SlideShare a Scribd company logo
DESIGN OF BATTEN
PLATES USING BOLT
CONNECTION
Example: A batten column of 10-m long is carrying a factored
load of 1150 kN. The column is restrained in position but not in
direction at both ends. Design a built up column using channel
sections placed back to back.
Design batten plates using bolt connection.
Let us try two ISMC 350 @ 413 N/m
Relevant properties of ISMC 350 [ Table II SP 6 (1): 1964]
𝐴 = 5366 mm2, 𝑟𝑧𝑧 = 136.6 mm,
𝑟𝑦𝑦 = 28.3 mm 𝑡𝑓 = 13.5 mm
𝐼𝑧𝑧 = 10008 × 104 mm4 𝐼𝑦𝑦 = 430.6 × 104 mm4
𝑐𝑦𝑦 = 24.4 mm 𝑏 = 100 mm
Solution:
Design of column:
𝑃 = 1150 kN = 1150 × 103 N
L = 1.0 × 10 × 103 = 10000 mm
Let design axial compressive stress for the column be 125 MPa
Required area =
1150×103
125
= 9200 mm2
For
𝐾𝐿
𝑟 𝑒
= 80.53, 𝑓𝑦 = 250 MPa and buckling class c, the
design compressive stress from Table 9c of IS 800 :2007
𝑓𝑐𝑑 = 136 −
136−121
10
× 0.53 = 135.2 MPa
Therefore load carrying capacity = 𝐴𝑒𝑓𝑐𝑑
= 10732 × 135.2 × 10−3
= 1451 kN > 1200 kN, OK
Area provided = 2 × 5366 = 10732 mm2
𝐿
𝑟𝑧𝑧
=
10000
136.6
= 73.21
The effective slenderness ratio,
𝐾𝐿
𝑟 𝑒
= 1.1 × 73.21
= 80.53 < 180; ok
Spacing of channels:
2𝐼𝑧𝑧 = 2 𝐼𝑦𝑦 + 𝐴
𝑆
2
+ 𝐶𝑦𝑦
2
or 2 × 10008 × 104 = 2 × 430.6 × 104 + 5366
𝑆
2
+ 24.4
2
⇒ 𝑆 = 218.4 mm
Let us keep the channels at a spacing of 220 mm
Spacing of battens:
As per clause 7.7.3 of IS 800: 2007,
𝐶
𝑟𝑦𝑦
< 0.7𝜆
𝑜𝑟 𝐶 < 0.7 × 𝜆 × 𝑟𝑦𝑦 = 0.7 × 80.53 × 28.3 = 1595.3 mm
Also
𝐶
𝑟𝑦𝑦
< 50 or 𝐶 < 50 × 28.3 = 1415 mm
Hence, provide battens at a spacing of 1400 mm.
Size of end battens (cl. 7.7.2.3 of IS 800 :2007):
Provide 20 mm bolts.
Edge distance = 1.5 × ℎ𝑜𝑙𝑒 𝑑𝑖𝑎𝑚𝑒𝑡𝑒𝑟 [Cl. 10.2.4.2 IS 800:2007]
= 1.5 × 20 + 2 = 33 mm
Effective depth = 𝑠 + 𝐶𝑦𝑦
= 220 + 2 × 24.4 = 268.8 mm > 2 × 100 mm
Hence, chosen effective depth is safe.
Overall depth = 268.8 + 2 × 33 = 334.8 mm
Required thickness of batten =
1
50
× 220 + 2 × 50 = 6.4 mm
Length of batten = 220 + 2 × 100 = 420 mm
Provide 420×340×8 mm end batten plates.
Size of intermediate battens (cl. 7.7.2.3 of IS 800 :2007):
Effective depth =
3
4
× (220 + 2 × 𝐶𝑦𝑦)
=
3
4
× (220 + 2 × 24.4) = 201.6 mm
> 2 × 100 = 200 mm
Hence adopt an effective depth of 210 mm
Overall depth = 210 + 2 × 33 = 276 mm
Therefore, provide a 420×300×8 mm batten plates @1400 mm
c/c.
Design forces:
Transverse shear, 𝑉 =
2.5
100
× 𝑃 =
2.5
100
× 1150 × 103
= 28750 N
Longitudinal shear 𝑉𝑙 =
𝑉𝐶
𝑁𝑆
Spacing of battens, C = 1400 mm
N = No of parallel planes of battens = 2
S = minimum transverse distance between the centroid of the
bolt/weld group = 220 + 2 × 50 = 320 mm
∴ 𝑉𝑙 =
28750×1400
2×320
= 62891 N
Moment, 𝑀 =
𝑉𝐶
2𝑁
=
28750×1400
2×2
= 10.06 × 106 N-mm
Check
i) For end battens
Shear stress =
62891
340×8
= 23.12 MPa <
250
3×1.1
= 131.22 MPa
Bending stress =
6𝑀
𝑡𝑑2 =
6×10.06×106
8×3402
= 65.27 MPa <
250
1.1
= 227.27 MPa
Hence safe.
b) For intermediate battens
Shear stress =
62891
300×8
= 26.2 MPa < 131.22 MPa
Bending stress =
6×10.06×106
8×3002 = 83.83 MPa < 227.27 MPa
Hence safe.
Connection:
The connection should be designed to transmit both shear and
bending moment.
Assuming 20 mm diameter bolts.
Strength of bolt in single shear
=
𝐴𝑛𝑏×𝑓𝑢𝑏
3×𝛾𝑚𝑏
=
0.78×
𝜋×202
4
×400
3×1.25
× 10−3= 45.27 kN
Minimum pitch, p = 2.5d=2.5×20=50 mm
Minimum end distance, e = 1.5 d0 =1.5×22=33 mm
Provide p = 60 mm and e = 35 mm
kb is smaller of 35/(3×22), 60/(3×22)-0.25, 400/410, 1
Kb = 0.53
Strength of bolt in bearing = 2.5𝑘𝑏𝑑𝑡𝑓𝑢/𝛾𝑚𝑏
= 2.5 × 0.53 × 20 × 8 ×
410
1.25
× 10−3 = 69.5 kN
Hence, strength of bolt = 45.27 kN
Number of bolts required =
62891
45.27×103 = 1.39
Let us provide four bolts to take account the stresses due to
bending moments as well.
Check for combined action: For end battens
Force in each bolt due to shear =
62891
4
= 15723 N
Pitch provided = (D-2e)/3= (340-2×35)/3 = 90 mm.
𝑟2 = 2[(90/2)2+(90+90/2)2) = 2[452+1352] = 40500 mm2
Force due to moment =
𝑀𝑟
𝑟2 =
10.06×106×135
40500
= 33533 N
Resultant force = 157232 + 335332
= 37036 N = 37 kN < 45.26 kN
Hence safe.
Check for combined action: For intermediate battens
Force in each bolt due to shear =
62891
4
= 15723 N
Pitch provided = (D-2e)/3= (300-2×35)/3 = 77 mm.
𝑟2 = 2[(77/2)2+(77+77/2)2) = 2[38.52+115.52] = 29645 mm2
Force due to moment =
𝑀𝑟
𝑟2 =
10.06×106×115.5
29645
= 39195 N
Resultant force = 157232 + 391952
= 42231N = 42.23 kN < 45.26 kN
Hence safe.
ISMC 350
350 mm
220 mm
220 mm
1400
mm
Intermediate batten
420 mm×300 mm×8 mm
End batten
420 mm×340 mm×8 mm
20 mm bolt
Channels back-to-back connected by bolts:
DESIGN OF BATTEN
PLATES USING WELD
CONNECTION
Example: A batten column of 10-m long is carrying a factored
load of 1150 kN. The column is restrained in position but not in
direction at both ends. Design a built up column using channel
sections placed back to back.
Design batten plates using weld connection.
Let us try two ISMC 350 @ 413 N/m
Relevant properties of ISMC 350 [ Table II SP 6 (1): 1964]
𝐴 = 5366 mm2, 𝑟𝑧𝑧 = 136.6 mm,
𝑟𝑦𝑦 = 28.3 mm 𝑡𝑓 = 13.5 mm
𝐼𝑧𝑧 = 10008 × 104 mm4 𝐼𝑦𝑦 = 430.6 × 104 mm4
𝑐𝑦𝑦 = 24.4 mm 𝑏 = 100 mm
Solution:
Design of column:
𝑃 = 1150 kN = 1150 × 103 N
L = 1.0 × 10 × 103 = 10000 mm
Let design axial compressive stress for the column be 125 MPa
Required area =
1150×103
125
= 9200 mm2
For
𝐾𝐿
𝑟 𝑒
= 80.53, 𝑓𝑦 = 250 MPa and buckling class c, the
design compressive stress from Table 9c of IS 800 :2007
𝑓𝑐𝑑 = 136 −
136;121
10
× 0.53 = 135.2 MPa
Therefore load carrying capacity = 𝐴𝑒𝑓𝑐𝑑
= 10732 × 135.2 × 10;3
= 1451 kN > 1200 kN, OK
Area provided = 2 × 5366 = 10732 mm2
𝐿
𝑟𝑧𝑧
=
10000
136.6
= 73.21
The effective slenderness ratio,
𝐾𝐿
𝑟 𝑒
= 1.1 × 73.21
= 80.53 < 180; ok
Spacing of channels:
2𝐼𝑧𝑧 = 2 𝐼𝑦𝑦 + 𝐴
𝑆
2
+ 𝐶𝑦𝑦
2
or 2 × 10008 × 104 = 2 × 430.6 × 104 + 5366
𝑆
2
+ 24.4
2
⇒ 𝑆 = 218.4 mm
Let us keep the channels at a spacing of 220 mm
Spacing of battens:
As per clause 7.7.3 of IS 800: 2007,
𝐶
𝑟𝑦𝑦
< 0.7𝜆
𝑜𝑟 𝐶 < 0.7 × 𝜆 × 𝑟𝑦𝑦 = 0.7 × 80.53 × 28.3 = 1595.3 mm
Also
𝐶
𝑟𝑦𝑦
< 50 or 𝐶 < 50 × 28.3 = 1415 mm
Hence, provide battens at a spacing of 1400 mm.
Size of end battens (cl. 7.7.2.3 of IS 800 :2007):
Overall depth of batten = 220 + 2 × 𝐶𝑦𝑦
= 220 + 2 × 24.4 = 268.8 ≈ 270 mm
Required thickness of batten =
1
50
× 220 = 4.4 mm
Adopt battens with the thickness of 6-mm
Let provide a 70 mm overlap of battens on channel flange for
welding.
[Overlap > 4 t = 4 × 6 = 24 mm] OK
Length of batten = 220 + 2 × 70 = 360 mm
Provide 360×270×6 mm end batten plates.
Size of intermediate battens (cl. 7.7.2.3 of IS 800 :2007):
Overall depth =
3
4
× (220 + 2 × 𝐶𝑦𝑦)
=
3
4
× (220 + 2 × 24.4) = 201.6 mm
> 2 × 100 = 200 mm
Hence adopt overall depth of 220 mm
Therefore, provide a 360×220×6 mm batten plates.
Design forces:
Transverse shear, 𝑉 =
2.5
100
× 𝑃 =
2.5
100
× 1150 × 103
= 28750 N
Longitudinal shear 𝑉𝑙 =
𝑉𝐶
𝑁𝑆
Spacing of battens, C = 1400 mm
N = No of parallel planes of battens = 2
S = minimum transverse distance between the centroid of the
bolt/weld group = 220 + 2 × 50 = 320 mm
∴ 𝑉𝑙 =
28750×1400
2×320
= 62891 N
Moment, 𝑀 =
𝑉𝐶
2𝑁
=
28750×1400
2×2
= 10.06 × 106 N-mm
Check
i) For end battens.
Shear stress =
62891
270×6
= 38.82 MPa <
250
3×1.1
= 131.22 MPa
Bending stress =
6𝑀
𝑡𝑑2 =
6×10.06×106
6×2702
= 138 MPa <
250
1.1
= 227.27 MPa
Hence safe.
b) For intermediate battens.
Shear stress =
62891
220×6
= 47.64 MPa < 131.22 MPa
Bending stress =
6×10.06×106
6×2202 = 207.85 MPa < 227.27 MPa
Hence safe.
Design of weld:
Welding is done on all the four sides as shown in the figure.
Let 𝑡 = throat thickness of weld.
𝐼𝑧𝑧 = 2 ×
70 × 𝑡3
12
+ 70 × 𝑡 ×
220
2
2
+
2 × 𝑡 × 2203
12
Neglecting the term 2 ×
70×𝑡3
12
being insignificant.
Therefore, 𝐼𝑧𝑧 = 346.87 × 104𝑡 mm4
𝐼𝑦𝑦 = 2 ×
𝑡 × 703
12
+ 2 ×
220 × 𝑡3
12
+ 2 × 220 × 𝑡 ×
70
2
2
Neglecting the term 2 ×
220×𝑡3
12
being insignificant.
Therefore, 𝐼𝑦𝑦 = 59.62 × 104𝑡 mm4
𝐼𝑝 = 𝐼𝑧𝑧 + 𝐼𝑦𝑦 = 346.87 × 104
𝑡 + 59.62 × 104
𝑡
= 406.49 × 104
𝑡 mm4
𝑟 =
220
2
2
+
70
2
2
= 115.43 mm
𝑐𝑜𝑠𝜃 =
35
115.43
= 0.30
Direct shear stress (cl. 10.5.9 of IS 800:2007)
=
62891
2×70:2×220 𝑡
=
108.43
𝑡
N/mm2
Shear stress due to bending moment =
10.06×106×115.43
406.49×104𝑡
=
285.67
𝑡
N/mm2
Combined stress due to shear and bending
=
108.43
𝑡
2
+
285.67
𝑡
2
+ 2 ×
108.43
𝑡
×
285.67
𝑡
× 0.3
=
334.59
𝑡
<
410
3 × 1.25
= 189.4
or 𝑡 = 1.77 mm
Size of weld = 1.77/0.7 = 2.5 mm
The size of weld should not be less than 5 mm for 13.5 mm
flange.
Hence provide a 5 mm weld to make the connection.
ISMC 350
350 mm
220 mm
220 mm
1400
mm
Intermediate batten
360 mm×220 mm×6 mm
End batten
360 mm×270 mm×6 mm
5 mm weld
Channels back-to-back connected by welding:
Design of Column Splices
Splices
• A joint when provided in the length of a member is called
splices.
• If a compression member is loaded concentrically,
theoretically no splice is required.
• However, the load is never truly axial and the real column has
to resist bending due to this eccentrically applied load.
Column sections can be spliced in the following cases:
1. When the length of the column is more than the length of
the column section available.
2. In case of multistorey buildings, the section of the column
required for the various storey may be different, as the
load goes on increasing for columns of the lower storeys.
Specifications for the design of splices
• Where the ends of the compression members are faced
for complete bearing over the whole area, these should be
spliced to hold the connected members accurately in
position, and to resist any tension when bending is
present.
• Where such members are not faced for complete bearing,
splices should be design to transmit all the forces to
which these are subjected.
• Splices are designed as short columns.
Various type of splices used in compression member
Steps for the design of splice
1. For axial compressive load the splice plates are provided
on the flanges of the two column sections to be spliced.
If the column has machined ends, the splice is designed only
to keep the columns in position and to carry tension due to the
bending moment to which it may be subjected. The splice
plate and the connection should be design to carry 50% of the
axial load and tension.
If the ends are not machined, the splice and connections are
design to resist the total axial load and any tension, if present
due to the bending moment.
Steps for the design of splice
• The load for the design of splice and connection due to axial
load,
𝑃𝑢1 =
𝑃𝑢
4
(for machined ends)
𝑃𝑢1 =
𝑃𝑢
2
(for non machined ends)
Where, 𝑃𝑢 is the axial factored load.
• The load for the design of splice and connection due
bending moment,
𝑃𝑢2 =
𝑀𝑢
𝑙𝑒𝑣𝑒𝑟 𝑎𝑟𝑚
Where, lever arm is the c/c distance of the two splice plates and
𝑀𝑢 is the factored bending moment.
Steps for the design of splice
2. Splice plates are assumed to act as short columns (with zero
slenderness ratio). So these plates will be subjected to yield
stress (𝑓𝑦).
3. The cross-sectional area of the splice plate is calculated by
dividing the appropriate portion of the factored load coming
over the splice by the yield stress.
c/s area required =
𝑃𝑢1+𝑃𝑢2
𝑓𝑦
4. The width of splice plate is usually kept equal to the width of
the column flange.
Width of splice = 𝑏𝑓 (width of flange)
The thickness of the splice plate can be found by dividing the
c/s area of the plates with its width.
Steps for the design of splice
5. Nominal diameter of bolts for connection is assumed and the
strength of the bolt is computed.
6. In case of bearing plate is to be designed between two
column sections, the length and width of the plate are kept
equal to the size of lower-storey column and the thickness is
computed by equating the ultimate moment due to the factored
load to the moment of resistance of plate section.
Example: A column ISHB 300 @ 576.8 N/m is to support a
factored axial load of 500 kN, shear force of 120 kN and
bending moment of 40 kNm. Design the splice plate and
connection using 4.6 grade bolts. Use steel of grade Fe 410.
Solution:
For steel of grade Fe 410: 𝑓𝑢 = 410 MPa, 𝑓𝑦 = 250 Mpa
For bolts of grade 4.6: 𝑓𝑢𝑏 = 400 MPa
Partial safety factors for material:(Table 5 IS 800:2007)
𝛾𝑚0 = 1.10 𝛾𝑚𝑏 = 1.25
The relevant properties of ISHB 300 @ 576.8 N/m are (Table I,
SP 6-1)
𝐴 = 7485 mm2 𝑏𝑓 = 250 mm,
𝑡𝑓 = 10.6 mm 𝑡𝑤 = 7.6 mm
Assume the ends of the column sections to be machined for
complete bearing. As the column ends are flush, it is assumed that
50% of the load is transferred directly and 50% is transferred
through the splice and fastenings. Therefore,
The direct load on each splice plate = 50% 𝑜𝑓
500
2
= 125 kN
Load on splice due to moment =
𝑀𝑢
𝑙𝑒𝑣𝑒𝑟 𝑎𝑟𝑚
=
40×103
300+6
= 130.72 kN
(Assuming 6 mm thick splice plate, the lever arm = 300 + 6 mm)
Total design load for splice, 𝑃𝑠 = 125 + 130.72 = 255.72 kN
Sectional area of splice plate required =
𝑃𝑠
𝑓𝑦
=
255.72×103
250
= 1022.9 mm2
Width of the splice plate should be kept equal to the width of
the flange.
Here, the width of the splice plate = 250 mm
Hence, thickness of splice plate =
1022.9
250
= 4.09 mm ≮ 6 mm
Provide a 250×6 mm splice plate.
The length of the splice plate depends upon the number of
bolts in vertical row.
Let us provide 20 mm diameter bolts of grade 4.6.
Strength of 20 mm diameter bolt in single shear (cl. 10.3.3, IS
800:2007)
=
𝐴𝑛𝑏
𝑓𝑢𝑏
3
𝛾𝑚𝑏
=
245×
400
3
1.25
× 10−3 = 45.26 kN
Strength of bolt in bearing = 2.5𝑘𝑏𝑑𝑡𝑓𝑢/𝛾𝑚𝑏 (cl. 10.3.4, IS
800:2007)
For 20 mm diameter bolts the minimum edge distance,
𝑒 = 1.5 × 𝑑0 = 1.5 × 20 + 2 = 33 mm
The minimum pitch, p = 2.5 × 20 = 50 mm
Let us provide an edge distance (e) of 35 mm and pitch (p) of
60 mm.
𝑘𝑏 is smaller of
𝑒
3𝑑0
=
35
3×22
= 0.53 ,
𝑝
3𝑑0
− 0.25 =
60
3×22
− 0.25 = 0.66 ,
𝑓𝑢𝑏
𝑓𝑢
=
400
410
= 0.98 and 1.0
Hence 𝑘𝑏 = 0.53
∴ Strength in bearing = 2.5 × 0.53 × 20 × 6 ×
410
1.25
× 10−3
= 52.15 kN
Hence, the strength of bolt (Bv) = 45.26 kN
Number of bolts required, n =
𝑃𝑠
𝐵𝑣
=
255.72
45.26
= 5.65 ≈ 6
Provide 6 bolts for each splice.
Length of the splice plate = 2 × (2 × 60 + 2 × 35) = 380 mm
Provide a splice plate 380×250×6 mm on column flanges as
shown in the figure.
Design of Column
Splices due to Shear
Example: A column ISHB 300 @ 576.8 N/m is to support a
factored axial load of 500 kN, shear force of 120 kN and
bending moment of 40 kNm. Design the splice plate and
connection using 4.6 grade bolts. Use steel of grade Fe 410.
Solution:
For steel of grade Fe 410: 𝑓𝑢 = 410 MPa, 𝑓𝑦 = 250 Mpa
For bolts of grade 4.6: 𝑓𝑢𝑏 = 400MPa
Partial safety factors for material:(Table 5 IS 800:2007)
𝛾𝑚0 = 1.10𝛾𝑚𝑏 = 1.25
The relevant properties of ISHB 300 @ 576.8 N/m are (Table I,
SP 6-1)
𝐴 = 7485 mm2𝑏𝑓 = 250 mm,
𝑡𝑓 = 10.6mm 𝑡𝑤 = 7.6 mm
Assume the ends of the column sections to be machined for
complete bearing. As the column ends are flush, it is assumed that
50% of the load is transferred directly and 50% is transferred
through the splice and fastenings. Therefore,
The direct load on each splice plate = 50% 𝑜𝑓
500
2
= 125 kN
Load on splice due to moment =
𝑀𝑢
𝑙𝑒𝑣𝑒𝑟 𝑎𝑟𝑚
=
40×103
300+6
= 130.72 kN
(Assuming 6 mm thick splice plate, the lever arm = 300 + 6 mm)
Total design load for splice, 𝑃𝑠 = 125 + 130.72 = 255.72 kN
Sectional area of splice plate required =
𝑃𝑠
𝑓𝑦
=
255.72×103
250
= 1022.9mm2
Width of the splice plate should be kept equal to the width of
the flange.
Here, the width of the splice plate = 250 mm
Hence, thickness of splice plate =
1022.9
250
= 4.09 mm ≮ 6 mm
Provide a 250×6 mm splice plate.
The length of the splice plate depends upon the number of
bolts in vertical row.
Let us provide 20 mm diameter bolts of grade 4.6.
Strength of 20 mm diameter bolt in single shear (cl. 10.3.3, IS
800:2007)
=
𝐴𝑛𝑏
𝑓𝑢𝑏
3
𝛾𝑚𝑏
=
245 ×
400
3
1.25
× 10−3
= 45.26 kN
Strength of bolt in bearing = 2.5𝑘𝑏𝑑𝑡𝑓𝑢/𝛾𝑚𝑏(cl. 10.3.4, IS
800:2007)
For 20 mm diameter bolts the minimum edge distance,
𝑒 = 1.5 × 𝑑0 = 1.5 × 20 + 2 = 33 mm
The minimum pitch, p = 2.5 × 20 = 50 mm
Let us provide an edge distance (e) of 35 mm and pitch (p) of
60 mm.
𝑘𝑏 is smaller of
𝑒
3𝑑0
=
35
3×22
= 0.53 ,
𝑝
3𝑑0
− 0.25 =
60
3×22
− 0.25 = 0.66 ,
𝑓𝑢𝑏
𝑓𝑢
=
400
410
= 0.98 and 1.0
Hence 𝑘𝑏 = 0.53
∴ Strength in bearing = 2.5 × 0.53 × 20 × 6 ×
410
1.25
× 10−3
= 52.15kN
Hence, the strength of bolt (Bv) = 45.26 kN
Number of bolts required, n =
𝑃𝑠
𝐵𝑣
=
255.72
45.26
= 5.65 ≈ 6
Provide 6 bolts for each splice.
Length of the splice plate = 2 × (2 × 60 + 2 × 35) = 380 mm
Provide a splice plate 380×250×6 mm on column flanges as
shown in the figure.
Splice plates for shear:
The splice plate for the shear force is provided on the web. A pair
of splice plate (one on each side of web) are provided.
Let us provide 20 mm diameter bolts of grade 4.6.
Strength of bolt in double shear = 45.26 × 2 = 90.52 kN
Strength in bearing = 2.5𝑘𝑏𝑑𝑡𝑓𝑢/𝛾𝑚𝑏
Where, 𝑘𝑏 = 0.53 (taking 𝑒 = 35 mm and p = 60 mm),
𝑡 = 7.6 mm (web thickness)
∴ Strength in bearing = 2.5 × 0.53 × 20 × 7.6 ×
410
1.25
× 10−3 =
66.06 kN
Hence, strength of 20 mm bolt = 66.06kN
Shear force in the web, 𝑉 = 120 kN
Number of bolts required =
120
66.06
= 1.8 ≈ 2
Provide 2, 20 mm diameter bolts on each side of the splice.
Length of the splice plate = 4 × 35 = 140 mm
Width of the splice plate = 60 + 2 × 35 = 130 mm
Design shear strength of splice plate (cl. 8.4, IS 800:2007),
𝑉𝑑 =
𝑓𝑦
3 × 𝛾𝑚0
× ℎ × 𝑡
=
250
3 × 1.1
× 130 × 2𝑡𝑠 × 10−3
= 34.12 𝑡𝑠 kN
Now, 𝑉𝑑 > 𝑉
or 34.12 𝑡𝑠 > 120
Thickness of the splice plate required,
𝑡𝑠 =
120
34.12
= 3.52 mm ≮ 6mm
So provide a pair of 140×130×6 mm shear splice plates on each
side of the web as shown in the figure.
35
35
35
35
60
60
60
60
60
35 35
140
ISHB
300
20 mm
bolts
Front view Side view
INTRODUCTION TO FLEXURAL
MEMBERS: BEAMS
INTRODUCTION
• Flexural members or bending members are commonly called
BEAMS.
• A beam is a structural member subjected to transverse loads
i.e., loads perpendicular to the longitudinal axis.
• The load produce Bending moment & Shear forces.
http://wasatchsteel.blogspot.in/
http://www.steel-bridges.com/
DIFFERENT TYPES OF BEAMS
• JOIST: A closely spaced beams supporting floors or roofs of
building but not supporting the other beams.
• GIRDER: A large beam, used for supporting a number of
joists.
• PURLIN: Purlins are used to carry roof loads in trusses.
• STRINGER: In building, beams supporting stair steps; in
bridges a longitudinal beam supporting deck floor & supported
by floor beam.
• FLOOR BEAM: A major beam supporting other beams in a
building; also the transverse beam in bridge floors.
• SPANDREL BEAM: In a building, a beam on the outside
perimeter of a floor, supporting the exterior walls and outside
edge of the floor
• GIRT: A horizontal beam spanning the wall columns of
industrial buildings used to support wall coverings is called a
GIRT.
• RAFTER: A roof beam usually supported by purlins.
• LINTELS: This type of beams are used to support the loads
from the masonry over the openings .
DIFFERENT TYPES OF BEAMS
NATURE OF FORCES ACTING ON BEAMS
• It is assumed that the beam is subjected to only transverse
loading.
• All the loads and sections lie in the plane of symmetry.
• It follows that such a beam will be primarily subjected to
bending accompanied by shear in the loading plane with no
external torsion and axial force.
• The problem of torsion can not completely be avoided in a
beam even if the beam shape is symmetrical and loads are in
the plane of symmetry.
• The reason is the instability caused by compressive stresses.
Such instability is defined as LATERAL BUCKLING .
When it is involving only local components of a beam it is
called LOCAL BUCKLING.
• Local buckling is a function of width-thickness ratio.
NATURE OF FORCES ACTING ON BEAMS
Primary modes of failure of beams are as follows:
1. Bending failure
2. Shear failure
3. Deflection failure
1. Bending failure: Bending failure generally occurs due to
crushing of compression flange or fracture of tension flange of
the beam.
2. Shear failure: This occurs due to buckling of web of the beam
near location of high shear forces. The beam can fail locally
due to crushing or buckling of the web near the reaction of
concentrated loads.
3. Deflection failure: A beam designed to have adequate strength
may become unsuitable if it is not able to support its load
without excessive deflections.
MODES OF FAILURE
TYPES OF STEEL SECTIONS
CASTELLATED BEAMS
CONSIDERATIONS IN DESIGN OF BEAMS
• Beams should be proportioned for strength in bending
keeping in view of the lateral and local stability of the
compression flange.
• The selected shape should have capacity to withstand
essential strength in shear and local bearing .
• The beam dimension should be suitably proportioned for
stiffness, keeping in mind their deflections and deformations
under service conditions .
LIMITATIONS OF ANGLES , T-SECTIONS AND
CHANNELS
• Angles and T-sections are weak in bending.
• Channels only be used for light loads.
• The rolled steel channels and angle sections are used in those
cases where they can be designed and executed satisfactory.
• This is because the load is not likely to be in the plane, which
removes torsional eccentricities .
• Also, it is complicated to calculate the lateral buckling
characteristics of these sections .

More Related Content

What's hot

Estudio de transito grupo 1
Estudio de transito grupo 1Estudio de transito grupo 1
Estudio de transito grupo 1
Oliannys Villahermosa
 
Chapter v 2. moment area method
Chapter v 2. moment area methodChapter v 2. moment area method
Chapter v 2. moment area method
MARTIN ATHIYO
 
Module1 c - rajesh sir
Module1 c - rajesh sirModule1 c - rajesh sir
Module1 c - rajesh sir
SHAMJITH KM
 
Analisis sismo resistente (nec se-ds) dinamico
Analisis sismo resistente (nec se-ds) dinamicoAnalisis sismo resistente (nec se-ds) dinamico
Analisis sismo resistente (nec se-ds) dinamico
Miguel Angel Tisalema Sisa
 
Iii design-of-steel-structures-unit-2
Iii design-of-steel-structures-unit-2Iii design-of-steel-structures-unit-2
Iii design-of-steel-structures-unit-2
saibabu48
 
Moment Co-efficient Method
Moment Co-efficient MethodMoment Co-efficient Method
Moment Co-efficient MethodYousuf Bin Aziz
 
Design calculations of raft foundation
Design calculations of raft foundationDesign calculations of raft foundation
Design calculations of raft foundation
Shahzad Ali
 
COLD-FORMED STEEL N1. Diseño de costaneras de sección canal atiesada. AISI S1...
COLD-FORMED STEEL N1. Diseño de costaneras de sección canal atiesada. AISI S1...COLD-FORMED STEEL N1. Diseño de costaneras de sección canal atiesada. AISI S1...
COLD-FORMED STEEL N1. Diseño de costaneras de sección canal atiesada. AISI S1...
AngelManrique7
 
Design of torsion reinforcement
 Design of torsion reinforcement Design of torsion reinforcement
Design of torsion reinforcement
MuskanDeura
 
ANALYSIS & DESIGN ASPECTS OF PRE-STRESSED MEMBERS USING F.R.P. TENDONS
ANALYSIS & DESIGN ASPECTS OF PRE-STRESSED MEMBERS USING F.R.P. TENDONSANALYSIS & DESIGN ASPECTS OF PRE-STRESSED MEMBERS USING F.R.P. TENDONS
ANALYSIS & DESIGN ASPECTS OF PRE-STRESSED MEMBERS USING F.R.P. TENDONS
Girish Singh
 
T espe-049298-d
T espe-049298-dT espe-049298-d
T espe-049298-d
Pauly Tapia Villamarín
 
Engineering mechanics-question-and-answers-for-gate-ias
Engineering mechanics-question-and-answers-for-gate-iasEngineering mechanics-question-and-answers-for-gate-ias
Engineering mechanics-question-and-answers-for-gate-iashitusp
 
Solution Manual for Structural Analysis 6th SI by Aslam Kassimali
Solution Manual for Structural Analysis 6th SI by Aslam KassimaliSolution Manual for Structural Analysis 6th SI by Aslam Kassimali
Solution Manual for Structural Analysis 6th SI by Aslam Kassimali
physicsbook
 
Análisis estático no lineal fema 356
Análisis estático no lineal fema 356Análisis estático no lineal fema 356
Análisis estático no lineal fema 356
Universidad Nacional de San Agustin
 
Lec.2 statically determinate structures &amp; statically indeterminate struct...
Lec.2 statically determinate structures &amp; statically indeterminate struct...Lec.2 statically determinate structures &amp; statically indeterminate struct...
Lec.2 statically determinate structures &amp; statically indeterminate struct...
Muthanna Abbu
 
Introduction to the theory of plates
Introduction to the theory of platesIntroduction to the theory of plates
Introduction to the theory of plates
ABHISHEK CHANDA
 
Geotechnical Engineering-II [Lec #18: Terzaghi Bearing Capacity Equation]
Geotechnical Engineering-II [Lec #18: Terzaghi Bearing Capacity Equation]Geotechnical Engineering-II [Lec #18: Terzaghi Bearing Capacity Equation]
Geotechnical Engineering-II [Lec #18: Terzaghi Bearing Capacity Equation]
Muhammad Irfan
 
SA-II Notes.pdf
SA-II  Notes.pdfSA-II  Notes.pdf
SA-II Notes.pdf
Parandh M
 
Soluc porticos
Soluc porticosSoluc porticos
Soluc porticos
MARIOCASAS37
 

What's hot (20)

Estudio de transito grupo 1
Estudio de transito grupo 1Estudio de transito grupo 1
Estudio de transito grupo 1
 
Chapter v 2. moment area method
Chapter v 2. moment area methodChapter v 2. moment area method
Chapter v 2. moment area method
 
Module1 c - rajesh sir
Module1 c - rajesh sirModule1 c - rajesh sir
Module1 c - rajesh sir
 
Analisis sismo resistente (nec se-ds) dinamico
Analisis sismo resistente (nec se-ds) dinamicoAnalisis sismo resistente (nec se-ds) dinamico
Analisis sismo resistente (nec se-ds) dinamico
 
Iii design-of-steel-structures-unit-2
Iii design-of-steel-structures-unit-2Iii design-of-steel-structures-unit-2
Iii design-of-steel-structures-unit-2
 
Moment Co-efficient Method
Moment Co-efficient MethodMoment Co-efficient Method
Moment Co-efficient Method
 
Design calculations of raft foundation
Design calculations of raft foundationDesign calculations of raft foundation
Design calculations of raft foundation
 
COLD-FORMED STEEL N1. Diseño de costaneras de sección canal atiesada. AISI S1...
COLD-FORMED STEEL N1. Diseño de costaneras de sección canal atiesada. AISI S1...COLD-FORMED STEEL N1. Diseño de costaneras de sección canal atiesada. AISI S1...
COLD-FORMED STEEL N1. Diseño de costaneras de sección canal atiesada. AISI S1...
 
Design of torsion reinforcement
 Design of torsion reinforcement Design of torsion reinforcement
Design of torsion reinforcement
 
ANALYSIS & DESIGN ASPECTS OF PRE-STRESSED MEMBERS USING F.R.P. TENDONS
ANALYSIS & DESIGN ASPECTS OF PRE-STRESSED MEMBERS USING F.R.P. TENDONSANALYSIS & DESIGN ASPECTS OF PRE-STRESSED MEMBERS USING F.R.P. TENDONS
ANALYSIS & DESIGN ASPECTS OF PRE-STRESSED MEMBERS USING F.R.P. TENDONS
 
T espe-049298-d
T espe-049298-dT espe-049298-d
T espe-049298-d
 
Engineering mechanics-question-and-answers-for-gate-ias
Engineering mechanics-question-and-answers-for-gate-iasEngineering mechanics-question-and-answers-for-gate-ias
Engineering mechanics-question-and-answers-for-gate-ias
 
Solution Manual for Structural Analysis 6th SI by Aslam Kassimali
Solution Manual for Structural Analysis 6th SI by Aslam KassimaliSolution Manual for Structural Analysis 6th SI by Aslam Kassimali
Solution Manual for Structural Analysis 6th SI by Aslam Kassimali
 
Análisis estático no lineal fema 356
Análisis estático no lineal fema 356Análisis estático no lineal fema 356
Análisis estático no lineal fema 356
 
Lec.2 statically determinate structures &amp; statically indeterminate struct...
Lec.2 statically determinate structures &amp; statically indeterminate struct...Lec.2 statically determinate structures &amp; statically indeterminate struct...
Lec.2 statically determinate structures &amp; statically indeterminate struct...
 
02 aashto cap-10
02 aashto cap-1002 aashto cap-10
02 aashto cap-10
 
Introduction to the theory of plates
Introduction to the theory of platesIntroduction to the theory of plates
Introduction to the theory of plates
 
Geotechnical Engineering-II [Lec #18: Terzaghi Bearing Capacity Equation]
Geotechnical Engineering-II [Lec #18: Terzaghi Bearing Capacity Equation]Geotechnical Engineering-II [Lec #18: Terzaghi Bearing Capacity Equation]
Geotechnical Engineering-II [Lec #18: Terzaghi Bearing Capacity Equation]
 
SA-II Notes.pdf
SA-II  Notes.pdfSA-II  Notes.pdf
SA-II Notes.pdf
 
Soluc porticos
Soluc porticosSoluc porticos
Soluc porticos
 

Similar to Week 9 Lecture Material_watermark.pdf

INDUSTRIAL BUILDING GANTRY GIRDER
INDUSTRIAL BUILDING  GANTRY GIRDERINDUSTRIAL BUILDING  GANTRY GIRDER
INDUSTRIAL BUILDING GANTRY GIRDER
Harsh Shani
 
131445983 jembatan-balok-t
131445983 jembatan-balok-t131445983 jembatan-balok-t
131445983 jembatan-balok-t
agustinamanru
 
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank  Design by Working Stress - IS Method.pdfIntze Overhead Water Tank  Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
Dhaka University of Engineering & Technology, Gazipur
 
onw way slab design
onw way slab designonw way slab design
onw way slab design
Palak Patel
 
C09 m-403032016 som
C09 m-403032016 somC09 m-403032016 som
C09 m-403032016 som
vinodh kumar
 
10-Design of Tension Member with Bolted Connection (Steel Structural Design &...
10-Design of Tension Member with Bolted Connection (Steel Structural Design &...10-Design of Tension Member with Bolted Connection (Steel Structural Design &...
10-Design of Tension Member with Bolted Connection (Steel Structural Design &...
Hossam Shafiq II
 
Worked example extract_flat_slabs
Worked example extract_flat_slabsWorked example extract_flat_slabs
Worked example extract_flat_slabs
luantvconst
 
Ref F2F Week 4 - Solution_unlocked.pdf
Ref F2F Week 4 - Solution_unlocked.pdfRef F2F Week 4 - Solution_unlocked.pdf
Ref F2F Week 4 - Solution_unlocked.pdf
Robin Arthur Flores
 
Worked example extract_flat_slabs
Worked example extract_flat_slabsWorked example extract_flat_slabs
Worked example extract_flat_slabsLuan Truong Van
 
Columns and struts_-_solved
Columns and struts_-_solvedColumns and struts_-_solved
Columns and struts_-_solved
ViriSharma
 
Numericals on Columns and struts_-_solved
Numericals on Columns and struts_-_solvedNumericals on Columns and struts_-_solved
Numericals on Columns and struts_-_solved
ViriSharma
 
Intze Tankd s sad sa das dsjkj kkk kds s kkksk
Intze Tankd s sad sa das dsjkj kkk kds s kkkskIntze Tankd s sad sa das dsjkj kkk kds s kkksk
Intze Tankd s sad sa das dsjkj kkk kds s kkksk
Krish Bhavsar
 
Intze Tank.ppt
Intze Tank.pptIntze Tank.ppt
Intze Tank.ppt
EmilyMuthiga1
 
steel question.pdf.pdf
steel question.pdf.pdfsteel question.pdf.pdf
steel question.pdf.pdf
nabal_iitb
 
design of steel flyover
design of steel flyoverdesign of steel flyover
design of steel flyover
Peer Mohideen
 
Compression member
Compression memberCompression member
Compression member
kamariya keyur
 
2 compression
2  compression2  compression
2 compression
Ahmed Gamal
 
Transformer design 2072 batch IOE - TU
Transformer design 2072 batch IOE - TU Transformer design 2072 batch IOE - TU
Transformer design 2072 batch IOE - TU
Bikash Gyawali
 

Similar to Week 9 Lecture Material_watermark.pdf (20)

INDUSTRIAL BUILDING GANTRY GIRDER
INDUSTRIAL BUILDING  GANTRY GIRDERINDUSTRIAL BUILDING  GANTRY GIRDER
INDUSTRIAL BUILDING GANTRY GIRDER
 
131445983 jembatan-balok-t
131445983 jembatan-balok-t131445983 jembatan-balok-t
131445983 jembatan-balok-t
 
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank  Design by Working Stress - IS Method.pdfIntze Overhead Water Tank  Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
 
onw way slab design
onw way slab designonw way slab design
onw way slab design
 
C09 m-403032016 som
C09 m-403032016 somC09 m-403032016 som
C09 m-403032016 som
 
10-Design of Tension Member with Bolted Connection (Steel Structural Design &...
10-Design of Tension Member with Bolted Connection (Steel Structural Design &...10-Design of Tension Member with Bolted Connection (Steel Structural Design &...
10-Design of Tension Member with Bolted Connection (Steel Structural Design &...
 
Worked example extract_flat_slabs
Worked example extract_flat_slabsWorked example extract_flat_slabs
Worked example extract_flat_slabs
 
Ref F2F Week 4 - Solution_unlocked.pdf
Ref F2F Week 4 - Solution_unlocked.pdfRef F2F Week 4 - Solution_unlocked.pdf
Ref F2F Week 4 - Solution_unlocked.pdf
 
Worked example extract_flat_slabs
Worked example extract_flat_slabsWorked example extract_flat_slabs
Worked example extract_flat_slabs
 
Columns and struts_-_solved
Columns and struts_-_solvedColumns and struts_-_solved
Columns and struts_-_solved
 
Numericals on Columns and struts_-_solved
Numericals on Columns and struts_-_solvedNumericals on Columns and struts_-_solved
Numericals on Columns and struts_-_solved
 
Unit i
Unit iUnit i
Unit i
 
Intze Tankd s sad sa das dsjkj kkk kds s kkksk
Intze Tankd s sad sa das dsjkj kkk kds s kkkskIntze Tankd s sad sa das dsjkj kkk kds s kkksk
Intze Tankd s sad sa das dsjkj kkk kds s kkksk
 
Intze Tank.ppt
Intze Tank.pptIntze Tank.ppt
Intze Tank.ppt
 
steel question.pdf.pdf
steel question.pdf.pdfsteel question.pdf.pdf
steel question.pdf.pdf
 
design of steel flyover
design of steel flyoverdesign of steel flyover
design of steel flyover
 
Chapter 3 (rib)MOSTAFA
Chapter 3 (rib)MOSTAFAChapter 3 (rib)MOSTAFA
Chapter 3 (rib)MOSTAFA
 
Compression member
Compression memberCompression member
Compression member
 
2 compression
2  compression2  compression
2 compression
 
Transformer design 2072 batch IOE - TU
Transformer design 2072 batch IOE - TU Transformer design 2072 batch IOE - TU
Transformer design 2072 batch IOE - TU
 

Recently uploaded

AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
AmarGB2
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 

Recently uploaded (20)

AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 

Week 9 Lecture Material_watermark.pdf

  • 1. DESIGN OF BATTEN PLATES USING BOLT CONNECTION
  • 2. Example: A batten column of 10-m long is carrying a factored load of 1150 kN. The column is restrained in position but not in direction at both ends. Design a built up column using channel sections placed back to back. Design batten plates using bolt connection.
  • 3. Let us try two ISMC 350 @ 413 N/m Relevant properties of ISMC 350 [ Table II SP 6 (1): 1964] 𝐴 = 5366 mm2, 𝑟𝑧𝑧 = 136.6 mm, 𝑟𝑦𝑦 = 28.3 mm 𝑡𝑓 = 13.5 mm 𝐼𝑧𝑧 = 10008 × 104 mm4 𝐼𝑦𝑦 = 430.6 × 104 mm4 𝑐𝑦𝑦 = 24.4 mm 𝑏 = 100 mm Solution: Design of column: 𝑃 = 1150 kN = 1150 × 103 N L = 1.0 × 10 × 103 = 10000 mm Let design axial compressive stress for the column be 125 MPa Required area = 1150×103 125 = 9200 mm2
  • 4. For 𝐾𝐿 𝑟 𝑒 = 80.53, 𝑓𝑦 = 250 MPa and buckling class c, the design compressive stress from Table 9c of IS 800 :2007 𝑓𝑐𝑑 = 136 − 136−121 10 × 0.53 = 135.2 MPa Therefore load carrying capacity = 𝐴𝑒𝑓𝑐𝑑 = 10732 × 135.2 × 10−3 = 1451 kN > 1200 kN, OK Area provided = 2 × 5366 = 10732 mm2 𝐿 𝑟𝑧𝑧 = 10000 136.6 = 73.21 The effective slenderness ratio, 𝐾𝐿 𝑟 𝑒 = 1.1 × 73.21 = 80.53 < 180; ok
  • 5. Spacing of channels: 2𝐼𝑧𝑧 = 2 𝐼𝑦𝑦 + 𝐴 𝑆 2 + 𝐶𝑦𝑦 2 or 2 × 10008 × 104 = 2 × 430.6 × 104 + 5366 𝑆 2 + 24.4 2 ⇒ 𝑆 = 218.4 mm Let us keep the channels at a spacing of 220 mm Spacing of battens: As per clause 7.7.3 of IS 800: 2007, 𝐶 𝑟𝑦𝑦 < 0.7𝜆 𝑜𝑟 𝐶 < 0.7 × 𝜆 × 𝑟𝑦𝑦 = 0.7 × 80.53 × 28.3 = 1595.3 mm Also 𝐶 𝑟𝑦𝑦 < 50 or 𝐶 < 50 × 28.3 = 1415 mm Hence, provide battens at a spacing of 1400 mm.
  • 6. Size of end battens (cl. 7.7.2.3 of IS 800 :2007): Provide 20 mm bolts. Edge distance = 1.5 × ℎ𝑜𝑙𝑒 𝑑𝑖𝑎𝑚𝑒𝑡𝑒𝑟 [Cl. 10.2.4.2 IS 800:2007] = 1.5 × 20 + 2 = 33 mm Effective depth = 𝑠 + 𝐶𝑦𝑦 = 220 + 2 × 24.4 = 268.8 mm > 2 × 100 mm Hence, chosen effective depth is safe. Overall depth = 268.8 + 2 × 33 = 334.8 mm Required thickness of batten = 1 50 × 220 + 2 × 50 = 6.4 mm Length of batten = 220 + 2 × 100 = 420 mm Provide 420×340×8 mm end batten plates.
  • 7. Size of intermediate battens (cl. 7.7.2.3 of IS 800 :2007): Effective depth = 3 4 × (220 + 2 × 𝐶𝑦𝑦) = 3 4 × (220 + 2 × 24.4) = 201.6 mm > 2 × 100 = 200 mm Hence adopt an effective depth of 210 mm Overall depth = 210 + 2 × 33 = 276 mm Therefore, provide a 420×300×8 mm batten plates @1400 mm c/c.
  • 8. Design forces: Transverse shear, 𝑉 = 2.5 100 × 𝑃 = 2.5 100 × 1150 × 103 = 28750 N Longitudinal shear 𝑉𝑙 = 𝑉𝐶 𝑁𝑆 Spacing of battens, C = 1400 mm N = No of parallel planes of battens = 2 S = minimum transverse distance between the centroid of the bolt/weld group = 220 + 2 × 50 = 320 mm ∴ 𝑉𝑙 = 28750×1400 2×320 = 62891 N Moment, 𝑀 = 𝑉𝐶 2𝑁 = 28750×1400 2×2 = 10.06 × 106 N-mm
  • 9. Check i) For end battens Shear stress = 62891 340×8 = 23.12 MPa < 250 3×1.1 = 131.22 MPa Bending stress = 6𝑀 𝑡𝑑2 = 6×10.06×106 8×3402 = 65.27 MPa < 250 1.1 = 227.27 MPa Hence safe. b) For intermediate battens Shear stress = 62891 300×8 = 26.2 MPa < 131.22 MPa Bending stress = 6×10.06×106 8×3002 = 83.83 MPa < 227.27 MPa Hence safe.
  • 10. Connection: The connection should be designed to transmit both shear and bending moment. Assuming 20 mm diameter bolts. Strength of bolt in single shear = 𝐴𝑛𝑏×𝑓𝑢𝑏 3×𝛾𝑚𝑏 = 0.78× 𝜋×202 4 ×400 3×1.25 × 10−3= 45.27 kN Minimum pitch, p = 2.5d=2.5×20=50 mm Minimum end distance, e = 1.5 d0 =1.5×22=33 mm Provide p = 60 mm and e = 35 mm kb is smaller of 35/(3×22), 60/(3×22)-0.25, 400/410, 1 Kb = 0.53
  • 11. Strength of bolt in bearing = 2.5𝑘𝑏𝑑𝑡𝑓𝑢/𝛾𝑚𝑏 = 2.5 × 0.53 × 20 × 8 × 410 1.25 × 10−3 = 69.5 kN Hence, strength of bolt = 45.27 kN Number of bolts required = 62891 45.27×103 = 1.39 Let us provide four bolts to take account the stresses due to bending moments as well. Check for combined action: For end battens Force in each bolt due to shear = 62891 4 = 15723 N Pitch provided = (D-2e)/3= (340-2×35)/3 = 90 mm. 𝑟2 = 2[(90/2)2+(90+90/2)2) = 2[452+1352] = 40500 mm2
  • 12. Force due to moment = 𝑀𝑟 𝑟2 = 10.06×106×135 40500 = 33533 N Resultant force = 157232 + 335332 = 37036 N = 37 kN < 45.26 kN Hence safe. Check for combined action: For intermediate battens Force in each bolt due to shear = 62891 4 = 15723 N Pitch provided = (D-2e)/3= (300-2×35)/3 = 77 mm. 𝑟2 = 2[(77/2)2+(77+77/2)2) = 2[38.52+115.52] = 29645 mm2 Force due to moment = 𝑀𝑟 𝑟2 = 10.06×106×115.5 29645 = 39195 N Resultant force = 157232 + 391952 = 42231N = 42.23 kN < 45.26 kN Hence safe.
  • 13. ISMC 350 350 mm 220 mm 220 mm 1400 mm Intermediate batten 420 mm×300 mm×8 mm End batten 420 mm×340 mm×8 mm 20 mm bolt Channels back-to-back connected by bolts:
  • 14. DESIGN OF BATTEN PLATES USING WELD CONNECTION
  • 15. Example: A batten column of 10-m long is carrying a factored load of 1150 kN. The column is restrained in position but not in direction at both ends. Design a built up column using channel sections placed back to back. Design batten plates using weld connection.
  • 16. Let us try two ISMC 350 @ 413 N/m Relevant properties of ISMC 350 [ Table II SP 6 (1): 1964] 𝐴 = 5366 mm2, 𝑟𝑧𝑧 = 136.6 mm, 𝑟𝑦𝑦 = 28.3 mm 𝑡𝑓 = 13.5 mm 𝐼𝑧𝑧 = 10008 × 104 mm4 𝐼𝑦𝑦 = 430.6 × 104 mm4 𝑐𝑦𝑦 = 24.4 mm 𝑏 = 100 mm Solution: Design of column: 𝑃 = 1150 kN = 1150 × 103 N L = 1.0 × 10 × 103 = 10000 mm Let design axial compressive stress for the column be 125 MPa Required area = 1150×103 125 = 9200 mm2
  • 17. For 𝐾𝐿 𝑟 𝑒 = 80.53, 𝑓𝑦 = 250 MPa and buckling class c, the design compressive stress from Table 9c of IS 800 :2007 𝑓𝑐𝑑 = 136 − 136;121 10 × 0.53 = 135.2 MPa Therefore load carrying capacity = 𝐴𝑒𝑓𝑐𝑑 = 10732 × 135.2 × 10;3 = 1451 kN > 1200 kN, OK Area provided = 2 × 5366 = 10732 mm2 𝐿 𝑟𝑧𝑧 = 10000 136.6 = 73.21 The effective slenderness ratio, 𝐾𝐿 𝑟 𝑒 = 1.1 × 73.21 = 80.53 < 180; ok
  • 18. Spacing of channels: 2𝐼𝑧𝑧 = 2 𝐼𝑦𝑦 + 𝐴 𝑆 2 + 𝐶𝑦𝑦 2 or 2 × 10008 × 104 = 2 × 430.6 × 104 + 5366 𝑆 2 + 24.4 2 ⇒ 𝑆 = 218.4 mm Let us keep the channels at a spacing of 220 mm Spacing of battens: As per clause 7.7.3 of IS 800: 2007, 𝐶 𝑟𝑦𝑦 < 0.7𝜆 𝑜𝑟 𝐶 < 0.7 × 𝜆 × 𝑟𝑦𝑦 = 0.7 × 80.53 × 28.3 = 1595.3 mm Also 𝐶 𝑟𝑦𝑦 < 50 or 𝐶 < 50 × 28.3 = 1415 mm Hence, provide battens at a spacing of 1400 mm.
  • 19. Size of end battens (cl. 7.7.2.3 of IS 800 :2007): Overall depth of batten = 220 + 2 × 𝐶𝑦𝑦 = 220 + 2 × 24.4 = 268.8 ≈ 270 mm Required thickness of batten = 1 50 × 220 = 4.4 mm Adopt battens with the thickness of 6-mm Let provide a 70 mm overlap of battens on channel flange for welding. [Overlap > 4 t = 4 × 6 = 24 mm] OK Length of batten = 220 + 2 × 70 = 360 mm Provide 360×270×6 mm end batten plates.
  • 20. Size of intermediate battens (cl. 7.7.2.3 of IS 800 :2007): Overall depth = 3 4 × (220 + 2 × 𝐶𝑦𝑦) = 3 4 × (220 + 2 × 24.4) = 201.6 mm > 2 × 100 = 200 mm Hence adopt overall depth of 220 mm Therefore, provide a 360×220×6 mm batten plates.
  • 21. Design forces: Transverse shear, 𝑉 = 2.5 100 × 𝑃 = 2.5 100 × 1150 × 103 = 28750 N Longitudinal shear 𝑉𝑙 = 𝑉𝐶 𝑁𝑆 Spacing of battens, C = 1400 mm N = No of parallel planes of battens = 2 S = minimum transverse distance between the centroid of the bolt/weld group = 220 + 2 × 50 = 320 mm ∴ 𝑉𝑙 = 28750×1400 2×320 = 62891 N Moment, 𝑀 = 𝑉𝐶 2𝑁 = 28750×1400 2×2 = 10.06 × 106 N-mm
  • 22. Check i) For end battens. Shear stress = 62891 270×6 = 38.82 MPa < 250 3×1.1 = 131.22 MPa Bending stress = 6𝑀 𝑡𝑑2 = 6×10.06×106 6×2702 = 138 MPa < 250 1.1 = 227.27 MPa Hence safe. b) For intermediate battens. Shear stress = 62891 220×6 = 47.64 MPa < 131.22 MPa Bending stress = 6×10.06×106 6×2202 = 207.85 MPa < 227.27 MPa Hence safe.
  • 23. Design of weld: Welding is done on all the four sides as shown in the figure. Let 𝑡 = throat thickness of weld. 𝐼𝑧𝑧 = 2 × 70 × 𝑡3 12 + 70 × 𝑡 × 220 2 2 + 2 × 𝑡 × 2203 12 Neglecting the term 2 × 70×𝑡3 12 being insignificant. Therefore, 𝐼𝑧𝑧 = 346.87 × 104𝑡 mm4 𝐼𝑦𝑦 = 2 × 𝑡 × 703 12 + 2 × 220 × 𝑡3 12 + 2 × 220 × 𝑡 × 70 2 2 Neglecting the term 2 × 220×𝑡3 12 being insignificant. Therefore, 𝐼𝑦𝑦 = 59.62 × 104𝑡 mm4
  • 24. 𝐼𝑝 = 𝐼𝑧𝑧 + 𝐼𝑦𝑦 = 346.87 × 104 𝑡 + 59.62 × 104 𝑡 = 406.49 × 104 𝑡 mm4 𝑟 = 220 2 2 + 70 2 2 = 115.43 mm 𝑐𝑜𝑠𝜃 = 35 115.43 = 0.30 Direct shear stress (cl. 10.5.9 of IS 800:2007) = 62891 2×70:2×220 𝑡 = 108.43 𝑡 N/mm2 Shear stress due to bending moment = 10.06×106×115.43 406.49×104𝑡 = 285.67 𝑡 N/mm2
  • 25. Combined stress due to shear and bending = 108.43 𝑡 2 + 285.67 𝑡 2 + 2 × 108.43 𝑡 × 285.67 𝑡 × 0.3 = 334.59 𝑡 < 410 3 × 1.25 = 189.4 or 𝑡 = 1.77 mm Size of weld = 1.77/0.7 = 2.5 mm The size of weld should not be less than 5 mm for 13.5 mm flange. Hence provide a 5 mm weld to make the connection.
  • 26. ISMC 350 350 mm 220 mm 220 mm 1400 mm Intermediate batten 360 mm×220 mm×6 mm End batten 360 mm×270 mm×6 mm 5 mm weld Channels back-to-back connected by welding:
  • 27. Design of Column Splices
  • 28. Splices • A joint when provided in the length of a member is called splices. • If a compression member is loaded concentrically, theoretically no splice is required. • However, the load is never truly axial and the real column has to resist bending due to this eccentrically applied load. Column sections can be spliced in the following cases: 1. When the length of the column is more than the length of the column section available. 2. In case of multistorey buildings, the section of the column required for the various storey may be different, as the load goes on increasing for columns of the lower storeys.
  • 29. Specifications for the design of splices • Where the ends of the compression members are faced for complete bearing over the whole area, these should be spliced to hold the connected members accurately in position, and to resist any tension when bending is present. • Where such members are not faced for complete bearing, splices should be design to transmit all the forces to which these are subjected. • Splices are designed as short columns.
  • 30. Various type of splices used in compression member
  • 31. Steps for the design of splice 1. For axial compressive load the splice plates are provided on the flanges of the two column sections to be spliced. If the column has machined ends, the splice is designed only to keep the columns in position and to carry tension due to the bending moment to which it may be subjected. The splice plate and the connection should be design to carry 50% of the axial load and tension. If the ends are not machined, the splice and connections are design to resist the total axial load and any tension, if present due to the bending moment.
  • 32. Steps for the design of splice • The load for the design of splice and connection due to axial load, 𝑃𝑢1 = 𝑃𝑢 4 (for machined ends) 𝑃𝑢1 = 𝑃𝑢 2 (for non machined ends) Where, 𝑃𝑢 is the axial factored load. • The load for the design of splice and connection due bending moment, 𝑃𝑢2 = 𝑀𝑢 𝑙𝑒𝑣𝑒𝑟 𝑎𝑟𝑚 Where, lever arm is the c/c distance of the two splice plates and 𝑀𝑢 is the factored bending moment.
  • 33. Steps for the design of splice 2. Splice plates are assumed to act as short columns (with zero slenderness ratio). So these plates will be subjected to yield stress (𝑓𝑦). 3. The cross-sectional area of the splice plate is calculated by dividing the appropriate portion of the factored load coming over the splice by the yield stress. c/s area required = 𝑃𝑢1+𝑃𝑢2 𝑓𝑦 4. The width of splice plate is usually kept equal to the width of the column flange. Width of splice = 𝑏𝑓 (width of flange) The thickness of the splice plate can be found by dividing the c/s area of the plates with its width.
  • 34. Steps for the design of splice 5. Nominal diameter of bolts for connection is assumed and the strength of the bolt is computed. 6. In case of bearing plate is to be designed between two column sections, the length and width of the plate are kept equal to the size of lower-storey column and the thickness is computed by equating the ultimate moment due to the factored load to the moment of resistance of plate section.
  • 35. Example: A column ISHB 300 @ 576.8 N/m is to support a factored axial load of 500 kN, shear force of 120 kN and bending moment of 40 kNm. Design the splice plate and connection using 4.6 grade bolts. Use steel of grade Fe 410. Solution: For steel of grade Fe 410: 𝑓𝑢 = 410 MPa, 𝑓𝑦 = 250 Mpa For bolts of grade 4.6: 𝑓𝑢𝑏 = 400 MPa Partial safety factors for material:(Table 5 IS 800:2007) 𝛾𝑚0 = 1.10 𝛾𝑚𝑏 = 1.25 The relevant properties of ISHB 300 @ 576.8 N/m are (Table I, SP 6-1) 𝐴 = 7485 mm2 𝑏𝑓 = 250 mm, 𝑡𝑓 = 10.6 mm 𝑡𝑤 = 7.6 mm
  • 36. Assume the ends of the column sections to be machined for complete bearing. As the column ends are flush, it is assumed that 50% of the load is transferred directly and 50% is transferred through the splice and fastenings. Therefore, The direct load on each splice plate = 50% 𝑜𝑓 500 2 = 125 kN Load on splice due to moment = 𝑀𝑢 𝑙𝑒𝑣𝑒𝑟 𝑎𝑟𝑚 = 40×103 300+6 = 130.72 kN (Assuming 6 mm thick splice plate, the lever arm = 300 + 6 mm) Total design load for splice, 𝑃𝑠 = 125 + 130.72 = 255.72 kN Sectional area of splice plate required = 𝑃𝑠 𝑓𝑦 = 255.72×103 250 = 1022.9 mm2
  • 37. Width of the splice plate should be kept equal to the width of the flange. Here, the width of the splice plate = 250 mm Hence, thickness of splice plate = 1022.9 250 = 4.09 mm ≮ 6 mm Provide a 250×6 mm splice plate. The length of the splice plate depends upon the number of bolts in vertical row. Let us provide 20 mm diameter bolts of grade 4.6. Strength of 20 mm diameter bolt in single shear (cl. 10.3.3, IS 800:2007) = 𝐴𝑛𝑏 𝑓𝑢𝑏 3 𝛾𝑚𝑏 = 245× 400 3 1.25 × 10−3 = 45.26 kN
  • 38. Strength of bolt in bearing = 2.5𝑘𝑏𝑑𝑡𝑓𝑢/𝛾𝑚𝑏 (cl. 10.3.4, IS 800:2007) For 20 mm diameter bolts the minimum edge distance, 𝑒 = 1.5 × 𝑑0 = 1.5 × 20 + 2 = 33 mm The minimum pitch, p = 2.5 × 20 = 50 mm Let us provide an edge distance (e) of 35 mm and pitch (p) of 60 mm. 𝑘𝑏 is smaller of 𝑒 3𝑑0 = 35 3×22 = 0.53 , 𝑝 3𝑑0 − 0.25 = 60 3×22 − 0.25 = 0.66 , 𝑓𝑢𝑏 𝑓𝑢 = 400 410 = 0.98 and 1.0 Hence 𝑘𝑏 = 0.53
  • 39. ∴ Strength in bearing = 2.5 × 0.53 × 20 × 6 × 410 1.25 × 10−3 = 52.15 kN Hence, the strength of bolt (Bv) = 45.26 kN Number of bolts required, n = 𝑃𝑠 𝐵𝑣 = 255.72 45.26 = 5.65 ≈ 6 Provide 6 bolts for each splice. Length of the splice plate = 2 × (2 × 60 + 2 × 35) = 380 mm Provide a splice plate 380×250×6 mm on column flanges as shown in the figure.
  • 40. Design of Column Splices due to Shear
  • 41. Example: A column ISHB 300 @ 576.8 N/m is to support a factored axial load of 500 kN, shear force of 120 kN and bending moment of 40 kNm. Design the splice plate and connection using 4.6 grade bolts. Use steel of grade Fe 410.
  • 42. Solution: For steel of grade Fe 410: 𝑓𝑢 = 410 MPa, 𝑓𝑦 = 250 Mpa For bolts of grade 4.6: 𝑓𝑢𝑏 = 400MPa Partial safety factors for material:(Table 5 IS 800:2007) 𝛾𝑚0 = 1.10𝛾𝑚𝑏 = 1.25 The relevant properties of ISHB 300 @ 576.8 N/m are (Table I, SP 6-1) 𝐴 = 7485 mm2𝑏𝑓 = 250 mm, 𝑡𝑓 = 10.6mm 𝑡𝑤 = 7.6 mm
  • 43. Assume the ends of the column sections to be machined for complete bearing. As the column ends are flush, it is assumed that 50% of the load is transferred directly and 50% is transferred through the splice and fastenings. Therefore, The direct load on each splice plate = 50% 𝑜𝑓 500 2 = 125 kN Load on splice due to moment = 𝑀𝑢 𝑙𝑒𝑣𝑒𝑟 𝑎𝑟𝑚 = 40×103 300+6 = 130.72 kN (Assuming 6 mm thick splice plate, the lever arm = 300 + 6 mm) Total design load for splice, 𝑃𝑠 = 125 + 130.72 = 255.72 kN Sectional area of splice plate required = 𝑃𝑠 𝑓𝑦 = 255.72×103 250 = 1022.9mm2
  • 44. Width of the splice plate should be kept equal to the width of the flange. Here, the width of the splice plate = 250 mm Hence, thickness of splice plate = 1022.9 250 = 4.09 mm ≮ 6 mm Provide a 250×6 mm splice plate. The length of the splice plate depends upon the number of bolts in vertical row. Let us provide 20 mm diameter bolts of grade 4.6. Strength of 20 mm diameter bolt in single shear (cl. 10.3.3, IS 800:2007) = 𝐴𝑛𝑏 𝑓𝑢𝑏 3 𝛾𝑚𝑏 = 245 × 400 3 1.25 × 10−3 = 45.26 kN
  • 45. Strength of bolt in bearing = 2.5𝑘𝑏𝑑𝑡𝑓𝑢/𝛾𝑚𝑏(cl. 10.3.4, IS 800:2007) For 20 mm diameter bolts the minimum edge distance, 𝑒 = 1.5 × 𝑑0 = 1.5 × 20 + 2 = 33 mm The minimum pitch, p = 2.5 × 20 = 50 mm Let us provide an edge distance (e) of 35 mm and pitch (p) of 60 mm. 𝑘𝑏 is smaller of 𝑒 3𝑑0 = 35 3×22 = 0.53 , 𝑝 3𝑑0 − 0.25 = 60 3×22 − 0.25 = 0.66 , 𝑓𝑢𝑏 𝑓𝑢 = 400 410 = 0.98 and 1.0 Hence 𝑘𝑏 = 0.53
  • 46. ∴ Strength in bearing = 2.5 × 0.53 × 20 × 6 × 410 1.25 × 10−3 = 52.15kN Hence, the strength of bolt (Bv) = 45.26 kN Number of bolts required, n = 𝑃𝑠 𝐵𝑣 = 255.72 45.26 = 5.65 ≈ 6 Provide 6 bolts for each splice. Length of the splice plate = 2 × (2 × 60 + 2 × 35) = 380 mm Provide a splice plate 380×250×6 mm on column flanges as shown in the figure.
  • 47. Splice plates for shear: The splice plate for the shear force is provided on the web. A pair of splice plate (one on each side of web) are provided. Let us provide 20 mm diameter bolts of grade 4.6. Strength of bolt in double shear = 45.26 × 2 = 90.52 kN Strength in bearing = 2.5𝑘𝑏𝑑𝑡𝑓𝑢/𝛾𝑚𝑏 Where, 𝑘𝑏 = 0.53 (taking 𝑒 = 35 mm and p = 60 mm), 𝑡 = 7.6 mm (web thickness) ∴ Strength in bearing = 2.5 × 0.53 × 20 × 7.6 × 410 1.25 × 10−3 = 66.06 kN Hence, strength of 20 mm bolt = 66.06kN
  • 48. Shear force in the web, 𝑉 = 120 kN Number of bolts required = 120 66.06 = 1.8 ≈ 2 Provide 2, 20 mm diameter bolts on each side of the splice. Length of the splice plate = 4 × 35 = 140 mm Width of the splice plate = 60 + 2 × 35 = 130 mm Design shear strength of splice plate (cl. 8.4, IS 800:2007), 𝑉𝑑 = 𝑓𝑦 3 × 𝛾𝑚0 × ℎ × 𝑡 = 250 3 × 1.1 × 130 × 2𝑡𝑠 × 10−3 = 34.12 𝑡𝑠 kN
  • 49. Now, 𝑉𝑑 > 𝑉 or 34.12 𝑡𝑠 > 120 Thickness of the splice plate required, 𝑡𝑠 = 120 34.12 = 3.52 mm ≮ 6mm So provide a pair of 140×130×6 mm shear splice plates on each side of the web as shown in the figure.
  • 52. INTRODUCTION • Flexural members or bending members are commonly called BEAMS. • A beam is a structural member subjected to transverse loads i.e., loads perpendicular to the longitudinal axis. • The load produce Bending moment & Shear forces.
  • 54. DIFFERENT TYPES OF BEAMS • JOIST: A closely spaced beams supporting floors or roofs of building but not supporting the other beams. • GIRDER: A large beam, used for supporting a number of joists. • PURLIN: Purlins are used to carry roof loads in trusses. • STRINGER: In building, beams supporting stair steps; in bridges a longitudinal beam supporting deck floor & supported by floor beam. • FLOOR BEAM: A major beam supporting other beams in a building; also the transverse beam in bridge floors.
  • 55. • SPANDREL BEAM: In a building, a beam on the outside perimeter of a floor, supporting the exterior walls and outside edge of the floor • GIRT: A horizontal beam spanning the wall columns of industrial buildings used to support wall coverings is called a GIRT. • RAFTER: A roof beam usually supported by purlins. • LINTELS: This type of beams are used to support the loads from the masonry over the openings . DIFFERENT TYPES OF BEAMS
  • 56. NATURE OF FORCES ACTING ON BEAMS • It is assumed that the beam is subjected to only transverse loading. • All the loads and sections lie in the plane of symmetry. • It follows that such a beam will be primarily subjected to bending accompanied by shear in the loading plane with no external torsion and axial force.
  • 57. • The problem of torsion can not completely be avoided in a beam even if the beam shape is symmetrical and loads are in the plane of symmetry. • The reason is the instability caused by compressive stresses. Such instability is defined as LATERAL BUCKLING . When it is involving only local components of a beam it is called LOCAL BUCKLING. • Local buckling is a function of width-thickness ratio. NATURE OF FORCES ACTING ON BEAMS
  • 58. Primary modes of failure of beams are as follows: 1. Bending failure 2. Shear failure 3. Deflection failure 1. Bending failure: Bending failure generally occurs due to crushing of compression flange or fracture of tension flange of the beam. 2. Shear failure: This occurs due to buckling of web of the beam near location of high shear forces. The beam can fail locally due to crushing or buckling of the web near the reaction of concentrated loads. 3. Deflection failure: A beam designed to have adequate strength may become unsuitable if it is not able to support its load without excessive deflections. MODES OF FAILURE
  • 59. TYPES OF STEEL SECTIONS
  • 61. CONSIDERATIONS IN DESIGN OF BEAMS • Beams should be proportioned for strength in bending keeping in view of the lateral and local stability of the compression flange. • The selected shape should have capacity to withstand essential strength in shear and local bearing . • The beam dimension should be suitably proportioned for stiffness, keeping in mind their deflections and deformations under service conditions .
  • 62. LIMITATIONS OF ANGLES , T-SECTIONS AND CHANNELS • Angles and T-sections are weak in bending. • Channels only be used for light loads. • The rolled steel channels and angle sections are used in those cases where they can be designed and executed satisfactory. • This is because the load is not likely to be in the plane, which removes torsional eccentricities . • Also, it is complicated to calculate the lateral buckling characteristics of these sections .