The risk assessment document identifies several risks associated with gas welding work and proposes control measures. It analyzes risks from pre-work preparation, unloading equipment, dismantling pipes, hot work activities, vehicle traffic, cleaning and poor housekeeping. Specific hazards include injuries from dropped objects, fires, explosions, toxic fumes, and musculoskeletal disorders. The document recommends procedures like permits, inspections, defined roles, proper PPE, designated areas, and waste disposal to mitigate risks and reduce the likelihood and severity of incidents during the work.
Project Name: xxx
RA Ref No.: xxx
RA compilation Date: Review date:
Date:
Compiled by:
Reviewed by:
Approved by:
Overall Task Details
Use of mechanical breakers – excavator – for demolition of concrete structure Relevant Applicable MAS:
• 00940 – Plant Operators; Additional Training required:
NOC’s Required for task:
RISK SCORE CALCULATOR
Use the Risk Score Calculator to Determine the Level of Risk of each Hazard
What would be the
CONSEQUENCE
of an occurrence be? What is the LIKELIHOOD of an occurrence? Hierarchy of Controls
Frequent/Almost certain (5)
Continuous or will happen frequently Often (4)
6 to 12 times a year Likely (3)
1 to 5 times a year Possible (2)
Once every 5 years Rarely (1)
Less than once every 5 years Can the hazard be Eliminated or removed from the work place?
Catastrophic (5)
Multiple Fatalities High 25 High 20 High 15 Medium 10 Medium 5 Can the product or process be substituted for a less hazardous alternative?
Serious (4)
Class 1 single fatality High 20 High 16 High 12 Medium 8 Low 4 Can the hazard be engineered away with guards or barriers?
Moderate (3)
Class2 (AWI or LTI) or Class 1 Permanently disabling effects High 15 High 12 Medium 9 Medium 6 Low 3 Can Administration Controls be adopted
I.e. procedures, job rotation etc.
Minor (2)
Medical attention needed, no work restrictions. MTI Medium10 Medium 8 Medium 6 Low 4 Low 2 Can Personal Protective Equipment & Clothing be worn to safe guard against hazards?
Insignificant (1)
FAI Medium10 Medium 4 Low 3 Low 2 Low 1
No Specific Task Step
(In sequence of works) Hazard Details Consequence/Risk Initial Risk Rating Control Measures Residual Risks Additional Control Measures RR
L C RR
1 Plant checks on arrival to site
PRIOR TO SITE ACCESS • Use of heavy plant for demolition; • Unauthorized operation of the plant resulting in incident;
• Failure due to use of un-certificated plant;
3 4 12
HIGH i. All plant to be Third Party Certificated by a DM approved inspector, documentation available on arrival to site;
ii. Operators to have in-date Third Party certificate by approved body, available for review on arrival to site;
iii. Visual inspection of plant undertaken by competent person; Documentation unavailable for review Plant quarantined until evidence provided Low
2 Demolition of concrete structure • Excavator breaker operation
• (Operator)Plant / pedestrian interaction;
• Operator visibility; • Incident due to use of defective plant or associated equipment;
• Plant reversing – risk of serious injury to pedestrians;
• Unauthorized use of plant by untrained personnel;
• Collision with plant and live traffic within site boundary;
• Workers struck by working plant, very high risk of fatality;
• Noise;
• Exposed rebar – risk of injury;
• Possible contamination of asbestos in structure;
• Proximity to public areas;
4 4 16 HIGH i. Demolition Method statement to be submitted and adhered to. Demolition to be undertaken in a sequential, controlled
Overhead crane, crane safety, lifting operation, EHS, Safety, Testing of Crane, Commissioning of Cranes,
for soft copy please email me at dawoodibrar@hotmail.com
Accommodation Name: Date :
Accommodation Location: Time :
SN Description Yes NO N/A Observation Control
Measures Due Date
ACCESS AND EGRESS
1 Is there segregation between vehicles/ pedestrians
2 Is entry to inside camp restricted to workforce only? How is this controlled
3 Is the entrance well lit
4 Is the entrance free from water pooling
GENERAL HOUSEKEEPING
1 Are there adequate dustbins available? Are they covered
2 Is garbage disposed of on a regular basis?
3 Are toilets wash areas cleaned regular?
4 Is there adequate water for toilet and bath
5 Are water tanks kept covered at all times
6 Is soap and hand towels available?
7 Is bathroom area cleaned on a regular basis and kept dry and non-slippery
8 Is the water tank cleaned on a regular basis
9 Is the laundry area electrical & connections/ wires are in good condition.
10 Is the laundry area kept clean and dry
11 Is the tumble dryer filters cleaned frequently to prevent overheating
SEPTIC TANKS
1 Is the camp on main drainage?
2 If not are septic tanks provided?
3 Are septic tanks fitted with overflow alarm if not how are they prevented from overflowing
4 If septic tank in ground is it in a membrane?
5 If above ground is it protected from being hit by vehicular traffic?
FOOD PREPARATION AREA
1 Is the area kept clean and tidy
2 Are food preparation areas cleaned and free from cracks
3 Are signs for "No smoking" being posted
4 Food waste storage area is cleaned, odour free. Flies area controlled
5 Floor drains are provided in sink area
6 All refrigerators and freezers are working at correct temperatures Refrigerators 1c0 to 4c0
Freezers -14c0 to -18c0
7 Are there temp gauges fitted?
8 Are these temperatures recorded?
9 The Dining and Kitchen areas have an overall clean, tidy and well maintained appearance
10 LPG cylinders are of good conditions (free of damages)
11 Is storage of LPG satisfactory under shed & outside kitchens with no flammable materials nearby
12 Are Piping not perished
13 Are firefighting equipment provided in kitchen area?
LIVING QUARTERS
1 Are Ventilation working well
2 Is lighting suitable
3 Are Emergency numbers being posted in each room
4 Are emergency procedures posted in each room
5 Are Electrical sockets in good condition not damaged & no bare wires are placed in sockets
6 Are sockets overloaded
7 ELCB is provided checks carried out and recorded by
8 Lifting Operations with mobile crane Risk Assessment Templates
Crane checks on arrival to site
PRIOR TO USE
Access of crane to work areas
Siting and setting up of crane
Lifting of equipment and material
(Mobile crane Operator)
Crane supervision
Crane Maintenance
(revised 06-06-2018)
Project Name: xxx
RA Ref No.: xxx
RA compilation Date: Review date:
Date:
Compiled by:
Reviewed by:
Approved by:
Overall Task Details
Use of mechanical breakers – excavator – for demolition of concrete structure Relevant Applicable MAS:
• 00940 – Plant Operators; Additional Training required:
NOC’s Required for task:
RISK SCORE CALCULATOR
Use the Risk Score Calculator to Determine the Level of Risk of each Hazard
What would be the
CONSEQUENCE
of an occurrence be? What is the LIKELIHOOD of an occurrence? Hierarchy of Controls
Frequent/Almost certain (5)
Continuous or will happen frequently Often (4)
6 to 12 times a year Likely (3)
1 to 5 times a year Possible (2)
Once every 5 years Rarely (1)
Less than once every 5 years Can the hazard be Eliminated or removed from the work place?
Catastrophic (5)
Multiple Fatalities High 25 High 20 High 15 Medium 10 Medium 5 Can the product or process be substituted for a less hazardous alternative?
Serious (4)
Class 1 single fatality High 20 High 16 High 12 Medium 8 Low 4 Can the hazard be engineered away with guards or barriers?
Moderate (3)
Class2 (AWI or LTI) or Class 1 Permanently disabling effects High 15 High 12 Medium 9 Medium 6 Low 3 Can Administration Controls be adopted
I.e. procedures, job rotation etc.
Minor (2)
Medical attention needed, no work restrictions. MTI Medium10 Medium 8 Medium 6 Low 4 Low 2 Can Personal Protective Equipment & Clothing be worn to safe guard against hazards?
Insignificant (1)
FAI Medium10 Medium 4 Low 3 Low 2 Low 1
No Specific Task Step
(In sequence of works) Hazard Details Consequence/Risk Initial Risk Rating Control Measures Residual Risks Additional Control Measures RR
L C RR
1 Plant checks on arrival to site
PRIOR TO SITE ACCESS • Use of heavy plant for demolition; • Unauthorized operation of the plant resulting in incident;
• Failure due to use of un-certificated plant;
3 4 12
HIGH i. All plant to be Third Party Certificated by a DM approved inspector, documentation available on arrival to site;
ii. Operators to have in-date Third Party certificate by approved body, available for review on arrival to site;
iii. Visual inspection of plant undertaken by competent person; Documentation unavailable for review Plant quarantined until evidence provided Low
2 Demolition of concrete structure • Excavator breaker operation
• (Operator)Plant / pedestrian interaction;
• Operator visibility; • Incident due to use of defective plant or associated equipment;
• Plant reversing – risk of serious injury to pedestrians;
• Unauthorized use of plant by untrained personnel;
• Collision with plant and live traffic within site boundary;
• Workers struck by working plant, very high risk of fatality;
• Noise;
• Exposed rebar – risk of injury;
• Possible contamination of asbestos in structure;
• Proximity to public areas;
4 4 16 HIGH i. Demolition Method statement to be submitted and adhered to. Demolition to be undertaken in a sequential, controlled
Overhead crane, crane safety, lifting operation, EHS, Safety, Testing of Crane, Commissioning of Cranes,
for soft copy please email me at dawoodibrar@hotmail.com
Accommodation Name: Date :
Accommodation Location: Time :
SN Description Yes NO N/A Observation Control
Measures Due Date
ACCESS AND EGRESS
1 Is there segregation between vehicles/ pedestrians
2 Is entry to inside camp restricted to workforce only? How is this controlled
3 Is the entrance well lit
4 Is the entrance free from water pooling
GENERAL HOUSEKEEPING
1 Are there adequate dustbins available? Are they covered
2 Is garbage disposed of on a regular basis?
3 Are toilets wash areas cleaned regular?
4 Is there adequate water for toilet and bath
5 Are water tanks kept covered at all times
6 Is soap and hand towels available?
7 Is bathroom area cleaned on a regular basis and kept dry and non-slippery
8 Is the water tank cleaned on a regular basis
9 Is the laundry area electrical & connections/ wires are in good condition.
10 Is the laundry area kept clean and dry
11 Is the tumble dryer filters cleaned frequently to prevent overheating
SEPTIC TANKS
1 Is the camp on main drainage?
2 If not are septic tanks provided?
3 Are septic tanks fitted with overflow alarm if not how are they prevented from overflowing
4 If septic tank in ground is it in a membrane?
5 If above ground is it protected from being hit by vehicular traffic?
FOOD PREPARATION AREA
1 Is the area kept clean and tidy
2 Are food preparation areas cleaned and free from cracks
3 Are signs for "No smoking" being posted
4 Food waste storage area is cleaned, odour free. Flies area controlled
5 Floor drains are provided in sink area
6 All refrigerators and freezers are working at correct temperatures Refrigerators 1c0 to 4c0
Freezers -14c0 to -18c0
7 Are there temp gauges fitted?
8 Are these temperatures recorded?
9 The Dining and Kitchen areas have an overall clean, tidy and well maintained appearance
10 LPG cylinders are of good conditions (free of damages)
11 Is storage of LPG satisfactory under shed & outside kitchens with no flammable materials nearby
12 Are Piping not perished
13 Are firefighting equipment provided in kitchen area?
LIVING QUARTERS
1 Are Ventilation working well
2 Is lighting suitable
3 Are Emergency numbers being posted in each room
4 Are emergency procedures posted in each room
5 Are Electrical sockets in good condition not damaged & no bare wires are placed in sockets
6 Are sockets overloaded
7 ELCB is provided checks carried out and recorded by
8 Lifting Operations with mobile crane Risk Assessment Templates
Crane checks on arrival to site
PRIOR TO USE
Access of crane to work areas
Siting and setting up of crane
Lifting of equipment and material
(Mobile crane Operator)
Crane supervision
Crane Maintenance
(revised 06-06-2018)
21 Confined Space Working Risk Assessment Templates
Planned confined space work in areas where live services may be present including:
• Water;
• Sewerage;
• Gas;
PRIOR TO ENTRY
Confined space working –
• Deep excavations;
• Tanks;
• Vessels;
• Manholes;
• NDRC pits;
• Bridge decks;
• Pipework;
• Sewerage;
• Lift shafts;
• Ducting;
• Etc.
Project Name: xxx
RA Ref No.: xxx
RA compilation Date: Review date:
Date:
Compiled by:
Reviewed by:
Approved by:
Overall Task Details
Laying blockwork with scaffold. Classed as Temporary Works Relevant Applicable MAS:
• 00939 - CoSHH
• 00236 – Housekeeping
• 00245 – Mobile Scaffolding Additional Training required:
Temporary Works Coordinator to be designated NOC’s Required for task:
RISK SCORE CALCULATOR
Use the Risk Score Calculator to Determine the Level of Risk of each Hazard
What would be the
CONSEQUENCE
of an occurrence be? What is the LIKELIHOOD of an occurrence? Hierarchy of Controls
Frequent/Almost certain (5)
Continuous or will happen frequently Often (4)
6 to 12 times a year Likely (3)
1 to 5 times a year Possible (2)
Once every 5 years Rarely (1)
Less than once every 5 years Can the hazard be Eliminated or removed from the work place?
Catastrophic (5)
Multiple Fatalities High 25 High 20 High 15 Medium 10 Medium 5 Can the product or process be substituted for a less hazardous alternative?
Serious (4)
Class 1 single fatality High 20 High 16 High 12 Medium 8 Low 4 Can the hazard be engineered away with guards or barriers?
Moderate (3)
Class2 (AWI or LTI) or Class 1 Permanently disabling effects High 15 High 12 Medium 9 Medium 6 Low 3 Can Administration Controls be adopted
I.e. procedures, job rotation etc.
Minor (2)
Medical attention needed, no work restrictions. MTI Medium10 Medium 8 Medium 6 Low 4 Low 2 Can Personal Protective Equipment & Clothing be worn to safe guard against hazards?
Insignificant (1)
FAI Medium10 Medium 4 Low 3 Low 2 Low 1
No Specific Task Step
(In sequence of works) Hazard Details Consequence/Risk Initial Risk Rating Control Measures Residual Risks Additional Control Measures RR
P S RR
1 Vehicles/Plant Equipment movements for block delivery
Hi-Abs, forklifts etc. • Use of plant;
• Plant / worker proximity; • Unauthorised use of untrained or unlicensed operators;
• Use of un-certificated plant and equipment;
• Striking against mobile and/or fixed objects/vehicles;
• Collision of plant, including those of other contractors in area;
• Collision with operatives, including other contractors; 4 4 16
HIGH i. Only competent and authorised personnel with licence for the category of plant they are operating are allowed to operate the machinery, reviewed by logistics before commencing on site;
ii. All plant and equipment shall be Third Party Certificated by a DM approved assessor;
iii. Heavy equipment shall be equipped with audible reversing alarm (not possible on bi-directional equipment);
iv. A flagman to be present to signal reversing vehicles, reversing of vehicles to be avoided where practicable;
v. All plant / vehicles to be controlled by banks man;
vi. Plant to be parked only in designated area, parking brake on, keys removed with working parts lowered;
vii. Protected access route(s) for pedestrians maintained where required;
viii. Effective Traffic Management System (TMS) to be s
Project Information:
Project Name: Date :
Project Location:
FIRE EXT. NO. CAPACITY/ TYPE (e.g. 7 Kg CO2) LOCATION 3rd Party Inspection valid SHIELDED FROM SUN VISUAL SEAL LOCK PIN INSP. TAG PRESSURE GUAGE DISCHARGE HOSE DISCHARGE NOZZLE REMARKS/ ACTION
Visual Seal : Check for cracking/denting in the case Pressure Gauge : Check for cracking/denting in the case
Lock Pin Check : Check that the lead seal on the wire clip which holds : Check that the gauge is green, not red
the pin on the handle in place is not broken. Discharge Hose : Check for cracking/splitting at the discharge nozzle
Inspection Tag : Check that the sticker indicating last checking
details of the extinguisher is in place. Discharge Nozzle : Check to see if it is cracked/broken
Inspected By: Signature:
Reviewed By HSE Manager / In charge : Signature:
Noted by: Project Leader/CM Signature:
20 use of suspended access cradles and platforms (temporary works) risk asses...Dwarika Bhushan Sharma
20 Use of Suspended Access cradles and Platforms (Temporary Works) Risk Assessment Templates
Cradle checks on arrival to site
PRIOR TO USE • Use of Access equipment • Failure due to use of un-certificated plant;
Pre-use checks of suspended access cradle or platform • Work at Height; • Collapse of cradle through damage or failure of equipment;
• Falling materials;
Cradle operation ; • Work at Height; • Fall from height;
• Material fall from height;
• Machine malfunction at height;
• Workers trapped at height;
NEVER allow people to be below a suspended load at any time!
ONE TO ONE RULE:
All personnel should be two meter away from the load for every meter the load is above the floor
10 Use of Mobile Concrete Pump Risk Assessment Templates
Concrete Pump checks on arrival to site
PRIOR TO SITE ACCESS
Access of mobile pump and delivery trucks to work areas
Siting and setting up of concrete pump
Pumping concrete
(Pump Operator)
Pumping operation supervision
19 use of mobile elevated work platforms risk assessment templatesDwarika Bhushan Sharma
19 Use of Mobile Elevated Work Platforms Risk Assessment Templates
MEWP checks on arrival to site
PRIOR TO SITE ACCESS • Use of Access plant • Unauthorized operation of the plant resulting in incident;
• Failure due to use of un-certificated plant;
MEWP operation
(Operator) • Operator competency;
• Plant / pedestrian interaction;
• Work at Height; • Incident due to use of defective plant or associated equipment;
• MEWP overturning;
• Plant reversing – risk of serious injury to pedestrians;
• Unauthorized use of MEWP by untrained personnel;
• Operators climbing onto hand rails;
• Collision with other plant and live traffic within site boundary;
• Workers struck by working MEWP, very high risk of fatality;
• Falling materials;
MEWP operation (supervision) • MEWP operations around workers;
• Workers in MEWP operating radius;
• Reversing vehicles; • Worker struck by vehicle;•
RISK SCORE CALCULATOR
Use the Risk Score Calculator to Determine the Level of Risk of each Hazard
What would be the
CONSEQUENCE
of an occurrence be? What is the LIKELIHOOD of an occurrence? Hierarchy of Controls
Frequent/Almost certain (5)
Continuous or will happen frequently Often (4)
6 to 12 times a year Likely (3)
1 to 5 times a year Possible (2)
Once every 5 years Rarely (1)
Less than once every 5 years Can the hazard be Eliminated or removed from the work place?
Catastrophic (5)
Multiple Fatalities High 25 High 20 High 15 Medium 10 Medium 5 Can the product or process be substituted for a less hazardous alternative?
Serious (4)
Class 1 single fatality High 20 High 16 High 12 Medium 8 Low 4 Can the hazard be engineered away with guards or barriers?
Moderate (3)
Class2 (AWI or LTI) or Class 1 Permanently disabling effects High 15 High 12 Medium 9 Medium 6 Low 3 Can Administration Controls be adopted
I.e. procedures, job rotation etc.
Minor (2)
Medical attention needed, no work restrictions. MTI Medium10 Medium 8 Medium 6 Low 4 Low 2 Can Personal Protective Equipment & Clothing be worn to safe guard against hazards?
Insignificant (1)
FAI Medium10 Medium 4 Low 3 Low 2 Low 1
Project Name: xxx
RA Ref No.: xxx
RA compilation Date: Review date:
Date:
Compiled by:
Reviewed by:
Approved by:
Overall Task Details
Excavation on site greater than 1.2 depth. Use of excavator
Note: Not under RTA Rail restrictions. Classed as Temporary Works Relevant Applicable MAS:
• 00246 – Excavations;
• 01413 – Underground services;
• 00940 – Plant Operators. Additional Training required:
Temporary Works Coordinator to be designated NOC’s Required for task:
Dubai Municipality
No Specific Task Step
(In sequence of works) Hazard Details Consequence/Risk Initial Risk Rating Control Measures Residual Risks Additional Control Measures RR
P S RR
1 Planned Excavation in areas where live services may be present including:
• Electrical;
• Water;
• Sewerage;
• Gas;
• Telecoms;
PRIOR TO WORKS • Presence of live underground services;
• Services not in area specified on drawings;
• Heavy plant or vehicles accessing work area;
• Presence of unmarked services;
• Risk of explosion due to gas line rupture;
• Risk of flooding of excavation and adjacent areas due to water main damage;
• Risk of electrocution or fire due to cable strike;
• Risk of hazardous waste entering excavation or water systems due to live sewerage damage;
• Risk of damage to low depth underground services from heavy vehicles;
• Risk of vehicles / Plant entering open excavation; 4 5 20
HIGH i. All existing utility service drawings reviewed for known service details and position;
ii. NOC and Utility provider and ATC Excavation permits to be completed, unique number added and recorded in log;
iii. Work Area, including access route for plant, to be CAT scanned to locate exact position of service by competent persons;
iv. Service clearly marked on ground, using posts, tags etc.;
v. Pla
Project Name: xxx
RA Ref No.: xxx
RA compilation Date: Review date:
Date:
Compiled by:
Reviewed by:
Approved by:
Overall Task Details
Lifting operations using Tower crane within site boundary Relevant Applicable MAS:
• 01412 – Lifting Operations;
• 00941 – Lifting equipment Additional Training required:
Riggers / Slingers NOC’s Required for task:
As applicable
RISK SCORE CALCULATOR
Use the Risk Score Calculator to Determine the Level of Risk of each Hazard
What would be the
CONSEQUENCE
of an occurrence be? What is the LIKELIHOOD of an occurrence? Hierarchy of Controls
Frequent/Almost certain (5)
Continuous or will happen frequently Often (4)
6 to 12 times a year Likely (3)
1 to 5 times a year Possible (2)
Once every 5 years Rarely (1)
Less than once every 5 years Can the hazard be Eliminated or removed from the work place?
Catastrophic (5)
Multiple Fatalities High 25 High 20 High 15 Medium 10 Medium 5 Can the product or process be substituted for a less hazardous alternative?
Serious (4)
Class 1 single fatality High 20 High 16 High 12 Medium 8 Low 4 Can the hazard be engineered away with guards or barriers?
Moderate (3)
Class2 (AWI or LTI) or Class 1 Permanently disabling effects High 15 High 12 Medium 9 Medium 6 Low 3 Can Administration Controls be adopted
I.e. procedures, job rotation etc.
Minor (2)
Medical attention needed, no work restrictions. MTI Medium10 Medium 8 Medium 6 Low 4 Low 2 Can Personal Protective Equipment & Clothing be worn to safe guard against hazards?
Insignificant (1)
FAI Medium10 Medium 4 Low 3 Low 2 Low 1
No Specific Task Step
(In sequence of works) Hazard Details Consequence/Risk Initial Risk Rating Control Measures Residual Risks Additional Control Measures RR
P S RR
1 Access of Tower crane sections to work areas
• Plant and workers in same working area as delivery truck; • Collision with plant or vehicles and live traffic;
• Workers struck by plant, very high risk of fatality;
• Uncontrolled crane reversing; 3 4 12 High i. Worker pedestrian routes to be designed and implemented with clear signage to provide segregation;
ii. Instruction to workers at induction on use of access routes around the project;
iii. Flagmen to be used to control crane movements;
iv. The Logistics plan shall clearly illustrate crane access and egress points; Workers not complying with flagmen Regular topic in TBT’s Low
2 Tower crane foundations • Excavations;
• Use of plant – excavators etc.;
• Use of concrete;
• Temporary Works; • See Risk Assessment 010 – Excavations;
• See Risk Assessment 014 – use of Mobile Concrete pump;
• Failure due to incorrect design; 4 5 20 High i. Crane foundations to be designed by approved persons, to clear design criteria;
ii. Foundations given adequate curing time before crane erection;
iii. Temporary Works Coordinator to control excavations and concrete pours; Low
3 Siting, setting up and testing of Tower crane • Works at Height;
• Working in proximity to existing struct
18 Laying blockwork with access scaffolding Risk Assessment Templates
Vehicles/Plant Equipment movements for block delivery
Hi-Abs, forklifts etc.
Access Scaffolding, Working platforms for high level block laying
Loading out blocks in work area and mixing mortar
Laying blockwork
Disposal of concrete – as per LEED requirements
Worker exposure to direct sun whist working on scaffolding
(as applicable)
Forklifts are extremely useful workplace vehicles, as long as they are used safely and appropriately by operators who are appropriately trained and competent to use them.
Forklifts can be dangerous: they account for 25% of injuries at work. Many workplace accidents involve people being hit or run over by forklift trucks (typically when the forklift is reversing) because the driver did not see them. Owing to their size and weight, injuries resulting from forklifts are generally very serious. Accidents involving them are often caused by poor supervision and a lack of training.
Always:
Wear appropriate personal protective clothing as provided by employer. Hard hat, protective footwear and high visibility clothing are recommended as a minimum when working around forklifts. Other equipment may be needed depending on the working environment
Report defects immediately to supervisor
Make sure work path is free of obstructions
Wear operator restraints, where fitted
Look all around before moving off
Look in the direction of travel
Avoid sudden stops and violent braking
Take care when driving on wet, icy , slippery or loose surfaces Slow down at corners, doorways, and at danger spots
Sound the horn several times when approaching blind corners, exits and entrances
Switch off and remove the key before leaving the forklift. Place the key in a safe location when driving task is completed
Apply the parking brake before leaving the forklift
Report any accidents or near misses to a supervisor
Park the forklift in a safe place, on level ground; never on a slope
Leave the forklift with the mast tilted forwards and the forks fully lowered, with the tips on the floor
Apply the parking brake, select neutral, switch off the engine and remove the key
Return keys or other activating devices to their place of safe-keeping
Report any malfunctions or defects immediately to a supervisor.
Assess the load before lifting. Check weight, size, load centre and security
Make sure that pallets are in good condition
Observe floor loading limits & Travel slowly when going down slopes
Find out the weight of the laden forklift
Check safe working load (SWL) of racking before placing loads onto it
Make sure load does not obstruct view. If it does, drive in reverse, looking in direction.
Make sure there is adequate clearance for the forklift and load, including overhead
Make sure the load is stable, Carry the load as close to ground as possible, Use controls smoothly & arms are fully inserted when travelling with a load
Position forks properly and as widely as possible
Make sure the fork Make sure the forklift is stopped before raising the load
Use suitable attachments for lifting unusual or wide loads
Ensure the forks face uphill when travelling up or down slopes with a load
Ensure the forks face downhill when travelling up or down slopes without a load
Adjust the tilt (where fitted) to suit the gradient and raise the forks to clear the ground
21 Confined Space Working Risk Assessment Templates
Planned confined space work in areas where live services may be present including:
• Water;
• Sewerage;
• Gas;
PRIOR TO ENTRY
Confined space working –
• Deep excavations;
• Tanks;
• Vessels;
• Manholes;
• NDRC pits;
• Bridge decks;
• Pipework;
• Sewerage;
• Lift shafts;
• Ducting;
• Etc.
Project Name: xxx
RA Ref No.: xxx
RA compilation Date: Review date:
Date:
Compiled by:
Reviewed by:
Approved by:
Overall Task Details
Laying blockwork with scaffold. Classed as Temporary Works Relevant Applicable MAS:
• 00939 - CoSHH
• 00236 – Housekeeping
• 00245 – Mobile Scaffolding Additional Training required:
Temporary Works Coordinator to be designated NOC’s Required for task:
RISK SCORE CALCULATOR
Use the Risk Score Calculator to Determine the Level of Risk of each Hazard
What would be the
CONSEQUENCE
of an occurrence be? What is the LIKELIHOOD of an occurrence? Hierarchy of Controls
Frequent/Almost certain (5)
Continuous or will happen frequently Often (4)
6 to 12 times a year Likely (3)
1 to 5 times a year Possible (2)
Once every 5 years Rarely (1)
Less than once every 5 years Can the hazard be Eliminated or removed from the work place?
Catastrophic (5)
Multiple Fatalities High 25 High 20 High 15 Medium 10 Medium 5 Can the product or process be substituted for a less hazardous alternative?
Serious (4)
Class 1 single fatality High 20 High 16 High 12 Medium 8 Low 4 Can the hazard be engineered away with guards or barriers?
Moderate (3)
Class2 (AWI or LTI) or Class 1 Permanently disabling effects High 15 High 12 Medium 9 Medium 6 Low 3 Can Administration Controls be adopted
I.e. procedures, job rotation etc.
Minor (2)
Medical attention needed, no work restrictions. MTI Medium10 Medium 8 Medium 6 Low 4 Low 2 Can Personal Protective Equipment & Clothing be worn to safe guard against hazards?
Insignificant (1)
FAI Medium10 Medium 4 Low 3 Low 2 Low 1
No Specific Task Step
(In sequence of works) Hazard Details Consequence/Risk Initial Risk Rating Control Measures Residual Risks Additional Control Measures RR
P S RR
1 Vehicles/Plant Equipment movements for block delivery
Hi-Abs, forklifts etc. • Use of plant;
• Plant / worker proximity; • Unauthorised use of untrained or unlicensed operators;
• Use of un-certificated plant and equipment;
• Striking against mobile and/or fixed objects/vehicles;
• Collision of plant, including those of other contractors in area;
• Collision with operatives, including other contractors; 4 4 16
HIGH i. Only competent and authorised personnel with licence for the category of plant they are operating are allowed to operate the machinery, reviewed by logistics before commencing on site;
ii. All plant and equipment shall be Third Party Certificated by a DM approved assessor;
iii. Heavy equipment shall be equipped with audible reversing alarm (not possible on bi-directional equipment);
iv. A flagman to be present to signal reversing vehicles, reversing of vehicles to be avoided where practicable;
v. All plant / vehicles to be controlled by banks man;
vi. Plant to be parked only in designated area, parking brake on, keys removed with working parts lowered;
vii. Protected access route(s) for pedestrians maintained where required;
viii. Effective Traffic Management System (TMS) to be s
Project Information:
Project Name: Date :
Project Location:
FIRE EXT. NO. CAPACITY/ TYPE (e.g. 7 Kg CO2) LOCATION 3rd Party Inspection valid SHIELDED FROM SUN VISUAL SEAL LOCK PIN INSP. TAG PRESSURE GUAGE DISCHARGE HOSE DISCHARGE NOZZLE REMARKS/ ACTION
Visual Seal : Check for cracking/denting in the case Pressure Gauge : Check for cracking/denting in the case
Lock Pin Check : Check that the lead seal on the wire clip which holds : Check that the gauge is green, not red
the pin on the handle in place is not broken. Discharge Hose : Check for cracking/splitting at the discharge nozzle
Inspection Tag : Check that the sticker indicating last checking
details of the extinguisher is in place. Discharge Nozzle : Check to see if it is cracked/broken
Inspected By: Signature:
Reviewed By HSE Manager / In charge : Signature:
Noted by: Project Leader/CM Signature:
20 use of suspended access cradles and platforms (temporary works) risk asses...Dwarika Bhushan Sharma
20 Use of Suspended Access cradles and Platforms (Temporary Works) Risk Assessment Templates
Cradle checks on arrival to site
PRIOR TO USE • Use of Access equipment • Failure due to use of un-certificated plant;
Pre-use checks of suspended access cradle or platform • Work at Height; • Collapse of cradle through damage or failure of equipment;
• Falling materials;
Cradle operation ; • Work at Height; • Fall from height;
• Material fall from height;
• Machine malfunction at height;
• Workers trapped at height;
NEVER allow people to be below a suspended load at any time!
ONE TO ONE RULE:
All personnel should be two meter away from the load for every meter the load is above the floor
10 Use of Mobile Concrete Pump Risk Assessment Templates
Concrete Pump checks on arrival to site
PRIOR TO SITE ACCESS
Access of mobile pump and delivery trucks to work areas
Siting and setting up of concrete pump
Pumping concrete
(Pump Operator)
Pumping operation supervision
19 use of mobile elevated work platforms risk assessment templatesDwarika Bhushan Sharma
19 Use of Mobile Elevated Work Platforms Risk Assessment Templates
MEWP checks on arrival to site
PRIOR TO SITE ACCESS • Use of Access plant • Unauthorized operation of the plant resulting in incident;
• Failure due to use of un-certificated plant;
MEWP operation
(Operator) • Operator competency;
• Plant / pedestrian interaction;
• Work at Height; • Incident due to use of defective plant or associated equipment;
• MEWP overturning;
• Plant reversing – risk of serious injury to pedestrians;
• Unauthorized use of MEWP by untrained personnel;
• Operators climbing onto hand rails;
• Collision with other plant and live traffic within site boundary;
• Workers struck by working MEWP, very high risk of fatality;
• Falling materials;
MEWP operation (supervision) • MEWP operations around workers;
• Workers in MEWP operating radius;
• Reversing vehicles; • Worker struck by vehicle;•
RISK SCORE CALCULATOR
Use the Risk Score Calculator to Determine the Level of Risk of each Hazard
What would be the
CONSEQUENCE
of an occurrence be? What is the LIKELIHOOD of an occurrence? Hierarchy of Controls
Frequent/Almost certain (5)
Continuous or will happen frequently Often (4)
6 to 12 times a year Likely (3)
1 to 5 times a year Possible (2)
Once every 5 years Rarely (1)
Less than once every 5 years Can the hazard be Eliminated or removed from the work place?
Catastrophic (5)
Multiple Fatalities High 25 High 20 High 15 Medium 10 Medium 5 Can the product or process be substituted for a less hazardous alternative?
Serious (4)
Class 1 single fatality High 20 High 16 High 12 Medium 8 Low 4 Can the hazard be engineered away with guards or barriers?
Moderate (3)
Class2 (AWI or LTI) or Class 1 Permanently disabling effects High 15 High 12 Medium 9 Medium 6 Low 3 Can Administration Controls be adopted
I.e. procedures, job rotation etc.
Minor (2)
Medical attention needed, no work restrictions. MTI Medium10 Medium 8 Medium 6 Low 4 Low 2 Can Personal Protective Equipment & Clothing be worn to safe guard against hazards?
Insignificant (1)
FAI Medium10 Medium 4 Low 3 Low 2 Low 1
Project Name: xxx
RA Ref No.: xxx
RA compilation Date: Review date:
Date:
Compiled by:
Reviewed by:
Approved by:
Overall Task Details
Excavation on site greater than 1.2 depth. Use of excavator
Note: Not under RTA Rail restrictions. Classed as Temporary Works Relevant Applicable MAS:
• 00246 – Excavations;
• 01413 – Underground services;
• 00940 – Plant Operators. Additional Training required:
Temporary Works Coordinator to be designated NOC’s Required for task:
Dubai Municipality
No Specific Task Step
(In sequence of works) Hazard Details Consequence/Risk Initial Risk Rating Control Measures Residual Risks Additional Control Measures RR
P S RR
1 Planned Excavation in areas where live services may be present including:
• Electrical;
• Water;
• Sewerage;
• Gas;
• Telecoms;
PRIOR TO WORKS • Presence of live underground services;
• Services not in area specified on drawings;
• Heavy plant or vehicles accessing work area;
• Presence of unmarked services;
• Risk of explosion due to gas line rupture;
• Risk of flooding of excavation and adjacent areas due to water main damage;
• Risk of electrocution or fire due to cable strike;
• Risk of hazardous waste entering excavation or water systems due to live sewerage damage;
• Risk of damage to low depth underground services from heavy vehicles;
• Risk of vehicles / Plant entering open excavation; 4 5 20
HIGH i. All existing utility service drawings reviewed for known service details and position;
ii. NOC and Utility provider and ATC Excavation permits to be completed, unique number added and recorded in log;
iii. Work Area, including access route for plant, to be CAT scanned to locate exact position of service by competent persons;
iv. Service clearly marked on ground, using posts, tags etc.;
v. Pla
Project Name: xxx
RA Ref No.: xxx
RA compilation Date: Review date:
Date:
Compiled by:
Reviewed by:
Approved by:
Overall Task Details
Lifting operations using Tower crane within site boundary Relevant Applicable MAS:
• 01412 – Lifting Operations;
• 00941 – Lifting equipment Additional Training required:
Riggers / Slingers NOC’s Required for task:
As applicable
RISK SCORE CALCULATOR
Use the Risk Score Calculator to Determine the Level of Risk of each Hazard
What would be the
CONSEQUENCE
of an occurrence be? What is the LIKELIHOOD of an occurrence? Hierarchy of Controls
Frequent/Almost certain (5)
Continuous or will happen frequently Often (4)
6 to 12 times a year Likely (3)
1 to 5 times a year Possible (2)
Once every 5 years Rarely (1)
Less than once every 5 years Can the hazard be Eliminated or removed from the work place?
Catastrophic (5)
Multiple Fatalities High 25 High 20 High 15 Medium 10 Medium 5 Can the product or process be substituted for a less hazardous alternative?
Serious (4)
Class 1 single fatality High 20 High 16 High 12 Medium 8 Low 4 Can the hazard be engineered away with guards or barriers?
Moderate (3)
Class2 (AWI or LTI) or Class 1 Permanently disabling effects High 15 High 12 Medium 9 Medium 6 Low 3 Can Administration Controls be adopted
I.e. procedures, job rotation etc.
Minor (2)
Medical attention needed, no work restrictions. MTI Medium10 Medium 8 Medium 6 Low 4 Low 2 Can Personal Protective Equipment & Clothing be worn to safe guard against hazards?
Insignificant (1)
FAI Medium10 Medium 4 Low 3 Low 2 Low 1
No Specific Task Step
(In sequence of works) Hazard Details Consequence/Risk Initial Risk Rating Control Measures Residual Risks Additional Control Measures RR
P S RR
1 Access of Tower crane sections to work areas
• Plant and workers in same working area as delivery truck; • Collision with plant or vehicles and live traffic;
• Workers struck by plant, very high risk of fatality;
• Uncontrolled crane reversing; 3 4 12 High i. Worker pedestrian routes to be designed and implemented with clear signage to provide segregation;
ii. Instruction to workers at induction on use of access routes around the project;
iii. Flagmen to be used to control crane movements;
iv. The Logistics plan shall clearly illustrate crane access and egress points; Workers not complying with flagmen Regular topic in TBT’s Low
2 Tower crane foundations • Excavations;
• Use of plant – excavators etc.;
• Use of concrete;
• Temporary Works; • See Risk Assessment 010 – Excavations;
• See Risk Assessment 014 – use of Mobile Concrete pump;
• Failure due to incorrect design; 4 5 20 High i. Crane foundations to be designed by approved persons, to clear design criteria;
ii. Foundations given adequate curing time before crane erection;
iii. Temporary Works Coordinator to control excavations and concrete pours; Low
3 Siting, setting up and testing of Tower crane • Works at Height;
• Working in proximity to existing struct
18 Laying blockwork with access scaffolding Risk Assessment Templates
Vehicles/Plant Equipment movements for block delivery
Hi-Abs, forklifts etc.
Access Scaffolding, Working platforms for high level block laying
Loading out blocks in work area and mixing mortar
Laying blockwork
Disposal of concrete – as per LEED requirements
Worker exposure to direct sun whist working on scaffolding
(as applicable)
Forklifts are extremely useful workplace vehicles, as long as they are used safely and appropriately by operators who are appropriately trained and competent to use them.
Forklifts can be dangerous: they account for 25% of injuries at work. Many workplace accidents involve people being hit or run over by forklift trucks (typically when the forklift is reversing) because the driver did not see them. Owing to their size and weight, injuries resulting from forklifts are generally very serious. Accidents involving them are often caused by poor supervision and a lack of training.
Always:
Wear appropriate personal protective clothing as provided by employer. Hard hat, protective footwear and high visibility clothing are recommended as a minimum when working around forklifts. Other equipment may be needed depending on the working environment
Report defects immediately to supervisor
Make sure work path is free of obstructions
Wear operator restraints, where fitted
Look all around before moving off
Look in the direction of travel
Avoid sudden stops and violent braking
Take care when driving on wet, icy , slippery or loose surfaces Slow down at corners, doorways, and at danger spots
Sound the horn several times when approaching blind corners, exits and entrances
Switch off and remove the key before leaving the forklift. Place the key in a safe location when driving task is completed
Apply the parking brake before leaving the forklift
Report any accidents or near misses to a supervisor
Park the forklift in a safe place, on level ground; never on a slope
Leave the forklift with the mast tilted forwards and the forks fully lowered, with the tips on the floor
Apply the parking brake, select neutral, switch off the engine and remove the key
Return keys or other activating devices to their place of safe-keeping
Report any malfunctions or defects immediately to a supervisor.
Assess the load before lifting. Check weight, size, load centre and security
Make sure that pallets are in good condition
Observe floor loading limits & Travel slowly when going down slopes
Find out the weight of the laden forklift
Check safe working load (SWL) of racking before placing loads onto it
Make sure load does not obstruct view. If it does, drive in reverse, looking in direction.
Make sure there is adequate clearance for the forklift and load, including overhead
Make sure the load is stable, Carry the load as close to ground as possible, Use controls smoothly & arms are fully inserted when travelling with a load
Position forks properly and as widely as possible
Make sure the fork Make sure the forklift is stopped before raising the load
Use suitable attachments for lifting unusual or wide loads
Ensure the forks face uphill when travelling up or down slopes with a load
Ensure the forks face downhill when travelling up or down slopes without a load
Adjust the tilt (where fitted) to suit the gradient and raise the forks to clear the ground
To Advise, Communicate & Implement my Corporate Legal Obligation under the International Labor Organizations Nationally Ratified Conventions & Recommendations while Exercising Due Diligence on behalf of my client in Guiding Management to Attain Zero Incidents through Proactive Behavior’s in Accordance with the Local OH&S Act, Regulation & Code under a professional & moral code of ethics.
Advise, Communicate & Implement my Corporate Legal Obligation under the International Labor Organizations Nationally Ratified Conventions & Recommendations while Exercising Due Diligence on behalf of my client in Guiding Management to Attain Zero Incidents through Proactive Behavior’s in Accordance with the Local OH&S Act, Regulation & Code under a professional & moral code of ethics.
Presentation I made for safety induction of people joining the "NUNCE" accommodation barge where I was HSE (Health,Safety & environment Officer) during the period 2009/2010.
Hazardous Waste Operations and Emergency Response requirements are governed by federal OSHA for emergency responders and contractors cleaning hazardous waste materials from spills and releases. Workers must be properly trained and educated on the health and safety hazards of the work tasks as well as the environment. OSHA has many requirements to ensure the workforce is protected from all types of chemical emergencies.
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsVictor Morales
K8sGPT is a tool that analyzes and diagnoses Kubernetes clusters. This presentation was used to share the requirements and dependencies to deploy K8sGPT in a local environment.
Hierarchical Digital Twin of a Naval Power SystemKerry Sado
A hierarchical digital twin of a Naval DC power system has been developed and experimentally verified. Similar to other state-of-the-art digital twins, this technology creates a digital replica of the physical system executed in real-time or faster, which can modify hardware controls. However, its advantage stems from distributing computational efforts by utilizing a hierarchical structure composed of lower-level digital twin blocks and a higher-level system digital twin. Each digital twin block is associated with a physical subsystem of the hardware and communicates with a singular system digital twin, which creates a system-level response. By extracting information from each level of the hierarchy, power system controls of the hardware were reconfigured autonomously. This hierarchical digital twin development offers several advantages over other digital twins, particularly in the field of naval power systems. The hierarchical structure allows for greater computational efficiency and scalability while the ability to autonomously reconfigure hardware controls offers increased flexibility and responsiveness. The hierarchical decomposition and models utilized were well aligned with the physical twin, as indicated by the maximum deviations between the developed digital twin hierarchy and the hardware.
Using recycled concrete aggregates (RCA) for pavements is crucial to achieving sustainability. Implementing RCA for new pavement can minimize carbon footprint, conserve natural resources, reduce harmful emissions, and lower life cycle costs. Compared to natural aggregate (NA), RCA pavement has fewer comprehensive studies and sustainability assessments.
Low power architecture of logic gates using adiabatic techniquesnooriasukmaningtyas
The growing significance of portable systems to limit power consumption in ultra-large-scale-integration chips of very high density, has recently led to rapid and inventive progresses in low-power design. The most effective technique is adiabatic logic circuit design in energy-efficient hardware. This paper presents two adiabatic approaches for the design of low power circuits, modified positive feedback adiabatic logic (modified PFAL) and the other is direct current diode based positive feedback adiabatic logic (DC-DB PFAL). Logic gates are the preliminary components in any digital circuit design. By improving the performance of basic gates, one can improvise the whole system performance. In this paper proposed circuit design of the low power architecture of OR/NOR, AND/NAND, and XOR/XNOR gates are presented using the said approaches and their results are analyzed for powerdissipation, delay, power-delay-product and rise time and compared with the other adiabatic techniques along with the conventional complementary metal oxide semiconductor (CMOS) designs reported in the literature. It has been found that the designs with DC-DB PFAL technique outperform with the percentage improvement of 65% for NOR gate and 7% for NAND gate and 34% for XNOR gate over the modified PFAL techniques at 10 MHz respectively.
We have compiled the most important slides from each speaker's presentation. This year’s compilation, available for free, captures the key insights and contributions shared during the DfMAy 2024 conference.
Understanding Inductive Bias in Machine LearningSUTEJAS
This presentation explores the concept of inductive bias in machine learning. It explains how algorithms come with built-in assumptions and preferences that guide the learning process. You'll learn about the different types of inductive bias and how they can impact the performance and generalizability of machine learning models.
The presentation also covers the positive and negative aspects of inductive bias, along with strategies for mitigating potential drawbacks. We'll explore examples of how bias manifests in algorithms like neural networks and decision trees.
By understanding inductive bias, you can gain valuable insights into how machine learning models work and make informed decisions when building and deploying them.
1. Project Name & Details
Project Name & Details
RISK ASSESSMENT FOR GAS WELDING
RISK ASSESSMENT FOR GAS WELDING
REF:
REF:
REV: 00
REV: 00
DATE:
DATE:
S.N
S.N
.
.
A
AC
CT
TI
IV
VI
IT
TY
Y H
HA
AZ
ZA
AR
RD
D
CAUSES OF
CAUSES OF
HAZARD
HAZARD
RISK
RISK
EVALUATION
EVALUATION
RISK
RISK
LEVEL
LEVEL IM
IM LEMENTED
LEMENTED CONTROL
CONTROL
MEASURES
MEASURES
RESIDUAL RISK
RESIDUAL RISK
ACCE
ACCE T
T Y/N?
Y/N?
S
S H
H/
/M
M/
/L
L S
S H
H/
/M
M/
/L
L
1
1
ermitting
ermitting work
work
and preparation
and preparation
Work condition not
Work condition not
safe
safe
Procedures and tasks
Procedures and tasks
not clear or respected
not clear or respected
Lack of supervisory
Lack of supervisory
Miscommunication
Miscommunication
Not correct PPE worn
Not correct PPE worn
Equipment not
Equipment not
inspected and
inspected and
certified
certified
Material
Material
damage
damage
Personnel
Personnel
injury
injury
2
2 4
4 4
4
HSE team to assess the conditions
HSE team to assess the conditions
of work in the assigned area prior
of work in the assigned area prior
and during the work
and during the work
Competency of personnel and
Competency of personnel and
supervision for the different
supervision for the different
activities
activities
Define hierarchy and reporting
Define hierarchy and reporting
flowcharts
flowcharts
Check inspection certificates of
Check inspection certificates of
equipment for the job
equipment for the job
CONTRACTOR PTW system should
CONTRACTOR PTW system should
be implemented
be implemented
Attend CONTRACTOR safety
Attend CONTRACTOR safety
trainings
trainings
Equipment checklist should be
Equipment checklist should be
made for all new equipment coming
made for all new equipment coming
to site
to site
Weekly equipment checklist should
Weekly equipment checklist should
be made and kept at engine
be made and kept at engine
Toolbox talks
Toolbox talks
Define proper PPE to be used for the
Define proper PPE to be used for the
work
work
1
1 1
1 1
1 Y
Y
1
1 Unloading
Unloading
Equipment
Equipment
(Mechanical
(Mechanical
Dropped object while
Dropped object while
unloading equipments /
unloading equipments /
swinging or tip over of
swinging or tip over of
Personnel
Personnel
injuries/
injuries/
fatalities
fatalities
2
2 4
4 4
4
lifting/ unloading of material under
lifting/ unloading of material under
PTW / JSA/ TBT/WMS
PTW / JSA/ TBT/WMS
1
1 1
1 1
1 Y
Y
Page1 of 8
Page1 of 8
2. Project Name & Details
Project Name & Details
RISK ASSESSMENT FOR GAS WELDING
RISK ASSESSMENT FOR GAS WELDING
REF:
REF:
REV: 00
REV: 00
DATE:
DATE:
and manual)
and manual)
load /
load /
collision between load &
collision between load &
facilities
facilities
Mechanical failure/ fire
Mechanical failure/ fire
Lifting gears failure
Lifting gears failure
Operating in a windy
Operating in a windy
weather
weather
Spills
Spills
Uneven
Uneven
Floor
Floor
Musculoskeletal
Musculoskeletal
disorder (MSDS) from
disorder (MSDS) from
manual heavy lift
manual heavy lift
Hands injuries from the
Hands injuries from the
sharp edges
sharp edges
Pinch Point / dropped
Pinch Point / dropped
loads
loads
Work in classified area
Work in classified area
Material
Material
damage
damage
Environmental
Environmental
impact
impact
Standard PPE Must Be worn
Standard PPE Must Be worn
Certified forklift / 70Tcrane
Certified forklift / 70Tcrane
Weekly checklist for the lifting
Weekly checklist for the lifting
equipment
equipment
Certified lifting accessory &
Certified lifting accessory &
gears Coded color ongoing
gears Coded color ongoing
Visual Inspection for the lifti
Visual Inspection for the lifting gears
ng gears
in prior to start any lift
in prior to start any lifting task
ing task
Close supervision / QHSE Supervisor
Close supervision / QHSE Supervisor
assigned at site
assigned at site
Never stand under suspended loads
Never stand under suspended loads
Respect the radius swing
Respect the radius swing
Competent & Certified operator
Competent & Certified operator
No blind lifting
No blind lifting
Lifting Area barricaded
Lifting Area barricaded
Certified containers pad eyes
Certified containers pad eyes
restricted access area (using warning
restricted access area (using warning
tape & safety signs)
tape & safety signs)
Banks man to guide the lifting
Banks man to guide the lifting
operation
operation
prohibit the lifting @
prohibit the lifting @ a wind speed
a wind speed
more than of 50 km/h
more than of 50 km/h
check the ground state
check the ground state
Apply the right manual handling
Apply the right manual handling
techniques / use a mechanical help if
techniques / use a mechanical help if
required
required
Use the SMART GRIP Technique
Use the SMART GRIP Technique
shadowed Shelters to be provided
shadowed Shelters to be provided
Continuous gas monitoring
Continuous gas monitoring
1
1 Dismantling of
Dismantling of
Pinch point / hand
Pinch point / hand People
People 2
2 4
4 4
4
PTW/JSA/TBT
PTW/JSA/TBT 1
1 1
1 1
1 Y
Y
Page2 of 8
Page2 of 8
3. Project Name & Details
Project Name & Details
RISK ASSESSMENT FOR GAS WELDING
RISK ASSESSMENT FOR GAS WELDING
REF:
REF:
REV: 00
REV: 00
DATE:
DATE:
the existing
the existing
corroded pipe
corroded pipe
injuries
injuries
Falling from height
Falling from height
MSDs(musculoskeleta
MSDs(musculoskeleta
l disorder/wrong
l disorder/wrong
posture)
posture)
Dropped object
Dropped object
Potential Sparks
Potential Sparks
ignition
ignition
Work in classified
Work in classified
area
area
assets
assets
Proper PPE: gloves (EN 388)
Proper PPE: gloves (EN 388)
Take extra attention when carrying
Take extra attention when carrying
out the dismantling task
out the dismantling task
Only green Tagged scaffold to be
Only green Tagged scaffold to be
used
used
Wear personnel fall arrest system if
Wear personnel fall arrest system if
required
required
Apply the right kinetic postures
Apply the right kinetic postures
Clear and isolate the lower area to
Clear and isolate the lower area to
prevent injuries from falling object
prevent injuries from falling object
Use only bronze tools
Use only bronze tools
1
1 H
Ho
ot
t w
wo
or
rk
k
(cutting,
(cutting,
grinding and
grinding and
welding)
welding)
Toxic fumes
Toxic fumes
inhalation
inhalation
Eyes irritation
Eyes irritation
Electrocution
Electrocution
/electrical shock
/electrical shock
Fire eruption
Fire eruption
Burns
Burns
Explosion
Explosion
Flying debris broken
Flying debris broken
disc
disc
Naked wires
Naked wires
Noise
Noise
Backfiring
Backfiring
Explosion due to
Explosion due to
overpressure of the
overpressure of the
compressed gas
compressed gas
cylinders
cylinders
Work in classified
Work in classified
People
People
Asset
Asset
2
2 4
4 4
4
Hot PTW/JSA/TBT
Hot PTW/JSA/TBT
Pressurized welding habitat
Pressurized welding habitat
Fire blanket
Fire blanket
Atex equipment
Atex equipment
Clear the nearby area from the
Clear the nearby area from the
combustibles
combustibles
Proper PPE (welding glovesEN
Proper PPE (welding glovesEN
407)/welding mask/face
407)/welding mask/face
shield/welding apron/ear plugs
shield/welding apron/ear plugs
RPM of the disk should be larger
RPM of the disk should be larger
than the angle grinder RPM
than the angle grinder RPM
Flashback arrestor
Flashback arrestor
Compressed gas cylinders should
Compressed gas cylinders should
be kept in upright position and
be kept in upright position and
secured , capped if not in use
secured , capped if not in use
Pressure gauge should be calibrated
Pressure gauge should be calibrated
Safety signs in place
Safety signs in place
1
1 1
1 1
1 Y
Y
Page3 of 8
Page3 of 8
4. Project Name & Details
Project Name & Details
RISK ASSESSMENT FOR GAS WELDING
RISK ASSESSMENT FOR GAS WELDING
REF:
REF:
REV: 00
REV: 00
DATE:
DATE:
area
area
Fire watch man in place
Fire watch man in place
Continuous gas monitoring
Continuous gas monitoring
1
1 V
Ve
eh
hiic
clle
es
s a
an
nd
d
Machinery
Machinery
Moving
Moving
Road Crossings
Road Crossings
vehicle crash
vehicle crash
Struck personnel
Struck personnel
Material
Material
damage
damage
Personnel
Personnel
injury
injury
2
2 4
4 4
4
Traffic if necessary will be
Traffic if necessary will be
controlled.
controlled.
Site drawings are available all the
Site drawings are available all the
time and used when needed
time and used when needed
Roads to be market and
Roads to be market and supervisors
supervisors
to be informed
to be informed
All crossing with main road should
All crossing with main road should
be secured with hard barriers if not
be secured with hard barriers if not
used or properly identified with
used or properly identified with
adequate road signs when in use.
adequate road signs when in use.
Permanent presence of the
Permanent presence of the
banksman
banksman
Speed limit 10km/h in the ROW
Speed limit 10km/h in the ROW
Warning signs
Warning signs
Road signs
Road signs
Correct hand signals
Correct hand signals
1
1 1
1 1
1 Y
Y
1
1 C
Clle
ea
an
niin
ng
g &
&
Housekeeping
Housekeeping
Musculoskeletal from
Musculoskeletal from
repetitive motion including
repetitive motion including
bending, stretching,
bending, stretching,
reaching etc.
reaching etc.
Personnel
Personnel
injury
injury
2
2 4
4 4
4
Training for good work practices to
Training for good work practices to
be held on site
be held on site
TBT in place before job,
TBT in place before job,
housekeeping issues to be
housekeeping issues to be
mentioned in all TBT
mentioned in all TBT
Personnel to perform cleaning and
Personnel to perform cleaning and
housekeeping without abuse to
housekeeping without abuse to
their bodies
their bodies
Good lifting practice to be applied
Good lifting practice to be applied
1
1 1
1 1
1 Y
Y
Page4 of 8
Page4 of 8
5. Project Name & Details
Project Name & Details
RISK ASSESSMENT FOR GAS WELDING
RISK ASSESSMENT FOR GAS WELDING
REF:
REF:
REV: 00
REV: 00
DATE:
DATE:
1
1 C
Clle
ea
an
niin
ng
g &
&
Housekeeping
Housekeeping
Pollution, Waste
Pollution, Waste
Environmental
Environmental
damage
damage
2
2 4
4 4
4
No waste is tolerated during the job
No waste is tolerated during the job
execution.
execution.
Personnel to end the day by
Personnel to end the day by
cleaning, inspecting equipment and
cleaning, inspecting equipment and
goodhousekeeping.
goodhousekeeping.
All waste has to be collected and
All waste has to be collected and
removed to a designated area.
removed to a designated area.
Any spill is to be contained in time, a
Any spill is to be contained in time, a
report to be issued to HSE
report to be issued to HSE
Manager.
Manager.
All ground disturbing has to be
All ground disturbing has to be
remained to its normal situation
remained to its normal situation
after work.
after work.
Any pollution or ground disturbing to
Any pollution or ground disturbing to
be reported directly to HSSE site
be reported directly to HSSE site
Manager and CONTRACTOR
Manager and CONTRACTOR
Waste disposal unit, containers in
Waste disposal unit, containers in
place
place
Plastic bags to collect waste
Plastic bags to collect waste
Waste separation to be applied
Waste separation to be applied
1
1 1
1 1
1 Y
Y
1
1 C
Clle
ea
an
niin
ng
g &
&
Housekeeping
Housekeeping Biological hazard
Biological hazard
Scorpion
Scorpion
stings / vipers
stings / vipers
bites
bites
2
2 4
4 4
4
Awareness regarding
Awareness regarding
scorpion/vipers risks.
scorpion/vipers risks.
1
1 1
1 1
1 Y
Y
Page5 of 8
Page5 of 8
6. Project Name & Details
Project Name & Details
RISK ASSESSMENT FOR GAS WELDING
RISK ASSESSMENT FOR GAS WELDING
REF:
REF:
REV: 00
REV: 00
DATE:
DATE:
Area inspection before operations to
Area inspection before operations to
ensure no insects.
ensure no insects.
Equipment appropriately stored after
Equipment appropriately stored after
the end of operations (not left on
the end of operations (not left on
the ground along the night).
the ground along the night).
Sand bags “under check” before
Sand bags “under check” before
removing.
removing.
Rests away insects shelters (stones,
Rests away insects shelters (stones,
bushes…)
bushes…)
PPE.
PPE.
TBT.
TBT.
ersons
ersons in da
in danger
nger
Workers undertaking the work
Workers undertaking the work
Persons passing the site location/ truck routes, e.g. members of the public and persons in the V
Persons passing the site location/ truck routes, e.g. members of the public and persons in the Vehicles.
ehicles.
ersonal
ersonal protective
protective equipment
equipment
Safety Helmet, Gum Boot, Proper Gloves &
Safety Helmet, Gum Boot, Proper Gloves & Safety Goggles
Safety Goggles
Information, instruction and training
Information, instruction and training
All personnel in the team are to be made aware of the sa
All personnel in the team are to be made aware of the safe systems of work.
fe systems of work.
Ensure that good housekeeping standard is maintained t
Ensure that good housekeeping standard is maintained throughout.
hroughout.
Training and experience for personnel to
Training and experience for personnel to use electrical equipments and vibratory equipments.
use electrical equipments and vibratory equipments.
Educate the personnel to handle chemicals such
Educate the personnel to handle chemicals such as concrete…
as concrete…
Page6 of 8
Page6 of 8
7. Project Name & Details
Project Name & Details
RISK ASSESSMENT FOR GAS WELDING
RISK ASSESSMENT FOR GAS WELDING
REF:
REF:
REV: 00
REV: 00
DATE:
DATE:
Emergency procedures
Emergency procedures
Site emergency procedures should make provision for t
Site emergency procedures should make provision for the rescue of individuals from
he rescue of individuals from heights.
heights.
First-aid facilities should be available to cope with any
First-aid facilities should be available to cope with any significant injuries that may arise from the work.
significant injuries that may arise from the work.
Monitoring and review
Monitoring and review
Work should be monitored by Foreman and charge hand who are trained to ensure that any additional
Work should be monitored by Foreman and charge hand who are trained to ensure that any additional
precautions or equipment required are provided.
precautions or equipment required are provided.
RISK ASSESSMENT COMMITTEE
RISK ASSESSMENT COMMITTEE:
: Project
Project Manager/
Manager/ Project
Project Engineer
Engineer
Safety Manager/ Safety Officer
Safety Manager/ Safety Officer
Reviewed by:
Reviewed by: (Safety Officer)
(Safety Officer) Approved by:
Approved by: (Project Manager)
(Project Manager)
RISK MATRIX
RISK MATRIX
Risk Rating (RR) – Severity x Likelihood
Risk Rating (RR) – Severity x Likelihood
LIKELIHOOD
LIKELIHOOD
( ROBABILITY)
( ROBABILITY)
(
( )
)
SEVERITY
SEVERITY
(IM ACT)
(IM ACT)
(S)
(S)
Rare
Rare
Remote possibility
Remote possibility
(once every 3
(once every 3
years or more)
years or more)
1
1
Unlikely
Unlikely
Could happen but
Could happen but
rare (typically once
rare (typically once
in a year)
in a year)
2
2
ossible
ossible
Could happen
Could happen
occasionally (on
occasionally (on
average quarterly)
average quarterly)
3
3
Likely
Likely
Could happen often
Could happen often
(on average once a
(on average once a
month or more)
month or more)
4
4
Almost certain
Almost certain
Could happen
Could happen
frequently (once a
frequently (once a
week or more)
week or more)
5
5
Page7 of 8
Page7 of 8
8. Project Name & Details
Project Name & Details
RISK ASSESSMENT FOR GAS WELDING
RISK ASSESSMENT FOR GAS WELDING
REF:
REF:
REV: 00
REV: 00
DATE:
DATE:
I
In
ns
siig
gn
niif
fiic
ca
an
nt
t 1
1
Low
Low
1
1
Low
Low
2
2
Low
Low
3
3
Low
Low
4
4
Medium
Medium
5
5
M
Miin
no
or
r 2
2
Low
Low
2
2
Low
Low
4
4
Medium
Medium
6
6
Medium
Medium
8
8
Medium
Medium
10
10
M
Mo
od
de
er
ra
at
te
e 3
3
Low
Low
3
3
Medium
Medium
6
6
Medium
Medium
9
9
Medium
Medium
12
12
High
High
15
15
S
Siig
gn
niif
fiic
ca
an
nt
t 4
4
Low
Low
4
4
Medium
Medium
8
8
Medium
Medium
12
12
High
High
16
16
High
High
20
20
M
Ma
ajjo
or
r 5
5 Medium
Medium
5
5
Medium
Medium
10
10
High
High
15
15
High
High
20
20
High
High
25
25
RISK
RISK BASED
BASED CONTROL
CONTROL LAN
LAN
R
RI
IS
SK
K L
LE
EV
VE
EL
L A
AC
CT
TI
IO
ON
N A
AN
ND
D T
TI
IM
ME
ES
SC
CA
AL
LE
E
1-4
1-4
Low
Low
Quick, easy controls should be implemented immediately and further action planned for when resources permit.
Quick, easy controls should be implemented immediately and further action planned for when resources permit.
Monitoring required ensuring controls are maintained.
Monitoring required ensuring controls are maintained. Manage through routine procedures. Go for economic
Manage through routine procedures. Go for economic
improvements where possible. Incident report must
improvements where possible. Incident report must be completed.
be completed.
5-12
5-12
Medium
Medium
Aim to reduce risks but costs of prevention may be limited. Underta
Aim to reduce risks but costs of prevention may be limited. Undertake a risk assessment of the situation / task and
ke a risk assessment of the situation / task and
implement the appropriate actions. Actions should have a timescale and should be monitored. Where the risk
implement the appropriate actions. Actions should have a timescale and should be monitored. Where the risk
involves work in progress undertake a risk assessment as soon as possible to ensure the safety of the situation or
involves work in progress undertake a risk assessment as soon as possible to ensure the safety of the situation or
task.
task. Work should not start until the risk is
Work should not start until the risk is reduced to an acceptable level.
reduced to an acceptable level. Considerable resources may have to be
Considerable resources may have to be
allocated. Contact your Manager and Risk Manager by telephone about the actions that should be taken to reduce
allocated. Contact your Manager and Risk Manager by telephone about the actions that should be taken to reduce
the risk/s. incident report must be completed. Incident must be added to service risk
the risk/s. incident report must be completed. Incident must be added to service risk register.
register.
15-25
15-25
High
High
Do not commence the activity until
Do not commence the activity until a risk assessment has been completed to ensure the safety of the situation or
a risk assessment has been completed to ensure the safety of the situation or
task. If it is
task. If it is not possible to reduce or eliminate the risk even with
not possible to reduce or eliminate the risk even with unlimited resources, work must remain prohibited.
unlimited resources, work must remain prohibited.
Inform your relevant Director, your Manager and the Risk Manager immediately by telephone. Incident report must be
Inform your relevant Director, your Manager and the Risk Manager immediately by telephone. Incident report must be
completed. Incident must be added to service risk register.
completed. Incident must be added to service risk register.
Page8 of 8
Page8 of 8