2. You are leading a large project that involves many stakeholders. You want to get two new team
members up to speed with the overall dynamics of the project and engage effectively with the
project stakeholders.
What should you do?
A. Ask the team members to record any issues they encounter into the issue log
B. Review the stakeholder register with the new team members
C. Schedule a meeting with the new team members and all project stakeholders
D. Submit a change request to update the stakeholder engagement plan
HINT: What document lists people or organizations either positively or negatively impacted by a
decision, activity or outcome of the project?
Question
3. The correct answer is B.
The stakeholder register is a project document that contains all current information about the
stakeholders. The stakeholder register includes the stakeholder identification information,
assessment information, and stakeholder classification. It is used by the project team to maintain
information about the stakeholder's expectations and interests with the project.
By reviewing the stakeholder register with the new team members, the project manager can
provide them with the information about each project stakeholder, politics surrounding the
project, and other relevant details about the project and the stakeholders that may help the new
team members to get up to speed with the overall dynamics of the project and engage
effectively with the project stakeholders.
Answer
4. All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge
(PMBOK® Guide) standard.