SlideShare a Scribd company logo
1 of 5
Download to read offline
PMP EXAM
SAMPLE Q & A
A project is six months into its nine-month projected duration. The project manager reports that
the project is at least three months behind schedule because certain key stakeholders were
resistant to consequential changes due to the project.
What might have been done differently during project planning to avoid this situation?
A. Better execution of the Manage Stakeholder Engagement process
B. Development of a stakeholder engagement assessment matrix
C. Creation of a comprehensive stakeholder register
D. Establishment of a more robust communications management plan
HINT: Which among the answer choices represent activities that might be performed during the
Planning Process Group?
Question
The stakeholder engagement assessment matrix is used as a tool during the Plan Stakeholder Engagement
process and identifies key stakeholders along with their current and desired engagement level. Classifications
for stakeholder engagement may include unaware, resistant, neutral, supportive, and leading.
The correct answer is B.
The scenario describes a situation where the resistance of certain key stakeholders has caused the project to
run behind schedule and is asking what might have been done differently during project planning.
Two of the answer choices represent activities, which are not associated with the Planning Process Group, and,
as a result, those responses can be eliminated. Both of the remaining answer choices represent plausible
actions that may have led to better stakeholder engagement.
The actual PMP exam may present questions with more than one correct answer, and the PMP aspirant must
select the 'best' answer among the potentially correct options. In this case, the development of the stakeholder
engagement assessment matrix directly addresses the issue described by the question.
Answer
Therefore, among the available options, the development of a stakeholder engagement assessment matrix is
the best answer to the question asked.
In this scenario, certain key stakeholders were resistant to the project, which caused the project to run behind
schedule. A stakeholder engagement assessment matrix is the best tool for identifying resistant stakeholders
with enough influence to undermine a project.
In this case, identifying the current and desired engagement levels of the key stakeholders might have allowed
the project manager to take action to address the undesirable engagement levels and prevent the
stakeholder's resistance from negatively impact the project's performance.
Answer
All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge
(PMBOK® Guide) standard.
Stop by at free.pm-exam-simulator.com/ and try the
PM Exam Simulator free for 7 days.
We are a trusted and experienced education provider.

More Related Content

Similar to Free PMP Exam Sample Question

PMP Certification Training Course Part-64
PMP Certification Training Course Part-64PMP Certification Training Course Part-64
PMP Certification Training Course Part-64Skillogic Solutions
 
01 pmp introduct to project management exam
01 pmp introduct to project management exam01 pmp introduct to project management exam
01 pmp introduct to project management examJamil Faraj , PMP
 
CHAPTER SIXTEENUnderstanding Context Evaluation and Measureme
CHAPTER SIXTEENUnderstanding Context Evaluation and MeasuremeCHAPTER SIXTEENUnderstanding Context Evaluation and Measureme
CHAPTER SIXTEENUnderstanding Context Evaluation and MeasuremeJinElias52
 
Identifying a project in trouble and re-planning
Identifying a project in trouble and re-planningIdentifying a project in trouble and re-planning
Identifying a project in trouble and re-planningmfarbstein
 
scope-statement-sample.doc
scope-statement-sample.docscope-statement-sample.doc
scope-statement-sample.docAhsanRahman13
 
Workbook for Designing a Process Evaluation
 Workbook for Designing a Process Evaluation  Workbook for Designing a Process Evaluation
Workbook for Designing a Process Evaluation MoseStaton39
 
Workbook for Designing a Process Evaluation .docx
Workbook for Designing a Process Evaluation .docxWorkbook for Designing a Process Evaluation .docx
Workbook for Designing a Process Evaluation .docxAASTHA76
 
Workbook for Designing a Process Evaluation
 Workbook for Designing a Process Evaluation  Workbook for Designing a Process Evaluation
Workbook for Designing a Process Evaluation MikeEly930
 
Pm0010 – interduction to project management
Pm0010 – interduction to project managementPm0010 – interduction to project management
Pm0010 – interduction to project managementsmumbahelp
 
1092019 New Transcript Templatemedia.capella.educoursem.docx
1092019 New Transcript Templatemedia.capella.educoursem.docx1092019 New Transcript Templatemedia.capella.educoursem.docx
1092019 New Transcript Templatemedia.capella.educoursem.docxaulasnilda
 
USER GUIDE M&E 2014 LENNY HIDAYAT
USER GUIDE M&E 2014 LENNY HIDAYATUSER GUIDE M&E 2014 LENNY HIDAYAT
USER GUIDE M&E 2014 LENNY HIDAYATLenny Hidayat
 
03 pmp project management processes exam
03 pmp project management processes exam03 pmp project management processes exam
03 pmp project management processes examJamil Faraj , PMP
 
Project Charter template (contains Scope Section) project nameExe.docx
Project Charter template (contains Scope Section)  project nameExe.docxProject Charter template (contains Scope Section)  project nameExe.docx
Project Charter template (contains Scope Section) project nameExe.docxstilliegeorgiana
 
Student 1 Hi,Project is a temporary goal that a team or an .docx
Student 1 Hi,Project is a temporary goal that a team or an .docxStudent 1 Hi,Project is a temporary goal that a team or an .docx
Student 1 Hi,Project is a temporary goal that a team or an .docxcpatriciarpatricia
 
Student 1 Hi,Project is a temporary goal that a team or an .docx
Student 1 Hi,Project is a temporary goal that a team or an .docxStudent 1 Hi,Project is a temporary goal that a team or an .docx
Student 1 Hi,Project is a temporary goal that a team or an .docxdeanmtaylor1545
 

Similar to Free PMP Exam Sample Question (20)

PMP Exam Q & A
PMP Exam Q & APMP Exam Q & A
PMP Exam Q & A
 
PMP Certification Training Course Part-64
PMP Certification Training Course Part-64PMP Certification Training Course Part-64
PMP Certification Training Course Part-64
 
01 pmp introduct to project management exam
01 pmp introduct to project management exam01 pmp introduct to project management exam
01 pmp introduct to project management exam
 
Exam1
Exam1Exam1
Exam1
 
Pmp1
Pmp1Pmp1
Pmp1
 
PMP Exam Sample Questions
PMP Exam Sample QuestionsPMP Exam Sample Questions
PMP Exam Sample Questions
 
CHAPTER SIXTEENUnderstanding Context Evaluation and Measureme
CHAPTER SIXTEENUnderstanding Context Evaluation and MeasuremeCHAPTER SIXTEENUnderstanding Context Evaluation and Measureme
CHAPTER SIXTEENUnderstanding Context Evaluation and Measureme
 
Identifying a project in trouble and re-planning
Identifying a project in trouble and re-planningIdentifying a project in trouble and re-planning
Identifying a project in trouble and re-planning
 
scope-statement-sample.doc
scope-statement-sample.docscope-statement-sample.doc
scope-statement-sample.doc
 
Workbook for Designing a Process Evaluation
 Workbook for Designing a Process Evaluation  Workbook for Designing a Process Evaluation
Workbook for Designing a Process Evaluation
 
Workbook for Designing a Process Evaluation .docx
Workbook for Designing a Process Evaluation .docxWorkbook for Designing a Process Evaluation .docx
Workbook for Designing a Process Evaluation .docx
 
Workbook for Designing a Process Evaluation
 Workbook for Designing a Process Evaluation  Workbook for Designing a Process Evaluation
Workbook for Designing a Process Evaluation
 
Pm0010 – interduction to project management
Pm0010 – interduction to project managementPm0010 – interduction to project management
Pm0010 – interduction to project management
 
PMBOK7-101-200.pdf
PMBOK7-101-200.pdfPMBOK7-101-200.pdf
PMBOK7-101-200.pdf
 
1092019 New Transcript Templatemedia.capella.educoursem.docx
1092019 New Transcript Templatemedia.capella.educoursem.docx1092019 New Transcript Templatemedia.capella.educoursem.docx
1092019 New Transcript Templatemedia.capella.educoursem.docx
 
USER GUIDE M&E 2014 LENNY HIDAYAT
USER GUIDE M&E 2014 LENNY HIDAYATUSER GUIDE M&E 2014 LENNY HIDAYAT
USER GUIDE M&E 2014 LENNY HIDAYAT
 
03 pmp project management processes exam
03 pmp project management processes exam03 pmp project management processes exam
03 pmp project management processes exam
 
Project Charter template (contains Scope Section) project nameExe.docx
Project Charter template (contains Scope Section)  project nameExe.docxProject Charter template (contains Scope Section)  project nameExe.docx
Project Charter template (contains Scope Section) project nameExe.docx
 
Student 1 Hi,Project is a temporary goal that a team or an .docx
Student 1 Hi,Project is a temporary goal that a team or an .docxStudent 1 Hi,Project is a temporary goal that a team or an .docx
Student 1 Hi,Project is a temporary goal that a team or an .docx
 
Student 1 Hi,Project is a temporary goal that a team or an .docx
Student 1 Hi,Project is a temporary goal that a team or an .docxStudent 1 Hi,Project is a temporary goal that a team or an .docx
Student 1 Hi,Project is a temporary goal that a team or an .docx
 

More from OSP International LLC

Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekOSP International LLC
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekOSP International LLC
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekOSP International LLC
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekOSP International LLC
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekOSP International LLC
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekOSP International LLC
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekOSP International LLC
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekOSP International LLC
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekOSP International LLC
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekOSP International LLC
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekOSP International LLC
 
Free CAPM Exam Sample Question of the Week!
Free CAPM Exam Sample Question of the Week!Free CAPM Exam Sample Question of the Week!
Free CAPM Exam Sample Question of the Week!OSP International LLC
 
Free PMP Exam Sample Question of the Week!
Free PMP Exam Sample Question of the Week!Free PMP Exam Sample Question of the Week!
Free PMP Exam Sample Question of the Week!OSP International LLC
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekOSP International LLC
 
Free PMP Exam Sample Question from the PM Exam Simulator
Free PMP Exam Sample Question from the PM Exam SimulatorFree PMP Exam Sample Question from the PM Exam Simulator
Free PMP Exam Sample Question from the PM Exam SimulatorOSP International LLC
 
Free CAPM Exam Sample Question from the PM Exam Simulator
Free CAPM Exam Sample Question from the PM Exam SimulatorFree CAPM Exam Sample Question from the PM Exam Simulator
Free CAPM Exam Sample Question from the PM Exam SimulatorOSP International LLC
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekOSP International LLC
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekOSP International LLC
 
Free PMP Exam Sample Question from The PM Exam Simulator
Free PMP Exam Sample Question from The PM Exam SimulatorFree PMP Exam Sample Question from The PM Exam Simulator
Free PMP Exam Sample Question from The PM Exam SimulatorOSP International LLC
 
Free CAPM Exam Sample Question of the Week!
Free CAPM Exam Sample Question of the Week!Free CAPM Exam Sample Question of the Week!
Free CAPM Exam Sample Question of the Week!OSP International LLC
 

More from OSP International LLC (20)

Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free CAPM Exam Sample Question of the Week!
Free CAPM Exam Sample Question of the Week!Free CAPM Exam Sample Question of the Week!
Free CAPM Exam Sample Question of the Week!
 
Free PMP Exam Sample Question of the Week!
Free PMP Exam Sample Question of the Week!Free PMP Exam Sample Question of the Week!
Free PMP Exam Sample Question of the Week!
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 
Free PMP Exam Sample Question from the PM Exam Simulator
Free PMP Exam Sample Question from the PM Exam SimulatorFree PMP Exam Sample Question from the PM Exam Simulator
Free PMP Exam Sample Question from the PM Exam Simulator
 
Free CAPM Exam Sample Question from the PM Exam Simulator
Free CAPM Exam Sample Question from the PM Exam SimulatorFree CAPM Exam Sample Question from the PM Exam Simulator
Free CAPM Exam Sample Question from the PM Exam Simulator
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 
Free PMP Exam Sample Question from The PM Exam Simulator
Free PMP Exam Sample Question from The PM Exam SimulatorFree PMP Exam Sample Question from The PM Exam Simulator
Free PMP Exam Sample Question from The PM Exam Simulator
 
Free CAPM Exam Sample Question of the Week!
Free CAPM Exam Sample Question of the Week!Free CAPM Exam Sample Question of the Week!
Free CAPM Exam Sample Question of the Week!
 

Recently uploaded

Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon AUnboundStockton
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfchloefrazer622
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppCeline George
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting DataJhengPantaleon
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesFatimaKhan178732
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3JemimahLaneBuaron
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application ) Sakshi Ghasle
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxmanuelaromero2013
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingTechSoup
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
Concept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfConcept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfUmakantAnnand
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentInMediaRes1
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 

Recently uploaded (20)

Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon A
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdf
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website App
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and Actinides
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application )
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptx
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy Consulting
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
Concept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfConcept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.Compdf
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media Component
 
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 

Free PMP Exam Sample Question

  • 2. A project is six months into its nine-month projected duration. The project manager reports that the project is at least three months behind schedule because certain key stakeholders were resistant to consequential changes due to the project. What might have been done differently during project planning to avoid this situation? A. Better execution of the Manage Stakeholder Engagement process B. Development of a stakeholder engagement assessment matrix C. Creation of a comprehensive stakeholder register D. Establishment of a more robust communications management plan HINT: Which among the answer choices represent activities that might be performed during the Planning Process Group? Question
  • 3. The stakeholder engagement assessment matrix is used as a tool during the Plan Stakeholder Engagement process and identifies key stakeholders along with their current and desired engagement level. Classifications for stakeholder engagement may include unaware, resistant, neutral, supportive, and leading. The correct answer is B. The scenario describes a situation where the resistance of certain key stakeholders has caused the project to run behind schedule and is asking what might have been done differently during project planning. Two of the answer choices represent activities, which are not associated with the Planning Process Group, and, as a result, those responses can be eliminated. Both of the remaining answer choices represent plausible actions that may have led to better stakeholder engagement. The actual PMP exam may present questions with more than one correct answer, and the PMP aspirant must select the 'best' answer among the potentially correct options. In this case, the development of the stakeholder engagement assessment matrix directly addresses the issue described by the question. Answer
  • 4. Therefore, among the available options, the development of a stakeholder engagement assessment matrix is the best answer to the question asked. In this scenario, certain key stakeholders were resistant to the project, which caused the project to run behind schedule. A stakeholder engagement assessment matrix is the best tool for identifying resistant stakeholders with enough influence to undermine a project. In this case, identifying the current and desired engagement levels of the key stakeholders might have allowed the project manager to take action to address the undesirable engagement levels and prevent the stakeholder's resistance from negatively impact the project's performance. Answer
  • 5. All our questions are updated to the latest A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at free.pm-exam-simulator.com/ and try the PM Exam Simulator free for 7 days. We are a trusted and experienced education provider.