This document discusses how open-ended activities can impact project completion dates when activity durations change. It provides two examples: 1) When activity B's duration increased from 30 to 50 days, and it was linked to predecessor and successor activities with finish-to-start and finish-to-start/start-to-start relationships, the project completion date was delayed by 20 days. 2) When activity B had start-to-start relationships with all successor activities, its increased duration from 30 to 50 days did not impact the project completion date, as long as activity B finished on or before the original project end date. This type of activity is called an "open-ended activity." Identification of open-ended