This risk assessment document evaluates the hazards associated with confined space work. It identifies risks such as exposure to live underground utilities, toxic gases, flooding, and restricted evacuation. Initial risks are rated as high. Control measures are outlined to reduce risks, such as obtaining permits, gas monitoring, ventilation, restricted hot works, lifelines, and rescue drills. Residual risks are rated as low when all controls are followed. Additional measures like supervisor monitoring and calibrated gas detectors are recommended to ensure safety protocols are strictly adhered to for confined space work.
20 use of suspended access cradles and platforms (temporary works) risk asses...Dwarika Bhushan Sharma
20 Use of Suspended Access cradles and Platforms (Temporary Works) Risk Assessment Templates
Cradle checks on arrival to site
PRIOR TO USE • Use of Access equipment • Failure due to use of un-certificated plant;
Pre-use checks of suspended access cradle or platform • Work at Height; • Collapse of cradle through damage or failure of equipment;
• Falling materials;
Cradle operation ; • Work at Height; • Fall from height;
• Material fall from height;
• Machine malfunction at height;
• Workers trapped at height;
RISK SCORE CALCULATOR
Use the Risk Score Calculator to Determine the Level of Risk of each Hazard
What would be the
CONSEQUENCE
of an occurrence be? What is the LIKELIHOOD of an occurrence? Hierarchy of Controls
Frequent/Almost certain (5)
Continuous or will happen frequently Often (4)
6 to 12 times a year Likely (3)
1 to 5 times a year Possible (2)
Once every 5 years Rarely (1)
Less than once every 5 years Can the hazard be Eliminated or removed from the work place?
Catastrophic (5)
Multiple Fatalities High 25 High 20 High 15 Medium 10 Medium 5 Can the product or process be substituted for a less hazardous alternative?
Serious (4)
Class 1 single fatality High 20 High 16 High 12 Medium 8 Low 4 Can the hazard be engineered away with guards or barriers?
Moderate (3)
Class2 (AWI or LTI) or Class 1 Permanently disabling effects High 15 High 12 Medium 9 Medium 6 Low 3 Can Administration Controls be adopted
I.e. procedures, job rotation etc.
Minor (2)
Medical attention needed, no work restrictions. MTI Medium10 Medium 8 Medium 6 Low 4 Low 2 Can Personal Protective Equipment & Clothing be worn to safe guard against hazards?
Insignificant (1)
FAI Medium10 Medium 4 Low 3 Low 2 Low 1
Project Name: xxx
RA Ref No.: xxx
RA compilation Date: Review date:
Date:
Compiled by:
Reviewed by:
Approved by:
Overall Task Details
Trial Trenches on site to locate/expose underground services. Use of excavator
Note: Wherever practicable trial trenches shall be hand dug to expose cables
Classed as Temporary Works Relevant Applicable MAS:
• 00246 – Excavations;
• 01413 – Underground services;
• 00940 – Plant Operators. Additional Training required:
Temporary Works Coordinator to be designated NOC’s Required for task:
Dubai Municipality
No Specific Task Step
(In sequence of works) Hazard Details Consequence/Risk Initial Risk Rating Control Measures Residual Risks Additional Control Measures RR
P S RR
1 Planned shallow Excavation (Trial Trench) in areas where live services may be present including:
• Electrical;
• Water;
• Sewerage;
• Gas;
• Telecoms;
PRIOR TO WORKS • Presence of live underground services;
• Services not in area specified on drawings;
• Heavy plant or vehicles accessing work area;
• Presence of unmarked services;
• Risk of explosion due to gas line rupture;
• Risk of flooding of trenches and adjacent areas due to water main damage;
• Risk of electrocution or fire due to cable strike;
• Risk of hazardous waste entering trenches or water systems due to live sewerage damage;
• Risk of damage to low depth underground services from heavy vehicles;
• Risk of vehicles / Plant entering open trenches; 4 3 12
HIGH i. All existing utility service drawings reviewed for known service details and position;
ii. NOC and Utility provider and ATC Excavation permits to be completed, unique number added and recorded in log;
iii. Work Area, including access route for plant, to be CAT scanned to locate exact position of service by competent per
10 Use of Mobile Concrete Pump Risk Assessment Templates
Concrete Pump checks on arrival to site
PRIOR TO SITE ACCESS
Access of mobile pump and delivery trucks to work areas
Siting and setting up of concrete pump
Pumping concrete
(Pump Operator)
Pumping operation supervision
18 Laying blockwork with access scaffolding Risk Assessment Templates
Vehicles/Plant Equipment movements for block delivery
Hi-Abs, forklifts etc.
Access Scaffolding, Working platforms for high level block laying
Loading out blocks in work area and mixing mortar
Laying blockwork
Disposal of concrete – as per LEED requirements
Worker exposure to direct sun whist working on scaffolding
(as applicable)
11 Piling Operations with Rebar Cage installation Risk Assessment Templates
Piling Rig checks on arrival to site
PRIOR TO USE
Access of rig and delivery vehicles to work areas
Siting and setting up of piling rig
Piling operation
(Mobile rig Operator)
Rebar cage fabrication
Pile case and rebar cage lifting operations
Project Name: xxx
RA Ref No.: xxx
RA compilation Date: Review date:
Date:
Compiled by:
Reviewed by:
Approved by:
Overall Task Details
Use of mechanical breakers – excavator – for demolition of concrete structure Relevant Applicable MAS:
• 00940 – Plant Operators; Additional Training required:
NOC’s Required for task:
RISK SCORE CALCULATOR
Use the Risk Score Calculator to Determine the Level of Risk of each Hazard
What would be the
CONSEQUENCE
of an occurrence be? What is the LIKELIHOOD of an occurrence? Hierarchy of Controls
Frequent/Almost certain (5)
Continuous or will happen frequently Often (4)
6 to 12 times a year Likely (3)
1 to 5 times a year Possible (2)
Once every 5 years Rarely (1)
Less than once every 5 years Can the hazard be Eliminated or removed from the work place?
Catastrophic (5)
Multiple Fatalities High 25 High 20 High 15 Medium 10 Medium 5 Can the product or process be substituted for a less hazardous alternative?
Serious (4)
Class 1 single fatality High 20 High 16 High 12 Medium 8 Low 4 Can the hazard be engineered away with guards or barriers?
Moderate (3)
Class2 (AWI or LTI) or Class 1 Permanently disabling effects High 15 High 12 Medium 9 Medium 6 Low 3 Can Administration Controls be adopted
I.e. procedures, job rotation etc.
Minor (2)
Medical attention needed, no work restrictions. MTI Medium10 Medium 8 Medium 6 Low 4 Low 2 Can Personal Protective Equipment & Clothing be worn to safe guard against hazards?
Insignificant (1)
FAI Medium10 Medium 4 Low 3 Low 2 Low 1
No Specific Task Step
(In sequence of works) Hazard Details Consequence/Risk Initial Risk Rating Control Measures Residual Risks Additional Control Measures RR
L C RR
1 Plant checks on arrival to site
PRIOR TO SITE ACCESS • Use of heavy plant for demolition; • Unauthorized operation of the plant resulting in incident;
• Failure due to use of un-certificated plant;
3 4 12
HIGH i. All plant to be Third Party Certificated by a DM approved inspector, documentation available on arrival to site;
ii. Operators to have in-date Third Party certificate by approved body, available for review on arrival to site;
iii. Visual inspection of plant undertaken by competent person; Documentation unavailable for review Plant quarantined until evidence provided Low
2 Demolition of concrete structure • Excavator breaker operation
• (Operator)Plant / pedestrian interaction;
• Operator visibility; • Incident due to use of defective plant or associated equipment;
• Plant reversing – risk of serious injury to pedestrians;
• Unauthorized use of plant by untrained personnel;
• Collision with plant and live traffic within site boundary;
• Workers struck by working plant, very high risk of fatality;
• Noise;
• Exposed rebar – risk of injury;
• Possible contamination of asbestos in structure;
• Proximity to public areas;
4 4 16 HIGH i. Demolition Method statement to be submitted and adhered to. Demolition to be undertaken in a sequential, controlled
7 Falsework (Temporary Works) Risk Assessment Templates
Access to work areas by personnel and plant.
Material delivery to work area;
Use of powered access equipment for assembly of false-work (if required)
Falsework installation
(Classified as Temporary Structures)
Dismantling of false-work
Maintenance of Falsework
Worker exposure to direct sun whist working on falsework
(as applicable)
20 use of suspended access cradles and platforms (temporary works) risk asses...Dwarika Bhushan Sharma
20 Use of Suspended Access cradles and Platforms (Temporary Works) Risk Assessment Templates
Cradle checks on arrival to site
PRIOR TO USE • Use of Access equipment • Failure due to use of un-certificated plant;
Pre-use checks of suspended access cradle or platform • Work at Height; • Collapse of cradle through damage or failure of equipment;
• Falling materials;
Cradle operation ; • Work at Height; • Fall from height;
• Material fall from height;
• Machine malfunction at height;
• Workers trapped at height;
RISK SCORE CALCULATOR
Use the Risk Score Calculator to Determine the Level of Risk of each Hazard
What would be the
CONSEQUENCE
of an occurrence be? What is the LIKELIHOOD of an occurrence? Hierarchy of Controls
Frequent/Almost certain (5)
Continuous or will happen frequently Often (4)
6 to 12 times a year Likely (3)
1 to 5 times a year Possible (2)
Once every 5 years Rarely (1)
Less than once every 5 years Can the hazard be Eliminated or removed from the work place?
Catastrophic (5)
Multiple Fatalities High 25 High 20 High 15 Medium 10 Medium 5 Can the product or process be substituted for a less hazardous alternative?
Serious (4)
Class 1 single fatality High 20 High 16 High 12 Medium 8 Low 4 Can the hazard be engineered away with guards or barriers?
Moderate (3)
Class2 (AWI or LTI) or Class 1 Permanently disabling effects High 15 High 12 Medium 9 Medium 6 Low 3 Can Administration Controls be adopted
I.e. procedures, job rotation etc.
Minor (2)
Medical attention needed, no work restrictions. MTI Medium10 Medium 8 Medium 6 Low 4 Low 2 Can Personal Protective Equipment & Clothing be worn to safe guard against hazards?
Insignificant (1)
FAI Medium10 Medium 4 Low 3 Low 2 Low 1
Project Name: xxx
RA Ref No.: xxx
RA compilation Date: Review date:
Date:
Compiled by:
Reviewed by:
Approved by:
Overall Task Details
Trial Trenches on site to locate/expose underground services. Use of excavator
Note: Wherever practicable trial trenches shall be hand dug to expose cables
Classed as Temporary Works Relevant Applicable MAS:
• 00246 – Excavations;
• 01413 – Underground services;
• 00940 – Plant Operators. Additional Training required:
Temporary Works Coordinator to be designated NOC’s Required for task:
Dubai Municipality
No Specific Task Step
(In sequence of works) Hazard Details Consequence/Risk Initial Risk Rating Control Measures Residual Risks Additional Control Measures RR
P S RR
1 Planned shallow Excavation (Trial Trench) in areas where live services may be present including:
• Electrical;
• Water;
• Sewerage;
• Gas;
• Telecoms;
PRIOR TO WORKS • Presence of live underground services;
• Services not in area specified on drawings;
• Heavy plant or vehicles accessing work area;
• Presence of unmarked services;
• Risk of explosion due to gas line rupture;
• Risk of flooding of trenches and adjacent areas due to water main damage;
• Risk of electrocution or fire due to cable strike;
• Risk of hazardous waste entering trenches or water systems due to live sewerage damage;
• Risk of damage to low depth underground services from heavy vehicles;
• Risk of vehicles / Plant entering open trenches; 4 3 12
HIGH i. All existing utility service drawings reviewed for known service details and position;
ii. NOC and Utility provider and ATC Excavation permits to be completed, unique number added and recorded in log;
iii. Work Area, including access route for plant, to be CAT scanned to locate exact position of service by competent per
10 Use of Mobile Concrete Pump Risk Assessment Templates
Concrete Pump checks on arrival to site
PRIOR TO SITE ACCESS
Access of mobile pump and delivery trucks to work areas
Siting and setting up of concrete pump
Pumping concrete
(Pump Operator)
Pumping operation supervision
18 Laying blockwork with access scaffolding Risk Assessment Templates
Vehicles/Plant Equipment movements for block delivery
Hi-Abs, forklifts etc.
Access Scaffolding, Working platforms for high level block laying
Loading out blocks in work area and mixing mortar
Laying blockwork
Disposal of concrete – as per LEED requirements
Worker exposure to direct sun whist working on scaffolding
(as applicable)
11 Piling Operations with Rebar Cage installation Risk Assessment Templates
Piling Rig checks on arrival to site
PRIOR TO USE
Access of rig and delivery vehicles to work areas
Siting and setting up of piling rig
Piling operation
(Mobile rig Operator)
Rebar cage fabrication
Pile case and rebar cage lifting operations
Project Name: xxx
RA Ref No.: xxx
RA compilation Date: Review date:
Date:
Compiled by:
Reviewed by:
Approved by:
Overall Task Details
Use of mechanical breakers – excavator – for demolition of concrete structure Relevant Applicable MAS:
• 00940 – Plant Operators; Additional Training required:
NOC’s Required for task:
RISK SCORE CALCULATOR
Use the Risk Score Calculator to Determine the Level of Risk of each Hazard
What would be the
CONSEQUENCE
of an occurrence be? What is the LIKELIHOOD of an occurrence? Hierarchy of Controls
Frequent/Almost certain (5)
Continuous or will happen frequently Often (4)
6 to 12 times a year Likely (3)
1 to 5 times a year Possible (2)
Once every 5 years Rarely (1)
Less than once every 5 years Can the hazard be Eliminated or removed from the work place?
Catastrophic (5)
Multiple Fatalities High 25 High 20 High 15 Medium 10 Medium 5 Can the product or process be substituted for a less hazardous alternative?
Serious (4)
Class 1 single fatality High 20 High 16 High 12 Medium 8 Low 4 Can the hazard be engineered away with guards or barriers?
Moderate (3)
Class2 (AWI or LTI) or Class 1 Permanently disabling effects High 15 High 12 Medium 9 Medium 6 Low 3 Can Administration Controls be adopted
I.e. procedures, job rotation etc.
Minor (2)
Medical attention needed, no work restrictions. MTI Medium10 Medium 8 Medium 6 Low 4 Low 2 Can Personal Protective Equipment & Clothing be worn to safe guard against hazards?
Insignificant (1)
FAI Medium10 Medium 4 Low 3 Low 2 Low 1
No Specific Task Step
(In sequence of works) Hazard Details Consequence/Risk Initial Risk Rating Control Measures Residual Risks Additional Control Measures RR
L C RR
1 Plant checks on arrival to site
PRIOR TO SITE ACCESS • Use of heavy plant for demolition; • Unauthorized operation of the plant resulting in incident;
• Failure due to use of un-certificated plant;
3 4 12
HIGH i. All plant to be Third Party Certificated by a DM approved inspector, documentation available on arrival to site;
ii. Operators to have in-date Third Party certificate by approved body, available for review on arrival to site;
iii. Visual inspection of plant undertaken by competent person; Documentation unavailable for review Plant quarantined until evidence provided Low
2 Demolition of concrete structure • Excavator breaker operation
• (Operator)Plant / pedestrian interaction;
• Operator visibility; • Incident due to use of defective plant or associated equipment;
• Plant reversing – risk of serious injury to pedestrians;
• Unauthorized use of plant by untrained personnel;
• Collision with plant and live traffic within site boundary;
• Workers struck by working plant, very high risk of fatality;
• Noise;
• Exposed rebar – risk of injury;
• Possible contamination of asbestos in structure;
• Proximity to public areas;
4 4 16 HIGH i. Demolition Method statement to be submitted and adhered to. Demolition to be undertaken in a sequential, controlled
7 Falsework (Temporary Works) Risk Assessment Templates
Access to work areas by personnel and plant.
Material delivery to work area;
Use of powered access equipment for assembly of false-work (if required)
Falsework installation
(Classified as Temporary Structures)
Dismantling of false-work
Maintenance of Falsework
Worker exposure to direct sun whist working on falsework
(as applicable)
16 Scaffolding (Temporary Works) Risk Assessment Templates
Access to work areas by personnel and plant.
Scaffold Material delivery to work area;
Scaffold design and erection standards
(Classified as Temporary Structure)
Scaffold erection
(Classified as Temporary Structure)
Dismantling of scaffold
Maintenance of Scaffold
Worker exposure to direct sun whist working on scaffold
(as applicable)
15 Formwork (Temporary Works) Risk Assessment Templates
Access to work areas by personnel and plant.
Material delivery to work area;
Formwork installation
(Classified as Temporary Structures)
Housekeeping when erecting formwork
Dismantling of form-work
Maintenance of Formwork
Worker exposure to direct sun whist working on formwork
(as applicable)
Project Name: xxx
RA Ref No.: xxx
RA compilation Date: Review date:
Date:
Compiled by:
Reviewed by:
Approved by:
Overall Task Details
Laying blockwork with scaffold. Classed as Temporary Works Relevant Applicable MAS:
• 00939 - CoSHH
• 00236 – Housekeeping
• 00245 – Mobile Scaffolding Additional Training required:
Temporary Works Coordinator to be designated NOC’s Required for task:
RISK SCORE CALCULATOR
Use the Risk Score Calculator to Determine the Level of Risk of each Hazard
What would be the
CONSEQUENCE
of an occurrence be? What is the LIKELIHOOD of an occurrence? Hierarchy of Controls
Frequent/Almost certain (5)
Continuous or will happen frequently Often (4)
6 to 12 times a year Likely (3)
1 to 5 times a year Possible (2)
Once every 5 years Rarely (1)
Less than once every 5 years Can the hazard be Eliminated or removed from the work place?
Catastrophic (5)
Multiple Fatalities High 25 High 20 High 15 Medium 10 Medium 5 Can the product or process be substituted for a less hazardous alternative?
Serious (4)
Class 1 single fatality High 20 High 16 High 12 Medium 8 Low 4 Can the hazard be engineered away with guards or barriers?
Moderate (3)
Class2 (AWI or LTI) or Class 1 Permanently disabling effects High 15 High 12 Medium 9 Medium 6 Low 3 Can Administration Controls be adopted
I.e. procedures, job rotation etc.
Minor (2)
Medical attention needed, no work restrictions. MTI Medium10 Medium 8 Medium 6 Low 4 Low 2 Can Personal Protective Equipment & Clothing be worn to safe guard against hazards?
Insignificant (1)
FAI Medium10 Medium 4 Low 3 Low 2 Low 1
No Specific Task Step
(In sequence of works) Hazard Details Consequence/Risk Initial Risk Rating Control Measures Residual Risks Additional Control Measures RR
P S RR
1 Vehicles/Plant Equipment movements for block delivery
Hi-Abs, forklifts etc. • Use of plant;
• Plant / worker proximity; • Unauthorised use of untrained or unlicensed operators;
• Use of un-certificated plant and equipment;
• Striking against mobile and/or fixed objects/vehicles;
• Collision of plant, including those of other contractors in area;
• Collision with operatives, including other contractors; 4 4 16
HIGH i. Only competent and authorised personnel with licence for the category of plant they are operating are allowed to operate the machinery, reviewed by logistics before commencing on site;
ii. All plant and equipment shall be Third Party Certificated by a DM approved assessor;
iii. Heavy equipment shall be equipped with audible reversing alarm (not possible on bi-directional equipment);
iv. A flagman to be present to signal reversing vehicles, reversing of vehicles to be avoided where practicable;
v. All plant / vehicles to be controlled by banks man;
vi. Plant to be parked only in designated area, parking brake on, keys removed with working parts lowered;
vii. Protected access route(s) for pedestrians maintained where required;
viii. Effective Traffic Management System (TMS) to be s
5 Trial Trenches (Temporary Works) Risk Assessment Templates
Planned shallow Excavation (Trial Trench) in areas where live services may be present including:
• Electrical;
• Water;
• Sewerage;
• Gas;
• Telecoms;
PRIOR TO WORKS
Use of Excavator for trial trenches and backfilling
Note:
Wherever practicable trial trenches shall be hand dug to expose services.
Trench (shallow excavation) open in site area
Maintenance of Trenches
Worker exposure to direct sun
(as applicable)
6 Excavations (Temporary Works) Risk Assessment Templates
Planned Excavation in areas where live services may be present including:
• Electrical;
• Water;
• Sewerage;
• Gas;
• Telecoms;
PRIOR TO WORKS
Use of Excavator for excavating and backfilling
Excavation open in site area
Confined space working – deep excavations
Maintenance of Excavations
Worker exposure to direct sun
(as applicable)
13 Initial Project Site Office Set-up Risk Assessment Templates
Working adjacent to public areas
Vehicles/Plant Equipment movements
Groundworks / excavations
Excavation in site area
Trial trenches, septic tank excavation etc.
Works at Height
(Office cabin set-up)
Use of Ladders and stepladders
Mobile Crane operation
(Cabin/unit placing)
Temporary electrics - offices
Site generators – offices and site
8 Lifting Operations with mobile crane Risk Assessment Templates
Crane checks on arrival to site
PRIOR TO USE
Access of crane to work areas
Siting and setting up of crane
Lifting of equipment and material
(Mobile crane Operator)
Crane supervision
Crane Maintenance
(revised 06-06-2018)
26 Storage of Substances under CoSHH Risk Assessment Templates.docxDwarika Bhushan Sharma
Project Name: xxx
RA Ref No.: xxx
RA compilation Date: Review date:
Date:
Compiled by:
Reviewed by:
Approved by:
Overall Task Details
Storage of substances classified under CoSHH on project sites, such as paints and associated thinners and cleaners, protective coatings, additives, adhesives and sealants, chemical sprays, fuels and oils, etc. Relevant Applicable MAS:
• 00939 – Storage of Substances Hazardous to Health Additional Training required:
NOC’s Required for task:
RISK SCORE CALCULATOR
Use the Risk Score Calculator to Determine the Level of Risk of each Hazard
What would be the
CONSEQUENCE
of an occurrence be? What is the LIKELIHOOD of an occurrence? Hierarchy of Controls
Frequent/Almost certain (5)
Continuous or will happen frequently Often (4)
6 to 12 times a year Likely (3)
1 to 5 times a year Possible (2)
Once every 5 years Rarely (1)
Less than once every 5 years Can the hazard be Eliminated or removed from the work place?
Catastrophic (5)
Multiple Fatalities High 25 High 20 High 15 Medium 10 Medium 5 Can the product or process be substituted for a less hazardous alternative?
Serious (4)
Class 1 single fatality High 20 High 16 High 12 Medium 8 Low 4 Can the hazard be engineered away with guards or barriers?
Moderate (3)
Class2 (AWI or LTI) or Class 1 Permanently disabling effects High 15 High 12 Medium 9 Medium 6 Low 3 Can Administration Controls be adopted
I.e. procedures, job rotation etc.
Minor (2)
Medical attention needed, no work restrictions. MTI Medium10 Medium 8 Medium 6 Low 4 Low 2 Can Personal Protective Equipment & Clothing be worn to safe guard against hazards?
Insignificant (1)
FAI Medium10 Medium 4 Low 3 Low 2 Low 1
No Specific Task Step
(In sequence of works) Hazard Details Consequence/Risk Initial Risk Rating Control Measures Residual Risks Additional Control Measures RR
L C RR
1 PRIOR TO / AT SITE DELIVERY • Hazardous substances • Poor or incorrect substance storage due to lack of manufacturer’s specification; 3 3 9 MED i. Store operatives to ensure a Hazard Data Sheet is supplied ideally prior to substance delivery, if not supplied when delivered to site; Documentation unavailable for review Substance quarantined until evidence provided Low
2 Storage • Storage of Substance potentially hazardous to worker health or to the environment; • Possible inhalation, absorption of hazardous fumes, vapor and substances hazardous to health;
• Build-up of flammable vapor in confined area;
• Fire;
• Inadequate cooling and ventilation of storage resulting in ill health or combustion;
• Inadequate signage and substance identification;
• Poor controls over distribution of substances/chemicals;
• Excessive quantities issued to work areas;
3 4 12 HIGH i. HLG Workplaces storing hazardous substances/chemicals, using hazardous materials and/or generating hazardous waste shall have a hazardous materials management system;
ii. A plan of the store showing locations of the hazardous materials / wastes
17 traffic operations working on live roads risk assessment templatesDwarika Bhushan Sharma
17 Traffic Op
erations - Working on live roads Risk Assessment Templates
• Road works
• Road delineation
• Diversions
• Closures
Vehicles and Equipment movements
(Truck and Hi-ab
Access to work areas within enclosed boundaries by personnel and plant.
Worker exposure to direct sun whist working on roads
(as applicable)
Plant checks on arrival to site
PRIOR TO SITE ACCESS • Use of heavy plant for demolition;
Demolition of concrete structure • Excavator breaker operation
• (Operator)Plant / pedestrian interaction;
• Operator visibility;
Demolition (supervision) • Plant operations around workers;
• Workers in plant operating radius;
Undertaking breaking Works – Manual operation using compressed air jack hammers; • Use of hand held breakers;
Removal of waste concrete and rebar • Truck operations around workers;
19 use of mobile elevated work platforms risk assessment templatesDwarika Bhushan Sharma
19 Use of Mobile Elevated Work Platforms Risk Assessment Templates
MEWP checks on arrival to site
PRIOR TO SITE ACCESS • Use of Access plant • Unauthorized operation of the plant resulting in incident;
• Failure due to use of un-certificated plant;
MEWP operation
(Operator) • Operator competency;
• Plant / pedestrian interaction;
• Work at Height; • Incident due to use of defective plant or associated equipment;
• MEWP overturning;
• Plant reversing – risk of serious injury to pedestrians;
• Unauthorized use of MEWP by untrained personnel;
• Operators climbing onto hand rails;
• Collision with other plant and live traffic within site boundary;
• Workers struck by working MEWP, very high risk of fatality;
• Falling materials;
MEWP operation (supervision) • MEWP operations around workers;
• Workers in MEWP operating radius;
• Reversing vehicles; • Worker struck by vehicle;•
Arrangements for management of the different conditions brought about by night works or what assessments will be undertaken to ensure this can be conducted safely. Detail should also include shift patterns and management of worker fatigue.
Working at night poses a serious safety risk for
highway & construction workers. Those who work
at night are at a higher risk for injury because of:
• Reduced visibility for Equipment and other
vehicle drivers.
• Reduced visibility for workers.
• Lack of communication between shifts
• Increased number of impaired or drowsy drivers
• Sleep deprivation for workers
14 use of plant graders and road rollers risk assessment templatesDwarika Bhushan Sharma
14 Use of Plant- Graders and road rollers Risk Assessment Templates
Grader /Roller checks on arrival to site
PRIOR TO SITE ACCESS • Use of heavy plant • Unauthorized operation of the plant resulting in incident;
• Failure due to use of un-certificated plant;
Grader and Roller operation
(Plant Operator) • Operator competency;
• Plant / pedestrian interaction;
• Operator visibility; • Incident due to use of defective plant or associated equipment;
• Plant reversing – risk of serious injury to pedestrians;
• Unauthorized use of plant by untrained personnel;
• Collision with plant and live traffic within site boundary;
• Workers struck by working plant, very high risk of fatality;
Plant operation supervision • Plant operations around workers;
• Workers in plant operating radius;
• Reversing vehicles; • Worker struck by vehicle;
• Plant operator unable to see task – screen covered;
•
Project Fire Risk Assessment Report
(Quarterly) By: App: Project Relevant legislation:
• Federal Law No. 8 – Chapter 5 Article 92 ;
• DM Code of Construction Practice – Chapter 5;
• Regulation NO. 5 2009 Railways in the Emirate of Dubai (RED);
• Railway Protection Code of Practice (RWPCOP);
• UAE Fire and Life Safety Code of Practice – Chapter 12 (FLSCOP);
• Abu Dhabi Occupational Safety and Health Center – Code of Practise (OSHAD – CoP)
Issued: Rev.
Area: Assessment Date:
Next Assessment date:
Report compiled by:
Designation:
ASSESSMENT CRITERIA FIRE AND EMERGENCY CONTROL MEASURES AND LEGAL REQUIREMENTS RELEVANT LEGISLATION IMPLEMENTED PROJECT CONTROLS FOR COMPLIANCE COMMENTS FROM LAST FIRE ASSESSMENT
1. Site set up of temporary offices and cabins
Incl. Fire risk assessment; • Fire risk assessment undertaken on site set up and maintained/amended as project progresses;
• A copy of the fire risk assessment is maintained by HSE personnel;
• Separation distances between buildings under construction and construction-related structures, such as temporary offices, trailers, sheds, and other facilities for the storage of tools and materials having combustible construction or contents;
• No offices to be erected within the 70m Metro Protection Zone; FLSCOP Chapter 12 Table 12.1
RWPCOP
Section 4.6.1
DM Chapter 5.4
OSHAD CoP 8.0 & 43.0 •
2. Use of Portable gas heating or cutting equipment.
(all areas) • Ensure equipment is used in accordance with MAS and adequately maintained;
• Ensure suitable extraction is in place in confined areas and equipment is suitably maintained, extractors regularly maintained/cleaned;
• Ensure suitable fire- fighting equipment available nearby;
• Ensure use of Hot Works and Permits to Work as per section 5 and OSHAD CoP 21.0 and CoP 28.0;
• Ensure flashback arrestors fitted, hoses and connections sound and leak proof (as per inspection regime);
• Gas cylinder storage detailed in Section 7 and OSHAD CoP 49.0; FLSCOP Chapter 12 Section 7
DM Chapters 5, 15
OSHAD CoP 21.0, 28.0 & 49.0 •
3. Electrical equipment (portable and fixed installation)
• Portable electrical equipment to be tested every 6 months. Test stickers on appliances for date of last testing;
• Ensure fixed/temporary installations are checked by a competent person monthly and that this check is recorded and registered;
• Ensure that socket/DB outlets are not overloaded and connections are correct to standards;
• Correct rated fuses and breakers to be installed;
• DB’s to be waterproof and mounted on metal frames if on site;
• All site supply cables to be armoured;
• Install overhead cable frames where practicable in congested areas;
• Damaged equipment and cords shall be removed from service and quarantined until repaired or destroyed;
• Temporary lights shall not be suspended by their electrical cords unless such cords and lights have been designed for that purpose; FLSCOP Chapter 12 Section 14
DM Chapters 5.6, 16 & 17
O
Planned excavation for NDRC pit in areas where live services may be present including:
• Electrical;
• Water;
• Sewerage;
• Gas;
• Telecoms;
PRIOR TO WORKS
Use of Excavator for excavating NDRC Pit and backfilling
Excavation open in site area
Confined space working – deep excavation for NDRC
NDRC – Thrust boring operation
Pipe electric welding inside pit
HDPE Welding inside pit
Maintenance of NDRC Excavation
Worker exposure to direct sun
(as applicable)
9 Lifting Operations with Tower crane Risk Assessment Templates
Access of Tower crane sections to work areas
Tower crane foundations
Siting, setting up and testing of Tower crane
Lifting of equipment and material
(Tower crane Operator)
Tower Crane supervision
Jumping and dismantling of Tower Crane
4 Cofferdams (Temporary Works) Risk Assessment Templates
Planned Cofferdam excavation in areas where live services may be present including:
• Electrical;
• Water;
• Sewerage;
• Gas;
• Telecoms;
PRIOR TO WORKS
Cofferdam Design under Temporary Works
Cofferdam excavation
Cofferdam sheet piling
Lifting operations
Confined space working – cofferdam
Installation of wales, bracing etc.
Maintenance of cofferdam
Temporary electric supply for temporary lighting • Correct installation of lighting; • Electric shock or electrocution from incorrect installation;
• Work undertaken by incompetent workers;
• Burns from halogen lights;
• Injury from broken glass from halogen lights;
Works undertaken in areas of low light or night works • Work in areas of low light levels;
• Slips and Trips;
• Incident due to insufficient lighting;
• Workers blinded by direct light source when moving around work area;
Emergency lighting • Power failure • Workers unable to locate emergency exits in the event of an incident;
RISK SCORE CALCULATOR
Use the Risk Score Calculator to Determine the Level of Risk of each Hazard
What would be the
CONSEQUENCE
of an occurrence be? What is the LIKELIHOOD of an occurrence? Hierarchy of Controls
Frequent/Almost certain (5)
Continuous or will happen frequently Often (4)
6 to 12 times a year Likely (3)
1 to 5 times a year Possible (2)
Once every 5 years Rarely (1)
Less than once every 5 years Can the hazard be Eliminated or removed from the work place?
Catastrophic (5)
Multiple Fatalities High 25 High 20 High 15 Medium 10 Medium 5 Can the product or process be substituted for a less hazardous alternative?
Serious (4)
Class 1 single fatality High 20 High 16 High 12 Medium 8 Low 4 Can the hazard be engineered away with guards or barriers?
Moderate (3)
Class2 (AWI or LTI) or Class 1 Permanently disabling effects High 15 High 12 Medium 9 Medium 6 Low 3 Can Administration Controls be adopted
I.e. procedures, job rotation etc.
Minor (2)
Medical attention needed, no work restrictions. MTI Medium10 Medium 8 Medium 6 Low 4 Low 2 Can Personal Protective Equipment & Clothing be worn to safe guard against hazards?
Insignificant (1)
FAI Medium10 Medium 4 Low 3 Low 2 Low 1
Project Name: xxx
RA Ref No.: xxx
RA compilation Date: Review date:
Date:
Compiled by:
Reviewed by:
Approved by:
Overall Task Details
Working in area designated as a confined space Relevant Applicable MAS:
• 00246 – Excavations;
• 00233 – Lift Shafts Additional Training required:
NOC’s Required for task:
No Specific Task Step
(In sequence of works) Hazard Details Consequence/Risk Initial Risk Rating Control Measures Residual Risks Additional Control Measures RR
P S RR
1 Planned confined space work in areas where live services may be present including:
• Water;
• Sewerage;
• Gas;
PRIOR TO ENTRY • Presence of live underground services;
• Services not in area specified on drawings;
• Presence of unmarked services;
• Risk of asphyxia;
• Risk of explosion due to gas ignition;
• Risk of flooding of confined space;
• Risk of hazardous waste entering confined space due to live sewerage;
• Risk of vehicles / Plant entering confined space; 4 4 20
HIGH i. All existing utility service drawings reviewed for known service details and position;
ii. NOC and Utility provider and HLG permits to be completed, unique number added and recorded in log;
iii. All services clearly communicated to all workers at briefings and TBT’s, signed off and recorded;
iv. Permit/NOC/JSEA/Approved design Drawings copies to be with task supervisor in work area for review;
v. Suitable training undertaken for operatives; LOW
2 Confined space working –
• Deep excavations;
• Tanks;
• Vessels;
• Manholes;
• NDRC pits;
• Bridge decks;
• Pipework;
• Sewerage;
• Lift shafts;
• Ducting;
• Etc. • Workers required to work in confined space; • Excess or lack of oxygen;
• Presence of Toxic gases;
• Ingress of water or other substances;
• Explosion due to build-up of gases;
• Sudden w
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates
Sheet piling Rig checks on arrival to site
PRIOR TO USE
Access of rig and sheet pile delivery vehicles to work areas
Siting and setting up of sheet piling rig
Sheet piling operation
(Mobile rig Operator)
Sheet piling operation
16 Scaffolding (Temporary Works) Risk Assessment Templates
Access to work areas by personnel and plant.
Scaffold Material delivery to work area;
Scaffold design and erection standards
(Classified as Temporary Structure)
Scaffold erection
(Classified as Temporary Structure)
Dismantling of scaffold
Maintenance of Scaffold
Worker exposure to direct sun whist working on scaffold
(as applicable)
15 Formwork (Temporary Works) Risk Assessment Templates
Access to work areas by personnel and plant.
Material delivery to work area;
Formwork installation
(Classified as Temporary Structures)
Housekeeping when erecting formwork
Dismantling of form-work
Maintenance of Formwork
Worker exposure to direct sun whist working on formwork
(as applicable)
Project Name: xxx
RA Ref No.: xxx
RA compilation Date: Review date:
Date:
Compiled by:
Reviewed by:
Approved by:
Overall Task Details
Laying blockwork with scaffold. Classed as Temporary Works Relevant Applicable MAS:
• 00939 - CoSHH
• 00236 – Housekeeping
• 00245 – Mobile Scaffolding Additional Training required:
Temporary Works Coordinator to be designated NOC’s Required for task:
RISK SCORE CALCULATOR
Use the Risk Score Calculator to Determine the Level of Risk of each Hazard
What would be the
CONSEQUENCE
of an occurrence be? What is the LIKELIHOOD of an occurrence? Hierarchy of Controls
Frequent/Almost certain (5)
Continuous or will happen frequently Often (4)
6 to 12 times a year Likely (3)
1 to 5 times a year Possible (2)
Once every 5 years Rarely (1)
Less than once every 5 years Can the hazard be Eliminated or removed from the work place?
Catastrophic (5)
Multiple Fatalities High 25 High 20 High 15 Medium 10 Medium 5 Can the product or process be substituted for a less hazardous alternative?
Serious (4)
Class 1 single fatality High 20 High 16 High 12 Medium 8 Low 4 Can the hazard be engineered away with guards or barriers?
Moderate (3)
Class2 (AWI or LTI) or Class 1 Permanently disabling effects High 15 High 12 Medium 9 Medium 6 Low 3 Can Administration Controls be adopted
I.e. procedures, job rotation etc.
Minor (2)
Medical attention needed, no work restrictions. MTI Medium10 Medium 8 Medium 6 Low 4 Low 2 Can Personal Protective Equipment & Clothing be worn to safe guard against hazards?
Insignificant (1)
FAI Medium10 Medium 4 Low 3 Low 2 Low 1
No Specific Task Step
(In sequence of works) Hazard Details Consequence/Risk Initial Risk Rating Control Measures Residual Risks Additional Control Measures RR
P S RR
1 Vehicles/Plant Equipment movements for block delivery
Hi-Abs, forklifts etc. • Use of plant;
• Plant / worker proximity; • Unauthorised use of untrained or unlicensed operators;
• Use of un-certificated plant and equipment;
• Striking against mobile and/or fixed objects/vehicles;
• Collision of plant, including those of other contractors in area;
• Collision with operatives, including other contractors; 4 4 16
HIGH i. Only competent and authorised personnel with licence for the category of plant they are operating are allowed to operate the machinery, reviewed by logistics before commencing on site;
ii. All plant and equipment shall be Third Party Certificated by a DM approved assessor;
iii. Heavy equipment shall be equipped with audible reversing alarm (not possible on bi-directional equipment);
iv. A flagman to be present to signal reversing vehicles, reversing of vehicles to be avoided where practicable;
v. All plant / vehicles to be controlled by banks man;
vi. Plant to be parked only in designated area, parking brake on, keys removed with working parts lowered;
vii. Protected access route(s) for pedestrians maintained where required;
viii. Effective Traffic Management System (TMS) to be s
5 Trial Trenches (Temporary Works) Risk Assessment Templates
Planned shallow Excavation (Trial Trench) in areas where live services may be present including:
• Electrical;
• Water;
• Sewerage;
• Gas;
• Telecoms;
PRIOR TO WORKS
Use of Excavator for trial trenches and backfilling
Note:
Wherever practicable trial trenches shall be hand dug to expose services.
Trench (shallow excavation) open in site area
Maintenance of Trenches
Worker exposure to direct sun
(as applicable)
6 Excavations (Temporary Works) Risk Assessment Templates
Planned Excavation in areas where live services may be present including:
• Electrical;
• Water;
• Sewerage;
• Gas;
• Telecoms;
PRIOR TO WORKS
Use of Excavator for excavating and backfilling
Excavation open in site area
Confined space working – deep excavations
Maintenance of Excavations
Worker exposure to direct sun
(as applicable)
13 Initial Project Site Office Set-up Risk Assessment Templates
Working adjacent to public areas
Vehicles/Plant Equipment movements
Groundworks / excavations
Excavation in site area
Trial trenches, septic tank excavation etc.
Works at Height
(Office cabin set-up)
Use of Ladders and stepladders
Mobile Crane operation
(Cabin/unit placing)
Temporary electrics - offices
Site generators – offices and site
8 Lifting Operations with mobile crane Risk Assessment Templates
Crane checks on arrival to site
PRIOR TO USE
Access of crane to work areas
Siting and setting up of crane
Lifting of equipment and material
(Mobile crane Operator)
Crane supervision
Crane Maintenance
(revised 06-06-2018)
26 Storage of Substances under CoSHH Risk Assessment Templates.docxDwarika Bhushan Sharma
Project Name: xxx
RA Ref No.: xxx
RA compilation Date: Review date:
Date:
Compiled by:
Reviewed by:
Approved by:
Overall Task Details
Storage of substances classified under CoSHH on project sites, such as paints and associated thinners and cleaners, protective coatings, additives, adhesives and sealants, chemical sprays, fuels and oils, etc. Relevant Applicable MAS:
• 00939 – Storage of Substances Hazardous to Health Additional Training required:
NOC’s Required for task:
RISK SCORE CALCULATOR
Use the Risk Score Calculator to Determine the Level of Risk of each Hazard
What would be the
CONSEQUENCE
of an occurrence be? What is the LIKELIHOOD of an occurrence? Hierarchy of Controls
Frequent/Almost certain (5)
Continuous or will happen frequently Often (4)
6 to 12 times a year Likely (3)
1 to 5 times a year Possible (2)
Once every 5 years Rarely (1)
Less than once every 5 years Can the hazard be Eliminated or removed from the work place?
Catastrophic (5)
Multiple Fatalities High 25 High 20 High 15 Medium 10 Medium 5 Can the product or process be substituted for a less hazardous alternative?
Serious (4)
Class 1 single fatality High 20 High 16 High 12 Medium 8 Low 4 Can the hazard be engineered away with guards or barriers?
Moderate (3)
Class2 (AWI or LTI) or Class 1 Permanently disabling effects High 15 High 12 Medium 9 Medium 6 Low 3 Can Administration Controls be adopted
I.e. procedures, job rotation etc.
Minor (2)
Medical attention needed, no work restrictions. MTI Medium10 Medium 8 Medium 6 Low 4 Low 2 Can Personal Protective Equipment & Clothing be worn to safe guard against hazards?
Insignificant (1)
FAI Medium10 Medium 4 Low 3 Low 2 Low 1
No Specific Task Step
(In sequence of works) Hazard Details Consequence/Risk Initial Risk Rating Control Measures Residual Risks Additional Control Measures RR
L C RR
1 PRIOR TO / AT SITE DELIVERY • Hazardous substances • Poor or incorrect substance storage due to lack of manufacturer’s specification; 3 3 9 MED i. Store operatives to ensure a Hazard Data Sheet is supplied ideally prior to substance delivery, if not supplied when delivered to site; Documentation unavailable for review Substance quarantined until evidence provided Low
2 Storage • Storage of Substance potentially hazardous to worker health or to the environment; • Possible inhalation, absorption of hazardous fumes, vapor and substances hazardous to health;
• Build-up of flammable vapor in confined area;
• Fire;
• Inadequate cooling and ventilation of storage resulting in ill health or combustion;
• Inadequate signage and substance identification;
• Poor controls over distribution of substances/chemicals;
• Excessive quantities issued to work areas;
3 4 12 HIGH i. HLG Workplaces storing hazardous substances/chemicals, using hazardous materials and/or generating hazardous waste shall have a hazardous materials management system;
ii. A plan of the store showing locations of the hazardous materials / wastes
17 traffic operations working on live roads risk assessment templatesDwarika Bhushan Sharma
17 Traffic Op
erations - Working on live roads Risk Assessment Templates
• Road works
• Road delineation
• Diversions
• Closures
Vehicles and Equipment movements
(Truck and Hi-ab
Access to work areas within enclosed boundaries by personnel and plant.
Worker exposure to direct sun whist working on roads
(as applicable)
Plant checks on arrival to site
PRIOR TO SITE ACCESS • Use of heavy plant for demolition;
Demolition of concrete structure • Excavator breaker operation
• (Operator)Plant / pedestrian interaction;
• Operator visibility;
Demolition (supervision) • Plant operations around workers;
• Workers in plant operating radius;
Undertaking breaking Works – Manual operation using compressed air jack hammers; • Use of hand held breakers;
Removal of waste concrete and rebar • Truck operations around workers;
19 use of mobile elevated work platforms risk assessment templatesDwarika Bhushan Sharma
19 Use of Mobile Elevated Work Platforms Risk Assessment Templates
MEWP checks on arrival to site
PRIOR TO SITE ACCESS • Use of Access plant • Unauthorized operation of the plant resulting in incident;
• Failure due to use of un-certificated plant;
MEWP operation
(Operator) • Operator competency;
• Plant / pedestrian interaction;
• Work at Height; • Incident due to use of defective plant or associated equipment;
• MEWP overturning;
• Plant reversing – risk of serious injury to pedestrians;
• Unauthorized use of MEWP by untrained personnel;
• Operators climbing onto hand rails;
• Collision with other plant and live traffic within site boundary;
• Workers struck by working MEWP, very high risk of fatality;
• Falling materials;
MEWP operation (supervision) • MEWP operations around workers;
• Workers in MEWP operating radius;
• Reversing vehicles; • Worker struck by vehicle;•
Arrangements for management of the different conditions brought about by night works or what assessments will be undertaken to ensure this can be conducted safely. Detail should also include shift patterns and management of worker fatigue.
Working at night poses a serious safety risk for
highway & construction workers. Those who work
at night are at a higher risk for injury because of:
• Reduced visibility for Equipment and other
vehicle drivers.
• Reduced visibility for workers.
• Lack of communication between shifts
• Increased number of impaired or drowsy drivers
• Sleep deprivation for workers
14 use of plant graders and road rollers risk assessment templatesDwarika Bhushan Sharma
14 Use of Plant- Graders and road rollers Risk Assessment Templates
Grader /Roller checks on arrival to site
PRIOR TO SITE ACCESS • Use of heavy plant • Unauthorized operation of the plant resulting in incident;
• Failure due to use of un-certificated plant;
Grader and Roller operation
(Plant Operator) • Operator competency;
• Plant / pedestrian interaction;
• Operator visibility; • Incident due to use of defective plant or associated equipment;
• Plant reversing – risk of serious injury to pedestrians;
• Unauthorized use of plant by untrained personnel;
• Collision with plant and live traffic within site boundary;
• Workers struck by working plant, very high risk of fatality;
Plant operation supervision • Plant operations around workers;
• Workers in plant operating radius;
• Reversing vehicles; • Worker struck by vehicle;
• Plant operator unable to see task – screen covered;
•
Project Fire Risk Assessment Report
(Quarterly) By: App: Project Relevant legislation:
• Federal Law No. 8 – Chapter 5 Article 92 ;
• DM Code of Construction Practice – Chapter 5;
• Regulation NO. 5 2009 Railways in the Emirate of Dubai (RED);
• Railway Protection Code of Practice (RWPCOP);
• UAE Fire and Life Safety Code of Practice – Chapter 12 (FLSCOP);
• Abu Dhabi Occupational Safety and Health Center – Code of Practise (OSHAD – CoP)
Issued: Rev.
Area: Assessment Date:
Next Assessment date:
Report compiled by:
Designation:
ASSESSMENT CRITERIA FIRE AND EMERGENCY CONTROL MEASURES AND LEGAL REQUIREMENTS RELEVANT LEGISLATION IMPLEMENTED PROJECT CONTROLS FOR COMPLIANCE COMMENTS FROM LAST FIRE ASSESSMENT
1. Site set up of temporary offices and cabins
Incl. Fire risk assessment; • Fire risk assessment undertaken on site set up and maintained/amended as project progresses;
• A copy of the fire risk assessment is maintained by HSE personnel;
• Separation distances between buildings under construction and construction-related structures, such as temporary offices, trailers, sheds, and other facilities for the storage of tools and materials having combustible construction or contents;
• No offices to be erected within the 70m Metro Protection Zone; FLSCOP Chapter 12 Table 12.1
RWPCOP
Section 4.6.1
DM Chapter 5.4
OSHAD CoP 8.0 & 43.0 •
2. Use of Portable gas heating or cutting equipment.
(all areas) • Ensure equipment is used in accordance with MAS and adequately maintained;
• Ensure suitable extraction is in place in confined areas and equipment is suitably maintained, extractors regularly maintained/cleaned;
• Ensure suitable fire- fighting equipment available nearby;
• Ensure use of Hot Works and Permits to Work as per section 5 and OSHAD CoP 21.0 and CoP 28.0;
• Ensure flashback arrestors fitted, hoses and connections sound and leak proof (as per inspection regime);
• Gas cylinder storage detailed in Section 7 and OSHAD CoP 49.0; FLSCOP Chapter 12 Section 7
DM Chapters 5, 15
OSHAD CoP 21.0, 28.0 & 49.0 •
3. Electrical equipment (portable and fixed installation)
• Portable electrical equipment to be tested every 6 months. Test stickers on appliances for date of last testing;
• Ensure fixed/temporary installations are checked by a competent person monthly and that this check is recorded and registered;
• Ensure that socket/DB outlets are not overloaded and connections are correct to standards;
• Correct rated fuses and breakers to be installed;
• DB’s to be waterproof and mounted on metal frames if on site;
• All site supply cables to be armoured;
• Install overhead cable frames where practicable in congested areas;
• Damaged equipment and cords shall be removed from service and quarantined until repaired or destroyed;
• Temporary lights shall not be suspended by their electrical cords unless such cords and lights have been designed for that purpose; FLSCOP Chapter 12 Section 14
DM Chapters 5.6, 16 & 17
O
Planned excavation for NDRC pit in areas where live services may be present including:
• Electrical;
• Water;
• Sewerage;
• Gas;
• Telecoms;
PRIOR TO WORKS
Use of Excavator for excavating NDRC Pit and backfilling
Excavation open in site area
Confined space working – deep excavation for NDRC
NDRC – Thrust boring operation
Pipe electric welding inside pit
HDPE Welding inside pit
Maintenance of NDRC Excavation
Worker exposure to direct sun
(as applicable)
9 Lifting Operations with Tower crane Risk Assessment Templates
Access of Tower crane sections to work areas
Tower crane foundations
Siting, setting up and testing of Tower crane
Lifting of equipment and material
(Tower crane Operator)
Tower Crane supervision
Jumping and dismantling of Tower Crane
4 Cofferdams (Temporary Works) Risk Assessment Templates
Planned Cofferdam excavation in areas where live services may be present including:
• Electrical;
• Water;
• Sewerage;
• Gas;
• Telecoms;
PRIOR TO WORKS
Cofferdam Design under Temporary Works
Cofferdam excavation
Cofferdam sheet piling
Lifting operations
Confined space working – cofferdam
Installation of wales, bracing etc.
Maintenance of cofferdam
Temporary electric supply for temporary lighting • Correct installation of lighting; • Electric shock or electrocution from incorrect installation;
• Work undertaken by incompetent workers;
• Burns from halogen lights;
• Injury from broken glass from halogen lights;
Works undertaken in areas of low light or night works • Work in areas of low light levels;
• Slips and Trips;
• Incident due to insufficient lighting;
• Workers blinded by direct light source when moving around work area;
Emergency lighting • Power failure • Workers unable to locate emergency exits in the event of an incident;
RISK SCORE CALCULATOR
Use the Risk Score Calculator to Determine the Level of Risk of each Hazard
What would be the
CONSEQUENCE
of an occurrence be? What is the LIKELIHOOD of an occurrence? Hierarchy of Controls
Frequent/Almost certain (5)
Continuous or will happen frequently Often (4)
6 to 12 times a year Likely (3)
1 to 5 times a year Possible (2)
Once every 5 years Rarely (1)
Less than once every 5 years Can the hazard be Eliminated or removed from the work place?
Catastrophic (5)
Multiple Fatalities High 25 High 20 High 15 Medium 10 Medium 5 Can the product or process be substituted for a less hazardous alternative?
Serious (4)
Class 1 single fatality High 20 High 16 High 12 Medium 8 Low 4 Can the hazard be engineered away with guards or barriers?
Moderate (3)
Class2 (AWI or LTI) or Class 1 Permanently disabling effects High 15 High 12 Medium 9 Medium 6 Low 3 Can Administration Controls be adopted
I.e. procedures, job rotation etc.
Minor (2)
Medical attention needed, no work restrictions. MTI Medium10 Medium 8 Medium 6 Low 4 Low 2 Can Personal Protective Equipment & Clothing be worn to safe guard against hazards?
Insignificant (1)
FAI Medium10 Medium 4 Low 3 Low 2 Low 1
Project Name: xxx
RA Ref No.: xxx
RA compilation Date: Review date:
Date:
Compiled by:
Reviewed by:
Approved by:
Overall Task Details
Working in area designated as a confined space Relevant Applicable MAS:
• 00246 – Excavations;
• 00233 – Lift Shafts Additional Training required:
NOC’s Required for task:
No Specific Task Step
(In sequence of works) Hazard Details Consequence/Risk Initial Risk Rating Control Measures Residual Risks Additional Control Measures RR
P S RR
1 Planned confined space work in areas where live services may be present including:
• Water;
• Sewerage;
• Gas;
PRIOR TO ENTRY • Presence of live underground services;
• Services not in area specified on drawings;
• Presence of unmarked services;
• Risk of asphyxia;
• Risk of explosion due to gas ignition;
• Risk of flooding of confined space;
• Risk of hazardous waste entering confined space due to live sewerage;
• Risk of vehicles / Plant entering confined space; 4 4 20
HIGH i. All existing utility service drawings reviewed for known service details and position;
ii. NOC and Utility provider and HLG permits to be completed, unique number added and recorded in log;
iii. All services clearly communicated to all workers at briefings and TBT’s, signed off and recorded;
iv. Permit/NOC/JSEA/Approved design Drawings copies to be with task supervisor in work area for review;
v. Suitable training undertaken for operatives; LOW
2 Confined space working –
• Deep excavations;
• Tanks;
• Vessels;
• Manholes;
• NDRC pits;
• Bridge decks;
• Pipework;
• Sewerage;
• Lift shafts;
• Ducting;
• Etc. • Workers required to work in confined space; • Excess or lack of oxygen;
• Presence of Toxic gases;
• Ingress of water or other substances;
• Explosion due to build-up of gases;
• Sudden w
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates
Sheet piling Rig checks on arrival to site
PRIOR TO USE
Access of rig and sheet pile delivery vehicles to work areas
Siting and setting up of sheet piling rig
Sheet piling operation
(Mobile rig Operator)
Sheet piling operation
RISK SCORE CALCULATOR
Use the Risk Score Calculator to Determine the Level of Risk of each Hazard
What would be the
CONSEQUENCE
of an occurrence be? What is the LIKELIHOOD of an occurrence? Hierarchy of Controls
Frequent/Almost certain (5)
Continuous or will happen frequently Often (4)
6 to 12 times a year Likely (3)
1 to 5 times a year Possible (2)
Once every 5 years Rarely (1)
Less than once every 5 years Can the hazard be Eliminated or removed from the work place?
Catastrophic (5)
Multiple Fatalities High 25 High 20 High 15 Medium 10 Medium 5 Can the product or process be substituted for a less hazardous alternative?
Serious (4)
Class 1 single fatality High 20 High 16 High 12 Medium 8 Low 4 Can the hazard be engineered away with guards or barriers?
Moderate (3)
Class2 (AWI or LTI) or Class 1 Permanently disabling effects High 15 High 12 Medium 9 Medium 6 Low 3 Can Administration Controls be adopted
I.e. procedures, job rotation etc.
Minor (2)
Medical attention needed, no work restrictions. MTI Medium10 Medium 8 Medium 6 Low 4 Low 2 Can Personal Protective Equipment & Clothing be worn to safe guard against hazards?
Insignificant (1)
FAI Medium10 Medium 4 Low 3 Low 2 Low 1
Project Name: xxx
RA Ref No.: xxx
RA compilation Date: Review date:
Date:
Compiled by:
Reviewed by:
Approved by:
Overall Task Details
Excavation on site greater than 1.2 depth for Non Disruptive Road Crossing (NDRC). Use of excavator and pipe thrust boring equipment
Classed as Temporary Works Relevant Applicable MAS:
• 00246 – Excavations;
• 01413 – Underground services;
• 00940 – Plant Operators. Additional Training required:
Temporary Works Coordinator to be designated NOC’s Required for task:
Municipality
No Specific Task Step
(In sequence of works) Hazard Details Consequence/Risk Initial Risk Rating Control Measures Residual Risks Additional Control Measures RR
L C RR
1 Planned excavation for NDRC pit in areas where live services may be present including:
• Electrical;
• Water;
• Sewerage;
• Gas;
• Telecoms;
PRIOR TO WORKS • Presence of live underground services;
• Services not in area specified on drawings;
• Heavy plant or vehicles accessing work area;
• Presence of unmarked services;
• Risk of explosion due to gas line rupture;
• Risk of flooding of excavation and adjacent areas due to water main damage;
• Risk of electrocution or fire due to cable strike;
• Risk of hazardous waste entering excavation or water systems due to live sewerage damage;
• Risk of damage to low depth underground services from heavy vehicles;
• Risk of vehicles / Plant entering open excavation; 4 5 20
HIGH i. All existing utility service drawings reviewed for known service details and position;
ii. NOC and Utility provider and ATC Excavation permits to be completed, unique number added and recorded in log;
iii. Work Area, including access route for plant, to be CAT scanned to locate exact position of service by competent persons;
iv. Service clearly marked
Project Name: xxx
RA Ref No.: xxx
RA compilation Date: Review date:
Date:
Compiled by:
Reviewed by:
Approved by:
Overall Task Details
Sheet piling operations using mobile rig within site boundary.
To be read, if required, which RA010 – Excavations. Classed as Temporary Works Relevant Applicable MAS:
• 01412 – Lifting Operations;
• 00941 – Lifting equipment Additional Training required:
Noise monitoring;
Temporary Works Coordinator NOC’s Required for task:
Underground utility provider
RISK SCORE CALCULATOR
Use the Risk Score Calculator to Determine the Level of Risk of each Hazard
What would be the
CONSEQUENCE
of an occurrence be? What is the LIKELIHOOD of an occurrence? Hierarchy of Controls
Frequent/Almost certain (5)
Continuous or will happen frequently Often (4)
6 to 12 times a year Likely (3)
1 to 5 times a year Possible (2)
Once every 5 years Rarely (1)
Less than once every 5 years Can the hazard be Eliminated or removed from the work place?
Catastrophic (5)
Multiple Fatalities High 25 High 20 High 15 Medium 10 Medium 5 Can the product or process be substituted for a less hazardous alternative?
Serious (4)
Class 1 single fatality High 20 High 16 High 12 Medium 8 Low 4 Can the hazard be engineered away with guards or barriers?
Moderate (3)
Class2 (AWI or LTI) or Class 1 Permanently disabling effects High 15 High 12 Medium 9 Medium 6 Low 3 Can Administration Controls be adopted
I.e. procedures, job rotation etc.
Minor (2)
Medical attention needed, no work restrictions. MTI Medium10 Medium 8 Medium 6 Low 4 Low 2 Can Personal Protective Equipment & Clothing be worn to safe guard against hazards?
Insignificant (1)
FAI Medium10 Medium 4 Low 3 Low 2 Low 1
No Specific Task Step
(In sequence of works) Hazard Details Consequence/Risk Initial Risk Rating Control Measures Residual Risks Additional Control Measures RR
P S RR
1 Sheet piling Rig checks on arrival to site
PRIOR TO USE • Use of Sheet piling Rig • Unauthorized operation of the mobile rig resulting in incident;
• Failure due to use of un-certificated rig;
3 4 12
HIGH i. All Sheet piling rigs to be Third Party Certificated by a DM approved inspector, documentation available on arrival to site;
ii. Operators to have in-date Third Party certificate by approved body, available for review on arrival to site;
iii. Rig load indicator to be installed and functioning correctly;
iv. Visual inspection of rig undertaken by competent person; Documentation unavailable for review Rig quarantined until evidence provided Low
2 Access of rig and sheet pile delivery vehicles to work areas
• Plant and workers in same working area; • Collision with plant or vehicles and live traffic;
• Workers struck by plant, very high risk of fatality;
• Uncontrolled rig movements; i. Worker pedestrian routes to be designed and implemented with clear signage to provide segregation;
ii. Instruction to workers at induction on access routes around the project;
iii. Flagmen to be used t
Project Name: xxx
RA Ref No.: xxx
RA compilation Date: Review date:
Date:
Compiled by:
Reviewed by:
Approved by:
Overall Task Details
Temporary Falsework for formwork support. Classed as Temporary Works Relevant Applicable MAS:
• 01411 – MEWP’s;
• 00236 - Housekeeping Additional Training required:
Temporary Works Coordinator to be designated NOC’s Required for task:
RISK SCORE CALCULATOR
Use the Risk Score Calculator to Determine the Level of Risk of each Hazard
What would be the
CONSEQUENCE
of an occurrence be? What is the LIKELIHOOD of an occurrence? Hierarchy of Controls
Frequent/Almost certain (5)
Continuous or will happen frequently Often (4)
6 to 12 times a year Likely (3)
1 to 5 times a year Possible (2)
Once every 5 years Rarely (1)
Less than once every 5 years Can the hazard be Eliminated or removed from the work place?
Catastrophic (5)
Multiple Fatalities High 25 High 20 High 15 Medium 10 Medium 5 Can the product or process be substituted for a less hazardous alternative?
Serious (4)
Class 1 single fatality High 20 High 16 High 12 Medium 8 Low 4 Can the hazard be engineered away with guards or barriers?
Moderate (3)
Class2 (AWI or LTI) or Class 1 Permanently disabling effects High 15 High 12 Medium 9 Medium 6 Low 3 Can Administration Controls be adopted
I.e. procedures, job rotation etc.
Minor (2)
Medical attention needed, no work restrictions. MTI Medium10 Medium 8 Medium 6 Low 4 Low 2 Can Personal Protective Equipment & Clothing be worn to safe guard against hazards?
Insignificant (1)
FAI Medium10 Medium 4 Low 3 Low 2 Low 1
No Specific Task Step
(In sequence of works) Hazard Details Consequence/Risk Initial Risk Rating Control Measures Residual Risks Additional Control Measures RR
P S RR
1 Access to work areas by personnel and plant.
Material delivery to work area;
• Vehicles and workers in same working area;
• Storage of materials for falsework;
• Use of plant – forklift etc.; • Collision with plant or vehicles and live traffic;ac
• Workers struck by plant, very high risk of fatality;
• Workers struck by plant;
• Poor or unsafe storage, collapse;
• Untrained operators; 4 5 20
HIGH i. Worker pedestrian routes to be designed and implemented with clear signage;
ii. Instruction to workers at induction on use of access routes around the project;
iii. All plant and operators to be Third Party certificated by approved body;
iv. Flagmen to be used to control personnel (only on roads below 80kph);
v. Falsework materials stored correctly, no more than 2 pallets high and banded together when transporting;
vi. In traffic enclosed areas suitable welfare and first aid facilities shall be implemented to minimized worker movements;
vii. The Logistics plan shall clearly illustrate access and egress points; Workers not complying with controls All supervision to monitor operation;
Regular topic in TBT’s Low
2 Use of powered access equipment for assembly of false-work (if required) • Use of MEWP
(Mobile Elevated
RISK SCORE CALCULATOR
Use the Risk Score Calculator to Determine the Level of Risk of each Hazard
What would be the
CONSEQUENCE
of an occurrence be? What is the LIKELIHOOD of an occurrence? Hierarchy of Controls
Frequent/Almost certain (5)
Continuous or will happen frequently Often (4)
6 to 12 times a year Likely (3)
1 to 5 times a year Possible (2)
Once every 5 years Rarely (1)
Less than once every 5 years Can the hazard be Eliminated or removed from the work place?
Catastrophic (5)
Multiple Fatalities High 25 High 20 High 15 Medium 10 Medium 5 Can the product or process be substituted for a less hazardous alternative?
Serious (4)
Class 1 single fatality High 20 High 16 High 12 Medium 8 Low 4 Can the hazard be engineered away with guards or barriers?
Moderate (3)
Class2 (AWI or LTI) or Class 1 Permanently disabling effects High 15 High 12 Medium 9 Medium 6 Low 3 Can Administration Controls be adopted
I.e. procedures, job rotation etc.
Minor (2)
Medical attention needed, no work restrictions. MTI Medium10 Medium 8 Medium 6 Low 4 Low 2 Can Personal Protective Equipment & Clothing be worn to safe guard against hazards?
Insignificant (1)
FAI Medium10 Medium 4 Low 3 Low 2 Low 1
Project Name: xxx
RA Ref No.: xxx
RA compilation Date: Review date:
Date:
Compiled by:
Reviewed by:
Approved by:
Overall Task Details
Formation of deep cofferdam. Classed as Temporary Works
Use in conjunction with RA10 - Excavations Relevant Applicable MAS:
• 00246 – Excavations;
• 01413 – Underground services; Additional Training required:
Temporary Works Coordinator to be designated NOC’s Required for task:
Dubai Municipality
No Specific Task Step
(In sequence of works) Hazard Details Consequence/Risk Initial Risk Rating Control Measures Residual Risks Additional Control Measures RR
P S RR
1 Planned Cofferdam excavation in areas where live services may be present including:
• Electrical;
• Water;
• Sewerage;
• Gas;
• Telecoms;
PRIOR TO WORKS • Presence of live underground services;
• Services not in area specified on drawings;
• Heavy plant or vehicles accessing work area;
• Presence of unmarked services;
• Incorrect cofferdam design;
• Risk of explosion due to gas line rupture;
• Risk of flooding of excavation and adjacent areas due to water main damage;
• Risk of electrocution or fire due to cable strike;
• Risk of hazardous waste entering excavation or water systems due to live sewerage damage;
• Risk of damage to low depth underground services from heavy vehicles;
• Risk of vehicles / Plant entering open excavation; 4 5 20
HIGH i. All existing utility service drawings reviewed for known service details and position;
ii. NOC and Utility provider and HLG Excavation permits to be completed, unique number added and recorded in log;
iii. Work Area, including access route for plant, to be CAT scanned to locate exact position of service by competent persons;
iv. Service clearly marked on ground, using posts, tags etc.;
v. Any unidentified s
RISK SCORE CALCULATOR
Use the Risk Score Calculator to Determine the Level of Risk of each Hazard
What would be the
CONSEQUENCE
of an occurrence be? What is the LIKELIHOOD of an occurrence? Hierarchy of Controls
Frequent/Almost certain (5)
Continuous or will happen frequently Often (4)
6 to 12 times a year Likely (3)
1 to 5 times a year Possible (2)
Once every 5 years Rarely (1)
Less than once every 5 years Can the hazard be Eliminated or removed from the work place?
Catastrophic (5)
Multiple Fatalities High 25 High 20 High 15 Medium 10 Medium 5 Can the product or process be substituted for a less hazardous alternative?
Serious (4)
Class 1 single fatality High 20 High 16 High 12 Medium 8 Low 4 Can the hazard be engineered away with guards or barriers?
Moderate (3)
Class2 (AWI or LTI) or Class 1 Permanently disabling effects High 15 High 12 Medium 9 Medium 6 Low 3 Can Administration Controls be adopted
I.e. procedures, job rotation etc.
Minor (2)
Medical attention needed, no work restrictions. MTI Medium10 Medium 8 Medium 6 Low 4 Low 2 Can Personal Protective Equipment & Clothing be worn to safe guard against hazards?
Insignificant (1)
FAI Medium10 Medium 4 Low 3 Low 2 Low 1
Project Name: xxx
RA Ref No.: xxx
RA compilation Date: Review date:
Date:
Compiled by:
Reviewed by:
Approved by:
Overall Task Details
Excavation on site greater than 1.2 depth. Use of excavator
Note: Not under RTA Rail restrictions. Classed as Temporary Works Relevant Applicable MAS:
• 00246 – Excavations;
• 01413 – Underground services;
• 00940 – Plant Operators. Additional Training required:
Temporary Works Coordinator to be designated NOC’s Required for task:
Dubai Municipality
No Specific Task Step
(In sequence of works) Hazard Details Consequence/Risk Initial Risk Rating Control Measures Residual Risks Additional Control Measures RR
P S RR
1 Planned Excavation in areas where live services may be present including:
• Electrical;
• Water;
• Sewerage;
• Gas;
• Telecoms;
PRIOR TO WORKS • Presence of live underground services;
• Services not in area specified on drawings;
• Heavy plant or vehicles accessing work area;
• Presence of unmarked services;
• Risk of explosion due to gas line rupture;
• Risk of flooding of excavation and adjacent areas due to water main damage;
• Risk of electrocution or fire due to cable strike;
• Risk of hazardous waste entering excavation or water systems due to live sewerage damage;
• Risk of damage to low depth underground services from heavy vehicles;
• Risk of vehicles / Plant entering open excavation; 4 5 20
HIGH i. All existing utility service drawings reviewed for known service details and position;
ii. NOC and Utility provider and ATC Excavation permits to be completed, unique number added and recorded in log;
iii. Work Area, including access route for plant, to be CAT scanned to locate exact position of service by competent persons;
iv. Service clearly marked on ground, using posts, tags etc.;
v. Pla
Project Name: xxx
RA Ref No.: xxx
RA compilation Date: Review date:
Date:
Compiled by:
Reviewed by:
Approved by:
Overall Task Details
Temporary Formwork for formwork support. Classed as Temporary Works Relevant Applicable MAS:
• 01411 – MEWP’s;
• 00236 - Housekeeping Additional Training required:
Temporary Works Coordinator to be designated NOC’s Required for task:
RISK SCORE CALCULATOR
Use the Risk Score Calculator to Determine the Level of Risk of each Hazard
What would be the
CONSEQUENCE
of an occurrence be? What is the LIKELIHOOD of an occurrence? Hierarchy of Controls
Frequent/Almost certain (5)
Continuous or will happen frequently Often (4)
6 to 12 times a year Likely (3)
1 to 5 times a year Possible (2)
Once every 5 years Rarely (1)
Less than once every 5 years Can the hazard be Eliminated or removed from the work place?
Catastrophic (5)
Multiple Fatalities High 25 High 20 High 15 Medium 10 Medium 5 Can the product or process be substituted for a less hazardous alternative?
Serious (4)
Class 1 single fatality High 20 High 16 High 12 Medium 8 Low 4 Can the hazard be engineered away with guards or barriers?
Moderate (3)
Class2 (AWI or LTI) or Class 1 Permanently disabling effects High 15 High 12 Medium 9 Medium 6 Low 3 Can Administration Controls be adopted
I.e. procedures, job rotation etc.
Minor (2)
Medical attention needed, no work restrictions. MTI Medium10 Medium 8 Medium 6 Low 4 Low 2 Can Personal Protective Equipment & Clothing be worn to safe guard against hazards?
Insignificant (1)
FAI Medium10 Medium 4 Low 3 Low 2 Low 1
No Specific Task Step
(In sequence of works) Hazard Details Consequence/Risk Initial Risk Rating Control Measures Residual Risks Additional Control Measures RR
P S RR
1 Access to work areas by personnel and plant.
Material delivery to work area;
• Vehicles and workers in same working area;
• Storage of materials for formwork;
• Use of plant – forklift etc.; • Collision with plant or vehicles and live traffic;
• Workers struck by plant, very high risk of fatality;
• Workers struck by plant;
• Poor or unsafe storage, collapse;
• Untrained operators; 4 5 20
HIGH i. Worker pedestrian routes to be designed and implemented with clear signage;
ii. Instruction to workers at induction on use of access routes around the project;
iii. All plant and operators to be Third Party certificated by approved body;
iv. Flagmen to be used to control personnel (only on roads below 80kph);
v. Formwork materials stored correctly, no more than 2 pallets high and banded together when transporting;
vi. In traffic enclosed areas suitable welfare and first aid facilities shall be implemented to minimized worker movements;
vii. The Logistics plan shall clearly illustrate access and egress points; Workers not complying with controls All supervision to monitor operation;
Regular topic in TBT’s Low
`3 Formwork installation
(Classified as Temporary Structures) • Works at Height;
• Manual Handling;
• Worker c
8 Lifting Operations with mobile crane Risk Assessment Templates.docxDwarika Bhushan Sharma
Project Name: xxx
RA Ref No.: xxx
RA compilation Date: Review date:
Date:
Compiled by:
Reviewed by:
Approved by:
Overall Task Details
Lifting operations using mobile crane within site boundary Relevant Applicable MAS:
• 01412 – Lifting Operations;
• 00941 – Lifting equipment Additional Training required:
Riggers / Slingers NOC’s Required for task:
RISK SCORE CALCULATOR
Use the Risk Score Calculator to Determine the Level of Risk of each Hazard
What would be the
CONSEQUENCE
of an occurrence be? What is the LIKELIHOOD of an occurrence? Hierarchy of Controls
Frequent/Almost certain (5)
Continuous or will happen frequently Often (4)
6 to 12 times a year Likely (3)
1 to 5 times a year Possible (2)
Once every 5 years Rarely (1)
Less than once every 5 years Can the hazard be Eliminated or removed from the work place?
Catastrophic (5)
Multiple Fatalities High 25 High 20 High 15 Medium 10 Medium 5 Can the product or process be substituted for a less hazardous alternative?
Serious (4)
Class 1 single fatality High 20 High 16 High 12 Medium 8 Low 4 Can the hazard be engineered away with guards or barriers?
Moderate (3)
Class2 (AWI or LTI) or Class 1 Permanently disabling effects High 15 High 12 Medium 9 Medium 6 Low 3 Can Administration Controls be adopted
I.e. procedures, job rotation etc.
Minor (2)
Medical attention needed, no work restrictions. MTI Medium10 Medium 8 Medium 6 Low 4 Low 2 Can Personal Protective Equipment & Clothing be worn to safe guard against hazards?
Insignificant (1)
FAI Medium10 Medium 4 Low 3 Low 2 Low 1
No Specific Task Step
(In sequence of works) Hazard Details Consequence/Risk Initial Risk Rating Control Measures Residual Risks Additional Control Measures RR
P S RR
1 Crane checks on arrival to site
PRIOR TO USE • Use of mobile crane • Unauthorized operation of the mobile crane resulting in incident;
• Failure due to use of un-certificated crane;
3 4 12
HIGH i. All cranes to be Third Party Certificated by a DM approved inspector, documentation available on arrival to site;
ii. Operators to have in-date Third Party certificate by approved body, available for review on arrival to site;
iii. Crane load indicator to be installed and functioning correctly;
iv. Visual inspection of crane undertaken by competent person; Documentation unavailable for review Crane quarantined until evidence provided Low
2 Access of crane to work areas
• Plant and workers in same working area; • Collision with plant or vehicles and live traffic;
• Workers struck by plant, very high risk of fatality;
• Uncontrolled crane reversing; i. Worker pedestrian routes to be designed and implemented with clear signage to provide segregation;
ii. Instruction to workers at induction on use of access routes around the project;
iii. Flagmen to be used to control crane movements;
iv. The Logistics plan shall clearly illustrate crane access and egress points; Workers not complying with flagmen Regular topic in TBT’s Low
3 Siti
Establishing exclusion zones • Personnel in area • Unauthorized access to test area;
• Workers struck by flying materials;
• Worker struck by High pressure water release;
Signage to test area • Personnel in area • Unauthorized access to test area;
• Inadequate signage to test area;
Pressure testing • High pressure to pipework; • Uncontrolled Stored Energy release;
• Rupture/failure in Pipe lines during testing;
• Valve/connection failure;
• Instrument failure resulting in system over-pressurization;
• End caps/plugs ejecting under high pressure;
• Weld/seal/fitting failure, flying objects;
• High pressure water/air injection.
Emergency procedures • High pressure to pipework; • Emergency procedures not briefed to task workers;
• Poor response in the event of an emergency;
Re-testing in the event of failure • Re-testing with high pressure • Injury due to uncontrolled testing;
• Worker injury due to working on pressurized system;
• Injury due to failure to ensure adequate pre-checks undertaken;
20 Use of Suspended Access cradles and Platforms (Temporary Works) Risk Asses...Dwarika Bhushan Sharma
Project Name: xxx
RA Ref No.: xxx
RA compilation Date: Review date:
Date:
Compiled by:
Reviewed by:
Approved by:
Overall Task Details
Use of Suspended access cradles and platforms
Relevant Applicable MAS:
• 0242 – Suspended access cradles and platforms Additional Training required:
NOC’s Required for task:
RISK SCORE CALCULATOR
Use the Risk Score Calculator to Determine the Level of Risk of each Hazard
What would be the
CONSEQUENCE
of an occurrence be? What is the LIKELIHOOD of an occurrence? Hierarchy of Controls
Frequent/Almost certain (5)
Continuous or will happen frequently Often (4)
6 to 12 times a year Likely (3)
1 to 5 times a year Possible (2)
Once every 5 years Rarely (1)
Less than once every 5 years Can the hazard be Eliminated or removed from the work place?
Catastrophic (5)
Multiple Fatalities High 25 High 20 High 15 Medium 10 Medium 5 Can the product or process be substituted for a less hazardous alternative?
Serious (4)
Class 1 single fatality High 20 High 16 High 12 Medium 8 Low 4 Can the hazard be engineered away with guards or barriers?
Moderate (3)
Class2 (AWI or LTI) or Class 1 Permanently disabling effects High 15 High 12 Medium 9 Medium 6 Low 3 Can Administration Controls be adopted
I.e. procedures, job rotation etc.
Minor (2)
Medical attention needed, no work restrictions. MTI Medium10 Medium 8 Medium 6 Low 4 Low 2 Can Personal Protective Equipment & Clothing be worn to safe guard against hazards?
Insignificant (1)
FAI Medium10 Medium 4 Low 3 Low 2 Low 1
No Specific Task Step
(In sequence of works) Hazard Details Consequence/Risk Initial Risk Rating Control Measures Residual Risks Additional Control Measures RR
P S RR
1 Cradle checks on arrival to site
PRIOR TO USE • Use of Access equipment • Failure due to use of un-certificated plant;
3 4 12
HIGH i. All plant to be Third Party Certificated by a DM approved inspector, documentation available on arrival to site (6 monthly check);
ii. Visual inspection of MEWP undertaken by competent person; Documentation unavailable for review Plant quarantined until evidence provided Low
2 Pre-use checks of suspended access cradle or platform • Work at Height; • Collapse of cradle through damage or failure of equipment;
• Falling materials;
4 5 20 HIGH i. Method statements and risk assessments to be submitted and adhered to;
ii. The safe working load must be clearly marked on the cradle and shall not be exceeded;
iii. It is erected and installed by a competent person, following the manufacturer’s instructions;
iv. An independent life line rope/wire and rope grabbing device installed;
v. All safety devices and controls are operating correctly;
vi. There are no visible signs of damage to the cradle and corresponding supports, tracks/runways;
vii. The ropes are free from damage and are correctly weaved through the drum and pulleys;
viii. Floors and guard rails are rigid and free from defects;
ix. All landing wheels must be attached and intact;
x. A
PRIOR TO / AT SITE DELIVERY • Hazardous substances
Storage • Storage of Substance potentially hazardous to worker health or to the environment;
Use of substances and chemicals on site • Use of Substances potentially hazardous to worker health or the environment;
Emergency procedures • Action to be taken in an emergency
Disposal of waste skips • Disposal of out of date substances;
• Disposal of used/empty containers;
Project Name: xxx
RA Ref No.: xxx
RA compilation Date: Review date:
Date:
Compiled by:
Reviewed by:
Approved by:
Overall Task Details
Hydrostatic pressure testing of pipework inside buildings Relevant Applicable MAS:
• Additional Training required:
NOC’s Required for task:
RISK SCORE CALCULATOR
Use the Risk Score Calculator to Determine the Level of Risk of each Hazard
What would be the
CONSEQUENCE
of an occurrence be? What is the LIKELIHOOD of an occurrence? Hierarchy of Controls
Frequent/Almost certain (5)
Continuous or will happen frequently Often (4)
6 to 12 times a year Likely (3)
1 to 5 times a year Possible (2)
Once every 5 years Rarely (1)
Less than once every 5 years Can the hazard be Eliminated or removed from the work place?
Catastrophic (5)
Multiple Fatalities High 25 High 20 High 15 Medium 10 Medium 5 Can the product or process be substituted for a less hazardous alternative?
Serious (4)
Class 1 single fatality High 20 High 16 High 12 Medium 8 Low 4 Can the hazard be engineered away with guards or barriers?
Moderate (3)
Class2 (AWI or LTI) or Class 1 Permanently disabling effects High 15 High 12 Medium 9 Medium 6 Low 3 Can Administration Controls be adopted
I.e. procedures, job rotation etc.
Minor (2)
Medical attention needed, no work restrictions. MTI Medium10 Medium 8 Medium 6 Low 4 Low 2 Can Personal Protective Equipment & Clothing be worn to safe guard against hazards?
Insignificant (1)
FAI Medium10 Medium 4 Low 3 Low 2 Low 1
No Specific Task Step
(In sequence of works) Hazard Details Consequence/Risk Initial Risk Rating Control Measures Residual Risks Additional Control Measures RR
L C RR
1 Pressure testing equipment • Use at high pressure; • Rupture/failure of pump during testing;
• Valve/connection failure;
• Instrument failure resulting in system over-pressurization;
3 3 9 MED i. The supervisor in charge of the test shall ensure that all pressure testing gauges etc. are in good sound condition, undamaged, correctly dated with the current valid calibration and that appropriate calibration certificates are available;
ii. All pumps shall be in sound condition and complete with a valid test certificate. Any vulnerable items such as manometers and pressure switches shall be removed or isolated from the system prior to testing if not required;
iii. The test supervisor shall carry out a thorough inspection of the system before requesting the permit detailed above to ensure that all isolations, blanks and other specified safety devices are in place before testing commences; No test documentation available Quarantine equipment until valid documentation provided Low
2 Permit to work system • Interaction of personnel and high pressure system; • Injury due to uncontrolled testing;
• Injury due to failure to ensure adequate pre-checks undertaken; 3 4 12 HIGH i. All pressure testing operations shall require a Permit to Work to ensure that no pressure testing will be allowed to commence until all,
19 Use of Mobile Elevated Work Platforms Risk Assessment Templates.docxDwarika Bhushan Sharma
Project Name: xxx
RA Ref No.: xxx
RA compilation Date: Review date:
Date:
Compiled by:
Reviewed by:
Approved by:
Overall Task Details
Use of plant – Mobile Elevated Work Platforms
Cherry pickers or Scissor Lifts Relevant Applicable MAS:
• 01411 – MEWPs;
• 00940 – Plant Operators; Additional Training required:
NOC’s Required for task:
RISK SCORE CALCULATOR
Use the Risk Score Calculator to Determine the Level of Risk of each Hazard
What would be the
CONSEQUENCE
of an occurrence be? What is the LIKELIHOOD of an occurrence? Hierarchy of Controls
Frequent/Almost certain (5)
Continuous or will happen frequently Often (4)
6 to 12 times a year Likely (3)
1 to 5 times a year Possible (2)
Once every 5 years Rarely (1)
Less than once every 5 years Can the hazard be Eliminated or removed from the work place?
Catastrophic (5)
Multiple Fatalities High 25 High 20 High 15 Medium 10 Medium 5 Can the product or process be substituted for a less hazardous alternative?
Serious (4)
Class 1 single fatality High 20 High 16 High 12 Medium 8 Low 4 Can the hazard be engineered away with guards or barriers?
Moderate (3)
Class2 (AWI or LTI) or Class 1 Permanently disabling effects High 15 High 12 Medium 9 Medium 6 Low 3 Can Administration Controls be adopted
I.e. procedures, job rotation etc.
Minor (2)
Medical attention needed, no work restrictions. MTI Medium10 Medium 8 Medium 6 Low 4 Low 2 Can Personal Protective Equipment & Clothing be worn to safe guard against hazards?
Insignificant (1)
FAI Medium10 Medium 4 Low 3 Low 2 Low 1
No Specific Task Step
(In sequence of works) Hazard Details Consequence/Risk Initial Risk Rating Control Measures Residual Risks Additional Control Measures RR
P S RR
1 MEWP checks on arrival to site
PRIOR TO SITE ACCESS • Use of Access plant • Unauthorized operation of the plant resulting in incident;
• Failure due to use of un-certificated plant;
3 4 12
HIGH i. All plant to be Third Party Certificated by a DM approved inspector, documentation available on arrival to site (6 monthly check);
ii. MEWP Operators to have in-date Third Party certificate by approved body, available for review on arrival to site;
iii. Visual inspection of MEWP undertaken by competent person; Documentation unavailable for review Plant quarantined until evidence provided Low
2 MEWP operation
(Operator) • Operator competency;
• Plant / pedestrian interaction;
• Work at Height; • Incident due to use of defective plant or associated equipment;
• MEWP overturning;
• Plant reversing – risk of serious injury to pedestrians;
• Unauthorized use of MEWP by untrained personnel;
• Operators climbing onto hand rails;
• Collision with other plant and live traffic within site boundary;
• Workers struck by working MEWP, very high risk of fatality;
• Falling materials;
4 4 16 HIGH i. Method statements and risk assessments to be submitted and adhered to;
ii. All MEWP operators to follow designated traffic routes, which should be level and compac
Project Name: xxx
RA Ref No.: xxx
RA compilation Date: Review date:
Date:
Compiled by:
Reviewed by:
Approved by:
Overall Task Details
Concrete Column using formwork Relevant Applicable MAS:
• 01412 – Lifting operations cranes;
• 00245 – Mobile scaffolds; Additional Training required:
Temporary Works Coordinator nominated NOC’s Required for task:
RISK SCORE CALCULATOR
Use the Risk Score Calculator to Determine the Level of Risk of each Hazard
What would be the
CONSEQUENCE
of an occurrence be? What is the LIKELIHOOD of an occurrence? Hierarchy of Controls
Frequent/Almost certain (5)
Continuous or will happen frequently Often (4)
6 to 12 times a year Likely (3)
1 to 5 times a year Possible (2)
Once every 5 years Rarely (1)
Less than once every 5 years Can the hazard be Eliminated or removed from the work place?
Catastrophic (5)
Multiple Fatalities High 25 High 20 High 15 Medium 10 Medium 5 Can the product or process be substituted for a less hazardous alternative?
Serious (4)
Class 1 single fatality High 20 High 16 High 12 Medium 8 Low 4 Can the hazard be engineered away with guards or barriers?
Moderate (3)
Class2 (AWI or LTI) or Class 1 Permanently disabling effects High 15 High 12 Medium 9 Medium 6 Low 3 Can Administration Controls be adopted
I.e. procedures, job rotation etc.
Minor (2)
Medical attention needed, no work restrictions. MTI Medium10 Medium 8 Medium 6 Low 4 Low 2 Can Personal Protective Equipment & Clothing be worn to safe guard against hazards?
Insignificant (1)
FAI Medium10 Medium 4 Low 3 Low 2 Low 1
No Specific Task Step
(In sequence of works) Hazard Details Consequence/Risk Initial Risk Rating Control Measures Residual Risks Additional Control Measures RR
L C RR
1 Concrete Pump checks on arrival to site
PRIOR TO SITE ACCESS • Use of mobile concrete pump • Unauthorized operation of the mobile pump resulting in incident;
• Failure due to use of un-certificated pump;
3 4 12
HIGH i. All mobile concrete pumps to be Third Party Certificated by a DM approved inspector, documentation available on arrival to site;
ii. Operators to have in-date Third Party certificate by approved body, available for review on arrival to site;
iii. Visual inspection of pump undertaken by competent person; Documentation unavailable for review Pump quarantined until evidence provided Low
2. Formwork for columns • Erection of formwork;
• Works at Height; • Injury from Fall from Heights;
• Injury from falling objects;
• Manual Handling injuries;
• Incorrect Design and Erection of formwork resulting in collapse;
• Use of unsupervised or untrained personnel to erect formwork;
• Erection of Formwork; 4 4 16 HIGH i. If required for lifting formwork into position, use of mobile crane as per RA012 – Mobile crane, or RA013 – Tower Crane as applicable;
ii. Safety harness and lanyard are to be used and hooked off to a secure anchor point when working around exposed edges; No shock lanyard to be used below 6m in height;
iii. All
It is well known that wastewater treatment projects worldwide has become one of the most
important, vital projects and linked to civilization. Since potable water and irrigation for agriculture water
considered a very low resources in the Kingdom of Saudi Arabia - desert regions - soit is necessary to pay more
attention to these projects, which already happened, where billions of Saudi Riyals have been invested in the
sewage and industrial water treatment projects.
Wastewater treatment industryin Saudi Arabiahas expanded to include a lot of units and departments, machines
and hundreds of workers and has become a danger to staff and the areas surrounding these stations.
In this research we mention the steps and methods to be used and followed by workers in dealing with the
various hazards. We start by identifying the hazards then point out how to analyze these hazards and classified
into several degrees according totheir severity.
Project Name: xxx
RA Ref No.: xxx
RA compilation Date: Review date:
Date:
Compiled by:
Reviewed by:
Approved by:
Overall Task Details
Piling operations using mobile rig and rebar installation within site boundary. Use in conjunction with RA012 - Use of Mobile Crane and RA014 – Use of Concrete Pump. Relevant Applicable MAS:
• 01412 – Lifting Operations;
• 00941 – Lifting equipment Additional Training required:
Noise monitoring NOC’s Required for task:
Underground utility provider
RISK SCORE CALCULATOR
Use the Risk Score Calculator to Determine the Level of Risk of each Hazard
What would be the
CONSEQUENCE
of an occurrence be? What is the LIKELIHOOD of an occurrence? Hierarchy of Controls
Frequent/Almost certain (5)
Continuous or will happen frequently Often (4)
6 to 12 times a year Likely (3)
1 to 5 times a year Possible (2)
Once every 5 years Rarely (1)
Less than once every 5 years Can the hazard be Eliminated or removed from the work place?
Catastrophic (5)
Multiple Fatalities High 25 High 20 High 15 Medium 10 Medium 5 Can the product or process be substituted for a less hazardous alternative?
Serious (4)
Class 1 single fatality High 20 High 16 High 12 Medium 8 Low 4 Can the hazard be engineered away with guards or barriers?
Moderate (3)
Class2 (AWI or LTI) or Class 1 Permanently disabling effects High 15 High 12 Medium 9 Medium 6 Low 3 Can Administration Controls be adopted
I.e. procedures, job rotation etc.
Minor (2)
Medical attention needed, no work restrictions. MTI Medium10 Medium 8 Medium 6 Low 4 Low 2 Can Personal Protective Equipment & Clothing be worn to safe guard against hazards?
Insignificant (1)
FAI Medium10 Medium 4 Low 3 Low 2 Low 1
No Specific Task Step
(In sequence of works) Hazard Details Consequence/Risk Initial Risk Rating Control Measures Residual Risks Additional Control Measures RR
L C RR
1 Piling Rig checks on arrival to site
PRIOR TO USE • Use of Piling Rig • Unauthorized operation of the mobile rig resulting in incident;
• Failure due to use of un-certificated rig;
3 4 12
HIGH i. All Piling rigs to be Third Party Certificated by a DM approved inspector, documentation available on arrival to site;
ii. Operators to have in-date Third Party certificate by approved body, available for review on arrival to site;
iii. Rig load indicator to be installed and functioning correctly;
iv. Visual inspection of rig undertaken by competent person; Documentation unavailable for review Rig quarantined until evidence provided Low
2 Access of rig and delivery vehicles to work areas
• Plant and workers in same working area; • Collision with plant or vehicles and live traffic;
• Workers struck by plant, very high risk of fatality;
• Uncontrolled rig movements; i. Worker pedestrian routes to be designed and implemented with clear signage to provide segregation;
ii. Instruction to workers at induction on use of access routes around the project;
iii. Flagmen to be used to control rig movements;
iv.
Project Name: xxx
RA Ref No.: xxx
Review date:
Date:
Compiled by:
Reviewed by:
Approved by:
Overall Task Details
Concrete slabs using formwork and falsework Relevant Applicable MAS:
• 01412 – Lifting operations cranes; Additional Training required:
Temporary Works Coordinator nominated NOC’s Required for task:
RISK SCORE CALCULATOR
Use the Risk Score Calculator to Determine the Level of Risk of each Hazard
What would be the
CONSEQUENCE
of an occurrence be? What is the LIKELIHOOD of an occurrence? Hierarchy of Controls
Frequent/Almost certain (5)
Continuous or will happen frequently Often (4)
6 to 12 times a year Likely (3)
1 to 5 times a year Possible (2)
Once every 5 years Rarely (1)
Less than once every 5 years Can the hazard be Eliminated or removed from the work place?
Catastrophic (5)
Multiple Fatalities High 25 High 20 High 15 Medium 10 Medium 5 Can the product or process be substituted for a less hazardous alternative?
Serious (4)
Class 1 single fatality High 20 High 16 High 12 Medium 8 Low 4 Can the hazard be engineered away with guards or barriers?
Moderate (3)
Class2 (AWI or LTI) or Class 1 Permanently disabling effects High 15 High 12 Medium 9 Medium 6 Low 3 Can Administration Controls be adopted
I.e. procedures, job rotation etc.
Minor (2)
Medical attention needed, no work restrictions. MTI Medium10 Medium 8 Medium 6 Low 4 Low 2 Can Personal Protective Equipment & Clothing be worn to safe guard against hazards?
Insignificant (1)
FAI Medium10 Medium 4 Low 3 Low 2 Low 1
No Specific Task Step
(In sequence of works) Hazard Details Consequence/Risk Initial Risk Rating Control Measures Residual Risks Additional Control Measures RR
L C RR
1 Concrete Pump checks on arrival to site
PRIOR TO SITE ACCESS • Use of mobile concrete pump • Unauthorized operation of the mobile pump resulting in incident;
• Failure due to use of un-certificated pump;
3 4 12
HIGH i. All mobile concrete pumps to be Third Party Certificated by a DM approved inspector, documentation available on arrival to site;
ii. Operators to have in-date Third Party certificate by approved body, available for review on arrival to site;
iii. Visual inspection of pump undertaken by competent person; Documentation unavailable for review Pump quarantined until evidence provided Low
2. Formwork for slab for temporary support • Erection of formwork;
• Works at Height; • Injury from Fall from Heights;
• Injury from falling objects;
• Manual Handling injuries;
• Incorrect Design and Erection of formwork resulting in collapse;
• Use of unsupervised or untrained personnel to erect formwork;
• Erection of Formwork; 4 4 16 HIGH i. If required for lifting formwork into position, use of mobile crane as per RA012 – Mobile crane, or RA013 – Tower Crane as applicable;
ii. Safety harness and lanyard are to be used and hooked off to a secure anchor point when working around exposed edges; No shock lanyard to be used below 6m in height;
iii. All hand tools to b
Similar to 21 confined space working risk assessment templates (19)
Project Information:
Project Name:
Location: Supervisor :
Company name : Date:
Task Description:
Before work starts, the following must be in place
Induction Supervision Test Certificates Communication in same language Method Statement Risk Assessment Permit To Work Area Lighting
SELECT HAZARDS SELECT CONTROLS
( Tick to identify the controls in place)
Fall from height Training Access Ladder Access Handrail Edge Protection Secure Ladder Adequate Work Platform Guards for Openings Safety Harness Life Lines
Others( Specify)
Manual Handling Training Check Weight Mechanical Aids Access Route Team Lifting Wrong method Right Method
Power tools Training Color code inspection tag Check Cable Wheel guards Safe plug & sockets Cable Protection Proper Scaffold Cable Overhead Rotatory part guards
Scaffold Scaffold Tag Edge Protection Check Overhead works Access Ladder Adequate Work Platform Weather condition Out riggers Ladder 3 feet above platform Safety Harness
SELECT HAZARDS SELECT CONTROLS
( Tick to identify the controls in place)
Risk Assessment
Lifting Plan Tag Lines Lifting points / hooks Banks man Load stability Check Lifting gear Examination /Inspection Sharp edges protected
Lifting operations Weather/ Wind Speed Ground conditions Exclusion zone Communication Loading/ unloading vehicles Spreader Beams Check Ground conditions Check outriggers Others
Fire Fire Extinguisher Fire Hose Fire Exit Assembly point others
Slip/Trip Clean before you go Barricade the waste Waste Management Clean Access Housekeeping Clean liquid spillage Access signs Maintain access/ Egress
PPE
Safety Harness
Safety Helmet Coveralls Hi vis Jacket Safety Shoe Face Shield Ear Protection
Dust mask Respiratory Equipment Life line/ harness anchorage Hand Gloves Goggles/ Glass
Pre start Briefing done by: Signature:
Reviewed By HSE Manager/ In charge: Signature:
1. Project Information:
Project Name: Checklist No.:
Sub-Contractor/Company:
Date:
2. Task Details:
Description of Task:
Location / Area :
Number of Workers:
Task Duration:
Time (from): _______Hrs.
Time (To): __________Hrs.
Date:
3. Prerequisites:
Checks Yes-No-NA Checks Yes-No-NA
Safety induction done. ☐ ☐ ☐
Safety tool box talk done. ☐ ☐ ☐
Method statement/Risk assessment in place. ☐ ☐ ☐
Training on Risk Assessment/ Method Statement done ☐ ☐ ☐
Job Safety Analysis done. ☐ ☐ ☐
3 Month Safety Look Ahead in place ☐ ☐ ☐
Permit to Work obtained ☐ ☐ ☐
Site Supervisor available ☐ ☐ ☐
PPE Available ☐ ☐ ☐
Working area is well lighted ☐ ☐ ☐
Tools and equipment inspected and tagged ☐ ☐ ☐
Unsafe conditions rectified ☐ ☐ ☐
Pre-Start Checks completed ☐ ☐ ☐
Emergency procedures communicated ☐ ☐ ☐
Unauthorized workers are cleared from the area.
☐ ☐ ☐
Other ( Specify): ☐ ☐ ☐
4. Acknowledgement by Sub-Contractor:
☐ Acknowledge that all above precautions/ controls measures have been taken. These have also been fully explained to the operatives, and I consider them competent to do it safely.
Initiator/Originator Name: Designation:
Signature: Date /Time:
Signature: Date /Time
Project Information
Project Name: Store No.
Location: Contact Person:
Company Name: Arabtec Construction LLC. Date:
Sr. Description Yes No N/A Comments
1. Is access to stores are restricted to authorized personnel only?
2. Are there clear spaces around racks and stacks of stored materials and are adequate gangways provided between them?
3. Are stacks and storage kept clear of light fittings and hot surfaces?
4. Are all stocks of flammable liquids kept in purpose-built flammable storage liquid stores?
5. Are storage areas generally cleaned and tidy?
6. Are flammable liquids kept away from all possible sources of ignition?
7. Emergency exit signs are available in right locations
8. Smoke detectors/fire alarm are visible and accessible.
9. Fire extinguishers are available are serviced regularly
10. Are free standing shelves and cupboards secured for stability?
11. Are heavy items stored at a suitable height?
12. Are chemical containers used for storage suitable and clearly labelled?
13. Is there adequate light in the storage area?
14. Are all small loose items secured in appropriate storage?
15. Are warning notices, prohibiting smoking and naked lights prominently displayed?
16. Others if any:
Remarks:
Inspected by: Signature:
Reviewed by Project Manager/HSE Manager Signature:
PROJECT:
LOCATION: DATE:
I (name)_____________________________________would like provide my statement as follows on.
I hereby acknowledge that the above statement are true to the best of my recollection, and that these are my very own written down by m myself s others _________Name and Signature________
Name : ____________________________ Signature: ______________________
Position: _________________________________________Date:_________________
1. Project Information:
Project Name: Click here to enter text.
Report No.: Click here to enter text.
Project Location: Click here to enter text.
Property No.: Click here to enter text.
☐ Fatality ☐ Major Injury ☐ Minor Injury ☐ Property Damage ☐ Environmental ☐ Other
2. Describe the Incident in detail:
Answer who, what, why, where, when & how in this section: (Attach additional pages if required)
3. Incident Root Causes:
Describe direct, indirect & root cause: (Attach additional pages if required)
4. Key Corrections Taken Immediately after the Incident:
Attach additional pages if more space is required:
5. Key Corrective Actions to Prevent Recurrence:
Describe the corrective actions with timeframe: (Attach additional pages if required)
Corporate Office Remarks:
1. Project Information: (To be filled by initiator/originator)
Project Name: Permit No.:
Project Location:
Requesting Contractor/Company
2. Permit Issuance Details: (To be filled by initiator/originator)
THIS PERMIT IS ONLY FOR ONE SHIFT AND NOT EXTENDABLE
Description of Task:
Detail of Surroundings:
Permit Validity:
Time (from): __________Hrs.
Time (To): __________Hrs.
Date:
3. Control Measures: (To be filled by initiator/originator and verified by Evaluator)
Checks Yes-No-NA Checks Yes-No-NA
Method statement & Risk assessment developed, approved & communicated? ☐ ☐ ☐
Availability of rescue procedure and equipment? ☐ ☐ ☐
Operatives are trained and competent? ☐ ☐ ☐
Workplace appropriately illuminated ☐ ☐ ☐
Any high risk activity associated that requires PTW (i.e. hot work, CSE)? ☐ ☐ ☐
Forced ventilation provided? ☐ ☐ ☐
Are all necessary Permit approved and displayed at work location? ☐ ☐ ☐
Means of communication available? (Mobile, radio etc.) ☐ ☐ ☐
Safe access / Working Platform provided? ☐ ☐ ☐
Mandatory/specific good condition PPEs are available ☐ ☐ ☐
Availability of barricades/protection to prevent unauthorized or accidental entry? ☐ ☐ ☐
Life Line provided? ☐ ☐ ☐
Warning signs posted? ☐ ☐ ☐
Fall Protection equipment (e.g. full body harness) available? ☐ ☐ ☐
Availability of Fall protection arrangement? ☐ ☐ ☐
Other(s): ☐ ☐ ☐
Adequate Lighting provided? ☐ ☐ ☐
☐ ☐ ☐
4. Acknowledgement by Initiator and Evaluator:
☐ Acknowledge that all above precautions have been taken. These have also been fully explained to the operatives, and I consider them competent to do it safely.
Initiator/Originator Name: Designation:
Signature: Time:
☐ Acknowledge that I have checked above control measures and consider the work area safe to carry out the activity
Evaluator (HSE Team): Designation:
Signature: Time
Comments (if any):
5. Authorization (PM/CM):
Name: Designation:
Signature: Time:
6. Completion/Cancelation of Permit:
☐ Acknowledge that the area have been restored to a safe and orderly condition.
Initiator Signature: Time:
☐ Acknowledge that I have checked the area and been restored to a safe and orderly condition.
Evaluator Signature: Time:
1. Project Information: (To be filled by initiator/originator)
Project Name: Permit No.:
Project Location:
Requesting Contractor/Company
2. Permit Issuance Details: (To be filled by initiator/originator)
THIS PERMIT IS ONLY FOR ONE SHIFT AND NOT EXTENDABLE
Description of Task:
Location / Area :
Panel No : Voltage:
Permit Validity:
Time (from): _______Hrs.
Time (To): __________Hrs.
Date:
3. Prerequisites: (To be filled by initiator/originator and verified by Evaluator)
No: Checks Yes-No-NA Checks Yes-No-NA
ENERGIZATION (“Power On”) ISOLATION (“Power Off”)
1. Safety tool box briefing done. ☐ ☐ ☐
Method statement/Risk assessment in place. ☐ ☐ ☐
2. Authorized personnel / operators available. ☐ ☐ ☐
Authorized personnel / operators available. ☐ ☐ ☐
3. Method statement/Risk assessment in place. ☐ ☐ ☐
Adjacent live areas protected. ☐ ☐ ☐
4. Safety Barriers in place and safety signage Displayed. ☐ ☐ ☐
PPE available, high voltage rubber gloves, Safety goggles and floor mat. ☐ ☐ ☐
5. Working area is well lighted. ☐ ☐ ☐
Isolation/Lock-out in place. ☐ ☐ ☐
6. Electrical instruments are available for any Purpose. ☐ ☐ ☐
Electrical circuits “proved” by calibrated Instrument and found out to be no power. ☐ ☐ ☐
7. Correct PPE available, high voltage rubber Gloves, safety goggles and floor mat. ☐ ☐ ☐
Unauthorized workers are cleared from the Area. ☐ ☐ ☐
8. Approved WIR for installation, testing and Termination are attached to the permit. ☐ ☐ ☐
Standby operatives in the event of contact With live circuits. ☐ ☐ ☐
9. Emergency light (Flashlight) available. ☐ ☐ ☐
Emergency light (Flashlight) available. ☐ ☐ ☐
10. Is live work absolutely necessary? ☐ ☐ ☐
Emergency response plan available ☐ ☐ ☐
11. Unauthorized workers are cleared from the area.
☐ ☐ ☐
Other ( Specify): ☒ ☐ ☐
12. Power cable route from panel board to plant & equipment has been checked ☐ ☐ ☐
13 Emergency response plan available ☐ ☐ ☐
14 Other ( Specify): ☐ ☐ ☐
4. Acknowledgement by Initiator and Evaluator:
☐ Acknowledge that all above precautions have been taken. These have also been fully explained to the operatives, and I consider them competent to do it safely.
Initiator/Originator Name: Designation:
Signature: Date /Time:
☐ Acknowledge that I have checked above control measures and consider the work area safe to carry out the activity
Evaluator (HSE Team): Designation:
Signature: Date /Time
Comments (if any):
5. Authorization (PM/CM):
Name: Designation:
Signature: Date /Time:
6. Completion/Cancelation of Permit:
☐ Acknowledge that the area have been restored to a safe and orderly condition.
Initiator Signature: Time:
☐ Acknowledge that I have checked the area and been restored to a safe and orderly condition.
Evaluator Signature: Time:
Project Information
Project Name:
Date: Location:
Sr. Equipment type / Name Registration No & Exp Date Company Name
Operator Name / Mb. No Operator Third party competency certificate expiry date Operator License expiry date Equipment & Plant 3rd Party Inspection Certificate expiry date SWL / Capacity Signalman /Rigger name & TPC Exp Comment
1
2
3
4
5
6
7
8
9
10.
Remarks:
Inspected By: Signature:
Reviewed By HSE Manager / In charge: Signature:
Accommodation Name: Date :
Accommodation Location: Time :
SN Description Yes NO N/A Observation Control
Measures Due Date
ACCESS AND EGRESS
1 Is there segregation between vehicles/ pedestrians
2 Is entry to inside camp restricted to workforce only? How is this controlled
3 Is the entrance well lit
4 Is the entrance free from water pooling
GENERAL HOUSEKEEPING
1 Are there adequate dustbins available? Are they covered
2 Is garbage disposed of on a regular basis?
3 Are toilets wash areas cleaned regular?
4 Is there adequate water for toilet and bath
5 Are water tanks kept covered at all times
6 Is soap and hand towels available?
7 Is bathroom area cleaned on a regular basis and kept dry and non-slippery
8 Is the water tank cleaned on a regular basis
9 Is the laundry area electrical & connections/ wires are in good condition.
10 Is the laundry area kept clean and dry
11 Is the tumble dryer filters cleaned frequently to prevent overheating
SEPTIC TANKS
1 Is the camp on main drainage?
2 If not are septic tanks provided?
3 Are septic tanks fitted with overflow alarm if not how are they prevented from overflowing
4 If septic tank in ground is it in a membrane?
5 If above ground is it protected from being hit by vehicular traffic?
FOOD PREPARATION AREA
1 Is the area kept clean and tidy
2 Are food preparation areas cleaned and free from cracks
3 Are signs for "No smoking" being posted
4 Food waste storage area is cleaned, odour free. Flies area controlled
5 Floor drains are provided in sink area
6 All refrigerators and freezers are working at correct temperatures Refrigerators 1c0 to 4c0
Freezers -14c0 to -18c0
7 Are there temp gauges fitted?
8 Are these temperatures recorded?
9 The Dining and Kitchen areas have an overall clean, tidy and well maintained appearance
10 LPG cylinders are of good conditions (free of damages)
11 Is storage of LPG satisfactory under shed & outside kitchens with no flammable materials nearby
12 Are Piping not perished
13 Are firefighting equipment provided in kitchen area?
LIVING QUARTERS
1 Are Ventilation working well
2 Is lighting suitable
3 Are Emergency numbers being posted in each room
4 Are emergency procedures posted in each room
5 Are Electrical sockets in good condition not damaged & no bare wires are placed in sockets
6 Are sockets overloaded
7 ELCB is provided checks carried out and recorded by
INCIDENT INVESTIGATION REPORT
(To be submitted to the HSEQ Corporate Office within 7 days of incident.)
1. Project Information:
Project Name: Click here to enter text.
Report No.: Click here to enter text.
Project Location: Click here to enter text.
Property No.: Click here to enter text.
☐ Fatality ☐ Major Incident ☐ Minor Incident
2. Describe the Incident in detail:
Answer who, what, why, where, when & how in this section: (Attach additional pages if required)
Click here to enter text.
☐ Photos Attached
3. Incident Root Causes:
Describe direct, indirect & root cause: (Attach additional pages if required)
Click here to enter text.
4. Key Corrective Actions to Prevent Recurrence:
Describe the corrective actions with timeframe: (Attach additional pages if required)
Click here to enter text.
5. Key Corrections Taken Immediately after the Incident:
Attach additional pages if more space is required:
Click here to enter text.
6. Witnesses:
I declare that I witnessed the incident and the information provided above is true, correct and complete.
No. Name Designation Signature Date
1. Click here to enter text.
Click here to enter text.
Click here to enter text.
2. Click here to enter text.
Click here to enter text.
Click here to enter text.
7. Incident Information:
Initial Incident Report No.: Click here to enter text.
Date Reported: Click here to enter text.
Date of Incident: Click here to enter text.
Time of Incident: Click here to enter text.
Type of Incident: ☐ Near Miss
☐ Major Environmental Incident
☐ Serious Dangerous Occurrence
☐ Equipment / Property Damage
☐ Medical Treatment Case (MTC)
☐ Restricted Work Case (RWC)
☐ Lost Workday Case (LWC)
☐ Serious Occupational Illness/Disease
☐ Class 1 Injuries
☐ Permanent Partial Disability (PPD)
☐ Permanent Total Disability (PTD)
☐ Fatality (F)
Recordkeeping: ☐ Reportable ☐ Recordable
Incident Location on Site: Click here to enter text.
Applicable Reports: ☐ Police
☐ Medical
☐ Other (Specify)
Click here to enter text.
Attached: ☐ Yes ☐ No
☐ Yes ☐ No
☐ Yes ☐ No
8. Injured Person’s Personal Details:
In case of an incident with more than one injured person, complete the information for each person using separate forms.
Name: Click here to enter text.
Occupation: Click here to enter text.
Company: Click here to enter text.
MB / Oracle No.: Click here to enter text.
Nationality: Click here to enter text.
Date of Birth: Click here to enter text.
Passport Number: Click here to enter text.
Length of Service: Click here to enter text.
Gender: ☐ Male ☐ Female
Labour Card No.: Click here to enter text.
9. Incident Causes Details: To be supported with factual evidence
Immediate Cause
(Unsafe Acts) ☐ Failure to secure
☐ Failure to warn
☐ Removing / Defeating Safety Devices
☐
HSE INDUCTION
(Workers)
Name: _________________________________ Trade: ____________________________
M.B. No./Company Name : ________________
Date of Joining: __________________________
SL. N SUBJECT ON INDUCTION PREVIOUS SAFETY EXPOSURE FURTHER SAFETY TRAINING NEED ANALYSIS
1. Introduction Safety Requirements
2. Working Safety is of Primary Importance
3. General Safety Rules
4. Basic Safety Requirements
5. House Keeping
6. Health, Hygiene & Welfare Facilities
7. Fire Extinguisher / Fire Fighting
8. Emergency Procedure
9. Safety Violations & Penalty
10. Safety Award
11. Manual Handling
Induction Given By: Name: ___________________________
Designation: ___________________________
1st Warning 0 Ref. No. ______________
2nd Warning 0
3rd Warning 0
4th Warning 0 Date: ________________
Employee’s Name : ______________________________________ M.B No. : __________
Occupation : _____________________________________________________________________
Location / Project Site: _____________________________________________________________________
You have committed the following HSE violation/s:
………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………….….
The employee is hereby warned that if the violation is repeated further disciplinary action can be
taken as per the company Code of Conduct.
ORIGINATOR APPROVED BY (MANAGER IN CHARGE / ARABTEC HSEQ & ORG. RISK Manager)
Name: _______________________________ Name: _____________________________
Designation: _______________________________ Designation: _____________________________
Signature:
_______________________________ Signature:
_____________________________
Employee Acknowledgement:
I the undersigned have received this Safety warning letter / disciplinary notice and I admit that I have understood the contents.
0 Received on: ………………………….. (Date) Signature: ………………………………..…..
Project Information
Project Name: Porta Cabin No:
Location: Contact Person:
Company Name: Date :
Sr. Description Yes No N/A Comments
1. Emergency exit signs are available in right locations
2. Fire alarms and fire extinguishers are visible and accessible.
3. Fire doors (e.g. in stairways) are kept closed unless equipped with automatic closing device
4. Fire extinguishers are serviced regularly
5. Corridors and stairways are kept free of obstruction
6. Fire escape/ evacuation plan available and posted
7. First aid box available
8. Floor surfaces are kept dry and free of slip hazards
9. Electrical cords and plugs are in good condition with proper Grounding
10. Kitchen equipment checked
11. Fire blanket available in the pantry
12. Heat detector available in the pantry
13. Toilets floor clean and dry
14. Are staff trained to use Fire Extinguishers
15. Hand wash/ soap solution available in the toilet
16. Civil Defense or Authority approval
17. Others if any:
Remarks:
Inspected By: Signature:
Reviewed By HSE Manager / In charge : Signature:
Model Attribute Check Company Auto PropertyCeline George
In Odoo, the multi-company feature allows you to manage multiple companies within a single Odoo database instance. Each company can have its own configurations while still sharing common resources such as products, customers, and suppliers.
The Roman Empire A Historical Colossus.pdfkaushalkr1407
The Roman Empire, a vast and enduring power, stands as one of history's most remarkable civilizations, leaving an indelible imprint on the world. It emerged from the Roman Republic, transitioning into an imperial powerhouse under the leadership of Augustus Caesar in 27 BCE. This transformation marked the beginning of an era defined by unprecedented territorial expansion, architectural marvels, and profound cultural influence.
The empire's roots lie in the city of Rome, founded, according to legend, by Romulus in 753 BCE. Over centuries, Rome evolved from a small settlement to a formidable republic, characterized by a complex political system with elected officials and checks on power. However, internal strife, class conflicts, and military ambitions paved the way for the end of the Republic. Julius Caesar’s dictatorship and subsequent assassination in 44 BCE created a power vacuum, leading to a civil war. Octavian, later Augustus, emerged victorious, heralding the Roman Empire’s birth.
Under Augustus, the empire experienced the Pax Romana, a 200-year period of relative peace and stability. Augustus reformed the military, established efficient administrative systems, and initiated grand construction projects. The empire's borders expanded, encompassing territories from Britain to Egypt and from Spain to the Euphrates. Roman legions, renowned for their discipline and engineering prowess, secured and maintained these vast territories, building roads, fortifications, and cities that facilitated control and integration.
The Roman Empire’s society was hierarchical, with a rigid class system. At the top were the patricians, wealthy elites who held significant political power. Below them were the plebeians, free citizens with limited political influence, and the vast numbers of slaves who formed the backbone of the economy. The family unit was central, governed by the paterfamilias, the male head who held absolute authority.
Culturally, the Romans were eclectic, absorbing and adapting elements from the civilizations they encountered, particularly the Greeks. Roman art, literature, and philosophy reflected this synthesis, creating a rich cultural tapestry. Latin, the Roman language, became the lingua franca of the Western world, influencing numerous modern languages.
Roman architecture and engineering achievements were monumental. They perfected the arch, vault, and dome, constructing enduring structures like the Colosseum, Pantheon, and aqueducts. These engineering marvels not only showcased Roman ingenuity but also served practical purposes, from public entertainment to water supply.
How to Make a Field invisible in Odoo 17Celine George
It is possible to hide or invisible some fields in odoo. Commonly using “invisible” attribute in the field definition to invisible the fields. This slide will show how to make a field invisible in odoo 17.
Instructions for Submissions thorugh G- Classroom.pptxJheel Barad
This presentation provides a briefing on how to upload submissions and documents in Google Classroom. It was prepared as part of an orientation for new Sainik School in-service teacher trainees. As a training officer, my goal is to ensure that you are comfortable and proficient with this essential tool for managing assignments and fostering student engagement.
Palestine last event orientationfvgnh .pptxRaedMohamed3
An EFL lesson about the current events in Palestine. It is intended to be for intermediate students who wish to increase their listening skills through a short lesson in power point.
Read| The latest issue of The Challenger is here! We are thrilled to announce that our school paper has qualified for the NATIONAL SCHOOLS PRESS CONFERENCE (NSPC) 2024. Thank you for your unwavering support and trust. Dive into the stories that made us stand out!
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptxEduSkills OECD
Andreas Schleicher presents at the OECD webinar ‘Digital devices in schools: detrimental distraction or secret to success?’ on 27 May 2024. The presentation was based on findings from PISA 2022 results and the webinar helped launch the PISA in Focus ‘Managing screen time: How to protect and equip students against distraction’ https://www.oecd-ilibrary.org/education/managing-screen-time_7c225af4-en and the OECD Education Policy Perspective ‘Students, digital devices and success’ can be found here - https://oe.cd/il/5yV
Operation “Blue Star” is the only event in the history of Independent India where the state went into war with its own people. Even after about 40 years it is not clear if it was culmination of states anger over people of the region, a political game of power or start of dictatorial chapter in the democratic setup.
The people of Punjab felt alienated from main stream due to denial of their just demands during a long democratic struggle since independence. As it happen all over the word, it led to militant struggle with great loss of lives of military, police and civilian personnel. Killing of Indira Gandhi and massacre of innocent Sikhs in Delhi and other India cities was also associated with this movement.
Ethnobotany and Ethnopharmacology:
Ethnobotany in herbal drug evaluation,
Impact of Ethnobotany in traditional medicine,
New development in herbals,
Bio-prospecting tools for drug discovery,
Role of Ethnopharmacology in drug evaluation,
Reverse Pharmacology.
2024.06.01 Introducing a competency framework for languag learning materials ...Sandy Millin
http://sandymillin.wordpress.com/iateflwebinar2024
Published classroom materials form the basis of syllabuses, drive teacher professional development, and have a potentially huge influence on learners, teachers and education systems. All teachers also create their own materials, whether a few sentences on a blackboard, a highly-structured fully-realised online course, or anything in between. Despite this, the knowledge and skills needed to create effective language learning materials are rarely part of teacher training, and are mostly learnt by trial and error.
Knowledge and skills frameworks, generally called competency frameworks, for ELT teachers, trainers and managers have existed for a few years now. However, until I created one for my MA dissertation, there wasn’t one drawing together what we need to know and do to be able to effectively produce language learning materials.
This webinar will introduce you to my framework, highlighting the key competencies I identified from my research. It will also show how anybody involved in language teaching (any language, not just English!), teacher training, managing schools or developing language learning materials can benefit from using the framework.
Synthetic Fiber Construction in lab .pptxPavel ( NSTU)
Synthetic fiber production is a fascinating and complex field that blends chemistry, engineering, and environmental science. By understanding these aspects, students can gain a comprehensive view of synthetic fiber production, its impact on society and the environment, and the potential for future innovations. Synthetic fibers play a crucial role in modern society, impacting various aspects of daily life, industry, and the environment. ynthetic fibers are integral to modern life, offering a range of benefits from cost-effectiveness and versatility to innovative applications and performance characteristics. While they pose environmental challenges, ongoing research and development aim to create more sustainable and eco-friendly alternatives. Understanding the importance of synthetic fibers helps in appreciating their role in the economy, industry, and daily life, while also emphasizing the need for sustainable practices and innovation.
21 confined space working risk assessment templates
1. HEALTH SAFETY AND ENVIRONMENT Author: Approved:
RISK ASSESSMENT: ACT/HSE/RA 001 CONFINED SPACE WORKING
Issued: Rev. Date:
Revision: 0
Page 1 of 1 HSEQ -Rev-01(Aug-2018)
No
Specific Task Step
(In sequence of
works)
Hazard Details Consequence/Risk
Initial Risk
Rating Control Measures Residual Risks
Additional Control
Measures
RR
P S RR
1
Planned confined
space work in areas
where live services
may be present
including:
Water;
Sewerage;
Gas;
PRIOR TO ENTRY
Presence oflive
underground services;
Services not in area
specified on drawings;
Presence of
unmarked services;
Risk of asphyxia;
Risk of explosion due to gas ignition;
Risk of flooding of confined space;
Risk of hazardous waste entering
confined space due to live sewerage;
Risk of vehicles / Plant entering
confined space;
4 4
20
HIGH
i. All existing utility service drawings reviewed for known service details and
position;
ii. NOC and Utility provider and HLG permits to be completed,unique
number added and recorded in log;
iii. All services clearlycommunicated to all workers at briefings and TBT’s,
signed offand recorded;
iv. Permit/NOC/JSEA/Approved design Drawings copies to be with task
supervisor in work area for review;
v. Suitable training undertaken for operatives;
LOW
2
Confined space
working –
Deep excavations;
Tanks;
Vessels;
Manholes;
NDRC pits;
Bridge decks;
Pipework;
Sewerage;
Lift shafts;
Ducting;
Etc.
Workers required to
work in confined
space;
Excess or lack of oxygen;
Presence ofToxic gases;
Ingress ofwater or other substances;
Explosion due to build-up of gases;
Sudden water ingress into excavation;
Collapse ofworker;
Restricted emergencyevacuation;
Musculoskeletal disorders;
4 5
20
High
i. Permitto be issued & gas monitoring undertaken ifrequired before works
commence;
ii. No works above, as in lift shafts etc.;
iii. Adequate air circulation & lighting to be maintained in work areas;
iv. Equipmentwhich mayrelease excess oxygen or carbon monoxide gases
shall notbe used in confined space areas withoutadequate extraction;
v. Local weather forecastshould be noted to watch for heavy rains which
may cause flooding;
vi. Special consideration to be given to any hot works or work using toxic
substances inside a confined space;
vii. Materials to be stored well away from confined space area;
viii. Top man to be appointed atthe entry of the confined space area as
required,regular contactwith workers in confined space;
ix. Workers connected to lifeline,leading to outside confined space;
x. Rescue drills to be undertaken as required to ensure rescue procedure is
communicated and understood;
xi. Workers should be physicallyfit and competentto enter and undertake
the work in confined spaces.
xii. Rotation of workers if area cramped / difficult to move;
Workers not
adhering to
requirements;
Gas detector not
calibrated
resulting in
incorrectreading
Supervision to constantly
monitor workers;
Regular TBT’s & Trainings to
be given on working Confined
space;
Gas detector to be calibrated
to standards and
manufacturers
recommendations.
Low
RISK SCORE CALCULATOR
Use the Risk Score Calculator to Determine the Level of Risk of each Hazard
What would be the
CONSEQUENCE
of an occurrence be?
What is the LIKELIHOOD of an occurrence? Hierarchy of Controls
Frequent/Almost certain (5)
Continuous or will happen
frequently
Often (4)
6 to 12 times a year
Likely (3)
1 to 5 times a year
Possible (2)
Once every 5 years
Rarely (1)
Less than once every 5
years
Can the hazard be Eliminated or removed
from the w ork place?
Catastrophic (5)
Multiple Fatalities
High 25 High 20 High 15 Medium 10 Medium 5
Can the product or process be substitutedfor
a less hazardous alternative?
Serious (4)
Class 1 single fatality
High 20 High 16 High 12 Medium 8 Low 4
Can the hazard be engineered aw ay w ith
guards or barriers?
Moderate (3)
Class2 (AWI or LTI) or Class 1
Permanently disabling effects
High 15 High 12 Medium 9 Medium 6 Low 3
Can Administration Controls be adopted
I.e. procedures, job rotation etc.
Minor (2)
Medical attention needed, no work
restrictions. MTI
Medium10 Medium 8 Medium 6 Low 4 Low 2 Can Personal Protective Equipment &
Clothing be w orn to safe guard against
hazards?Insignificant (1)
FAI
Medium10 Medium 4 Low 3 Low 2 Low 1
Project Name: xxx
RA Ref No.: xxx
RA compilation
Date:
Review date:
Date:
Compiled by:
Reviewed by:
Approved by:
Overall Task Details
Working in area designated as a confined space
Relevant Applicable MAS:
00246 – Excavations;
00233 – Lift Shafts
Additional Training required: NOC’s Required for task: