Problem
Solution
General Description
Operating Princíple
AGENDA
PROBLEM
Power utilities have installed power substations in their distribution grids to
accommodate the ever-increasing demand for dependable power with their rows
of large high voltage power transformers. Many precautions are taken to
safeguard them against failure because when all power fails, customers
complain, revenues are lost and medical emergencies can even happen.
One of the risks these large transformers are subjected to is fire. Although the
manufacturers of these oil filled transformers are building them with many
imbedded safety features, when they fail they often produce very large fires that
are very hard to extinguish and provoke environmental damages by the release of
thick black toxic smoke and spilling of transformer oil. This is why more and more
utilities are installing fire protection systems to protect their investment and to
prevent such fires. Containment curbs and runoff water catch basins are also
built around the transformers to prevent oil spills in case of problems.
When they are protected, most high voltage power transformers are with a
deluge sprinkler system and designers use NFPA-15 as a guide to design a
system that will cool off the transformer and eventually, extinguish the fire.
PROBLEM
Typical design calls for a grid of open type deluge/spray nozzles to be installed all
around the transformer. A typical system will use about 44 of them and will be
designed to spray about 500 gpm of water for a duration of one (1) hour.
That is a lot of water!
Example typical solution - use big amounts of water due
to flooding, cause collateral damage.
video
PROBLEM
NFPA-850 for Power Plant Design goes even farther, requesting water spray
duration to last a full two (2) hours! But minimum provisions for drainage are
specified to be only large enough to contain the spill from the largest single
container of any flammable or combustible liquid in the area and for fixed fire
suppression systems operating for a minimum of 10 minutes!
A lot of power substations are located in remote areas, or on the outskirts of
towns where water is often not readily available in these large quantities. Water
reservoirs have to be built (often underground) to accommodate this large
demand. They require an initial investment that is fairly high for the utility
company and they also need regular maintenance, factors that are rarely included
in the fire protection contractor's proposal.
Even when water is available in these quantities, powerful fire pumps will be
needed to provide water at a sufficiently high pressure to achieve the goals of the
fire protection system. Infrastructure costs for the utility company rise rapidly, to
the point where some of them don't protect their transformers at all and will simply
provide passive protection measures such as firewalls.
AGENDA
Problem
Solution
General Description
Operating Princíple
SOLUTION
The Impulse New Technologies has developed a solution to these problems:
System ISAS is designed for emergency cooling and extinguishing fires on
transformers using a technology spraying fine dispersed water. Neutral gas
generators are used to create the effect of fine water and water mist.
video
Solution
General Description
AGENDA
Problem
Operating Princíple
GENERAL DESCRIPTION
The system consists of special tanks (ISAS module) which contain not less than
7,500 liters of water and built-in neutral gas generators. Spraying is carried out
through a fine water pulverization system installed around the transformer.
GENERAL DESCRIPTION
ISAS modules must be located in the immediate vicinity from the transformer (the
place is determined together with the customer). ISAS module can be located on
the ground or can be completely hidden underground to create space around the
transformer. The location of the module does not affect its work.
Each ISAS module can operate in two modes:
- Emergency cooling mode, water consumption rate is from 20 to 200 liters per
second
- Fire extinguishing mode, water consumption rate is 300 liters per second.
Due to the possibility of ISAS system to support the constant pressure in the
pipelines during its operation, the levels and locations of pipelines and modules
do not affect the efficiency of the system and can be defined by the Customer to
achieve maximum comfort during operation and maintenance of transformers.
ISAS system has no electric valves and other electrical actuators. It is completely
independent on external power sources and eliminates the possibility of failure of
mechanisms that are bound to external electrical interference as a result of an
accident on the transformer.
GENERAL DESCRIPTION
The system can be adapted for extinguishing with foam.
ISAS system is guaranteed to execute:
1. Start water feed in a fire extinguishing mode not exceeding the timeframe of
five seconds after the fire source determination in an automatic mode. This
timeframe will not exceed 3 seconds in case of a manual start-up.
2. Execute fire extinguishing or emergency cooling at any time during 10 years
the least at the absence of external sources of electricity and water.
3. Perform its work in case of global disaster or accident at the transformers
station and electrical network with a large number of electrical interference.
Solution
Operating Princíple
AGENDA
Problem
General Description
OPERATING PRINCÍPLE
The launch of the ISAS module in the automatic mode is conducted by sending a
low power electrical signal or manually by pressing a button or pulling the
operation ring.
In the automatic mode, the signal to start the system is sent by special
autonomous thermal sensors that automatically generate an electrical signal.
Sensors are 100% independent on external sources of electricity. The sensor is
completely protected from external electrical noise.
After starting the pressure generator, neutral gas (fire aerosol) is supplied into
the module case and this starts the displacement of water into fine sprays or into
the water pipes. The capacity of gas and pressure in the housing is automatically
maintained at the same level regardless of the amount of displaced water. For
emergency pressure release, each ISAS module contains pressure release
valves.
The pressure level in the system during operation shall be determined during the
module charging procedure with pressure generators and can be any in the range
from 0.2 to 2 Mpa.
After starting the module all water is displaced and pressure generator resource
is completely consumed. Recharging the module is conducted by trained
personnel of the customer and it takes less than one hour.
IMPULSE-STORM.COM

More Related Content

What's hot

Testing of transformer
Testing of transformerTesting of transformer
Testing of transformer
SMRITI KESHARWANI
 
Loss of mains protection or anti islanding
Loss of mains protection or anti islandingLoss of mains protection or anti islanding
Loss of mains protection or anti islanding
Osama Shahumi
 
Critical Power: NFPA 110: Standard for Emergency and Standby Power
Critical Power: NFPA 110: Standard for Emergency and Standby Power Critical Power: NFPA 110: Standard for Emergency and Standby Power
Critical Power: NFPA 110: Standard for Emergency and Standby Power
ConsultingSpecifyingEngineer
 
LV SWITCHGEAR -Final PPT.pptx
LV SWITCHGEAR -Final PPT.pptxLV SWITCHGEAR -Final PPT.pptx
LV SWITCHGEAR -Final PPT.pptx
shivendra68
 
Protection settings calculation
Protection settings calculationProtection settings calculation
Protection settings calculation
LANOGWA RODGERS
 
Switchyard design overview
Switchyard design overviewSwitchyard design overview
Switchyard design overview
Milind Punj
 
Pre-Commissioning Tests for AC Side of Solar Power Plant
Pre-Commissioning Tests for AC Side of Solar Power PlantPre-Commissioning Tests for AC Side of Solar Power Plant
Pre-Commissioning Tests for AC Side of Solar Power Plant
Gensol Engineering Limited
 
Protection of power transformer
Protection of power transformerProtection of power transformer
Protection of power transformer
Ritesh Verma
 
PARTIAL DISCHARGES IN TRANSFORMERS
PARTIAL DISCHARGES IN TRANSFORMERSPARTIAL DISCHARGES IN TRANSFORMERS
PARTIAL DISCHARGES IN TRANSFORMERS
Power System Operation
 
Electrical SUBSTATION ppt
Electrical SUBSTATION pptElectrical SUBSTATION ppt
Electrical SUBSTATION ppt
TanvirkabirShishir
 
Alstom High Voltage Training Offer - Technical Institute
Alstom High Voltage Training Offer - Technical InstituteAlstom High Voltage Training Offer - Technical Institute
Alstom High Voltage Training Offer - Technical Institute
Thorne & Derrick International
 
Electrical Design calculations
Electrical Design calculationsElectrical Design calculations
Electrical Design calculations
Pankaj Chavan
 
Upgrading gen protect and grounding
Upgrading gen protect and groundingUpgrading gen protect and grounding
Upgrading gen protect and grounding
michaeljmack
 
MV MetalClad Switchgear
MV MetalClad SwitchgearMV MetalClad Switchgear
MV MetalClad Switchgear
michaeljmack
 
Switchgear Installation Precomissioning Inspection.PPT
Switchgear Installation  Precomissioning Inspection.PPTSwitchgear Installation  Precomissioning Inspection.PPT
Switchgear Installation Precomissioning Inspection.PPTAbdullah Al Dushaishi
 
High Voltage On-Site Testing with Partial Discharge Measurement (Cigre 502)
High Voltage On-Site Testing with Partial Discharge Measurement (Cigre 502)High Voltage On-Site Testing with Partial Discharge Measurement (Cigre 502)
High Voltage On-Site Testing with Partial Discharge Measurement (Cigre 502)
AHMED MOHAMED HEGAB
 
Transformers protection, an introduction
Transformers protection, an introductionTransformers protection, an introduction
Transformers protection, an introduction
H. Kheir
 
Training manual for engineers on solar pv system
Training manual for engineers on solar pv systemTraining manual for engineers on solar pv system
Training manual for engineers on solar pv system
Deepak Kumar
 
Short Circuit, Protective Device Coordination
Short Circuit, Protective Device CoordinationShort Circuit, Protective Device Coordination
Short Circuit, Protective Device Coordination
michaeljmack
 
RTCC & AVR
RTCC & AVRRTCC & AVR
RTCC & AVR
Indiran K
 

What's hot (20)

Testing of transformer
Testing of transformerTesting of transformer
Testing of transformer
 
Loss of mains protection or anti islanding
Loss of mains protection or anti islandingLoss of mains protection or anti islanding
Loss of mains protection or anti islanding
 
Critical Power: NFPA 110: Standard for Emergency and Standby Power
Critical Power: NFPA 110: Standard for Emergency and Standby Power Critical Power: NFPA 110: Standard for Emergency and Standby Power
Critical Power: NFPA 110: Standard for Emergency and Standby Power
 
LV SWITCHGEAR -Final PPT.pptx
LV SWITCHGEAR -Final PPT.pptxLV SWITCHGEAR -Final PPT.pptx
LV SWITCHGEAR -Final PPT.pptx
 
Protection settings calculation
Protection settings calculationProtection settings calculation
Protection settings calculation
 
Switchyard design overview
Switchyard design overviewSwitchyard design overview
Switchyard design overview
 
Pre-Commissioning Tests for AC Side of Solar Power Plant
Pre-Commissioning Tests for AC Side of Solar Power PlantPre-Commissioning Tests for AC Side of Solar Power Plant
Pre-Commissioning Tests for AC Side of Solar Power Plant
 
Protection of power transformer
Protection of power transformerProtection of power transformer
Protection of power transformer
 
PARTIAL DISCHARGES IN TRANSFORMERS
PARTIAL DISCHARGES IN TRANSFORMERSPARTIAL DISCHARGES IN TRANSFORMERS
PARTIAL DISCHARGES IN TRANSFORMERS
 
Electrical SUBSTATION ppt
Electrical SUBSTATION pptElectrical SUBSTATION ppt
Electrical SUBSTATION ppt
 
Alstom High Voltage Training Offer - Technical Institute
Alstom High Voltage Training Offer - Technical InstituteAlstom High Voltage Training Offer - Technical Institute
Alstom High Voltage Training Offer - Technical Institute
 
Electrical Design calculations
Electrical Design calculationsElectrical Design calculations
Electrical Design calculations
 
Upgrading gen protect and grounding
Upgrading gen protect and groundingUpgrading gen protect and grounding
Upgrading gen protect and grounding
 
MV MetalClad Switchgear
MV MetalClad SwitchgearMV MetalClad Switchgear
MV MetalClad Switchgear
 
Switchgear Installation Precomissioning Inspection.PPT
Switchgear Installation  Precomissioning Inspection.PPTSwitchgear Installation  Precomissioning Inspection.PPT
Switchgear Installation Precomissioning Inspection.PPT
 
High Voltage On-Site Testing with Partial Discharge Measurement (Cigre 502)
High Voltage On-Site Testing with Partial Discharge Measurement (Cigre 502)High Voltage On-Site Testing with Partial Discharge Measurement (Cigre 502)
High Voltage On-Site Testing with Partial Discharge Measurement (Cigre 502)
 
Transformers protection, an introduction
Transformers protection, an introductionTransformers protection, an introduction
Transformers protection, an introduction
 
Training manual for engineers on solar pv system
Training manual for engineers on solar pv systemTraining manual for engineers on solar pv system
Training manual for engineers on solar pv system
 
Short Circuit, Protective Device Coordination
Short Circuit, Protective Device CoordinationShort Circuit, Protective Device Coordination
Short Circuit, Protective Device Coordination
 
RTCC & AVR
RTCC & AVRRTCC & AVR
RTCC & AVR
 

Similar to ISAS system for transformer fire fighting

Power backups
Power backupsPower backups
Power backups
Prachi Gupta
 
Subtech profile
Subtech profile Subtech profile
Subtech profile
latesh sharma
 
Inplant training about 110kv/11kv substation
Inplant training about 110kv/11kv substationInplant training about 110kv/11kv substation
Inplant training about 110kv/11kv substation
shivashankar307
 
Presentation training
Presentation trainingPresentation training
Presentation trainingSrajan Raj
 
RELINK - benefit of micro inverters
RELINK - benefit of micro invertersRELINK - benefit of micro inverters
RELINK - benefit of micro inverters
Marco Achilli
 
Feigin Electric Co. Ltd.
Feigin Electric Co. Ltd.Feigin Electric Co. Ltd.
Feigin Electric Co. Ltd.
Feigin Electric Co.Ltd
 
Hybrid Cooler
Hybrid CoolerHybrid Cooler
Hybrid Cooler
IRJET Journal
 
ISAS-F
ISAS-FISAS-F
TotalEcoEnergy Smart homebuilding solutions
TotalEcoEnergy Smart homebuilding solutionsTotalEcoEnergy Smart homebuilding solutions
TotalEcoEnergy Smart homebuilding solutions
Azi Col
 
Seminar report theory
Seminar report theorySeminar report theory
Seminar report theory
Ranjan kumar
 
Moisture controller report total
Moisture controller report totalMoisture controller report total
Moisture controller report total
Patruni Chidananda Sastry
 
Service solahart bogor 081313462267
Service solahart bogor 081313462267Service solahart bogor 081313462267
Service solahart bogor 081313462267
Service Solahart 081313462267
 
Transformerless inverters with thin film technology-Danfoss thin film and pid...
Transformerless inverters with thin film technology-Danfoss thin film and pid...Transformerless inverters with thin film technology-Danfoss thin film and pid...
Transformerless inverters with thin film technology-Danfoss thin film and pid...
Andreas ILIOU - Elektro- Solar
 
PMG Newsletter (Volume 03. Issue 10).pdf
PMG Newsletter (Volume 03. Issue 10).pdfPMG Newsletter (Volume 03. Issue 10).pdf
PMG Newsletter (Volume 03. Issue 10).pdf
PMG Engineering Private Limited
 
FIRE PREVENTION & FIRE FIGHTING EQUIPMENT-N PPT.pptx
FIRE PREVENTION & FIRE FIGHTING EQUIPMENT-N PPT.pptxFIRE PREVENTION & FIRE FIGHTING EQUIPMENT-N PPT.pptx
FIRE PREVENTION & FIRE FIGHTING EQUIPMENT-N PPT.pptx
NeerajTiwari965955
 
Over/Under Voltage Protection Circuit
Over/Under Voltage Protection CircuitOver/Under Voltage Protection Circuit
Over/Under Voltage Protection Circuit
MuhammadFazilMemon
 
3 phase transformer protection
3 phase transformer protection3 phase transformer protection
3 phase transformer protection
Himanshu Paghdal
 
Final Presentation.pptx
Final Presentation.pptxFinal Presentation.pptx
Final Presentation.pptx
MohamedHassanain8
 
Minimax power plant
Minimax power plantMinimax power plant
Minimax power plant
Faiz Husein
 
AUTOMATIC RAIN ALARM SENSOR/ CONTINUITY TESTER
    AUTOMATIC RAIN ALARM SENSOR/ CONTINUITY TESTER    AUTOMATIC RAIN ALARM SENSOR/ CONTINUITY TESTER
AUTOMATIC RAIN ALARM SENSOR/ CONTINUITY TESTER
FAIZAN SHAFI
 

Similar to ISAS system for transformer fire fighting (20)

Power backups
Power backupsPower backups
Power backups
 
Subtech profile
Subtech profile Subtech profile
Subtech profile
 
Inplant training about 110kv/11kv substation
Inplant training about 110kv/11kv substationInplant training about 110kv/11kv substation
Inplant training about 110kv/11kv substation
 
Presentation training
Presentation trainingPresentation training
Presentation training
 
RELINK - benefit of micro inverters
RELINK - benefit of micro invertersRELINK - benefit of micro inverters
RELINK - benefit of micro inverters
 
Feigin Electric Co. Ltd.
Feigin Electric Co. Ltd.Feigin Electric Co. Ltd.
Feigin Electric Co. Ltd.
 
Hybrid Cooler
Hybrid CoolerHybrid Cooler
Hybrid Cooler
 
ISAS-F
ISAS-FISAS-F
ISAS-F
 
TotalEcoEnergy Smart homebuilding solutions
TotalEcoEnergy Smart homebuilding solutionsTotalEcoEnergy Smart homebuilding solutions
TotalEcoEnergy Smart homebuilding solutions
 
Seminar report theory
Seminar report theorySeminar report theory
Seminar report theory
 
Moisture controller report total
Moisture controller report totalMoisture controller report total
Moisture controller report total
 
Service solahart bogor 081313462267
Service solahart bogor 081313462267Service solahart bogor 081313462267
Service solahart bogor 081313462267
 
Transformerless inverters with thin film technology-Danfoss thin film and pid...
Transformerless inverters with thin film technology-Danfoss thin film and pid...Transformerless inverters with thin film technology-Danfoss thin film and pid...
Transformerless inverters with thin film technology-Danfoss thin film and pid...
 
PMG Newsletter (Volume 03. Issue 10).pdf
PMG Newsletter (Volume 03. Issue 10).pdfPMG Newsletter (Volume 03. Issue 10).pdf
PMG Newsletter (Volume 03. Issue 10).pdf
 
FIRE PREVENTION & FIRE FIGHTING EQUIPMENT-N PPT.pptx
FIRE PREVENTION & FIRE FIGHTING EQUIPMENT-N PPT.pptxFIRE PREVENTION & FIRE FIGHTING EQUIPMENT-N PPT.pptx
FIRE PREVENTION & FIRE FIGHTING EQUIPMENT-N PPT.pptx
 
Over/Under Voltage Protection Circuit
Over/Under Voltage Protection CircuitOver/Under Voltage Protection Circuit
Over/Under Voltage Protection Circuit
 
3 phase transformer protection
3 phase transformer protection3 phase transformer protection
3 phase transformer protection
 
Final Presentation.pptx
Final Presentation.pptxFinal Presentation.pptx
Final Presentation.pptx
 
Minimax power plant
Minimax power plantMinimax power plant
Minimax power plant
 
AUTOMATIC RAIN ALARM SENSOR/ CONTINUITY TESTER
    AUTOMATIC RAIN ALARM SENSOR/ CONTINUITY TESTER    AUTOMATIC RAIN ALARM SENSOR/ CONTINUITY TESTER
AUTOMATIC RAIN ALARM SENSOR/ CONTINUITY TESTER
 

More from Valeriy Ivanov

Presentation Impulse Storm technologies
Presentation Impulse Storm technologiesPresentation Impulse Storm technologies
Presentation Impulse Storm technologies
Valeriy Ivanov
 
New generation technology for firefighting oil tank 80 000 m3
New generation technology for firefighting oil tank 80 000 m3New generation technology for firefighting oil tank 80 000 m3
New generation technology for firefighting oil tank 80 000 m3
Valeriy Ivanov
 
Tunnels firefighting
Tunnels firefightingTunnels firefighting
Tunnels firefighting
Valeriy Ivanov
 
Presentation ird direct
Presentation ird directPresentation ird direct
Presentation ird direct
Valeriy Ivanov
 
Fire tunnels
Fire tunnelsFire tunnels
Fire tunnels
Valeriy Ivanov
 
Supercompressed foam ISAS
Supercompressed foam ISASSupercompressed foam ISAS
Supercompressed foam ISAS
Valeriy Ivanov
 
Mobile ISAS firefighting system
Mobile ISAS firefighting systemMobile ISAS firefighting system
Mobile ISAS firefighting system
Valeriy Ivanov
 
ISAS IMPULSE STORM-A(S) JET COMBINED FOAM FIRE-FIGHTING SYSTEM
 ISAS IMPULSE STORM-A(S)   JET COMBINED FOAM FIRE-FIGHTING SYSTEM ISAS IMPULSE STORM-A(S)   JET COMBINED FOAM FIRE-FIGHTING SYSTEM
ISAS IMPULSE STORM-A(S) JET COMBINED FOAM FIRE-FIGHTING SYSTEM
Valeriy Ivanov
 

More from Valeriy Ivanov (8)

Presentation Impulse Storm technologies
Presentation Impulse Storm technologiesPresentation Impulse Storm technologies
Presentation Impulse Storm technologies
 
New generation technology for firefighting oil tank 80 000 m3
New generation technology for firefighting oil tank 80 000 m3New generation technology for firefighting oil tank 80 000 m3
New generation technology for firefighting oil tank 80 000 m3
 
Tunnels firefighting
Tunnels firefightingTunnels firefighting
Tunnels firefighting
 
Presentation ird direct
Presentation ird directPresentation ird direct
Presentation ird direct
 
Fire tunnels
Fire tunnelsFire tunnels
Fire tunnels
 
Supercompressed foam ISAS
Supercompressed foam ISASSupercompressed foam ISAS
Supercompressed foam ISAS
 
Mobile ISAS firefighting system
Mobile ISAS firefighting systemMobile ISAS firefighting system
Mobile ISAS firefighting system
 
ISAS IMPULSE STORM-A(S) JET COMBINED FOAM FIRE-FIGHTING SYSTEM
 ISAS IMPULSE STORM-A(S)   JET COMBINED FOAM FIRE-FIGHTING SYSTEM ISAS IMPULSE STORM-A(S)   JET COMBINED FOAM FIRE-FIGHTING SYSTEM
ISAS IMPULSE STORM-A(S) JET COMBINED FOAM FIRE-FIGHTING SYSTEM
 

Recently uploaded

weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfCOLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
Kamal Acharya
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
Kamal Acharya
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
MuhammadTufail242431
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
Kamal Acharya
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
ssuser9bd3ba
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
abh.arya
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
Kamal Acharya
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
DuvanRamosGarzon1
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 

Recently uploaded (20)

weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfCOLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 

ISAS system for transformer fire fighting

  • 1. FIRE FIGHTING IN HIGH VOLTAGE TRANSFORMERS NEW IMPULSE TECHNOLOGIES FIREFIGHTING IMPULSE STORM TECHNOLOGIES AND SYSTEMS MARCH/2015
  • 3. PROBLEM Power utilities have installed power substations in their distribution grids to accommodate the ever-increasing demand for dependable power with their rows of large high voltage power transformers. Many precautions are taken to safeguard them against failure because when all power fails, customers complain, revenues are lost and medical emergencies can even happen. One of the risks these large transformers are subjected to is fire. Although the manufacturers of these oil filled transformers are building them with many imbedded safety features, when they fail they often produce very large fires that are very hard to extinguish and provoke environmental damages by the release of thick black toxic smoke and spilling of transformer oil. This is why more and more utilities are installing fire protection systems to protect their investment and to prevent such fires. Containment curbs and runoff water catch basins are also built around the transformers to prevent oil spills in case of problems. When they are protected, most high voltage power transformers are with a deluge sprinkler system and designers use NFPA-15 as a guide to design a system that will cool off the transformer and eventually, extinguish the fire.
  • 4. PROBLEM Typical design calls for a grid of open type deluge/spray nozzles to be installed all around the transformer. A typical system will use about 44 of them and will be designed to spray about 500 gpm of water for a duration of one (1) hour. That is a lot of water! Example typical solution - use big amounts of water due to flooding, cause collateral damage. video
  • 5. PROBLEM NFPA-850 for Power Plant Design goes even farther, requesting water spray duration to last a full two (2) hours! But minimum provisions for drainage are specified to be only large enough to contain the spill from the largest single container of any flammable or combustible liquid in the area and for fixed fire suppression systems operating for a minimum of 10 minutes! A lot of power substations are located in remote areas, or on the outskirts of towns where water is often not readily available in these large quantities. Water reservoirs have to be built (often underground) to accommodate this large demand. They require an initial investment that is fairly high for the utility company and they also need regular maintenance, factors that are rarely included in the fire protection contractor's proposal. Even when water is available in these quantities, powerful fire pumps will be needed to provide water at a sufficiently high pressure to achieve the goals of the fire protection system. Infrastructure costs for the utility company rise rapidly, to the point where some of them don't protect their transformers at all and will simply provide passive protection measures such as firewalls.
  • 7. SOLUTION The Impulse New Technologies has developed a solution to these problems: System ISAS is designed for emergency cooling and extinguishing fires on transformers using a technology spraying fine dispersed water. Neutral gas generators are used to create the effect of fine water and water mist. video
  • 9. GENERAL DESCRIPTION The system consists of special tanks (ISAS module) which contain not less than 7,500 liters of water and built-in neutral gas generators. Spraying is carried out through a fine water pulverization system installed around the transformer.
  • 10. GENERAL DESCRIPTION ISAS modules must be located in the immediate vicinity from the transformer (the place is determined together with the customer). ISAS module can be located on the ground or can be completely hidden underground to create space around the transformer. The location of the module does not affect its work. Each ISAS module can operate in two modes: - Emergency cooling mode, water consumption rate is from 20 to 200 liters per second - Fire extinguishing mode, water consumption rate is 300 liters per second. Due to the possibility of ISAS system to support the constant pressure in the pipelines during its operation, the levels and locations of pipelines and modules do not affect the efficiency of the system and can be defined by the Customer to achieve maximum comfort during operation and maintenance of transformers. ISAS system has no electric valves and other electrical actuators. It is completely independent on external power sources and eliminates the possibility of failure of mechanisms that are bound to external electrical interference as a result of an accident on the transformer.
  • 11. GENERAL DESCRIPTION The system can be adapted for extinguishing with foam. ISAS system is guaranteed to execute: 1. Start water feed in a fire extinguishing mode not exceeding the timeframe of five seconds after the fire source determination in an automatic mode. This timeframe will not exceed 3 seconds in case of a manual start-up. 2. Execute fire extinguishing or emergency cooling at any time during 10 years the least at the absence of external sources of electricity and water. 3. Perform its work in case of global disaster or accident at the transformers station and electrical network with a large number of electrical interference.
  • 13. OPERATING PRINCÍPLE The launch of the ISAS module in the automatic mode is conducted by sending a low power electrical signal or manually by pressing a button or pulling the operation ring. In the automatic mode, the signal to start the system is sent by special autonomous thermal sensors that automatically generate an electrical signal. Sensors are 100% independent on external sources of electricity. The sensor is completely protected from external electrical noise. After starting the pressure generator, neutral gas (fire aerosol) is supplied into the module case and this starts the displacement of water into fine sprays or into the water pipes. The capacity of gas and pressure in the housing is automatically maintained at the same level regardless of the amount of displaced water. For emergency pressure release, each ISAS module contains pressure release valves. The pressure level in the system during operation shall be determined during the module charging procedure with pressure generators and can be any in the range from 0.2 to 2 Mpa. After starting the module all water is displaced and pressure generator resource is completely consumed. Recharging the module is conducted by trained personnel of the customer and it takes less than one hour.