-load time 0.25 min 0.33 min 0.45 min
Acceleration empty 0.4m/s^2
Acceleration full 0.35m/s^2
Deceleration -1m/s^2
Max speed rim
Tunnel
15km/h
Max speed
extraction tunnel
16km/h
Max speed of drawpoint tunnel 4km/h
Turn speed 4km/h
Max speed limit in
transfer area
16km/h
Refuel time 13 min
Service interval 125 hours
Service duration 240 min 360 min 600 min
MTBF 40 h 45 h 60 h
MTTR 1.5h 2h 2.5h
FUEL CONSUMPTION 40l/h 45l/h 50l/h
TRUCK PARAMETER
PARAMETER MINIMUM TYPICAL MAXIMUM
Speed limit 25km/h
Intersection speed
Limit
5km/h
Safety zone 10 meter
Off-load time 38 sec
Acceleration empty 0.49m/s^2
Acceleration full 0.35m/s^2
Deceleration -1m/s^2
Bucket size 45 ton
Fuel tank 700 ltr
Refuel time 13 min
Fuel consumption 70l/h 80l/h 90l/h
Service interval 125 hours
Service duration 240 min 360 min 600 min
MTBF 40 h 45 h 60 h
MTTR 1.5h 2h 2.5h
CRUSHER PARAMETERS
PARAMETER MININMUM TYPICAL MAXIMUM
capacity 140 ton
Minimum level 30 ton
Crush rate 800 t/h
Simulation environment: the tunnel outlines can be seen and the circles
represent draw points. The circle at the bottom represents the crusher, and the
loop at the bottom is the tunnel connecting the transfer points with the crusher
(this is not drawn according to scale).
DETAILS OF MINE LAYOUT
Figure represent detailed representation of the simulated LHD
environment, including dimension
Figure represent detailed representation of the simulated truck
environment, including dimensions.
STRATEGIES FOR DISPATHING
 All the strategy is run for the equivalent of one week of production i.e 5
days, with 3 shifts of 8 hours each per day.
 Zero state indicates an even ore level, with no ore loaded from any draw
point, and an empty crusher level.
 The main objective of the different dispatching strategies is therefore to
maximize the total tons produced.
 Another important objective specific to a block cave mine, is to keep the
ore level above the drawpoints as even as possible.
 last objective of the simulated dispatching strategies is to minimize the
number of crusher shutdowns.
STRATEGY 1
 The first strategy is based on current dispatching strategies and will
be used to compare other strategies.
 Each LHD is assigned to a specific tunnel and has only one LHD
assigned to it.
 The LHD sequentially visits each active drawpoint in its assigned
tunnel. After each visit to a drawpoint the LHD visits a transfer point
one closest to the tunnel that the LHD is assigned to.
 If an LHD has to be serviced, repaired or refuelled or tunnel
becomes inactive because of hangups ,it moves to the service area.
 The trucks move in clockwise direction around the loop connecting
the transfer points and the crusher.If a truck is empty it moves to the
nearest transfer point where no other truck is present.
The figure gives a simple representation of the sequence in which the drawpoints are visited by an LHD.
The figure only shows 3 drawpoints on each side of the tunnel. The number of drawpoints used in the
simulation is 15 on each side of a tunnel. The arrows only indicate the sequence, and not the physical
movement of the LHD. Between successive drawpoints the LHD visits a transfer point to unload.
The figure shows the direction of movement of the trucks around the loop connecting the transfer points and the
crusher. The path actually indicates the movement of a truck that receives it load from transfer point 1 and then
unloads in the crusher. The crusher is indicated with a ‘C’ and each transfer point is indicated with a ‘T’.
STRATEGY 2
 This strategy is same as strategy 1. Each LHD is still assigned
to a specific tunnel. However, the sequence in which the
drawpoints are visited is reversed for every other tunnel thus
keeping ore level even.
 The movement of the trucks correspond exactly to that found
in strategy 1.
The figure shows the drawpoint visiting sequence of three LHDs assigned to three adjacent tunnels. This is
according to strategy 2. The figure again only shows a reduced number of drawpoints
STRATEGY 3
 This strategy has same objective as strategy 2. The LHDs are still assigned to
specific tunnels, but the sequence in which the drawpoints are visited is not
fixed.
 A cost function is used to determine the next drawpoint that an LHD visits
after it has unloaded.
 The drawpoint that gives the smallest value for the cost function is assigned
as the LHD’s new destination.
 The cost function contains the following two terms:-
 The cost function then looks as follows:
Jk=T1+T2,1+T2,2+T2,3+T2,4
With k =1,2,..., # drawpts _ in _ tunnel.Each drawpoint has four adjacent
drawpoints and therefore term 2 is included four times in the cost function.
STRATEGY 4
 This strategy focuses on the dispatching of the trucks.
The LHD movements correspond to that found in
strategy 1.
 Aim of this strategy is to space the arrivals of the trucks
at the crusher to minimize the crusher shutdowns.
 Truck can only move to another transfer point, one
ahead in the crusher loop if it is not occupied. If more
than one transfer point satisfy this condition then truck
will move to the closest one.
 The decision to move to another transfer point, or not, is
made when a truck has just received a load from an
LHD.
 If a truck is at the last transfer point in the crusher loop,
and not yet full, then it must stay at that transfer point
until it is full.
STRATEGY 5
 Strategy 5 is basically the same as strategy 3 but in this
case each LHD is not assigned to a specific tunnel.
Truck movements correspond to that found in strategy 1.
 The cost function is computed for all the active
drawpoints in all the available tunnels. The drawpoint
resulting in the lowest value for the cost function is
chosen as the new destination of the LHD.
 An available tunnel is one in which no LHD is present,
and no LHD is already on its way to. It is also not closed
for secondary breaking.
 This strategy will obviously place a lot of strain on the
collision avoidance algorithms
 Transfer point are assigned to the specific tunnels.
COMBINATION
 Some of the strategies focus on the LHD
dispatching (strategy 1 to 3, and 5), and one
focuses on the truck dispatching (strategy 4).
 It makes sense to combine these strategies to
determine if a more optimal solution can be found
for the overall system. Strategy 4 is effectively a
combination of strategy 1 and 4.
 The combinations that remain are: strategy 2 + 4,
strategy 3 + 4,4+5.thus these are also tested to
compute the result.
CRUSHER RESULT:
Optimal number of trucks for strategy 4:-
DRAWPOINT RESULT:
CONCLUSION
 strategy 2 performed the best in terms of total tons produced,
and strategy 5 the worst.
 Strategy 2 also produced one of the lowest number of crusher
shutdowns.
 Strategy 4 and their combinations produced low values for the
total tons dumped in the crusher, but produced the least
number of crusher shutdowns.
 Optimal number of trucks are 4.
 Strategy 3 being the best in keeping the ore level even and
also achieving high level of production value.
 Strategy 5 have lowest drawpoint deviation but it cannot be
compared with other strategies as it production level is less.
FUTURE SCOPE
 Various assumptions were used to develop the
simulation model , therefore possible future work
exists in terms of refining the simulation to reflect a
true system even more accurately.
 Develop a model, which explicitly describes the
processes in a mine in terms of money.the
strategies will then be refined to maximize the
profit.
 Improve on the proposed strategies, and to
investigate the physical implementation of these
strategies more thoroughly.
REFERENCES
 www.smenet.org
 www.Google.com
 UNIVERSITY OF PRETORIA (p.sayamann)
 PUKKILA, J. and SÄRKKÄ, P. Intelligent mine technology
program and its implementation.
 YAVIN, Y. Modelling the motion of an underground mining
vehicle.
 Venetia mine of de beers group in Botswana,South Africa.
 Camisani-Calzolari F.R. (2004), “Modelling of an autonomous
underground mine vehicle

More Related Content

Similar to Optimization of an autonomous vehicle dispatch system in an underground mine

Lecture 04 Capacity for TWSC (Traffic Engineering هندسة المرور & Dr. Usama Sh...
Lecture 04 Capacity for TWSC (Traffic Engineering هندسة المرور & Dr. Usama Sh...Lecture 04 Capacity for TWSC (Traffic Engineering هندسة المرور & Dr. Usama Sh...
Lecture 04 Capacity for TWSC (Traffic Engineering هندسة المرور & Dr. Usama Sh...Hossam Shafiq I
 
Dispatching taxi cabs with passenger pool
Dispatching taxi cabs with passenger poolDispatching taxi cabs with passenger pool
Dispatching taxi cabs with passenger poolBogusz Jelinski
 
A feasible solution algorithm for a primitive vehicle routing problem
A feasible solution algorithm for a primitive vehicle routing problemA feasible solution algorithm for a primitive vehicle routing problem
A feasible solution algorithm for a primitive vehicle routing problemCem Recai Çırak
 
Highway traffic optimization by variable speed limits
Highway traffic optimization by variable speed limitsHighway traffic optimization by variable speed limits
Highway traffic optimization by variable speed limitsJoseph Chow
 
REVIEW OF OPTIMAL SPEED MODEL
REVIEW OF OPTIMAL SPEED MODELREVIEW OF OPTIMAL SPEED MODEL
REVIEW OF OPTIMAL SPEED MODELGyambar Adamu
 
Updated-Traffic Simulation of Construction zone for Baranagar -.pptx
Updated-Traffic Simulation of Construction zone for Baranagar -.pptxUpdated-Traffic Simulation of Construction zone for Baranagar -.pptx
Updated-Traffic Simulation of Construction zone for Baranagar -.pptxJitendraWadhwani7
 
MDM-Chapter-9-Updated latest.pptx
MDM-Chapter-9-Updated latest.pptxMDM-Chapter-9-Updated latest.pptx
MDM-Chapter-9-Updated latest.pptxJimSotio
 
COORDINATION OF ACTUATED SIGNALS FOR A CORRIDOR
COORDINATION OF ACTUATED SIGNALS FOR A CORRIDORCOORDINATION OF ACTUATED SIGNALS FOR A CORRIDOR
COORDINATION OF ACTUATED SIGNALS FOR A CORRIDORRakesh Venkateswaran
 
Traffic enginering highway capacity and los presentation
Traffic enginering highway capacity and los presentationTraffic enginering highway capacity and los presentation
Traffic enginering highway capacity and los presentationDanilign Mekonnen
 
Future of Traffic Management and ITS
Future of Traffic Management and ITSFuture of Traffic Management and ITS
Future of Traffic Management and ITSSerge Hoogendoorn
 
Methods of route assignment
Methods of route assignmentMethods of route assignment
Methods of route assignmentKathan Sindhvad
 
Rail yard container terminal
Rail yard container terminalRail yard container terminal
Rail yard container terminalKapilLamba6
 
When and where are bus express services justified?
When and where are bus express services justified?When and where are bus express services justified?
When and where are bus express services justified?BRTCoE
 
Airport Capacity and the case of a new London Airport
Airport Capacity and the case of a new London AirportAirport Capacity and the case of a new London Airport
Airport Capacity and the case of a new London AirportAndreas Mavrodis
 

Similar to Optimization of an autonomous vehicle dispatch system in an underground mine (20)

robotaxi2023.pdf
robotaxi2023.pdfrobotaxi2023.pdf
robotaxi2023.pdf
 
Lecture 04 Capacity for TWSC (Traffic Engineering هندسة المرور & Dr. Usama Sh...
Lecture 04 Capacity for TWSC (Traffic Engineering هندسة المرور & Dr. Usama Sh...Lecture 04 Capacity for TWSC (Traffic Engineering هندسة المرور & Dr. Usama Sh...
Lecture 04 Capacity for TWSC (Traffic Engineering هندسة المرور & Dr. Usama Sh...
 
Dispatching taxi cabs with passenger pool
Dispatching taxi cabs with passenger poolDispatching taxi cabs with passenger pool
Dispatching taxi cabs with passenger pool
 
A feasible solution algorithm for a primitive vehicle routing problem
A feasible solution algorithm for a primitive vehicle routing problemA feasible solution algorithm for a primitive vehicle routing problem
A feasible solution algorithm for a primitive vehicle routing problem
 
Highway traffic optimization by variable speed limits
Highway traffic optimization by variable speed limitsHighway traffic optimization by variable speed limits
Highway traffic optimization by variable speed limits
 
REVIEW OF OPTIMAL SPEED MODEL
REVIEW OF OPTIMAL SPEED MODELREVIEW OF OPTIMAL SPEED MODEL
REVIEW OF OPTIMAL SPEED MODEL
 
Updated-Traffic Simulation of Construction zone for Baranagar -.pptx
Updated-Traffic Simulation of Construction zone for Baranagar -.pptxUpdated-Traffic Simulation of Construction zone for Baranagar -.pptx
Updated-Traffic Simulation of Construction zone for Baranagar -.pptx
 
Shivendra singh
Shivendra singhShivendra singh
Shivendra singh
 
RIOH / RWS workshop
RIOH / RWS workshopRIOH / RWS workshop
RIOH / RWS workshop
 
MDM-Chapter-9-Updated latest.pptx
MDM-Chapter-9-Updated latest.pptxMDM-Chapter-9-Updated latest.pptx
MDM-Chapter-9-Updated latest.pptx
 
COORDINATION OF ACTUATED SIGNALS FOR A CORRIDOR
COORDINATION OF ACTUATED SIGNALS FOR A CORRIDORCOORDINATION OF ACTUATED SIGNALS FOR A CORRIDOR
COORDINATION OF ACTUATED SIGNALS FOR A CORRIDOR
 
Traffic enginering highway capacity and los presentation
Traffic enginering highway capacity and los presentationTraffic enginering highway capacity and los presentation
Traffic enginering highway capacity and los presentation
 
LOCO TRAINING REPORT
LOCO TRAINING REPORTLOCO TRAINING REPORT
LOCO TRAINING REPORT
 
Future of Traffic Management and ITS
Future of Traffic Management and ITSFuture of Traffic Management and ITS
Future of Traffic Management and ITS
 
himanshu (1)
himanshu (1)himanshu (1)
himanshu (1)
 
Methods of route assignment
Methods of route assignmentMethods of route assignment
Methods of route assignment
 
Urban streets
Urban streetsUrban streets
Urban streets
 
Rail yard container terminal
Rail yard container terminalRail yard container terminal
Rail yard container terminal
 
When and where are bus express services justified?
When and where are bus express services justified?When and where are bus express services justified?
When and where are bus express services justified?
 
Airport Capacity and the case of a new London Airport
Airport Capacity and the case of a new London AirportAirport Capacity and the case of a new London Airport
Airport Capacity and the case of a new London Airport
 

More from Safdar Ali

Safety in mines
Safety in minesSafety in mines
Safety in minesSafdar Ali
 
Explosives and accesories
Explosives and accesoriesExplosives and accesories
Explosives and accesoriesSafdar Ali
 
Role of management information systems in a mine.
Role of management information systems in a mine.Role of management information systems in a mine.
Role of management information systems in a mine.Safdar Ali
 
Pre requisites of marine operations
Pre requisites of marine operationsPre requisites of marine operations
Pre requisites of marine operationsSafdar Ali
 
Nuclear devices for mining
Nuclear devices for miningNuclear devices for mining
Nuclear devices for miningSafdar Ali
 
Mining of manganese nodules from sea floor
Mining of manganese nodules from sea floorMining of manganese nodules from sea floor
Mining of manganese nodules from sea floorSafdar Ali
 
Mine water risk in open pit slope stability
Mine water risk in open pit slope stabilityMine water risk in open pit slope stability
Mine water risk in open pit slope stabilitySafdar Ali
 
Innovations and trend in metal mining & tunnellng
Innovations and trend in metal mining & tunnellngInnovations and trend in metal mining & tunnellng
Innovations and trend in metal mining & tunnellngSafdar Ali
 
Lighting terminlologyand their units
Lighting terminlologyand their unitsLighting terminlologyand their units
Lighting terminlologyand their unitsSafdar Ali
 
Evaluation of slope stability for waste rock dumps in a mine
Evaluation of slope stability for waste rock dumps in a mineEvaluation of slope stability for waste rock dumps in a mine
Evaluation of slope stability for waste rock dumps in a mineSafdar Ali
 
Final grouting freezing
Final grouting freezingFinal grouting freezing
Final grouting freezingSafdar Ali
 
Digitization and 3d modelling of a mine plan
Digitization and 3d modelling of a mine planDigitization and 3d modelling of a mine plan
Digitization and 3d modelling of a mine planSafdar Ali
 
Variety of mine plans and sections & second schedule
Variety of mine plans and sections & second scheduleVariety of mine plans and sections & second schedule
Variety of mine plans and sections & second scheduleSafdar Ali
 
Statutory provisions for the preaparation of mine plans and sections
Statutory provisions for the preaparation of mine plans and sectionsStatutory provisions for the preaparation of mine plans and sections
Statutory provisions for the preaparation of mine plans and sectionsSafdar Ali
 
Gps & its applications in opencast mine surveying
Gps & its applications in opencast mine surveyingGps & its applications in opencast mine surveying
Gps & its applications in opencast mine surveyingSafdar Ali
 
Laser and its mining applications
Laser and its mining applicationsLaser and its mining applications
Laser and its mining applicationsSafdar Ali
 
Gyrotheodolite
GyrotheodoliteGyrotheodolite
GyrotheodoliteSafdar Ali
 

More from Safdar Ali (20)

Safety in mines
Safety in minesSafety in mines
Safety in mines
 
Tunneling
TunnelingTunneling
Tunneling
 
Explosives and accesories
Explosives and accesoriesExplosives and accesories
Explosives and accesories
 
Role of management information systems in a mine.
Role of management information systems in a mine.Role of management information systems in a mine.
Role of management information systems in a mine.
 
Basting
BastingBasting
Basting
 
Pre requisites of marine operations
Pre requisites of marine operationsPre requisites of marine operations
Pre requisites of marine operations
 
Nuclear devices for mining
Nuclear devices for miningNuclear devices for mining
Nuclear devices for mining
 
Mining of manganese nodules from sea floor
Mining of manganese nodules from sea floorMining of manganese nodules from sea floor
Mining of manganese nodules from sea floor
 
Mine water risk in open pit slope stability
Mine water risk in open pit slope stabilityMine water risk in open pit slope stability
Mine water risk in open pit slope stability
 
Innovations and trend in metal mining & tunnellng
Innovations and trend in metal mining & tunnellngInnovations and trend in metal mining & tunnellng
Innovations and trend in metal mining & tunnellng
 
Lighting terminlologyand their units
Lighting terminlologyand their unitsLighting terminlologyand their units
Lighting terminlologyand their units
 
Evaluation of slope stability for waste rock dumps in a mine
Evaluation of slope stability for waste rock dumps in a mineEvaluation of slope stability for waste rock dumps in a mine
Evaluation of slope stability for waste rock dumps in a mine
 
Final grouting freezing
Final grouting freezingFinal grouting freezing
Final grouting freezing
 
Digitization and 3d modelling of a mine plan
Digitization and 3d modelling of a mine planDigitization and 3d modelling of a mine plan
Digitization and 3d modelling of a mine plan
 
Variety of mine plans and sections & second schedule
Variety of mine plans and sections & second scheduleVariety of mine plans and sections & second schedule
Variety of mine plans and sections & second schedule
 
Statutory provisions for the preaparation of mine plans and sections
Statutory provisions for the preaparation of mine plans and sectionsStatutory provisions for the preaparation of mine plans and sections
Statutory provisions for the preaparation of mine plans and sections
 
Gps & its applications in opencast mine surveying
Gps & its applications in opencast mine surveyingGps & its applications in opencast mine surveying
Gps & its applications in opencast mine surveying
 
Laser and its mining applications
Laser and its mining applicationsLaser and its mining applications
Laser and its mining applications
 
Gyrotheodolite
GyrotheodoliteGyrotheodolite
Gyrotheodolite
 
Gps2
Gps2Gps2
Gps2
 

Recently uploaded

21st_Century_Skills_Framework_Final_Presentation_2.pptx
21st_Century_Skills_Framework_Final_Presentation_2.pptx21st_Century_Skills_Framework_Final_Presentation_2.pptx
21st_Century_Skills_Framework_Final_Presentation_2.pptxJoelynRubio1
 
Ernest Hemingway's For Whom the Bell Tolls
Ernest Hemingway's For Whom the Bell TollsErnest Hemingway's For Whom the Bell Tolls
Ernest Hemingway's For Whom the Bell TollsPallavi Parmar
 
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptxHMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptxmarlenawright1
 
Understanding Accommodations and Modifications
Understanding  Accommodations and ModificationsUnderstanding  Accommodations and Modifications
Understanding Accommodations and ModificationsMJDuyan
 
Spellings Wk 4 and Wk 5 for Grade 4 at CAPS
Spellings Wk 4 and Wk 5 for Grade 4 at CAPSSpellings Wk 4 and Wk 5 for Grade 4 at CAPS
Spellings Wk 4 and Wk 5 for Grade 4 at CAPSAnaAcapella
 
UGC NET Paper 1 Unit 7 DATA INTERPRETATION.pdf
UGC NET Paper 1 Unit 7 DATA INTERPRETATION.pdfUGC NET Paper 1 Unit 7 DATA INTERPRETATION.pdf
UGC NET Paper 1 Unit 7 DATA INTERPRETATION.pdfNirmal Dwivedi
 
How to Add New Custom Addons Path in Odoo 17
How to Add New Custom Addons Path in Odoo 17How to Add New Custom Addons Path in Odoo 17
How to Add New Custom Addons Path in Odoo 17Celine George
 
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdf
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdfUnit 3 Emotional Intelligence and Spiritual Intelligence.pdf
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdfDr Vijay Vishwakarma
 
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptxHMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptxEsquimalt MFRC
 
How to Manage Call for Tendor in Odoo 17
How to Manage Call for Tendor in Odoo 17How to Manage Call for Tendor in Odoo 17
How to Manage Call for Tendor in Odoo 17Celine George
 
Michaelis Menten Equation and Estimation Of Vmax and Tmax.pptx
Michaelis Menten Equation and Estimation Of Vmax and Tmax.pptxMichaelis Menten Equation and Estimation Of Vmax and Tmax.pptx
Michaelis Menten Equation and Estimation Of Vmax and Tmax.pptxRugvedSathawane
 
diagnosting testing bsc 2nd sem.pptx....
diagnosting testing bsc 2nd sem.pptx....diagnosting testing bsc 2nd sem.pptx....
diagnosting testing bsc 2nd sem.pptx....Ritu480198
 
dusjagr & nano talk on open tools for agriculture research and learning
dusjagr & nano talk on open tools for agriculture research and learningdusjagr & nano talk on open tools for agriculture research and learning
dusjagr & nano talk on open tools for agriculture research and learningMarc Dusseiller Dusjagr
 
Observing-Correct-Grammar-in-Making-Definitions.pptx
Observing-Correct-Grammar-in-Making-Definitions.pptxObserving-Correct-Grammar-in-Making-Definitions.pptx
Observing-Correct-Grammar-in-Making-Definitions.pptxAdelaideRefugio
 
SPLICE Working Group: Reusable Code Examples
SPLICE Working Group:Reusable Code ExamplesSPLICE Working Group:Reusable Code Examples
SPLICE Working Group: Reusable Code ExamplesPeter Brusilovsky
 
How to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptxHow to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptxCeline George
 
Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...
Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...
Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...EADTU
 
Towards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptxTowards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptxJisc
 
QUATER-1-PE-HEALTH-LC2- this is just a sample of unpacked lesson
QUATER-1-PE-HEALTH-LC2- this is just a sample of unpacked lessonQUATER-1-PE-HEALTH-LC2- this is just a sample of unpacked lesson
QUATER-1-PE-HEALTH-LC2- this is just a sample of unpacked lessonhttgc7rh9c
 
How to Add a Tool Tip to a Field in Odoo 17
How to Add a Tool Tip to a Field in Odoo 17How to Add a Tool Tip to a Field in Odoo 17
How to Add a Tool Tip to a Field in Odoo 17Celine George
 

Recently uploaded (20)

21st_Century_Skills_Framework_Final_Presentation_2.pptx
21st_Century_Skills_Framework_Final_Presentation_2.pptx21st_Century_Skills_Framework_Final_Presentation_2.pptx
21st_Century_Skills_Framework_Final_Presentation_2.pptx
 
Ernest Hemingway's For Whom the Bell Tolls
Ernest Hemingway's For Whom the Bell TollsErnest Hemingway's For Whom the Bell Tolls
Ernest Hemingway's For Whom the Bell Tolls
 
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptxHMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
 
Understanding Accommodations and Modifications
Understanding  Accommodations and ModificationsUnderstanding  Accommodations and Modifications
Understanding Accommodations and Modifications
 
Spellings Wk 4 and Wk 5 for Grade 4 at CAPS
Spellings Wk 4 and Wk 5 for Grade 4 at CAPSSpellings Wk 4 and Wk 5 for Grade 4 at CAPS
Spellings Wk 4 and Wk 5 for Grade 4 at CAPS
 
UGC NET Paper 1 Unit 7 DATA INTERPRETATION.pdf
UGC NET Paper 1 Unit 7 DATA INTERPRETATION.pdfUGC NET Paper 1 Unit 7 DATA INTERPRETATION.pdf
UGC NET Paper 1 Unit 7 DATA INTERPRETATION.pdf
 
How to Add New Custom Addons Path in Odoo 17
How to Add New Custom Addons Path in Odoo 17How to Add New Custom Addons Path in Odoo 17
How to Add New Custom Addons Path in Odoo 17
 
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdf
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdfUnit 3 Emotional Intelligence and Spiritual Intelligence.pdf
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdf
 
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptxHMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
 
How to Manage Call for Tendor in Odoo 17
How to Manage Call for Tendor in Odoo 17How to Manage Call for Tendor in Odoo 17
How to Manage Call for Tendor in Odoo 17
 
Michaelis Menten Equation and Estimation Of Vmax and Tmax.pptx
Michaelis Menten Equation and Estimation Of Vmax and Tmax.pptxMichaelis Menten Equation and Estimation Of Vmax and Tmax.pptx
Michaelis Menten Equation and Estimation Of Vmax and Tmax.pptx
 
diagnosting testing bsc 2nd sem.pptx....
diagnosting testing bsc 2nd sem.pptx....diagnosting testing bsc 2nd sem.pptx....
diagnosting testing bsc 2nd sem.pptx....
 
dusjagr & nano talk on open tools for agriculture research and learning
dusjagr & nano talk on open tools for agriculture research and learningdusjagr & nano talk on open tools for agriculture research and learning
dusjagr & nano talk on open tools for agriculture research and learning
 
Observing-Correct-Grammar-in-Making-Definitions.pptx
Observing-Correct-Grammar-in-Making-Definitions.pptxObserving-Correct-Grammar-in-Making-Definitions.pptx
Observing-Correct-Grammar-in-Making-Definitions.pptx
 
SPLICE Working Group: Reusable Code Examples
SPLICE Working Group:Reusable Code ExamplesSPLICE Working Group:Reusable Code Examples
SPLICE Working Group: Reusable Code Examples
 
How to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptxHow to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptx
 
Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...
Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...
Transparency, Recognition and the role of eSealing - Ildiko Mazar and Koen No...
 
Towards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptxTowards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptx
 
QUATER-1-PE-HEALTH-LC2- this is just a sample of unpacked lesson
QUATER-1-PE-HEALTH-LC2- this is just a sample of unpacked lessonQUATER-1-PE-HEALTH-LC2- this is just a sample of unpacked lesson
QUATER-1-PE-HEALTH-LC2- this is just a sample of unpacked lesson
 
How to Add a Tool Tip to a Field in Odoo 17
How to Add a Tool Tip to a Field in Odoo 17How to Add a Tool Tip to a Field in Odoo 17
How to Add a Tool Tip to a Field in Odoo 17
 

Optimization of an autonomous vehicle dispatch system in an underground mine

  • 1.
  • 2. OPTIMIZATION OF AN AUTONOMOUS VEHICLE DISPATCH SYSTEM IN AN UNDERGROUND MINE
  • 3. OBJECTIVES  Develop a simulation to accurately simulate the movement and other activities of autonomous vehicles in an underground mine.  Determine evaluation criteria to optimize the dispatch strategies  Develop and implement dispatch strategies with the evaluation criteria in mind  Evaluate the improvement (if any) obtained by implementing the dispatch strategies, as compared to the baseline strategy
  • 4. INTRODUCTION  The project deals with the optimization of autonomous vehicle dispatch system for a block cave mine. DRAW POINT TRANSFER POINT CRUSHER DSPATCH SYSTEM
  • 5. LITERATURE REVIEW: NEED FOR AUTOMATION IN UNDERGROUND MINE  Conventional mining method for dispatching rely on intuition of supervisor.  Hazardous environment of underground mines and increase death rates  Mismanagement due to improper supervision  With autonomous vehicles an operator can be in a control room safely above ground, and production efficiency could increase
  • 6. NEED FOR OPTIMIZATION OF AUTONOMOUS VEHICLE  Draw point hang-ups  Vehicle breakdowns.  Trucks shutdowns  Frequent crusher shutdowns  Mismanagement in workings.  Pressure of increased productivity
  • 7. MINING AUTOMATION  Type of mining automation: computer-aided mining (CAM) and telerobotic mining (TRM).  Communication network connecting all the parts of the automated system for real-time monitoring and control  Information and data acquisition system (local sensors on vehicles, central database etc.).  Computerized database with open access for mine planning, control and maintenance systems.
  • 8. VEHICLE DISPATCH SYSTEM IN MINING  Objective is to control a certain number of vehicles to complete tasks.  AGVs follow fixed routes  Active area in a mine is constantly shifting  Communication with satellite is inhibited  Sensors could be the possible solution..
  • 9. METHODOLOGY-OPTIMIZATION OF AUTONOMOUS VEHICLE Parameter consider for formation of strategy:-  Controllable parameter  Vehicles speed  Direction of movement  Number of vehicle in the system  Fixed parameter  Maximum acceleration  Maximum speed  Fuel consumption  Capacity of crusher  Capacity of vehicle
  • 10. METHODOLOGY-OPTIMIZATION OF AUTONOMOUS VEHICLE  Optimization of autonomous vehicles can be done in two ways:-  Collision avoidance strategies  Strategies for dispatch system
  • 12. STRATEGICALY PARAMETERS FOR LHD DISPATCHING
  • 13. STRATEGICAL PARAMETERS FOR TRUCK DISPATCHING
  • 14. SIMULATION MODEL  The goal of the simulation is to model the real-life system of vehicles in an underground mine as close as possible.  Active area in mine will shift with time.  In a real-life system however, a lot of unpredictable factors play a role,but these factors are very hard, and sometimes impossible, to model accurately.  Thus stress is laid to develop the simplest model that is adequate to determine the desired outcome.
  • 15. ASSUMPTIONS  The active area that is simulated consists of 7 tunnels with 15 drawpoints on both sides of each tunnel  Secondary blasting, in a specific tunnel, is done when 55% or more of the drawpoints in that tunnel are inactive due to hangups, or drawpoint has been inactive for more than 3 days.  During secondary blasting the tunnel is closed for production until all the drawpoints are active again. There is also a waiting period, of about 60 minutes, after blasting before production vehicles can re-enter the specific tunnel  The crusher is switched off if it stays empty for more than 12 minutes  Limit on the amount of ore that can be drawn daily is 200mm of solid rock per day.
  • 16. LHD PARAMETER PARAMETER MINIMUM TYPICAL MAXIMUM Bucket load 9 ton fuel tank 450 ltrs Load delay 0.5 minutes 0.6 minutes 0.75 minutes Off-load time 0.25 min 0.33 min 0.45 min Acceleration empty 0.4m/s^2 Acceleration full 0.35m/s^2 Deceleration -1m/s^2 Max speed rim Tunnel 15km/h Max speed extraction tunnel 16km/h Max speed of drawpoint tunnel 4km/h Turn speed 4km/h Max speed limit in transfer area 16km/h Refuel time 13 min Service interval 125 hours Service duration 240 min 360 min 600 min MTBF 40 h 45 h 60 h MTTR 1.5h 2h 2.5h FUEL CONSUMPTION 40l/h 45l/h 50l/h
  • 17. TRUCK PARAMETER PARAMETER MINIMUM TYPICAL MAXIMUM Speed limit 25km/h Intersection speed Limit 5km/h Safety zone 10 meter Off-load time 38 sec Acceleration empty 0.49m/s^2 Acceleration full 0.35m/s^2 Deceleration -1m/s^2 Bucket size 45 ton Fuel tank 700 ltr Refuel time 13 min Fuel consumption 70l/h 80l/h 90l/h Service interval 125 hours Service duration 240 min 360 min 600 min MTBF 40 h 45 h 60 h MTTR 1.5h 2h 2.5h
  • 18. CRUSHER PARAMETERS PARAMETER MININMUM TYPICAL MAXIMUM capacity 140 ton Minimum level 30 ton Crush rate 800 t/h
  • 19. Simulation environment: the tunnel outlines can be seen and the circles represent draw points. The circle at the bottom represents the crusher, and the loop at the bottom is the tunnel connecting the transfer points with the crusher (this is not drawn according to scale).
  • 20. DETAILS OF MINE LAYOUT Figure represent detailed representation of the simulated LHD environment, including dimension
  • 21. Figure represent detailed representation of the simulated truck environment, including dimensions.
  • 22. STRATEGIES FOR DISPATHING  All the strategy is run for the equivalent of one week of production i.e 5 days, with 3 shifts of 8 hours each per day.  Zero state indicates an even ore level, with no ore loaded from any draw point, and an empty crusher level.  The main objective of the different dispatching strategies is therefore to maximize the total tons produced.  Another important objective specific to a block cave mine, is to keep the ore level above the drawpoints as even as possible.  last objective of the simulated dispatching strategies is to minimize the number of crusher shutdowns.
  • 23. STRATEGY 1  The first strategy is based on current dispatching strategies and will be used to compare other strategies.  Each LHD is assigned to a specific tunnel and has only one LHD assigned to it.  The LHD sequentially visits each active drawpoint in its assigned tunnel. After each visit to a drawpoint the LHD visits a transfer point one closest to the tunnel that the LHD is assigned to.  If an LHD has to be serviced, repaired or refuelled or tunnel becomes inactive because of hangups ,it moves to the service area.  The trucks move in clockwise direction around the loop connecting the transfer points and the crusher.If a truck is empty it moves to the nearest transfer point where no other truck is present.
  • 24. The figure gives a simple representation of the sequence in which the drawpoints are visited by an LHD. The figure only shows 3 drawpoints on each side of the tunnel. The number of drawpoints used in the simulation is 15 on each side of a tunnel. The arrows only indicate the sequence, and not the physical movement of the LHD. Between successive drawpoints the LHD visits a transfer point to unload. The figure shows the direction of movement of the trucks around the loop connecting the transfer points and the crusher. The path actually indicates the movement of a truck that receives it load from transfer point 1 and then unloads in the crusher. The crusher is indicated with a ‘C’ and each transfer point is indicated with a ‘T’.
  • 25. STRATEGY 2  This strategy is same as strategy 1. Each LHD is still assigned to a specific tunnel. However, the sequence in which the drawpoints are visited is reversed for every other tunnel thus keeping ore level even.  The movement of the trucks correspond exactly to that found in strategy 1. The figure shows the drawpoint visiting sequence of three LHDs assigned to three adjacent tunnels. This is according to strategy 2. The figure again only shows a reduced number of drawpoints
  • 26. STRATEGY 3  This strategy has same objective as strategy 2. The LHDs are still assigned to specific tunnels, but the sequence in which the drawpoints are visited is not fixed.  A cost function is used to determine the next drawpoint that an LHD visits after it has unloaded.  The drawpoint that gives the smallest value for the cost function is assigned as the LHD’s new destination.  The cost function contains the following two terms:-  The cost function then looks as follows: Jk=T1+T2,1+T2,2+T2,3+T2,4 With k =1,2,..., # drawpts _ in _ tunnel.Each drawpoint has four adjacent drawpoints and therefore term 2 is included four times in the cost function.
  • 27. STRATEGY 4  This strategy focuses on the dispatching of the trucks. The LHD movements correspond to that found in strategy 1.  Aim of this strategy is to space the arrivals of the trucks at the crusher to minimize the crusher shutdowns.  Truck can only move to another transfer point, one ahead in the crusher loop if it is not occupied. If more than one transfer point satisfy this condition then truck will move to the closest one.  The decision to move to another transfer point, or not, is made when a truck has just received a load from an LHD.  If a truck is at the last transfer point in the crusher loop, and not yet full, then it must stay at that transfer point until it is full.
  • 28. STRATEGY 5  Strategy 5 is basically the same as strategy 3 but in this case each LHD is not assigned to a specific tunnel. Truck movements correspond to that found in strategy 1.  The cost function is computed for all the active drawpoints in all the available tunnels. The drawpoint resulting in the lowest value for the cost function is chosen as the new destination of the LHD.  An available tunnel is one in which no LHD is present, and no LHD is already on its way to. It is also not closed for secondary breaking.  This strategy will obviously place a lot of strain on the collision avoidance algorithms  Transfer point are assigned to the specific tunnels.
  • 29. COMBINATION  Some of the strategies focus on the LHD dispatching (strategy 1 to 3, and 5), and one focuses on the truck dispatching (strategy 4).  It makes sense to combine these strategies to determine if a more optimal solution can be found for the overall system. Strategy 4 is effectively a combination of strategy 1 and 4.  The combinations that remain are: strategy 2 + 4, strategy 3 + 4,4+5.thus these are also tested to compute the result.
  • 31. Optimal number of trucks for strategy 4:-
  • 33. CONCLUSION  strategy 2 performed the best in terms of total tons produced, and strategy 5 the worst.  Strategy 2 also produced one of the lowest number of crusher shutdowns.  Strategy 4 and their combinations produced low values for the total tons dumped in the crusher, but produced the least number of crusher shutdowns.  Optimal number of trucks are 4.  Strategy 3 being the best in keeping the ore level even and also achieving high level of production value.  Strategy 5 have lowest drawpoint deviation but it cannot be compared with other strategies as it production level is less.
  • 34. FUTURE SCOPE  Various assumptions were used to develop the simulation model , therefore possible future work exists in terms of refining the simulation to reflect a true system even more accurately.  Develop a model, which explicitly describes the processes in a mine in terms of money.the strategies will then be refined to maximize the profit.  Improve on the proposed strategies, and to investigate the physical implementation of these strategies more thoroughly.
  • 35. REFERENCES  www.smenet.org  www.Google.com  UNIVERSITY OF PRETORIA (p.sayamann)  PUKKILA, J. and SÄRKKÄ, P. Intelligent mine technology program and its implementation.  YAVIN, Y. Modelling the motion of an underground mining vehicle.  Venetia mine of de beers group in Botswana,South Africa.  Camisani-Calzolari F.R. (2004), “Modelling of an autonomous underground mine vehicle