SlideShare a Scribd company logo
FPSO FLOATING
STRUCTURES
• MUHAMAD NAZHIIM ADLI BIN AZLI (TH18049)
• DANIAL ANZALLAH BIN ROZAMAN (TH20053)
• MOHAMAD HASSAN BIN M ALI (TH18016)
INTRODUCTION TO FPSO
• A floating vessel that can produce crude oil and gas is known as an FPSO (floating, production, storage, and off-loading
unit). There are two pieces to it: the topside and the hull.
• The FPSO, on the other hand, cannot generate oil and gas on the oil field by itself.
• As depicted in Figure 1, several offshore production systems are required, including subsea production systems (SPS),
umbilical, flow lines and risers (UFR), mooring lines, a shuttle tanker, and an off-loading buoy.
FIGURE 1: Offshore Production
System
• Figure 2 depicts a typical FPSO unit architecture.
• It is split into two sections: the topside and the hull.
• The flare tower, living quarters, lay-down area, mooring fairleads, and a helicopter deck are all part of an FPSO unit.
Figure 2: Typical Layout of an FPSO
Unit
INTRODUCTION TO THE NIGERIA FIELD DEVELOPMENT
PROJECT
• The Nigeria field is located in Nigeria's offshore region known as OPL 246, as depicted in Figure 3.
• The Nigeria field development project is made up of several important components.
• Nigerian National Petroleum Company (NNPC), South Atlantic Petroleum, Nigerian Company (Sapetro), Brazilian Oil
Company (Petrobras), and others.
• This project is primarily comprised of the FPSO, SPS, UFR, and offshore loading terminal (OLT), as seen in Figure 1.
• The methodologies utilised to develop the detailed design and construction of the FPSO hull are being examined in
order to aid future design and construction of FPSO hulls.
REASON FOR CHOOSING FPSO
STABILITY CALCULATION
• FPSO needs an ability to return to its undisturbed position
after the removal of the external force , called as Stability.
• It is a crucial because FPSO needs to remain float on the sea
floor or remains bouyant.
• FPSO must aqquired both static and dynamic stability.
STABILITY CALCULATION
MOORING SYSTEM
• Method for solving line dynamics: lumped mass method ( divides a mooring line into small segment
• Wind and current force important mooring load.
• Wind – consider dynamic, computed using mean wind speed associated recognized wind gust spectra
and wind load coefficients
• Current – consider static, computed using case of FOIs with ship shape hulls, formula from OCIMF
publication
MOORING SYSTEM CALCULATION
FPSO STRUCTURE INSTALLATION
• An exploration and feasibility study must first be completed before the field can be developed.
• Then, based on the study's findings, the front-end engineering design (FEED) of an FPSO is initiated if the economic value
of the field development is positive, taking into consideration the circumstances of the offshore market.
• Figure 3 shows the overall procedure of the FPSO field development of this study.
Figure 3: Overall procedure of
the FPSO field development in
this study
• Figure 4 depicts the detailed design method for the FPSO hull and the key detailed design tasks.
• The preparation of the piping and instrumentation diagram (P&ID) for each system or facility of the hull, as
illustrated in Figure 4, is at the heart of the detailed design.
Figure 4: Detailed design
procedure for P&ID of the
hull of an FPSO unit
• In general, hull scantlings are designed with two factors in mind: load (demand) and strength (capability).
• Loads are useful in strength equations and calculation techniques when permissible stresses reflect a desirable
strength level.
• Figure 5 depicts the comprehensive design method of the FPSO's hull structure and appurtenance supports, as well
as the primary detailed design tasks.
• The techniques for designing the hull and appurtenance supports, as illustrated in Figure 5, may be separated into
four components, which are as follows:
Figure 5: Detailed design
procedure for the hull of
FPSO
The pre-design phases are the same as the P&ID approach described above.
• Specification incorporation
• FEED clarification
• Incorporation of lessons learned from previous project
Hull scantling and strength analysis
• Priority tasks in the fundamental design process from IFR to IFC include longitudinal scantling and primary hull
strength analysis.
• The following are the fundamental design processes for hull scantling and strength analysis:
- Hull key plan drawing and calculation
- Appurtenance key drawing
- Strength analysis for hull and appurtenance supports
- Fatigue assessment for hull and appurtenance supports
- Impact analysis including design brief
Detailed structure drawings
• Based on the hull key plan and key drawing of appurtenances, detailed structure drawings may be created.
• These designs have been divided based on the structure's characteristics and have been updated with the outfitting
system.
Block production drawings
• Based on the hull construction drawings, block production drawings may be created and divided according to the block
division plan design.
- Block division
- Detailed assembly procedures (See Figure 6)
- Block fabrication drawings
- Welding map
- Non-destructive test plan
Figure 6: Detailed block assembly procedures
Procedure of the hull construction of an FPSO
• Figure 7 depicts the building methods for an FPSO's hull, which include the procurement stage, the dry dock stage,
and the on-shore stage.
• Raw materials such as steel are ordered in advance during the procurement stage, taking into consideration aspects
like as lead time (typically 60–180 days).
Figure 7: Detailed procedure of
the hull construction of an FPSO
unit
MAIN ACTIVITIES OF THE HULL CONSTRUCTION OF AN FPSO
Activities of the procurement stage
• After completing the basic and comprehensive design of an FPSO's hull, the first steel order is placed six months
before construction begins or steel cutting (W/C), taking into account the steel procurement lead time.
• The initial steel order contains bottom blocks, longitudinal bulkhead blocks, transverse bulkhead block plates, and
built-up elements that may be worked on ahead of time.
Activities of the dry dock stage
• The major tasks during the dry dock stage are the assembly of hull blocks, including L/Q, the installation of
appurtenances, and the loading of pipe racks.
• More information about this may be found below:
- Activities related to hull blocks
- Activities related to L/Q blocks
- Activities related to hull appurtenances
- Activities related to pipe racks
Activities of the on-shore stage
• After launching, the primary activities, such as hull cabling including L/Q, fire work, insulation/unit cabin installations,
pipe spool installation, and so on, are completed at the on-shore stage.
• If the total operation goes smoothly, the hull of the FPSO will be delivered following pre-commissioning and
commissioning. At this point, the on-shore interface work between the topside and the hull is critical for smoothly
hooking up SPS, which is installed in the field after sail away.
• Figure 8 depicts the launching of the FPSO's hull, which was fabricated by HSHI.
Figure 8: Launching and
dock out of the hull of an
FPSO unit
CONCLUSION
• This research delivers the following findings based on our extensive expertise with the technical design and
construction of an FPSO unit's hull.
• First, the FPSO field development strategy was investigated.
• Second, the comprehensive design techniques and activities of an FPSO unit's hull have been investigated.
• Third, the hull's construction techniques and activities have been investigated.
• Finally, crucial interaction work between systems and disciplines in hull building has been investigated.
• The aforementioned contents will be utilised as guidance to lessen M/H and cost implications on the design and
construction of future FPSO units' hulls.

More Related Content

What's hot

Harlem Park Building Design Project
Harlem Park Building Design ProjectHarlem Park Building Design Project
Harlem Park Building Design Project
Ed Guerra, P.E.
 
Horizontal Vessel Loading Calculation
 Horizontal Vessel Loading Calculation Horizontal Vessel Loading Calculation
Horizontal Vessel Loading Calculation
Fadhel AlMohammad
 
Understanding Stress Analysis Topics
Understanding Stress Analysis TopicsUnderstanding Stress Analysis Topics
Understanding Stress Analysis Topics
Zachary Swartz
 
Major structure - Decoded
Major structure - DecodedMajor structure - Decoded
Major structure - Decoded
ChandanKriss
 
La te-x3
La te-x3La te-x3
La te-x3
Asif Hussain
 
DESIGN AND ANALAYSIS OF MULTI STOREY BUILDING USING STAAD PRO
DESIGN AND ANALAYSIS OF MULTI STOREY BUILDING USING STAAD PRODESIGN AND ANALAYSIS OF MULTI STOREY BUILDING USING STAAD PRO
DESIGN AND ANALAYSIS OF MULTI STOREY BUILDING USING STAAD PRO
Ali Meer
 
Vertical vessel loading calculation
Vertical vessel loading calculationVertical vessel loading calculation
Vertical vessel loading calculation
Fadhel AlMohammad
 
WIND LOAD DESIGN OF STEEL STRUCTURE ON ROOF TOP UNDER QCS 2014 CASE STUDY : O...
WIND LOAD DESIGN OF STEEL STRUCTURE ON ROOF TOP UNDER QCS 2014 CASE STUDY : O...WIND LOAD DESIGN OF STEEL STRUCTURE ON ROOF TOP UNDER QCS 2014 CASE STUDY : O...
WIND LOAD DESIGN OF STEEL STRUCTURE ON ROOF TOP UNDER QCS 2014 CASE STUDY : O...
firdaus Muhammad Adnan
 
Six week software training ppt at Tcc Ludhiana
Six week software training ppt at Tcc LudhianaSix week software training ppt at Tcc Ludhiana
Six week software training ppt at Tcc Ludhiana
Gurjant Singh
 
Introduction to machine maintinance and installation
Introduction to machine maintinance and installationIntroduction to machine maintinance and installation
Introduction to machine maintinance and installation
technovic
 
Static load test method statement cm - ms- bw - 003
Static load test method statement  cm - ms- bw - 003Static load test method statement  cm - ms- bw - 003
Static load test method statement cm - ms- bw - 003
Minh Bui Si
 
multistorey building design by sap and autocad
multistorey building design by sap and autocadmultistorey building design by sap and autocad
multistorey building design by sap and autocad
Razes Dhakal
 
CFM 56-7B AGB LH FWD Mount Damper Change Tool
CFM 56-7B AGB LH FWD Mount Damper Change ToolCFM 56-7B AGB LH FWD Mount Damper Change Tool
CFM 56-7B AGB LH FWD Mount Damper Change Tool
Yassine Rayad
 

What's hot (13)

Harlem Park Building Design Project
Harlem Park Building Design ProjectHarlem Park Building Design Project
Harlem Park Building Design Project
 
Horizontal Vessel Loading Calculation
 Horizontal Vessel Loading Calculation Horizontal Vessel Loading Calculation
Horizontal Vessel Loading Calculation
 
Understanding Stress Analysis Topics
Understanding Stress Analysis TopicsUnderstanding Stress Analysis Topics
Understanding Stress Analysis Topics
 
Major structure - Decoded
Major structure - DecodedMajor structure - Decoded
Major structure - Decoded
 
La te-x3
La te-x3La te-x3
La te-x3
 
DESIGN AND ANALAYSIS OF MULTI STOREY BUILDING USING STAAD PRO
DESIGN AND ANALAYSIS OF MULTI STOREY BUILDING USING STAAD PRODESIGN AND ANALAYSIS OF MULTI STOREY BUILDING USING STAAD PRO
DESIGN AND ANALAYSIS OF MULTI STOREY BUILDING USING STAAD PRO
 
Vertical vessel loading calculation
Vertical vessel loading calculationVertical vessel loading calculation
Vertical vessel loading calculation
 
WIND LOAD DESIGN OF STEEL STRUCTURE ON ROOF TOP UNDER QCS 2014 CASE STUDY : O...
WIND LOAD DESIGN OF STEEL STRUCTURE ON ROOF TOP UNDER QCS 2014 CASE STUDY : O...WIND LOAD DESIGN OF STEEL STRUCTURE ON ROOF TOP UNDER QCS 2014 CASE STUDY : O...
WIND LOAD DESIGN OF STEEL STRUCTURE ON ROOF TOP UNDER QCS 2014 CASE STUDY : O...
 
Six week software training ppt at Tcc Ludhiana
Six week software training ppt at Tcc LudhianaSix week software training ppt at Tcc Ludhiana
Six week software training ppt at Tcc Ludhiana
 
Introduction to machine maintinance and installation
Introduction to machine maintinance and installationIntroduction to machine maintinance and installation
Introduction to machine maintinance and installation
 
Static load test method statement cm - ms- bw - 003
Static load test method statement  cm - ms- bw - 003Static load test method statement  cm - ms- bw - 003
Static load test method statement cm - ms- bw - 003
 
multistorey building design by sap and autocad
multistorey building design by sap and autocadmultistorey building design by sap and autocad
multistorey building design by sap and autocad
 
CFM 56-7B AGB LH FWD Mount Damper Change Tool
CFM 56-7B AGB LH FWD Mount Damper Change ToolCFM 56-7B AGB LH FWD Mount Damper Change Tool
CFM 56-7B AGB LH FWD Mount Damper Change Tool
 

Similar to Fpso floating structures

C2. Functional Requirements of FPSO
C2. Functional Requirements of FPSOC2. Functional Requirements of FPSO
C2. Functional Requirements of FPSO
David Seow
 
RINA - AOG 2017 - Development of Self Installing Deepwater Spar - ARUP - Ashi...
RINA - AOG 2017 - Development of Self Installing Deepwater Spar - ARUP - Ashi...RINA - AOG 2017 - Development of Self Installing Deepwater Spar - ARUP - Ashi...
RINA - AOG 2017 - Development of Self Installing Deepwater Spar - ARUP - Ashi...
Nick Bentley
 
Overview of Technology Development _ S_ F _Vhora
Overview of Technology Development _ S_ F _VhoraOverview of Technology Development _ S_ F _Vhora
Overview of Technology Development _ S_ F _Vhora
ProSIM R & D Pvt. Ltd.
 
Abdelraheim Mohamed-1
Abdelraheim Mohamed-1Abdelraheim Mohamed-1
Abdelraheim Mohamed-1
Abdelraheim Mohamed
 
FPSO Redeployment
FPSO RedeploymentFPSO Redeployment
FPSO Redeployment
Dan Benson
 
Outfitting related structural defects
Outfitting related structural defectsOutfitting related structural defects
Outfitting related structural defects
Nam Nguyen
 
Offshore structure design, Sigve Hamilton Aspelund
Offshore structure design, Sigve Hamilton AspelundOffshore structure design, Sigve Hamilton Aspelund
Offshore structure design, Sigve Hamilton Aspelund
Sigve Hamilton Aspelund
 
joblayoutmobequipcoord-jan-2014.ppt
joblayoutmobequipcoord-jan-2014.pptjoblayoutmobequipcoord-jan-2014.ppt
joblayoutmobequipcoord-jan-2014.ppt
yokeceg852
 
Steel structure presentation for students
Steel structure presentation for studentsSteel structure presentation for students
Steel structure presentation for students
someoneslife167
 
4. Mechanical design of pressure vessels_slides.pdf
4. Mechanical design of pressure vessels_slides.pdf4. Mechanical design of pressure vessels_slides.pdf
4. Mechanical design of pressure vessels_slides.pdf
YafetTilahun
 
A Sattar CV-II
A Sattar CV-IIA Sattar CV-II
Buildingworkmethodstatement cm-ms-bw-001-141120013134-conversion-gate01(1)
Buildingworkmethodstatement cm-ms-bw-001-141120013134-conversion-gate01(1)Buildingworkmethodstatement cm-ms-bw-001-141120013134-conversion-gate01(1)
Buildingworkmethodstatement cm-ms-bw-001-141120013134-conversion-gate01(1)
Krm Chari
 
A Sattar CV-II
A Sattar CV-IIA Sattar CV-II
Metode Konstruksi Offshore Platform_2016_2_18.ppt
Metode Konstruksi Offshore Platform_2016_2_18.pptMetode Konstruksi Offshore Platform_2016_2_18.ppt
Metode Konstruksi Offshore Platform_2016_2_18.ppt
MFaridGeonova
 
In situ Ship repair maintenance Presentation.pptx
In situ Ship repair maintenance Presentation.pptxIn situ Ship repair maintenance Presentation.pptx
In situ Ship repair maintenance Presentation.pptx
Hieu Dang
 
Designing a Cold-Formed Steel Beam Using AS4600:2018 and 2005 - Webinar
Designing a Cold-Formed Steel Beam Using AS4600:2018 and 2005 - WebinarDesigning a Cold-Formed Steel Beam Using AS4600:2018 and 2005 - Webinar
Designing a Cold-Formed Steel Beam Using AS4600:2018 and 2005 - Webinar
ClearCalcs
 
C9 FPSO Layout and Turret 2004
C9 FPSO Layout and Turret 2004C9 FPSO Layout and Turret 2004
C9 FPSO Layout and Turret 2004
David Seow
 
Mechanical cv
Mechanical cvMechanical cv
Mechanical cv
Umar Faruque
 
E473007
E473007E473007
Well completion d.pptx
Well completion d.pptxWell completion d.pptx
Well completion d.pptx
AihamAltayeh1
 

Similar to Fpso floating structures (20)

C2. Functional Requirements of FPSO
C2. Functional Requirements of FPSOC2. Functional Requirements of FPSO
C2. Functional Requirements of FPSO
 
RINA - AOG 2017 - Development of Self Installing Deepwater Spar - ARUP - Ashi...
RINA - AOG 2017 - Development of Self Installing Deepwater Spar - ARUP - Ashi...RINA - AOG 2017 - Development of Self Installing Deepwater Spar - ARUP - Ashi...
RINA - AOG 2017 - Development of Self Installing Deepwater Spar - ARUP - Ashi...
 
Overview of Technology Development _ S_ F _Vhora
Overview of Technology Development _ S_ F _VhoraOverview of Technology Development _ S_ F _Vhora
Overview of Technology Development _ S_ F _Vhora
 
Abdelraheim Mohamed-1
Abdelraheim Mohamed-1Abdelraheim Mohamed-1
Abdelraheim Mohamed-1
 
FPSO Redeployment
FPSO RedeploymentFPSO Redeployment
FPSO Redeployment
 
Outfitting related structural defects
Outfitting related structural defectsOutfitting related structural defects
Outfitting related structural defects
 
Offshore structure design, Sigve Hamilton Aspelund
Offshore structure design, Sigve Hamilton AspelundOffshore structure design, Sigve Hamilton Aspelund
Offshore structure design, Sigve Hamilton Aspelund
 
joblayoutmobequipcoord-jan-2014.ppt
joblayoutmobequipcoord-jan-2014.pptjoblayoutmobequipcoord-jan-2014.ppt
joblayoutmobequipcoord-jan-2014.ppt
 
Steel structure presentation for students
Steel structure presentation for studentsSteel structure presentation for students
Steel structure presentation for students
 
4. Mechanical design of pressure vessels_slides.pdf
4. Mechanical design of pressure vessels_slides.pdf4. Mechanical design of pressure vessels_slides.pdf
4. Mechanical design of pressure vessels_slides.pdf
 
A Sattar CV-II
A Sattar CV-IIA Sattar CV-II
A Sattar CV-II
 
Buildingworkmethodstatement cm-ms-bw-001-141120013134-conversion-gate01(1)
Buildingworkmethodstatement cm-ms-bw-001-141120013134-conversion-gate01(1)Buildingworkmethodstatement cm-ms-bw-001-141120013134-conversion-gate01(1)
Buildingworkmethodstatement cm-ms-bw-001-141120013134-conversion-gate01(1)
 
A Sattar CV-II
A Sattar CV-IIA Sattar CV-II
A Sattar CV-II
 
Metode Konstruksi Offshore Platform_2016_2_18.ppt
Metode Konstruksi Offshore Platform_2016_2_18.pptMetode Konstruksi Offshore Platform_2016_2_18.ppt
Metode Konstruksi Offshore Platform_2016_2_18.ppt
 
In situ Ship repair maintenance Presentation.pptx
In situ Ship repair maintenance Presentation.pptxIn situ Ship repair maintenance Presentation.pptx
In situ Ship repair maintenance Presentation.pptx
 
Designing a Cold-Formed Steel Beam Using AS4600:2018 and 2005 - Webinar
Designing a Cold-Formed Steel Beam Using AS4600:2018 and 2005 - WebinarDesigning a Cold-Formed Steel Beam Using AS4600:2018 and 2005 - Webinar
Designing a Cold-Formed Steel Beam Using AS4600:2018 and 2005 - Webinar
 
C9 FPSO Layout and Turret 2004
C9 FPSO Layout and Turret 2004C9 FPSO Layout and Turret 2004
C9 FPSO Layout and Turret 2004
 
Mechanical cv
Mechanical cvMechanical cv
Mechanical cv
 
E473007
E473007E473007
E473007
 
Well completion d.pptx
Well completion d.pptxWell completion d.pptx
Well completion d.pptx
 

Recently uploaded

Advanced Java[Extra Concepts, Not Difficult].docx
Advanced Java[Extra Concepts, Not Difficult].docxAdvanced Java[Extra Concepts, Not Difficult].docx
Advanced Java[Extra Concepts, Not Difficult].docx
adhitya5119
 
Hindi varnamala | hindi alphabet PPT.pdf
Hindi varnamala | hindi alphabet PPT.pdfHindi varnamala | hindi alphabet PPT.pdf
Hindi varnamala | hindi alphabet PPT.pdf
Dr. Mulla Adam Ali
 
Présentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptx
Présentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptxPrésentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptx
Présentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptx
siemaillard
 
Solutons Maths Escape Room Spatial .pptx
Solutons Maths Escape Room Spatial .pptxSolutons Maths Escape Room Spatial .pptx
Solutons Maths Escape Room Spatial .pptx
spdendr
 
Film vocab for eal 3 students: Australia the movie
Film vocab for eal 3 students: Australia the movieFilm vocab for eal 3 students: Australia the movie
Film vocab for eal 3 students: Australia the movie
Nicholas Montgomery
 
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...
Nguyen Thanh Tu Collection
 
IGCSE Biology Chapter 14- Reproduction in Plants.pdf
IGCSE Biology Chapter 14- Reproduction in Plants.pdfIGCSE Biology Chapter 14- Reproduction in Plants.pdf
IGCSE Biology Chapter 14- Reproduction in Plants.pdf
Amin Marwan
 
What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...
What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...
What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...
GeorgeMilliken2
 
Beyond Degrees - Empowering the Workforce in the Context of Skills-First.pptx
Beyond Degrees - Empowering the Workforce in the Context of Skills-First.pptxBeyond Degrees - Empowering the Workforce in the Context of Skills-First.pptx
Beyond Degrees - Empowering the Workforce in the Context of Skills-First.pptx
EduSkills OECD
 
A Independência da América Espanhola LAPBOOK.pdf
A Independência da América Espanhola LAPBOOK.pdfA Independência da América Espanhola LAPBOOK.pdf
A Independência da América Espanhola LAPBOOK.pdf
Jean Carlos Nunes Paixão
 
Philippine Edukasyong Pantahanan at Pangkabuhayan (EPP) Curriculum
Philippine Edukasyong Pantahanan at Pangkabuhayan (EPP) CurriculumPhilippine Edukasyong Pantahanan at Pangkabuhayan (EPP) Curriculum
Philippine Edukasyong Pantahanan at Pangkabuhayan (EPP) Curriculum
MJDuyan
 
The History of Stoke Newington Street Names
The History of Stoke Newington Street NamesThe History of Stoke Newington Street Names
The History of Stoke Newington Street Names
History of Stoke Newington
 
ZK on Polkadot zero knowledge proofs - sub0.pptx
ZK on Polkadot zero knowledge proofs - sub0.pptxZK on Polkadot zero knowledge proofs - sub0.pptx
ZK on Polkadot zero knowledge proofs - sub0.pptx
dot55audits
 
spot a liar (Haiqa 146).pptx Technical writhing and presentation skills
spot a liar (Haiqa 146).pptx Technical writhing and presentation skillsspot a liar (Haiqa 146).pptx Technical writhing and presentation skills
spot a liar (Haiqa 146).pptx Technical writhing and presentation skills
haiqairshad
 
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
PECB
 
Bed Making ( Introduction, Purpose, Types, Articles, Scientific principles, N...
Bed Making ( Introduction, Purpose, Types, Articles, Scientific principles, N...Bed Making ( Introduction, Purpose, Types, Articles, Scientific principles, N...
Bed Making ( Introduction, Purpose, Types, Articles, Scientific principles, N...
Leena Ghag-Sakpal
 
Leveraging Generative AI to Drive Nonprofit Innovation
Leveraging Generative AI to Drive Nonprofit InnovationLeveraging Generative AI to Drive Nonprofit Innovation
Leveraging Generative AI to Drive Nonprofit Innovation
TechSoup
 
Constructing Your Course Container for Effective Communication
Constructing Your Course Container for Effective CommunicationConstructing Your Course Container for Effective Communication
Constructing Your Course Container for Effective Communication
Chevonnese Chevers Whyte, MBA, B.Sc.
 
UGC NET Exam Paper 1- Unit 1:Teaching Aptitude
UGC NET Exam Paper 1- Unit 1:Teaching AptitudeUGC NET Exam Paper 1- Unit 1:Teaching Aptitude
UGC NET Exam Paper 1- Unit 1:Teaching Aptitude
S. Raj Kumar
 
LAND USE LAND COVER AND NDVI OF MIRZAPUR DISTRICT, UP
LAND USE LAND COVER AND NDVI OF MIRZAPUR DISTRICT, UPLAND USE LAND COVER AND NDVI OF MIRZAPUR DISTRICT, UP
LAND USE LAND COVER AND NDVI OF MIRZAPUR DISTRICT, UP
RAHUL
 

Recently uploaded (20)

Advanced Java[Extra Concepts, Not Difficult].docx
Advanced Java[Extra Concepts, Not Difficult].docxAdvanced Java[Extra Concepts, Not Difficult].docx
Advanced Java[Extra Concepts, Not Difficult].docx
 
Hindi varnamala | hindi alphabet PPT.pdf
Hindi varnamala | hindi alphabet PPT.pdfHindi varnamala | hindi alphabet PPT.pdf
Hindi varnamala | hindi alphabet PPT.pdf
 
Présentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptx
Présentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptxPrésentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptx
Présentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptx
 
Solutons Maths Escape Room Spatial .pptx
Solutons Maths Escape Room Spatial .pptxSolutons Maths Escape Room Spatial .pptx
Solutons Maths Escape Room Spatial .pptx
 
Film vocab for eal 3 students: Australia the movie
Film vocab for eal 3 students: Australia the movieFilm vocab for eal 3 students: Australia the movie
Film vocab for eal 3 students: Australia the movie
 
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...
 
IGCSE Biology Chapter 14- Reproduction in Plants.pdf
IGCSE Biology Chapter 14- Reproduction in Plants.pdfIGCSE Biology Chapter 14- Reproduction in Plants.pdf
IGCSE Biology Chapter 14- Reproduction in Plants.pdf
 
What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...
What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...
What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...
 
Beyond Degrees - Empowering the Workforce in the Context of Skills-First.pptx
Beyond Degrees - Empowering the Workforce in the Context of Skills-First.pptxBeyond Degrees - Empowering the Workforce in the Context of Skills-First.pptx
Beyond Degrees - Empowering the Workforce in the Context of Skills-First.pptx
 
A Independência da América Espanhola LAPBOOK.pdf
A Independência da América Espanhola LAPBOOK.pdfA Independência da América Espanhola LAPBOOK.pdf
A Independência da América Espanhola LAPBOOK.pdf
 
Philippine Edukasyong Pantahanan at Pangkabuhayan (EPP) Curriculum
Philippine Edukasyong Pantahanan at Pangkabuhayan (EPP) CurriculumPhilippine Edukasyong Pantahanan at Pangkabuhayan (EPP) Curriculum
Philippine Edukasyong Pantahanan at Pangkabuhayan (EPP) Curriculum
 
The History of Stoke Newington Street Names
The History of Stoke Newington Street NamesThe History of Stoke Newington Street Names
The History of Stoke Newington Street Names
 
ZK on Polkadot zero knowledge proofs - sub0.pptx
ZK on Polkadot zero knowledge proofs - sub0.pptxZK on Polkadot zero knowledge proofs - sub0.pptx
ZK on Polkadot zero knowledge proofs - sub0.pptx
 
spot a liar (Haiqa 146).pptx Technical writhing and presentation skills
spot a liar (Haiqa 146).pptx Technical writhing and presentation skillsspot a liar (Haiqa 146).pptx Technical writhing and presentation skills
spot a liar (Haiqa 146).pptx Technical writhing and presentation skills
 
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
 
Bed Making ( Introduction, Purpose, Types, Articles, Scientific principles, N...
Bed Making ( Introduction, Purpose, Types, Articles, Scientific principles, N...Bed Making ( Introduction, Purpose, Types, Articles, Scientific principles, N...
Bed Making ( Introduction, Purpose, Types, Articles, Scientific principles, N...
 
Leveraging Generative AI to Drive Nonprofit Innovation
Leveraging Generative AI to Drive Nonprofit InnovationLeveraging Generative AI to Drive Nonprofit Innovation
Leveraging Generative AI to Drive Nonprofit Innovation
 
Constructing Your Course Container for Effective Communication
Constructing Your Course Container for Effective CommunicationConstructing Your Course Container for Effective Communication
Constructing Your Course Container for Effective Communication
 
UGC NET Exam Paper 1- Unit 1:Teaching Aptitude
UGC NET Exam Paper 1- Unit 1:Teaching AptitudeUGC NET Exam Paper 1- Unit 1:Teaching Aptitude
UGC NET Exam Paper 1- Unit 1:Teaching Aptitude
 
LAND USE LAND COVER AND NDVI OF MIRZAPUR DISTRICT, UP
LAND USE LAND COVER AND NDVI OF MIRZAPUR DISTRICT, UPLAND USE LAND COVER AND NDVI OF MIRZAPUR DISTRICT, UP
LAND USE LAND COVER AND NDVI OF MIRZAPUR DISTRICT, UP
 

Fpso floating structures

  • 1. FPSO FLOATING STRUCTURES • MUHAMAD NAZHIIM ADLI BIN AZLI (TH18049) • DANIAL ANZALLAH BIN ROZAMAN (TH20053) • MOHAMAD HASSAN BIN M ALI (TH18016)
  • 2. INTRODUCTION TO FPSO • A floating vessel that can produce crude oil and gas is known as an FPSO (floating, production, storage, and off-loading unit). There are two pieces to it: the topside and the hull. • The FPSO, on the other hand, cannot generate oil and gas on the oil field by itself. • As depicted in Figure 1, several offshore production systems are required, including subsea production systems (SPS), umbilical, flow lines and risers (UFR), mooring lines, a shuttle tanker, and an off-loading buoy. FIGURE 1: Offshore Production System
  • 3. • Figure 2 depicts a typical FPSO unit architecture. • It is split into two sections: the topside and the hull. • The flare tower, living quarters, lay-down area, mooring fairleads, and a helicopter deck are all part of an FPSO unit. Figure 2: Typical Layout of an FPSO Unit
  • 4. INTRODUCTION TO THE NIGERIA FIELD DEVELOPMENT PROJECT • The Nigeria field is located in Nigeria's offshore region known as OPL 246, as depicted in Figure 3. • The Nigeria field development project is made up of several important components. • Nigerian National Petroleum Company (NNPC), South Atlantic Petroleum, Nigerian Company (Sapetro), Brazilian Oil Company (Petrobras), and others. • This project is primarily comprised of the FPSO, SPS, UFR, and offshore loading terminal (OLT), as seen in Figure 1. • The methodologies utilised to develop the detailed design and construction of the FPSO hull are being examined in order to aid future design and construction of FPSO hulls.
  • 6. STABILITY CALCULATION • FPSO needs an ability to return to its undisturbed position after the removal of the external force , called as Stability. • It is a crucial because FPSO needs to remain float on the sea floor or remains bouyant. • FPSO must aqquired both static and dynamic stability.
  • 8. MOORING SYSTEM • Method for solving line dynamics: lumped mass method ( divides a mooring line into small segment • Wind and current force important mooring load. • Wind – consider dynamic, computed using mean wind speed associated recognized wind gust spectra and wind load coefficients • Current – consider static, computed using case of FOIs with ship shape hulls, formula from OCIMF publication
  • 10. FPSO STRUCTURE INSTALLATION • An exploration and feasibility study must first be completed before the field can be developed. • Then, based on the study's findings, the front-end engineering design (FEED) of an FPSO is initiated if the economic value of the field development is positive, taking into consideration the circumstances of the offshore market. • Figure 3 shows the overall procedure of the FPSO field development of this study. Figure 3: Overall procedure of the FPSO field development in this study
  • 11. • Figure 4 depicts the detailed design method for the FPSO hull and the key detailed design tasks. • The preparation of the piping and instrumentation diagram (P&ID) for each system or facility of the hull, as illustrated in Figure 4, is at the heart of the detailed design. Figure 4: Detailed design procedure for P&ID of the hull of an FPSO unit
  • 12. • In general, hull scantlings are designed with two factors in mind: load (demand) and strength (capability). • Loads are useful in strength equations and calculation techniques when permissible stresses reflect a desirable strength level. • Figure 5 depicts the comprehensive design method of the FPSO's hull structure and appurtenance supports, as well as the primary detailed design tasks. • The techniques for designing the hull and appurtenance supports, as illustrated in Figure 5, may be separated into four components, which are as follows: Figure 5: Detailed design procedure for the hull of FPSO
  • 13. The pre-design phases are the same as the P&ID approach described above. • Specification incorporation • FEED clarification • Incorporation of lessons learned from previous project Hull scantling and strength analysis • Priority tasks in the fundamental design process from IFR to IFC include longitudinal scantling and primary hull strength analysis. • The following are the fundamental design processes for hull scantling and strength analysis: - Hull key plan drawing and calculation - Appurtenance key drawing - Strength analysis for hull and appurtenance supports - Fatigue assessment for hull and appurtenance supports - Impact analysis including design brief
  • 14. Detailed structure drawings • Based on the hull key plan and key drawing of appurtenances, detailed structure drawings may be created. • These designs have been divided based on the structure's characteristics and have been updated with the outfitting system. Block production drawings • Based on the hull construction drawings, block production drawings may be created and divided according to the block division plan design. - Block division - Detailed assembly procedures (See Figure 6) - Block fabrication drawings - Welding map - Non-destructive test plan Figure 6: Detailed block assembly procedures
  • 15. Procedure of the hull construction of an FPSO • Figure 7 depicts the building methods for an FPSO's hull, which include the procurement stage, the dry dock stage, and the on-shore stage. • Raw materials such as steel are ordered in advance during the procurement stage, taking into consideration aspects like as lead time (typically 60–180 days). Figure 7: Detailed procedure of the hull construction of an FPSO unit
  • 16. MAIN ACTIVITIES OF THE HULL CONSTRUCTION OF AN FPSO Activities of the procurement stage • After completing the basic and comprehensive design of an FPSO's hull, the first steel order is placed six months before construction begins or steel cutting (W/C), taking into account the steel procurement lead time. • The initial steel order contains bottom blocks, longitudinal bulkhead blocks, transverse bulkhead block plates, and built-up elements that may be worked on ahead of time. Activities of the dry dock stage • The major tasks during the dry dock stage are the assembly of hull blocks, including L/Q, the installation of appurtenances, and the loading of pipe racks. • More information about this may be found below: - Activities related to hull blocks - Activities related to L/Q blocks - Activities related to hull appurtenances - Activities related to pipe racks
  • 17. Activities of the on-shore stage • After launching, the primary activities, such as hull cabling including L/Q, fire work, insulation/unit cabin installations, pipe spool installation, and so on, are completed at the on-shore stage. • If the total operation goes smoothly, the hull of the FPSO will be delivered following pre-commissioning and commissioning. At this point, the on-shore interface work between the topside and the hull is critical for smoothly hooking up SPS, which is installed in the field after sail away. • Figure 8 depicts the launching of the FPSO's hull, which was fabricated by HSHI. Figure 8: Launching and dock out of the hull of an FPSO unit
  • 18. CONCLUSION • This research delivers the following findings based on our extensive expertise with the technical design and construction of an FPSO unit's hull. • First, the FPSO field development strategy was investigated. • Second, the comprehensive design techniques and activities of an FPSO unit's hull have been investigated. • Third, the hull's construction techniques and activities have been investigated. • Finally, crucial interaction work between systems and disciplines in hull building has been investigated. • The aforementioned contents will be utilised as guidance to lessen M/H and cost implications on the design and construction of future FPSO units' hulls.