SlideShare a Scribd company logo
1 of 4
Download to read offline
Schedule Risk Analysis
Asaman Patnaik
Project schedules are plans for future activities based on estimates of time and cost. There is
always a factor of uncertainty in predicting these estimates. Estimates about activity time and
cost are predictions for the future and depend on human beings who often tend to be overly
optimistic (most of the projects worldwide experience time overrun of more than 50%) or, on the
contrary, may add some reserve safety to protect themselves against unexpected events.
Thus, knowledge about the potential impact of these estimation errors on the project objective is
a key add-on to the construction of a project’s baseline schedule. Schedule Risk Analysis is a
simple but effective technique that connects the time and cost risk uncertainty of individual
activities to the base line schedule by replacing the deterministic duration for each task by a
distribution representing the range of likely durations.
Steps for Schedule Risk Analysis:
1. Baseline schedule: Construct an activity timetable
2. Define uncertainty: Define activity time and cost probability distributions
3. Run Monte-Carlo simulations: Run multiple project progress simulations
4. Interpret the simulation results: Interpret the sensitivity measures
1. Baseline schedule
The construction of a project baseline schedule involves the definition of start and finish times
for each project activity, using earliest and latest start calculations.
The project baseline schedule serves as a point of reference. In case everything goes according
to plan, then the project can be completed as per this base line schedule which is very unlikely.
2. Define risk/uncertainty
Time and cost estimates are often subject to a margin for error. It is more accurate to estimate a
range of duration and cost estimates for project activities.
3. Monte-Carlo simulations
Monte-Carlo simulation is a simple technique to quickly generate multiple runs simulating real
project progress. Each simulation run generates duration for each project activity.
4. Sensitivity results
The output of a schedule risk analysis is a set of measures that define the degree of activity
criticality and sensitivity. Each measure gives the project manager an indication of how sensitive
the activity is towards the final project duration or total cost
A case study of cost and schedule risk analysis carried out for an Industrial Waste Water
Treatment Plant Project at Saudi Arabia is outlined in the subsequent paragraphs.
ABOUT THE PROJECT
Make up water for the client’s existing plant at Saudi Arabia is met by purchasing from a utility
company. The effluent generated in the plant is also sent for treatment at a common effluent
plant for which the client pays the treatment cost.
The client proposes to set up an Industrial Waste Water Treatment Plant to treat about 6000
cum/ day of waste water, to generate around 3600 cum/day of treated water that can replace
part of makeup water being used in the plant. The IWWTP shall generate about 2200 cum/day
of reject that still needs to be sent to CETP.
Thus, by setting up the project, client will reduce the cost towards purchase of makeup water of
3600 cum/day and also reduce the cost of treatment of effluent from 6000 cum/day to 2200
cum/day.
TCE was asked by the client to carry out the cost risk analysis and schedule risk analysis for the
project.
A. Cost Risk Analysis
Cost Risk Analysis carried out consisted of the following:
A1 Impact: Impact of variation in cost and sales revenue on the financial indices such as
Profit before Tax (PBT) and Contribution was calculated. This was estimated by carrying out the
financial evaluation of the project, followed by a sensitivity analysis for variation of 5 to 20% in
(a) variable costs (b) sales revenue and combination of both (a) and (b).
For each of three scenarios the variation of PBT for base case, 5%, 10%, 15% and 20% were
plotted.
Further, considering stable operation in 3rd
year, the trend of PBT and contribution was analyzed
for the above 5 cases to indentify the sensitivity.
For decrease in sales revenue, two options were analyzed. (1) Decrease in makeup water price
(2) Decrease in productivity.
A2 Likelihood: The likelihood of variation in cost, sales volume was identified.
Key items of variable cost are treatment cost (45%), chemicals (22%) and electricity (13%). The
price trends for these were analyzed, and also the future trend as per Dow’s Chemical Index
was analyzed, to predict likelihood of increase in variable cost.
The trends of makeup water cost over the last 10 years were analyzed, to predict the likelihood
of decrease in sales price.
A3 Conclusion
Based on the above, the risk on financial parameters of the project was analyzed and mitigation
plan suggested.
B. Schedule Risk Analysis
The schedule risk analysis was carried out to find the impact and likelihood of project
delay.
B1 Impact
The impact on project cost, revenue and profit for 10 years period were estimated for base case
(on schedule), delay of 3 month, 6 months, 9 months and one year.
B2 Likelihood
The likelihood of project delay was estimated using Monte Carlo Simulation as follows:
1. The probabilistic duration of each activity the project was analyzed and mutually agreed
with client on three scenarios:
(a) Likely (Probable)
(b) Best Case (Minimum)
(c) Worst Case (Maximum)
2. The overall project duration was found out for the above three scenarios.
3. Based on the minimum and maximum duration, a Monte Carlo Simulation was carried
out by generating 1000 random numbers. The simulation was done 500 times. Based on
the same, the probability of project completion with 80% and 90% confidence level were
found out.
B3 Causes of Project Delay and Mitigation Plan
The probable causes of project delay and mitigation plan were identified and tabulated.
0.00%
2.00%
4.00%
6.00%
8.00%
10.00%
12.00%
14.00%
16.00%
353637383940414243444546474849
Likelihood%
Project Completion in Months
0.00%
10.00%
20.00%
30.00%
40.00%
50.00%
60.00%
70.00%
80.00%
90.00%
100.00%
35 36 37 38 39 40 41 42 43 44 45 46 47 48 49
Likelihood%
Project Completion on or before, months

More Related Content

What's hot

COBRA/Omnibus 4 Industry Day 2016- Contract Life Cycle (CLC) Performance Anal...
COBRA/Omnibus 4 Industry Day 2016- Contract Life Cycle (CLC) Performance Anal...COBRA/Omnibus 4 Industry Day 2016- Contract Life Cycle (CLC) Performance Anal...
COBRA/Omnibus 4 Industry Day 2016- Contract Life Cycle (CLC) Performance Anal...Ilka T. De León, MBA
 
Cis 500 assignment 6 vo ip part 4 (risk register)
Cis 500 assignment 6 vo ip part 4 (risk register)Cis 500 assignment 6 vo ip part 4 (risk register)
Cis 500 assignment 6 vo ip part 4 (risk register)Anakinzs
 
Using Risk Analysis and Simulation in Project Management
Using Risk Analysis and Simulation in Project ManagementUsing Risk Analysis and Simulation in Project Management
Using Risk Analysis and Simulation in Project ManagementMike Tulkoff
 
Project Cost Risk Analysis - Reporting
Project Cost Risk Analysis - ReportingProject Cost Risk Analysis - Reporting
Project Cost Risk Analysis - ReportingIntaver Insititute
 
Session B3 - Introduction to Project Cost and Schedule Risk Analysis
Session B3 - Introduction to Project Cost and Schedule Risk AnalysisSession B3 - Introduction to Project Cost and Schedule Risk Analysis
Session B3 - Introduction to Project Cost and Schedule Risk AnalysisProject Controls Expo
 

What's hot (10)

COBRA/Omnibus 4 Industry Day 2016- Contract Life Cycle (CLC) Performance Anal...
COBRA/Omnibus 4 Industry Day 2016- Contract Life Cycle (CLC) Performance Anal...COBRA/Omnibus 4 Industry Day 2016- Contract Life Cycle (CLC) Performance Anal...
COBRA/Omnibus 4 Industry Day 2016- Contract Life Cycle (CLC) Performance Anal...
 
Cis 500 assignment 6 vo ip part 4 (risk register)
Cis 500 assignment 6 vo ip part 4 (risk register)Cis 500 assignment 6 vo ip part 4 (risk register)
Cis 500 assignment 6 vo ip part 4 (risk register)
 
Using Risk Analysis and Simulation in Project Management
Using Risk Analysis and Simulation in Project ManagementUsing Risk Analysis and Simulation in Project Management
Using Risk Analysis and Simulation in Project Management
 
Project Cost Risk Analysis - Reporting
Project Cost Risk Analysis - ReportingProject Cost Risk Analysis - Reporting
Project Cost Risk Analysis - Reporting
 
Session B3 - Introduction to Project Cost and Schedule Risk Analysis
Session B3 - Introduction to Project Cost and Schedule Risk AnalysisSession B3 - Introduction to Project Cost and Schedule Risk Analysis
Session B3 - Introduction to Project Cost and Schedule Risk Analysis
 
Instrument cost estimating
Instrument cost estimatingInstrument cost estimating
Instrument cost estimating
 
Cost management
Cost managementCost management
Cost management
 
Earned value analysis
Earned value analysisEarned value analysis
Earned value analysis
 
Software measurement and estimation
Software measurement and estimationSoftware measurement and estimation
Software measurement and estimation
 
Nodoc1
Nodoc1Nodoc1
Nodoc1
 

Viewers also liked

Phone chase advert pitch
Phone chase advert pitchPhone chase advert pitch
Phone chase advert pitchFreedean
 
Finca Interactiva
Finca InteractivaFinca Interactiva
Finca Interactivaguestf20354
 
Why preserve your money - 2015
Why preserve your money - 2015Why preserve your money - 2015
Why preserve your money - 2015Sonette Willett
 
Financial Express July 10, 2009 Article 1
Financial Express July 10, 2009   Article 1Financial Express July 10, 2009   Article 1
Financial Express July 10, 2009 Article 1Jagannadham Thunuguntla
 
Bảng báo giá dịch vụ content marketing - Viết nội dung, viết bài chuẩn SEO
Bảng báo giá dịch vụ content marketing - Viết nội dung, viết bài chuẩn SEOBảng báo giá dịch vụ content marketing - Viết nội dung, viết bài chuẩn SEO
Bảng báo giá dịch vụ content marketing - Viết nội dung, viết bài chuẩn SEOFPT Univesity
 
Laplace periodic function with graph
Laplace periodic function with graphLaplace periodic function with graph
Laplace periodic function with graphKaushal Surti
 

Viewers also liked (9)

Revista virtual
Revista virtualRevista virtual
Revista virtual
 
Phone chase advert pitch
Phone chase advert pitchPhone chase advert pitch
Phone chase advert pitch
 
Simuladinho 07
Simuladinho 07Simuladinho 07
Simuladinho 07
 
AJEETcv
AJEETcvAJEETcv
AJEETcv
 
Finca Interactiva
Finca InteractivaFinca Interactiva
Finca Interactiva
 
Why preserve your money - 2015
Why preserve your money - 2015Why preserve your money - 2015
Why preserve your money - 2015
 
Financial Express July 10, 2009 Article 1
Financial Express July 10, 2009   Article 1Financial Express July 10, 2009   Article 1
Financial Express July 10, 2009 Article 1
 
Bảng báo giá dịch vụ content marketing - Viết nội dung, viết bài chuẩn SEO
Bảng báo giá dịch vụ content marketing - Viết nội dung, viết bài chuẩn SEOBảng báo giá dịch vụ content marketing - Viết nội dung, viết bài chuẩn SEO
Bảng báo giá dịch vụ content marketing - Viết nội dung, viết bài chuẩn SEO
 
Laplace periodic function with graph
Laplace periodic function with graphLaplace periodic function with graph
Laplace periodic function with graph
 

Similar to Blog Cost and Schedule Risk Analysis

Sub project management
Sub   project managementSub   project management
Sub project managementsmumbahelp
 
Risk Management Processes from Jerry Klanac
Risk Management Processes from Jerry KlanacRisk Management Processes from Jerry Klanac
Risk Management Processes from Jerry KlanacPMA Consultants
 
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...IRJET Journal
 
Capital Budegting.pdf
Capital Budegting.pdfCapital Budegting.pdf
Capital Budegting.pdfsauravjain15
 
Contractual implications of cash flow on owner and contractor in villa constr...
Contractual implications of cash flow on owner and contractor in villa constr...Contractual implications of cash flow on owner and contractor in villa constr...
Contractual implications of cash flow on owner and contractor in villa constr...eSAT Publishing House
 
Deepwater Decommissioning Cost Estimation Whitepaper (2016-01)
Deepwater Decommissioning Cost Estimation Whitepaper (2016-01)Deepwater Decommissioning Cost Estimation Whitepaper (2016-01)
Deepwater Decommissioning Cost Estimation Whitepaper (2016-01)Robert Byrd
 
Estimate costs in fragile and transitional contexts - July - 2014
Estimate costs in fragile and transitional contexts - July - 2014Estimate costs in fragile and transitional contexts - July - 2014
Estimate costs in fragile and transitional contexts - July - 2014Abdulrahman Ismail
 
IRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building ProjectIRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building ProjectIRJET Journal
 
Cost Risk Analysis (CRA) by Pedram Daneshmand 19-Jan-2011
Cost Risk Analysis (CRA) by Pedram Daneshmand 19-Jan-2011Cost Risk Analysis (CRA) by Pedram Daneshmand 19-Jan-2011
Cost Risk Analysis (CRA) by Pedram Daneshmand 19-Jan-2011Pedram Danesh-Mand
 
Cost-Estimation-Techniques unit 2.pptx
Cost-Estimation-Techniques unit 2.pptxCost-Estimation-Techniques unit 2.pptx
Cost-Estimation-Techniques unit 2.pptxSudipBalLama
 
Comparative characteristics of pert and cpm
Comparative characteristics of pert and cpmComparative characteristics of pert and cpm
Comparative characteristics of pert and cpmKinshook Chaturvedi
 
1. Which of the following is INCORRECT regarding the process capab.docx
1. Which of the following is INCORRECT regarding the process capab.docx1. Which of the following is INCORRECT regarding the process capab.docx
1. Which of the following is INCORRECT regarding the process capab.docxjackiewalcutt
 
FN6033-CORP FIN-LECTURE 5A.ppt
FN6033-CORP FIN-LECTURE 5A.pptFN6033-CORP FIN-LECTURE 5A.ppt
FN6033-CORP FIN-LECTURE 5A.ppthass6
 
Risk analysis in investment
Risk analysis in investmentRisk analysis in investment
Risk analysis in investmenthimanshujaiswal
 

Similar to Blog Cost and Schedule Risk Analysis (20)

CCP_SEC2_ Cost Estimating
CCP_SEC2_ Cost EstimatingCCP_SEC2_ Cost Estimating
CCP_SEC2_ Cost Estimating
 
Sub project management
Sub   project managementSub   project management
Sub project management
 
Pm assignment
Pm assignmentPm assignment
Pm assignment
 
Risk Management Processes from Jerry Klanac
Risk Management Processes from Jerry KlanacRisk Management Processes from Jerry Klanac
Risk Management Processes from Jerry Klanac
 
Cb practice problems
Cb practice problemsCb practice problems
Cb practice problems
 
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
 
Capital Budegting.pdf
Capital Budegting.pdfCapital Budegting.pdf
Capital Budegting.pdf
 
Costing
CostingCosting
Costing
 
Contractual implications of cash flow on owner and contractor in villa constr...
Contractual implications of cash flow on owner and contractor in villa constr...Contractual implications of cash flow on owner and contractor in villa constr...
Contractual implications of cash flow on owner and contractor in villa constr...
 
Delay Analysis and Concurrent Delay
Delay Analysis and Concurrent DelayDelay Analysis and Concurrent Delay
Delay Analysis and Concurrent Delay
 
Project cost management
Project cost management Project cost management
Project cost management
 
Deepwater Decommissioning Cost Estimation Whitepaper (2016-01)
Deepwater Decommissioning Cost Estimation Whitepaper (2016-01)Deepwater Decommissioning Cost Estimation Whitepaper (2016-01)
Deepwater Decommissioning Cost Estimation Whitepaper (2016-01)
 
Estimate costs in fragile and transitional contexts - July - 2014
Estimate costs in fragile and transitional contexts - July - 2014Estimate costs in fragile and transitional contexts - July - 2014
Estimate costs in fragile and transitional contexts - July - 2014
 
IRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building ProjectIRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building Project
 
Cost Risk Analysis (CRA) by Pedram Daneshmand 19-Jan-2011
Cost Risk Analysis (CRA) by Pedram Daneshmand 19-Jan-2011Cost Risk Analysis (CRA) by Pedram Daneshmand 19-Jan-2011
Cost Risk Analysis (CRA) by Pedram Daneshmand 19-Jan-2011
 
Cost-Estimation-Techniques unit 2.pptx
Cost-Estimation-Techniques unit 2.pptxCost-Estimation-Techniques unit 2.pptx
Cost-Estimation-Techniques unit 2.pptx
 
Comparative characteristics of pert and cpm
Comparative characteristics of pert and cpmComparative characteristics of pert and cpm
Comparative characteristics of pert and cpm
 
1. Which of the following is INCORRECT regarding the process capab.docx
1. Which of the following is INCORRECT regarding the process capab.docx1. Which of the following is INCORRECT regarding the process capab.docx
1. Which of the following is INCORRECT regarding the process capab.docx
 
FN6033-CORP FIN-LECTURE 5A.ppt
FN6033-CORP FIN-LECTURE 5A.pptFN6033-CORP FIN-LECTURE 5A.ppt
FN6033-CORP FIN-LECTURE 5A.ppt
 
Risk analysis in investment
Risk analysis in investmentRisk analysis in investment
Risk analysis in investment
 

Blog Cost and Schedule Risk Analysis

  • 1. Schedule Risk Analysis Asaman Patnaik Project schedules are plans for future activities based on estimates of time and cost. There is always a factor of uncertainty in predicting these estimates. Estimates about activity time and cost are predictions for the future and depend on human beings who often tend to be overly optimistic (most of the projects worldwide experience time overrun of more than 50%) or, on the contrary, may add some reserve safety to protect themselves against unexpected events. Thus, knowledge about the potential impact of these estimation errors on the project objective is a key add-on to the construction of a project’s baseline schedule. Schedule Risk Analysis is a simple but effective technique that connects the time and cost risk uncertainty of individual activities to the base line schedule by replacing the deterministic duration for each task by a distribution representing the range of likely durations. Steps for Schedule Risk Analysis: 1. Baseline schedule: Construct an activity timetable 2. Define uncertainty: Define activity time and cost probability distributions 3. Run Monte-Carlo simulations: Run multiple project progress simulations 4. Interpret the simulation results: Interpret the sensitivity measures 1. Baseline schedule The construction of a project baseline schedule involves the definition of start and finish times for each project activity, using earliest and latest start calculations. The project baseline schedule serves as a point of reference. In case everything goes according to plan, then the project can be completed as per this base line schedule which is very unlikely. 2. Define risk/uncertainty Time and cost estimates are often subject to a margin for error. It is more accurate to estimate a range of duration and cost estimates for project activities. 3. Monte-Carlo simulations Monte-Carlo simulation is a simple technique to quickly generate multiple runs simulating real project progress. Each simulation run generates duration for each project activity. 4. Sensitivity results
  • 2. The output of a schedule risk analysis is a set of measures that define the degree of activity criticality and sensitivity. Each measure gives the project manager an indication of how sensitive the activity is towards the final project duration or total cost A case study of cost and schedule risk analysis carried out for an Industrial Waste Water Treatment Plant Project at Saudi Arabia is outlined in the subsequent paragraphs. ABOUT THE PROJECT Make up water for the client’s existing plant at Saudi Arabia is met by purchasing from a utility company. The effluent generated in the plant is also sent for treatment at a common effluent plant for which the client pays the treatment cost. The client proposes to set up an Industrial Waste Water Treatment Plant to treat about 6000 cum/ day of waste water, to generate around 3600 cum/day of treated water that can replace part of makeup water being used in the plant. The IWWTP shall generate about 2200 cum/day of reject that still needs to be sent to CETP. Thus, by setting up the project, client will reduce the cost towards purchase of makeup water of 3600 cum/day and also reduce the cost of treatment of effluent from 6000 cum/day to 2200 cum/day. TCE was asked by the client to carry out the cost risk analysis and schedule risk analysis for the project. A. Cost Risk Analysis Cost Risk Analysis carried out consisted of the following: A1 Impact: Impact of variation in cost and sales revenue on the financial indices such as Profit before Tax (PBT) and Contribution was calculated. This was estimated by carrying out the financial evaluation of the project, followed by a sensitivity analysis for variation of 5 to 20% in (a) variable costs (b) sales revenue and combination of both (a) and (b). For each of three scenarios the variation of PBT for base case, 5%, 10%, 15% and 20% were plotted. Further, considering stable operation in 3rd year, the trend of PBT and contribution was analyzed for the above 5 cases to indentify the sensitivity. For decrease in sales revenue, two options were analyzed. (1) Decrease in makeup water price (2) Decrease in productivity. A2 Likelihood: The likelihood of variation in cost, sales volume was identified.
  • 3. Key items of variable cost are treatment cost (45%), chemicals (22%) and electricity (13%). The price trends for these were analyzed, and also the future trend as per Dow’s Chemical Index was analyzed, to predict likelihood of increase in variable cost. The trends of makeup water cost over the last 10 years were analyzed, to predict the likelihood of decrease in sales price. A3 Conclusion Based on the above, the risk on financial parameters of the project was analyzed and mitigation plan suggested. B. Schedule Risk Analysis The schedule risk analysis was carried out to find the impact and likelihood of project delay. B1 Impact The impact on project cost, revenue and profit for 10 years period were estimated for base case (on schedule), delay of 3 month, 6 months, 9 months and one year. B2 Likelihood The likelihood of project delay was estimated using Monte Carlo Simulation as follows: 1. The probabilistic duration of each activity the project was analyzed and mutually agreed with client on three scenarios: (a) Likely (Probable) (b) Best Case (Minimum) (c) Worst Case (Maximum) 2. The overall project duration was found out for the above three scenarios. 3. Based on the minimum and maximum duration, a Monte Carlo Simulation was carried out by generating 1000 random numbers. The simulation was done 500 times. Based on the same, the probability of project completion with 80% and 90% confidence level were found out.
  • 4. B3 Causes of Project Delay and Mitigation Plan The probable causes of project delay and mitigation plan were identified and tabulated. 0.00% 2.00% 4.00% 6.00% 8.00% 10.00% 12.00% 14.00% 16.00% 353637383940414243444546474849 Likelihood% Project Completion in Months 0.00% 10.00% 20.00% 30.00% 40.00% 50.00% 60.00% 70.00% 80.00% 90.00% 100.00% 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 Likelihood% Project Completion on or before, months