The document discusses new security and safety directives issued by the High Commission for Industrial Security (HCIS) in Saudi Arabia that must be applied to all new and existing industrial projects and facilities. It outlines the HCIS approval process for security and safety designs and systems. This involves conducting a security vulnerability assessment, developing preliminary and detailed designs, and obtaining HCIS approval at various stages. It also discusses general requirements and specific directives for security measures, fire protection systems, and developing an incident management system to ensure safety. Non-compliance with the new standards may result in serious consequences for plant owners.
This document provides a crane lifting plan and risk assessment for a lifting operation. It details the crane and lift information, including load details, lifting tackle, and crane setup procedures. Safety procedures are outlined, such as conducting a site inspection, briefing personnel, establishing communication methods, and following weather restrictions. Personnel qualifications and roles are defined. The plan is intended to ensure the lifting operation is carried out safely in compliance with relevant standards and regulations.
6 71-0051 rev. 4 standard specification for pipeline construction (onshore)MAHESH PANDIT
This document outlines standards and specifications for onshore pipeline construction. It covers the scope of work, which includes clearing and grading the right-of-way, trenching, bending, welding, laying, backfilling, tie-ins and special installations. It references applicable codes and standards. Safety measures are outlined, including requirements when working near existing pipelines, cables and high voltage lines. Specific safety instructions are provided for working within 50 meters of high voltage systems.
This document provides a risk assessment for hydro testing and pressure testing of pipe works conducted by Arabian Bemco Contracting Co. It identifies several hazards associated with the work including high pressure leaks, over pressure, slips trips and falls. For each hazard, it lists the persons at risk, initial risk rating, and proposed control measures to reduce the risk. The control measures include training, use of personal protective equipment, safety signage, permitting, and having emergency response measures in place.
Saes w-011-welding on plot ( process ) pipingabhi10apr
This document outlines welding requirements for on-plot piping at Saudi Aramco. It specifies approved welding processes, welding consumables, welding procedures, welder qualification requirements, joint details, corrosion resistant materials, technique and workmanship standards, preheat and post weld heat treatment needs, production weld hardness testing, inspection access, weld identification, inspection requirements, and repair standards. The document provides detailed requirements to ensure welding is completed according to applicable codes and standards for safety and quality.
This document provides important notices and disclaimers regarding NFPA standards. It states that NFPA develops standards through a consensus process but does not guarantee the accuracy of the information or endorse any judgments or opinions in the standards. It also notes that NFPA standards may be updated over time and provides instructions for determining the most current version. The document outlines NFPA's policies regarding intellectual property, compliance with laws, interpretations of standards, and other legal matters pertaining to the use of NFPA standards.
This document provides guidance for inspectors on paints and coatings. It outlines approved coating systems for various applications and services, including internal and external pipe coatings for buried, insulated, and atmospheric exposure conditions. It also provides standards on surface preparation, coating application, thickness measurement, and repair. Inspectors are instructed to follow the coating manufacturer's recommendations and use properly calibrated equipment to ensure coatings meet thickness and cure requirements.
This document is a proposal from Dirham Mujahid Al-Salah Est. for general contracting, building, road construction, mechanical, electrical maintenance and operation works. It was prepared for the Master Gas Pipeline Phase I Projects Division of the Ministry of Energy, Industry and Mineral Resources in Riyadh, Saudi Arabia, under contract number S6il0032833 with C.A.T. International Co. LTD. The proposal includes the contractor's contact information and credentials.
The document provides a method statement for piping installation works at the Dabbiya site for the Al Dabbiya Phase-1 Additional Injection Wells Tie-Ins project. It outlines the scope of works, sequence of activities, resources, HSE requirements, and emergency contacts. Piping works will involve transporting prefabricated spools to site, lifting them into position, welding field joints, installing valves, and testing. Welding will follow approved procedures and NDT testing. HSE precautions like PPE and fire safety will be enforced during the medium risk work.
This document provides a crane lifting plan and risk assessment for a lifting operation. It details the crane and lift information, including load details, lifting tackle, and crane setup procedures. Safety procedures are outlined, such as conducting a site inspection, briefing personnel, establishing communication methods, and following weather restrictions. Personnel qualifications and roles are defined. The plan is intended to ensure the lifting operation is carried out safely in compliance with relevant standards and regulations.
6 71-0051 rev. 4 standard specification for pipeline construction (onshore)MAHESH PANDIT
This document outlines standards and specifications for onshore pipeline construction. It covers the scope of work, which includes clearing and grading the right-of-way, trenching, bending, welding, laying, backfilling, tie-ins and special installations. It references applicable codes and standards. Safety measures are outlined, including requirements when working near existing pipelines, cables and high voltage lines. Specific safety instructions are provided for working within 50 meters of high voltage systems.
This document provides a risk assessment for hydro testing and pressure testing of pipe works conducted by Arabian Bemco Contracting Co. It identifies several hazards associated with the work including high pressure leaks, over pressure, slips trips and falls. For each hazard, it lists the persons at risk, initial risk rating, and proposed control measures to reduce the risk. The control measures include training, use of personal protective equipment, safety signage, permitting, and having emergency response measures in place.
Saes w-011-welding on plot ( process ) pipingabhi10apr
This document outlines welding requirements for on-plot piping at Saudi Aramco. It specifies approved welding processes, welding consumables, welding procedures, welder qualification requirements, joint details, corrosion resistant materials, technique and workmanship standards, preheat and post weld heat treatment needs, production weld hardness testing, inspection access, weld identification, inspection requirements, and repair standards. The document provides detailed requirements to ensure welding is completed according to applicable codes and standards for safety and quality.
This document provides important notices and disclaimers regarding NFPA standards. It states that NFPA develops standards through a consensus process but does not guarantee the accuracy of the information or endorse any judgments or opinions in the standards. It also notes that NFPA standards may be updated over time and provides instructions for determining the most current version. The document outlines NFPA's policies regarding intellectual property, compliance with laws, interpretations of standards, and other legal matters pertaining to the use of NFPA standards.
This document provides guidance for inspectors on paints and coatings. It outlines approved coating systems for various applications and services, including internal and external pipe coatings for buried, insulated, and atmospheric exposure conditions. It also provides standards on surface preparation, coating application, thickness measurement, and repair. Inspectors are instructed to follow the coating manufacturer's recommendations and use properly calibrated equipment to ensure coatings meet thickness and cure requirements.
This document is a proposal from Dirham Mujahid Al-Salah Est. for general contracting, building, road construction, mechanical, electrical maintenance and operation works. It was prepared for the Master Gas Pipeline Phase I Projects Division of the Ministry of Energy, Industry and Mineral Resources in Riyadh, Saudi Arabia, under contract number S6il0032833 with C.A.T. International Co. LTD. The proposal includes the contractor's contact information and credentials.
The document provides a method statement for piping installation works at the Dabbiya site for the Al Dabbiya Phase-1 Additional Injection Wells Tie-Ins project. It outlines the scope of works, sequence of activities, resources, HSE requirements, and emergency contacts. Piping works will involve transporting prefabricated spools to site, lifting them into position, welding field joints, installing valves, and testing. Welding will follow approved procedures and NDT testing. HSE precautions like PPE and fire safety will be enforced during the medium risk work.
This document outlines the scope of work for an EPC contract for a Central Area Field Complex Project in Algeria. It includes 180 pages describing the project overview, general contracting requirements, work descriptions, design and engineering scope, HSE requirements, materials procurement, construction, commissioning, and special notes. The contractor will be responsible for engineering, procurement, construction, and commissioning of the facilities, and must comply with Algerian regulations and international HSE standards.
This presentation simplifies the key postulates of Static and Mobile Pressure Vessel Rules (2016) last amended in 2018, for the design, License, operation and maintenance of LNG storage and regasification station.
This document provides guidance on overhead crane safety. It outlines requirements for daily operator inspections, including checking the hook, wire rope, control devices and runway systems. Periodic inspections by a qualified person are also required, with frequencies ranging from quarterly to annually depending on crane use. Operational safety procedures are reviewed, such as following signal instructions, maintaining clear views, and not overloading. Recommended forms include a maintenance log, checklists, and training questionnaires. Standard hand signals for crane operations are also presented.
This document provides construction standards for cable trenches as part of Saudi Electricity Company's underground distribution network. It outlines procedures for obtaining rights-of-way, installing cables directly buried in trenches, soil classification and testing, installing duct banks at road crossings, and notes on horizontal directional drilling works. The document specifies design and installation practices to achieve standardization and ensure satisfactory and economical operation with minimal operational errors for safety and reliability.
RA for Hot works at MOE-Ghim Moh (Ceiling support works).pdfMohPhoolay
This document is an activity-based risk assessment form for hot works (ceiling support works) being conducted at the MOE at Ghim Moh project by Create Logic Pte Ltd. It identifies 5 major hazards - improper manual handling, hot works causing fires/explosions, arc welding electrocutions and fires, gas cutting and arc welding fires, and trip and fall hazards from gas hoses and cables. For each hazard, it evaluates the existing and additional risk controls and assigns risk probability numbers. It also provides a risk level matrix to define acceptable risk levels and recommended actions.
Inspection of Pressure Vessels as per ASME Sec VIII Division -1Gaurav Singh Rajput
The document discusses a seminar presentation on inspection of pressure vessels according to ASME Section VIII Division 1. The presentation outline covers what is authorized inspection, an overview of ASME codes, code stamps, inspection responsibilities of manufacturers and authorized inspectors, the scope and organization of ASME Section VIII, and inspection requirements of Section VIII Division 1. It provides background information on ASME, outlines the hierarchy of standards including various ASME code sections, and describes the organization and key requirements of Section VIII Division 1 for pressure vessel inspection.
The document provides guidance on quality inspection procedures for low voltage switchboards. It discusses the justification and importance of quality inspection to ensure compliance with standards and customer requirements. The key aspects covered include incoming delivery inspection, in-process inspection during manufacturing, and final inspection. In-process inspection uses checklists to verify conformity after each production step is completed, while final inspection involves comprehensive checks of mechanical, electrical, and other characteristics before equipment is shipped. Maintaining rigorous quality inspection is important to reduce costs from defects, protect safety, and uphold the company's brand reputation.
This document provides procedures for the fabrication, installation, and erection of piping. It outlines responsibilities for construction management, engineering, quality control, and health and safety. It also describes procedures for receiving and storing materials, pre-fabrication including cutting, beveling and fit-up, welding, testing, and installation of underground and erected piping. Attachments include job safety analyses, work flows, lifting plans, and inspection forms. The goal is to ensure compliance with contractual and health, safety, and environmental requirements for piping work.
The document outlines plans for temporary site facilities for the Dasherkandi Sewage Treatment Plant Project. It details the scope of work, organization structure, construction methodology, safety plans, and site layout. Temporary facilities will include site offices, dormitories, workshops, warehouses, and batching plants. The project aims to treat wastewater from several areas of Dhaka to reduce pollution in the Balu River.
NFPA 2001,Clean Agent Fire Extinguishing Systems.pdfBhuiyan academy
NFPA 2001, Clean Agent Fire Extinguishing Systems. This edition of NFPA 2001, Standard on Clean Agent Fire Extinguishing Systems, was prepared by the
Technical Committee on Gaseous Fire Extinguishing Systems and acted on by the NFPA membership
during the 2021 NFPA Technical Meeting held June 14-July 2. It was issued by the Standards Council
on August 26, 2021, with an effective date of September 15, 2021, and supersedes all previous
editions.
This edition of NFPA 2001 was approved as an American National Standard on September 15,
2021. The Technical Committee on Halon Alternative Protection Options was organized in 1991 and immediately started work to address the new total flooding clean agents that were being developed to replace Halon 1301. A need existed for an explanation of how to design, install, maintain, and operate systems using these new clean agents, and NFPA 2001 was established to address that need.
The 1994 edition was the first edition of NFPA 2001. The standard was revised in 1996, 2000, and 2004.IMPORTANT NOTE: This NFPA document is made available for
use subject to important notices and legal disclaimers. These notices
and disclaimers appear in all publications containing this document
and may be found under the heading “Important Notices and
Disclaimers Concerning NFPA Standards. ” They can also be viewed
at wurw.nfpa.org/disclaimers or obtained on request from NFPA.
Saudi arabian-engineering-standards-saes-j-502nadim khan
This document establishes standards for the design and construction of analyzer shelters at Saudi Aramco. It specifies requirements for shelters to be pre-engineered, packaged units containing sampling systems, analyzers, ventilation, electrical, and other services. Shelters must be able to withstand Saudi Aramco's environmental conditions and hazardous area classifications. The document provides detailed guidelines on shelter layout, size, location, mechanical/structural design, electrical systems, and other design aspects. It aims to ensure shelters and enclosed analyzers are safely and reliably operated in Saudi Aramco's facilities.
PetroSync - Pre-Commissioning, Commissioning and Start-UpPetroSync
Successful commissioning new or starting-up revised equipment and systems requires meticulous planning, organizing and controlling. Careful methodical, detailed planning – early – is the key to the success of any commissioning.
A Hazard and Operability (HAZOP) study is a structured and systematic examination of a planned or existing process or operation in order to identify and evaluate problems that may represent risks to personnel or equipment, or prevent efficient operation.
This document provides a hazard identification and risk assessment for welding work being conducted at a project site in Versova, Mumbai. It identifies several hazards associated with welding including electric shock, fire, health issues from fumes and sparks, and improper use of equipment. For each hazard, it evaluates the severity and likelihood of risks. It also identifies applicable legal requirements and provides control measures to reduce risks. Controls include inspection of equipment, use of protective gear like face shields, isolating work areas, training workers, and ensuring only authorized personnel conduct welding. The overall risk level is determined to be "acceptable and non-significant" when proper controls are implemented.
The document provides guidelines for OSHA compliance officers to inspect mobile cranes used in construction. It discusses lifting principles and considerations for crane operations. The guidelines describe the inspection process and identify 18 critical components to examine, such as the electrical system, load charts, and safety devices. Maintaining and properly inspecting cranes is important for preventing accidents on construction sites.
8 Lifting Operations with mobile crane Risk Assessment Templates
Crane checks on arrival to site
PRIOR TO USE
Access of crane to work areas
Siting and setting up of crane
Lifting of equipment and material
(Mobile crane Operator)
Crane supervision
Crane Maintenance
(revised 06-06-2018)
The document discusses HAZOP (Hazard and Operability) studies and QRA (Qualitative Risk Analysis) studies conducted in process industries. It provides details on how HAZOP studies work, including forming a HAZOP team, identifying system elements and parameters, considering potential deviations, and identifying hazards. It also discusses QRA methodology which includes hazard identification, scenario selection, frequency and consequence estimation. The document emphasizes the importance of HAZOP and QRA studies in identifying risks and improving safety.
( Itp ag pipe) rapid p006 a scs qac itp 3200 0007Tonni Bruce
This document is a Field Inspection and Test Plan (ITP) for above ground piping work on the Rapid Package 6A LLDPE Project. It defines inspection points including hold points, witness points, and approval points. It references applicable codes and standards. The ITP covers material control, qualification of welding procedures, welders, and NDT technicians, consumable control, and defines required inspection forms. Inspection points include material receiving, storage and preservation, WPS and welder qualification, consumable receiving, storage, baking and issuance. The ITP provides acceptance criteria for ensuring quality of above ground piping work.
Pre Commissioning Testing Training and Maintenance of Instrumentation Analyzer, Metering Skid, Crude Oil Samplers, Corrosion, CP Radio Monitoring system, Laser HF and H2S Hydrogen, Oxygen Emerson oxymitter, Emerson Bentely Navada Vibration Analyzers, Thermography, Gas cement Petroleum Analyzers, Gas Chromatograph in Refinery Oil Gas Plants Petrochemical Aramco Sabic.
Extensive coordination between client and supplier in make sure all resolution successfully covered to achieve end client satisfaction.
This document outlines the scope of work for an EPC contract for a Central Area Field Complex Project in Algeria. It includes 180 pages describing the project overview, general contracting requirements, work descriptions, design and engineering scope, HSE requirements, materials procurement, construction, commissioning, and special notes. The contractor will be responsible for engineering, procurement, construction, and commissioning of the facilities, and must comply with Algerian regulations and international HSE standards.
This presentation simplifies the key postulates of Static and Mobile Pressure Vessel Rules (2016) last amended in 2018, for the design, License, operation and maintenance of LNG storage and regasification station.
This document provides guidance on overhead crane safety. It outlines requirements for daily operator inspections, including checking the hook, wire rope, control devices and runway systems. Periodic inspections by a qualified person are also required, with frequencies ranging from quarterly to annually depending on crane use. Operational safety procedures are reviewed, such as following signal instructions, maintaining clear views, and not overloading. Recommended forms include a maintenance log, checklists, and training questionnaires. Standard hand signals for crane operations are also presented.
This document provides construction standards for cable trenches as part of Saudi Electricity Company's underground distribution network. It outlines procedures for obtaining rights-of-way, installing cables directly buried in trenches, soil classification and testing, installing duct banks at road crossings, and notes on horizontal directional drilling works. The document specifies design and installation practices to achieve standardization and ensure satisfactory and economical operation with minimal operational errors for safety and reliability.
RA for Hot works at MOE-Ghim Moh (Ceiling support works).pdfMohPhoolay
This document is an activity-based risk assessment form for hot works (ceiling support works) being conducted at the MOE at Ghim Moh project by Create Logic Pte Ltd. It identifies 5 major hazards - improper manual handling, hot works causing fires/explosions, arc welding electrocutions and fires, gas cutting and arc welding fires, and trip and fall hazards from gas hoses and cables. For each hazard, it evaluates the existing and additional risk controls and assigns risk probability numbers. It also provides a risk level matrix to define acceptable risk levels and recommended actions.
Inspection of Pressure Vessels as per ASME Sec VIII Division -1Gaurav Singh Rajput
The document discusses a seminar presentation on inspection of pressure vessels according to ASME Section VIII Division 1. The presentation outline covers what is authorized inspection, an overview of ASME codes, code stamps, inspection responsibilities of manufacturers and authorized inspectors, the scope and organization of ASME Section VIII, and inspection requirements of Section VIII Division 1. It provides background information on ASME, outlines the hierarchy of standards including various ASME code sections, and describes the organization and key requirements of Section VIII Division 1 for pressure vessel inspection.
The document provides guidance on quality inspection procedures for low voltage switchboards. It discusses the justification and importance of quality inspection to ensure compliance with standards and customer requirements. The key aspects covered include incoming delivery inspection, in-process inspection during manufacturing, and final inspection. In-process inspection uses checklists to verify conformity after each production step is completed, while final inspection involves comprehensive checks of mechanical, electrical, and other characteristics before equipment is shipped. Maintaining rigorous quality inspection is important to reduce costs from defects, protect safety, and uphold the company's brand reputation.
This document provides procedures for the fabrication, installation, and erection of piping. It outlines responsibilities for construction management, engineering, quality control, and health and safety. It also describes procedures for receiving and storing materials, pre-fabrication including cutting, beveling and fit-up, welding, testing, and installation of underground and erected piping. Attachments include job safety analyses, work flows, lifting plans, and inspection forms. The goal is to ensure compliance with contractual and health, safety, and environmental requirements for piping work.
The document outlines plans for temporary site facilities for the Dasherkandi Sewage Treatment Plant Project. It details the scope of work, organization structure, construction methodology, safety plans, and site layout. Temporary facilities will include site offices, dormitories, workshops, warehouses, and batching plants. The project aims to treat wastewater from several areas of Dhaka to reduce pollution in the Balu River.
NFPA 2001,Clean Agent Fire Extinguishing Systems.pdfBhuiyan academy
NFPA 2001, Clean Agent Fire Extinguishing Systems. This edition of NFPA 2001, Standard on Clean Agent Fire Extinguishing Systems, was prepared by the
Technical Committee on Gaseous Fire Extinguishing Systems and acted on by the NFPA membership
during the 2021 NFPA Technical Meeting held June 14-July 2. It was issued by the Standards Council
on August 26, 2021, with an effective date of September 15, 2021, and supersedes all previous
editions.
This edition of NFPA 2001 was approved as an American National Standard on September 15,
2021. The Technical Committee on Halon Alternative Protection Options was organized in 1991 and immediately started work to address the new total flooding clean agents that were being developed to replace Halon 1301. A need existed for an explanation of how to design, install, maintain, and operate systems using these new clean agents, and NFPA 2001 was established to address that need.
The 1994 edition was the first edition of NFPA 2001. The standard was revised in 1996, 2000, and 2004.IMPORTANT NOTE: This NFPA document is made available for
use subject to important notices and legal disclaimers. These notices
and disclaimers appear in all publications containing this document
and may be found under the heading “Important Notices and
Disclaimers Concerning NFPA Standards. ” They can also be viewed
at wurw.nfpa.org/disclaimers or obtained on request from NFPA.
Saudi arabian-engineering-standards-saes-j-502nadim khan
This document establishes standards for the design and construction of analyzer shelters at Saudi Aramco. It specifies requirements for shelters to be pre-engineered, packaged units containing sampling systems, analyzers, ventilation, electrical, and other services. Shelters must be able to withstand Saudi Aramco's environmental conditions and hazardous area classifications. The document provides detailed guidelines on shelter layout, size, location, mechanical/structural design, electrical systems, and other design aspects. It aims to ensure shelters and enclosed analyzers are safely and reliably operated in Saudi Aramco's facilities.
PetroSync - Pre-Commissioning, Commissioning and Start-UpPetroSync
Successful commissioning new or starting-up revised equipment and systems requires meticulous planning, organizing and controlling. Careful methodical, detailed planning – early – is the key to the success of any commissioning.
A Hazard and Operability (HAZOP) study is a structured and systematic examination of a planned or existing process or operation in order to identify and evaluate problems that may represent risks to personnel or equipment, or prevent efficient operation.
This document provides a hazard identification and risk assessment for welding work being conducted at a project site in Versova, Mumbai. It identifies several hazards associated with welding including electric shock, fire, health issues from fumes and sparks, and improper use of equipment. For each hazard, it evaluates the severity and likelihood of risks. It also identifies applicable legal requirements and provides control measures to reduce risks. Controls include inspection of equipment, use of protective gear like face shields, isolating work areas, training workers, and ensuring only authorized personnel conduct welding. The overall risk level is determined to be "acceptable and non-significant" when proper controls are implemented.
The document provides guidelines for OSHA compliance officers to inspect mobile cranes used in construction. It discusses lifting principles and considerations for crane operations. The guidelines describe the inspection process and identify 18 critical components to examine, such as the electrical system, load charts, and safety devices. Maintaining and properly inspecting cranes is important for preventing accidents on construction sites.
8 Lifting Operations with mobile crane Risk Assessment Templates
Crane checks on arrival to site
PRIOR TO USE
Access of crane to work areas
Siting and setting up of crane
Lifting of equipment and material
(Mobile crane Operator)
Crane supervision
Crane Maintenance
(revised 06-06-2018)
The document discusses HAZOP (Hazard and Operability) studies and QRA (Qualitative Risk Analysis) studies conducted in process industries. It provides details on how HAZOP studies work, including forming a HAZOP team, identifying system elements and parameters, considering potential deviations, and identifying hazards. It also discusses QRA methodology which includes hazard identification, scenario selection, frequency and consequence estimation. The document emphasizes the importance of HAZOP and QRA studies in identifying risks and improving safety.
( Itp ag pipe) rapid p006 a scs qac itp 3200 0007Tonni Bruce
This document is a Field Inspection and Test Plan (ITP) for above ground piping work on the Rapid Package 6A LLDPE Project. It defines inspection points including hold points, witness points, and approval points. It references applicable codes and standards. The ITP covers material control, qualification of welding procedures, welders, and NDT technicians, consumable control, and defines required inspection forms. Inspection points include material receiving, storage and preservation, WPS and welder qualification, consumable receiving, storage, baking and issuance. The ITP provides acceptance criteria for ensuring quality of above ground piping work.
Pre Commissioning Testing Training and Maintenance of Instrumentation Analyzer, Metering Skid, Crude Oil Samplers, Corrosion, CP Radio Monitoring system, Laser HF and H2S Hydrogen, Oxygen Emerson oxymitter, Emerson Bentely Navada Vibration Analyzers, Thermography, Gas cement Petroleum Analyzers, Gas Chromatograph in Refinery Oil Gas Plants Petrochemical Aramco Sabic.
Extensive coordination between client and supplier in make sure all resolution successfully covered to achieve end client satisfaction.
Here are the key points I gathered from our discussion:
- The group proposed installing a redundant pump to address the risk of a single pump failure causing a process shutdown. This would allow one pump to act as a backup if the primary pump fails.
- One challenge was determining the appropriate size for the redundant pump to ensure it could handle the full process flow if needed. The group had to research pump specifications.
- Another issue was how to integrate controls for the redundant pump. The group consulted the facility's instrumentation and controls standards to identify the best approach.
- Overall the discussion showed good problem solving. The group worked together to analyze the problem, propose a solution, anticipate challenges, and leverage available resources to address those
This document provides a project execution plan for a district cooling plant project in Rihan Heights, UAE. Key details include:
- The project involves design, construction, and operation of a 4,000 ton district cooling plant, reticulation network, and energy transfer stations.
- The fast track project is to be completed by May 13, 2011 on a fixed price contract.
- Execution will involve in-house engineering, procurement through central procedures, and subcontracting of packages while ensuring quality and safety standards.
The document provides guidelines for project handover from contractors to the University of Newcastle's Infrastructure and Facilities Services. It outlines requirements for connection and commissioning, licenses and certificates, post-completion maintenance, training, and provision of as-built documentation including asset lists, manuals, drawings and other information. The guidelines are intended to help ensure an efficient transfer of ownership and smooth operation of facilities after project completion.
Ali Raza Qaisrani is an instrumentation engineer with over 7 years of experience in Saudi Arabia. He has expertise in designing instrumentation control systems including DCS, PLC, ESD, and SCADA systems. Some of his responsibilities include project management, engineering design, commissioning, and working with clients in the oil and gas industry. He is proficient in AutoCAD, Microstation, and Microsoft Office and has participated in numerous projects for companies like SABIC affiliates and Pakistan Oilfields Limited.
This document defines terms and acronyms related to quality assurance and control for Saudi Aramco engineering projects. It includes definitions for Saudi Aramco engineering procedures, standards, reports and requirements. It also defines quality management terms like quality assurance, quality control, inspection hold points, and roles such as quality manager and supplier. Acronyms are defined for inspection related documents and tests, as well as manufacturing and project terms.
Abhinesh Thomas is an Electrical and Instrumentation Superintendent with over 8 years of experience. He holds a B.Tech in Applied Electronics and Instrumentation. He is currently working at Global Process Systems in Abu Dhabi, where he supervises a team of engineers, foremen, and technicians. Previously he has worked on projects involving oil and gas processing, power distribution systems, control systems, and more. He has extensive experience in project installation, commissioning, engineering, and maintenance.
Enefen how to_have_a_successful_field_inspection_approvalSbremkamp
This presentation discusses how to have a successful field inspection and approval. It outlines key steps such as defining the project scope, identifying authorities having jurisdiction, and finding an organization to handle inspections and approvals. It explains concepts like certification, field approval, and differences between the two. It also discusses safety codes, regulations, and the roles of organizations like Standards Council of Canada and Safety Codes Council of Alberta in accreditation and oversight.
This document provides a health, safety, and environmental (HSE) presentation by Al Hamad Trading for a project involving the detailed inspection and overhauling of on-load tap changers. The summary includes:
1) Al Hamad Trading is certified to ISO 9001, ISO 14001, and OHSAS 18001 standards for quality, environmental, and occupational health and safety management.
2) Relevant laws and regulations that will be followed include Qatar labor laws, Qatar Foundation mandatory standards, UK health and safety at work act, electricity at work regulations, and Kahramaa safety rules.
3) Hazards associated with the project such as electrocution, falls, and working
John kingsley OT ICS SCADA Cyber security consultantJohn Kingsley
John kingsley OT ICS SCADA Cyber security consultant
SCADA ICS Security Courses
Lack of SCADA ICS security professionals that lead to big gaps between compliance against the respected guidelines with the real situation at site. Critical needs for proper security professional in SCADA ICS
SCADA ICS Security Assurance
Ensuring the SCADA ICS environment to comply with the security requirements in order to maintain the production operations and sustain the business performance
SCADA ICS (OT) Security Services
SCADA ICS Security Services Summary
SCADA ICS Security Asset Management
SCADA ICS Security Risk Management
SCADA ICS Security Assessment
SCADA ICS Standard, Policy & Procedure Management
SCADA ICS Security Implementation
Cyber Security Services
Vulnerability Assessment
Penetration Testing
ISO 27001 Certified Management System Audit
Resource Group provides software and firmware engineering services for safety-critical systems in industries like aerospace, rail, automotive and defense. They have over 20 years of experience meeting exacting requirements and standards like DO-178B/C, DO-278, IEC 61508. Their services include requirements, architecture, design, implementation, verification, validation, testing and certification consultancy. They also help clients address certification challenges for complex FPGA/PLD implementations.
The document provides a table of contents for fire protection, fire prevention and fire/emergency control regulations. It outlines 31 appendices on various related topics. The main sections cover the scope of the regulations, requirements for consultancy services and fire protection experts, risk assessment studies, fire layout drawings, building design and safety measures, miscellaneous provisions, fire prevention, emergency control, certification and approval processes, and definitions. Compliance with National Fire Protection Association standards is required.
The document provides an overview of integrated commissioning and start-up services. It describes the standard implementation path which includes home office and site phases. In the home office phase, pre-commissioning engineering activities such as system definition, planning, manual development are carried out. The site phase involves mechanical completion checks, pre-commissioning, commissioning, start-up and system turnover management. Detailed descriptions of activities in each phase are provided.
AN ISO SCHEME FOR USE AS A REVIEW GUIDE OR FOR CERTIFICATION OF PERFORMANCE-B...Dr. Monideep Dey
This paper proposes development of an ISO scheme that could be used either as a review guide or for the certification of a performance-based fire safety design in accordance with ISO 23932 – Fire Safety Engineering: General Principles . Deytec, Inc., a company member of the American National Standards Institute (ANSI), plans to propose the development of this ISO scheme to the ANSI International Conformity Assessment Committee (ICAC) which is the U.S. interface to the ISO Council Committee on Conformity Assessment (ISO CASCO). ISO CASCO writes standards and guides for the effective operation of conformity assessment bodies and activities. The purpose of the proposed scheme is to address present issues faced by national authorities and applicants in the review and approval of performance-based fire safety designs.
Monideep Dey, PhD
President, Deytec, Inc.
The document discusses SyCAS, a graphical system developed by Vega Systems for conformity assessment of complex products and systems. SyCAS allows for the development of assessment schemas for any product/system standard, and can then be used repeatedly for certification without requiring the original experts each time. It provides benefits like structured and consistent assessment processes, feedback on deficiencies, and savings from reduced risks and more efficient approval. Vega Systems offers training and long-term support packages to help clients implement and effectively use SyCAS within their organization.
Code of practice for physical security systems in banksSamer Al Basha
The document is a draft Indian standard code of practice for physical security systems in banks. It outlines organizational responsibilities for security, including having a security manual and program. It describes location and infrastructure considerations as well as security measures like risk categorization, primary in-built measures, essential general measures, and desirable additional measures. It also provides procedures for opening, closing, and accessing branches after hours. In the event of an incident, branches must immediately report to law enforcement and authorities.
A Deep Dive into Secure Product Development Frameworks.pdfICS
We tackle the question of what is a SPDF for medical device cybersecurity. We look to provide actionable advice that clarifies implementation, and you can apply in your day-to-day tasks.
Development agency will prepare the Technical Specification Document for each individual SRU and
will get it approved by airworthiness agency through HAL. Also, the electrical ICD need to be
generated by Development agency.
Essential
2 4.iv
Development agency will submit the application for airworthiness assessment of store, TAB (Type
approval basis), ACP (Airworthiness Certification Plan) and Quality Assurance Plan (QAP) documents
in co-ordination with HAL to airworthiness agencies for approval.
Essential
3 4.v
Development agency will carry out the TRR, PDR, CDR & TARB with prior intimation (min. 15 working
days) to HAL and airworthiness agencies.
Essential
4 4.vi
Development agency will develop all necessary Design documents, Process documents & Test
Documents required for airworthiness certification and will get the approval by airworthiness agency
through HAL.
Essential
5 4.vii
Development agency will do necessary procurement of raw material required for fabrication of
prototypes, along with CoC traceable to OEM as per approved Bill of Material. Essential
6 4.viii
Development agency will develop tools and fixtures required for fabrication of prototypes and get it
approved from airworthiness agencies. Essential
7 4.ix
Development agency will fabricate the prototype (02 nos. of each types of SRU) as per approved
design / process document to meet the requirement of approved Technical Specification. Essential
8 4.x
The fabricated SRU will be Form, Fit, Function and Integration (FFFI) substitution of required
respective SRU. Essential
9 4.xi
A test rig is to be developed and fabricated for carrying out the functional tests and get it approved
from airworthiness agencies.
Development agency will prepare the Technical Specification Document for each individual SRU and
will get it approved by airworthiness agency through HAL. Also, the electrical ICD need to be
generated by Development agency.
Essential
2 4.iv
Development agency will submit the application for airworthiness assessment of store, TAB (Type
approval basis), ACP (Airworthiness Certification Plan) and Quality Assurance Plan (QAP) documents
in co-ordination with HAL to airworthiness agencies for approval.
Essential
3 4.v
Development agency will carry out the TRR, PDR, CDR & TARB with prior intimation (min. 15 working
days) to HAL and airworthiness agencies.
Essential
4 4.vi
Development agency will develop all necessary Design documents, Process documents & Test
Documents required for airworthiness certification and will get the approval by airworthiness agency
through HAL.
Essential
5 4.vii
Development agency will do necessary procurement of raw material required for fabrication of
prototypes, along with CoC traceable to OEM as per approved Bill of Material. Essential
6 4.viii
Development agency will develop tools and fixtures required for fabrication of prototypes and get it
approved from airworthiness agencies. Essential
7 4.ix
Development agency will fabricate th
A successful cyber attack on a plant’s Industrial Control Systems (ICS) can be catastrophic. It can impact the plant’s operations, finances, damage reputation and even threaten lives. A resilient cyber security programme is essential in order to mitigate against potential cyber attacks. To help ensure that your plant is fully prepared to defend against potential cyber attacks, we provide a range of ICS Cyber Security services, each customised for your plant’s unique requirements, based on the latest international cyber security standards and best practice. Pöyry is active in designing, assessing and supervising the implementation of ICS cyber security programmes to both operating and greenfield facilities.
Jennifer Schaus and Associates hosts a complimentary webinar series on The FAR in 2024. Join the webinars on Wednesdays and Fridays at noon, eastern.
Recordings are on YouTube and the company website.
https://www.youtube.com/@jenniferschaus/videos
Monitoring Health for the SDGs - Global Health Statistics 2024 - WHOChristina Parmionova
The 2024 World Health Statistics edition reviews more than 50 health-related indicators from the Sustainable Development Goals and WHO’s Thirteenth General Programme of Work. It also highlights the findings from the Global health estimates 2021, notably the impact of the COVID-19 pandemic on life expectancy and healthy life expectancy.
Jennifer Schaus and Associates hosts a complimentary webinar series on The FAR in 2024. Join the webinars on Wednesdays and Fridays at noon, eastern.
Recordings are on YouTube and the company website.
https://www.youtube.com/@jenniferschaus/videos
Combined Illegal, Unregulated and Unreported (IUU) Vessel List.Christina Parmionova
The best available, up-to-date information on all fishing and related vessels that appear on the illegal, unregulated, and unreported (IUU) fishing vessel lists published by Regional Fisheries Management Organisations (RFMOs) and related organisations. The aim of the site is to improve the effectiveness of the original IUU lists as a tool for a wide variety of stakeholders to better understand and combat illegal fishing and broader fisheries crime.
To date, the following regional organisations maintain or share lists of vessels that have been found to carry out or support IUU fishing within their own or adjacent convention areas and/or species of competence:
Commission for the Conservation of Antarctic Marine Living Resources (CCAMLR)
Commission for the Conservation of Southern Bluefin Tuna (CCSBT)
General Fisheries Commission for the Mediterranean (GFCM)
Inter-American Tropical Tuna Commission (IATTC)
International Commission for the Conservation of Atlantic Tunas (ICCAT)
Indian Ocean Tuna Commission (IOTC)
Northwest Atlantic Fisheries Organisation (NAFO)
North East Atlantic Fisheries Commission (NEAFC)
North Pacific Fisheries Commission (NPFC)
South East Atlantic Fisheries Organisation (SEAFO)
South Pacific Regional Fisheries Management Organisation (SPRFMO)
Southern Indian Ocean Fisheries Agreement (SIOFA)
Western and Central Pacific Fisheries Commission (WCPFC)
The Combined IUU Fishing Vessel List merges all these sources into one list that provides a single reference point to identify whether a vessel is currently IUU listed. Vessels that have been IUU listed in the past and subsequently delisted (for example because of a change in ownership, or because the vessel is no longer in service) are also retained on the site, so that the site contains a full historic record of IUU listed fishing vessels.
Unlike the IUU lists published on individual RFMO websites, which may update vessel details infrequently or not at all, the Combined IUU Fishing Vessel List is kept up to date with the best available information regarding changes to vessel identity, flag state, ownership, location, and operations.
A Guide to AI for Smarter Nonprofits - Dr. Cori Faklaris, UNC CharlotteCori Faklaris
Working with data is a challenge for many organizations. Nonprofits in particular may need to collect and analyze sensitive, incomplete, and/or biased historical data about people. In this talk, Dr. Cori Faklaris of UNC Charlotte provides an overview of current AI capabilities and weaknesses to consider when integrating current AI technologies into the data workflow. The talk is organized around three takeaways: (1) For better or sometimes worse, AI provides you with “infinite interns.” (2) Give people permission & guardrails to learn what works with these “interns” and what doesn’t. (3) Create a roadmap for adding in more AI to assist nonprofit work, along with strategies for bias mitigation.
Contributi dei parlamentari del PD - Contributi L. 3/2019Partito democratico
DI SEGUITO SONO PUBBLICATI, AI SENSI DELL'ART. 11 DELLA LEGGE N. 3/2019, GLI IMPORTI RICEVUTI DALL'ENTRATA IN VIGORE DELLA SUDDETTA NORMA (31/01/2019) E FINO AL MESE SOLARE ANTECEDENTE QUELLO DELLA PUBBLICAZIONE SUL PRESENTE SITO
Jennifer Schaus and Associates hosts a complimentary webinar series on The FAR in 2024. Join the webinars on Wednesdays and Fridays at noon, eastern.
Recordings are on YouTube and the company website.
https://www.youtube.com/@jenniferschaus/videos
2024: The FAR - Federal Acquisition Regulations, Part 39
HCIS approval & procedure
1. Understanding the New Directives and their impact on the
projects and existing security of industrial facilities in KSA
Ministry of the Interior, Kingdom of Saudi Arabia,
High Commission for Industrial Security HCIS
8. General Requirements (SEC-01)
4.1.1: The HCIS reserves the right to modify and/or make changes to the
Security Directives without prior notice.
4.1.2: The criticality of each facility varies depending on the product or service
provided.
4.1.3: The HCIS will have the ultimate authority on classifying all facilities.
4.1.4: The level of protection shall be dictated by its security classification.
4.1.6: All security design shall be carried out by qualified security consultants
approved by HCIS.
4.1.7: The operator shall develop a detailed security vulnerability assessment,
or risk analysis, performed by a qualified security consultant, that shall be used
as the basis of facility qualification. This SVA shall follow the API Methodology.
4.1.8 The facility classification and Risk Analysis shall be submitted to HCIS for
approval prior to security system design or implementation.
10. The HCIS Security Process:
•Security
Vulnerability
Assessment
(SVA)
HCIS
Approval
•Concept of
Design (10%)
HCIS
Approval •Front End
Engineering
Design (30%)
HCIS
Approval
•Detail Design
(60%)
HCIS
Approval •Detail Design
(90%)
HCIS
Approval
•Issued for
Construction
(100%)
FAT / SAT
oSecurity Integrator Prequalification Review (HCIS bidder approval process
required)
oTechnical Scope of Work for client (Request for Proposal)
oBid Evaluation (technical evaluation of integrator bids)
oPolicy, Plan and Procedures
oManpower Study
oSecurity Awareness and Training Programmes
11. Security Directives:
Procedure
Security
Vulnerability
Assessment
(SVA)
The plant owner commissions a Security Vulnerability Assessment to be
carried out by an HCIS approved Security Consultant.
The SVA has to be carried out following the API methodology. The purpose
of the SVA is twofold:
1. Identify critical assets, threats, risks, vulnerability and propose
mitigation measures
2. Classify the facility according to a class 1 to 4 system.
12. Security Directives:
Procedure
Concept of
design (COD)
After the approval of the Security Vulnerability Assessment, the plant
owner commissions an HCIS approved Security consultant to take the
results from the SVA and produce a security Concept of Design (COD)
This Concept of Design (also called 10% Preliminary design) provides a
design solution to the mitigation measures proposed and approved during
the SVA exercise.
13. Security Directives:
Procedure
Front End
Engineering
Design
(FEED)
After the approval of the concept of design (COD), the plant owner
commissions an HCIS approved Security consultant to produce a Front
End Engineering Document from the SVA and Concept of Design (COD) .
The FEED (or 30% Design) will form the basis of the Technical Scope of
Work that will form part of the Request for Proposal (RFP).
This RFP will be issued to approved System Integrators to prepare a
Tender Bid.
The TSOW and RFP need not be approved by HCIS, but the FEED
document does and the security system integrators must be approved by
the HCIS.
The EPC should submit the prequalification document of the security
system integrator to the HCIS consultant for comment/approval before
submission to the owner for transmission to and approval by the HCIS.
14. Security Directives:
Procedure
Detailed
Design 60%
After the award of the security contract to an approved integrator the
integrator will produce a 60% detailed design that is in accordance with the
FEED design (30%). The design will include details of all hardware and
software to be used and will detail how the software is configured to
produce an integrated system.
The 60% detailed design is submitted to the HCIS approved consultant for
comment and review before submittal by the EPC to the owner for
transmission and approval by the HCIS.
15. Security Directives:
Procedure
Detailed
Design 90%
After the approval of the 60% detailed design the Security Systems
integrator will produce the 90% engineering submittal. This will include
information on the total system down to individual field item level showing
location, mechanical installation and all electrical terminations
The 90% detailed design is submitted to the HCIS approved consultant for
comment and review before submittal by the EPC to the owner for
transmission and approval by the HCIS.
16. Security Directives:
Procedure
Issued For
Construction
After the approval of the 90% design package the Security Systems
Integrator will prepare the system for the Factory Acceptance Test (FAT)
The Security System Integrator will produce a FAT document for submittal
and approval by the HCIS before the FAT is carried out .
The FAT will be attended by the HCIS representative, the HCIS consultant,
the owner and the EPC.
The approved consultant will lead a Site Acceptance Test (SAT) and issue a
Final Completion report (100%) for the HCIS.
17.
18. 4.5 Requirements for Executing Fire Protection Projects (SAF)
4.5.1 Designers, suppliers, contractors shall be approved by the HCIS.
4.5.3 Contractors and suppliers shall be certified by the Ministry of Interior (Civil Defense) and Ministry
Commerce and Industry.
4.5.4 The Owner shall submit qualification documents to the HCIS for approval
4.5.5 The Owner shall ensure that the company selected for safety and fire protection related work shal
adequate engineering capabilities and qualified manpower to design, install, test and maintain the safet
fire protection systems and execute all other work requirements competently. .
4.5.7 The HCIS reserves the exclusive right to approve or reject any candidate design agency performin
work.
4.5.8 The Owner shall ensure that the company selected for safety and fire protection related work shal
prior technical experience.
4.5.11 The HCIS shall have the right to reject any equipment, system, or suppliers
4.5.14 The Owner shall not permit any start on safety and fire protection related work until HCIS approv
the design, contractor, major fire protection equipment and systems is received.
19. The Safety Directives (1)
SAF 01 -Application of Safety and Fire Protection Directives
SAF 02 - Environmental, Health and Safety (EHS) Management
SAF 03 - Plant Buildings
SAF 04 - Fire Protection Systems
SAF 05 - Industrial Drainage
SAF 06 -Plant Layout, Spacing, and Access
SAF 07 - Well site Safety
SAF 08 - Storage Tanks and Storage Vessels
SAF 09 - Fireproofing in Plants
SAF 10 - Pressure Piping, Pressure Vessels, and Transportation Pipelines
SAF 11 - Emergency Shutdown, Isolation, and De-pressuring
SAF 12 - Electrical Safety
20. The Safety Directives (2)
SAF 13 - Work Permits
SAF 14 - Safe Manufacture, Transportation, Storage, and Use of Explosive Materials and Pyrotechnic Articles
SAF 15 - Private Industrial Fleet Vehicle Filling Stations
SAF 16 - Bulk Plants and Air Fuelling Support Facilities
SAF 17 - Offshore Production Facilities
SAF 18 - Mines and Mineral Processing Plants
SAF 19 - Electric Power Generating Plants and Associated Facilities
SAF 20 - Pre-Incident Planning and Management of Emergencies
SAF 21 - Personal Protective Equipment
SAF 22 – Portable Electric and Electronic Devices
21. Safety Directives:
• Preliminary
Design Phase
HCIS
Approval
• Detailed
Design Phase
HCIS
Approval • Operational
Aspects (prior
to operations)
HCIS
Approval
Normally carried out
at the FEED stage to
produce a document
that meets HCIS
requirements and an
EPC can bid against
Produced by a local Saudi
Fire contractor as part of
a design, supply, install
and commission contract
Produced by either the
owner or the EPC and
must include all
operational aspects of
safety.
22. Safety Directives:
• Preliminary
Design Phase
HCIS
Approval
• Detailed
Design Phase
HCIS
Approval • Operational
Aspects (prior
to operations)
HCIS
Approval
General plot plans
showing fire main &
pump house, site
drainage, building
spacing etc. and
general specifications
Detailed fire detection and
protection layout
including all types of
extinguishing systems
and hydraulic calculations
Site operational systems
including Incident
Management System,
permit to work system
and all other safety
related procedures
23. Safety Directives:
Procedure
Preliminary
Design Phase
When the project is being designed at the FEED stage a preliminary design
for the site should be produced by the FEED engineers.
The FEED should take into account all 22 of the SAF standards.
The preliminary design has to be submitted to an HCIS approved
consultant for approval before the plant owner submits to HCIS for final
approval.
The HCIS consultant will produce a compliance matrix to show
compliance/non compliance to the HCIS codes and consult with the FEED
engineers to then ensure that the preliminary design is 100% in
compliance.
The preliminary design together with the compliance matrix is submitted
by the plant owner to the HCIS for approval
24. Safety Directives:
Procedure
The EPC will receive a bid package from the owner, based on the FEED
preliminary engineering. This includes the requirement that the EPC
selects a fire engineering company that meets the requirements of HCIS
SAF 1.
The EPC should select a fire contractor(s) that meets the requirements of
the HCIS and submit the companies pre-qualification document to the HCIS
consultant for comment. If the consultant approves the document then the
EPC should submit to the plant owner for transmission to and approval by
the HCIS.
The EPC should issue tender enquiries to the chosen approved
contractor(s)
The EPC should award the contract for the design, supply, installation and
commissioning of the fire systems to the approved fire contractor
Detailed
Design Phase
25. Safety Directives:
Procedure
The owner, in conjunction with the EPC will produce Site operational
systems including Incident Management System, permit to work system
and all other safety related procedures
The Incident Management System (IMS) shall meet the requirements of
SAF20 and be integrated with the Site Security Systems and the Site wide
fire alarm and fire protection system.
The IMS should be integrated from a hardware and software perspective to
produce an easy to use system that can be used to:
o Reduce loss of life
o Reduce loss or damage to assets
o Ensure any situation is controlled
o Ensure the safety of personnel and Assets
o Reduce hostile effects in the environment.
Operational
Aspects (prior
to operations)
26. Safety Directives:
Procedure
Operational
Aspects (prior
to operations)
The IMS must provide Fast, Effective Access to Critical Incident Data
Clear Command Communications
Common Operational Picture:
o Shared across an incident
o Shared between many agencies
Capacity to:
o Operate on a massive scale
o Operate over long timescales
o Manage massive numbers of victims and resources
o Minimise ecological and environmental damage
27. Safety Directives:
Procedure
The Incident Management System shall meet the requirements of the
NFPA.
NFPA 450 Emergency Medical Services and Systems
NFPA 472 Competence of Responders to Hazardous Materials/ Weapons
of Mass Destruction Incidents
NFPA 473 Competencies for EMS Personnel Responding to Hazardous
Materials / Weapons of Mass Destruction Incidents
NFPA 1006 Rescue Technician Professional Qualifications
NFPA 1620 Pre-Incident Planning
NFPA 1670 Operations and Training for Technical Rescue Incidents
NFPA 1951 Protective Ensembles for Technical Rescue Incidents
Operational
Aspects (prior
to operations)
28. These New Directives must be applied on all new projects
in the Kingdom of Saudi Arabia for Security and Safety.
From July 2012 they will apply to all existing industrial
facilities in Saudi Arabia.
Any plant owner not meeting the standards will face
serious consequences.
Ministry of the Interior, Kingdom of Saudi Arabia,
High Commission for Industrial Security HCIS
29. Understanding the New Directives and their impact on the
projects and existing security of industrial facilities in KSA
Ministry of the Interior, Kingdom of Saudi Arabia,
High Commission for Industrial Security HCIS