SlideShare a Scribd company logo
Lean Manufacturing Applications Implementation
Graduation Project
Presented by :
• Mostafa Saad Mostafa Mahmoud
• Mostafa Hassan Mostafa Kamal
• Ahmed Ayad Ibrahim
• Ahmed Samir Abdelaleem
• Kareem Montasser Abduallah
Supervised by: Dr. Ismail Zahran
• We were ambitious to gain a lot of experience in
reality projects, followed by the knowledge of how to
actually analyze and improve them.
• So, we found that Lean Manufacturing is the
best way to Achieve what we strive for.
• Lean is a mindset, or way of thinking, that uses a comprehensive
set of techniques that, when combined and matured, will allow you
to identify, reduce and then eliminate the eight wastes.
• It is achieved by simplifying and continuously improving all
processes and relationships in an environment of trust, respect
and full employee involvement.
• It is about people, simplicity, flow, visibility, partnerships and true
value as perceived by the customer.
Lean Techniques Applied
in Acrow
H20 Production Line
Overall Equipment Effectiveness (OEE)
World Class ValueMetric
90.00%AVAILABILITY
95.00%PERFORMANCE
99.90%QUALITY
85.00%OEE
Production Data
Shift Length : 7 hours & 30 minutes = 450 minutes
Meal Break : 30 minutes
Factory : Acrow Misr
Plant : 2
Cell : N
Machine : Press 250 Ton
Product : H20 Connection
Duration : During (March-April ) 2014
Ideal Run Rate : 16 ppm ( pieces per minute )
Total Pieces : 2750
Rejected Pieces : 50
Planned Production Time = Shift Length - Breaks = 450 - 30 = 420 minutes
Operating Time = Planned Production Time - Down Time = 420 - 220 = 200
minutes
Good Pieces = Total Pieces - Rejected Pieces = 2750 - 50 = 2700
Availability Operating Time /
Planned
Production Time
200/ 420 = 0.476 47.6 %
Performance ( Total Pieces /
Operating Time )
/ Ideal Run Rate
( 2750 / 200 ) / 16
= 0.86
86 %
Quality Good Pieces /
Total Pieces
2700 / 2750 = 0.98 98 %
Overall OEE Availability *
Performance *
Quality
0.476 * 0.86 * 0.98
= 0.40
40 %
OEE metric Losses example Solution
1.Availability 1. operator works on press 250
ton consumes a lot of time
moving containers and racks
inside and outside of the plant
and this is not related to his work
The Plant manager or supervisor must
make it clear to all of the operators the
role of each one and to make sure that
each operator do only his job without
interfering other tasks not related to his
main job.
2. Unloading of products on press
250 ton takes a lot of time
Suggestion is to make unloading process
become much easier by making a sliding
surface or a roller between unloading
container and the base of the press, so
that products slide easily in the
container.
3. Operator Moving outside of the
plant to bring supporting
materials
All of the supporting materials that
operator need during work must be
available with enough quantity and be
kept in place very close to related
machine before arrival of operator (e.g.
: oil , grease and inspection tools )
OEE metric losses Solution
2.Performance 1. Product flow stoppage Sometimes the flow of product
is affected due to stick of one
of the products between
cutting tool of press 200 ton ,
the solution is to make sure to
apply grease and oil on the
cutting tool to prevent the
sticking problem.
3.Quality 1. Product Misfeeds This problem depends on level
of operator training. The
solution is more Training and
awareness of line balance
theory
Mapping the Value Stream for H20
Production Line
Customer Demand:
2200 pieces per Day
(Takt Time 24.5 secs.)
Customer
Shear
Value Add: 90 seconds
4
Packing
Value Add: 60 minutes
2
Production planning
Supplier
3 weeks
schedule
Monthly
schedule
90 seconds
900 minutes
90 seconds
900 minutes
5 seconds
60 minutes
5700 seconds
150 minutes
35 seconds
60 minutes
3600 seconds
Lead Time = 2229 minutes
VA / T = 9520 seconds
RM = 0 seconds
WIP = 2229 minutes
FG = 0 seconds
Steel sheets
Press 63
(Cut)
Value Add: 90 seconds
1
Press 250
(Cut+Stamp)
Value Add: 45 seconds
1
Press 160
(Forming)
German
Value Add: 5 seconds
1
Assembly
Value Add: 35 seconds
3
Surface
Treatment
Value Add: 95 minutes
3
Body
2400 pcs.
1 days
Leg
4800 pcs.
1 days
Body
2400 pcs.
1 days
Body
2400 pcs.
1 hours
Body 3500 pcs.
+
Leg 7000 pcs.
2.5 hours
Body+Leg
2700 pcs.
1 hours
Leg
4800 pcs.
1 days
Twice a week
Daily
Press 160
(Forming)
Italian
Value Add: 4 seconds
1
Leg
4800 pcs.
1 hoursC/T 8 hrs.
2 shifts
Av. 64.16%
C/T 8 hrs
2 shifts
Av. 42.1%
C/T 8 hrs
2 shifts
Av. 48.3%
C/T 8 hrs.
2 shifts
Av. 46.25%
C/T 8 hrs.
2 shifts
Av. 46.25%
Monthly Schedule
Value-adding Activities (V/A)
 Cutting steel sheets on the shear machine into leg or body
sheets.
 Cutting, stamping and forming each body sheet into 10
parts.
 Cutting and forming each leg sheet into 14 parts.
 Treating & galvanizing the surface of parts.
 Assembling body with 2 legs by a connecting bolt.
 Packing H20 products to prepare them for transportation.
Non Value-adding Activities (NV/A)
 Storing raw material before production.
 Long inventory times between stations.
 Adjusting pieces manually on the machines causes defects
on the parts.
 It takes one third of shift time to move parts from surface
treatment station to assembly and prepare them.
Essential Non Value-adding Activities
 Raw material transportation from suppliers depends on
MRP rather than uniform supply.
 Machines used to make H20 products take a very long time,
consumes a lot of energy and costs too much labor while it
can be done on one machine.
 Surface treating of H20 passes through many stages which
consumes a lot of time.
After defining H20 activities as
V/A, NV/A & Essential NV/A … We
used the following tools to reduce
forms of waste along H20
production line.
What’s 5S !
Before After
III.I. Sorting(Seiri)
Before After
III.I. Sorting Cont,
Before After
III.I. Sorting Cont,
SORT ACTIVITY DESCRIPTIONS SCORE
Only the required spare parts, materials, WIP, etc. are present at the workstation. Items
not required to make the current product are removed from the workplace. 0
Only the required tools are present at the workstation. Items not required to make the
current product are removed from the workplace. 0
Only the required paperwork is present at the workstation. Out-dated or otherwise
unnecessary posters, memos, announcements, reports, etc. are removed from the
workplace.
0
Only the required equipment is present at the workstation. All obsolete, broken or
unnecessary equipment, shelves, lockers, workbenches, etc. not required to make the
current product is removed from the workplace.
0
Only the required furniture is present at the workstation. All broken or unnecessary chairs,
shelves, lockers, workbenches, etc. not required to make the current product is removed
from the workplace.
0
Tripping dangers such as electrical cables, etc. are removed from standing/walking areas.
0
III.II. Set in order(Seiton)
- For Pipes we suggest that they should be moved to the space available in
front of the factory 2 (10*3 m^2).
- For C-shape we suggest that they should be moved to the area of work
assigned to them which is the region for grinding and welding. (6*2 m^2 for
each cell)
III.II. Set in order cont,
- For scrape they must be taken away from the machines areas regularly
into space behind factory 3 (22 *2 m^2).
- For re-work parts must be taken away from the press 250 area regularly to
the space in front of factory 2.
SET IN ORDER ACTIVITY DESCRIPTIONS SCORE
Locations for containers, boxes, bins, WIP, materials, etc. is clearly defined by painted lines and properly
labeled (part number, quantity, etc.).
0
Tools have a designated storage location that is within reach of the operator. The location is properly
labeled and tools can easily be identified if absent.
0
Paperwork is properly labeled and has a clearly defined and labeled location that is visible to the
operators and away from work surfaces.
0
Equipment is clearly identified (numbered, named, color coded, etc.) and placed in a properly identified
location. Critical maintenance points are clearly marked.
0
Furniture is clearly identified (numbered, named, color coded, etc.) and placed in a properly identified
location.
0
Work areas requiring personal protective equipment are clearly labeled. 0
Stop switches and breakers are highly visible and located for easy access in case of emergency.
0
Fire hoses, fire extinguishers and other emergency equipment are prominently displayed and are
unobstructed.
0
Working conditions are ergonomically friendly. Tools are stored at appropriate heights, lift assist devices
are provided where necessary, etc. 0
The workplace layout accommodates easy exit in case of emergency.
0
Walkways and vehicle paths are clearly identified and unobstructed. Exits are clearly labeled and
unobstructed.
0
III.III. Systematic clean (Seiso)
III.IV. Standardize(Seiketsu)
STANDARDIZE ACTIVITY DESCRIPTIONS SCORE
Tools, equipment, paperwork, furniture, etc. are stored neatly in designated areas and are
returned immediately after each use.
0
Documents are labeled clearly as to contents and responsibility for control and revision.
The date and revision number are clearly visible. 0
Equipment maintenance records are visible and clearly state when maintenance last
occurred and when next maintenance is scheduled.
0
Product waste (e.g. shavings, containers, liquids, wrappers, etc.) is consistently and often
cleaned up and removed from the workplace.
0
Preventive measures have been implemented to ensure the workplace meets 5S guidelines
(e.g. systems that do not allow waste to accumulate such as containers to collect product
debris from machines).
0
The results of the previous audit are posted and clearly visible to the entire team. 0
Areas for improvement identified during the previous audit have been completed. 0
The work environment satisfies the requirements of the work being performed. Lighting
(brightness and color), air quality, temperature, etc. 0
III.V. SUSTAIN(Shitsuke)
SUSTAIN ACTIVITY DESCRIPTIONS SCORE
A member of Management has participated in a 5S activity such as an audit or
other activity within the past 3 audit periods. 0
Recognition is given to teams who get involved in 5S activities. 0
Time and resources are allocated to 5S activities (e.g. designated daily/weekly
clean-up time, 5S team leader, etc.) 0
All operators, team leaders, supervisors, etc. are assigned 5S activities to be
completed at least once/week. 0
The team took the initiative to make improvements to the workplace that was
not identified during the last 5S audit. 0
Concept that says all setups should and can take less than 10 minutes
Change Over & Change Over Time
Changeover time is the total elapsed time during Changeover process
between the last unit of good production of the previous run, at
normal line efficiency, to the first unit of good production of the
succeeding run, at full line efficiency.
Mold Change
Colour Change
Mold change Inspect/Adjust
Setup
Time
1st Piece Time
(good or bad)
1st Good
Piece Time
0
Last good part
Internal & External set-up activities
All Setup Activities Run
III IE E EE Run
Externals Internals Run
ExternalsPost-setup
externals
Internal set-up activities
Operations that must be performed while the machine/process is stopped
External set-up activities
Operations that can be performed while the machine/process is running
Preliminary
Stage
First Stage
Second
Stage
Third Stage Final Stage
CHANGEOVER RECORD
DATE SHIFT FROM TO
TIME
(MIN)
COMMENTS
20-march 2014 1 1:3 1:32 2
changes in the journey of cutting tool and the M/C die’s
moving part
1 1:32 1:34 2 Nuts are removed
1 1:34 1:44 10 die disconnected
1 1:44 1:47 3 New die transformed with overhead lift
1 1:47 1:54 7 die stand installation (from Scrap)
1 1:54 2:09 15 new die installation
Total Time 39
0. Preliminary Stage: Internal and External Setups are Mixed.
1. First Stage: Separate Internal and External Setups.
2. Second Stage: Convert Internal Setup to External Setup.
3. Third Stage: Streamline both Internal and External Setups.
The M/C operator can call another Technical operator to help him to make
(Die Disconnect) that another operator who observe time shift or anyone
has done his daily work.
Time is critical for productivity, capacity and cost. Here, the
product's changeover was reduced from 36 minutes to consistently
below 8.5 minutes, a difference of 27.5 minutes
Final Stage: Document Internal and External Procedures
What’s kaizen !
• Project Name: Acrow Event.
• Event Location: Factory 2, H20 production line.
• Process: work standardization in the production line.
Kaizen Event
Kaizen team selection:
• Team sponsor - champion: factory director
• Team leader - process owner: production line engineer
• Team member: hoisting crane operator
• Team member: shear operator
• Team member: press 160 tons operator
• Team member: Press 250 tons operator
• Team member: Press 63 Ton operator
• Team member: Clark left operator
• Kaizen facilitator: foreman
Event scheduling (5 days)
• Day of learning
Day 1
• Day of Discovery & Developing
Improvement IdeasDay 2
• Day of Improvement &Creating the
New processDay 3
• Day of Design Implementation &
DocumentationDay 4
• Day of Celebration &Results Schedule
Day 5
What’s Production Leveling (Heijunka) !
• Heijunka: Is the leveling of production by both volume and
product mix. It does not build products according to the
actual flow of customer orders, which can swing up and down
wildly, but takes the total volume of orders in a period and
levels them out so the same amount and mix are being made
each day
Name of product Average monthly
demand
Symbol
1. Corner Splice 45 × 45 50
2. Corner Splice 60 × 60 500 A
3. Pivot Splice 42X42 CM (double) 50
4. Splice 60 Cm Double 2100 B
5. Splice 90 Cm Double 70
6. Universal Corner Angle Tie (New)
1400 C
We worked on different products that produced from
press 200 ton
Before Leveling
0
500
1000
1500
2000
2500
Demand
Time
Corner Splice 60 × 60
Splice 60 Cm Double
Universal Corner Angle Tie
(New)
After Leveling
0
500
1000
1500
2000
2500
Demand
Time
Corner Splice 60 × 60
Splice 60 Cm Double
Universal Corner Angle Tie
(New)
Setup a model for determining leveling production schedule
according to volume and mix of the 3 products. (Corner Splice 60 × 60
, Splice 60 Cm Double , Universal Corner Angle Tie (New) ).
We will use mixed model sequencing as a leveling model.
Steps of mixed model sequencing are as follows:
1. Determine the total monthly demand for each type of product
i. Corner Splice 60 × 60 = 500 units
ii. Splice 60 Cm Double = 2100 units
iii. Universal Corner Angle Tie (New) = 1400 units
2. Calculate the weekly requirement for each product type
i. Corner Splice 60 × 60 = 500/4 = 125 units
ii. Splice 60 Cm Double = 2100/4 = 525 units
iii. Universal Corner Angle Tie (New) = 1400/4= 350 units
iv. Total Weekly production= 1000 units
Steps of mixed model sequencing Cont.:
3. Compute the build ratio and the production frequency for each
product type by determine the largest integer that Divides evenly
into weekly requirements of all products in this case (25) but I have
chosen for the frequency to be (5) instead of (25) since 25 times as a
frequency is a large number and more errors in changeover will
occur if applied.
i. Corner Splice 60 × 60 = 125/5 = 25 units
ii. Splice 60 Cm Double = 525/5 = 105 units
iii. Universal Corner Angle Tie (New) = 350/5 = 70 units
iv. Production frequency = 1000/5 = 200 units
Steps of mixed model sequencing Cont.:
4. Determine the build frequency:
• Corner Splice 60 × 60 –25 units will be produced every
200 units
• Splice 60 Cm Double –105 units will be produced every
200 units
• Universal Corner Angle Tie (New) - 70 units will be
produced every 200 units
Steps of mixed model sequencing Cont.:
5. Set a build schedule:
(BBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBB
BBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBAAAAAAAAAAAAAAAAAA
AAAAAAACCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCC
CCCCCCCCCCCC)
The above schedule will be executed 5 times a week .
Process Capability:
 It's a tool which is used to check the conformance of process
output to the customer requirements specifications to:
* Manage variations in the process output
* Measure the uniformity of the process
* Be compared with another process or competitor.
4.3754.2504.1254.0003.8753.7503.625
LSL Target USL
Total N 100
Subgroup size 100
Mean 3.9548
StDev (overall) 0.089437
StDev (within) 0.089663
Process Characterization
Cp 1.49
Cpk 1.32
Z.Bench 3.95
% Out of spec (expected) 0.00
PPM (DPMO) (expected) 38
Actual (overall)
Pp 1.49
Ppk 1.32
Z.Bench 3.96
% Out of spec (observed) 0.00
% Out of spec (expected) 0.00
PPM (DPMO) (observed) 0
PPM (DPMO) (expected) 37
Potential (within)
Capability Statistics
Actual (overall) capability is what the customer experiences.
shifts and drifts were eliminated.
Potential (within) capability is what could be achieved if process
Capability Analysis for C1
Process Performance Report
Capability Histogram
Are the data inside the limits and close to the target?
1st Sample Capability Analysis
4.324.204.083.963.843.723.60
LSL Target USL
Total N 100
Subgroup size 100
Mean 3.9615
StDev (overall) 0.076136
StDev (within) 0.076329
Process Characterization
Cp 1.75
Cpk 1.58
Z.Bench 4.74
% Out of spec (expected) 0.00
PPM (DPMO) (expected) 1
Actual (overall)
Pp 1.75
Ppk 1.58
Z.Bench 4.75
% Out of spec (observed) 0.00
% Out of spec (expected) 0.00
PPM (DPMO) (observed) 0
PPM (DPMO) (expected) 1
Potential (within)
Capability Statistics
Actual (overall) capability is what the customer experiences.
shifts and drifts were eliminated.
Potential (within) capability is what could be achieved if process
Capability Analysis for C1
Process Performance Report
Capability Histogram
Are the data inside the limits and close to the target?
2nd Sample Capability Analysis
4.3754.2504.1254.0003.8753.7503.625
Before
LSL Target USL
After
Process Characterization
Total N 100 100
Subgroup size 100 100
Mean 3.9548 3.9615 0.0067
StDev (overall) 0.089437 0.076136 -0.013301
StDev (within) 0.089663 0.076329 -0.013334
Before After Change
Capability Statistics
Cp 1.49 1.75 0.26
Cpk 1.32 1.58 0.26
Z.Bench 3.95 4.74 0.78
% Out of spec (exp) 0.00 0.00 -0.00
PPM (DPMO) (exp) 38 1 -37
Actual (overall)
Pp 1.49 1.75 0.26
Ppk 1.32 1.58 0.26
Z.Bench 3.96 4.75 0.78
% Out of spec (obs) 0.00 0.00 0.00
% Out of spec (exp) 0.00 0.00 -0.00
PPM (DPMO) (obs) 0 0 0
PPM (DPMO) (exp) 37 1 -36
Potential (within)
Before After Change
Actual (overall) capability is what the customer experiences.
process shifts and drifts were eliminated.
Potential (within) capability is what could be achieved if
Before/After Capability Comparison for before vs after
Process Performance Report
Capability Histogram
Are the data inside the limits and close to the target?
Comparing 1st and 2nd Samples Capabilities
Lean Manufacturing Applications Implementation

More Related Content

What's hot

Industrial Attachment presentation at Impress Newtex Composite Textile Ltd.
 Industrial Attachment presentation at Impress Newtex Composite Textile Ltd. Industrial Attachment presentation at Impress Newtex Composite Textile Ltd.
Industrial Attachment presentation at Impress Newtex Composite Textile Ltd.
Mushfiqur Rahman
 
Study on Exports T-Shirts Manufacturing Units in Tirupur
Study on Exports T-Shirts Manufacturing Units in TirupurStudy on Exports T-Shirts Manufacturing Units in Tirupur
Study on Exports T-Shirts Manufacturing Units in Tirupur
Abhishek Raj
 
PURCHINEERING through MISUMISATION: Everything from a Single Source at Indust...
PURCHINEERING through MISUMISATION: Everything from a Single Source at Indust...PURCHINEERING through MISUMISATION: Everything from a Single Source at Indust...
PURCHINEERING through MISUMISATION: Everything from a Single Source at Indust...
MISUMI Europa GmbH
 
Cleaning & Disinfecting
Cleaning & DisinfectingCleaning & Disinfecting
Cleaning & Disinfecting
SS Engineers & Consultants
 
Process planning and cost estimation unit v
Process planning and cost estimation  unit   vProcess planning and cost estimation  unit   v
Process planning and cost estimation unit v
s Kumaravel
 
Kleenol Nigeria Limited - Company Profile
Kleenol Nigeria Limited - Company ProfileKleenol Nigeria Limited - Company Profile
Kleenol Nigeria Limited - Company Profile
Oluwole Awoniyi
 
Industrial Visit at Youngone (CEPZ) LTd. by NITER student
Industrial Visit at Youngone (CEPZ) LTd. by NITER studentIndustrial Visit at Youngone (CEPZ) LTd. by NITER student
Industrial Visit at Youngone (CEPZ) LTd. by NITER student
SalmanHossainBhuiyan
 
Hitta en inhemsk Städfirma
Hitta en inhemsk StädfirmaHitta en inhemsk Städfirma
Hitta en inhemsk Städfirma
Holm69
 
Surneha Services, Gujarat, Bag Closer & Sealer Machine
Surneha Services, Gujarat, Bag Closer & Sealer MachineSurneha Services, Gujarat, Bag Closer & Sealer Machine
Surneha Services, Gujarat, Bag Closer & Sealer Machine
IndiaMART InterMESH Limited
 
Best Package Boiler Manufacturer in Punjab
Best Package Boiler Manufacturer in PunjabBest Package Boiler Manufacturer in Punjab
Best Package Boiler Manufacturer in Punjab
Neha Sharma
 
Smeg laboratory glassware washers
Smeg laboratory glassware washersSmeg laboratory glassware washers
Smeg laboratory glassware washers
ForrayFerenc
 
Cleaning Combustible Dust
Cleaning Combustible DustCleaning Combustible Dust
Cleaning Combustible Dust
Jon Barrett
 
Noman Weaving Mills Ltd Industrial Report by Md.Mehedi Hassan Rifat
Noman Weaving Mills Ltd Industrial Report by Md.Mehedi Hassan RifatNoman Weaving Mills Ltd Industrial Report by Md.Mehedi Hassan Rifat
Noman Weaving Mills Ltd Industrial Report by Md.Mehedi Hassan Rifat
Md.Mehedi Hassan
 
Productivity Improvement in a Sewing Line Through Line Balancing in a Garment...
Productivity Improvement in a Sewing Line Through Line Balancing in a Garment...Productivity Improvement in a Sewing Line Through Line Balancing in a Garment...
Productivity Improvement in a Sewing Line Through Line Balancing in a Garment...
ijtsrd
 
Project Report on Textile Industrial Engineering
Project Report on Textile Industrial EngineeringProject Report on Textile Industrial Engineering
Project Report on Textile Industrial Engineering
Amanuzzaman Aman
 
Brandix Apparel India - Apparel Internship
Brandix Apparel India - Apparel InternshipBrandix Apparel India - Apparel Internship
Brandix Apparel India - Apparel Internship
Abhishek Raj
 
Knit Dyeing Training Report in Arvind Ltd. by SujayMajumder Manojit Barman
Knit Dyeing Training Report in Arvind Ltd. by SujayMajumder Manojit BarmanKnit Dyeing Training Report in Arvind Ltd. by SujayMajumder Manojit Barman
Knit Dyeing Training Report in Arvind Ltd. by SujayMajumder Manojit Barman
MANOJIT BARMAN
 
Cost of quality
Cost of qualityCost of quality
Cost of quality
Shaheen Sardar
 

What's hot (19)

Industrial Attachment presentation at Impress Newtex Composite Textile Ltd.
 Industrial Attachment presentation at Impress Newtex Composite Textile Ltd. Industrial Attachment presentation at Impress Newtex Composite Textile Ltd.
Industrial Attachment presentation at Impress Newtex Composite Textile Ltd.
 
Study on Exports T-Shirts Manufacturing Units in Tirupur
Study on Exports T-Shirts Manufacturing Units in TirupurStudy on Exports T-Shirts Manufacturing Units in Tirupur
Study on Exports T-Shirts Manufacturing Units in Tirupur
 
PURCHINEERING through MISUMISATION: Everything from a Single Source at Indust...
PURCHINEERING through MISUMISATION: Everything from a Single Source at Indust...PURCHINEERING through MISUMISATION: Everything from a Single Source at Indust...
PURCHINEERING through MISUMISATION: Everything from a Single Source at Indust...
 
Cleaning & Disinfecting
Cleaning & DisinfectingCleaning & Disinfecting
Cleaning & Disinfecting
 
Process planning and cost estimation unit v
Process planning and cost estimation  unit   vProcess planning and cost estimation  unit   v
Process planning and cost estimation unit v
 
Kleenol Nigeria Limited - Company Profile
Kleenol Nigeria Limited - Company ProfileKleenol Nigeria Limited - Company Profile
Kleenol Nigeria Limited - Company Profile
 
Industrial Visit at Youngone (CEPZ) LTd. by NITER student
Industrial Visit at Youngone (CEPZ) LTd. by NITER studentIndustrial Visit at Youngone (CEPZ) LTd. by NITER student
Industrial Visit at Youngone (CEPZ) LTd. by NITER student
 
Sai JM Hygiene Cleaning and Services
Sai JM Hygiene Cleaning and ServicesSai JM Hygiene Cleaning and Services
Sai JM Hygiene Cleaning and Services
 
Hitta en inhemsk Städfirma
Hitta en inhemsk StädfirmaHitta en inhemsk Städfirma
Hitta en inhemsk Städfirma
 
Surneha Services, Gujarat, Bag Closer & Sealer Machine
Surneha Services, Gujarat, Bag Closer & Sealer MachineSurneha Services, Gujarat, Bag Closer & Sealer Machine
Surneha Services, Gujarat, Bag Closer & Sealer Machine
 
Best Package Boiler Manufacturer in Punjab
Best Package Boiler Manufacturer in PunjabBest Package Boiler Manufacturer in Punjab
Best Package Boiler Manufacturer in Punjab
 
Smeg laboratory glassware washers
Smeg laboratory glassware washersSmeg laboratory glassware washers
Smeg laboratory glassware washers
 
Cleaning Combustible Dust
Cleaning Combustible DustCleaning Combustible Dust
Cleaning Combustible Dust
 
Noman Weaving Mills Ltd Industrial Report by Md.Mehedi Hassan Rifat
Noman Weaving Mills Ltd Industrial Report by Md.Mehedi Hassan RifatNoman Weaving Mills Ltd Industrial Report by Md.Mehedi Hassan Rifat
Noman Weaving Mills Ltd Industrial Report by Md.Mehedi Hassan Rifat
 
Productivity Improvement in a Sewing Line Through Line Balancing in a Garment...
Productivity Improvement in a Sewing Line Through Line Balancing in a Garment...Productivity Improvement in a Sewing Line Through Line Balancing in a Garment...
Productivity Improvement in a Sewing Line Through Line Balancing in a Garment...
 
Project Report on Textile Industrial Engineering
Project Report on Textile Industrial EngineeringProject Report on Textile Industrial Engineering
Project Report on Textile Industrial Engineering
 
Brandix Apparel India - Apparel Internship
Brandix Apparel India - Apparel InternshipBrandix Apparel India - Apparel Internship
Brandix Apparel India - Apparel Internship
 
Knit Dyeing Training Report in Arvind Ltd. by SujayMajumder Manojit Barman
Knit Dyeing Training Report in Arvind Ltd. by SujayMajumder Manojit BarmanKnit Dyeing Training Report in Arvind Ltd. by SujayMajumder Manojit Barman
Knit Dyeing Training Report in Arvind Ltd. by SujayMajumder Manojit Barman
 
Cost of quality
Cost of qualityCost of quality
Cost of quality
 

Similar to Lean Manufacturing Applications Implementation

Application Of Workstudy
Application Of WorkstudyApplication Of Workstudy
Application Of Workstudy
bejayrocks
 
MSE 507 San Fernando Valley Lattet_ (5S)
MSE 507 San Fernando Valley Lattet_ (5S)MSE 507 San Fernando Valley Lattet_ (5S)
MSE 507 San Fernando Valley Lattet_ (5S)Viralkumar Jayswal
 
Designing Facility Layout and Effective Material Handling for a Ceramic Insul...
Designing Facility Layout and Effective Material Handling for a Ceramic Insul...Designing Facility Layout and Effective Material Handling for a Ceramic Insul...
Designing Facility Layout and Effective Material Handling for a Ceramic Insul...
IRJET Journal
 
Addis Ababa City Administration Technical, Vocational, Education And Training...
Addis Ababa City Administration Technical, Vocational, Education And Training...Addis Ababa City Administration Technical, Vocational, Education And Training...
Addis Ababa City Administration Technical, Vocational, Education And Training...
Haileyesus Wondwossen
 
Production & operations management
Production & operations managementProduction & operations management
Production & operations management
Harold B. Duran, LCB
 
Operations Management power point Chapter Five
Operations Management power point Chapter FiveOperations Management power point Chapter Five
Operations Management power point Chapter Five
AYNETUTEREFE1
 
4AD15ME042.pptx
4AD15ME042.pptx4AD15ME042.pptx
4AD15ME042.pptx
MrHAD
 
Layout and flow by sir taj mohammad tamkeen
Layout and flow by sir taj mohammad tamkeenLayout and flow by sir taj mohammad tamkeen
Layout and flow by sir taj mohammad tamkeen
Taj Mohammad Tamkeen
 
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...
Karina Islam
 
Micro Project - Design of Can Manufacturing Facility
Micro Project - Design of Can Manufacturing FacilityMicro Project - Design of Can Manufacturing Facility
Micro Project - Design of Can Manufacturing Facility
Amr El-Ganainy
 
Pen facility layout
Pen facility layoutPen facility layout
Pen facility layout
mohmedx
 
Effective shop floor oranization
Effective shop floor oranizationEffective shop floor oranization
Effective shop floor oranization
Colin Porter
 
Final Project 541
Final Project 541Final Project 541
Final Project 541voigt18
 
IMPLEMENTATION OF LEAN TOOLS AND EGONOMIC ASPECTS IN THE DESIGN OF A CARAVAN
IMPLEMENTATION OF LEAN TOOLS AND EGONOMIC ASPECTS IN THE DESIGN OF A CARAVANIMPLEMENTATION OF LEAN TOOLS AND EGONOMIC ASPECTS IN THE DESIGN OF A CARAVAN
IMPLEMENTATION OF LEAN TOOLS AND EGONOMIC ASPECTS IN THE DESIGN OF A CARAVAN
IRJET Journal
 
Process Selection and Facility layout.ppt
Process Selection and Facility layout.pptProcess Selection and Facility layout.ppt
Process Selection and Facility layout.ppt
SandipanMaji3
 
Application of value stream mapping tool to reduce wastes in bearing industry
Application of value stream mapping tool to reduce wastes in bearing industryApplication of value stream mapping tool to reduce wastes in bearing industry
Application of value stream mapping tool to reduce wastes in bearing industry
ijmech
 

Similar to Lean Manufacturing Applications Implementation (20)

Application Of Workstudy
Application Of WorkstudyApplication Of Workstudy
Application Of Workstudy
 
MSE 507 San Fernando Valley Lattet_ (5S)
MSE 507 San Fernando Valley Lattet_ (5S)MSE 507 San Fernando Valley Lattet_ (5S)
MSE 507 San Fernando Valley Lattet_ (5S)
 
Designing Facility Layout and Effective Material Handling for a Ceramic Insul...
Designing Facility Layout and Effective Material Handling for a Ceramic Insul...Designing Facility Layout and Effective Material Handling for a Ceramic Insul...
Designing Facility Layout and Effective Material Handling for a Ceramic Insul...
 
Addis Ababa City Administration Technical, Vocational, Education And Training...
Addis Ababa City Administration Technical, Vocational, Education And Training...Addis Ababa City Administration Technical, Vocational, Education And Training...
Addis Ababa City Administration Technical, Vocational, Education And Training...
 
Production & operations management
Production & operations managementProduction & operations management
Production & operations management
 
Operations Management power point Chapter Five
Operations Management power point Chapter FiveOperations Management power point Chapter Five
Operations Management power point Chapter Five
 
4AD15ME042.pptx
4AD15ME042.pptx4AD15ME042.pptx
4AD15ME042.pptx
 
Layout and flow by sir taj mohammad tamkeen
Layout and flow by sir taj mohammad tamkeenLayout and flow by sir taj mohammad tamkeen
Layout and flow by sir taj mohammad tamkeen
 
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...
 
Micro Project - Design of Can Manufacturing Facility
Micro Project - Design of Can Manufacturing FacilityMicro Project - Design of Can Manufacturing Facility
Micro Project - Design of Can Manufacturing Facility
 
Pen facility layout
Pen facility layoutPen facility layout
Pen facility layout
 
Effective shop floor oranization
Effective shop floor oranizationEffective shop floor oranization
Effective shop floor oranization
 
Final Project 541
Final Project 541Final Project 541
Final Project 541
 
IMPLEMENTATION OF LEAN TOOLS AND EGONOMIC ASPECTS IN THE DESIGN OF A CARAVAN
IMPLEMENTATION OF LEAN TOOLS AND EGONOMIC ASPECTS IN THE DESIGN OF A CARAVANIMPLEMENTATION OF LEAN TOOLS AND EGONOMIC ASPECTS IN THE DESIGN OF A CARAVAN
IMPLEMENTATION OF LEAN TOOLS AND EGONOMIC ASPECTS IN THE DESIGN OF A CARAVAN
 
Process Selection and Facility layout.ppt
Process Selection and Facility layout.pptProcess Selection and Facility layout.ppt
Process Selection and Facility layout.ppt
 
Application of value stream mapping tool to reduce wastes in bearing industry
Application of value stream mapping tool to reduce wastes in bearing industryApplication of value stream mapping tool to reduce wastes in bearing industry
Application of value stream mapping tool to reduce wastes in bearing industry
 
Pmm
PmmPmm
Pmm
 
SMT Sales 2011
SMT Sales 2011SMT Sales 2011
SMT Sales 2011
 
SMT 2011
SMT 2011SMT 2011
SMT 2011
 
SMT 2011
SMT  2011SMT  2011
SMT 2011
 

Recently uploaded

Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
PrashantGoswami42
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
Kamal Acharya
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
Kamal Acharya
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
ssuser9bd3ba
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 

Recently uploaded (20)

Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 

Lean Manufacturing Applications Implementation

  • 1. Lean Manufacturing Applications Implementation Graduation Project
  • 2. Presented by : • Mostafa Saad Mostafa Mahmoud • Mostafa Hassan Mostafa Kamal • Ahmed Ayad Ibrahim • Ahmed Samir Abdelaleem • Kareem Montasser Abduallah Supervised by: Dr. Ismail Zahran
  • 3. • We were ambitious to gain a lot of experience in reality projects, followed by the knowledge of how to actually analyze and improve them. • So, we found that Lean Manufacturing is the best way to Achieve what we strive for.
  • 4. • Lean is a mindset, or way of thinking, that uses a comprehensive set of techniques that, when combined and matured, will allow you to identify, reduce and then eliminate the eight wastes. • It is achieved by simplifying and continuously improving all processes and relationships in an environment of trust, respect and full employee involvement. • It is about people, simplicity, flow, visibility, partnerships and true value as perceived by the customer.
  • 5.
  • 6. Lean Techniques Applied in Acrow H20 Production Line
  • 7.
  • 10. Production Data Shift Length : 7 hours & 30 minutes = 450 minutes Meal Break : 30 minutes Factory : Acrow Misr Plant : 2 Cell : N Machine : Press 250 Ton Product : H20 Connection Duration : During (March-April ) 2014 Ideal Run Rate : 16 ppm ( pieces per minute ) Total Pieces : 2750 Rejected Pieces : 50
  • 11. Planned Production Time = Shift Length - Breaks = 450 - 30 = 420 minutes Operating Time = Planned Production Time - Down Time = 420 - 220 = 200 minutes Good Pieces = Total Pieces - Rejected Pieces = 2750 - 50 = 2700 Availability Operating Time / Planned Production Time 200/ 420 = 0.476 47.6 % Performance ( Total Pieces / Operating Time ) / Ideal Run Rate ( 2750 / 200 ) / 16 = 0.86 86 % Quality Good Pieces / Total Pieces 2700 / 2750 = 0.98 98 % Overall OEE Availability * Performance * Quality 0.476 * 0.86 * 0.98 = 0.40 40 %
  • 12. OEE metric Losses example Solution 1.Availability 1. operator works on press 250 ton consumes a lot of time moving containers and racks inside and outside of the plant and this is not related to his work The Plant manager or supervisor must make it clear to all of the operators the role of each one and to make sure that each operator do only his job without interfering other tasks not related to his main job. 2. Unloading of products on press 250 ton takes a lot of time Suggestion is to make unloading process become much easier by making a sliding surface or a roller between unloading container and the base of the press, so that products slide easily in the container. 3. Operator Moving outside of the plant to bring supporting materials All of the supporting materials that operator need during work must be available with enough quantity and be kept in place very close to related machine before arrival of operator (e.g. : oil , grease and inspection tools )
  • 13. OEE metric losses Solution 2.Performance 1. Product flow stoppage Sometimes the flow of product is affected due to stick of one of the products between cutting tool of press 200 ton , the solution is to make sure to apply grease and oil on the cutting tool to prevent the sticking problem. 3.Quality 1. Product Misfeeds This problem depends on level of operator training. The solution is more Training and awareness of line balance theory
  • 14.
  • 15. Mapping the Value Stream for H20 Production Line
  • 16. Customer Demand: 2200 pieces per Day (Takt Time 24.5 secs.) Customer Shear Value Add: 90 seconds 4 Packing Value Add: 60 minutes 2 Production planning Supplier 3 weeks schedule Monthly schedule 90 seconds 900 minutes 90 seconds 900 minutes 5 seconds 60 minutes 5700 seconds 150 minutes 35 seconds 60 minutes 3600 seconds Lead Time = 2229 minutes VA / T = 9520 seconds RM = 0 seconds WIP = 2229 minutes FG = 0 seconds Steel sheets Press 63 (Cut) Value Add: 90 seconds 1 Press 250 (Cut+Stamp) Value Add: 45 seconds 1 Press 160 (Forming) German Value Add: 5 seconds 1 Assembly Value Add: 35 seconds 3 Surface Treatment Value Add: 95 minutes 3 Body 2400 pcs. 1 days Leg 4800 pcs. 1 days Body 2400 pcs. 1 days Body 2400 pcs. 1 hours Body 3500 pcs. + Leg 7000 pcs. 2.5 hours Body+Leg 2700 pcs. 1 hours Leg 4800 pcs. 1 days Twice a week Daily Press 160 (Forming) Italian Value Add: 4 seconds 1 Leg 4800 pcs. 1 hoursC/T 8 hrs. 2 shifts Av. 64.16% C/T 8 hrs 2 shifts Av. 42.1% C/T 8 hrs 2 shifts Av. 48.3% C/T 8 hrs. 2 shifts Av. 46.25% C/T 8 hrs. 2 shifts Av. 46.25% Monthly Schedule
  • 17. Value-adding Activities (V/A)  Cutting steel sheets on the shear machine into leg or body sheets.  Cutting, stamping and forming each body sheet into 10 parts.  Cutting and forming each leg sheet into 14 parts.  Treating & galvanizing the surface of parts.  Assembling body with 2 legs by a connecting bolt.  Packing H20 products to prepare them for transportation.
  • 18. Non Value-adding Activities (NV/A)  Storing raw material before production.  Long inventory times between stations.  Adjusting pieces manually on the machines causes defects on the parts.  It takes one third of shift time to move parts from surface treatment station to assembly and prepare them.
  • 19. Essential Non Value-adding Activities  Raw material transportation from suppliers depends on MRP rather than uniform supply.  Machines used to make H20 products take a very long time, consumes a lot of energy and costs too much labor while it can be done on one machine.  Surface treating of H20 passes through many stages which consumes a lot of time.
  • 20. After defining H20 activities as V/A, NV/A & Essential NV/A … We used the following tools to reduce forms of waste along H20 production line.
  • 21.
  • 26. SORT ACTIVITY DESCRIPTIONS SCORE Only the required spare parts, materials, WIP, etc. are present at the workstation. Items not required to make the current product are removed from the workplace. 0 Only the required tools are present at the workstation. Items not required to make the current product are removed from the workplace. 0 Only the required paperwork is present at the workstation. Out-dated or otherwise unnecessary posters, memos, announcements, reports, etc. are removed from the workplace. 0 Only the required equipment is present at the workstation. All obsolete, broken or unnecessary equipment, shelves, lockers, workbenches, etc. not required to make the current product is removed from the workplace. 0 Only the required furniture is present at the workstation. All broken or unnecessary chairs, shelves, lockers, workbenches, etc. not required to make the current product is removed from the workplace. 0 Tripping dangers such as electrical cables, etc. are removed from standing/walking areas. 0
  • 27. III.II. Set in order(Seiton) - For Pipes we suggest that they should be moved to the space available in front of the factory 2 (10*3 m^2). - For C-shape we suggest that they should be moved to the area of work assigned to them which is the region for grinding and welding. (6*2 m^2 for each cell)
  • 28. III.II. Set in order cont, - For scrape they must be taken away from the machines areas regularly into space behind factory 3 (22 *2 m^2). - For re-work parts must be taken away from the press 250 area regularly to the space in front of factory 2.
  • 29. SET IN ORDER ACTIVITY DESCRIPTIONS SCORE Locations for containers, boxes, bins, WIP, materials, etc. is clearly defined by painted lines and properly labeled (part number, quantity, etc.). 0 Tools have a designated storage location that is within reach of the operator. The location is properly labeled and tools can easily be identified if absent. 0 Paperwork is properly labeled and has a clearly defined and labeled location that is visible to the operators and away from work surfaces. 0 Equipment is clearly identified (numbered, named, color coded, etc.) and placed in a properly identified location. Critical maintenance points are clearly marked. 0 Furniture is clearly identified (numbered, named, color coded, etc.) and placed in a properly identified location. 0 Work areas requiring personal protective equipment are clearly labeled. 0 Stop switches and breakers are highly visible and located for easy access in case of emergency. 0 Fire hoses, fire extinguishers and other emergency equipment are prominently displayed and are unobstructed. 0 Working conditions are ergonomically friendly. Tools are stored at appropriate heights, lift assist devices are provided where necessary, etc. 0 The workplace layout accommodates easy exit in case of emergency. 0 Walkways and vehicle paths are clearly identified and unobstructed. Exits are clearly labeled and unobstructed. 0
  • 31. III.IV. Standardize(Seiketsu) STANDARDIZE ACTIVITY DESCRIPTIONS SCORE Tools, equipment, paperwork, furniture, etc. are stored neatly in designated areas and are returned immediately after each use. 0 Documents are labeled clearly as to contents and responsibility for control and revision. The date and revision number are clearly visible. 0 Equipment maintenance records are visible and clearly state when maintenance last occurred and when next maintenance is scheduled. 0 Product waste (e.g. shavings, containers, liquids, wrappers, etc.) is consistently and often cleaned up and removed from the workplace. 0 Preventive measures have been implemented to ensure the workplace meets 5S guidelines (e.g. systems that do not allow waste to accumulate such as containers to collect product debris from machines). 0 The results of the previous audit are posted and clearly visible to the entire team. 0 Areas for improvement identified during the previous audit have been completed. 0 The work environment satisfies the requirements of the work being performed. Lighting (brightness and color), air quality, temperature, etc. 0
  • 32. III.V. SUSTAIN(Shitsuke) SUSTAIN ACTIVITY DESCRIPTIONS SCORE A member of Management has participated in a 5S activity such as an audit or other activity within the past 3 audit periods. 0 Recognition is given to teams who get involved in 5S activities. 0 Time and resources are allocated to 5S activities (e.g. designated daily/weekly clean-up time, 5S team leader, etc.) 0 All operators, team leaders, supervisors, etc. are assigned 5S activities to be completed at least once/week. 0 The team took the initiative to make improvements to the workplace that was not identified during the last 5S audit. 0
  • 33. Concept that says all setups should and can take less than 10 minutes
  • 34. Change Over & Change Over Time Changeover time is the total elapsed time during Changeover process between the last unit of good production of the previous run, at normal line efficiency, to the first unit of good production of the succeeding run, at full line efficiency. Mold Change Colour Change Mold change Inspect/Adjust Setup Time 1st Piece Time (good or bad) 1st Good Piece Time 0 Last good part
  • 35. Internal & External set-up activities All Setup Activities Run III IE E EE Run Externals Internals Run ExternalsPost-setup externals Internal set-up activities Operations that must be performed while the machine/process is stopped External set-up activities Operations that can be performed while the machine/process is running
  • 37. CHANGEOVER RECORD DATE SHIFT FROM TO TIME (MIN) COMMENTS 20-march 2014 1 1:3 1:32 2 changes in the journey of cutting tool and the M/C die’s moving part 1 1:32 1:34 2 Nuts are removed 1 1:34 1:44 10 die disconnected 1 1:44 1:47 3 New die transformed with overhead lift 1 1:47 1:54 7 die stand installation (from Scrap) 1 1:54 2:09 15 new die installation Total Time 39 0. Preliminary Stage: Internal and External Setups are Mixed.
  • 38. 1. First Stage: Separate Internal and External Setups.
  • 39. 2. Second Stage: Convert Internal Setup to External Setup.
  • 40. 3. Third Stage: Streamline both Internal and External Setups. The M/C operator can call another Technical operator to help him to make (Die Disconnect) that another operator who observe time shift or anyone has done his daily work.
  • 41. Time is critical for productivity, capacity and cost. Here, the product's changeover was reduced from 36 minutes to consistently below 8.5 minutes, a difference of 27.5 minutes Final Stage: Document Internal and External Procedures
  • 42.
  • 44. • Project Name: Acrow Event. • Event Location: Factory 2, H20 production line. • Process: work standardization in the production line. Kaizen Event
  • 45. Kaizen team selection: • Team sponsor - champion: factory director • Team leader - process owner: production line engineer • Team member: hoisting crane operator • Team member: shear operator • Team member: press 160 tons operator • Team member: Press 250 tons operator • Team member: Press 63 Ton operator • Team member: Clark left operator • Kaizen facilitator: foreman
  • 46. Event scheduling (5 days) • Day of learning Day 1 • Day of Discovery & Developing Improvement IdeasDay 2 • Day of Improvement &Creating the New processDay 3 • Day of Design Implementation & DocumentationDay 4 • Day of Celebration &Results Schedule Day 5
  • 47.
  • 48. What’s Production Leveling (Heijunka) ! • Heijunka: Is the leveling of production by both volume and product mix. It does not build products according to the actual flow of customer orders, which can swing up and down wildly, but takes the total volume of orders in a period and levels them out so the same amount and mix are being made each day
  • 49. Name of product Average monthly demand Symbol 1. Corner Splice 45 × 45 50 2. Corner Splice 60 × 60 500 A 3. Pivot Splice 42X42 CM (double) 50 4. Splice 60 Cm Double 2100 B 5. Splice 90 Cm Double 70 6. Universal Corner Angle Tie (New) 1400 C We worked on different products that produced from press 200 ton
  • 50. Before Leveling 0 500 1000 1500 2000 2500 Demand Time Corner Splice 60 × 60 Splice 60 Cm Double Universal Corner Angle Tie (New)
  • 51. After Leveling 0 500 1000 1500 2000 2500 Demand Time Corner Splice 60 × 60 Splice 60 Cm Double Universal Corner Angle Tie (New)
  • 52. Setup a model for determining leveling production schedule according to volume and mix of the 3 products. (Corner Splice 60 × 60 , Splice 60 Cm Double , Universal Corner Angle Tie (New) ). We will use mixed model sequencing as a leveling model.
  • 53. Steps of mixed model sequencing are as follows: 1. Determine the total monthly demand for each type of product i. Corner Splice 60 × 60 = 500 units ii. Splice 60 Cm Double = 2100 units iii. Universal Corner Angle Tie (New) = 1400 units 2. Calculate the weekly requirement for each product type i. Corner Splice 60 × 60 = 500/4 = 125 units ii. Splice 60 Cm Double = 2100/4 = 525 units iii. Universal Corner Angle Tie (New) = 1400/4= 350 units iv. Total Weekly production= 1000 units
  • 54. Steps of mixed model sequencing Cont.: 3. Compute the build ratio and the production frequency for each product type by determine the largest integer that Divides evenly into weekly requirements of all products in this case (25) but I have chosen for the frequency to be (5) instead of (25) since 25 times as a frequency is a large number and more errors in changeover will occur if applied. i. Corner Splice 60 × 60 = 125/5 = 25 units ii. Splice 60 Cm Double = 525/5 = 105 units iii. Universal Corner Angle Tie (New) = 350/5 = 70 units iv. Production frequency = 1000/5 = 200 units
  • 55. Steps of mixed model sequencing Cont.: 4. Determine the build frequency: • Corner Splice 60 × 60 –25 units will be produced every 200 units • Splice 60 Cm Double –105 units will be produced every 200 units • Universal Corner Angle Tie (New) - 70 units will be produced every 200 units
  • 56. Steps of mixed model sequencing Cont.: 5. Set a build schedule: (BBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBB BBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBBAAAAAAAAAAAAAAAAAA AAAAAAACCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCCC CCCCCCCCCCCC) The above schedule will be executed 5 times a week .
  • 57.
  • 58. Process Capability:  It's a tool which is used to check the conformance of process output to the customer requirements specifications to: * Manage variations in the process output * Measure the uniformity of the process * Be compared with another process or competitor.
  • 59.
  • 60. 4.3754.2504.1254.0003.8753.7503.625 LSL Target USL Total N 100 Subgroup size 100 Mean 3.9548 StDev (overall) 0.089437 StDev (within) 0.089663 Process Characterization Cp 1.49 Cpk 1.32 Z.Bench 3.95 % Out of spec (expected) 0.00 PPM (DPMO) (expected) 38 Actual (overall) Pp 1.49 Ppk 1.32 Z.Bench 3.96 % Out of spec (observed) 0.00 % Out of spec (expected) 0.00 PPM (DPMO) (observed) 0 PPM (DPMO) (expected) 37 Potential (within) Capability Statistics Actual (overall) capability is what the customer experiences. shifts and drifts were eliminated. Potential (within) capability is what could be achieved if process Capability Analysis for C1 Process Performance Report Capability Histogram Are the data inside the limits and close to the target? 1st Sample Capability Analysis
  • 61. 4.324.204.083.963.843.723.60 LSL Target USL Total N 100 Subgroup size 100 Mean 3.9615 StDev (overall) 0.076136 StDev (within) 0.076329 Process Characterization Cp 1.75 Cpk 1.58 Z.Bench 4.74 % Out of spec (expected) 0.00 PPM (DPMO) (expected) 1 Actual (overall) Pp 1.75 Ppk 1.58 Z.Bench 4.75 % Out of spec (observed) 0.00 % Out of spec (expected) 0.00 PPM (DPMO) (observed) 0 PPM (DPMO) (expected) 1 Potential (within) Capability Statistics Actual (overall) capability is what the customer experiences. shifts and drifts were eliminated. Potential (within) capability is what could be achieved if process Capability Analysis for C1 Process Performance Report Capability Histogram Are the data inside the limits and close to the target? 2nd Sample Capability Analysis
  • 62. 4.3754.2504.1254.0003.8753.7503.625 Before LSL Target USL After Process Characterization Total N 100 100 Subgroup size 100 100 Mean 3.9548 3.9615 0.0067 StDev (overall) 0.089437 0.076136 -0.013301 StDev (within) 0.089663 0.076329 -0.013334 Before After Change Capability Statistics Cp 1.49 1.75 0.26 Cpk 1.32 1.58 0.26 Z.Bench 3.95 4.74 0.78 % Out of spec (exp) 0.00 0.00 -0.00 PPM (DPMO) (exp) 38 1 -37 Actual (overall) Pp 1.49 1.75 0.26 Ppk 1.32 1.58 0.26 Z.Bench 3.96 4.75 0.78 % Out of spec (obs) 0.00 0.00 0.00 % Out of spec (exp) 0.00 0.00 -0.00 PPM (DPMO) (obs) 0 0 0 PPM (DPMO) (exp) 37 1 -36 Potential (within) Before After Change Actual (overall) capability is what the customer experiences. process shifts and drifts were eliminated. Potential (within) capability is what could be achieved if Before/After Capability Comparison for before vs after Process Performance Report Capability Histogram Are the data inside the limits and close to the target? Comparing 1st and 2nd Samples Capabilities