SlideShare a Scribd company logo
1 of 1
Download to read offline
Gig Harbor High School
HVAC Improvements, Gig Harbor, Washington
Owner
Peninsula School
District
Building Type
Grades 9,10,11,12
Building Areas
80,000 Sq ft
Construction
Costs
$4,400,000
Mechanical
Systems
Gas Boilers
350 ton Chiller
Hydronic Piping
VAV boxes
Electrical Systems
Power
Fire Alarm
Main Distribution
Completion Date
August 2005
Front Entrance
Project Description
The Gig Harbor High School was originally
opened in 1980 with major additions in 1988 and
1992. To address an aging HVAC system and
concerns about indoor air quality, a complete
replacement of the existing hydronic VAV system
was accomplished over the summer of 2005.
Boiler room equipment was completely replaced
with three new condensing boilers, pumps and
piping along with a 350 ton chiller. Two new
45,000 cfm rooftop units replaced existing units to
serve classroom VAV systems. Heat recovery
units were replaced at the swimming pool and
locker rooms, new rooftop units were also
provided at the gymnasiums, theater and misc
spaces.
Hot water and chilled water pipes were replaced
throughout located above ceiling tiles. Much of
the ductwork was replaced, any existing ductwork
that was reused was cleaned, sealed and
resupported to meet current code requirements.
The shop building was also upgraded and an
existing auto shop was converted to a weight
room.
In addition to the HVAC work, supporting
documents were prepared including work done to
ceiling systems, carpet, flooring and structural
upgrades to handle added weight of equipment.
Minor modification to the sprinkler system were
done to accommodate new work.
Electrical systems included providing power to
new mechanical equipment and replacing the
entire fire alarm system. The main distribution
panels and conduits were replaced.
For the most part, all work was completed over
the school’s summer break. In order to meet the
summer construction schedule, the project was
bid early enough in the spring so that the day
school let out in June, the equipment was already
ordered with VAV boxes on site. To expedite
piping installation, above ceiling work was started
earlier during after school hours and the boiler
room was fabricated first off site and then brought
over and reinstalled.
New Pool Heat Recovery
Boiler Room Piping
Units craned on to roof
Units screened on
roof
New gym ductwork

More Related Content

What's hot

Deep Retrofit: Retrofit of a 1950s Crumlin Cottage
Deep Retrofit: Retrofit of a 1950s Crumlin CottageDeep Retrofit: Retrofit of a 1950s Crumlin Cottage
Deep Retrofit: Retrofit of a 1950s Crumlin CottageSustainableEnergyAut
 
Efficiency in Repurposed Office Tower
Efficiency in Repurposed Office TowerEfficiency in Repurposed Office Tower
Efficiency in Repurposed Office TowerMcKenney's Inc
 
LEED_NC and LEED_EB
LEED_NC and LEED_EBLEED_NC and LEED_EB
LEED_NC and LEED_EBArn Akbarieh
 
111127 Penwith Ha Heat Pod Project V3
111127 Penwith Ha Heat Pod Project V3111127 Penwith Ha Heat Pod Project V3
111127 Penwith Ha Heat Pod Project V3DenysStephens
 
Conventional Roofing Assemblies: Measuring the Thermal Benefits of Light to D...
Conventional Roofing Assemblies: Measuring the Thermal Benefits of Light to D...Conventional Roofing Assemblies: Measuring the Thermal Benefits of Light to D...
Conventional Roofing Assemblies: Measuring the Thermal Benefits of Light to D...RDH Building Science
 
ASHRAE 2006 - BVNHS
ASHRAE 2006 - BVNHSASHRAE 2006 - BVNHS
ASHRAE 2006 - BVNHSjemegerson
 
Deep Retrofit: The Dun Laoghaire-Rathdown Experience
Deep Retrofit: The Dun Laoghaire-Rathdown ExperienceDeep Retrofit: The Dun Laoghaire-Rathdown Experience
Deep Retrofit: The Dun Laoghaire-Rathdown ExperienceSustainableEnergyAut
 
Cool Building System, Inc.
Cool Building System, Inc.Cool Building System, Inc.
Cool Building System, Inc.David Hakim
 
Energy Consumption in Mid to High-rise Residential Buildings both Before and ...
Energy Consumption in Mid to High-rise Residential Buildings both Before and ...Energy Consumption in Mid to High-rise Residential Buildings both Before and ...
Energy Consumption in Mid to High-rise Residential Buildings both Before and ...RDH Building Science
 
Border foods
Border foodsBorder foods
Border foodsDms1999
 
Part l dwellings - nzeb and major renovations
Part l dwellings - nzeb and major renovationsPart l dwellings - nzeb and major renovations
Part l dwellings - nzeb and major renovationsSustainableEnergyAut
 
Ventilation in Multi-Family Buildings - Summer Camp 2015
Ventilation in Multi-Family Buildings - Summer Camp 2015Ventilation in Multi-Family Buildings - Summer Camp 2015
Ventilation in Multi-Family Buildings - Summer Camp 2015Lorne Ricketts
 
Cem 350 hvac ductwork ii 11 2015
Cem 350 hvac ductwork ii 11 2015Cem 350 hvac ductwork ii 11 2015
Cem 350 hvac ductwork ii 11 2015miresmaeil
 
Fort Benning Adds Energy-Efficient Barracks - Building Information Modeling (...
Fort Benning Adds Energy-Efficient Barracks - Building Information Modeling (...Fort Benning Adds Energy-Efficient Barracks - Building Information Modeling (...
Fort Benning Adds Energy-Efficient Barracks - Building Information Modeling (...McKenney's Inc
 

What's hot (20)

Deep Retrofit: Retrofit of a 1950s Crumlin Cottage
Deep Retrofit: Retrofit of a 1950s Crumlin CottageDeep Retrofit: Retrofit of a 1950s Crumlin Cottage
Deep Retrofit: Retrofit of a 1950s Crumlin Cottage
 
Efficiency in Repurposed Office Tower
Efficiency in Repurposed Office TowerEfficiency in Repurposed Office Tower
Efficiency in Repurposed Office Tower
 
Innovations in Multifamily Building Energy Savings
Innovations in Multifamily Building Energy SavingsInnovations in Multifamily Building Energy Savings
Innovations in Multifamily Building Energy Savings
 
LEED_NC and LEED_EB
LEED_NC and LEED_EBLEED_NC and LEED_EB
LEED_NC and LEED_EB
 
Terry Plaisted, Automatic Heating
Terry Plaisted, Automatic HeatingTerry Plaisted, Automatic Heating
Terry Plaisted, Automatic Heating
 
Condensing Boiler Optimization
Condensing Boiler OptimizationCondensing Boiler Optimization
Condensing Boiler Optimization
 
111127 Penwith Ha Heat Pod Project V3
111127 Penwith Ha Heat Pod Project V3111127 Penwith Ha Heat Pod Project V3
111127 Penwith Ha Heat Pod Project V3
 
Webinar- Air Source Heat Pumps: Cold Climate Ready
Webinar- Air Source Heat Pumps: Cold Climate ReadyWebinar- Air Source Heat Pumps: Cold Climate Ready
Webinar- Air Source Heat Pumps: Cold Climate Ready
 
Conventional Roofing Assemblies: Measuring the Thermal Benefits of Light to D...
Conventional Roofing Assemblies: Measuring the Thermal Benefits of Light to D...Conventional Roofing Assemblies: Measuring the Thermal Benefits of Light to D...
Conventional Roofing Assemblies: Measuring the Thermal Benefits of Light to D...
 
ASHRAE 2006 - BVNHS
ASHRAE 2006 - BVNHSASHRAE 2006 - BVNHS
ASHRAE 2006 - BVNHS
 
Cold Cliamte Air Source Heat Pumps: Study Update
Cold Cliamte Air Source Heat Pumps: Study UpdateCold Cliamte Air Source Heat Pumps: Study Update
Cold Cliamte Air Source Heat Pumps: Study Update
 
Deep Retrofit: The Dun Laoghaire-Rathdown Experience
Deep Retrofit: The Dun Laoghaire-Rathdown ExperienceDeep Retrofit: The Dun Laoghaire-Rathdown Experience
Deep Retrofit: The Dun Laoghaire-Rathdown Experience
 
Cool Building System, Inc.
Cool Building System, Inc.Cool Building System, Inc.
Cool Building System, Inc.
 
Saving Energy in Existing Multifamily Buildings
Saving Energy in Existing Multifamily BuildingsSaving Energy in Existing Multifamily Buildings
Saving Energy in Existing Multifamily Buildings
 
Energy Consumption in Mid to High-rise Residential Buildings both Before and ...
Energy Consumption in Mid to High-rise Residential Buildings both Before and ...Energy Consumption in Mid to High-rise Residential Buildings both Before and ...
Energy Consumption in Mid to High-rise Residential Buildings both Before and ...
 
Border foods
Border foodsBorder foods
Border foods
 
Part l dwellings - nzeb and major renovations
Part l dwellings - nzeb and major renovationsPart l dwellings - nzeb and major renovations
Part l dwellings - nzeb and major renovations
 
Ventilation in Multi-Family Buildings - Summer Camp 2015
Ventilation in Multi-Family Buildings - Summer Camp 2015Ventilation in Multi-Family Buildings - Summer Camp 2015
Ventilation in Multi-Family Buildings - Summer Camp 2015
 
Cem 350 hvac ductwork ii 11 2015
Cem 350 hvac ductwork ii 11 2015Cem 350 hvac ductwork ii 11 2015
Cem 350 hvac ductwork ii 11 2015
 
Fort Benning Adds Energy-Efficient Barracks - Building Information Modeling (...
Fort Benning Adds Energy-Efficient Barracks - Building Information Modeling (...Fort Benning Adds Energy-Efficient Barracks - Building Information Modeling (...
Fort Benning Adds Energy-Efficient Barracks - Building Information Modeling (...
 

Viewers also liked

Promotional Sheet - Fife JH
Promotional Sheet - Fife JHPromotional Sheet - Fife JH
Promotional Sheet - Fife JHLinda Burman
 
Kennydale Promotional Sheet
Kennydale Promotional SheetKennydale Promotional Sheet
Kennydale Promotional SheetLinda Burman
 
HSDC Promotional Page
HSDC Promotional PageHSDC Promotional Page
HSDC Promotional PageLinda Burman
 
Promotional Sheet - Sequayah
Promotional Sheet - SequayahPromotional Sheet - Sequayah
Promotional Sheet - SequayahLinda Burman
 
Promotional Sheet - Grand Mound
Promotional Sheet - Grand MoundPromotional Sheet - Grand Mound
Promotional Sheet - Grand MoundLinda Burman
 
Linda Burman resume and work history
Linda Burman resume and work historyLinda Burman resume and work history
Linda Burman resume and work historyLinda Burman
 

Viewers also liked (6)

Promotional Sheet - Fife JH
Promotional Sheet - Fife JHPromotional Sheet - Fife JH
Promotional Sheet - Fife JH
 
Kennydale Promotional Sheet
Kennydale Promotional SheetKennydale Promotional Sheet
Kennydale Promotional Sheet
 
HSDC Promotional Page
HSDC Promotional PageHSDC Promotional Page
HSDC Promotional Page
 
Promotional Sheet - Sequayah
Promotional Sheet - SequayahPromotional Sheet - Sequayah
Promotional Sheet - Sequayah
 
Promotional Sheet - Grand Mound
Promotional Sheet - Grand MoundPromotional Sheet - Grand Mound
Promotional Sheet - Grand Mound
 
Linda Burman resume and work history
Linda Burman resume and work historyLinda Burman resume and work history
Linda Burman resume and work history
 

Similar to Gig Harbor High School Promotional Sheet

Building Goodwill Under Pressure - HVAC Rebuild in Charlotte, NC
Building Goodwill Under Pressure - HVAC Rebuild in Charlotte, NCBuilding Goodwill Under Pressure - HVAC Rebuild in Charlotte, NC
Building Goodwill Under Pressure - HVAC Rebuild in Charlotte, NCMcKenney's Inc
 
A Breakout Turnkey HVAC Conversion - Turnkey Design/Build
A Breakout Turnkey HVAC Conversion - Turnkey Design/BuildA Breakout Turnkey HVAC Conversion - Turnkey Design/Build
A Breakout Turnkey HVAC Conversion - Turnkey Design/BuildMcKenney's Inc
 
2010 Building Science Corporation Expert Session - Mechanical System Selection
2010 Building Science Corporation Expert Session - Mechanical System Selection2010 Building Science Corporation Expert Session - Mechanical System Selection
2010 Building Science Corporation Expert Session - Mechanical System SelectionPetersen Engineering, Inc.
 
Building services-i (2)
Building services-i (2)Building services-i (2)
Building services-i (2)Lwj Welson
 
King Street Station Utilities Installation 2.20.11 slide show
King Street Station Utilities Installation 2.20.11 slide showKing Street Station Utilities Installation 2.20.11 slide show
King Street Station Utilities Installation 2.20.11 slide showallieger
 
R. A. Edwards and Partners Ltd. Company Profile
R. A. Edwards and Partners Ltd.   Company ProfileR. A. Edwards and Partners Ltd.   Company Profile
R. A. Edwards and Partners Ltd. Company Profiledownsy222
 
Cooling Down a Refrigeration Plant - Columbus, Georgia
Cooling Down a Refrigeration Plant - Columbus, GeorgiaCooling Down a Refrigeration Plant - Columbus, Georgia
Cooling Down a Refrigeration Plant - Columbus, GeorgiaMcKenney's Inc
 
Rock Valley College - Chilled Beams Lesson Learned
Rock Valley College - Chilled Beams Lesson LearnedRock Valley College - Chilled Beams Lesson Learned
Rock Valley College - Chilled Beams Lesson LearnedIllinois ASHRAE
 
13 Us Vrv Vrv S Us Installs
13 Us Vrv Vrv S Us Installs13 Us Vrv Vrv S Us Installs
13 Us Vrv Vrv S Us InstallsTNIFTP
 
Renewable Energy Systems For Building Professionals Great Lakes Brewing Com...
Renewable Energy Systems For Building Professionals   Great Lakes Brewing Com...Renewable Energy Systems For Building Professionals   Great Lakes Brewing Com...
Renewable Energy Systems For Building Professionals Great Lakes Brewing Com...gogeisel
 
April Forum: The Hit List - The Top Tips to Green NYC Buildings Part 1 of 3 E...
April Forum: The Hit List - The Top Tips to Green NYC Buildings Part 1 of 3 E...April Forum: The Hit List - The Top Tips to Green NYC Buildings Part 1 of 3 E...
April Forum: The Hit List - The Top Tips to Green NYC Buildings Part 1 of 3 E...GreenHomeNYC
 
Manufacturing Facility Hits the Floor Running - Process Piping and HVAC Syste...
Manufacturing Facility Hits the Floor Running - Process Piping and HVAC Syste...Manufacturing Facility Hits the Floor Running - Process Piping and HVAC Syste...
Manufacturing Facility Hits the Floor Running - Process Piping and HVAC Syste...McKenney's Inc
 
500 Ton Chiller Project
500 Ton Chiller Project500 Ton Chiller Project
500 Ton Chiller ProjectPaul Gerber
 
Pre-fab Headers Keep Job Ahead of Schedule
Pre-fab Headers Keep Job Ahead of SchedulePre-fab Headers Keep Job Ahead of Schedule
Pre-fab Headers Keep Job Ahead of ScheduleMcKenney's Inc
 
HVAC Installation Makes the Grade
HVAC Installation Makes the GradeHVAC Installation Makes the Grade
HVAC Installation Makes the GradeMcKenney's Inc
 
Cooling Tower and Pump Retrofit | HVAC Installation
Cooling Tower and Pump Retrofit | HVAC Installation Cooling Tower and Pump Retrofit | HVAC Installation
Cooling Tower and Pump Retrofit | HVAC Installation McKenney's Inc
 
Northern Illinois University_Cole Hall2 CHI cs
Northern Illinois University_Cole Hall2 CHI csNorthern Illinois University_Cole Hall2 CHI cs
Northern Illinois University_Cole Hall2 CHI csMonica LaBrot
 
A Greener Hospital by Design
A Greener Hospital by DesignA Greener Hospital by Design
A Greener Hospital by DesignMcKenney's Inc
 

Similar to Gig Harbor High School Promotional Sheet (20)

Building Goodwill Under Pressure - HVAC Rebuild in Charlotte, NC
Building Goodwill Under Pressure - HVAC Rebuild in Charlotte, NCBuilding Goodwill Under Pressure - HVAC Rebuild in Charlotte, NC
Building Goodwill Under Pressure - HVAC Rebuild in Charlotte, NC
 
Major Project List
Major Project ListMajor Project List
Major Project List
 
A Breakout Turnkey HVAC Conversion - Turnkey Design/Build
A Breakout Turnkey HVAC Conversion - Turnkey Design/BuildA Breakout Turnkey HVAC Conversion - Turnkey Design/Build
A Breakout Turnkey HVAC Conversion - Turnkey Design/Build
 
2009 Summer Capital Projects
2009 Summer Capital Projects2009 Summer Capital Projects
2009 Summer Capital Projects
 
2010 Building Science Corporation Expert Session - Mechanical System Selection
2010 Building Science Corporation Expert Session - Mechanical System Selection2010 Building Science Corporation Expert Session - Mechanical System Selection
2010 Building Science Corporation Expert Session - Mechanical System Selection
 
Building services-i (2)
Building services-i (2)Building services-i (2)
Building services-i (2)
 
King Street Station Utilities Installation 2.20.11 slide show
King Street Station Utilities Installation 2.20.11 slide showKing Street Station Utilities Installation 2.20.11 slide show
King Street Station Utilities Installation 2.20.11 slide show
 
R. A. Edwards and Partners Ltd. Company Profile
R. A. Edwards and Partners Ltd.   Company ProfileR. A. Edwards and Partners Ltd.   Company Profile
R. A. Edwards and Partners Ltd. Company Profile
 
Cooling Down a Refrigeration Plant - Columbus, Georgia
Cooling Down a Refrigeration Plant - Columbus, GeorgiaCooling Down a Refrigeration Plant - Columbus, Georgia
Cooling Down a Refrigeration Plant - Columbus, Georgia
 
Rock Valley College - Chilled Beams Lesson Learned
Rock Valley College - Chilled Beams Lesson LearnedRock Valley College - Chilled Beams Lesson Learned
Rock Valley College - Chilled Beams Lesson Learned
 
13 Us Vrv Vrv S Us Installs
13 Us Vrv Vrv S Us Installs13 Us Vrv Vrv S Us Installs
13 Us Vrv Vrv S Us Installs
 
Renewable Energy Systems For Building Professionals Great Lakes Brewing Com...
Renewable Energy Systems For Building Professionals   Great Lakes Brewing Com...Renewable Energy Systems For Building Professionals   Great Lakes Brewing Com...
Renewable Energy Systems For Building Professionals Great Lakes Brewing Com...
 
April Forum: The Hit List - The Top Tips to Green NYC Buildings Part 1 of 3 E...
April Forum: The Hit List - The Top Tips to Green NYC Buildings Part 1 of 3 E...April Forum: The Hit List - The Top Tips to Green NYC Buildings Part 1 of 3 E...
April Forum: The Hit List - The Top Tips to Green NYC Buildings Part 1 of 3 E...
 
Manufacturing Facility Hits the Floor Running - Process Piping and HVAC Syste...
Manufacturing Facility Hits the Floor Running - Process Piping and HVAC Syste...Manufacturing Facility Hits the Floor Running - Process Piping and HVAC Syste...
Manufacturing Facility Hits the Floor Running - Process Piping and HVAC Syste...
 
500 Ton Chiller Project
500 Ton Chiller Project500 Ton Chiller Project
500 Ton Chiller Project
 
Pre-fab Headers Keep Job Ahead of Schedule
Pre-fab Headers Keep Job Ahead of SchedulePre-fab Headers Keep Job Ahead of Schedule
Pre-fab Headers Keep Job Ahead of Schedule
 
HVAC Installation Makes the Grade
HVAC Installation Makes the GradeHVAC Installation Makes the Grade
HVAC Installation Makes the Grade
 
Cooling Tower and Pump Retrofit | HVAC Installation
Cooling Tower and Pump Retrofit | HVAC Installation Cooling Tower and Pump Retrofit | HVAC Installation
Cooling Tower and Pump Retrofit | HVAC Installation
 
Northern Illinois University_Cole Hall2 CHI cs
Northern Illinois University_Cole Hall2 CHI csNorthern Illinois University_Cole Hall2 CHI cs
Northern Illinois University_Cole Hall2 CHI cs
 
A Greener Hospital by Design
A Greener Hospital by DesignA Greener Hospital by Design
A Greener Hospital by Design
 

Gig Harbor High School Promotional Sheet

  • 1. Gig Harbor High School HVAC Improvements, Gig Harbor, Washington Owner Peninsula School District Building Type Grades 9,10,11,12 Building Areas 80,000 Sq ft Construction Costs $4,400,000 Mechanical Systems Gas Boilers 350 ton Chiller Hydronic Piping VAV boxes Electrical Systems Power Fire Alarm Main Distribution Completion Date August 2005 Front Entrance Project Description The Gig Harbor High School was originally opened in 1980 with major additions in 1988 and 1992. To address an aging HVAC system and concerns about indoor air quality, a complete replacement of the existing hydronic VAV system was accomplished over the summer of 2005. Boiler room equipment was completely replaced with three new condensing boilers, pumps and piping along with a 350 ton chiller. Two new 45,000 cfm rooftop units replaced existing units to serve classroom VAV systems. Heat recovery units were replaced at the swimming pool and locker rooms, new rooftop units were also provided at the gymnasiums, theater and misc spaces. Hot water and chilled water pipes were replaced throughout located above ceiling tiles. Much of the ductwork was replaced, any existing ductwork that was reused was cleaned, sealed and resupported to meet current code requirements. The shop building was also upgraded and an existing auto shop was converted to a weight room. In addition to the HVAC work, supporting documents were prepared including work done to ceiling systems, carpet, flooring and structural upgrades to handle added weight of equipment. Minor modification to the sprinkler system were done to accommodate new work. Electrical systems included providing power to new mechanical equipment and replacing the entire fire alarm system. The main distribution panels and conduits were replaced. For the most part, all work was completed over the school’s summer break. In order to meet the summer construction schedule, the project was bid early enough in the spring so that the day school let out in June, the equipment was already ordered with VAV boxes on site. To expedite piping installation, above ceiling work was started earlier during after school hours and the boiler room was fabricated first off site and then brought over and reinstalled. New Pool Heat Recovery Boiler Room Piping Units craned on to roof Units screened on roof New gym ductwork