SlideShare a Scribd company logo
1 of 1
Download to read offline
Hearing Speech and Deafness Center
Seattle, WA
Owner
HSDC
Area of Building
32,000 Sq. Ft.
Construction
Cost
Mechanical-
$653,000
Electrical-
Mechanical
Systems
Gas Boilers
Chiller
Air Handlers
VAV
Electrical
Systems
Lighting
Power Distribution
Fire Alarm
Telephone/Data
Television
Security
Completion Date
Fall 2003
Project Description
Project involved a new two story office
building with hearing labs to replace
an existing aging facility. Two levels
of parking were constructed below and
six levels of condominium units in two
towers were built above.
Mechanical:
The central heating plant consists of
two gas fired boilers which pipe hot
water through a two pipe hydronic
loop to central air handlers and VAV
boxes. A rooftop chiller provided
cooling to a central air handler located
in the parking garage as well as
smaller fan coil units to serve future
retail spaces.
Special consideration was given to
acoustics in order to allow for proper
facility operation as a hearing center.
Special system design included sound
attenuators, reduced velocity duct
work sizing and low noise air terminal
selection.
Exterior
Exterior Elevation
Entry/Hall
Kid’s Space

More Related Content

What's hot

King Street Station Utilities Installation 2.20.11 slide show
King Street Station Utilities Installation 2.20.11 slide showKing Street Station Utilities Installation 2.20.11 slide show
King Street Station Utilities Installation 2.20.11 slide showallieger
 
Retrofitting skyscraper
Retrofitting skyscraper Retrofitting skyscraper
Retrofitting skyscraper Shamitha Reddy
 
Thermoelectricpresentation
ThermoelectricpresentationThermoelectricpresentation
ThermoelectricpresentationZondits
 
Courtyard Effect (passive cooling technique)
Courtyard Effect (passive cooling technique)Courtyard Effect (passive cooling technique)
Courtyard Effect (passive cooling technique)Drishty Ranjit
 
Concept of radiant cooling and geothermal system
Concept of radiant cooling and geothermal systemConcept of radiant cooling and geothermal system
Concept of radiant cooling and geothermal systemENERGIA INNOVATION Ltd
 
Turbo energy limited (active india)
Turbo energy limited (active india)Turbo energy limited (active india)
Turbo energy limited (active india)Mudra Redkar
 
Sem 2 bs1 Hot water supply system 2
Sem 2 bs1 Hot water supply system 2Sem 2 bs1 Hot water supply system 2
Sem 2 bs1 Hot water supply system 2Est
 
Looking for Energy Savings In All The Right Places - Eric Oliver
Looking for Energy Savings In All The Right Places - Eric OliverLooking for Energy Savings In All The Right Places - Eric Oliver
Looking for Energy Savings In All The Right Places - Eric OliverChris Cheatham
 
Remko WKF inverter heat pump/ Bomba de calor inverter Remko WKF
Remko WKF inverter heat pump/ Bomba de calor inverter Remko WKFRemko WKF inverter heat pump/ Bomba de calor inverter Remko WKF
Remko WKF inverter heat pump/ Bomba de calor inverter Remko WKFDynamic444
 
THE CRYSTAL, LONDON: A SUSTAINABLE INTELLIGENT BUILDING CASESTUDY BY LAKSHMI ...
THE CRYSTAL, LONDON: A SUSTAINABLE INTELLIGENT BUILDING CASESTUDY BY LAKSHMI ...THE CRYSTAL, LONDON: A SUSTAINABLE INTELLIGENT BUILDING CASESTUDY BY LAKSHMI ...
THE CRYSTAL, LONDON: A SUSTAINABLE INTELLIGENT BUILDING CASESTUDY BY LAKSHMI ...Lakshmi Ravi Chandu Kolusu
 
Evaporative cooling
Evaporative coolingEvaporative cooling
Evaporative coolingNEHA SINGHI
 
40 gallon propane water heater
40 gallon propane water heater40 gallon propane water heater
40 gallon propane water heaterwaterheater
 

What's hot (20)

King Street Station Utilities Installation 2.20.11 slide show
King Street Station Utilities Installation 2.20.11 slide showKing Street Station Utilities Installation 2.20.11 slide show
King Street Station Utilities Installation 2.20.11 slide show
 
Radiant cooling
Radiant coolingRadiant cooling
Radiant cooling
 
Retrofitting skyscraper
Retrofitting skyscraper Retrofitting skyscraper
Retrofitting skyscraper
 
Thermoelectricpresentation
ThermoelectricpresentationThermoelectricpresentation
Thermoelectricpresentation
 
Courtyard Effect (passive cooling technique)
Courtyard Effect (passive cooling technique)Courtyard Effect (passive cooling technique)
Courtyard Effect (passive cooling technique)
 
ZERO ENERGY BUILDING ENVELOPE COMPONENTS
ZERO ENERGY BUILDING ENVELOPE COMPONENTSZERO ENERGY BUILDING ENVELOPE COMPONENTS
ZERO ENERGY BUILDING ENVELOPE COMPONENTS
 
Presentation
PresentationPresentation
Presentation
 
Concept of radiant cooling and geothermal system
Concept of radiant cooling and geothermal systemConcept of radiant cooling and geothermal system
Concept of radiant cooling and geothermal system
 
Turbo energy limited (active india)
Turbo energy limited (active india)Turbo energy limited (active india)
Turbo energy limited (active india)
 
Natural ventilation
Natural ventilationNatural ventilation
Natural ventilation
 
Projects
ProjectsProjects
Projects
 
GSW Headquaters,Berlin
GSW Headquaters,BerlinGSW Headquaters,Berlin
GSW Headquaters,Berlin
 
Light and ventalitaion
Light and ventalitaionLight and ventalitaion
Light and ventalitaion
 
Sem 2 bs1 Hot water supply system 2
Sem 2 bs1 Hot water supply system 2Sem 2 bs1 Hot water supply system 2
Sem 2 bs1 Hot water supply system 2
 
Looking for Energy Savings In All The Right Places - Eric Oliver
Looking for Energy Savings In All The Right Places - Eric OliverLooking for Energy Savings In All The Right Places - Eric Oliver
Looking for Energy Savings In All The Right Places - Eric Oliver
 
Natural ventilation
Natural ventilationNatural ventilation
Natural ventilation
 
Remko WKF inverter heat pump/ Bomba de calor inverter Remko WKF
Remko WKF inverter heat pump/ Bomba de calor inverter Remko WKFRemko WKF inverter heat pump/ Bomba de calor inverter Remko WKF
Remko WKF inverter heat pump/ Bomba de calor inverter Remko WKF
 
THE CRYSTAL, LONDON: A SUSTAINABLE INTELLIGENT BUILDING CASESTUDY BY LAKSHMI ...
THE CRYSTAL, LONDON: A SUSTAINABLE INTELLIGENT BUILDING CASESTUDY BY LAKSHMI ...THE CRYSTAL, LONDON: A SUSTAINABLE INTELLIGENT BUILDING CASESTUDY BY LAKSHMI ...
THE CRYSTAL, LONDON: A SUSTAINABLE INTELLIGENT BUILDING CASESTUDY BY LAKSHMI ...
 
Evaporative cooling
Evaporative coolingEvaporative cooling
Evaporative cooling
 
40 gallon propane water heater
40 gallon propane water heater40 gallon propane water heater
40 gallon propane water heater
 

Similar to Hearing and Speech Center Construction Project in Seattle

Alan Beshansky resume 42116 1
Alan Beshansky resume 42116 1Alan Beshansky resume 42116 1
Alan Beshansky resume 42116 1Alan Beshansky
 
Kennydale Promotional Sheet
Kennydale Promotional SheetKennydale Promotional Sheet
Kennydale Promotional SheetLinda Burman
 
Air Conditioning case study
Air Conditioning case studyAir Conditioning case study
Air Conditioning case studySona Rawat
 
LeeHanveyPortfolio2016
LeeHanveyPortfolio2016LeeHanveyPortfolio2016
LeeHanveyPortfolio2016Lee Hanvey
 
A Breakout Turnkey HVAC Conversion - Turnkey Design/Build
A Breakout Turnkey HVAC Conversion - Turnkey Design/BuildA Breakout Turnkey HVAC Conversion - Turnkey Design/Build
A Breakout Turnkey HVAC Conversion - Turnkey Design/BuildMcKenney's Inc
 
Hot Aisle & Cold Aisle Containment Solutions & Case Studies
Hot Aisle & Cold Aisle Containment Solutions & Case StudiesHot Aisle & Cold Aisle Containment Solutions & Case Studies
Hot Aisle & Cold Aisle Containment Solutions & Case Studies42U Data Center Solutions
 
Km89 fridge in a cooler (wecompress)
Km89 fridge in a cooler (wecompress)Km89 fridge in a cooler (wecompress)
Km89 fridge in a cooler (wecompress)1000kv technologies
 
Promotional Sheet - Sequayah
Promotional Sheet - SequayahPromotional Sheet - Sequayah
Promotional Sheet - SequayahLinda Burman
 
3 cf ch-006_hvac_systems
3 cf ch-006_hvac_systems3 cf ch-006_hvac_systems
3 cf ch-006_hvac_systemsbhattbhai
 
Rock Valley College - Chilled Beams Lesson Learned
Rock Valley College - Chilled Beams Lesson LearnedRock Valley College - Chilled Beams Lesson Learned
Rock Valley College - Chilled Beams Lesson LearnedIllinois ASHRAE
 
Rooftop Data Center Chilled Water Plant Installation | Atlanta, GA
Rooftop Data Center Chilled Water Plant Installation | Atlanta, GARooftop Data Center Chilled Water Plant Installation | Atlanta, GA
Rooftop Data Center Chilled Water Plant Installation | Atlanta, GAMcKenney's Inc
 
Cooling & Power Issues
Cooling & Power IssuesCooling & Power Issues
Cooling & Power Issuesinstor
 
Heatstar Technical Advice paper - 'New 2022 building regulations'
Heatstar Technical Advice paper - 'New 2022 building regulations'Heatstar Technical Advice paper - 'New 2022 building regulations'
Heatstar Technical Advice paper - 'New 2022 building regulations'Heatstar
 
13 Us Vrv Vrv S Us Installs
13 Us Vrv Vrv S Us Installs13 Us Vrv Vrv S Us Installs
13 Us Vrv Vrv S Us InstallsTNIFTP
 

Similar to Hearing and Speech Center Construction Project in Seattle (20)

Alan Beshansky resume 42116 1
Alan Beshansky resume 42116 1Alan Beshansky resume 42116 1
Alan Beshansky resume 42116 1
 
Kennydale Promotional Sheet
Kennydale Promotional SheetKennydale Promotional Sheet
Kennydale Promotional Sheet
 
Bs2 assignment
Bs2 assignmentBs2 assignment
Bs2 assignment
 
Air Conditioning case study
Air Conditioning case studyAir Conditioning case study
Air Conditioning case study
 
Bahniuk Utility Job
Bahniuk Utility JobBahniuk Utility Job
Bahniuk Utility Job
 
LeeHanveyPortfolio2016
LeeHanveyPortfolio2016LeeHanveyPortfolio2016
LeeHanveyPortfolio2016
 
A Breakout Turnkey HVAC Conversion - Turnkey Design/Build
A Breakout Turnkey HVAC Conversion - Turnkey Design/BuildA Breakout Turnkey HVAC Conversion - Turnkey Design/Build
A Breakout Turnkey HVAC Conversion - Turnkey Design/Build
 
Hot Aisle & Cold Aisle Containment Solutions & Case Studies
Hot Aisle & Cold Aisle Containment Solutions & Case StudiesHot Aisle & Cold Aisle Containment Solutions & Case Studies
Hot Aisle & Cold Aisle Containment Solutions & Case Studies
 
Km89 fridge in a cooler (wecompress)
Km89 fridge in a cooler (wecompress)Km89 fridge in a cooler (wecompress)
Km89 fridge in a cooler (wecompress)
 
Promotional Sheet - Sequayah
Promotional Sheet - SequayahPromotional Sheet - Sequayah
Promotional Sheet - Sequayah
 
Citigroup clayco
Citigroup claycoCitigroup clayco
Citigroup clayco
 
3 cf ch-006_hvac_systems
3 cf ch-006_hvac_systems3 cf ch-006_hvac_systems
3 cf ch-006_hvac_systems
 
2015 Resume
2015 Resume2015 Resume
2015 Resume
 
Rock Valley College - Chilled Beams Lesson Learned
Rock Valley College - Chilled Beams Lesson LearnedRock Valley College - Chilled Beams Lesson Learned
Rock Valley College - Chilled Beams Lesson Learned
 
O & C Refurb
O & C RefurbO & C Refurb
O & C Refurb
 
Rooftop Data Center Chilled Water Plant Installation | Atlanta, GA
Rooftop Data Center Chilled Water Plant Installation | Atlanta, GARooftop Data Center Chilled Water Plant Installation | Atlanta, GA
Rooftop Data Center Chilled Water Plant Installation | Atlanta, GA
 
Cooling & Power Issues
Cooling & Power IssuesCooling & Power Issues
Cooling & Power Issues
 
Final Poster
Final PosterFinal Poster
Final Poster
 
Heatstar Technical Advice paper - 'New 2022 building regulations'
Heatstar Technical Advice paper - 'New 2022 building regulations'Heatstar Technical Advice paper - 'New 2022 building regulations'
Heatstar Technical Advice paper - 'New 2022 building regulations'
 
13 Us Vrv Vrv S Us Installs
13 Us Vrv Vrv S Us Installs13 Us Vrv Vrv S Us Installs
13 Us Vrv Vrv S Us Installs
 

Hearing and Speech Center Construction Project in Seattle

  • 1. Hearing Speech and Deafness Center Seattle, WA Owner HSDC Area of Building 32,000 Sq. Ft. Construction Cost Mechanical- $653,000 Electrical- Mechanical Systems Gas Boilers Chiller Air Handlers VAV Electrical Systems Lighting Power Distribution Fire Alarm Telephone/Data Television Security Completion Date Fall 2003 Project Description Project involved a new two story office building with hearing labs to replace an existing aging facility. Two levels of parking were constructed below and six levels of condominium units in two towers were built above. Mechanical: The central heating plant consists of two gas fired boilers which pipe hot water through a two pipe hydronic loop to central air handlers and VAV boxes. A rooftop chiller provided cooling to a central air handler located in the parking garage as well as smaller fan coil units to serve future retail spaces. Special consideration was given to acoustics in order to allow for proper facility operation as a hearing center. Special system design included sound attenuators, reduced velocity duct work sizing and low noise air terminal selection. Exterior Exterior Elevation Entry/Hall Kid’s Space