SlideShare a Scribd company logo
CONSTRUCTION OF TRANSMISSION LINES WORKS 35Kv-400 kV
Contractor:
Client
INSTALLATION PROCEDURE OF OPGW
Document Number -
00 12/02/2018 Approval A.Dogani F.Koranqe&Isa.Kurti E. Barhani F.Doko
REV DATE ISSUED FOR ISSUED BY CHECKED BY QA/QC TD CPM
Engineer
□ □ □
DATE BY APPROVED REJECTED NA COMMENTS
Present document is property of the ow ner ArberQamil Dogani and it is prohibited any copy and/or convey of its original copy w ith any means,
before the w ritten confirmation and approvalof the Company's legal representative.
2 | o f 1 8
REVISION TRACKING PAGE
Revision
Number
Revised
Page
Revision Date Description of Revision Prepared by
000 all 12/02/2018 Prepared and Published Arber Dogani
Rev No. 0 1 2 3 4 5 6 7 8 9
Date
12.02.201
8
3 | o f 1 8
4 | o f 1 8
1. - PURPOSE
Describe the system used for installation and delivery of OPGW fibre optic cables.
2. - SCOPE
This document covers all the activities usually performed by Company for on-site installation of
OPGW fibre optic cables, including transport, installation, accessory assembly, verification of
optical transmission characteristics and final certification.
3. - REFERENCES
 Quality Assurance Manual
4. - GENERAL
In general, the system and the equipment used for installation of the OPGW Cable with
optical fibre are similar to those used for installation of the standard ground wire cable.
Nevertheless, since there is an optical fiber core, special care should be taken to avoid any
damage to the fibers by observing the minimum bending radius at all times. Therefore,
specific components and machinery are used for the OPGW cable: pullers, tensioners, ant
twisting
counterweights, swivels, pulling grips, pulley-blocks,
self-gripping
clamps, pulling
ropes, pulling cables, etc.
5. – PROCEDURES
5.1. – Survey of the line
Prior planning for installation of the OPGW cable is performed by monitoring the line, taking
into account the following parameters:
5.1.1. – Length of each drum
The OPGW drum lengths are determined based on the following considerations: position of
the tension towers, tower access, distance between supports and crossing with other lines,
roads, railways, routes, services and other obstacles.
5.1.2.- Splices
The position of the splices depends on the maximum available length of OPGW, on the
position of the towers and the tower access.
5 | o f 1 8
6 | o f 1 8
7 | o f 1 8
It is compulsory to perform the calibration of the dynamometer, at least once a year. The
Company supervisor could demand the Certificate of Calibration. This certificate will be
emitted by an independent official laboratory.
8 | o f 1 8
9 | o f 1 8
10 | o f 1 8
11 | o f 1 8
12 | o f 1 8
13 | o f 1 8
As a rule, one drum at a time of OPGW cable is installed. In case of any difficulties, contact
manufacturer. We will give the correct guidelines to proceed with the OPGW cable
installation.
Ensure that the metal part of the pulleys do not make contact with the cable to prevent it from
14 | o f 1 8
being damaged.
5.4.1.2 Stringing speed
recommends an installation speed about 60 m/min, depending always on the
environmental conditions and the topology of the overhead line. The supervisors (or the
technical responsible) for the in spallation will take care that all recommendations are
fully applied during the installation process.
5.4.1.3 Pulling tension
The recommended pulling tension shall be lower than 1.5 times the weight (kg) of 1 km OPGW
cable length.
In case that higher pulling tensions are required (i.e. live installations,), further information
should be asked to CLIENT supervisor or Manufacture. in order to know the maximum
permissible pulling tension for such particular installation.
5.4.1.4 Minimum bending radius
The minimum bending radius are as follows:
- on tensioner reels 40 times the cable diameter
- during installation 400 mm
- after installation 20 times the cable diameter
5.4.1.5 Communications during stringing
The personnel located at the puller, the tensioner, the pulley crossings and the cable ends are
in communication at all times by communication system.
5.5 Sagging of the cable
Generally, the methods used to obtain the correct sag values of the OPGW cables are the same
used for conventional ground wire cables. The specific recommendations are as follows:
Pulling is performed by a preformed fitting or tension clamp (in intermediate spans) or with the
15 | o f 1 8
pull jacket at the end. Special attention must be taken on using appropriate clamps adapted to
the OPGW cable diameter.
Sagging of the cable and fittings installation are always performed after stringing. At this time,
the attachment fittings are also installed to prevent damage to the OPGW cable.
The installer is responsible for any damage to the OPGW cable that may occur due to failure
cause by incorrect application of the previous points.
If the tension and sags are different from the expected values, the stringing or sagging should
be halted. The supervisor and the project leader will be consulted in order to safely
continue the installation operations.
5.6 Installation of fittings and accessories
The fittings: tension clamps, suspensions, earthling clamps, dampers, etc. should be installed in
accordance with the manufacturer’s instructions and using the appropriate tools. Special
attention must be taken on using appropriate clamps adapted to the OPGW cable diameter.
From the top of the tower, OPGW falls down, it is necessary to introduce a cable loop of three
spires of 1 m diameter in the top of the tower and each 20 m from the top. Finally, the cable
must
be conducted till the joint box place.
5.7 Personnel training
All personnel who participate in the installation of the OPGW cable should be informed of
handling problems and installation procedures for the OPGW cable.
It is responsibility of the installer to assure the correct instruction to the whole personnel
involved in the installation works.
5.8 Supervision
Over requisition, Manufactures offers the service of a supervisor that will be responsible for
ensuring compliance with all of the points indicated in this document as well as all required
standards applicable to the specific installation.
The supervisor r will communicate to Manufactures for ,any non-conformity detected in the
cable or cable installation procedures.
If a situation occurs that is not covered in the present installation procedure, whenever this
occurs with an OPGW cable, the Supervisor will determine whether or not the action is
correct.
16 | o f 1 8
The supervisor will request the installer to provide a descriptive list of the components to be
used for installation. Moreover, he will verify that these components are sufficient and
adequate.
To place the supervision on record, the supervisor will register all of the items
indicated in point 5 of this document in Q-09 -F-PA-004 format.
5.9 - Splices
After stringing and the optical measurements taken to verify it meets the customer’s
requirements, the OPGW cable will be spliced
The joint boxes used should have a device for fixing properly the center element (multitude
configuration) or the aramid yarns (nanotube configuration). recommend to use
the Manufacture joint boxes specially designed for the correct jointing of OPGW cables (Q-
09PE-PA-004
“Installation of EWJ and EWMJ splice boxes”)
5.10 – Transmission test during the installation phases
Prior to as well as during the installation phases, the transmission characteristics of the fibre
optic cables are verified in order to ensure proper installation and be sure that the final tests
are within the specified range of tolerances.
5.10.1 – Measurements before OPGW cable installation
Prior to OPGW cable installation, each optical fibres is verified using OTDR.
The attenuation values recorded are registered in during installation phase” and saved on
an electronic diskette. This computer register is kept by DOKO.
5.10.2 - Measurements after installation
After the cable has been installed, and prior to the splices, each of the cable fibres is
verified once again using OTDR. These new values are compared with those obtained in
5.11.1. in order to ensure the absence of any problems.
The attenuation values recorded are registered saved on an electronic diskette. This
computer register is kept by. The measurements are suitable identified and
referenced.
5.10.3 – Splices measurement
After splicing, each joint is optically verified using OTDR in order to ensure that the
attenuation values are within the required values.
17 | o f 1 8
The attenuation values recorded are registered and on electronic format. This computer
register is kept by DOKO.
5.11 – Final acceptance test
After installation, a final measurement of the transmission characteristics is and the values
are duly recorded. A copy of this is submitted to the customer. These measurements are also
recorded and kept by Company.
5.12 – Safety and hygiene
The supervisor designated by is responsible for compliance with the general
safety and hygiene standards for manufacture cables or the requirements stipulated by
contract, if any.
5.13 – Environment
5.13.1 – Withdrawal of special waste (toxic and dangerous)
If any type of special waste such as oil, grease, solvents, saturation of gloves or rags, etc.
are produced during cable installation, proceed as follows:
 Place in heavy-duty carboys or steel drums, indicating what type of waste it is.
 If installation is performed in the Community of Montenegro, contact the IIC Quality and
Environment Department. This department will furnish the data for the administrator in
charge of such waste. Another option is to contact the Waste Committee of the
Company directly (tel. +355689095223).
 If the installation is located outside of the Community, contact the Town
Council or Community in this location so that such bodies can provide information on the
administrators authorized to treat this waste.
 Such waste must not be abandoned, mixed with other waste, or sent to the dumping
ground.
5.13.2 – Withdrawal of non-special or inert waste
 If there are excess materials or waste such as aluminium, optic fibre, plastic, wood, iron,
etc., whenever possible, this should be sent to an authorized recycler or a controlled
dumping ground.
 Regardless of the amount, the waste should never be abandoned. Moreover, the area
should be cleaned when the work is finished.
6. – APPLICABLE FORMATS
18 | o f 1 8
7.- APPLICABLEPROCEDURES
Code Document
_______________________INSTALLATION OF EWJ and EWMJ SPLICE BOXES
8.- MODIFICATIONSTO THE PREVIOUS REVISION
Point 5.6: down lead cable in the jointing towers
Point 5.9.: fixing the center element (multitude configuration) or the aramid yarns (monotone
configuration)

More Related Content

What's hot

transmission line installation
transmission line installationtransmission line installation
transmission line installation
Maria Romina Angustia
 
transmission line
transmission line transmission line
transmission line
singh1515
 
Power Line Carrier Communication PLCC
Power Line Carrier Communication PLCCPower Line Carrier Communication PLCC
Power Line Carrier Communication PLCC
Power System Operation
 
Equipments of power transmission
Equipments of power transmissionEquipments of power transmission
Equipments of power transmission
Rasika Ghongade
 
Basics Of Electrical Wires & Cables - Residential & Commercial Projects
Basics Of  Electrical  Wires & Cables  - Residential & Commercial Projects Basics Of  Electrical  Wires & Cables  - Residential & Commercial Projects
Basics Of Electrical Wires & Cables - Residential & Commercial Projects
SSudhaVelan
 
main content
main contentmain content
main contentRaj Kumar
 
Underground cables
Underground cablesUnderground cables
Underground cables
Jatinder Singh
 
Underground cables
Underground cablesUnderground cables
Underground cables
Poonam Sarawgi
 
High voltage underground cables
High voltage underground cablesHigh voltage underground cables
Design and construction of underground cable transmission line
Design and construction of underground cable transmission lineDesign and construction of underground cable transmission line
Design and construction of underground cable transmission line
Fazlur Rahman
 
What is Optical fiber ?
What is Optical fiber ?What is Optical fiber ?
What is Optical fiber ?
Likan Patra
 
Cable Course.pptx
Cable Course.pptxCable Course.pptx
Cable Course.pptx
ssuserbb4da6
 
UNIT - 02 SERVICE MAIN
UNIT - 02 SERVICE MAINUNIT - 02 SERVICE MAIN
UNIT - 02 SERVICE MAIN
PremanandDesai
 
Extra High Voltage Underground Power Cable
Extra High Voltage Underground Power CableExtra High Voltage Underground Power Cable
Extra High Voltage Underground Power CableLeonardo ENERGY
 
Microwave Links Correct Installation at Telecom Site
Microwave Links Correct Installation at Telecom SiteMicrowave Links Correct Installation at Telecom Site
Microwave Links Correct Installation at Telecom Site
ibrahimnabil17
 
Nexans Euromold Connectors 400 Series Interface C Symmetrical Cable Connector...
Nexans Euromold Connectors 400 Series Interface C Symmetrical Cable Connector...Nexans Euromold Connectors 400 Series Interface C Symmetrical Cable Connector...
Nexans Euromold Connectors 400 Series Interface C Symmetrical Cable Connector...
Thorne & Derrick International
 
AC Distribution System - Generation Distribution and Transmission
AC Distribution System - Generation Distribution and TransmissionAC Distribution System - Generation Distribution and Transmission
AC Distribution System - Generation Distribution and Transmission
Gowtham Cr
 

What's hot (20)

transmission line installation
transmission line installationtransmission line installation
transmission line installation
 
Ofc ppt
Ofc pptOfc ppt
Ofc ppt
 
transmission line
transmission line transmission line
transmission line
 
Power Line Carrier Communication PLCC
Power Line Carrier Communication PLCCPower Line Carrier Communication PLCC
Power Line Carrier Communication PLCC
 
Equipments of power transmission
Equipments of power transmissionEquipments of power transmission
Equipments of power transmission
 
Basics Of Electrical Wires & Cables - Residential & Commercial Projects
Basics Of  Electrical  Wires & Cables  - Residential & Commercial Projects Basics Of  Electrical  Wires & Cables  - Residential & Commercial Projects
Basics Of Electrical Wires & Cables - Residential & Commercial Projects
 
main content
main contentmain content
main content
 
Underground cables
Underground cablesUnderground cables
Underground cables
 
Underground cables
Underground cablesUnderground cables
Underground cables
 
High voltage underground cables
High voltage underground cablesHigh voltage underground cables
High voltage underground cables
 
Design and construction of underground cable transmission line
Design and construction of underground cable transmission lineDesign and construction of underground cable transmission line
Design and construction of underground cable transmission line
 
What is Optical fiber ?
What is Optical fiber ?What is Optical fiber ?
What is Optical fiber ?
 
Cable Course.pptx
Cable Course.pptxCable Course.pptx
Cable Course.pptx
 
UNIT - 02 SERVICE MAIN
UNIT - 02 SERVICE MAINUNIT - 02 SERVICE MAIN
UNIT - 02 SERVICE MAIN
 
Extra High Voltage Underground Power Cable
Extra High Voltage Underground Power CableExtra High Voltage Underground Power Cable
Extra High Voltage Underground Power Cable
 
Microwave Links Correct Installation at Telecom Site
Microwave Links Correct Installation at Telecom SiteMicrowave Links Correct Installation at Telecom Site
Microwave Links Correct Installation at Telecom Site
 
Singapore Power
Singapore PowerSingapore Power
Singapore Power
 
Nexans Euromold Connectors 400 Series Interface C Symmetrical Cable Connector...
Nexans Euromold Connectors 400 Series Interface C Symmetrical Cable Connector...Nexans Euromold Connectors 400 Series Interface C Symmetrical Cable Connector...
Nexans Euromold Connectors 400 Series Interface C Symmetrical Cable Connector...
 
al59
al59al59
al59
 
AC Distribution System - Generation Distribution and Transmission
AC Distribution System - Generation Distribution and TransmissionAC Distribution System - Generation Distribution and Transmission
AC Distribution System - Generation Distribution and Transmission
 

Similar to Ohl transmission lines opgw instalation procedure for fiber optic cables rev.00

61131730 transmission-line-case-study
61131730 transmission-line-case-study61131730 transmission-line-case-study
61131730 transmission-line-case-study
homeworkping4
 
PROFINET network qualification Peter Thomas - oct 2015
PROFINET network qualification   Peter Thomas - oct 2015PROFINET network qualification   Peter Thomas - oct 2015
PROFINET network qualification Peter Thomas - oct 2015
PROFIBUS and PROFINET InternationaI - PI UK
 
Profinet network qualification - Peter Thomas
Profinet network qualification - Peter ThomasProfinet network qualification - Peter Thomas
Profinet network qualification - Peter Thomas
PROFIBUS and PROFINET InternationaI - PI UK
 
ASSET 11 FOUL NETWORK Jan '15 REV B
ASSET 11 FOUL NETWORK Jan '15 REV BASSET 11 FOUL NETWORK Jan '15 REV B
ASSET 11 FOUL NETWORK Jan '15 REV BNoel Carroll
 
VD4+12+44kA+Manual+1VDU09004-YN.pdf
VD4+12+44kA+Manual+1VDU09004-YN.pdfVD4+12+44kA+Manual+1VDU09004-YN.pdf
VD4+12+44kA+Manual+1VDU09004-YN.pdf
SajidAhmed676573
 
202029263 electra-560
202029263 electra-560202029263 electra-560
202029263 electra-560
zaga76
 
Wire rope inspection service
Wire rope inspection serviceWire rope inspection service
Wire rope inspection service
Infrastructure Preservation Corporation
 
194 adss cable-installationguide
194 adss cable-installationguide194 adss cable-installationguide
194 adss cable-installationguide
bui thequan
 
Motorway Communications - Series 1500 - Highway Works Specification
Motorway Communications - Series 1500 - Highway Works SpecificationMotorway Communications - Series 1500 - Highway Works Specification
Motorway Communications - Series 1500 - Highway Works Specification
Thorne & Derrick International
 
BR08 Proposed Section B - B
BR08 Proposed Section B - BBR08 Proposed Section B - B
BR08 Proposed Section B - Bsarah ralphs
 
Catalog biến tần Inovance MD500
Catalog biến tần Inovance MD500Catalog biến tần Inovance MD500
Catalog biến tần Inovance MD500
CTY TNHH HẠO PHƯƠNG
 
Pfisterer Electrical Safety Equipment - Voltage Detectors, Phase Comparators,...
Pfisterer Electrical Safety Equipment - Voltage Detectors, Phase Comparators,...Pfisterer Electrical Safety Equipment - Voltage Detectors, Phase Comparators,...
Pfisterer Electrical Safety Equipment - Voltage Detectors, Phase Comparators,...
Thorne & Derrick International
 
BR07 Proposed Section A - A
BR07 Proposed Section A - ABR07 Proposed Section A - A
BR07 Proposed Section A - Asarah ralphs
 
HV Interface Presentation (1)
HV Interface Presentation (1)HV Interface Presentation (1)
HV Interface Presentation (1)paul doherty
 
Catalog biến tần Inovance MD290
Catalog biến tần Inovance MD290Catalog biến tần Inovance MD290
Catalog biến tần Inovance MD290
CTY TNHH HẠO PHƯƠNG
 
Water Detection System for Air Conditional&Mechanical Ventilation Installation
Water Detection System for Air Conditional&Mechanical Ventilation InstallationWater Detection System for Air Conditional&Mechanical Ventilation Installation
Water Detection System for Air Conditional&Mechanical Ventilation Installation
Johnny Tsai
 
Profibus and Profinet shield currents - Peter Thomas
Profibus and Profinet shield currents - Peter ThomasProfibus and Profinet shield currents - Peter Thomas
Profibus and Profinet shield currents - Peter Thomas
PROFIBUS and PROFINET InternationaI - PI UK
 
6. functional bonding and shielding of profibus and profinet peter thomas
6. functional bonding and shielding of profibus and profinet   peter thomas6. functional bonding and shielding of profibus and profinet   peter thomas
6. functional bonding and shielding of profibus and profinet peter thomas
PROFIBUS and PROFINET InternationaI - PI UK
 
Results of 10 years after installation tests with partial discharge detection...
Results of 10 years after installation tests with partial discharge detection...Results of 10 years after installation tests with partial discharge detection...
Results of 10 years after installation tests with partial discharge detection...
HighVoltageDUT
 

Similar to Ohl transmission lines opgw instalation procedure for fiber optic cables rev.00 (20)

61131730 transmission-line-case-study
61131730 transmission-line-case-study61131730 transmission-line-case-study
61131730 transmission-line-case-study
 
PROFINET network qualification Peter Thomas - oct 2015
PROFINET network qualification   Peter Thomas - oct 2015PROFINET network qualification   Peter Thomas - oct 2015
PROFINET network qualification Peter Thomas - oct 2015
 
EIT_Presentation
EIT_PresentationEIT_Presentation
EIT_Presentation
 
Profinet network qualification - Peter Thomas
Profinet network qualification - Peter ThomasProfinet network qualification - Peter Thomas
Profinet network qualification - Peter Thomas
 
ASSET 11 FOUL NETWORK Jan '15 REV B
ASSET 11 FOUL NETWORK Jan '15 REV BASSET 11 FOUL NETWORK Jan '15 REV B
ASSET 11 FOUL NETWORK Jan '15 REV B
 
VD4+12+44kA+Manual+1VDU09004-YN.pdf
VD4+12+44kA+Manual+1VDU09004-YN.pdfVD4+12+44kA+Manual+1VDU09004-YN.pdf
VD4+12+44kA+Manual+1VDU09004-YN.pdf
 
202029263 electra-560
202029263 electra-560202029263 electra-560
202029263 electra-560
 
Wire rope inspection service
Wire rope inspection serviceWire rope inspection service
Wire rope inspection service
 
194 adss cable-installationguide
194 adss cable-installationguide194 adss cable-installationguide
194 adss cable-installationguide
 
Motorway Communications - Series 1500 - Highway Works Specification
Motorway Communications - Series 1500 - Highway Works SpecificationMotorway Communications - Series 1500 - Highway Works Specification
Motorway Communications - Series 1500 - Highway Works Specification
 
BR08 Proposed Section B - B
BR08 Proposed Section B - BBR08 Proposed Section B - B
BR08 Proposed Section B - B
 
Catalog biến tần Inovance MD500
Catalog biến tần Inovance MD500Catalog biến tần Inovance MD500
Catalog biến tần Inovance MD500
 
Pfisterer Electrical Safety Equipment - Voltage Detectors, Phase Comparators,...
Pfisterer Electrical Safety Equipment - Voltage Detectors, Phase Comparators,...Pfisterer Electrical Safety Equipment - Voltage Detectors, Phase Comparators,...
Pfisterer Electrical Safety Equipment - Voltage Detectors, Phase Comparators,...
 
BR07 Proposed Section A - A
BR07 Proposed Section A - ABR07 Proposed Section A - A
BR07 Proposed Section A - A
 
HV Interface Presentation (1)
HV Interface Presentation (1)HV Interface Presentation (1)
HV Interface Presentation (1)
 
Catalog biến tần Inovance MD290
Catalog biến tần Inovance MD290Catalog biến tần Inovance MD290
Catalog biến tần Inovance MD290
 
Water Detection System for Air Conditional&Mechanical Ventilation Installation
Water Detection System for Air Conditional&Mechanical Ventilation InstallationWater Detection System for Air Conditional&Mechanical Ventilation Installation
Water Detection System for Air Conditional&Mechanical Ventilation Installation
 
Profibus and Profinet shield currents - Peter Thomas
Profibus and Profinet shield currents - Peter ThomasProfibus and Profinet shield currents - Peter Thomas
Profibus and Profinet shield currents - Peter Thomas
 
6. functional bonding and shielding of profibus and profinet peter thomas
6. functional bonding and shielding of profibus and profinet   peter thomas6. functional bonding and shielding of profibus and profinet   peter thomas
6. functional bonding and shielding of profibus and profinet peter thomas
 
Results of 10 years after installation tests with partial discharge detection...
Results of 10 years after installation tests with partial discharge detection...Results of 10 years after installation tests with partial discharge detection...
Results of 10 years after installation tests with partial discharge detection...
 

More from Arber Dogani

Risk evaluation template Prepared by A.Dogani 2016(1)
Risk evaluation template Prepared by A.Dogani 2016(1)Risk evaluation template Prepared by A.Dogani 2016(1)
Risk evaluation template Prepared by A.Dogani 2016(1)
Arber Dogani
 
Vleresimi i riskut per punimet e percjellesit dhe trosit 110k v banje cerri...
Vleresimi  i riskut  per punimet e percjellesit dhe trosit 110k v banje cerri...Vleresimi  i riskut  per punimet e percjellesit dhe trosit 110k v banje cerri...
Vleresimi i riskut per punimet e percjellesit dhe trosit 110k v banje cerri...
Arber Dogani
 
Vleresimi i riskut montimi i shtyllave 2x110k v ulez shkopet-skuraj) 01.07.2016
Vleresimi i riskut montimi i shtyllave 2x110k v ulez shkopet-skuraj) 01.07.2016Vleresimi i riskut montimi i shtyllave 2x110k v ulez shkopet-skuraj) 01.07.2016
Vleresimi i riskut montimi i shtyllave 2x110k v ulez shkopet-skuraj) 01.07.2016
Arber Dogani
 
Analiza e rrezikut ne pune montim percjellesi dhe trosi 110k v banje cerrik ...
Analiza e rrezikut ne pune montim percjellesi dhe trosi  110k v banje cerrik ...Analiza e rrezikut ne pune montim percjellesi dhe trosi  110k v banje cerrik ...
Analiza e rrezikut ne pune montim percjellesi dhe trosi 110k v banje cerrik ...
Arber Dogani
 
'' Plani menaxhimit te cilesise per linja transmetimi tu tm-tl dhe nenstacio...
'' Plani menaxhimit te cilesise  per linja transmetimi tu tm-tl dhe nenstacio...'' Plani menaxhimit te cilesise  per linja transmetimi tu tm-tl dhe nenstacio...
'' Plani menaxhimit te cilesise per linja transmetimi tu tm-tl dhe nenstacio...
Arber Dogani
 
Hse plan zbatim ''siguria shendeti dhe mjedisi'' 2018.04.11 .rev.03
Hse  plan zbatim  ''siguria shendeti dhe mjedisi'' 2018.04.11 .rev.03Hse  plan zbatim  ''siguria shendeti dhe mjedisi'' 2018.04.11 .rev.03
Hse plan zbatim ''siguria shendeti dhe mjedisi'' 2018.04.11 .rev.03
Arber Dogani
 
Specific method of statmeents risk assessment -job hazard analysis for land ...
Specific method of statmeents  risk assessment -job hazard analysis for land ...Specific method of statmeents  risk assessment -job hazard analysis for land ...
Specific method of statmeents risk assessment -job hazard analysis for land ...
Arber Dogani
 
Specific method of statmeents risk assessment -job hazard analysis for land ...
Specific method of statmeents  risk assessment -job hazard analysis for land ...Specific method of statmeents  risk assessment -job hazard analysis for land ...
Specific method of statmeents risk assessment -job hazard analysis for land ...
Arber Dogani
 
Investigation report 05.12.2017 lifting operation failure during tower erect...
Investigation report 05.12.2017  lifting operation failure during tower erect...Investigation report 05.12.2017  lifting operation failure during tower erect...
Investigation report 05.12.2017 lifting operation failure during tower erect...
Arber Dogani
 
Risk assessment for soil investigation at towers 5,6,7,8 rev01 a.dogani
Risk assessment for soil investigation at towers 5,6,7,8  rev01  a.doganiRisk assessment for soil investigation at towers 5,6,7,8  rev01  a.dogani
Risk assessment for soil investigation at towers 5,6,7,8 rev01 a.dogani
Arber Dogani
 
Incident&accident report date 02.08.2014 by arber dogani example for aplic...
Incident&accident  report date 02.08.2014  by arber dogani  example for aplic...Incident&accident  report date 02.08.2014  by arber dogani  example for aplic...
Incident&accident report date 02.08.2014 by arber dogani example for aplic...
Arber Dogani
 
Hse monthly report june 2015. rev.01 by.arber dogani example statistics
Hse monthly report   june 2015. rev.01 by.arber dogani  example statisticsHse monthly report   june 2015. rev.01 by.arber dogani  example statistics
Hse monthly report june 2015. rev.01 by.arber dogani example statistics
Arber Dogani
 
Hse templates by.arber dogani
Hse templates by.arber doganiHse templates by.arber dogani
Hse templates by.arber dogani
Arber Dogani
 
Ditar kantieri (formular)
Ditar kantieri (formular)Ditar kantieri (formular)
Ditar kantieri (formular)
Arber Dogani
 
Raport javor punimesh linja transmetimi format raportimi javor _ arber do...
Raport javor punimesh  linja transmetimi format raportimi javor    _ arber do...Raport javor punimesh  linja transmetimi format raportimi javor    _ arber do...
Raport javor punimesh linja transmetimi format raportimi javor _ arber do...
Arber Dogani
 
Raport javor siguria shendeti dhe mjedisi Raportim Mujor Statistika Arber Do...
Raport javor siguria shendeti dhe mjedisi  Raportim Mujor Statistika Arber Do...Raport javor siguria shendeti dhe mjedisi  Raportim Mujor Statistika Arber Do...
Raport javor siguria shendeti dhe mjedisi Raportim Mujor Statistika Arber Do...
Arber Dogani
 
Plan menanxhimi (mjedisi linjat e transmetimit)rev.00 arber dogani
Plan menanxhimi (mjedisi linjat e transmetimit)rev.00  arber doganiPlan menanxhimi (mjedisi linjat e transmetimit)rev.00  arber dogani
Plan menanxhimi (mjedisi linjat e transmetimit)rev.00 arber dogani
Arber Dogani
 
Plani emergjences linja transmetimit 110k v rev.00 22.07.2015 arber dogani
Plani emergjences linja transmetimit 110k v rev.00 22.07.2015 arber doganiPlani emergjences linja transmetimit 110k v rev.00 22.07.2015 arber dogani
Plani emergjences linja transmetimit 110k v rev.00 22.07.2015 arber dogani
Arber Dogani
 
Training hse housekeeping albanian mirembajtja e vendit te punes
Training hse housekeeping albanian mirembajtja e vendit te punesTraining hse housekeeping albanian mirembajtja e vendit te punes
Training hse housekeeping albanian mirembajtja e vendit te punes
Arber Dogani
 
Hse trainings respiratory protection albanian by a.dogani
Hse trainings respiratory protection albanian by a.doganiHse trainings respiratory protection albanian by a.dogani
Hse trainings respiratory protection albanian by a.dogani
Arber Dogani
 

More from Arber Dogani (20)

Risk evaluation template Prepared by A.Dogani 2016(1)
Risk evaluation template Prepared by A.Dogani 2016(1)Risk evaluation template Prepared by A.Dogani 2016(1)
Risk evaluation template Prepared by A.Dogani 2016(1)
 
Vleresimi i riskut per punimet e percjellesit dhe trosit 110k v banje cerri...
Vleresimi  i riskut  per punimet e percjellesit dhe trosit 110k v banje cerri...Vleresimi  i riskut  per punimet e percjellesit dhe trosit 110k v banje cerri...
Vleresimi i riskut per punimet e percjellesit dhe trosit 110k v banje cerri...
 
Vleresimi i riskut montimi i shtyllave 2x110k v ulez shkopet-skuraj) 01.07.2016
Vleresimi i riskut montimi i shtyllave 2x110k v ulez shkopet-skuraj) 01.07.2016Vleresimi i riskut montimi i shtyllave 2x110k v ulez shkopet-skuraj) 01.07.2016
Vleresimi i riskut montimi i shtyllave 2x110k v ulez shkopet-skuraj) 01.07.2016
 
Analiza e rrezikut ne pune montim percjellesi dhe trosi 110k v banje cerrik ...
Analiza e rrezikut ne pune montim percjellesi dhe trosi  110k v banje cerrik ...Analiza e rrezikut ne pune montim percjellesi dhe trosi  110k v banje cerrik ...
Analiza e rrezikut ne pune montim percjellesi dhe trosi 110k v banje cerrik ...
 
'' Plani menaxhimit te cilesise per linja transmetimi tu tm-tl dhe nenstacio...
'' Plani menaxhimit te cilesise  per linja transmetimi tu tm-tl dhe nenstacio...'' Plani menaxhimit te cilesise  per linja transmetimi tu tm-tl dhe nenstacio...
'' Plani menaxhimit te cilesise per linja transmetimi tu tm-tl dhe nenstacio...
 
Hse plan zbatim ''siguria shendeti dhe mjedisi'' 2018.04.11 .rev.03
Hse  plan zbatim  ''siguria shendeti dhe mjedisi'' 2018.04.11 .rev.03Hse  plan zbatim  ''siguria shendeti dhe mjedisi'' 2018.04.11 .rev.03
Hse plan zbatim ''siguria shendeti dhe mjedisi'' 2018.04.11 .rev.03
 
Specific method of statmeents risk assessment -job hazard analysis for land ...
Specific method of statmeents  risk assessment -job hazard analysis for land ...Specific method of statmeents  risk assessment -job hazard analysis for land ...
Specific method of statmeents risk assessment -job hazard analysis for land ...
 
Specific method of statmeents risk assessment -job hazard analysis for land ...
Specific method of statmeents  risk assessment -job hazard analysis for land ...Specific method of statmeents  risk assessment -job hazard analysis for land ...
Specific method of statmeents risk assessment -job hazard analysis for land ...
 
Investigation report 05.12.2017 lifting operation failure during tower erect...
Investigation report 05.12.2017  lifting operation failure during tower erect...Investigation report 05.12.2017  lifting operation failure during tower erect...
Investigation report 05.12.2017 lifting operation failure during tower erect...
 
Risk assessment for soil investigation at towers 5,6,7,8 rev01 a.dogani
Risk assessment for soil investigation at towers 5,6,7,8  rev01  a.doganiRisk assessment for soil investigation at towers 5,6,7,8  rev01  a.dogani
Risk assessment for soil investigation at towers 5,6,7,8 rev01 a.dogani
 
Incident&accident report date 02.08.2014 by arber dogani example for aplic...
Incident&accident  report date 02.08.2014  by arber dogani  example for aplic...Incident&accident  report date 02.08.2014  by arber dogani  example for aplic...
Incident&accident report date 02.08.2014 by arber dogani example for aplic...
 
Hse monthly report june 2015. rev.01 by.arber dogani example statistics
Hse monthly report   june 2015. rev.01 by.arber dogani  example statisticsHse monthly report   june 2015. rev.01 by.arber dogani  example statistics
Hse monthly report june 2015. rev.01 by.arber dogani example statistics
 
Hse templates by.arber dogani
Hse templates by.arber doganiHse templates by.arber dogani
Hse templates by.arber dogani
 
Ditar kantieri (formular)
Ditar kantieri (formular)Ditar kantieri (formular)
Ditar kantieri (formular)
 
Raport javor punimesh linja transmetimi format raportimi javor _ arber do...
Raport javor punimesh  linja transmetimi format raportimi javor    _ arber do...Raport javor punimesh  linja transmetimi format raportimi javor    _ arber do...
Raport javor punimesh linja transmetimi format raportimi javor _ arber do...
 
Raport javor siguria shendeti dhe mjedisi Raportim Mujor Statistika Arber Do...
Raport javor siguria shendeti dhe mjedisi  Raportim Mujor Statistika Arber Do...Raport javor siguria shendeti dhe mjedisi  Raportim Mujor Statistika Arber Do...
Raport javor siguria shendeti dhe mjedisi Raportim Mujor Statistika Arber Do...
 
Plan menanxhimi (mjedisi linjat e transmetimit)rev.00 arber dogani
Plan menanxhimi (mjedisi linjat e transmetimit)rev.00  arber doganiPlan menanxhimi (mjedisi linjat e transmetimit)rev.00  arber dogani
Plan menanxhimi (mjedisi linjat e transmetimit)rev.00 arber dogani
 
Plani emergjences linja transmetimit 110k v rev.00 22.07.2015 arber dogani
Plani emergjences linja transmetimit 110k v rev.00 22.07.2015 arber doganiPlani emergjences linja transmetimit 110k v rev.00 22.07.2015 arber dogani
Plani emergjences linja transmetimit 110k v rev.00 22.07.2015 arber dogani
 
Training hse housekeeping albanian mirembajtja e vendit te punes
Training hse housekeeping albanian mirembajtja e vendit te punesTraining hse housekeeping albanian mirembajtja e vendit te punes
Training hse housekeeping albanian mirembajtja e vendit te punes
 
Hse trainings respiratory protection albanian by a.dogani
Hse trainings respiratory protection albanian by a.doganiHse trainings respiratory protection albanian by a.dogani
Hse trainings respiratory protection albanian by a.dogani
 

Recently uploaded

Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
symbo111
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
Online aptitude test management system project report.pdf
Online aptitude test management system project report.pdfOnline aptitude test management system project report.pdf
Online aptitude test management system project report.pdf
Kamal Acharya
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
Rahul
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
ChristineTorrepenida1
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
SyedAbiiAzazi1
 
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
ssuser7dcef0
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
NidhalKahouli2
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
camseq
 
原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样
原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样
原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样
obonagu
 
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
awadeshbabu
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
TOP 10 B TECH COLLEGES IN JAIPUR 2024.pptx
TOP 10 B TECH COLLEGES IN JAIPUR 2024.pptxTOP 10 B TECH COLLEGES IN JAIPUR 2024.pptx
TOP 10 B TECH COLLEGES IN JAIPUR 2024.pptx
nikitacareer3
 
digital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdfdigital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdf
drwaing
 
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.pptPROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
bhadouriyakaku
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
gestioneergodomus
 

Recently uploaded (20)

Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
Online aptitude test management system project report.pdf
Online aptitude test management system project report.pdfOnline aptitude test management system project report.pdf
Online aptitude test management system project report.pdf
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
 
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
 
原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样
原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样
原版制作(unimelb毕业证书)墨尔本大学毕业证Offer一模一样
 
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
TOP 10 B TECH COLLEGES IN JAIPUR 2024.pptx
TOP 10 B TECH COLLEGES IN JAIPUR 2024.pptxTOP 10 B TECH COLLEGES IN JAIPUR 2024.pptx
TOP 10 B TECH COLLEGES IN JAIPUR 2024.pptx
 
digital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdfdigital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdf
 
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.pptPROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
 

Ohl transmission lines opgw instalation procedure for fiber optic cables rev.00

  • 1. CONSTRUCTION OF TRANSMISSION LINES WORKS 35Kv-400 kV Contractor: Client INSTALLATION PROCEDURE OF OPGW Document Number - 00 12/02/2018 Approval A.Dogani F.Koranqe&Isa.Kurti E. Barhani F.Doko REV DATE ISSUED FOR ISSUED BY CHECKED BY QA/QC TD CPM Engineer □ □ □ DATE BY APPROVED REJECTED NA COMMENTS Present document is property of the ow ner ArberQamil Dogani and it is prohibited any copy and/or convey of its original copy w ith any means, before the w ritten confirmation and approvalof the Company's legal representative.
  • 2. 2 | o f 1 8 REVISION TRACKING PAGE Revision Number Revised Page Revision Date Description of Revision Prepared by 000 all 12/02/2018 Prepared and Published Arber Dogani Rev No. 0 1 2 3 4 5 6 7 8 9 Date 12.02.201 8
  • 3. 3 | o f 1 8
  • 4. 4 | o f 1 8 1. - PURPOSE Describe the system used for installation and delivery of OPGW fibre optic cables. 2. - SCOPE This document covers all the activities usually performed by Company for on-site installation of OPGW fibre optic cables, including transport, installation, accessory assembly, verification of optical transmission characteristics and final certification. 3. - REFERENCES  Quality Assurance Manual 4. - GENERAL In general, the system and the equipment used for installation of the OPGW Cable with optical fibre are similar to those used for installation of the standard ground wire cable. Nevertheless, since there is an optical fiber core, special care should be taken to avoid any damage to the fibers by observing the minimum bending radius at all times. Therefore, specific components and machinery are used for the OPGW cable: pullers, tensioners, ant twisting counterweights, swivels, pulling grips, pulley-blocks, self-gripping clamps, pulling ropes, pulling cables, etc. 5. – PROCEDURES 5.1. – Survey of the line Prior planning for installation of the OPGW cable is performed by monitoring the line, taking into account the following parameters: 5.1.1. – Length of each drum The OPGW drum lengths are determined based on the following considerations: position of the tension towers, tower access, distance between supports and crossing with other lines, roads, railways, routes, services and other obstacles. 5.1.2.- Splices The position of the splices depends on the maximum available length of OPGW, on the position of the towers and the tower access.
  • 5. 5 | o f 1 8
  • 6. 6 | o f 1 8
  • 7. 7 | o f 1 8 It is compulsory to perform the calibration of the dynamometer, at least once a year. The Company supervisor could demand the Certificate of Calibration. This certificate will be emitted by an independent official laboratory.
  • 8. 8 | o f 1 8
  • 9. 9 | o f 1 8
  • 10. 10 | o f 1 8
  • 11. 11 | o f 1 8
  • 12. 12 | o f 1 8
  • 13. 13 | o f 1 8 As a rule, one drum at a time of OPGW cable is installed. In case of any difficulties, contact manufacturer. We will give the correct guidelines to proceed with the OPGW cable installation. Ensure that the metal part of the pulleys do not make contact with the cable to prevent it from
  • 14. 14 | o f 1 8 being damaged. 5.4.1.2 Stringing speed recommends an installation speed about 60 m/min, depending always on the environmental conditions and the topology of the overhead line. The supervisors (or the technical responsible) for the in spallation will take care that all recommendations are fully applied during the installation process. 5.4.1.3 Pulling tension The recommended pulling tension shall be lower than 1.5 times the weight (kg) of 1 km OPGW cable length. In case that higher pulling tensions are required (i.e. live installations,), further information should be asked to CLIENT supervisor or Manufacture. in order to know the maximum permissible pulling tension for such particular installation. 5.4.1.4 Minimum bending radius The minimum bending radius are as follows: - on tensioner reels 40 times the cable diameter - during installation 400 mm - after installation 20 times the cable diameter 5.4.1.5 Communications during stringing The personnel located at the puller, the tensioner, the pulley crossings and the cable ends are in communication at all times by communication system. 5.5 Sagging of the cable Generally, the methods used to obtain the correct sag values of the OPGW cables are the same used for conventional ground wire cables. The specific recommendations are as follows: Pulling is performed by a preformed fitting or tension clamp (in intermediate spans) or with the
  • 15. 15 | o f 1 8 pull jacket at the end. Special attention must be taken on using appropriate clamps adapted to the OPGW cable diameter. Sagging of the cable and fittings installation are always performed after stringing. At this time, the attachment fittings are also installed to prevent damage to the OPGW cable. The installer is responsible for any damage to the OPGW cable that may occur due to failure cause by incorrect application of the previous points. If the tension and sags are different from the expected values, the stringing or sagging should be halted. The supervisor and the project leader will be consulted in order to safely continue the installation operations. 5.6 Installation of fittings and accessories The fittings: tension clamps, suspensions, earthling clamps, dampers, etc. should be installed in accordance with the manufacturer’s instructions and using the appropriate tools. Special attention must be taken on using appropriate clamps adapted to the OPGW cable diameter. From the top of the tower, OPGW falls down, it is necessary to introduce a cable loop of three spires of 1 m diameter in the top of the tower and each 20 m from the top. Finally, the cable must be conducted till the joint box place. 5.7 Personnel training All personnel who participate in the installation of the OPGW cable should be informed of handling problems and installation procedures for the OPGW cable. It is responsibility of the installer to assure the correct instruction to the whole personnel involved in the installation works. 5.8 Supervision Over requisition, Manufactures offers the service of a supervisor that will be responsible for ensuring compliance with all of the points indicated in this document as well as all required standards applicable to the specific installation. The supervisor r will communicate to Manufactures for ,any non-conformity detected in the cable or cable installation procedures. If a situation occurs that is not covered in the present installation procedure, whenever this occurs with an OPGW cable, the Supervisor will determine whether or not the action is correct.
  • 16. 16 | o f 1 8 The supervisor will request the installer to provide a descriptive list of the components to be used for installation. Moreover, he will verify that these components are sufficient and adequate. To place the supervision on record, the supervisor will register all of the items indicated in point 5 of this document in Q-09 -F-PA-004 format. 5.9 - Splices After stringing and the optical measurements taken to verify it meets the customer’s requirements, the OPGW cable will be spliced The joint boxes used should have a device for fixing properly the center element (multitude configuration) or the aramid yarns (nanotube configuration). recommend to use the Manufacture joint boxes specially designed for the correct jointing of OPGW cables (Q- 09PE-PA-004 “Installation of EWJ and EWMJ splice boxes”) 5.10 – Transmission test during the installation phases Prior to as well as during the installation phases, the transmission characteristics of the fibre optic cables are verified in order to ensure proper installation and be sure that the final tests are within the specified range of tolerances. 5.10.1 – Measurements before OPGW cable installation Prior to OPGW cable installation, each optical fibres is verified using OTDR. The attenuation values recorded are registered in during installation phase” and saved on an electronic diskette. This computer register is kept by DOKO. 5.10.2 - Measurements after installation After the cable has been installed, and prior to the splices, each of the cable fibres is verified once again using OTDR. These new values are compared with those obtained in 5.11.1. in order to ensure the absence of any problems. The attenuation values recorded are registered saved on an electronic diskette. This computer register is kept by. The measurements are suitable identified and referenced. 5.10.3 – Splices measurement After splicing, each joint is optically verified using OTDR in order to ensure that the attenuation values are within the required values.
  • 17. 17 | o f 1 8 The attenuation values recorded are registered and on electronic format. This computer register is kept by DOKO. 5.11 – Final acceptance test After installation, a final measurement of the transmission characteristics is and the values are duly recorded. A copy of this is submitted to the customer. These measurements are also recorded and kept by Company. 5.12 – Safety and hygiene The supervisor designated by is responsible for compliance with the general safety and hygiene standards for manufacture cables or the requirements stipulated by contract, if any. 5.13 – Environment 5.13.1 – Withdrawal of special waste (toxic and dangerous) If any type of special waste such as oil, grease, solvents, saturation of gloves or rags, etc. are produced during cable installation, proceed as follows:  Place in heavy-duty carboys or steel drums, indicating what type of waste it is.  If installation is performed in the Community of Montenegro, contact the IIC Quality and Environment Department. This department will furnish the data for the administrator in charge of such waste. Another option is to contact the Waste Committee of the Company directly (tel. +355689095223).  If the installation is located outside of the Community, contact the Town Council or Community in this location so that such bodies can provide information on the administrators authorized to treat this waste.  Such waste must not be abandoned, mixed with other waste, or sent to the dumping ground. 5.13.2 – Withdrawal of non-special or inert waste  If there are excess materials or waste such as aluminium, optic fibre, plastic, wood, iron, etc., whenever possible, this should be sent to an authorized recycler or a controlled dumping ground.  Regardless of the amount, the waste should never be abandoned. Moreover, the area should be cleaned when the work is finished. 6. – APPLICABLE FORMATS
  • 18. 18 | o f 1 8 7.- APPLICABLEPROCEDURES Code Document _______________________INSTALLATION OF EWJ and EWMJ SPLICE BOXES 8.- MODIFICATIONSTO THE PREVIOUS REVISION Point 5.6: down lead cable in the jointing towers Point 5.9.: fixing the center element (multitude configuration) or the aramid yarns (monotone configuration)