SlideShare a Scribd company logo
SANCTION OF CRS TO BE OBTAINED PRIOR TO EXECUTION OF THE WORK.
General Notes
1. Unless otherwise specified, all measurements are shown in mm and levels are shown in meters.
2. The foundation levels shown in the drawing are to be verified at site based on confirmatory subsoil investigation prior to commencement of
work.
3. Max pressure on the soil at foundation level is specified in concerned detailed drawings pertaining to foundations.
4. The bridge shall be designed to IRC class 'A' loading or 70R loading or 385T (S.V Loading) whichever gives worst effect for the given
carriageway width as per IRC standards.
5. Stair cases are to be provided on both sides of the ROB outside railway boundary to suit pedestrian traffic (wherever footpaths are provided).
6. 4.00m wide strip with polysulphide paint preferably in black colour shall be provided on the soffit of deck and footpath slabs over running
tracks.
7. Guard rails shall be provided on tracks below ROB.
8. No construction joint shall be allowed in concrete work unless it is specified in detailed drawings as per design considerations.
9. The details, type and dimensions of foundations, & sub-structure and super structure elements shown in the drawing are indicative and may
vary as per actual design and detailed drawings. However obligatory clearances mentioned in the drawings shall not be reduced under any
circumstances without prior approval of CBE.
10.High containment crash barrier of 1.80m height within Railway boundary and 1.50m height in approaches beyond Railway boundary for
minimum length of 90.00m above footpath level shall be provided as per IRC 5&6 guide lines.
11.The land boundaries indicated in the drawing here may not reflect the actual Railway boundary and reckoning actual land. The certified land
plan as available in HQ of divisional offices only is the final authority. The land boundaries shown in this plan cannot be of authority for this
purpose.
Specification and design related notes:
1. The grade of concrete for various RCC/Mass concrete works, & grade of steel for composite structures shall be in accordance with IRS
concrete bridge code 1997 & new I.S.456-2000 and IRC Codes & specifications etc.
2. Expansion joints shall be strip seal joints as per MORTH specifications. Confined POT Bearings shall mandatory be provided for spans
exceeding 30.0m.
3. Elastomeric/Pot-Ptfe Bearings shall be as per MORTH standards and specifications.
4. Protective coatings for reinforcement against corrosion should be provided as per latest correction slip of IRS concrete bridge code edition.
5. Drainage spouts shall be provided 2.00m away from the center line of existing / future track considering the traction / future traction and same
has to be ensured in the detailed drawings and by the Engineer-in-charge at site.
6. During construction a minimum clearance of 2575mm to be maintained between centre line of existing track to the face of Temporary
Arrangements Structure.
7. Variation of transverse slopes shall be maintained in deck/superstructure only. Under any circumstances, wearing coat thickness should not
exceed 80mm thick during execution and maintenance period. This shall be ensuring by Road authority under Railway supervision from time
to time”.
8. Bridge is to be designed assuming exposure condition as moderate.
9. Provision of clamps in the superstructure for supporting the traction wire to be made in communication with concerned authority.
Reference notes/ Drawings:
1. Wearing coat with uniform thickness, and misc. items such as drainage spouts with grating arrangements etc., shall be similar to MORTH
drawing No.SD/205. Location of drainage spouts shall invariably be shown in detailed drawings.
2. Expansion joints, Elastomeric & Confined POT/PTFE bearings shall be procured only from pre-qualified manufacturers of MORTH. Warranty
and maintenance conditions on these items have to be ensured as per MORTH guidelines/circulars issued from time to time.
3. For 36.0m composite super structure refer DRg. Nos: RDSO/B-10775, to 10775/12.
4. for 18.0m composite girder super structure refer drawing no. RDSO/B-11772 to RDSO/B-11772/12, RDSO/B-11776 series and CBS-0044
IMPORTANT NOTES:
1. A common bench mark should be established by Railways and Road Authority Engineers before starting the work.
2. Concerned Road Authority (NHAI) has to enter an MOU with south central Railway.
as per draft MOU vetted by PCE office before commencement of the work. PCE office will coordinate to finalize the draft copy of
MOU. ROB work in Railway portion shall be commenced accordingly as per terms and conditions of MOU. MOU shall be signed in triplicate.
Original shall be retained by PCE office. Duplicate and Triplicate copies shall be retained with NHAI and Devision.
3. Concerned Road Authority has to submit Completion Drawings of Detailed drawings & GAD and final design in original (drawings in cloth
tracing) duly signed by them and Railway Divisional officials after immediate completion of the work in accordance with para 911 of Indian
Railway Works Manual.
4. Load test has to be carried out in presence of NHAI & Railway Authorities immediately after completion of the superstructure considering the
provisions of IRC SP 51-2015 - Guide lines for load testing of Bridges.
5. All the records of Quality Assurance / Quality Control, testing of the materials and satisfactory completion of an activity shall be maintained at
site by the Contractor's Engineer and Supervising Engineers. On the basis of the records, Railways Engineers shall do stage wise clearance.
Without such stage clearance, the work in the next stage of construction shall be not allowed by the Railway Supervisor, unless proper system
of check and exercise is followed at the site.
6. CRS permission shall be obtained prior to commencement of work considering para 1202 {Clause-2(g)} of Indian Railway P.Way Manual.
7. Safety Pre-Cautions and Measures to be observed during execution of ROB shall be finalized by Vijayawada Division with the
concerned road authority before commencement of work as per Railway Board Directives communicated to Divisions vide letter no: W-
71/BR/Safety/General dated: 16.11.2009.
8. Narrow road over bridges having width of deck less than approaches, traffic safety measures on approaches to narrow road over bridges shall
be provided by concerned road authority as per MORTH letter No.RW/NH/33044/23/2007-S&R® Dated: 31-10-2008. Concerned Railway
Division has to ensure it.
9. Procedural guidelines of Annexure-II and Annexure-I etc. issued by Railway Board vide their letter No.2001/CE-I/Misc/NH/4 Pt.III dated:
28.06.2010 shall be ensured during submission of proposal and during execution etc.
10.The scope of Railway supervision is main span of 3x36.0 composite+1x18.0mts composite (RDSO standard span). And the piers over which
the main span is resting. The arrangement of approach spans beyond Railway boundary shall not be changed without prior permission of
Railways as approved in the drawing.
11.The substructure and foundation shall be designed by considering RDSO standard drawings bearing Drg. Nos RDSO/B-11772 to
RDSO/B-11772/12 for 18.0m.and RDSO/B-10775/R to RDSO/B-10775/12 for 36.0m.
12.Para 1851 to 1853, 1033, 1617 & 1618 etc. of Indian Railway Code for Engineering Department mutatis-mutandis will apply for these works
and Concerned Road Authority/Railway Division has to ensure it from time to time.
13.This approval is subjected deposition of way leave charges, land leave charges and other charges as per extant Railway norms.
14.(a) As per clause A-3 of Memorandum dt.10/11/14 entered between ministry of Railways and ministry of Transport and Highways. NHAI has
to develop instrumentation scheme. Accordingly, NHAI has to submit detailed instrumentation in monitoring system as part of design &
drawings before commencement of the work.
(b)NHAI shall do the instrumentation in the Railway super structure across the Railway bridge portion NHAI has to develop maintenance &
inspection manual to maintain the ROB from time to time. NHAI also has to develop instrumentation system of ROB. The same have to be
ratified by Railways. NHAI has to submit periodical reports of the instrumentation system of super structure and bearings from time to time
Annual basis or the period specified by the railway division whichever less is.
15.Design of bearing is dependent on time period and flexibility of substructure. Therefore, the design of bearing shall be considered as part of
substructure for which the seismic forces are computed by considering time period of whole structure.
16.The inspection of steel composite girders of ROB shall be done as per railway board letter no: 2016/54/CE-III/BR/RDSO/MISC. Date:
15/07/2019 (Composite girder)
17.As per Railway board Lr. No: 2015/CE-IV/ROB/78 Pt. Date:07/12/2020 if work was not started after approval of GAD, The GAD needs to be
revalidate after a reasonable period of 2 years to match the prevailing ground situation.
18.Inspection of steel girder for ROB'S shall be done by RDSO (both at workshop & site) as per railway board letter no.
2016/54/CE-III/BR/RDSO/MISE Date: 15/07/2019
19.Height gueges need to be provided at starting of approaches in case of bowstring arrangement.
20.Proposed RCL indicated will be tentative approaches including approach span shall not be taken until finalization of detailed design and
drawings including launching scheme of main span crossing over railway track with bowstring type superstructure (bowstring girder).
21. Fixing of any electrical or communications cable, ducts, lighting mast/polls, boards etc.,over the crash barrier/parapet in the railway portion of
the viaduct is not permitted without prior approval of railway division officials.
22.Necessary reposition has to be made by road authorities (NHAI/MORTH) for shifting of railway assets temporaing/permanenthy due to
construction of ROB to railways before and during execution of ROB work.
DESCRIPTION
0.065
RAIL TOP LVL. (EXIST. TRACK)
LEVELS
MIN. VERTICAL CLEARANCE 6.55M
WEARING COAT THK.
M
M
M
UNITS
PROPOSED FRL CALCULATIONS
CROSS FALL OR
CAMBER M 0.3825
97.220
DEPTH OF GIRDER INCLUDING
SLAB (18.0M / 36.0M) M 1.165/1.881
℄OF EXPANSION JOINT
℄OF EXPANSION JOINT
(80MM)
P3
P2
FINISHED ROAD LEVEL
A2
93.014
FOUNDATION BOTTOM LEVEL
P2
P1
TO CHITRAKOOT
HALF PLAN AT TOP
HALF PLAN AT BOTTOM
RE WALL
RE WALL
APPROACH
TO MOHANGANJ
SLAB
(SCALE 1:150)
TO CHITRAKOOT
SECTION ELEVATION (RAILWAY PORTION)
( SCALE 1:150)
36 M STANDARD GIRDER
AS PER RDSO SPAN
(RDSO/B-11775)
A1
106.100
94.068
RE WALL
RAILWAY
BOUNDARY
℄OF PIER
CHAINAGE 43+578.7
43+541.7
43+504.7 43+633.7
106.100 106.100 106.100
94.750 95.414
26.973
GROUND LVL.
1.
2.
3.
4.
G.L
G.L
RAILWAY
BOUNDARY
43+560
95.711
BORE
HOLE-1
BORE
HOLE-1
32000 53000
PILE CAP
TOP LVL.
PILE CAP CUT LVL.
5100
3600
750 750
DIVERTED
CANAL /DRAIN
G.L
FRL.103.328
℄OF BEARING
2.50 % SLOPE
PILE
Ø1200(TYP.)
RE WALL
℄OF EXPANSION JOINT
(80MM)
5100
3600 750
750
1500
2000
330
℄
O
F
E
X
IS
T
IN
G
T
R
A
C
K
53000 SQ 56771 SK
32000 SQ 3428 SK RAILWAY BOUNDARY
℄
F
U
T
U
R
E
T
R
A
C
K
PILE CAP
TOP LVL.
PILE CAP CUT LVL.
5100
3600 750
750
℄OF BEARING
℄OF BEARING
36700 SQ 39311 SK (OVERALL
LENGTH OF STEEL GIRDER)
37000 SQ 39632SK(C/C OF EJ.)
36000 SQ 38560 SK
2.50 % SLOPE
PILE Ø1200(TYP.)
RE WALL
5100
3600
750 750
36 M STANDARD GIRDER
AS PER RDSO SPAN
(RDSO/B-11775)
℄OF TRACK ℄FUTURE TRACK
℄FUTURE TRACK
7800 SQ 8355 SK
℄OF EXPANSION JOINT
℄OF EXPANSION JOINT
(80MM)
A1 P1
℄OF EXPANSION JOINT
(80MM)
9695 SQ 10385 SK
TO MOHANGANJ
5100
'1'
'2'
7
5
0
3
6
0
0
3
6
0
0
7
5
0
3
6
0
0
1
2
3
0
0
5100
5100 SQ
5463 SK
G.L
PILE CAP
TOP LVL.
PILE CAP CUT LVL.
5100
3600
750 750
℄OF BEARING
18700 SQ 20030 SK (OVERALL
LENGTH OF STEEL GIRDER)
19080 SQ 20437 SK(C/C OF EJ.)
18000 SQ 19281 SK C/C OF BRG.
EXISTING CANAL / DRAIN
RAILWAY BOUNDARY
EXISTING CANAL / DRAIN DIVERTED
22262 SQ 23846 SK 12540 SQ 13454 SK 33540 SQ 35926 SK 1460 SQ 1564 SK 16869
6550
(MIN.
VERTICAL
CLEARANCE)
20°
21°
'3'
RE WALL
BORE
HOLE-2
5100
5100
7
5
0
3
6
0
0
3
6
0
0
7
5
0
3
6
0
0
1
2
3
0
0
7
5
0
S
Q
8
0
3
S
K
3
6
0
0
S
Q
3
8
5
6
S
K
1
2
3
0
0
S
Q
1
3
1
7
5
S
K
BORE
HOLE-2
A2
2000
9695 SQ
10385 SK
7800 SQ
8355 SK
36700 SQ 39311 SK (OVERALL
LENGTH OF STEEL GIRDER)
37000 SQ 39632SK(C/C OF EJ.)
36000 SQ 38560 SK
36700 SQ 39311 SK (OVERALL
LENGTH OF STEEL GIRDER)
37000 SQ 39632SK(C/C OF EJ.)
36000 SQ 38560 SK
7800 SQ 8355 SK
36000 SQ 38560 SK 36000 SQ 38560 SK 36000 SQ 38560 SK 18000 SQ 19281 SK
3
6
0
0
S
Q
3
8
5
6
S
K
3
6
0
0
S
Q
3
8
5
6
S
K
7
5
0
S
Q
8
0
3
S
K
7
5
0
S
Q
8
0
3
S
K
3
6
0
0
S
Q
3
8
5
6
S
K
1
2
3
0
0
S
Q
1
3
1
7
5
S
K
3
6
0
0
S
Q
3
8
5
6
S
K
3
6
0
0
S
Q
3
8
5
6
S
K
7
5
0
S
Q
8
0
3
S
K
7
5
0
S
Q
8
0
3
S
K
3
6
0
0
S
Q
3
8
5
6
S
K
1
2
3
0
0
S
Q
1
3
1
7
5
S
K
3
6
0
0
S
Q
3
8
5
6
S
K
3
6
0
0
S
Q
3
8
5
6
S
K
7
5
0
S
Q
8
0
3
S
K
7
5
0
S
Q
8
0
3
S
K
3
6
0
0
S
Q
3
8
5
6
S
K
1
2
3
0
0
S
Q
1
3
1
7
5
S
K
3
6
0
0
S
Q
3
8
5
6
S
K
3
6
0
0
S
Q
3
8
5
6
S
K
7
5
0
S
Q
8
0
3
S
K
7800 SQ
8355 SK
9695 SQ
10385 SK
95.200
43+615.7
106.100
P3
94.137 94.188 95.180 94.068 95.501 96.052 96.440 93.121 93.003
RAILWAY BRIDGE 49
'3'
T
O
U
N
C
H
A
H
A
R
T
O
P
H
A
P
H
A
M
A
U
/
P
R
A
Y
A
G
R
A
J
℄
F
U
T
U
R
E
T
R
A
C
K
℄
F
U
T
U
R
E
T
R
A
C
K
℄
F
U
T
U
R
E
T
R
A
C
K
℄
E
X
IS
T
IN
G
T
R
A
C
K
9695 SQ 10385 SK
9695 SQ
10385 SK
7800 SQ
8355 SK
7800 SQ
8355 SK
9695 SQ
10385 SK
18 M STANDARD GIRDER
AS PER RDSO SPAN
(RDSO/B-11772)
RTL
43+515 43+525 43+550 43+570 43+590 43+600 43+610 43+525
43+620
97.220
(RECHANNELISED )
RE 26/13
RE
26/11
3
6
5
0
0
*^
5
8
7
0
0
^^
21
90
0
*^
*^ = DISTANCE OF OHE MAST FROM ROB EDGE ABOVE
^^ = DISTANCE OF OHE MAST TO OHE MAST
6
2
9
0
0
^^
54801.2
^^
48247.7
*^
6553.5
*^
7546.5
*^
5872.22
^^
24646.5*^
34075.7*^
CENTER LINE OF EXISTING TRACK
RE 26/12
ABRIVATION:-
F.R.L FINISHED ROAD LEVEL
LVL.
TYP.
CENTER LINE
LEVEL
TYPICAL
C
L
THK. THICK
C/C
G.L
CENTER TO CENTER
GROUND LEVEL
FDN. FOUNDING LEVEL
EXP. EXPANSION
BRG. BEARING
SYMM. SYMMETRICAL
SQ SQUARE DIMENSION
SK. SKEW DIMENSION
BH BORE HOLE
FEATURES
PROPOSED WORK RED
COLOUR
TO BE DISMANTLE
GREEN
BLUE
FUTURE
EXIST. RAILWAY TRACK BLACK
PROP. RAILWAY TRACK GREEN
300
1500
500 250 1500 10500
CARRIAGE WAY
500
250
2500 2500 2500 2500 2500
SHY DISTANCE
CRASH BARRIER
RAILING FOOT
PATH
15300 SQ 16389 SK
300
1500
500
250
1500
10500
CARRIAGE WAY
500 250
SHY DISTANCE
CRASH BARRIER RAILING
FOOT
PATH
15300 SQ 16389 SK
2500
2500
2500
2500
2500
750
3600
750
12300
FOUNDATION AS PER DESIGN
FND. LVL. FND. LVL.
(SCALE 1:120)
SECTION AT A-A (ABUTMENT)
15300
(SCALE 1:150)
750
750
1500
2500 1650 7000 2500
3600 3600
PILE TOP LVL.
PILE TOP LVL.
GROUND LVL.
AS PER HIGHWAY PROFILE
2500
1650
7000
1650
2500
REWALL
2.5% SLOPE 2.5% SLOPE
750
12300
FOUNDATION AS PER DESIGN
3600 3600 3600
1825 1825 1825 1825
ABUTMENT CAP PLAN
1650
1600SQ
1714SK 2500SQ
2678SK
1200SQ
1285SK
15300 SQ/16389 SK
℄
OF
BRG.
JACKING
LOCATION (TYP.)
℄
OF
EXP.JOINT
1800SQ
1928SK
2500SQ
2678SK
2500SQ
2678SK
2500SQ
2678SK
2500SQ
2678SK
1600SQ
1714SK
2500SQ
2678SK
1200SQ
1285SK
15300 SQ/16389 SK
2500SQ
2678SK
2500SQ
2678SK
2500SQ
2678SK
2500SQ
2678SK
GAD NEED TO BE REVALIDATED AFTER A REASONABLE PERIOD OF 2 YEARS TO MATCH THE PREVAILING GROUND SITUATION.
GAD NEED TO BE REVALIDATED AFTER A REASONABLE PERIOD OF 2 YEARS TO MATCH THE PREVAILING GROUND SITUATION.
# FRL SHALL BE DECIDED AS PER RTL MAINTAINING MIN. CLEARANCE OF 6.50M BETWEEN RTL & GIRDER BOTTOM LEVEL.
DEPTH
(M) STRATA
BH A1(R.L.97.100m)
DESCRIPTION
SILTY WITH
GRAVEL
SAND AND
GRAVELLY
CLAY WITH SAND
SILT WITH
GRAVEL
FINE SAND
AND SILT
DETAILS OF BORE HOLE
43+500
43+600
43+700
43+800
EXISTING BRIDGE NO. 49
CANAL TO BE RETAINED AT
ABUTMENT PIER LOCATION
PROPOSED ROB DRAIN
26.973
510
0
10951
510
0
123
00
(SCALE 1:50)
DETAIL-'2' 1631
250
1881
DEPTH
(M) STRATA
DESCRIPTION
SILTY WITH
GRAVEL
SILTY CLAY
SILTY CLAY WITH
GRAVEL
SILT SAND WITH
GRAVEL
SILTY CLAY
WITH GRAVEL
GRAVEL WITH
SILT
BH P3(R.L.97.100m)
300
1500500 250 1500 10500
CARRIAGE WAY
500
250
2500 2500 2500 2500 2500
SHY DISTANCE
CRASH BARRIER
RAILING FOOT
PATH
15300
300
1500
500
250
1500
10500
CARRIAGE WAY
500 250
SHY DISTANCE
CRASH BARRIER RAILING
FOOT
PATH
15300
2500
2500
2500
2500
2500
(SCALE 1:120)
15300
750
750
1500
2500 2150 2150 2500
GROUND LVL. GROUND LVL.
AS PER HIGHWAY PROFILE
2500
2150
2150
2500
2.5% SLOPE 2.5% SLOPE
6000 6000
(SCALE 1:150)
PIER CAP PLAN
℄
OF
BRG.
℄
OF
EXP.JOINT
2330SQ
2496SK
1600SQ
1714SK 2500SQ
2678SK
1200SQ
1285SK
2500SQ
2678SK
2500SQ
2678SK
2500SQ
2678SK
2500SQ
2678SK
750
3600
750 3600 3600 750
3600 3600 3600
SECTION AT B-B (PIER)
15300 SQ/16389 SK
1600SQ
1714SK
2500SQ
2678SK
1200SQ
1285SK
2500SQ
2678SK
2500SQ
2678SK
2500SQ
2678SK
2500SQ
2678SK
15300 SQ/16389 SK
PILE TOP LVL.
PILE TOP LVL.
330
1631
250
1881
2000
1650
(SCALE 1:50)
DETAIL-'1'
750
750
330
915
250
1165
2000
1650
(SCALE 1:50)
DETAIL-'4'
750
750
(SCALE 1:50)
DETAIL-'3'
915
250
1165
1631
250
1881
KEY PLAN
GAD FOR CONSTRUCTION OF 4-LANE GREEN FIELD HIGHWAY FROM Km 35.000
TO KM 49.155 (AUTARPUR TO SINGARAUR UPHAR) OF NH -731A AT RAILWAY KM
26KM 750M 26/12 TP.
Consultancy Services for Feasibility Study & Preparation of Detailed Project Report for
improvement & up-gradation of in principle & newly declared National Highways in the
state of Uttar pradesh. Package-II (i) Stretch from Near Pratapgarh(NH-31) - Jethwada -
Shrangvepur-Manjhanpur-Rajapur - Near Chitrakoot (NH-35) & Length -160.000Km
DWG NO: ARKI/MORT&H/UP-17358/NH-731A/ROB/GAD/101
NORTHERN RAILWAY
CLIENT:
AUTHORITY OF WORK
DATE: JUNE 2022 PAPER SIZE: A0
SCALE : AS SHOWN REVISION : R2
DIVISION: SECTION: PHAPHAMAU-UNCHAHAR
PROPOSED ID : NRLK00040
LUCKNOW
Arkitechno Consultants(I) Pvt.Ltd.
N3/91, I.R.C Village, Near Maharishi Public School,Nayapalli, Bhubaneswar- 751015.Odisha
Telephone :+91 674 2554 205; Fax:+91 674 2553689
DESIGN CONSULTANTS
DRG. NO.
DRAWING TITLE:
CHECKED BY: A.A
DRAWN BY : D.R
EE,UPPWD
NH-DIVISION-1
DRM
Sr. DEN / COORDINATION
Sr. DEE (TRD)
Sr. DSTE
Sr. DOM
Sr. DEN / 6
PRAYAGRAJ
NR
NR
NR
NR
NR
NR
ADRM
NR
THE FEASIBILITY OF PROPOSED PLAN IS BEING
CHECKED AT SITE AND FOUND CORRECT
SSE / WORKS / PRG SSE / P. WAY / PRG ADEN / PRG
FOR SITE FEASIBILITY STUDY :-
CBE
DY. CE / ROB

More Related Content

What's hot

Introduction
IntroductionIntroduction
Introduction
sky hawk
 
Sp34 str detailing
Sp34     str detailingSp34     str detailing
Sp34 str detailingMohd Danish
 
Deck slab bridge
Deck slab bridgeDeck slab bridge
Deck slab bridge
Animesh Verma
 
Training Report on Bridge Construction
Training Report on Bridge ConstructionTraining Report on Bridge Construction
Training Report on Bridge Construction
MAHAVIR MEENA
 
retrofitting of fire damaged rcc slabs,colums,beams
retrofitting of fire damaged rcc slabs,colums,beamsretrofitting of fire damaged rcc slabs,colums,beams
retrofitting of fire damaged rcc slabs,colums,beams
Nayana 54321
 
Minor Project Report On Construction of Pipe Culvert
Minor Project Report  On Construction of  Pipe CulvertMinor Project Report  On Construction of  Pipe Culvert
Minor Project Report On Construction of Pipe Culvert
=> No nEEd FoH WoRk , Um gOod cOnsUMer oF PArentx MOnEy
 
PRESENTATION ON CASTING YARD OF LUCKNOW METRO
PRESENTATION ON CASTING YARD OF LUCKNOW METRO PRESENTATION ON CASTING YARD OF LUCKNOW METRO
PRESENTATION ON CASTING YARD OF LUCKNOW METRO
Akanksha Priya
 
What are methods of steel structure design
What are methods of steel structure designWhat are methods of steel structure design
What are methods of steel structure design
najeeb muhamed
 
Introduction & under ground water tank problem
Introduction & under ground water tank problemIntroduction & under ground water tank problem
Introduction & under ground water tank problem
dhineshkumar002
 
BALANCED CANTILEVER BRIDGE
BALANCED CANTILEVER BRIDGEBALANCED CANTILEVER BRIDGE
BALANCED CANTILEVER BRIDGE
srinivas cnu
 
Design and construction of well foundations
Design and construction of well foundationsDesign and construction of well foundations
Design and construction of well foundations
Dar Hilal
 
Rigid pavements
Rigid pavements Rigid pavements
Rigid pavements
pradip dangar
 
Loss of pre stress in pre-stressed concrete
Loss of pre stress in pre-stressed concrete Loss of pre stress in pre-stressed concrete
Loss of pre stress in pre-stressed concrete
Abdulrahman Salah
 
Design of combined footing ppt
Design of combined footing pptDesign of combined footing ppt
Design of combined footing ppt
Bharti Shinde
 
Design of steel structures, jntuh syllabus
Design of steel structures, jntuh syllabusDesign of steel structures, jntuh syllabus
Design of steel structures, jntuh syllabus
GARRE RAVI KUMAR
 
Precast pretensioned concrete girders
Precast pretensioned concrete girdersPrecast pretensioned concrete girders
Precast pretensioned concrete girders
MD.Yeasin Mostafiz
 
Bc prestressing
Bc prestressingBc prestressing
Bc prestressing
Anuj Singhal
 
Erection of steel Structure
Erection of steel StructureErection of steel Structure
Erection of steel Structure
Gaurang Kakadiya
 
Railway engg geometric design
Railway engg geometric designRailway engg geometric design
Railway engg geometric design
Vijai Krishnan V
 

What's hot (20)

Introduction
IntroductionIntroduction
Introduction
 
Sp34 str detailing
Sp34     str detailingSp34     str detailing
Sp34 str detailing
 
Deck slab bridge
Deck slab bridgeDeck slab bridge
Deck slab bridge
 
Training Report on Bridge Construction
Training Report on Bridge ConstructionTraining Report on Bridge Construction
Training Report on Bridge Construction
 
retrofitting of fire damaged rcc slabs,colums,beams
retrofitting of fire damaged rcc slabs,colums,beamsretrofitting of fire damaged rcc slabs,colums,beams
retrofitting of fire damaged rcc slabs,colums,beams
 
Minor Project Report On Construction of Pipe Culvert
Minor Project Report  On Construction of  Pipe CulvertMinor Project Report  On Construction of  Pipe Culvert
Minor Project Report On Construction of Pipe Culvert
 
PRESENTATION ON CASTING YARD OF LUCKNOW METRO
PRESENTATION ON CASTING YARD OF LUCKNOW METRO PRESENTATION ON CASTING YARD OF LUCKNOW METRO
PRESENTATION ON CASTING YARD OF LUCKNOW METRO
 
7 losses in prestress
7 losses in prestress7 losses in prestress
7 losses in prestress
 
What are methods of steel structure design
What are methods of steel structure designWhat are methods of steel structure design
What are methods of steel structure design
 
Introduction & under ground water tank problem
Introduction & under ground water tank problemIntroduction & under ground water tank problem
Introduction & under ground water tank problem
 
BALANCED CANTILEVER BRIDGE
BALANCED CANTILEVER BRIDGEBALANCED CANTILEVER BRIDGE
BALANCED CANTILEVER BRIDGE
 
Design and construction of well foundations
Design and construction of well foundationsDesign and construction of well foundations
Design and construction of well foundations
 
Rigid pavements
Rigid pavements Rigid pavements
Rigid pavements
 
Loss of pre stress in pre-stressed concrete
Loss of pre stress in pre-stressed concrete Loss of pre stress in pre-stressed concrete
Loss of pre stress in pre-stressed concrete
 
Design of combined footing ppt
Design of combined footing pptDesign of combined footing ppt
Design of combined footing ppt
 
Design of steel structures, jntuh syllabus
Design of steel structures, jntuh syllabusDesign of steel structures, jntuh syllabus
Design of steel structures, jntuh syllabus
 
Precast pretensioned concrete girders
Precast pretensioned concrete girdersPrecast pretensioned concrete girders
Precast pretensioned concrete girders
 
Bc prestressing
Bc prestressingBc prestressing
Bc prestressing
 
Erection of steel Structure
Erection of steel StructureErection of steel Structure
Erection of steel Structure
 
Railway engg geometric design
Railway engg geometric designRailway engg geometric design
Railway engg geometric design
 

Similar to GADFORROB.pdf

Tes p-122.08-r0
Tes p-122.08-r0Tes p-122.08-r0
Tes p-122.08-r0
Ibrahim Ali
 
Design Example_Prestressed Concrete Girder Bridge.pdf
Design Example_Prestressed Concrete Girder Bridge.pdfDesign Example_Prestressed Concrete Girder Bridge.pdf
Design Example_Prestressed Concrete Girder Bridge.pdf
SaminSiraj1
 
Design of Elevated Viaduct.pptx
Design of Elevated Viaduct.pptxDesign of Elevated Viaduct.pptx
Design of Elevated Viaduct.pptx
Aman Khandelwal
 
0400 Series - Safetydfsdfsdf Fencing & Parapets.doc
0400 Series - Safetydfsdfsdf Fencing & Parapets.doc0400 Series - Safetydfsdfsdf Fencing & Parapets.doc
0400 Series - Safetydfsdfsdf Fencing & Parapets.doc
matrixpmp2
 
PWD Road cutting Trenching of PWD roads by KWA Modified Guidelines 14.02.202...
PWD Road cutting Trenching of PWD roads by KWA  Modified Guidelines 14.02.202...PWD Road cutting Trenching of PWD roads by KWA  Modified Guidelines 14.02.202...
PWD Road cutting Trenching of PWD roads by KWA Modified Guidelines 14.02.202...
Jamesadhikaram land matter consultancy 9447464502
 
Lrr new alignment
Lrr new alignmentLrr new alignment
Lrr new alignment
Jawad Amjad Ghauri
 
viewNitPdf_3777461.pdf
viewNitPdf_3777461.pdfviewNitPdf_3777461.pdf
viewNitPdf_3777461.pdf
DivyanshTotla
 
Irs concrete bridge code
Irs concrete bridge codeIrs concrete bridge code
Irs concrete bridge code
Ajay Kumar
 
Building work method statement cm - ms- bw - 001
Building work method statement  cm - ms- bw - 001Building work method statement  cm - ms- bw - 001
Building work method statement cm - ms- bw - 001Minh Bui Si
 
Buildingworkmethodstatement cm-ms-bw-001-141120013134-conversion-gate01(1)
Buildingworkmethodstatement cm-ms-bw-001-141120013134-conversion-gate01(1)Buildingworkmethodstatement cm-ms-bw-001-141120013134-conversion-gate01(1)
Buildingworkmethodstatement cm-ms-bw-001-141120013134-conversion-gate01(1)
Krm Chari
 
Delhi metro presention
Delhi   metro presentionDelhi   metro presention
Delhi metro presention
Dharmendra Kumar
 
HV Transmission line specifications
HV Transmission line specificationsHV Transmission line specifications
HV Transmission line specifications
Hilal Bhat
 
Village networking ppt
Village networking pptVillage networking ppt
Village networking ppt
Patel Tapan
 
Concrete method rev02
Concrete method rev02Concrete method rev02
Concrete method rev02Minh Bui Si
 
Metroppt
MetropptMetroppt
Escalator replacement specifications rev 2 consolidated comments
Escalator replacement specifications   rev 2 consolidated commentsEscalator replacement specifications   rev 2 consolidated comments
Escalator replacement specifications rev 2 consolidated comments
gulilero
 

Similar to GADFORROB.pdf (20)

Tes p-122.08-r0
Tes p-122.08-r0Tes p-122.08-r0
Tes p-122.08-r0
 
Design Example_Prestressed Concrete Girder Bridge.pdf
Design Example_Prestressed Concrete Girder Bridge.pdfDesign Example_Prestressed Concrete Girder Bridge.pdf
Design Example_Prestressed Concrete Girder Bridge.pdf
 
Design of Elevated Viaduct.pptx
Design of Elevated Viaduct.pptxDesign of Elevated Viaduct.pptx
Design of Elevated Viaduct.pptx
 
0400 Series - Safetydfsdfsdf Fencing & Parapets.doc
0400 Series - Safetydfsdfsdf Fencing & Parapets.doc0400 Series - Safetydfsdfsdf Fencing & Parapets.doc
0400 Series - Safetydfsdfsdf Fencing & Parapets.doc
 
5 (1)
5 (1)5 (1)
5 (1)
 
PWD Road cutting Trenching of PWD roads by KWA Modified Guidelines 14.02.202...
PWD Road cutting Trenching of PWD roads by KWA  Modified Guidelines 14.02.202...PWD Road cutting Trenching of PWD roads by KWA  Modified Guidelines 14.02.202...
PWD Road cutting Trenching of PWD roads by KWA Modified Guidelines 14.02.202...
 
7251
72517251
7251
 
Lrr new alignment
Lrr new alignmentLrr new alignment
Lrr new alignment
 
viewNitPdf_3777461.pdf
viewNitPdf_3777461.pdfviewNitPdf_3777461.pdf
viewNitPdf_3777461.pdf
 
Irs concrete bridge code
Irs concrete bridge codeIrs concrete bridge code
Irs concrete bridge code
 
Building work method statement cm - ms- bw - 001
Building work method statement  cm - ms- bw - 001Building work method statement  cm - ms- bw - 001
Building work method statement cm - ms- bw - 001
 
Buildingworkmethodstatement cm-ms-bw-001-141120013134-conversion-gate01(1)
Buildingworkmethodstatement cm-ms-bw-001-141120013134-conversion-gate01(1)Buildingworkmethodstatement cm-ms-bw-001-141120013134-conversion-gate01(1)
Buildingworkmethodstatement cm-ms-bw-001-141120013134-conversion-gate01(1)
 
4880 5
4880 54880 5
4880 5
 
Delhi metro presention
Delhi   metro presentionDelhi   metro presention
Delhi metro presention
 
HV Transmission line specifications
HV Transmission line specificationsHV Transmission line specifications
HV Transmission line specifications
 
Village networking ppt
Village networking pptVillage networking ppt
Village networking ppt
 
Concrete method rev02
Concrete method rev02Concrete method rev02
Concrete method rev02
 
Metroppt
MetropptMetroppt
Metroppt
 
Escalator replacement specifications rev 2 consolidated comments
Escalator replacement specifications   rev 2 consolidated commentsEscalator replacement specifications   rev 2 consolidated comments
Escalator replacement specifications rev 2 consolidated comments
 
785
785785
785
 

Recently uploaded

ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
BrazilAccount1
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
ongomchris
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 

Recently uploaded (20)

ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 

GADFORROB.pdf

  • 1. SANCTION OF CRS TO BE OBTAINED PRIOR TO EXECUTION OF THE WORK. General Notes 1. Unless otherwise specified, all measurements are shown in mm and levels are shown in meters. 2. The foundation levels shown in the drawing are to be verified at site based on confirmatory subsoil investigation prior to commencement of work. 3. Max pressure on the soil at foundation level is specified in concerned detailed drawings pertaining to foundations. 4. The bridge shall be designed to IRC class 'A' loading or 70R loading or 385T (S.V Loading) whichever gives worst effect for the given carriageway width as per IRC standards. 5. Stair cases are to be provided on both sides of the ROB outside railway boundary to suit pedestrian traffic (wherever footpaths are provided). 6. 4.00m wide strip with polysulphide paint preferably in black colour shall be provided on the soffit of deck and footpath slabs over running tracks. 7. Guard rails shall be provided on tracks below ROB. 8. No construction joint shall be allowed in concrete work unless it is specified in detailed drawings as per design considerations. 9. The details, type and dimensions of foundations, & sub-structure and super structure elements shown in the drawing are indicative and may vary as per actual design and detailed drawings. However obligatory clearances mentioned in the drawings shall not be reduced under any circumstances without prior approval of CBE. 10.High containment crash barrier of 1.80m height within Railway boundary and 1.50m height in approaches beyond Railway boundary for minimum length of 90.00m above footpath level shall be provided as per IRC 5&6 guide lines. 11.The land boundaries indicated in the drawing here may not reflect the actual Railway boundary and reckoning actual land. The certified land plan as available in HQ of divisional offices only is the final authority. The land boundaries shown in this plan cannot be of authority for this purpose. Specification and design related notes: 1. The grade of concrete for various RCC/Mass concrete works, & grade of steel for composite structures shall be in accordance with IRS concrete bridge code 1997 & new I.S.456-2000 and IRC Codes & specifications etc. 2. Expansion joints shall be strip seal joints as per MORTH specifications. Confined POT Bearings shall mandatory be provided for spans exceeding 30.0m. 3. Elastomeric/Pot-Ptfe Bearings shall be as per MORTH standards and specifications. 4. Protective coatings for reinforcement against corrosion should be provided as per latest correction slip of IRS concrete bridge code edition. 5. Drainage spouts shall be provided 2.00m away from the center line of existing / future track considering the traction / future traction and same has to be ensured in the detailed drawings and by the Engineer-in-charge at site. 6. During construction a minimum clearance of 2575mm to be maintained between centre line of existing track to the face of Temporary Arrangements Structure. 7. Variation of transverse slopes shall be maintained in deck/superstructure only. Under any circumstances, wearing coat thickness should not exceed 80mm thick during execution and maintenance period. This shall be ensuring by Road authority under Railway supervision from time to time”. 8. Bridge is to be designed assuming exposure condition as moderate. 9. Provision of clamps in the superstructure for supporting the traction wire to be made in communication with concerned authority. Reference notes/ Drawings: 1. Wearing coat with uniform thickness, and misc. items such as drainage spouts with grating arrangements etc., shall be similar to MORTH drawing No.SD/205. Location of drainage spouts shall invariably be shown in detailed drawings. 2. Expansion joints, Elastomeric & Confined POT/PTFE bearings shall be procured only from pre-qualified manufacturers of MORTH. Warranty and maintenance conditions on these items have to be ensured as per MORTH guidelines/circulars issued from time to time. 3. For 36.0m composite super structure refer DRg. Nos: RDSO/B-10775, to 10775/12. 4. for 18.0m composite girder super structure refer drawing no. RDSO/B-11772 to RDSO/B-11772/12, RDSO/B-11776 series and CBS-0044 IMPORTANT NOTES: 1. A common bench mark should be established by Railways and Road Authority Engineers before starting the work. 2. Concerned Road Authority (NHAI) has to enter an MOU with south central Railway. as per draft MOU vetted by PCE office before commencement of the work. PCE office will coordinate to finalize the draft copy of MOU. ROB work in Railway portion shall be commenced accordingly as per terms and conditions of MOU. MOU shall be signed in triplicate. Original shall be retained by PCE office. Duplicate and Triplicate copies shall be retained with NHAI and Devision. 3. Concerned Road Authority has to submit Completion Drawings of Detailed drawings & GAD and final design in original (drawings in cloth tracing) duly signed by them and Railway Divisional officials after immediate completion of the work in accordance with para 911 of Indian Railway Works Manual. 4. Load test has to be carried out in presence of NHAI & Railway Authorities immediately after completion of the superstructure considering the provisions of IRC SP 51-2015 - Guide lines for load testing of Bridges. 5. All the records of Quality Assurance / Quality Control, testing of the materials and satisfactory completion of an activity shall be maintained at site by the Contractor's Engineer and Supervising Engineers. On the basis of the records, Railways Engineers shall do stage wise clearance. Without such stage clearance, the work in the next stage of construction shall be not allowed by the Railway Supervisor, unless proper system of check and exercise is followed at the site. 6. CRS permission shall be obtained prior to commencement of work considering para 1202 {Clause-2(g)} of Indian Railway P.Way Manual. 7. Safety Pre-Cautions and Measures to be observed during execution of ROB shall be finalized by Vijayawada Division with the concerned road authority before commencement of work as per Railway Board Directives communicated to Divisions vide letter no: W- 71/BR/Safety/General dated: 16.11.2009. 8. Narrow road over bridges having width of deck less than approaches, traffic safety measures on approaches to narrow road over bridges shall be provided by concerned road authority as per MORTH letter No.RW/NH/33044/23/2007-S&R® Dated: 31-10-2008. Concerned Railway Division has to ensure it. 9. Procedural guidelines of Annexure-II and Annexure-I etc. issued by Railway Board vide their letter No.2001/CE-I/Misc/NH/4 Pt.III dated: 28.06.2010 shall be ensured during submission of proposal and during execution etc. 10.The scope of Railway supervision is main span of 3x36.0 composite+1x18.0mts composite (RDSO standard span). And the piers over which the main span is resting. The arrangement of approach spans beyond Railway boundary shall not be changed without prior permission of Railways as approved in the drawing. 11.The substructure and foundation shall be designed by considering RDSO standard drawings bearing Drg. Nos RDSO/B-11772 to RDSO/B-11772/12 for 18.0m.and RDSO/B-10775/R to RDSO/B-10775/12 for 36.0m. 12.Para 1851 to 1853, 1033, 1617 & 1618 etc. of Indian Railway Code for Engineering Department mutatis-mutandis will apply for these works and Concerned Road Authority/Railway Division has to ensure it from time to time. 13.This approval is subjected deposition of way leave charges, land leave charges and other charges as per extant Railway norms. 14.(a) As per clause A-3 of Memorandum dt.10/11/14 entered between ministry of Railways and ministry of Transport and Highways. NHAI has to develop instrumentation scheme. Accordingly, NHAI has to submit detailed instrumentation in monitoring system as part of design & drawings before commencement of the work. (b)NHAI shall do the instrumentation in the Railway super structure across the Railway bridge portion NHAI has to develop maintenance & inspection manual to maintain the ROB from time to time. NHAI also has to develop instrumentation system of ROB. The same have to be ratified by Railways. NHAI has to submit periodical reports of the instrumentation system of super structure and bearings from time to time Annual basis or the period specified by the railway division whichever less is. 15.Design of bearing is dependent on time period and flexibility of substructure. Therefore, the design of bearing shall be considered as part of substructure for which the seismic forces are computed by considering time period of whole structure. 16.The inspection of steel composite girders of ROB shall be done as per railway board letter no: 2016/54/CE-III/BR/RDSO/MISC. Date: 15/07/2019 (Composite girder) 17.As per Railway board Lr. No: 2015/CE-IV/ROB/78 Pt. Date:07/12/2020 if work was not started after approval of GAD, The GAD needs to be revalidate after a reasonable period of 2 years to match the prevailing ground situation. 18.Inspection of steel girder for ROB'S shall be done by RDSO (both at workshop & site) as per railway board letter no. 2016/54/CE-III/BR/RDSO/MISE Date: 15/07/2019 19.Height gueges need to be provided at starting of approaches in case of bowstring arrangement. 20.Proposed RCL indicated will be tentative approaches including approach span shall not be taken until finalization of detailed design and drawings including launching scheme of main span crossing over railway track with bowstring type superstructure (bowstring girder). 21. Fixing of any electrical or communications cable, ducts, lighting mast/polls, boards etc.,over the crash barrier/parapet in the railway portion of the viaduct is not permitted without prior approval of railway division officials. 22.Necessary reposition has to be made by road authorities (NHAI/MORTH) for shifting of railway assets temporaing/permanenthy due to construction of ROB to railways before and during execution of ROB work. DESCRIPTION 0.065 RAIL TOP LVL. (EXIST. TRACK) LEVELS MIN. VERTICAL CLEARANCE 6.55M WEARING COAT THK. M M M UNITS PROPOSED FRL CALCULATIONS CROSS FALL OR CAMBER M 0.3825 97.220 DEPTH OF GIRDER INCLUDING SLAB (18.0M / 36.0M) M 1.165/1.881 ℄OF EXPANSION JOINT ℄OF EXPANSION JOINT (80MM) P3 P2 FINISHED ROAD LEVEL A2 93.014 FOUNDATION BOTTOM LEVEL P2 P1 TO CHITRAKOOT HALF PLAN AT TOP HALF PLAN AT BOTTOM RE WALL RE WALL APPROACH TO MOHANGANJ SLAB (SCALE 1:150) TO CHITRAKOOT SECTION ELEVATION (RAILWAY PORTION) ( SCALE 1:150) 36 M STANDARD GIRDER AS PER RDSO SPAN (RDSO/B-11775) A1 106.100 94.068 RE WALL RAILWAY BOUNDARY ℄OF PIER CHAINAGE 43+578.7 43+541.7 43+504.7 43+633.7 106.100 106.100 106.100 94.750 95.414 26.973 GROUND LVL. 1. 2. 3. 4. G.L G.L RAILWAY BOUNDARY 43+560 95.711 BORE HOLE-1 BORE HOLE-1 32000 53000 PILE CAP TOP LVL. PILE CAP CUT LVL. 5100 3600 750 750 DIVERTED CANAL /DRAIN G.L FRL.103.328 ℄OF BEARING 2.50 % SLOPE PILE Ø1200(TYP.) RE WALL ℄OF EXPANSION JOINT (80MM) 5100 3600 750 750 1500 2000 330 ℄ O F E X IS T IN G T R A C K 53000 SQ 56771 SK 32000 SQ 3428 SK RAILWAY BOUNDARY ℄ F U T U R E T R A C K PILE CAP TOP LVL. PILE CAP CUT LVL. 5100 3600 750 750 ℄OF BEARING ℄OF BEARING 36700 SQ 39311 SK (OVERALL LENGTH OF STEEL GIRDER) 37000 SQ 39632SK(C/C OF EJ.) 36000 SQ 38560 SK 2.50 % SLOPE PILE Ø1200(TYP.) RE WALL 5100 3600 750 750 36 M STANDARD GIRDER AS PER RDSO SPAN (RDSO/B-11775) ℄OF TRACK ℄FUTURE TRACK ℄FUTURE TRACK 7800 SQ 8355 SK ℄OF EXPANSION JOINT ℄OF EXPANSION JOINT (80MM) A1 P1 ℄OF EXPANSION JOINT (80MM) 9695 SQ 10385 SK TO MOHANGANJ 5100 '1' '2' 7 5 0 3 6 0 0 3 6 0 0 7 5 0 3 6 0 0 1 2 3 0 0 5100 5100 SQ 5463 SK G.L PILE CAP TOP LVL. PILE CAP CUT LVL. 5100 3600 750 750 ℄OF BEARING 18700 SQ 20030 SK (OVERALL LENGTH OF STEEL GIRDER) 19080 SQ 20437 SK(C/C OF EJ.) 18000 SQ 19281 SK C/C OF BRG. EXISTING CANAL / DRAIN RAILWAY BOUNDARY EXISTING CANAL / DRAIN DIVERTED 22262 SQ 23846 SK 12540 SQ 13454 SK 33540 SQ 35926 SK 1460 SQ 1564 SK 16869 6550 (MIN. VERTICAL CLEARANCE) 20° 21° '3' RE WALL BORE HOLE-2 5100 5100 7 5 0 3 6 0 0 3 6 0 0 7 5 0 3 6 0 0 1 2 3 0 0 7 5 0 S Q 8 0 3 S K 3 6 0 0 S Q 3 8 5 6 S K 1 2 3 0 0 S Q 1 3 1 7 5 S K BORE HOLE-2 A2 2000 9695 SQ 10385 SK 7800 SQ 8355 SK 36700 SQ 39311 SK (OVERALL LENGTH OF STEEL GIRDER) 37000 SQ 39632SK(C/C OF EJ.) 36000 SQ 38560 SK 36700 SQ 39311 SK (OVERALL LENGTH OF STEEL GIRDER) 37000 SQ 39632SK(C/C OF EJ.) 36000 SQ 38560 SK 7800 SQ 8355 SK 36000 SQ 38560 SK 36000 SQ 38560 SK 36000 SQ 38560 SK 18000 SQ 19281 SK 3 6 0 0 S Q 3 8 5 6 S K 3 6 0 0 S Q 3 8 5 6 S K 7 5 0 S Q 8 0 3 S K 7 5 0 S Q 8 0 3 S K 3 6 0 0 S Q 3 8 5 6 S K 1 2 3 0 0 S Q 1 3 1 7 5 S K 3 6 0 0 S Q 3 8 5 6 S K 3 6 0 0 S Q 3 8 5 6 S K 7 5 0 S Q 8 0 3 S K 7 5 0 S Q 8 0 3 S K 3 6 0 0 S Q 3 8 5 6 S K 1 2 3 0 0 S Q 1 3 1 7 5 S K 3 6 0 0 S Q 3 8 5 6 S K 3 6 0 0 S Q 3 8 5 6 S K 7 5 0 S Q 8 0 3 S K 7 5 0 S Q 8 0 3 S K 3 6 0 0 S Q 3 8 5 6 S K 1 2 3 0 0 S Q 1 3 1 7 5 S K 3 6 0 0 S Q 3 8 5 6 S K 3 6 0 0 S Q 3 8 5 6 S K 7 5 0 S Q 8 0 3 S K 7800 SQ 8355 SK 9695 SQ 10385 SK 95.200 43+615.7 106.100 P3 94.137 94.188 95.180 94.068 95.501 96.052 96.440 93.121 93.003 RAILWAY BRIDGE 49 '3' T O U N C H A H A R T O P H A P H A M A U / P R A Y A G R A J ℄ F U T U R E T R A C K ℄ F U T U R E T R A C K ℄ F U T U R E T R A C K ℄ E X IS T IN G T R A C K 9695 SQ 10385 SK 9695 SQ 10385 SK 7800 SQ 8355 SK 7800 SQ 8355 SK 9695 SQ 10385 SK 18 M STANDARD GIRDER AS PER RDSO SPAN (RDSO/B-11772) RTL 43+515 43+525 43+550 43+570 43+590 43+600 43+610 43+525 43+620 97.220 (RECHANNELISED ) RE 26/13 RE 26/11 3 6 5 0 0 *^ 5 8 7 0 0 ^^ 21 90 0 *^ *^ = DISTANCE OF OHE MAST FROM ROB EDGE ABOVE ^^ = DISTANCE OF OHE MAST TO OHE MAST 6 2 9 0 0 ^^ 54801.2 ^^ 48247.7 *^ 6553.5 *^ 7546.5 *^ 5872.22 ^^ 24646.5*^ 34075.7*^ CENTER LINE OF EXISTING TRACK RE 26/12 ABRIVATION:- F.R.L FINISHED ROAD LEVEL LVL. TYP. CENTER LINE LEVEL TYPICAL C L THK. THICK C/C G.L CENTER TO CENTER GROUND LEVEL FDN. FOUNDING LEVEL EXP. EXPANSION BRG. BEARING SYMM. SYMMETRICAL SQ SQUARE DIMENSION SK. SKEW DIMENSION BH BORE HOLE FEATURES PROPOSED WORK RED COLOUR TO BE DISMANTLE GREEN BLUE FUTURE EXIST. RAILWAY TRACK BLACK PROP. RAILWAY TRACK GREEN 300 1500 500 250 1500 10500 CARRIAGE WAY 500 250 2500 2500 2500 2500 2500 SHY DISTANCE CRASH BARRIER RAILING FOOT PATH 15300 SQ 16389 SK 300 1500 500 250 1500 10500 CARRIAGE WAY 500 250 SHY DISTANCE CRASH BARRIER RAILING FOOT PATH 15300 SQ 16389 SK 2500 2500 2500 2500 2500 750 3600 750 12300 FOUNDATION AS PER DESIGN FND. LVL. FND. LVL. (SCALE 1:120) SECTION AT A-A (ABUTMENT) 15300 (SCALE 1:150) 750 750 1500 2500 1650 7000 2500 3600 3600 PILE TOP LVL. PILE TOP LVL. GROUND LVL. AS PER HIGHWAY PROFILE 2500 1650 7000 1650 2500 REWALL 2.5% SLOPE 2.5% SLOPE 750 12300 FOUNDATION AS PER DESIGN 3600 3600 3600 1825 1825 1825 1825 ABUTMENT CAP PLAN 1650 1600SQ 1714SK 2500SQ 2678SK 1200SQ 1285SK 15300 SQ/16389 SK ℄ OF BRG. JACKING LOCATION (TYP.) ℄ OF EXP.JOINT 1800SQ 1928SK 2500SQ 2678SK 2500SQ 2678SK 2500SQ 2678SK 2500SQ 2678SK 1600SQ 1714SK 2500SQ 2678SK 1200SQ 1285SK 15300 SQ/16389 SK 2500SQ 2678SK 2500SQ 2678SK 2500SQ 2678SK 2500SQ 2678SK GAD NEED TO BE REVALIDATED AFTER A REASONABLE PERIOD OF 2 YEARS TO MATCH THE PREVAILING GROUND SITUATION. GAD NEED TO BE REVALIDATED AFTER A REASONABLE PERIOD OF 2 YEARS TO MATCH THE PREVAILING GROUND SITUATION. # FRL SHALL BE DECIDED AS PER RTL MAINTAINING MIN. CLEARANCE OF 6.50M BETWEEN RTL & GIRDER BOTTOM LEVEL. DEPTH (M) STRATA BH A1(R.L.97.100m) DESCRIPTION SILTY WITH GRAVEL SAND AND GRAVELLY CLAY WITH SAND SILT WITH GRAVEL FINE SAND AND SILT DETAILS OF BORE HOLE 43+500 43+600 43+700 43+800 EXISTING BRIDGE NO. 49 CANAL TO BE RETAINED AT ABUTMENT PIER LOCATION PROPOSED ROB DRAIN 26.973 510 0 10951 510 0 123 00 (SCALE 1:50) DETAIL-'2' 1631 250 1881 DEPTH (M) STRATA DESCRIPTION SILTY WITH GRAVEL SILTY CLAY SILTY CLAY WITH GRAVEL SILT SAND WITH GRAVEL SILTY CLAY WITH GRAVEL GRAVEL WITH SILT BH P3(R.L.97.100m) 300 1500500 250 1500 10500 CARRIAGE WAY 500 250 2500 2500 2500 2500 2500 SHY DISTANCE CRASH BARRIER RAILING FOOT PATH 15300 300 1500 500 250 1500 10500 CARRIAGE WAY 500 250 SHY DISTANCE CRASH BARRIER RAILING FOOT PATH 15300 2500 2500 2500 2500 2500 (SCALE 1:120) 15300 750 750 1500 2500 2150 2150 2500 GROUND LVL. GROUND LVL. AS PER HIGHWAY PROFILE 2500 2150 2150 2500 2.5% SLOPE 2.5% SLOPE 6000 6000 (SCALE 1:150) PIER CAP PLAN ℄ OF BRG. ℄ OF EXP.JOINT 2330SQ 2496SK 1600SQ 1714SK 2500SQ 2678SK 1200SQ 1285SK 2500SQ 2678SK 2500SQ 2678SK 2500SQ 2678SK 2500SQ 2678SK 750 3600 750 3600 3600 750 3600 3600 3600 SECTION AT B-B (PIER) 15300 SQ/16389 SK 1600SQ 1714SK 2500SQ 2678SK 1200SQ 1285SK 2500SQ 2678SK 2500SQ 2678SK 2500SQ 2678SK 2500SQ 2678SK 15300 SQ/16389 SK PILE TOP LVL. PILE TOP LVL. 330 1631 250 1881 2000 1650 (SCALE 1:50) DETAIL-'1' 750 750 330 915 250 1165 2000 1650 (SCALE 1:50) DETAIL-'4' 750 750 (SCALE 1:50) DETAIL-'3' 915 250 1165 1631 250 1881 KEY PLAN GAD FOR CONSTRUCTION OF 4-LANE GREEN FIELD HIGHWAY FROM Km 35.000 TO KM 49.155 (AUTARPUR TO SINGARAUR UPHAR) OF NH -731A AT RAILWAY KM 26KM 750M 26/12 TP. Consultancy Services for Feasibility Study & Preparation of Detailed Project Report for improvement & up-gradation of in principle & newly declared National Highways in the state of Uttar pradesh. Package-II (i) Stretch from Near Pratapgarh(NH-31) - Jethwada - Shrangvepur-Manjhanpur-Rajapur - Near Chitrakoot (NH-35) & Length -160.000Km DWG NO: ARKI/MORT&H/UP-17358/NH-731A/ROB/GAD/101 NORTHERN RAILWAY CLIENT: AUTHORITY OF WORK DATE: JUNE 2022 PAPER SIZE: A0 SCALE : AS SHOWN REVISION : R2 DIVISION: SECTION: PHAPHAMAU-UNCHAHAR PROPOSED ID : NRLK00040 LUCKNOW Arkitechno Consultants(I) Pvt.Ltd. N3/91, I.R.C Village, Near Maharishi Public School,Nayapalli, Bhubaneswar- 751015.Odisha Telephone :+91 674 2554 205; Fax:+91 674 2553689 DESIGN CONSULTANTS DRG. NO. DRAWING TITLE: CHECKED BY: A.A DRAWN BY : D.R EE,UPPWD NH-DIVISION-1 DRM Sr. DEN / COORDINATION Sr. DEE (TRD) Sr. DSTE Sr. DOM Sr. DEN / 6 PRAYAGRAJ NR NR NR NR NR NR ADRM NR THE FEASIBILITY OF PROPOSED PLAN IS BEING CHECKED AT SITE AND FOUND CORRECT SSE / WORKS / PRG SSE / P. WAY / PRG ADEN / PRG FOR SITE FEASIBILITY STUDY :- CBE DY. CE / ROB