SlideShare a Scribd company logo
1 of 36
• Generation
• Peak Demand : 132 GW
• Growth Rate : 9 – 10 % (per annum)
India - Present Power Scenario
Total Installed
Capacity – 228.7 GW
(As on 30.09.13)
NER
ER
NR
WR
SR
A
N
D
A
M
A
N
&
N
IC
O
B
A
R
L
A
K
S
H
A
D
W
E
E
P
National
Grid
1950-60’s
1970-80s
2000 onwards
Local
1950’s
State
Grids by
SEBs
Regional Grids
with ATS of
Central
Generation
(Paradigm Shift from self
sufficiency at Regional level
concept to National level)
Interconnecting
Regional Grids
with HVDC
1990s
0
50000
100000
IX Plan X Plan XI Plan XII Plan
5100
14100
27750 66400
IR Capacity (MW)
Evolution of National Grid
4
NEW Grid
South
Grid
South
West
North
East
Northeast
Five Regional Grids
Five Frequencies
October 1991
East and Northeast
synchronized
March 2003
West synchronized
With East & Northeast
August 2006
North synchronized
With Central Grid
Central Grid
Five Regional Grids
Two Frequencies
Installed Capacity 229 GW
MERGING
OF
MARKETS
 Transmission network
 spread geographically over 3.3million sq
km : Inter-State and Intra-State level
 Transmission line : 2,80,571 ckm
(POWERGRID : 1,020,000 ckm)
 765kV : 7910 ckm
 400kV : 1,20,693 ckm
 220kV : 1,42,536 ckm
 HVDC Bipole (±500kV) : 9,432 ckms
 Transformation capacity (MVA/MW)
 HVAC :474,091 MVA
(POWERGRID : 170,000MVA, 171 S/s)
− 765kV : 56,500 MVA
− 400kV : 170,397 MVA
− 220kV : 247,194 MVA
 HVDC : 13,500 MW
 FSC – 33nos., TCSC – 6 nos.
SOUTH
ERN
REGION
WESTE
RNREGI
ON
EASTER
N
REGION
NORTHE
RN
REGION NORTH-
EASTER
N
REGION
1
2
The
‘Electrical’
Regions
Transmission Network - Present
6
14,230 MW
WR
NR
NER
ER
SR
1,520 MW
3,630 MW
4,390 MW
1,260 MW
6,220 MW
Present IR Capacity – 31,850 MW
WR
Inter-Regional Capacity - Existing
Generators
Central/State GENCO, IPP, Captive
CTU
Inter-State Trans. system,
Open Access
STU
Intra-State Tr./Sub-tr. system
DISCOMS
System
Operator
Consumers
Industries, household,
agriculture
Traders
Power
Exchange
Players in the Power Sector
• To undertake transmission of electricity through ISTS
• To discharge all functions of planning and co-ordination
relating to ISTS with Central Govt, CEA, RPC, STU, Trans
Licensees.
• To ensure development of an efficient, co-ordinated and
economical system of ISTS lines for smooth flow of electricity
from generating stations to the load centres
• To provide non-discriminatory access to its transmission
system for use by any licensee or generating company on
payment of the transmission charges; or any consumer as
and when such open access is provided by the State
Commission
Role of POWERGRID as CTU
NLDC:
Ensure integrated operation of
National Grid
RLDC:
Ensure integrated operation of
Regional Grid
SLDC:
Ensure integrated operation of State
Grid
31
5
Grid Management - Hierarchy
NATIONAL GRID - FUTURE
NEED OF NEW INITIATIVES IN TRANSMISSION
** Source- Planning commission report on IEP
Present Generation Capacity & Demand - 228 GW & 132 GW
# Considering 9% GDP growth rate
205GW
Projected Power Scenario
Source: NASA Satellite Snapshot
Bangalore &
Chennai
Mumbai &
Pune
Ahmedabad
Hyderabad
Demand Pattern in India
 Coal – In Central India
- Chhattisgarh : 58000 MW
- Orissa : 30000 MW
- Jharkhand : 15000 MW
- Madhya Pradesh:16000 MW
 Hydro – In North Eastern &
Northern Himalayan region
 Coastal based
- Andhra Pradesh: 24000 MW
- Tamil Nadu : 10000 MW
- Gujarat : 11000 MW
Expected Installed Capacity (2025) : 6,00,000MW
Lara
Expected Generating Stations - 2025
Partabpur
Talcher/Ib Valley
Krishnapatnam
NEPAL
Korba
Bhopal
Indore
Tadri
Girye
Kaiga
Thiruvananthapuram
Pipavav
Kudankulam
SR
Bangalore
Kayamkulam
WR
Tarapur
Mumbai
Cuddalore
Ennore
Akaltara
Raipur
Hyderabad
RAPP
Gandhinagar
Mudra
Delhi
Ludhiana
NR
Jaipur
Jammu
Sasan
Vindhyachal
Lucknow
Load Centre Based Generation
Ultra-Mega Generation
Hydro Based Generation
Coastal Generation
Coal Based generation
Nuclear generation
Bhubaneswar
Darlipali
Vizag
Simhadri
LEGEND
Load-Centre
NER
Guwahati
Koderma
SIKKIM
Kolkata
ER
Patna
NECK
CHICKEN
BHUTAN
DESH
BANGLA
M
Y
A
N
M
M
A
R
Mangalore
Kozhikode
South Madras
Chennai
Energy resources (coal, water etc.) unevenly distributed
Hydro
Coal
Energy Resource Map
 12th Plan (2012-17) Capacity Addition : 88 GW
• Thermal – 72 GW
• Hydro – 11 GW
• Nuclear – 6 GW
 Renewable Capacity Addition - 12th Plan(2012-17) : 42 GW
• Wind – 30 GW
• Solar – 10 GW
• Small Hydro – 2 GW
Future Generation Scenario (5-6 Years)
 Transmission Line : 1,10,000 ckm
(POWERGRID – 40,000ckm)
 765kV – 27,000 ckm
 400kV – 38,000 ckm
 220kV/132kV – 35,000 ckm
 HVDC – 9,500 ckm
 Substations : about 270,000 MVA
(POWERGRID – 100,000 MVA)
Expansion Programme – 12th Plan
National Grid – A Continuing Process
27750
66000
0
20000
40000
60000
80000
2011-12 By 2016-17
 National Grid comprises of Inter-State, Intra-State and
Inter-regional transmission system
 Cummulative Growth of Inter-regional capacity in MW
Emerging National Grid
17
WR
NR
NER
ER
SR
6400 MW
10200 MW
8400 MW
6000 MW
1600 MW
5800 MW
National Grid - XII Plan addition – 38,400 MW
National Grid - Total by XII Plan – 66,000 MW
Augmentation of IR Capacity in
XII Plan
TECHNOLOGY
Voltage
(kV)
1977 1990 2000 2002 2012 2017-18
Year
220kV
400kV
500kV
HVDC
765kV
800kV
HVDC
1200kV
765kV D/C
- AC
World’s Highest
Voltage level – Test station
Charged in Oct.’12
World’s longest
multi-terminal
HVDC to harness renewable
Hydro Power from North-east
Pursuing Higher Voltage Levels
 High Voltage line
 Increase the capacity of trans. corridor through HSIL/re-
conductoring with HTLS /Upgradation
 Utilisation of existing transmission lines upto full thermal
capacity – Series capacitors, SVC, FACTS
 Optimization of Tower design – tall tower, multi-ckt. tower
 GIS substation
 EHVAC : 400kV  765kV  1200kV
 HVDC : 500kV  800kV
Technology being Adopted
ROAD MAP FOR INDIAN POWER SYSTEM
RoW
(m)
Capacity
(MW)
MW/m
RoW
400kV S/c 52 500 9.6
400kV D/c 46 1000 21.8
765kV S/c 64 2500 39
765kV D/c 67 4000 60
800kV HVDC 69 6000 87
69 m
176
m
High Power Intensity Corridor
World’s longest
multi-terminal
±800 kV HVDC
under
implementation
from Biswanath
Chariali, North-
Eastern Region to
Agra, Northern
Region.
Shall transmit
power to the tune
of 6000-8000 MW.
2000 km
Agra
Biswanath
Chariali
Implementing +800kV HVDC Bipole Link
World’s highest voltage,
1200kV UHV AC, test
charged at Bina, Madhya
Pradesh in October 2012.
Has been Developed
Indigenously through
Public Private Partnership
(PPP) with 35 Indian
manufacturers in open
collaboration.
Indigenous Development of 1200kV UHVAC
DEVELOPMENT PLAN
Central Sector State Sector Private Sector Total
15220 (30%) 16732(30%) 23012(42%) 54964
26181 (30%) 15530(17%) 46825(53%) 88537
XI
XII
Change in Generation Profile
 Long-term Open Access
– Application Received : 218no. , 132,000MW
– Granted : 148 No., 83,000 MW :
Connectivity
– Application Received : 188no. , 176,300MW
– Granted : 84 No., 74,400 MW
Short Term Open Access
– 2012-13 : 32,000 transactions, 74BU energy
Long Term Open Access / Connectivity
S.No Corridor Ins. Capacity (MW) LTOA granted (MW)
1 HCPTC –I
( for IPP projects in Orissa)
10090 6080
2 HCPTC –II
( for IPP projects in Jharkhand)
3820 3510
3 HCPTC-III
(for IPP projects in Sikkim)
2162 2162
4 HCTPC-IV
( for IPP projects in M.P & Chhattisgarh)
4370 3554
5 HCTPC –V
( for IPP projects in Chhattisgarh)
18270 16289
6 HCTPC –VI
( for IPP projects in Krishnapatnam)
4240 3516
7 HCTPC –VII
( for IPP projects in Tuticorin)
2520 2000
8 HCTPC –VIII
( for IPP projects in Srikakulam)
1320 1240.8
9 HCTPC –IX
( for IPP projects in SR, for transfer of power to WR/NR)
8446 7026
10 HCTPC –X
( for IPP projects in Vemagiri)
4568 4325
11 HCTPC –XI
( for IPP projects in Nagapattinam/ Cuddalore )
2250 2137
Total 62,000 52,000
High Capacity Corridors
28
HIGH CAPACITY
CORRIDORS
CROSS-COUNTRY INTERCONNECTION
Linkages with
Neighboring
Countries
31
BOGRA
SOUTH
BHERAMARA
NAOGAON
NIAMATPUR
FARRAKA
SUBHASGRAM
KATWA
GOKARNA
JEERAT
KHULNA
(SOUTH)
BOTTAIL
BAHARAMPUR
CH. NAWABGANJ
RAGHUNATHGANJ
KAHALGAON
SAGARDIGHI
RAJSHAHI
BAHARAMPUR
ISHURDI
NATORE
KHEJURIA
FARIDPUR
BAGHABARI
GHORASAL
MADHOPUR
SHAHJAD
PABNA
PUR
SIRAJGANJ
BOGRA
INTERCONNECTION BETWEEN INDIA AND BANGLADESH GRIDS
400 kV
230 kV
132 kV
THE PROJECT
LEGEND
BAKRESHWAR
KOLAGHAT
BANGLADESH
INDIA
400kV D/c
(400 KV)
MALDA
DHULIAN
DURGAPUR
Existing
Under Constr. / Future
JAYPURHAT BARAPUKURIA
32
India - Bhutan : Interconnection
33
India - Nepal : Interconnection
130 Kms
120 Kms
110 Kms
Proposed Route for Interconnection
Madurai-New
Panaikulam
New Anuradhapura
Taliamannar
Thirukketiswaram *
48 Kms
Madurai
India – Sri Lanka Interconnection
ROAD MAP FOR INDIAN POWER SYSTEM
 Issues concerning availability of RoW and same are
becoming critical –
 Resistance of people, terrains in areas of mountains and forest
 Sector to grow from 228 GW to 600 GW in next 20 years –
Even 765kV system may not be good enough. New methods
have to be found out
 Challenges to develop Transmission system to meet the
requirement of power flow from anywhere to anywhere.
 With increasing magnitude of power transmission, create
new challenges of proper O&M
Issues & Challenges
Thank you

More Related Content

Similar to presentation-by-pgcil-development-of-transmission-system-in-india-foir-workshop-at-goa-21-10-2013.ppt

1 hvdc systems_in_india
1 hvdc systems_in_india1 hvdc systems_in_india
1 hvdc systems_in_indiaganesh g
 
National Transmission And Dispatch Company (NTDC)
National Transmission And Dispatch Company (NTDC)National Transmission And Dispatch Company (NTDC)
National Transmission And Dispatch Company (NTDC)Aneel-k Suthar
 
Power Sector in Pakistan - 2017
Power Sector in Pakistan - 2017Power Sector in Pakistan - 2017
Power Sector in Pakistan - 2017Salman Haider
 
Power industries and solar pv power plant in pakistan
Power industries and solar pv power plant in pakistanPower industries and solar pv power plant in pakistan
Power industries and solar pv power plant in pakistanIBRAR AHMAD
 
Indian power system (an overview)
Indian power  system (an overview)Indian power  system (an overview)
Indian power system (an overview)PARVINDAR CHAUDHARY
 
17. NECS 2016 _ Energy_ Evolving power situation and investment opportunities...
17. NECS 2016 _ Energy_ Evolving power situation and investment opportunities...17. NECS 2016 _ Energy_ Evolving power situation and investment opportunities...
17. NECS 2016 _ Energy_ Evolving power situation and investment opportunities...FICCINorthEast
 
Operational description of 400kv switchyard NTPC Ramagundam RSTPS
Operational description of 400kv switchyard NTPC Ramagundam RSTPSOperational description of 400kv switchyard NTPC Ramagundam RSTPS
Operational description of 400kv switchyard NTPC Ramagundam RSTPSPradeep Avanigadda
 
1200 kv ultra high voltage transmission system by prannaya kumar giri & b...
1200 kv  ultra high voltage transmission system  by   prannaya kumar giri & b...1200 kv  ultra high voltage transmission system  by   prannaya kumar giri & b...
1200 kv ultra high voltage transmission system by prannaya kumar giri & b...Prannay Kumar Giri
 
O&m of hvdc station power grid india
O&m of hvdc station power grid indiaO&m of hvdc station power grid india
O&m of hvdc station power grid indiaVaibhav Jain
 
Power sector in India
Power sector in IndiaPower sector in India
Power sector in IndiaDaya Kherwar
 
Power genaration in bangladesh
Power genaration in bangladeshPower genaration in bangladesh
Power genaration in bangladeshMd. Atiqur Rahman
 
CASA-1000 Kyrgyzstan & Tajikistan to Afghanistan & Pakistan
CASA-1000 Kyrgyzstan & Tajikistan to Afghanistan & PakistanCASA-1000 Kyrgyzstan & Tajikistan to Afghanistan & Pakistan
CASA-1000 Kyrgyzstan & Tajikistan to Afghanistan & PakistanPower System Operation
 
15. Future Power System for the year 2030.pptx
15. Future Power System for the year 2030.pptx15. Future Power System for the year 2030.pptx
15. Future Power System for the year 2030.pptxssuser0f80df
 
Production of Electricity in PAKISTAN 2017-18
Production  of Electricity  in PAKISTAN 2017-18Production  of Electricity  in PAKISTAN 2017-18
Production of Electricity in PAKISTAN 2017-18MuhammadUsman829
 
Power transmission sector
Power transmission sectorPower transmission sector
Power transmission sectorRahul Gupta
 
power sector &ehv
power sector &ehvpower sector &ehv
power sector &ehvAjay Kishor
 
Engineering the power system of the future
Engineering the power system of the futureEngineering the power system of the future
Engineering the power system of the futureemmaroche
 
9i9 determination-of-bus-voltages-libre
9i9 determination-of-bus-voltages-libre9i9 determination-of-bus-voltages-libre
9i9 determination-of-bus-voltages-libreAbanihi
 

Similar to presentation-by-pgcil-development-of-transmission-system-in-india-foir-workshop-at-goa-21-10-2013.ppt (20)

1 hvdc systems_in_india
1 hvdc systems_in_india1 hvdc systems_in_india
1 hvdc systems_in_india
 
National Transmission And Dispatch Company (NTDC)
National Transmission And Dispatch Company (NTDC)National Transmission And Dispatch Company (NTDC)
National Transmission And Dispatch Company (NTDC)
 
Power Sector in Pakistan - 2017
Power Sector in Pakistan - 2017Power Sector in Pakistan - 2017
Power Sector in Pakistan - 2017
 
Power industries and solar pv power plant in pakistan
Power industries and solar pv power plant in pakistanPower industries and solar pv power plant in pakistan
Power industries and solar pv power plant in pakistan
 
Indian power system (an overview)
Indian power  system (an overview)Indian power  system (an overview)
Indian power system (an overview)
 
17. NECS 2016 _ Energy_ Evolving power situation and investment opportunities...
17. NECS 2016 _ Energy_ Evolving power situation and investment opportunities...17. NECS 2016 _ Energy_ Evolving power situation and investment opportunities...
17. NECS 2016 _ Energy_ Evolving power situation and investment opportunities...
 
21PESGM2656.pptx
21PESGM2656.pptx21PESGM2656.pptx
21PESGM2656.pptx
 
Operational description of 400kv switchyard NTPC Ramagundam RSTPS
Operational description of 400kv switchyard NTPC Ramagundam RSTPSOperational description of 400kv switchyard NTPC Ramagundam RSTPS
Operational description of 400kv switchyard NTPC Ramagundam RSTPS
 
1200 kv ultra high voltage transmission system by prannaya kumar giri & b...
1200 kv  ultra high voltage transmission system  by   prannaya kumar giri & b...1200 kv  ultra high voltage transmission system  by   prannaya kumar giri & b...
1200 kv ultra high voltage transmission system by prannaya kumar giri & b...
 
O&m of hvdc station power grid india
O&m of hvdc station power grid indiaO&m of hvdc station power grid india
O&m of hvdc station power grid india
 
Power sector in India
Power sector in IndiaPower sector in India
Power sector in India
 
Power genaration in bangladesh
Power genaration in bangladeshPower genaration in bangladesh
Power genaration in bangladesh
 
CASA-1000 Kyrgyzstan & Tajikistan to Afghanistan & Pakistan
CASA-1000 Kyrgyzstan & Tajikistan to Afghanistan & PakistanCASA-1000 Kyrgyzstan & Tajikistan to Afghanistan & Pakistan
CASA-1000 Kyrgyzstan & Tajikistan to Afghanistan & Pakistan
 
15. Future Power System for the year 2030.pptx
15. Future Power System for the year 2030.pptx15. Future Power System for the year 2030.pptx
15. Future Power System for the year 2030.pptx
 
Production of Electricity in PAKISTAN 2017-18
Production  of Electricity  in PAKISTAN 2017-18Production  of Electricity  in PAKISTAN 2017-18
Production of Electricity in PAKISTAN 2017-18
 
Power Scenario in India
Power Scenario in IndiaPower Scenario in India
Power Scenario in India
 
Power transmission sector
Power transmission sectorPower transmission sector
Power transmission sector
 
power sector &ehv
power sector &ehvpower sector &ehv
power sector &ehv
 
Engineering the power system of the future
Engineering the power system of the futureEngineering the power system of the future
Engineering the power system of the future
 
9i9 determination-of-bus-voltages-libre
9i9 determination-of-bus-voltages-libre9i9 determination-of-bus-voltages-libre
9i9 determination-of-bus-voltages-libre
 

More from WondererBack

unit 1 all-Copy.pdf
unit 1 all-Copy.pdfunit 1 all-Copy.pdf
unit 1 all-Copy.pdfWondererBack
 
LHB COACH PAINTING.PPT
LHB COACH PAINTING.PPTLHB COACH PAINTING.PPT
LHB COACH PAINTING.PPTWondererBack
 
LHB COACH PAINTING AVINASH.PPT
LHB COACH PAINTING AVINASH.PPTLHB COACH PAINTING AVINASH.PPT
LHB COACH PAINTING AVINASH.PPTWondererBack
 
AIR BRAKING SYSTEM AVINASH.pptx
AIR BRAKING SYSTEM AVINASH.pptxAIR BRAKING SYSTEM AVINASH.pptx
AIR BRAKING SYSTEM AVINASH.pptxWondererBack
 
2161902150123119053-170323180029.pdf
2161902150123119053-170323180029.pdf2161902150123119053-170323180029.pdf
2161902150123119053-170323180029.pdfWondererBack
 
newmicrosoftofficepowerpointpresentation1-161115095922.pdf
newmicrosoftofficepowerpointpresentation1-161115095922.pdfnewmicrosoftofficepowerpointpresentation1-161115095922.pdf
newmicrosoftofficepowerpointpresentation1-161115095922.pdfWondererBack
 
emissions-feb2016-160722103546.pdf
emissions-feb2016-160722103546.pdfemissions-feb2016-160722103546.pdf
emissions-feb2016-160722103546.pdfWondererBack
 
combustionsienginesslideshare-180201093555 (1).pdf
combustionsienginesslideshare-180201093555 (1).pdfcombustionsienginesslideshare-180201093555 (1).pdf
combustionsienginesslideshare-180201093555 (1).pdfWondererBack
 
blood relations.pdf
blood relations.pdfblood relations.pdf
blood relations.pdfWondererBack
 

More from WondererBack (14)

unit 1 all-Copy.pdf
unit 1 all-Copy.pdfunit 1 all-Copy.pdf
unit 1 all-Copy.pdf
 
LHB COACH PAINTING.PPT
LHB COACH PAINTING.PPTLHB COACH PAINTING.PPT
LHB COACH PAINTING.PPT
 
LHB COACH PAINTING AVINASH.PPT
LHB COACH PAINTING AVINASH.PPTLHB COACH PAINTING AVINASH.PPT
LHB COACH PAINTING AVINASH.PPT
 
AIR BRAKING SYSTEM AVINASH.pptx
AIR BRAKING SYSTEM AVINASH.pptxAIR BRAKING SYSTEM AVINASH.pptx
AIR BRAKING SYSTEM AVINASH.pptx
 
CNC1.ppt
CNC1.pptCNC1.ppt
CNC1.ppt
 
CNC1 (1).ppt
CNC1 (1).pptCNC1 (1).ppt
CNC1 (1).ppt
 
unit 4.pdf
unit 4.pdfunit 4.pdf
unit 4.pdf
 
mcl345-41.ppt
mcl345-41.pptmcl345-41.ppt
mcl345-41.ppt
 
2161902150123119053-170323180029.pdf
2161902150123119053-170323180029.pdf2161902150123119053-170323180029.pdf
2161902150123119053-170323180029.pdf
 
newmicrosoftofficepowerpointpresentation1-161115095922.pdf
newmicrosoftofficepowerpointpresentation1-161115095922.pdfnewmicrosoftofficepowerpointpresentation1-161115095922.pdf
newmicrosoftofficepowerpointpresentation1-161115095922.pdf
 
emissions-feb2016-160722103546.pdf
emissions-feb2016-160722103546.pdfemissions-feb2016-160722103546.pdf
emissions-feb2016-160722103546.pdf
 
polynomials_.pdf
polynomials_.pdfpolynomials_.pdf
polynomials_.pdf
 
combustionsienginesslideshare-180201093555 (1).pdf
combustionsienginesslideshare-180201093555 (1).pdfcombustionsienginesslideshare-180201093555 (1).pdf
combustionsienginesslideshare-180201093555 (1).pdf
 
blood relations.pdf
blood relations.pdfblood relations.pdf
blood relations.pdf
 

Recently uploaded

Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacingjaychoudhary37
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 

Recently uploaded (20)

Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacing
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 

presentation-by-pgcil-development-of-transmission-system-in-india-foir-workshop-at-goa-21-10-2013.ppt

  • 1.
  • 2. • Generation • Peak Demand : 132 GW • Growth Rate : 9 – 10 % (per annum) India - Present Power Scenario Total Installed Capacity – 228.7 GW (As on 30.09.13) NER ER NR WR SR A N D A M A N & N IC O B A R L A K S H A D W E E P
  • 3. National Grid 1950-60’s 1970-80s 2000 onwards Local 1950’s State Grids by SEBs Regional Grids with ATS of Central Generation (Paradigm Shift from self sufficiency at Regional level concept to National level) Interconnecting Regional Grids with HVDC 1990s 0 50000 100000 IX Plan X Plan XI Plan XII Plan 5100 14100 27750 66400 IR Capacity (MW) Evolution of National Grid
  • 4. 4 NEW Grid South Grid South West North East Northeast Five Regional Grids Five Frequencies October 1991 East and Northeast synchronized March 2003 West synchronized With East & Northeast August 2006 North synchronized With Central Grid Central Grid Five Regional Grids Two Frequencies Installed Capacity 229 GW MERGING OF MARKETS
  • 5.  Transmission network  spread geographically over 3.3million sq km : Inter-State and Intra-State level  Transmission line : 2,80,571 ckm (POWERGRID : 1,020,000 ckm)  765kV : 7910 ckm  400kV : 1,20,693 ckm  220kV : 1,42,536 ckm  HVDC Bipole (±500kV) : 9,432 ckms  Transformation capacity (MVA/MW)  HVAC :474,091 MVA (POWERGRID : 170,000MVA, 171 S/s) − 765kV : 56,500 MVA − 400kV : 170,397 MVA − 220kV : 247,194 MVA  HVDC : 13,500 MW  FSC – 33nos., TCSC – 6 nos. SOUTH ERN REGION WESTE RNREGI ON EASTER N REGION NORTHE RN REGION NORTH- EASTER N REGION 1 2 The ‘Electrical’ Regions Transmission Network - Present
  • 6. 6 14,230 MW WR NR NER ER SR 1,520 MW 3,630 MW 4,390 MW 1,260 MW 6,220 MW Present IR Capacity – 31,850 MW WR Inter-Regional Capacity - Existing
  • 7. Generators Central/State GENCO, IPP, Captive CTU Inter-State Trans. system, Open Access STU Intra-State Tr./Sub-tr. system DISCOMS System Operator Consumers Industries, household, agriculture Traders Power Exchange Players in the Power Sector
  • 8. • To undertake transmission of electricity through ISTS • To discharge all functions of planning and co-ordination relating to ISTS with Central Govt, CEA, RPC, STU, Trans Licensees. • To ensure development of an efficient, co-ordinated and economical system of ISTS lines for smooth flow of electricity from generating stations to the load centres • To provide non-discriminatory access to its transmission system for use by any licensee or generating company on payment of the transmission charges; or any consumer as and when such open access is provided by the State Commission Role of POWERGRID as CTU
  • 9. NLDC: Ensure integrated operation of National Grid RLDC: Ensure integrated operation of Regional Grid SLDC: Ensure integrated operation of State Grid 31 5 Grid Management - Hierarchy
  • 10. NATIONAL GRID - FUTURE
  • 11. NEED OF NEW INITIATIVES IN TRANSMISSION ** Source- Planning commission report on IEP Present Generation Capacity & Demand - 228 GW & 132 GW # Considering 9% GDP growth rate 205GW Projected Power Scenario
  • 12. Source: NASA Satellite Snapshot Bangalore & Chennai Mumbai & Pune Ahmedabad Hyderabad Demand Pattern in India
  • 13.  Coal – In Central India - Chhattisgarh : 58000 MW - Orissa : 30000 MW - Jharkhand : 15000 MW - Madhya Pradesh:16000 MW  Hydro – In North Eastern & Northern Himalayan region  Coastal based - Andhra Pradesh: 24000 MW - Tamil Nadu : 10000 MW - Gujarat : 11000 MW Expected Installed Capacity (2025) : 6,00,000MW Lara Expected Generating Stations - 2025 Partabpur Talcher/Ib Valley Krishnapatnam NEPAL Korba Bhopal Indore Tadri Girye Kaiga Thiruvananthapuram Pipavav Kudankulam SR Bangalore Kayamkulam WR Tarapur Mumbai Cuddalore Ennore Akaltara Raipur Hyderabad RAPP Gandhinagar Mudra Delhi Ludhiana NR Jaipur Jammu Sasan Vindhyachal Lucknow Load Centre Based Generation Ultra-Mega Generation Hydro Based Generation Coastal Generation Coal Based generation Nuclear generation Bhubaneswar Darlipali Vizag Simhadri LEGEND Load-Centre NER Guwahati Koderma SIKKIM Kolkata ER Patna NECK CHICKEN BHUTAN DESH BANGLA M Y A N M M A R Mangalore Kozhikode South Madras Chennai Energy resources (coal, water etc.) unevenly distributed Hydro Coal Energy Resource Map
  • 14.  12th Plan (2012-17) Capacity Addition : 88 GW • Thermal – 72 GW • Hydro – 11 GW • Nuclear – 6 GW  Renewable Capacity Addition - 12th Plan(2012-17) : 42 GW • Wind – 30 GW • Solar – 10 GW • Small Hydro – 2 GW Future Generation Scenario (5-6 Years)
  • 15.  Transmission Line : 1,10,000 ckm (POWERGRID – 40,000ckm)  765kV – 27,000 ckm  400kV – 38,000 ckm  220kV/132kV – 35,000 ckm  HVDC – 9,500 ckm  Substations : about 270,000 MVA (POWERGRID – 100,000 MVA) Expansion Programme – 12th Plan
  • 16. National Grid – A Continuing Process 27750 66000 0 20000 40000 60000 80000 2011-12 By 2016-17  National Grid comprises of Inter-State, Intra-State and Inter-regional transmission system  Cummulative Growth of Inter-regional capacity in MW Emerging National Grid
  • 17. 17 WR NR NER ER SR 6400 MW 10200 MW 8400 MW 6000 MW 1600 MW 5800 MW National Grid - XII Plan addition – 38,400 MW National Grid - Total by XII Plan – 66,000 MW Augmentation of IR Capacity in XII Plan
  • 19. Voltage (kV) 1977 1990 2000 2002 2012 2017-18 Year 220kV 400kV 500kV HVDC 765kV 800kV HVDC 1200kV 765kV D/C - AC World’s Highest Voltage level – Test station Charged in Oct.’12 World’s longest multi-terminal HVDC to harness renewable Hydro Power from North-east Pursuing Higher Voltage Levels
  • 20.  High Voltage line  Increase the capacity of trans. corridor through HSIL/re- conductoring with HTLS /Upgradation  Utilisation of existing transmission lines upto full thermal capacity – Series capacitors, SVC, FACTS  Optimization of Tower design – tall tower, multi-ckt. tower  GIS substation  EHVAC : 400kV  765kV  1200kV  HVDC : 500kV  800kV Technology being Adopted
  • 21. ROAD MAP FOR INDIAN POWER SYSTEM RoW (m) Capacity (MW) MW/m RoW 400kV S/c 52 500 9.6 400kV D/c 46 1000 21.8 765kV S/c 64 2500 39 765kV D/c 67 4000 60 800kV HVDC 69 6000 87 69 m 176 m High Power Intensity Corridor
  • 22. World’s longest multi-terminal ±800 kV HVDC under implementation from Biswanath Chariali, North- Eastern Region to Agra, Northern Region. Shall transmit power to the tune of 6000-8000 MW. 2000 km Agra Biswanath Chariali Implementing +800kV HVDC Bipole Link
  • 23. World’s highest voltage, 1200kV UHV AC, test charged at Bina, Madhya Pradesh in October 2012. Has been Developed Indigenously through Public Private Partnership (PPP) with 35 Indian manufacturers in open collaboration. Indigenous Development of 1200kV UHVAC
  • 25. Central Sector State Sector Private Sector Total 15220 (30%) 16732(30%) 23012(42%) 54964 26181 (30%) 15530(17%) 46825(53%) 88537 XI XII Change in Generation Profile
  • 26.  Long-term Open Access – Application Received : 218no. , 132,000MW – Granted : 148 No., 83,000 MW : Connectivity – Application Received : 188no. , 176,300MW – Granted : 84 No., 74,400 MW Short Term Open Access – 2012-13 : 32,000 transactions, 74BU energy Long Term Open Access / Connectivity
  • 27. S.No Corridor Ins. Capacity (MW) LTOA granted (MW) 1 HCPTC –I ( for IPP projects in Orissa) 10090 6080 2 HCPTC –II ( for IPP projects in Jharkhand) 3820 3510 3 HCPTC-III (for IPP projects in Sikkim) 2162 2162 4 HCTPC-IV ( for IPP projects in M.P & Chhattisgarh) 4370 3554 5 HCTPC –V ( for IPP projects in Chhattisgarh) 18270 16289 6 HCTPC –VI ( for IPP projects in Krishnapatnam) 4240 3516 7 HCTPC –VII ( for IPP projects in Tuticorin) 2520 2000 8 HCTPC –VIII ( for IPP projects in Srikakulam) 1320 1240.8 9 HCTPC –IX ( for IPP projects in SR, for transfer of power to WR/NR) 8446 7026 10 HCTPC –X ( for IPP projects in Vemagiri) 4568 4325 11 HCTPC –XI ( for IPP projects in Nagapattinam/ Cuddalore ) 2250 2137 Total 62,000 52,000 High Capacity Corridors
  • 31. 31 BOGRA SOUTH BHERAMARA NAOGAON NIAMATPUR FARRAKA SUBHASGRAM KATWA GOKARNA JEERAT KHULNA (SOUTH) BOTTAIL BAHARAMPUR CH. NAWABGANJ RAGHUNATHGANJ KAHALGAON SAGARDIGHI RAJSHAHI BAHARAMPUR ISHURDI NATORE KHEJURIA FARIDPUR BAGHABARI GHORASAL MADHOPUR SHAHJAD PABNA PUR SIRAJGANJ BOGRA INTERCONNECTION BETWEEN INDIA AND BANGLADESH GRIDS 400 kV 230 kV 132 kV THE PROJECT LEGEND BAKRESHWAR KOLAGHAT BANGLADESH INDIA 400kV D/c (400 KV) MALDA DHULIAN DURGAPUR Existing Under Constr. / Future JAYPURHAT BARAPUKURIA
  • 32. 32 India - Bhutan : Interconnection
  • 33. 33 India - Nepal : Interconnection
  • 34. 130 Kms 120 Kms 110 Kms Proposed Route for Interconnection Madurai-New Panaikulam New Anuradhapura Taliamannar Thirukketiswaram * 48 Kms Madurai India – Sri Lanka Interconnection
  • 35. ROAD MAP FOR INDIAN POWER SYSTEM  Issues concerning availability of RoW and same are becoming critical –  Resistance of people, terrains in areas of mountains and forest  Sector to grow from 228 GW to 600 GW in next 20 years – Even 765kV system may not be good enough. New methods have to be found out  Challenges to develop Transmission system to meet the requirement of power flow from anywhere to anywhere.  With increasing magnitude of power transmission, create new challenges of proper O&M Issues & Challenges