Laying Of Heavy Cables Job Hazard Analysis
PROJECT / TASK CONTRACTOR JOB No.:
SUPERVISOR LOCATION: DATE:
JOB STEP
Break the job into steps.
Listing work which may be hazardous.
HAZARDS
List the hazard or type of harm
identified with each step
Consequence
Likelihood
Risk
Ranking
Control Measure
List the necessary control measures to be
followed to eliminate the identified hazards
Consequence
Likelihood
Risk
Ranking
ACTION
Person who will
ensure this
happens
1.Shifting of Poles By Hydra or
M Manually
 Hitting Hazard
( By Crane To The
Person Or objects )
 Falling Of Cables
3 2 5  Use Of P.P.E,
 Use Of Proper pathway
 Specific Path For Crane
Movement.
 As per checklist Hydra Crane
check.
 All Lifting tools and tackle will be
Properly checked before used by
Competent person.
 Proper Signal. (Only One Man
Signal)
 Use of Guide Rope.
 Proper co-ordination With Crane
operator.
 Proper Communication
1 1 2
2. Laying of Cable into Excavated
Trench
 Fall of Cables
 Hand injury
3 2 5  Use Of P.P.E.( safety shoe,
safety goggle, Hand gloves,
safety helmet.)
 Area Barricaded.
 Proper Communication
 Proper Supervision.
1 1 2
Job Hazard Analysis Attendees:
Signature Date
Written by: ICE JOSHI
Reviewed by:
Score TABLE OF CONSEQUENCE Score LIKELIHOOD
People Plant Environment
5 – Very High/
Catastrophic
Multiple Fatalities Greater than
$10Million Loss
Catastrophe, destruction of sensitive environment, worldwide
attention. Likely EPA prosecution. More than 30 days delay.
5 – Almost
certain
The event is expected to occur in most
circumstances. Likely to occur frequently-
More than 1 per year
4 – High/ Major Fatality or Permanent Disabilities $1Million to
$10Million Loss
Disaster, high levels of media attention, high cost of clean
up. Offsite environmental harm, more than 10 days delay.
4 – likely/
probable
The event will probably occur in most
circumstances. Likely to occur several tines.
1 per year
3 – Moderate Major Injuries - Incapacitations or
requiring time of work
$100Thousand to
$1Million Loss
Major spills, onsite release, substantial environmental
nuisance, more than 1day delay. (Leads to an additional
resources call out i.e. SES)
3 –
moderate/
occasional
The event should occur at some time. Likely
to occur some time. 1 per 5 years
2 – Low/ Minor Significant Injuries – Medical
Treatments, non-permanent injury
$10Thousand to
$100Thousand Loss
Significant spills (leads to a call out of Site Emergency
Response Group)
2 – remote/
unlikely
The event could occur at some time. Unlikely
but possible. 1 per 10 years
1 – Very Low/
Insignificant
Minor Injuries – First Aid Treatments
(cuts/bruises)
Less than
$10Thousand Loss
Low environmental impact. Minor Spills less than 80 Litres. 1 – rare/
very
unlikely
The event may occur only in exceptional
circumstances. Assumed it may not be
experienced. 1 per 100 years
Risk Rating = Consequence + Likelihood Risk Rating - Definitions
Consequence Risk Rating Risk Rating Definitions Action Required
5 6 7 8 9 10 8 - 10
Intolerable Task not to start till the risk is eliminated or reduced. Bring to the immediate attention of
management. Formal assessment required. MUST reduce the risk as a matter of priority.
4 5 6 7 8 9 7
High Bring to the immediate attention of management. Task not to start till the risk is eliminated or
reduced. Further Assessment required. MUST reduce the risk as a matter of priority.
3 4 5 6 7 8 6
Significant Risk Bring to the attention of supervision. Review risks and ensure that they are reduced to as low as
reasonably practicable. To be dealt with as soon as possible, preferably before the task
commences. Introduce some form of hardware to control risk.
2 3 4 5 6 7 5
Moderate Risk Needs to be controlled but not necessarily immediately, an action plan to control the risk should be
drawn up. Review effectiveness of controls. Ensure responsibilities for control are specified.
1 2 3 4 5 6 2-4
Low Risk If practical reduce the risk. Ensure personnel are competent to do the task. Manage by routing
procedure. Monitor for change
1 2 3 4 5 A JHA considers a variety of activities/tasks involved in a job scope and analyses the key hazards (sources of harm) and their
consequences (types of harm) eg. Sources of harm – lifting a heavy pipe, which is manual handling. Types of harm – Back strain.
Likelihood
Main Points – On how to write a JHA.
1. Define the task – what is to be done.
2. Review previous JHA if any – have we done it before?
3. Identify the steps – what is to be done.
4. Identify the hazards of each step.
5. Identify who or what could be harmed.
6. Give the task a risk rating – Consequence + Frequency
7. Develop solutions to eliminate or control hazards in each step.
8. Review the risk rating after the control system has been implemented.
9. If risk rating unacceptable review the solutions till risk rating acceptable.
10. Agree who will implement the control system.
11. Document the JHA and discuss with the relevant personnel.
Hierarchy of Hazard Management – Control Measures
These steps outline what should be planned for when deciding what control measures are to be put in
place. Whenever possible the highest step should be used first and then progress down the list.
1. Eliminate the hazard.
2. Substitution.
3. Reducing the frequency of a hazardous task.
4. Enclosing the hazard.
5. Additional procedures.
6. Additional supervision.
7. Additional training.
8. Instructions / information.
9. Some personal protective equipment.

More Related Content

What's hot

Work at Height | Safety during work at hight
Work at Height | Safety during work at hightWork at Height | Safety during work at hight
Work at Height | Safety during work at hightGaurav Singh Rajput
 
Toolbox Talk
Toolbox TalkToolbox Talk
Toolbox Talktxheaven
 
TBT on Working at Height.ppt
TBT on Working at Height.pptTBT on Working at Height.ppt
TBT on Working at Height.pptmohammadillias
 
13 initial project site office set up risk assessment templates
13 initial project site office set up risk assessment templates13 initial project site office set up risk assessment templates
13 initial project site office set up risk assessment templatesDwarika Bhushan Sharma
 
16 scaffolding (temporary works) risk assessment templates
16 scaffolding (temporary works) risk assessment templates16 scaffolding (temporary works) risk assessment templates
16 scaffolding (temporary works) risk assessment templatesDwarika Bhushan Sharma
 
Conveyor Safety
Conveyor SafetyConveyor Safety
Conveyor Safetyvtsiri
 
Lifting equipment at work
Lifting equipment at workLifting equipment at work
Lifting equipment at workPaul Smith
 
Industrial safetY of height works
Industrial safetY of height worksIndustrial safetY of height works
Industrial safetY of height worksPavan Noel
 
Safety harness - fall protection - Wessam Atif
Safety harness - fall protection - Wessam AtifSafety harness - fall protection - Wessam Atif
Safety harness - fall protection - Wessam AtifWessam Atif
 
Crane | Crane Safety | Crane Safety Parts | Gaurav Singh Rajput
Crane | Crane Safety | Crane Safety Parts | Gaurav Singh RajputCrane | Crane Safety | Crane Safety Parts | Gaurav Singh Rajput
Crane | Crane Safety | Crane Safety Parts | Gaurav Singh RajputGaurav Singh Rajput
 
Lifting Presentation.
Lifting Presentation.Lifting Presentation.
Lifting Presentation.paul doherty
 
Risk Assessment Example.pdf
Risk Assessment Example.pdfRisk Assessment Example.pdf
Risk Assessment Example.pdfBalamuruganD26
 

What's hot (20)

Work at Height | Safety during work at hight
Work at Height | Safety during work at hightWork at Height | Safety during work at hight
Work at Height | Safety during work at hight
 
Hse alert 43 forklift safety
Hse alert 43 forklift safetyHse alert 43 forklift safety
Hse alert 43 forklift safety
 
Mobile crane
Mobile craneMobile crane
Mobile crane
 
Working at heights
Working at heightsWorking at heights
Working at heights
 
Toolbox Talk
Toolbox TalkToolbox Talk
Toolbox Talk
 
Lifting & Rigging Safety.pptx
Lifting & Rigging Safety.pptxLifting & Rigging Safety.pptx
Lifting & Rigging Safety.pptx
 
TBT on Working at Height.ppt
TBT on Working at Height.pptTBT on Working at Height.ppt
TBT on Working at Height.ppt
 
FORKLIFT SAFETY
FORKLIFT SAFETYFORKLIFT SAFETY
FORKLIFT SAFETY
 
13 initial project site office set up risk assessment templates
13 initial project site office set up risk assessment templates13 initial project site office set up risk assessment templates
13 initial project site office set up risk assessment templates
 
16 scaffolding (temporary works) risk assessment templates
16 scaffolding (temporary works) risk assessment templates16 scaffolding (temporary works) risk assessment templates
16 scaffolding (temporary works) risk assessment templates
 
Conveyor Safety
Conveyor SafetyConveyor Safety
Conveyor Safety
 
Lifting equipment at work
Lifting equipment at workLifting equipment at work
Lifting equipment at work
 
Industrial safetY of height works
Industrial safetY of height worksIndustrial safetY of height works
Industrial safetY of height works
 
Safety harness - fall protection - Wessam Atif
Safety harness - fall protection - Wessam AtifSafety harness - fall protection - Wessam Atif
Safety harness - fall protection - Wessam Atif
 
Crane | Crane Safety | Crane Safety Parts | Gaurav Singh Rajput
Crane | Crane Safety | Crane Safety Parts | Gaurav Singh RajputCrane | Crane Safety | Crane Safety Parts | Gaurav Singh Rajput
Crane | Crane Safety | Crane Safety Parts | Gaurav Singh Rajput
 
Near Miss Reporting
Near Miss ReportingNear Miss Reporting
Near Miss Reporting
 
Lifting Presentation.
Lifting Presentation.Lifting Presentation.
Lifting Presentation.
 
Lifting Safety
Lifting Safety  Lifting Safety
Lifting Safety
 
Lifting Operation Safety ppt.pptx
Lifting Operation Safety ppt.pptxLifting Operation Safety ppt.pptx
Lifting Operation Safety ppt.pptx
 
Risk Assessment Example.pdf
Risk Assessment Example.pdfRisk Assessment Example.pdf
Risk Assessment Example.pdf
 

Similar to JSA Laying of heavy cable.doc

Risk Management Process
Risk Management ProcessRisk Management Process
Risk Management Processno suhaila
 
Risk management process
Risk management processRisk management process
Risk management processtoru6168
 
Risk Assessment - Refresher Training for Managers
Risk Assessment - Refresher Training for ManagersRisk Assessment - Refresher Training for Managers
Risk Assessment - Refresher Training for ManagersVictoria Finch
 
Military + Civilian Best Practices: Risk Management ver 1.1
Military + Civilian Best Practices: Risk Management ver 1.1Military + Civilian Best Practices: Risk Management ver 1.1
Military + Civilian Best Practices: Risk Management ver 1.1Alejandro Perez
 
7EL996_Risk Assessment_FINAL_2023.pptx
7EL996_Risk Assessment_FINAL_2023.pptx7EL996_Risk Assessment_FINAL_2023.pptx
7EL996_Risk Assessment_FINAL_2023.pptxRichard175921
 
Hazard identification and risk assessment(HIRA) &Safe Work method Statement.
Hazard identification and risk assessment(HIRA) &Safe Work method Statement.Hazard identification and risk assessment(HIRA) &Safe Work method Statement.
Hazard identification and risk assessment(HIRA) &Safe Work method Statement.Yuvraj Shrivastava
 
PECB Webinar: Hazard Identification, Risk Assessment and Determining Controls...
PECB Webinar: Hazard Identification, Risk Assessment and Determining Controls...PECB Webinar: Hazard Identification, Risk Assessment and Determining Controls...
PECB Webinar: Hazard Identification, Risk Assessment and Determining Controls...PECB
 
Performing Risk Assessments1
Performing Risk Assessments1Performing Risk Assessments1
Performing Risk Assessments1Mary Harris
 
Manie information needed to evaluate risky investment.
Manie information needed to evaluate risky investment.Manie information needed to evaluate risky investment.
Manie information needed to evaluate risky investment.mtlobrido
 
11. CHAPTER 2.0 OHS MANAGEMENT SYSTEM.pdf
11. CHAPTER 2.0  OHS MANAGEMENT SYSTEM.pdf11. CHAPTER 2.0  OHS MANAGEMENT SYSTEM.pdf
11. CHAPTER 2.0 OHS MANAGEMENT SYSTEM.pdfMohdJamilBinMohdHamb
 
Construction Safety Training_Session 10_Risk Assessment, Hierarchy of Control...
Construction Safety Training_Session 10_Risk Assessment, Hierarchy of Control...Construction Safety Training_Session 10_Risk Assessment, Hierarchy of Control...
Construction Safety Training_Session 10_Risk Assessment, Hierarchy of Control...Muizz Anibire
 
B Part 4 Risk Assessment & Study Example By J Mc Cann
B  Part 4 Risk Assessment &  Study Example By J Mc CannB  Part 4 Risk Assessment &  Study Example By J Mc Cann
B Part 4 Risk Assessment & Study Example By J Mc CannJames McCann
 
Risk assessment 3
Risk  assessment 3Risk  assessment 3
Risk assessment 3Ime David
 
07 Manual Handling Assessment - RPS Floor Sorting.pdf
07 Manual Handling Assessment - RPS Floor Sorting.pdf07 Manual Handling Assessment - RPS Floor Sorting.pdf
07 Manual Handling Assessment - RPS Floor Sorting.pdfajengps11
 
Risk Analysis & Management | Gaurav Singh Rajput
Risk Analysis & Management | Gaurav Singh Rajput Risk Analysis & Management | Gaurav Singh Rajput
Risk Analysis & Management | Gaurav Singh Rajput Gaurav Singh Rajput
 

Similar to JSA Laying of heavy cable.doc (20)

Risk Management Process
Risk Management ProcessRisk Management Process
Risk Management Process
 
Risk management process
Risk management processRisk management process
Risk management process
 
Risk assessment
Risk assessmentRisk assessment
Risk assessment
 
Risk Assessment - Refresher Training for Managers
Risk Assessment - Refresher Training for ManagersRisk Assessment - Refresher Training for Managers
Risk Assessment - Refresher Training for Managers
 
Military + Civilian Best Practices: Risk Management ver 1.1
Military + Civilian Best Practices: Risk Management ver 1.1Military + Civilian Best Practices: Risk Management ver 1.1
Military + Civilian Best Practices: Risk Management ver 1.1
 
7EL996_Risk Assessment_FINAL_2023.pptx
7EL996_Risk Assessment_FINAL_2023.pptx7EL996_Risk Assessment_FINAL_2023.pptx
7EL996_Risk Assessment_FINAL_2023.pptx
 
Hazard identification and risk assessment(HIRA) &Safe Work method Statement.
Hazard identification and risk assessment(HIRA) &Safe Work method Statement.Hazard identification and risk assessment(HIRA) &Safe Work method Statement.
Hazard identification and risk assessment(HIRA) &Safe Work method Statement.
 
PECB Webinar: Hazard Identification, Risk Assessment and Determining Controls...
PECB Webinar: Hazard Identification, Risk Assessment and Determining Controls...PECB Webinar: Hazard Identification, Risk Assessment and Determining Controls...
PECB Webinar: Hazard Identification, Risk Assessment and Determining Controls...
 
Performing Risk Assessments1
Performing Risk Assessments1Performing Risk Assessments1
Performing Risk Assessments1
 
Manie information needed to evaluate risky investment.
Manie information needed to evaluate risky investment.Manie information needed to evaluate risky investment.
Manie information needed to evaluate risky investment.
 
11. CHAPTER 2.0 OHS MANAGEMENT SYSTEM.pdf
11. CHAPTER 2.0  OHS MANAGEMENT SYSTEM.pdf11. CHAPTER 2.0  OHS MANAGEMENT SYSTEM.pdf
11. CHAPTER 2.0 OHS MANAGEMENT SYSTEM.pdf
 
Construction Safety Training_Session 10_Risk Assessment, Hierarchy of Control...
Construction Safety Training_Session 10_Risk Assessment, Hierarchy of Control...Construction Safety Training_Session 10_Risk Assessment, Hierarchy of Control...
Construction Safety Training_Session 10_Risk Assessment, Hierarchy of Control...
 
Topic 04 risk mangement
Topic 04 risk mangementTopic 04 risk mangement
Topic 04 risk mangement
 
B Part 4 Risk Assessment & Study Example By J Mc Cann
B  Part 4 Risk Assessment &  Study Example By J Mc CannB  Part 4 Risk Assessment &  Study Example By J Mc Cann
B Part 4 Risk Assessment & Study Example By J Mc Cann
 
Risk assessment 3
Risk  assessment 3Risk  assessment 3
Risk assessment 3
 
Risk assessment
Risk assessment Risk assessment
Risk assessment
 
Topik5
Topik5Topik5
Topik5
 
07 Manual Handling Assessment - RPS Floor Sorting.pdf
07 Manual Handling Assessment - RPS Floor Sorting.pdf07 Manual Handling Assessment - RPS Floor Sorting.pdf
07 Manual Handling Assessment - RPS Floor Sorting.pdf
 
HEMP
HEMPHEMP
HEMP
 
Risk Analysis & Management | Gaurav Singh Rajput
Risk Analysis & Management | Gaurav Singh Rajput Risk Analysis & Management | Gaurav Singh Rajput
Risk Analysis & Management | Gaurav Singh Rajput
 

Recently uploaded

HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAbhinavSharma374939
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 

Recently uploaded (20)

HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog Converter
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 

JSA Laying of heavy cable.doc

  • 1. Laying Of Heavy Cables Job Hazard Analysis PROJECT / TASK CONTRACTOR JOB No.: SUPERVISOR LOCATION: DATE: JOB STEP Break the job into steps. Listing work which may be hazardous. HAZARDS List the hazard or type of harm identified with each step Consequence Likelihood Risk Ranking Control Measure List the necessary control measures to be followed to eliminate the identified hazards Consequence Likelihood Risk Ranking ACTION Person who will ensure this happens 1.Shifting of Poles By Hydra or M Manually  Hitting Hazard ( By Crane To The Person Or objects )  Falling Of Cables 3 2 5  Use Of P.P.E,  Use Of Proper pathway  Specific Path For Crane Movement.  As per checklist Hydra Crane check.  All Lifting tools and tackle will be Properly checked before used by Competent person.  Proper Signal. (Only One Man Signal)  Use of Guide Rope.  Proper co-ordination With Crane operator.  Proper Communication 1 1 2
  • 2. 2. Laying of Cable into Excavated Trench  Fall of Cables  Hand injury 3 2 5  Use Of P.P.E.( safety shoe, safety goggle, Hand gloves, safety helmet.)  Area Barricaded.  Proper Communication  Proper Supervision. 1 1 2 Job Hazard Analysis Attendees: Signature Date Written by: ICE JOSHI Reviewed by:
  • 3. Score TABLE OF CONSEQUENCE Score LIKELIHOOD People Plant Environment 5 – Very High/ Catastrophic Multiple Fatalities Greater than $10Million Loss Catastrophe, destruction of sensitive environment, worldwide attention. Likely EPA prosecution. More than 30 days delay. 5 – Almost certain The event is expected to occur in most circumstances. Likely to occur frequently- More than 1 per year 4 – High/ Major Fatality or Permanent Disabilities $1Million to $10Million Loss Disaster, high levels of media attention, high cost of clean up. Offsite environmental harm, more than 10 days delay. 4 – likely/ probable The event will probably occur in most circumstances. Likely to occur several tines. 1 per year 3 – Moderate Major Injuries - Incapacitations or requiring time of work $100Thousand to $1Million Loss Major spills, onsite release, substantial environmental nuisance, more than 1day delay. (Leads to an additional resources call out i.e. SES) 3 – moderate/ occasional The event should occur at some time. Likely to occur some time. 1 per 5 years 2 – Low/ Minor Significant Injuries – Medical Treatments, non-permanent injury $10Thousand to $100Thousand Loss Significant spills (leads to a call out of Site Emergency Response Group) 2 – remote/ unlikely The event could occur at some time. Unlikely but possible. 1 per 10 years 1 – Very Low/ Insignificant Minor Injuries – First Aid Treatments (cuts/bruises) Less than $10Thousand Loss Low environmental impact. Minor Spills less than 80 Litres. 1 – rare/ very unlikely The event may occur only in exceptional circumstances. Assumed it may not be experienced. 1 per 100 years Risk Rating = Consequence + Likelihood Risk Rating - Definitions Consequence Risk Rating Risk Rating Definitions Action Required 5 6 7 8 9 10 8 - 10 Intolerable Task not to start till the risk is eliminated or reduced. Bring to the immediate attention of management. Formal assessment required. MUST reduce the risk as a matter of priority. 4 5 6 7 8 9 7 High Bring to the immediate attention of management. Task not to start till the risk is eliminated or reduced. Further Assessment required. MUST reduce the risk as a matter of priority. 3 4 5 6 7 8 6 Significant Risk Bring to the attention of supervision. Review risks and ensure that they are reduced to as low as reasonably practicable. To be dealt with as soon as possible, preferably before the task commences. Introduce some form of hardware to control risk. 2 3 4 5 6 7 5 Moderate Risk Needs to be controlled but not necessarily immediately, an action plan to control the risk should be drawn up. Review effectiveness of controls. Ensure responsibilities for control are specified. 1 2 3 4 5 6 2-4 Low Risk If practical reduce the risk. Ensure personnel are competent to do the task. Manage by routing procedure. Monitor for change 1 2 3 4 5 A JHA considers a variety of activities/tasks involved in a job scope and analyses the key hazards (sources of harm) and their consequences (types of harm) eg. Sources of harm – lifting a heavy pipe, which is manual handling. Types of harm – Back strain. Likelihood Main Points – On how to write a JHA. 1. Define the task – what is to be done. 2. Review previous JHA if any – have we done it before? 3. Identify the steps – what is to be done. 4. Identify the hazards of each step. 5. Identify who or what could be harmed. 6. Give the task a risk rating – Consequence + Frequency 7. Develop solutions to eliminate or control hazards in each step. 8. Review the risk rating after the control system has been implemented. 9. If risk rating unacceptable review the solutions till risk rating acceptable. 10. Agree who will implement the control system. 11. Document the JHA and discuss with the relevant personnel. Hierarchy of Hazard Management – Control Measures These steps outline what should be planned for when deciding what control measures are to be put in place. Whenever possible the highest step should be used first and then progress down the list. 1. Eliminate the hazard. 2. Substitution. 3. Reducing the frequency of a hazardous task. 4. Enclosing the hazard. 5. Additional procedures. 6. Additional supervision. 7. Additional training. 8. Instructions / information. 9. Some personal protective equipment.