SlideShare a Scribd company logo
1 of 1
Earned Value Formulas
PV (Planned Value) = BCWS (Budgeted Cost of Work Scheduled
EV (Earned Value) = BCWP (Budgeted Cost of Work Performed)
AC (Actual Cost) = ACWP (Actual Cost of Work Performed)
SV = EV – PV (minus is behind schedule)
CV = EV – AC (minus is over budget)
SPI = EV/PV (Less than 1 is behind schedule)
CPI = EV/AC (Less than 1 is over budget)
EAC = AC + (BAC-EV) Use when variances are atypical
EAC = BAC/CPI Use when variances are typical
(Note: This is the same as EAC = BAC/CPI)
VAC = BAC – EAC
ETC = BAC – EV Use when variances are atypical
ETC = (BAC – EV)/CPI Use when variances are typical
ETC = EAC – AC Use when original estimates were flawed
Project Selection Financials
NPV (Net Present Value) = FV/(1+r)n
FV= Future Value, r= interest rate, n= no. of time periods
Higher NPV is better
IRR (Internal Rate of Return) = Solve the NPV equation for “r”
Also called Hurdle Rate
Higher IRR percentage is better
BCR (Benefit/Cost Ratio)
Higher BCR is better.
Beware, exam can call it CBR, where lower is better
Payback Period = Time to recover cost of the project
Lower payback period is better
Cash Flow = Cash In – Cash Out
Network Diagrams
Precedence Diagramming Method (PDM)
Also called Activity on Node (AON): Activities are in boxes
Most commonly used today
Has 4 relationships: F-S, S-S, F-F, S-F
No “dummies” (zero duration dependencies) allowed
Can analyze using either Three-Point Estimates or CPM
Arrow Diagramming Method (ADM)
Also called Activity on Arrow (AOA)
Only 1 relationship: F-S
Can have “dummies”
Can analyze using either Three-Point Estimates or CPM
Graphical Evaluation and Review Technique (GERT)
Allows loops and repetitive activities
Three Point Estimates, or PERT
PERT = PROGRAM Evaluation and Review Technique
Holds schedule and lets cost float
3 estimates for each task: Optimistic, Pessimistic, and Most Likely
Mean Estimate = (O + 4*ML + P)/6
Standard Deviation (σ) = (P – O)/6
Critical Path Method, CPM Analysis
1 bestimate per activity: the Most Likely estimate
Holds cost and lets schedule float
Calculating Slack or Float
Total Float (also called Slack, Float, or Project Float) is the
total amount of time an activity can be delayed without
delaying the project finish date.
Free Float/Slack is the amount of time an activity can be
delayed without delaying its successor (following
activity).
LS – ES: Calculates slack with forward pass
LF – EF: Calculates slack with backwards pass
Lag Time: Inserted wait time between activities
Lead Time: Overlapping activities, also called paralleling or
fast tracking.
“Lead In; Lag Out”
Accuracy of Estimates
Order of Magnitude: -25% to +75%
Budget Estimate: -10% to +25%
Definitive Estimate: -5% to +10%
Standard Deviations from the Norm
± 1 σ = 68.26%
± 2 σ = 95.46%
± 3 σ = 99.73%
± 6 σ = 99.99%
Powers of a Project Manager
1. Expert: Best, earned on your own
2. Reward: Next best. Based on PM position
3. Formal: Power, based on PM position
4. Referent: Referring to positions of others
5. Penalty: Worst. Based on PM position
Conflict Resolution (Best to Worst)
1. Problem Solving: Also called Confronting
2. Compromising: Solutions satisfy both parties
3. Withdrawal: Postponing a decision
4. Smoothing: Emphasis on agreement
5. Forcing: One viewpoint at expense of another.
Channels of Communication
Between Team Members = N(N-1)/2
Sources of Conflict (Order of Priority)
1. Schedules
2. Project Priorities
3. Resources
4. Technical Opinions
5. Administrative Procedures
6. Cost
7. Personality
Herzberg’s Motivators
1. Achievement
2. Recognition
3. Challenge of the work itself
4. Responsibility
5. Advancement
6. Growth
Also, remember Maslow’s Hierarchy of Needs
Closing
Project is closed when administrative closure is complete.
Administrative closure is done at end of each Project Phase and
at the end of the Project.
Contract closure: verification that deliverables were acceptable; it
is done once at the end of the contract.
Contract Closure Procedure is produced under “Close Project”
PMP Test Preparation

More Related Content

What's hot

Project cost management PMBOK 5th Edition
Project cost management PMBOK 5th EditionProject cost management PMBOK 5th Edition
Project cost management PMBOK 5th Editionpankajsh10
 
Understanding Scrum in 30 Minutes
Understanding Scrum in 30 MinutesUnderstanding Scrum in 30 Minutes
Understanding Scrum in 30 MinutesAltaf Najvani
 
Project Management Fundamentals
Project Management FundamentalsProject Management Fundamentals
Project Management FundamentalsNishant Munjal
 
Introduction to project management( framework and processes )
Introduction to project management( framework and processes )Introduction to project management( framework and processes )
Introduction to project management( framework and processes )Qussay Karam
 
Critical Chain Project Management
Critical Chain Project ManagementCritical Chain Project Management
Critical Chain Project ManagementFred Wiersma
 
What is scrum in Agile methodology?
What is scrum in Agile methodology?What is scrum in Agile methodology?
What is scrum in Agile methodology?Mario Lucero
 
Free Online Agile & SCRUM Study Training Material for PMI ACP Certification P...
Free Online Agile & SCRUM Study Training Material for PMI ACP Certification P...Free Online Agile & SCRUM Study Training Material for PMI ACP Certification P...
Free Online Agile & SCRUM Study Training Material for PMI ACP Certification P...GlobalSkillup
 
Project Management Methodologies and Project Governance
Project Management Methodologies and Project GovernanceProject Management Methodologies and Project Governance
Project Management Methodologies and Project GovernancePMIUKChapter
 
Key principles in continuous improvement culture
Key principles in continuous improvement cultureKey principles in continuous improvement culture
Key principles in continuous improvement cultureGopala P.
 
Agile Scrum Training, Day 1 (1/2)
Agile Scrum Training, Day 1 (1/2)Agile Scrum Training, Day 1 (1/2)
Agile Scrum Training, Day 1 (1/2)Jens Wilke
 
Scrum Training (One Day)
Scrum Training (One Day)Scrum Training (One Day)
Scrum Training (One Day)beLithe
 
2. Project management body of knowledge
2. Project management body of knowledge2. Project management body of knowledge
2. Project management body of knowledgeBhuWan Khadka
 
Project Quality Management Plan Checklist PowerPoint Presentation Slides
Project Quality Management Plan Checklist PowerPoint Presentation SlidesProject Quality Management Plan Checklist PowerPoint Presentation Slides
Project Quality Management Plan Checklist PowerPoint Presentation SlidesSlideTeam
 
7.4 Earned Value Analysis
7.4 Earned Value Analysis7.4 Earned Value Analysis
7.4 Earned Value AnalysisDavidMcLachlan1
 

What's hot (20)

Pmp formulas v5
Pmp formulas v5Pmp formulas v5
Pmp formulas v5
 
PMP PMBOK 6th
PMP PMBOK 6thPMP PMBOK 6th
PMP PMBOK 6th
 
Project cost management PMBOK 5th Edition
Project cost management PMBOK 5th EditionProject cost management PMBOK 5th Edition
Project cost management PMBOK 5th Edition
 
Understanding Scrum in 30 Minutes
Understanding Scrum in 30 MinutesUnderstanding Scrum in 30 Minutes
Understanding Scrum in 30 Minutes
 
Project Management Fundamentals
Project Management FundamentalsProject Management Fundamentals
Project Management Fundamentals
 
Introduction to project management( framework and processes )
Introduction to project management( framework and processes )Introduction to project management( framework and processes )
Introduction to project management( framework and processes )
 
Agile Project Management training by manohar prasad
Agile Project Management training by manohar prasadAgile Project Management training by manohar prasad
Agile Project Management training by manohar prasad
 
Critical Chain Project Management
Critical Chain Project ManagementCritical Chain Project Management
Critical Chain Project Management
 
Project management best practices
Project management best practicesProject management best practices
Project management best practices
 
What is scrum in Agile methodology?
What is scrum in Agile methodology?What is scrum in Agile methodology?
What is scrum in Agile methodology?
 
Project management
Project managementProject management
Project management
 
Free Online Agile & SCRUM Study Training Material for PMI ACP Certification P...
Free Online Agile & SCRUM Study Training Material for PMI ACP Certification P...Free Online Agile & SCRUM Study Training Material for PMI ACP Certification P...
Free Online Agile & SCRUM Study Training Material for PMI ACP Certification P...
 
Prince2 Methodology
Prince2 MethodologyPrince2 Methodology
Prince2 Methodology
 
Project Management Methodologies and Project Governance
Project Management Methodologies and Project GovernanceProject Management Methodologies and Project Governance
Project Management Methodologies and Project Governance
 
Key principles in continuous improvement culture
Key principles in continuous improvement cultureKey principles in continuous improvement culture
Key principles in continuous improvement culture
 
Agile Scrum Training, Day 1 (1/2)
Agile Scrum Training, Day 1 (1/2)Agile Scrum Training, Day 1 (1/2)
Agile Scrum Training, Day 1 (1/2)
 
Scrum Training (One Day)
Scrum Training (One Day)Scrum Training (One Day)
Scrum Training (One Day)
 
2. Project management body of knowledge
2. Project management body of knowledge2. Project management body of knowledge
2. Project management body of knowledge
 
Project Quality Management Plan Checklist PowerPoint Presentation Slides
Project Quality Management Plan Checklist PowerPoint Presentation SlidesProject Quality Management Plan Checklist PowerPoint Presentation Slides
Project Quality Management Plan Checklist PowerPoint Presentation Slides
 
7.4 Earned Value Analysis
7.4 Earned Value Analysis7.4 Earned Value Analysis
7.4 Earned Value Analysis
 

Similar to cheat sheet.ppt

Formula pocket guide
Formula pocket guideFormula pocket guide
Formula pocket guideVicky Maly
 
Formulas for PMP exam
Formulas for PMP examFormulas for PMP exam
Formulas for PMP examMrudul Patil
 
cost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.pptcost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.pptRedhaElhuni
 
A simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value ManagementA simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value ManagementProPM Academy
 
#PMP Formulae @ a Glance By SN Panigrahi
#PMP Formulae @ a Glance By SN Panigrahi#PMP Formulae @ a Glance By SN Panigrahi
#PMP Formulae @ a Glance By SN PanigrahiSN Panigrahi, PMP
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost ManagementSerdar Temiz
 
Top Metrics for Agile @Agile NCR2011
Top Metrics for Agile @Agile NCR2011Top Metrics for Agile @Agile NCR2011
Top Metrics for Agile @Agile NCR2011Priyank Pathak
 
PMP preparation and PMI Framework
PMP preparation and PMI FrameworkPMP preparation and PMI Framework
PMP preparation and PMI FrameworkUzma Khan
 
Project : formulation,evaluation and monitoring
Project : formulation,evaluation and monitoringProject : formulation,evaluation and monitoring
Project : formulation,evaluation and monitoringtarzan1990
 
projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)Nita Cristian
 
Project cost & control
Project cost & controlProject cost & control
Project cost & controlAMARAYYA
 

Similar to cheat sheet.ppt (20)

Pmp formula pocket guide
Pmp formula pocket guidePmp formula pocket guide
Pmp formula pocket guide
 
Pmp formula pocket guide
Pmp formula pocket guidePmp formula pocket guide
Pmp formula pocket guide
 
Formula pocket guide
Formula pocket guideFormula pocket guide
Formula pocket guide
 
Formulas for PMP exam
Formulas for PMP examFormulas for PMP exam
Formulas for PMP exam
 
PMBOK 6th ed Formulas.pdf
PMBOK 6th ed Formulas.pdfPMBOK 6th ed Formulas.pdf
PMBOK 6th ed Formulas.pdf
 
cost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.pptcost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.ppt
 
Learning pmp formulas the easy way
Learning pmp formulas the easy wayLearning pmp formulas the easy way
Learning pmp formulas the easy way
 
Formulas for pmp exam
Formulas for pmp examFormulas for pmp exam
Formulas for pmp exam
 
PMP Exam Formulas To Know
PMP Exam Formulas To KnowPMP Exam Formulas To Know
PMP Exam Formulas To Know
 
A simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value ManagementA simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value Management
 
Project cost management
Project cost managementProject cost management
Project cost management
 
Lo4b (nabil) breakeven analysis
Lo4b (nabil)   breakeven analysisLo4b (nabil)   breakeven analysis
Lo4b (nabil) breakeven analysis
 
#PMP Formulae @ a Glance By SN Panigrahi
#PMP Formulae @ a Glance By SN Panigrahi#PMP Formulae @ a Glance By SN Panigrahi
#PMP Formulae @ a Glance By SN Panigrahi
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Top Metrics for Agile @Agile NCR2011
Top Metrics for Agile @Agile NCR2011Top Metrics for Agile @Agile NCR2011
Top Metrics for Agile @Agile NCR2011
 
7 cost PMBOK
7 cost PMBOK7 cost PMBOK
7 cost PMBOK
 
PMP preparation and PMI Framework
PMP preparation and PMI FrameworkPMP preparation and PMI Framework
PMP preparation and PMI Framework
 
Project : formulation,evaluation and monitoring
Project : formulation,evaluation and monitoringProject : formulation,evaluation and monitoring
Project : formulation,evaluation and monitoring
 
projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)
 
Project cost & control
Project cost & controlProject cost & control
Project cost & control
 

More from IrfanAwan25

Scaffolding safety training.ppt
Scaffolding safety training.pptScaffolding safety training.ppt
Scaffolding safety training.pptIrfanAwan25
 
Progress Pictures Aug-19.pptx
Progress Pictures Aug-19.pptxProgress Pictures Aug-19.pptx
Progress Pictures Aug-19.pptxIrfanAwan25
 
Progress Pictures 07-Dec-2019.pptx
Progress Pictures 07-Dec-2019.pptxProgress Pictures 07-Dec-2019.pptx
Progress Pictures 07-Dec-2019.pptxIrfanAwan25
 
product-development-roadmap-template.pptx
product-development-roadmap-template.pptxproduct-development-roadmap-template.pptx
product-development-roadmap-template.pptxIrfanAwan25
 
Construction of Data Centre (Hemel Hempstead).pptx
Construction of Data Centre (Hemel Hempstead).pptxConstruction of Data Centre (Hemel Hempstead).pptx
Construction of Data Centre (Hemel Hempstead).pptxIrfanAwan25
 
Colt Hayes Planning Approach v1 220121.pptx
Colt Hayes Planning Approach v1 220121.pptxColt Hayes Planning Approach v1 220121.pptx
Colt Hayes Planning Approach v1 220121.pptxIrfanAwan25
 
PECDisputeResolution25102018.pptx
PECDisputeResolution25102018.pptxPECDisputeResolution25102018.pptx
PECDisputeResolution25102018.pptxIrfanAwan25
 
presentation.pptx
presentation.pptxpresentation.pptx
presentation.pptxIrfanAwan25
 
Colt Hayes Planning Approach v2 220121.pptx
Colt Hayes Planning Approach v2 220121.pptxColt Hayes Planning Approach v2 220121.pptx
Colt Hayes Planning Approach v2 220121.pptxIrfanAwan25
 
Colt Hayes Planning Approach v1 220121.pptx
Colt Hayes Planning Approach v1 220121.pptxColt Hayes Planning Approach v1 220121.pptx
Colt Hayes Planning Approach v1 220121.pptxIrfanAwan25
 

More from IrfanAwan25 (11)

Scaffolding safety training.ppt
Scaffolding safety training.pptScaffolding safety training.ppt
Scaffolding safety training.ppt
 
Progress Pictures Aug-19.pptx
Progress Pictures Aug-19.pptxProgress Pictures Aug-19.pptx
Progress Pictures Aug-19.pptx
 
Das HSE.ppt
Das HSE.pptDas HSE.ppt
Das HSE.ppt
 
Progress Pictures 07-Dec-2019.pptx
Progress Pictures 07-Dec-2019.pptxProgress Pictures 07-Dec-2019.pptx
Progress Pictures 07-Dec-2019.pptx
 
product-development-roadmap-template.pptx
product-development-roadmap-template.pptxproduct-development-roadmap-template.pptx
product-development-roadmap-template.pptx
 
Construction of Data Centre (Hemel Hempstead).pptx
Construction of Data Centre (Hemel Hempstead).pptxConstruction of Data Centre (Hemel Hempstead).pptx
Construction of Data Centre (Hemel Hempstead).pptx
 
Colt Hayes Planning Approach v1 220121.pptx
Colt Hayes Planning Approach v1 220121.pptxColt Hayes Planning Approach v1 220121.pptx
Colt Hayes Planning Approach v1 220121.pptx
 
PECDisputeResolution25102018.pptx
PECDisputeResolution25102018.pptxPECDisputeResolution25102018.pptx
PECDisputeResolution25102018.pptx
 
presentation.pptx
presentation.pptxpresentation.pptx
presentation.pptx
 
Colt Hayes Planning Approach v2 220121.pptx
Colt Hayes Planning Approach v2 220121.pptxColt Hayes Planning Approach v2 220121.pptx
Colt Hayes Planning Approach v2 220121.pptx
 
Colt Hayes Planning Approach v1 220121.pptx
Colt Hayes Planning Approach v1 220121.pptxColt Hayes Planning Approach v1 220121.pptx
Colt Hayes Planning Approach v1 220121.pptx
 

Recently uploaded

1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdfAldoGarca30
 
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...ronahami
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...Amil baba
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startQuintin Balsdon
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdfKamal Acharya
 
Digital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxDigital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxpritamlangde
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Arindam Chakraborty, Ph.D., P.E. (CA, TX)
 
Electromagnetic relays used for power system .pptx
Electromagnetic relays used for power system .pptxElectromagnetic relays used for power system .pptx
Electromagnetic relays used for power system .pptxNANDHAKUMARA10
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdfKamal Acharya
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Call Girls Mumbai
 
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxOrlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxMuhammadAsimMuhammad6
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityMorshed Ahmed Rahath
 
Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Ramkumar k
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxSCMS School of Architecture
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.Kamal Acharya
 
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptxrouholahahmadi9876
 

Recently uploaded (20)

1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
 
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
 
Digital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxDigital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptx
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
Electromagnetic relays used for power system .pptx
Electromagnetic relays used for power system .pptxElectromagnetic relays used for power system .pptx
Electromagnetic relays used for power system .pptx
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdf
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
 
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxOrlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
 
Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx
 

cheat sheet.ppt

  • 1. Earned Value Formulas PV (Planned Value) = BCWS (Budgeted Cost of Work Scheduled EV (Earned Value) = BCWP (Budgeted Cost of Work Performed) AC (Actual Cost) = ACWP (Actual Cost of Work Performed) SV = EV – PV (minus is behind schedule) CV = EV – AC (minus is over budget) SPI = EV/PV (Less than 1 is behind schedule) CPI = EV/AC (Less than 1 is over budget) EAC = AC + (BAC-EV) Use when variances are atypical EAC = BAC/CPI Use when variances are typical (Note: This is the same as EAC = BAC/CPI) VAC = BAC – EAC ETC = BAC – EV Use when variances are atypical ETC = (BAC – EV)/CPI Use when variances are typical ETC = EAC – AC Use when original estimates were flawed Project Selection Financials NPV (Net Present Value) = FV/(1+r)n FV= Future Value, r= interest rate, n= no. of time periods Higher NPV is better IRR (Internal Rate of Return) = Solve the NPV equation for “r” Also called Hurdle Rate Higher IRR percentage is better BCR (Benefit/Cost Ratio) Higher BCR is better. Beware, exam can call it CBR, where lower is better Payback Period = Time to recover cost of the project Lower payback period is better Cash Flow = Cash In – Cash Out Network Diagrams Precedence Diagramming Method (PDM) Also called Activity on Node (AON): Activities are in boxes Most commonly used today Has 4 relationships: F-S, S-S, F-F, S-F No “dummies” (zero duration dependencies) allowed Can analyze using either Three-Point Estimates or CPM Arrow Diagramming Method (ADM) Also called Activity on Arrow (AOA) Only 1 relationship: F-S Can have “dummies” Can analyze using either Three-Point Estimates or CPM Graphical Evaluation and Review Technique (GERT) Allows loops and repetitive activities Three Point Estimates, or PERT PERT = PROGRAM Evaluation and Review Technique Holds schedule and lets cost float 3 estimates for each task: Optimistic, Pessimistic, and Most Likely Mean Estimate = (O + 4*ML + P)/6 Standard Deviation (σ) = (P – O)/6 Critical Path Method, CPM Analysis 1 bestimate per activity: the Most Likely estimate Holds cost and lets schedule float Calculating Slack or Float Total Float (also called Slack, Float, or Project Float) is the total amount of time an activity can be delayed without delaying the project finish date. Free Float/Slack is the amount of time an activity can be delayed without delaying its successor (following activity). LS – ES: Calculates slack with forward pass LF – EF: Calculates slack with backwards pass Lag Time: Inserted wait time between activities Lead Time: Overlapping activities, also called paralleling or fast tracking. “Lead In; Lag Out” Accuracy of Estimates Order of Magnitude: -25% to +75% Budget Estimate: -10% to +25% Definitive Estimate: -5% to +10% Standard Deviations from the Norm ± 1 σ = 68.26% ± 2 σ = 95.46% ± 3 σ = 99.73% ± 6 σ = 99.99% Powers of a Project Manager 1. Expert: Best, earned on your own 2. Reward: Next best. Based on PM position 3. Formal: Power, based on PM position 4. Referent: Referring to positions of others 5. Penalty: Worst. Based on PM position Conflict Resolution (Best to Worst) 1. Problem Solving: Also called Confronting 2. Compromising: Solutions satisfy both parties 3. Withdrawal: Postponing a decision 4. Smoothing: Emphasis on agreement 5. Forcing: One viewpoint at expense of another. Channels of Communication Between Team Members = N(N-1)/2 Sources of Conflict (Order of Priority) 1. Schedules 2. Project Priorities 3. Resources 4. Technical Opinions 5. Administrative Procedures 6. Cost 7. Personality Herzberg’s Motivators 1. Achievement 2. Recognition 3. Challenge of the work itself 4. Responsibility 5. Advancement 6. Growth Also, remember Maslow’s Hierarchy of Needs Closing Project is closed when administrative closure is complete. Administrative closure is done at end of each Project Phase and at the end of the Project. Contract closure: verification that deliverables were acceptable; it is done once at the end of the contract. Contract Closure Procedure is produced under “Close Project” PMP Test Preparation