SlideShare a Scribd company logo
1 of 50
A PRESENTATION
ON
GAS INSULATED
SUBSTATION
PRINCIPLE OF GIS
IT IS BASED ON THE PRINCIPLE OF
COMPLETE ENCLOSURE OF ALL
ENERGISED PARTS IN A METALLIC
ENCLOSURES WHICH SHIELDS FROM THE
EXTERNAL ENVIRONMENT.
ADVANTAGE OF GIS
 Compactness : The space occupied by the GIS installation is
only about 10% of Conventional switch yard.
 Protection from : Highly preferred in coastal areas where
Pollution effect due to salt deposition is very high.
 Superior Arc : The system has better Arc quenching
interruption capability because of higher dielectric
strength.
 Maintenance free : The equipments require minimum
maintenance once installed properly. The
cost on maintenance will be reduced
considerably.
 Increased safety : Owing to very high insulation level and since
the enclosures are at earth potential, there is
no possibility of Electric accident.
INSULATION IN GIS
Sulphur Hexa Fluoride (SF6) is used as an
Insulating medium between Enclosures
and Current carrying bus bars.
PROPERTIES OF SF6
 Dielectric Strength :The Dielectric strength of SF6 is
about 2.5 to 3 times higher than the corresponding
values of Air.
 Arc Quenching Capacity : The Thermal Properties and
Low ionisation temperature of SF6 exhibits outstanding
Characteristics for extinguishing electric arcs. The arc
quenching time using SF6 is about 100 times less than
that using air.
 Heat Transferability : The heat transferability is 2 to
2.5 times that of air at same pressure. Hence for equal
conductor size, the current carrying capacity is relatively
more.
PROPERTIES OF SF6
Low Arc time constant : Because of the
Electronegative property of SF6, the arc
time constant is very low and the rate of
rise of dielectric strength is very high.
Inert : Since the gas is inert the inside
compartments do not get oxidised or
deteriorated.
INSTALLATION OF GIS
CIVIL COMPLETION
EQUIPMENT ERECTION
GAS TREATMENT
TESTING
COMMISSIONING
CIVIL COMPLETION
EOT CRANE ERECTION & COMMISSIONING
LIGHTING & VENTILATION WORKS
COMPLETE PAINTNG INCLUDING EPOXY FLOOR
FINISH
CIVIL CHECKS
FIX THE REFERENCE LINE OF CB
FIX THE REFERENCE LINE OF BUS BAR
ERECTION & ALIGNMENT OF HALFEN BEAMS
ERECTION OF GIS EQUIPMENTS
INDOOR
OUTDOOR
INDOOR ERECTION
ERECTION OF CIRCUIT BREAKERS
ERECTION OF DISCONNECTORS
ERECTION OF ENCLOSURES & BUS BARS
ERECTION OF CURRENT TRANSFORMER
ERECTION OF VOLTAGE TRANSFORMER
TYPICAL CIRCUIT BREAKER
WITH OUT CLOSING RESISTOR
1. CIRCUIT BREAKER
2. HYDRAULIC OPERATING
MECHANISM
3. DISCONNECTOR
4. EARTH SWITCH
5. CURRENT TRANSFORMER
6. VOLTAGE TRANSFORMER
7. CABLE CONNECTION
TYPICAL CIRCUIT BREAKER
WITH CLOSING RESISTOR
1. CIRCUIT BREAKER WITH
CLOSING RESISTOR
2. HYDRAULIC OPERATING
MECHANISM
3. DISCONNECTOR
4. EARTH SWITCH
5. CURRENT TRANSFORMER
6. VOLTAGE TRANSFORMER
7. CABLE CONNECTION
TYPICAL ARRANGEMENT OF
DISCONNECTORS
TYPICAL ARRANGEMENT OF
CURRENT TRANSFORMER
1. MAIN CONDUCTOR
2. SECONDARY WINDING
3. SHUNT
4. INSULATING PART
TYPICAL ARRANGEMENT OF
VOLTAGE TRANSFORMER
TYPICAL CONNECTION
ARRANGEMENT OF GIS WITH
TRANSFORMER
1. CONNECTING CONTACT
2. SF6 / OIL BUSHING
3. REMOVABLE LINK
4. SERVICE UNIT
TYPICAL ARRANGEMENT OF SURGE
ARRESTOR & CABLE CONNECTION
TYPICAL ARRANGEMENT OF
INSULATING CONES
ERECTION OF CIRCUIT BREAKER
THE PACKING MATERIALS MEANT FOR
TRANSPORTATION INSIDE CB TO BE REMOVED
BEFORE ERECTION.
PRESENCE OF NITROGEN TO BE ENSURED.
ALIGNMENT TO BE DONE WITH THEODALITE.
TIGHTNESS OF FOUNDATION BOLT TO BE
DONE STRICTLY AS PER MANUFACTURER’S
RECOMMENDATION.
ERECTION OF CIRCUIT BREAKER
TILTING
TOOL
ERECTION OF DISCONNECTORS
 PRESENCE OF NITROGEN TO BE ENSURED ON ALL THE
PARTS OF DISCONNECTORS.
 O-RINGS SHOULD BE CHECKED THROUGHLY BEFORE
PLACING THEM IN POSITION.
 GREASE TO BE APPLED EVENLY IN THE O-RING.
 APPLY CONTACT GREASE IN CONTACT PORTION OF
BUS BAR.
 NEVER MIX THE CONTACT GREASE AND THE ONE USED
FOR O-RINGS.
 ENSURE THAT O-RINGS ARE NOT DAMAGED DURING
CONNECTION.
ERECTION OF DISCONNECTORS
CB SIDE
CONNECTION
BUS
BAR-I
BUS BAR-
II
PREPARATION & ERECTION OF
BUS BAR
BUS BARS SHALL BE THROUGHLY CLEANED
WITH ISOPROPANOL.
ANY PROTRUSION IN THE BUS BAR SHOULD BE
REMOVED WITH FINE EMERY PAPER.
THE SPRING CONTACTS SHOULD BE IN
POSITION DURING CONNECTION.
NO SCRATCHES IN THE BUS BAR IS ALLOWED.
PREPARATION & ERECTION OF
BUS BAR
ERECTION OF CT
 CHECK FOR ANY DAMAGE ON THE SECONDARY CORES
OF CT.
 PRESENCE OF NITROGEN TO BE ENSURED ON ALL THE
PARTS OF DISCONNECTORS.
 PERFORM THE FUNCTIONAL CHECKS.
 CHECK THE INTERNAL PART OF ENCLOSURES FOR
PROTRUSIONIF ANY.
 PERFORM THE ERECTION DEPENDING ON THE
ARRANGEMNT EITHER WITH ENCLOSURES OR
DIRECTLY WITH EQUIPMENT.
ERECTION OF CT IN GENERATOR BAY
CONNECTION
UNDER
PROGRESS
WITH CB
ERECTION OF VOLTAGE
TRANSFORMER
 CHECK VT FOR DAMAGE IF ANY WITH THE VIBRATION
INDICATOR PROVIDED.
 NEVER OPEN THE COVER AS POSITIVE PRESSURE OF
SF6 IS MAINTAINED INSIDE.
 PERFORM FUNCTIONAL CHECKS.
 PERFORM THE ERECTION.
OUTDOOR ERECTION
 PREPARE A PLATFORM FOR ASSEMBLY OF VARIOUS
EQUIPMENTS.
 PREPARE A MOBILE SHED (PREFERABLY WITH WOOD)
FOR CONNECTION.
 NEVER KEEP ANY EQUIPMENT UNDER OPEN POSITION.
ALWAYS COVER WITH POLYTHENE PAPER TO AVOID
ENTRY OF FOREIGN PARTICLE.
EQUIPMENTS TOBE ERECTED
OUTDOOR
LIGHTNING ARRESTORS
SF6 / AIR BUSHING
TRANSFORMER END CONNECTION
ERECTION OF LIGHTNING
ARRESTORS
ACTIVE PART SHALL BE THROUGHLY
CLEANED TO REMOVE FOREIGN MATTER.
POSITIONING OF Zno IN EACH STACK
SHALL BE CHECKED.
ENSURE PROPER PLACING OF ACTIVE
PART INSIDE ENCLOSURE.
ERECTION OF ACTIVE PART
LA ACTIVE
PART
ENCLOSURE
FOR ACTIVE
PART
ERECTION OF SF6/ AIR BUSHING
 THIS IS END PORTION OF GIS FOR EVACUATION OF
POWER.
 CHECK FOR PHYSICAL DAMAGE OF INSULATORS.
 PERFORM THE CONNECTION OF ENCLOSURE WITH
BUSHING.
 MAKE SUITABLE PLATFORM FOR ERECTION OF
BUSHING WITH INSIDE BAY.
 PREPARE THE ROLLER SUPPORT ON THE WALL BEFORE
ERECTION OF ENCLOSURE .
INSIDE VIEW OF BUSHING WITH
BUS BAR
DOUBLE SEAL
ARRANGEMENT
TEMPORARY SUPPORT
OF BUS BAR
ERECTION OF BUSHING
HYDRAULIC OPERATING
MECHANISM
 THE BREAKER OPERATION IS THROUGH HYDRAULIC
OPERATING MECHANISM.
 DURING FILLING OF OIL CARE SHOULD BE TAKEN TO
AVOID AIR TRAP INSIDE.
 NITROGEN ACCUMULATORS ARE PROVIDED TO FASTER
OPERATION OF CB DURING OPEN & CLOSE
OPERATIONS.
DRIVE ROD MECHANISM
THE DISCONNECTORS OF ALL THE PHASES
SHALL BE IN OPEN POSITION BEFORE
ASSEMBLY.
NUMBER OF ROTATIONS SHALL BE AS PER
MANUFACTURER’S RECOMMENDATION.
MECHANICAL INTERLOCK IF ANY IS TO BE
PROVIDED BETWEEN DISCONNECTOR AND
EARTH SWITCH.
CABLE TRAYS, CABLING
 THE CABLE TRAYS WORK CAN BE STARTED ONCE A
COMPLETE BAY IS ERECTED.
 CABLING WORK CAN BE STARTED ONCE PART OF
CABLE TRAY ERCTION IS OVER.
EARTHING
SINCE THE ENCLOSURE IS ALUMINIUM, IT
OFFERS CONTINUITY.
WHEREVER FLANGE JOINTS ARE THERE, THE
PAINTING SHALL BE PROPERLY REMOVED.
THE FLANGES OF SHALL BE SHORTED ACROSS
CT WITH EARTH FLATS.
VARISTORS SHALL BE PROVIDED IN THE CT
JOINT. THIS IS TO AVOID THE DAMAGE OF CT
OWING TO SWITCHING TRANSIENTS.
GAS TREATMENT
THE VACCUM PUMP SHALL BE USED TO CREATE
VACCUM INSIDE THE BAY WHICH IS READY.
CHECK WITH GAUGE THE EXTENT OF VACCUM.
MAINTAIN IT FOR 12 HOURS.
PURGE THE BAY WITH NITROGEN IF
MOISTURE IS IN EXCESS.
CONTINUE THE VACCUM PROCESS TILL THE
DESIRED LEVEL IS REACHED.
VACCUM PUMP & GAS
TREATMENT CART
GAS TREATMENT
 DILO CART SHALL BE MADE VACCUM BEFORE ACTUAL
FILLING STARTS.
 THE SF6 GAS FILLING SHALL BE GRADUAL.
 SF6 BEING A HEAVIER GAS WILL SETTLE DOWN AT
THE BOTTOM. ADEQUATE CARE SHALL BE TAKEN.
 NEVER KEEP THE HOSES OPEN WHEN SF6 GAS IS NOT
FILLED.
 SF6 SHALL BE FILLED IN EACH COMPARTMENTS AT
REQUIRED PRESSURE AS PER MANUFACTURER’S
RECOMMENDATION.
TESTING
HYDRAULIC CHECKING
LCC CONTROL CHECKING
CT TESTING
SF6 GAS CHECKING
OPERATION CHECKING OF DRIVE MECHANISM
TESTING OF PRESSURE SWITCH
CONTACT RESISTANCE CHECKING
HYDRAULIC CHECKING
ENSURE ENOUGH OIL IS TOPPED UP INSIDE
THE TANK.
ALLOW THE OIL TO FLOW TILL NO AIR
BUBBLES ARE TRAPPED INSIDE.
THE PRESSURE SWITCH FOR HYDRAULIC
MECHANISM AT EACH LEVELS SHALL BE
CHECKED AS PER MANUFACTURER’S
RECOMMENDATION.
TYPICAL PRESSURE SCALE
HV TESTING
ONCE ALL THE CONTROL CHECKING IS OVER
THEN THE EQUIPMENT IS READY FOR HV
TESTING.
THE ASSEMBLY OF HV TEST KIT ALONG WITH
CONTROL EQUIPMENTS SHALL BE DONE.
TYPICAL ARRANGEMENT OF HV
TESTING KIT
POINTS TO BE NOTED PRIOR TO
HV TESTING
SF6 GAS PRESSURE IS CHECKED IN ALL THE
COMPARTMENTS.
CT SECONDARY TERMINALS ARE SHORTED.
VOLTAGE TRANSFORMER IS DICONNECTED.
LIGHTNING ARRESTOR IS DICONNECTED.
CABLE CONNECTION IS DISCONNECTED.
SF6/AIR BUSHING IS THROUGHLY CLEANED.
DISMANTLING ARRANGEMENT OF
BUS BARS

More Related Content

Similar to GIS-presentation1.ppt

Gas insulated substation 1
Gas insulated substation 1Gas insulated substation 1
Gas insulated substation 1Ronal Parmar
 
Rocsole profiler vs. nucleonic device
Rocsole profiler vs. nucleonic deviceRocsole profiler vs. nucleonic device
Rocsole profiler vs. nucleonic deviceRocsole Ltd
 
Murex arc-and-gas-cutting-and-welding-equipment-machines-removed
Murex arc-and-gas-cutting-and-welding-equipment-machines-removedMurex arc-and-gas-cutting-and-welding-equipment-machines-removed
Murex arc-and-gas-cutting-and-welding-equipment-machines-removedEngr.A.K.M Saiful Islam
 
CIRCUIT BREAKER USED IN THERMAL POWER PLANTS
CIRCUIT BREAKER USED IN THERMAL POWER PLANTSCIRCUIT BREAKER USED IN THERMAL POWER PLANTS
CIRCUIT BREAKER USED IN THERMAL POWER PLANTSDigantaSinha1
 
Gas insulated substation
Gas insulated substationGas insulated substation
Gas insulated substationRaushanKumar582
 
Humdification plant check list
Humdification plant check listHumdification plant check list
Humdification plant check listibrahimM12
 
15RDM01-2016-Academy Utility Plan
15RDM01-2016-Academy Utility Plan15RDM01-2016-Academy Utility Plan
15RDM01-2016-Academy Utility PlanKevin Stober
 
Sequence of well completion part 1
Sequence of well completion part 1Sequence of well completion part 1
Sequence of well completion part 1Elsayed Amer
 
Sequence of well completion part 1
Sequence of well completion part 1Sequence of well completion part 1
Sequence of well completion part 1Elsayed Amer
 
PPT ON CIM ,BHEL HARIDWAR
PPT ON CIM ,BHEL HARIDWARPPT ON CIM ,BHEL HARIDWAR
PPT ON CIM ,BHEL HARIDWARABHISHEK SINGH
 
circuitbreakerbyanubhabmohanty-121126030611-phpapp02.pdf
circuitbreakerbyanubhabmohanty-121126030611-phpapp02.pdfcircuitbreakerbyanubhabmohanty-121126030611-phpapp02.pdf
circuitbreakerbyanubhabmohanty-121126030611-phpapp02.pdfrolli2
 
TEMPERATURE EXPANSION OF FLANGE JOINTS
TEMPERATURE EXPANSION OF FLANGE JOINTSTEMPERATURE EXPANSION OF FLANGE JOINTS
TEMPERATURE EXPANSION OF FLANGE JOINTSAndrey Zhilin
 
instrumentation,characterization of water stationary phase in cGAS CHROMATOGR...
instrumentation,characterization of water stationary phase in cGAS CHROMATOGR...instrumentation,characterization of water stationary phase in cGAS CHROMATOGR...
instrumentation,characterization of water stationary phase in cGAS CHROMATOGR...Parimi Anuradha
 
GAS INSULATED SUB-STATION
GAS INSULATED SUB-STATIONGAS INSULATED SUB-STATION
GAS INSULATED SUB-STATIONsujitmandalsk
 
Richard Blakeley - Options for managing safety with elderly switchgear
Richard Blakeley - Options for managing safety with elderly switchgearRichard Blakeley - Options for managing safety with elderly switchgear
Richard Blakeley - Options for managing safety with elderly switchgearNSW Environment and Planning
 

Similar to GIS-presentation1.ppt (20)

Gas insulated substation 1
Gas insulated substation 1Gas insulated substation 1
Gas insulated substation 1
 
Rocsole profiler vs. nucleonic device
Rocsole profiler vs. nucleonic deviceRocsole profiler vs. nucleonic device
Rocsole profiler vs. nucleonic device
 
Murex arc-and-gas-cutting-and-welding-equipment-machines-removed
Murex arc-and-gas-cutting-and-welding-equipment-machines-removedMurex arc-and-gas-cutting-and-welding-equipment-machines-removed
Murex arc-and-gas-cutting-and-welding-equipment-machines-removed
 
CIRCUIT BREAKER USED IN THERMAL POWER PLANTS
CIRCUIT BREAKER USED IN THERMAL POWER PLANTSCIRCUIT BREAKER USED IN THERMAL POWER PLANTS
CIRCUIT BREAKER USED IN THERMAL POWER PLANTS
 
Gas insulated substation
Gas insulated substationGas insulated substation
Gas insulated substation
 
Humdification plant check list
Humdification plant check listHumdification plant check list
Humdification plant check list
 
15RDM01-2016-Academy Utility Plan
15RDM01-2016-Academy Utility Plan15RDM01-2016-Academy Utility Plan
15RDM01-2016-Academy Utility Plan
 
Sequence of well completion part 1
Sequence of well completion part 1Sequence of well completion part 1
Sequence of well completion part 1
 
Sequence of well completion part 1
Sequence of well completion part 1Sequence of well completion part 1
Sequence of well completion part 1
 
Circuitbreaker
Circuitbreaker Circuitbreaker
Circuitbreaker
 
PPT ON CIM ,BHEL HARIDWAR
PPT ON CIM ,BHEL HARIDWARPPT ON CIM ,BHEL HARIDWAR
PPT ON CIM ,BHEL HARIDWAR
 
Lightning arresters
Lightning arrestersLightning arresters
Lightning arresters
 
circuitbreakerbyanubhabmohanty-121126030611-phpapp02.pdf
circuitbreakerbyanubhabmohanty-121126030611-phpapp02.pdfcircuitbreakerbyanubhabmohanty-121126030611-phpapp02.pdf
circuitbreakerbyanubhabmohanty-121126030611-phpapp02.pdf
 
TEMPERATURE EXPANSION OF FLANGE JOINTS
TEMPERATURE EXPANSION OF FLANGE JOINTSTEMPERATURE EXPANSION OF FLANGE JOINTS
TEMPERATURE EXPANSION OF FLANGE JOINTS
 
Gas insulated substation.
Gas insulated substation.Gas insulated substation.
Gas insulated substation.
 
Gagan
GaganGagan
Gagan
 
instrumentation,characterization of water stationary phase in cGAS CHROMATOGR...
instrumentation,characterization of water stationary phase in cGAS CHROMATOGR...instrumentation,characterization of water stationary phase in cGAS CHROMATOGR...
instrumentation,characterization of water stationary phase in cGAS CHROMATOGR...
 
GAS INSULATED SUB-STATION
GAS INSULATED SUB-STATIONGAS INSULATED SUB-STATION
GAS INSULATED SUB-STATION
 
Richard Blakeley - Options for managing safety with elderly switchgear
Richard Blakeley - Options for managing safety with elderly switchgearRichard Blakeley - Options for managing safety with elderly switchgear
Richard Blakeley - Options for managing safety with elderly switchgear
 
Riparazione piste aeroportuali
Riparazione piste aeroportualiRiparazione piste aeroportuali
Riparazione piste aeroportuali
 

Recently uploaded

Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdfKamal Acharya
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwaitjaanualu31
 
Worksharing and 3D Modeling with Revit.pptx
Worksharing and 3D Modeling with Revit.pptxWorksharing and 3D Modeling with Revit.pptx
Worksharing and 3D Modeling with Revit.pptxMustafa Ahmed
 
Post office management system project ..pdf
Post office management system project ..pdfPost office management system project ..pdf
Post office management system project ..pdfKamal Acharya
 
Unsatisfied Bhabhi ℂall Girls Ahmedabad Book Esha 6378878445 Top Class ℂall G...
Unsatisfied Bhabhi ℂall Girls Ahmedabad Book Esha 6378878445 Top Class ℂall G...Unsatisfied Bhabhi ℂall Girls Ahmedabad Book Esha 6378878445 Top Class ℂall G...
Unsatisfied Bhabhi ℂall Girls Ahmedabad Book Esha 6378878445 Top Class ℂall G...Payal Garg #K09
 
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...HenryBriggs2
 
Adsorption (mass transfer operations 2) ppt
Adsorption (mass transfer operations 2) pptAdsorption (mass transfer operations 2) ppt
Adsorption (mass transfer operations 2) pptjigup7320
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdfAldoGarca30
 
Compressing and Sparsifying LLM in GenAI Applications
Compressing and Sparsifying LLM in GenAI ApplicationsCompressing and Sparsifying LLM in GenAI Applications
Compressing and Sparsifying LLM in GenAI ApplicationsMFatihSIRA
 
INTERRUPT CONTROLLER 8259 MICROPROCESSOR
INTERRUPT CONTROLLER 8259 MICROPROCESSORINTERRUPT CONTROLLER 8259 MICROPROCESSOR
INTERRUPT CONTROLLER 8259 MICROPROCESSORTanishkaHira1
 
8086 Microprocessor Architecture: 16-bit microprocessor
8086 Microprocessor Architecture: 16-bit microprocessor8086 Microprocessor Architecture: 16-bit microprocessor
8086 Microprocessor Architecture: 16-bit microprocessorAshwiniTodkar4
 
8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...josephjonse
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayEpec Engineered Technologies
 
Introduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptxIntroduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptxhublikarsn
 
Fundamentals of Internet of Things (IoT) Part-2
Fundamentals of Internet of Things (IoT) Part-2Fundamentals of Internet of Things (IoT) Part-2
Fundamentals of Internet of Things (IoT) Part-2ChandrakantDivate1
 
litvinenko_Henry_Intrusion_Hong-Kong_2024.pdf
litvinenko_Henry_Intrusion_Hong-Kong_2024.pdflitvinenko_Henry_Intrusion_Hong-Kong_2024.pdf
litvinenko_Henry_Intrusion_Hong-Kong_2024.pdfAlexander Litvinenko
 
Passive Air Cooling System and Solar Water Heater.ppt
Passive Air Cooling System and Solar Water Heater.pptPassive Air Cooling System and Solar Water Heater.ppt
Passive Air Cooling System and Solar Water Heater.pptamrabdallah9
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdfKamal Acharya
 

Recently uploaded (20)

Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
 
Worksharing and 3D Modeling with Revit.pptx
Worksharing and 3D Modeling with Revit.pptxWorksharing and 3D Modeling with Revit.pptx
Worksharing and 3D Modeling with Revit.pptx
 
Post office management system project ..pdf
Post office management system project ..pdfPost office management system project ..pdf
Post office management system project ..pdf
 
Unsatisfied Bhabhi ℂall Girls Ahmedabad Book Esha 6378878445 Top Class ℂall G...
Unsatisfied Bhabhi ℂall Girls Ahmedabad Book Esha 6378878445 Top Class ℂall G...Unsatisfied Bhabhi ℂall Girls Ahmedabad Book Esha 6378878445 Top Class ℂall G...
Unsatisfied Bhabhi ℂall Girls Ahmedabad Book Esha 6378878445 Top Class ℂall G...
 
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
 
Adsorption (mass transfer operations 2) ppt
Adsorption (mass transfer operations 2) pptAdsorption (mass transfer operations 2) ppt
Adsorption (mass transfer operations 2) ppt
 
Signal Processing and Linear System Analysis
Signal Processing and Linear System AnalysisSignal Processing and Linear System Analysis
Signal Processing and Linear System Analysis
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
 
Compressing and Sparsifying LLM in GenAI Applications
Compressing and Sparsifying LLM in GenAI ApplicationsCompressing and Sparsifying LLM in GenAI Applications
Compressing and Sparsifying LLM in GenAI Applications
 
INTERRUPT CONTROLLER 8259 MICROPROCESSOR
INTERRUPT CONTROLLER 8259 MICROPROCESSORINTERRUPT CONTROLLER 8259 MICROPROCESSOR
INTERRUPT CONTROLLER 8259 MICROPROCESSOR
 
8086 Microprocessor Architecture: 16-bit microprocessor
8086 Microprocessor Architecture: 16-bit microprocessor8086 Microprocessor Architecture: 16-bit microprocessor
8086 Microprocessor Architecture: 16-bit microprocessor
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
Introduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptxIntroduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptx
 
Fundamentals of Internet of Things (IoT) Part-2
Fundamentals of Internet of Things (IoT) Part-2Fundamentals of Internet of Things (IoT) Part-2
Fundamentals of Internet of Things (IoT) Part-2
 
litvinenko_Henry_Intrusion_Hong-Kong_2024.pdf
litvinenko_Henry_Intrusion_Hong-Kong_2024.pdflitvinenko_Henry_Intrusion_Hong-Kong_2024.pdf
litvinenko_Henry_Intrusion_Hong-Kong_2024.pdf
 
Passive Air Cooling System and Solar Water Heater.ppt
Passive Air Cooling System and Solar Water Heater.pptPassive Air Cooling System and Solar Water Heater.ppt
Passive Air Cooling System and Solar Water Heater.ppt
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdf
 

GIS-presentation1.ppt

  • 2. PRINCIPLE OF GIS IT IS BASED ON THE PRINCIPLE OF COMPLETE ENCLOSURE OF ALL ENERGISED PARTS IN A METALLIC ENCLOSURES WHICH SHIELDS FROM THE EXTERNAL ENVIRONMENT.
  • 3. ADVANTAGE OF GIS  Compactness : The space occupied by the GIS installation is only about 10% of Conventional switch yard.  Protection from : Highly preferred in coastal areas where Pollution effect due to salt deposition is very high.  Superior Arc : The system has better Arc quenching interruption capability because of higher dielectric strength.  Maintenance free : The equipments require minimum maintenance once installed properly. The cost on maintenance will be reduced considerably.  Increased safety : Owing to very high insulation level and since the enclosures are at earth potential, there is no possibility of Electric accident.
  • 4. INSULATION IN GIS Sulphur Hexa Fluoride (SF6) is used as an Insulating medium between Enclosures and Current carrying bus bars.
  • 5. PROPERTIES OF SF6  Dielectric Strength :The Dielectric strength of SF6 is about 2.5 to 3 times higher than the corresponding values of Air.  Arc Quenching Capacity : The Thermal Properties and Low ionisation temperature of SF6 exhibits outstanding Characteristics for extinguishing electric arcs. The arc quenching time using SF6 is about 100 times less than that using air.  Heat Transferability : The heat transferability is 2 to 2.5 times that of air at same pressure. Hence for equal conductor size, the current carrying capacity is relatively more.
  • 6. PROPERTIES OF SF6 Low Arc time constant : Because of the Electronegative property of SF6, the arc time constant is very low and the rate of rise of dielectric strength is very high. Inert : Since the gas is inert the inside compartments do not get oxidised or deteriorated.
  • 7.
  • 8. INSTALLATION OF GIS CIVIL COMPLETION EQUIPMENT ERECTION GAS TREATMENT TESTING COMMISSIONING
  • 9. CIVIL COMPLETION EOT CRANE ERECTION & COMMISSIONING LIGHTING & VENTILATION WORKS COMPLETE PAINTNG INCLUDING EPOXY FLOOR FINISH
  • 10. CIVIL CHECKS FIX THE REFERENCE LINE OF CB FIX THE REFERENCE LINE OF BUS BAR ERECTION & ALIGNMENT OF HALFEN BEAMS
  • 11. ERECTION OF GIS EQUIPMENTS INDOOR OUTDOOR
  • 12. INDOOR ERECTION ERECTION OF CIRCUIT BREAKERS ERECTION OF DISCONNECTORS ERECTION OF ENCLOSURES & BUS BARS ERECTION OF CURRENT TRANSFORMER ERECTION OF VOLTAGE TRANSFORMER
  • 13. TYPICAL CIRCUIT BREAKER WITH OUT CLOSING RESISTOR 1. CIRCUIT BREAKER 2. HYDRAULIC OPERATING MECHANISM 3. DISCONNECTOR 4. EARTH SWITCH 5. CURRENT TRANSFORMER 6. VOLTAGE TRANSFORMER 7. CABLE CONNECTION
  • 14. TYPICAL CIRCUIT BREAKER WITH CLOSING RESISTOR 1. CIRCUIT BREAKER WITH CLOSING RESISTOR 2. HYDRAULIC OPERATING MECHANISM 3. DISCONNECTOR 4. EARTH SWITCH 5. CURRENT TRANSFORMER 6. VOLTAGE TRANSFORMER 7. CABLE CONNECTION
  • 16. TYPICAL ARRANGEMENT OF CURRENT TRANSFORMER 1. MAIN CONDUCTOR 2. SECONDARY WINDING 3. SHUNT 4. INSULATING PART
  • 18. TYPICAL CONNECTION ARRANGEMENT OF GIS WITH TRANSFORMER 1. CONNECTING CONTACT 2. SF6 / OIL BUSHING 3. REMOVABLE LINK 4. SERVICE UNIT
  • 19. TYPICAL ARRANGEMENT OF SURGE ARRESTOR & CABLE CONNECTION
  • 21. ERECTION OF CIRCUIT BREAKER THE PACKING MATERIALS MEANT FOR TRANSPORTATION INSIDE CB TO BE REMOVED BEFORE ERECTION. PRESENCE OF NITROGEN TO BE ENSURED. ALIGNMENT TO BE DONE WITH THEODALITE. TIGHTNESS OF FOUNDATION BOLT TO BE DONE STRICTLY AS PER MANUFACTURER’S RECOMMENDATION.
  • 22. ERECTION OF CIRCUIT BREAKER TILTING TOOL
  • 23. ERECTION OF DISCONNECTORS  PRESENCE OF NITROGEN TO BE ENSURED ON ALL THE PARTS OF DISCONNECTORS.  O-RINGS SHOULD BE CHECKED THROUGHLY BEFORE PLACING THEM IN POSITION.  GREASE TO BE APPLED EVENLY IN THE O-RING.  APPLY CONTACT GREASE IN CONTACT PORTION OF BUS BAR.  NEVER MIX THE CONTACT GREASE AND THE ONE USED FOR O-RINGS.  ENSURE THAT O-RINGS ARE NOT DAMAGED DURING CONNECTION.
  • 24. ERECTION OF DISCONNECTORS CB SIDE CONNECTION BUS BAR-I BUS BAR- II
  • 25. PREPARATION & ERECTION OF BUS BAR BUS BARS SHALL BE THROUGHLY CLEANED WITH ISOPROPANOL. ANY PROTRUSION IN THE BUS BAR SHOULD BE REMOVED WITH FINE EMERY PAPER. THE SPRING CONTACTS SHOULD BE IN POSITION DURING CONNECTION. NO SCRATCHES IN THE BUS BAR IS ALLOWED.
  • 27. ERECTION OF CT  CHECK FOR ANY DAMAGE ON THE SECONDARY CORES OF CT.  PRESENCE OF NITROGEN TO BE ENSURED ON ALL THE PARTS OF DISCONNECTORS.  PERFORM THE FUNCTIONAL CHECKS.  CHECK THE INTERNAL PART OF ENCLOSURES FOR PROTRUSIONIF ANY.  PERFORM THE ERECTION DEPENDING ON THE ARRANGEMNT EITHER WITH ENCLOSURES OR DIRECTLY WITH EQUIPMENT.
  • 28. ERECTION OF CT IN GENERATOR BAY CONNECTION UNDER PROGRESS WITH CB
  • 29. ERECTION OF VOLTAGE TRANSFORMER  CHECK VT FOR DAMAGE IF ANY WITH THE VIBRATION INDICATOR PROVIDED.  NEVER OPEN THE COVER AS POSITIVE PRESSURE OF SF6 IS MAINTAINED INSIDE.  PERFORM FUNCTIONAL CHECKS.  PERFORM THE ERECTION.
  • 30. OUTDOOR ERECTION  PREPARE A PLATFORM FOR ASSEMBLY OF VARIOUS EQUIPMENTS.  PREPARE A MOBILE SHED (PREFERABLY WITH WOOD) FOR CONNECTION.  NEVER KEEP ANY EQUIPMENT UNDER OPEN POSITION. ALWAYS COVER WITH POLYTHENE PAPER TO AVOID ENTRY OF FOREIGN PARTICLE.
  • 31. EQUIPMENTS TOBE ERECTED OUTDOOR LIGHTNING ARRESTORS SF6 / AIR BUSHING TRANSFORMER END CONNECTION
  • 32. ERECTION OF LIGHTNING ARRESTORS ACTIVE PART SHALL BE THROUGHLY CLEANED TO REMOVE FOREIGN MATTER. POSITIONING OF Zno IN EACH STACK SHALL BE CHECKED. ENSURE PROPER PLACING OF ACTIVE PART INSIDE ENCLOSURE.
  • 33. ERECTION OF ACTIVE PART LA ACTIVE PART ENCLOSURE FOR ACTIVE PART
  • 34. ERECTION OF SF6/ AIR BUSHING  THIS IS END PORTION OF GIS FOR EVACUATION OF POWER.  CHECK FOR PHYSICAL DAMAGE OF INSULATORS.  PERFORM THE CONNECTION OF ENCLOSURE WITH BUSHING.  MAKE SUITABLE PLATFORM FOR ERECTION OF BUSHING WITH INSIDE BAY.  PREPARE THE ROLLER SUPPORT ON THE WALL BEFORE ERECTION OF ENCLOSURE .
  • 35. INSIDE VIEW OF BUSHING WITH BUS BAR DOUBLE SEAL ARRANGEMENT TEMPORARY SUPPORT OF BUS BAR
  • 37. HYDRAULIC OPERATING MECHANISM  THE BREAKER OPERATION IS THROUGH HYDRAULIC OPERATING MECHANISM.  DURING FILLING OF OIL CARE SHOULD BE TAKEN TO AVOID AIR TRAP INSIDE.  NITROGEN ACCUMULATORS ARE PROVIDED TO FASTER OPERATION OF CB DURING OPEN & CLOSE OPERATIONS.
  • 38. DRIVE ROD MECHANISM THE DISCONNECTORS OF ALL THE PHASES SHALL BE IN OPEN POSITION BEFORE ASSEMBLY. NUMBER OF ROTATIONS SHALL BE AS PER MANUFACTURER’S RECOMMENDATION. MECHANICAL INTERLOCK IF ANY IS TO BE PROVIDED BETWEEN DISCONNECTOR AND EARTH SWITCH.
  • 39. CABLE TRAYS, CABLING  THE CABLE TRAYS WORK CAN BE STARTED ONCE A COMPLETE BAY IS ERECTED.  CABLING WORK CAN BE STARTED ONCE PART OF CABLE TRAY ERCTION IS OVER.
  • 40. EARTHING SINCE THE ENCLOSURE IS ALUMINIUM, IT OFFERS CONTINUITY. WHEREVER FLANGE JOINTS ARE THERE, THE PAINTING SHALL BE PROPERLY REMOVED. THE FLANGES OF SHALL BE SHORTED ACROSS CT WITH EARTH FLATS. VARISTORS SHALL BE PROVIDED IN THE CT JOINT. THIS IS TO AVOID THE DAMAGE OF CT OWING TO SWITCHING TRANSIENTS.
  • 41. GAS TREATMENT THE VACCUM PUMP SHALL BE USED TO CREATE VACCUM INSIDE THE BAY WHICH IS READY. CHECK WITH GAUGE THE EXTENT OF VACCUM. MAINTAIN IT FOR 12 HOURS. PURGE THE BAY WITH NITROGEN IF MOISTURE IS IN EXCESS. CONTINUE THE VACCUM PROCESS TILL THE DESIRED LEVEL IS REACHED.
  • 42. VACCUM PUMP & GAS TREATMENT CART
  • 43. GAS TREATMENT  DILO CART SHALL BE MADE VACCUM BEFORE ACTUAL FILLING STARTS.  THE SF6 GAS FILLING SHALL BE GRADUAL.  SF6 BEING A HEAVIER GAS WILL SETTLE DOWN AT THE BOTTOM. ADEQUATE CARE SHALL BE TAKEN.  NEVER KEEP THE HOSES OPEN WHEN SF6 GAS IS NOT FILLED.  SF6 SHALL BE FILLED IN EACH COMPARTMENTS AT REQUIRED PRESSURE AS PER MANUFACTURER’S RECOMMENDATION.
  • 44. TESTING HYDRAULIC CHECKING LCC CONTROL CHECKING CT TESTING SF6 GAS CHECKING OPERATION CHECKING OF DRIVE MECHANISM TESTING OF PRESSURE SWITCH CONTACT RESISTANCE CHECKING
  • 45. HYDRAULIC CHECKING ENSURE ENOUGH OIL IS TOPPED UP INSIDE THE TANK. ALLOW THE OIL TO FLOW TILL NO AIR BUBBLES ARE TRAPPED INSIDE. THE PRESSURE SWITCH FOR HYDRAULIC MECHANISM AT EACH LEVELS SHALL BE CHECKED AS PER MANUFACTURER’S RECOMMENDATION.
  • 47. HV TESTING ONCE ALL THE CONTROL CHECKING IS OVER THEN THE EQUIPMENT IS READY FOR HV TESTING. THE ASSEMBLY OF HV TEST KIT ALONG WITH CONTROL EQUIPMENTS SHALL BE DONE.
  • 48. TYPICAL ARRANGEMENT OF HV TESTING KIT
  • 49. POINTS TO BE NOTED PRIOR TO HV TESTING SF6 GAS PRESSURE IS CHECKED IN ALL THE COMPARTMENTS. CT SECONDARY TERMINALS ARE SHORTED. VOLTAGE TRANSFORMER IS DICONNECTED. LIGHTNING ARRESTOR IS DICONNECTED. CABLE CONNECTION IS DISCONNECTED. SF6/AIR BUSHING IS THROUGHLY CLEANED.