Integrated Project OF Introduction
to Drawing AND Construction
Industry
GROUP UNKNOWN
Leader:SU BANG ZHENG
Member:SII Siaw Hua :Ryan Bunsu
:Ng Sheng Zhe :Qayyum
:Pui Chun Shian :Mashruk Asad
Title:Architect
what is an architect
ARCHITECT IS A PERSON WHO DESIGNS BUILDINGS
AND ADVISES IN THEIR CONSTRUCTION.
INTRODUCTION TO
CONSTRUCTION INDUSTRY
RESPONSIBILITIES
&
TASK AT DIFFERENT STAGES OF
CONSTRUCTION
&
THE SCOPE OF WORK HANDLE BY ARCHITECT
attend site meeting or analysis
and other problem which may
be critical
Need to know the full detail of
the project and follow the
required and some request by
clients
Work with other professional such
as engineer and QS
Inform clients other professional
required
The Architect has the authority to order
inspection or testing of the Work by
contractor.
writing the term of condition of the
appointment and request
confirmation
state the clients’ financial limit and
request to the Professional
BEFORE CONSTRUCTION
1.meet with clients
2.communicate with
other professionals
3.participate in all
meetings
4.research for design
criteria
5.report progress to
clients
6.prepare blueprints
7.submit the
drawings to the
clients
• Second phase in the design of a project
• From the sketch for the initial design
• provides Conceptual Site Plans, Preliminary Building Plans, Sections, Elevations and/or
other drawings required to communicate the design intent.
• Allow 2-3 weeks for the process
Schematic Design/Sketch
• GATHER ALL THE INFORMATION
• THE ARCHITECT COMES UP WITH KEY CONCEPT
AND ROUGH SKETCHES.
• ALLOW 1-2 WEEKS FOR THE PROCESS
1.Initial Design
2.Schematic design
• Second phase in the design of a project
• From the sketch for the initial design
• provides Conceptual Site Plans, Preliminary Building Plans, Sections,
Elevations and/or other drawings required to communicate the design
intent.
• Allow 2-3 weeks for the process
3.Design
development
• Turn a rough sketch into the real
building design complete with
floor plan,roof design etc.
• Include scale drawing,basic
structural plan,and basic
specification for main
components of a building
• Allow 2 weeks for this process
4.Construction document
• The blueprint are prepare to obtain the building
permit.
• The blueprint should be detail enough that you
can get apple-to-apple bids from contractor and
sub-contractor
• Answering queries from the
various contractor and sub-
contractor
• Analysis and checking tender
compliance
• Architect and clients will
cooperate evaluate and choose
the best contractor or sub-
contractor(lowest price)
5.BIDDING OR NEGOTIATION
During construction
advise clients on stage payment
Solve the problem.
inspecting the building work
observe the site progress.
be the middle man between clients and contractor
6.Construction Administration
• Architect function as the owner’s agent
• preparing additional detailed drawing if needed
• approving the contractor’s request for progress
payment(ensure that the price is fair and reasonable)
• resolving any issues stemming from conflicts.
After construction
• Part of the payment due to the builder – the retention
– is held back for up to twelve months and is only
paid out on the architect’s instruction, after any
defects have been rectified by the contractor
• Remember that the architect’s Opinion on
Compliance with Planning and Building Regulations
is subject to work not being changed during
construction.
TYPE&FUNCTION OF
ARCHITECTURAL DRAWING
AND
STAGE&EXAMPLE USED TO
COMMUNICATION IDEA
INTRODUCTION TO DRAWING
Architectural drawing
• type of drawing gives a complete view of
building.
• usually use A0 size paper (841mm X
1189mm)
• to develop the rough
sketch
• have a better
communication idea.
1.Sketching
Function
BUBBLE
DIAGRAM
&
PRELIMINARY
DESIGN
2.Schematic design
FUNCTION
can used to represent the flows.
To develop,explore,communicate idea and solution.
i)Bubble Diagram
ii)Preliminary design
FUNCTION
TO EXPLORING DESIGN
CONCEPT,MATERIAL SELECTION,AND
A BASIS FOR THE PREPARATION OF
FINISHED WORKING DESIGN
3.Presentation drawing
Function
To explain the merits of the building
WORKING
DRAWING
&
DETAIL DRAWING
4.Design Development
i)WORKING DRAWING
Location Drawing
Assembly Drawing
Component Drawing
Location drawing
Function
• show the location of construction element.
Floor plan
• Define the spaces & its functional relationship
Fix window Bay window
Pocket door Bifold door
Project brief
Roof
BUILDING ELEVATION
Function
To show four main faces of a building:north,south,east & west.
Assembly drawing
Function
to list all parts and sub-assemblies that make the final product.
Function
It can shows individual
components in the unfixed
state
Function• TO SHOW HOW THE COMPONENT PART FIT
TOGETHER.
• TO SEE CLEARLY HOW THE INDIVIDUAL PART
MADE
ii)DETAIL DRAWING
Thank You!!
Reference
• http://www.slideshare.net/FiQahhAmiNn/types-of-
drawing-29679170
• http://www.prospects.ac.uk/
architect_job_description.htm
• http://gilespike.com/roles-and-responsibilities.html
• http://www.lowneyarch.com/process/schem.html
• http://www.planningportal.gov.uk/uploads/1app/
maps_plans_and_planning_apps.pdf
• http://www.aia.org/aiaucmp/groups/secure/documents/
pdf/aiap026834.pdf
• http://perkinswill.com/sites/default/files/ID
%202_PWRJ_Vol0401_01_Architectural%20Services
%20During%20Construction.pdf

Iciitd2 150816125948-lva1-app6892