SlideShare a Scribd company logo
1 of 3
Download to read offline
by Edward Chung, PMP (http://edward-designer.com/web/pmp/)
PMP Formulas mentioned in the
PMBOK Guide 6th Edition
Name (Abbreviation) Formula Interpretation
No. of
Communication
Channels
n (n-1)/2
n = number of members in the team
n should include the project
manager
e.g. if the no. of team members
increase from 4 to 5, the increase
in communication channels:
5(5-1)/2 – 4(4-1)/2 = 4
Schedule
Performance Index
(SPI)
SPI = EV/PV
EV = Earned Value
PV = Planned Value
< 1 behind schedule
= 1 on schedule
> 1 ahead of schedule
Cost Performance
Index (CPI)
CPI = EV/AC
EV = Earned Value
AC = Actual Cost
< 1 Over budget
= 1 On budget
> 1 Under budget
sometimes the term ‘cumulative
CPI’ would be shown, which
actually is the CPI up to that
moment
Schedule Variance
(SV)
SV = EV – PV
EV = Earned Value
PV = Planned Value
< 0 Behind schedule
= 0 On schedule
> 0 Ahead of schedule
Cost Variance (CV)
CV = EV – AC
EV = Earned Value
AC = Actual Cost
< 0 Over budget
= 0 On budget
> 0 Within budget
Estimate at
Completion (EAC) if
original is flawed
EAC = AC + New ETC
AC = Actual Cost
New ETC = New Estimate to Completion
if the original estimate is based
on wrong data/assumptions or
circumstances have changed
Estimate at
Completion (EAC) if
BAC remains the
same
EAC = AC + BAC – EV
AC = Actual Cost
BAC = Budget at completion
EV = Earned Value
the variance is caused by a one-
time event and is not likely to
happen again
by Edward Chung, PMP (http://edward-designer.com/web/pmp/)
Name (Abbreviation) Formula Interpretation
Estimate at
Completion (EAC) if
CPI remains the
same
EAC = BAC/CPI
BAC = Budget at completion
CPI = Cost performance index
if the CPI would remain the same
till end of project, i.e. the original
estimation is not accurate
Estimate at
Completion (EAC) if
substandard
performance
continues
EAC = AC + (BAC -
EV)/(CPI*SPI)
AC = Actual Cost
BAC = Budget at completion
EV = Earned Value
CPI = Cost Performance Index
SPI = Schedule Performance Index
use when the question gives all
the values (AC, BAC, EV, CPI
and SPI), otherwise, this formula
is not likely to be used
To-Complete
Performance Index
(TCPI)
TCPI = (BAC – EV) /
(BAC – AC)
BAC = Budget at completion
EV = Earned value
AC = Actual Cost
TCPI = Remaining Work
/Remaining Funds
BAC = Budget at completion
EV = Earned value
CPI = Cost performance index
< 1 Under budget
= 1 On budget
> 1 Over budget
Estimate to
Completion
ETC = EAC -AC
EAC = Estimate at Completion
AC = Actual Cost
by Edward Chung, PMP (http://edward-designer.com/web/pmp/)
Name (Abbreviation) Formula Interpretation
Variance at
Completion
VAC = BAC – EAC
BAC = Budget at completion
EAC = Estimate at Completion
< 0 Over budget
= 0 On budget
> 0 Under budget
PERT Estimation
(O + 4M + P)/6
O= Optimistic estimate
M= Most Likely estimate
P= Pessimistic estimate
Standard Deviation
(P – O)/6
O= Optimistic estimate
P= Pessimistic estimate
this is a rough estimate for the
standard deviation
Float/Slack
LS – ES
LS = Late start
ES = Early start
LF – EF
LF = Late finish
EF = Early finish
= 0 On critical path
< 0 Behind schedule
The above 17 PMP formulas are all that you’ll need for the PMP Exam. Learn them and
understand their application. You will be able to solve the calculation questions in the
certification exam.
However, if you are still struggling with PMP® formulas or you want some more guided
descriptions on how to apply them with PMP® practice questions, you are advised to
explore the PM Exam Formulas Study Guide authored by Cornelius Fitchner (the same
author of the acclaimed online PMP® Exam Prep course which I used to clear my PMP®
exam – the PM PrepCast™).

More Related Content

What's hot

Comment évaluer la maturité organisationnelle en projet ? Cas d&rsquo;étude d...
Comment évaluer la maturité organisationnelle en projet ? Cas d&rsquo;étude d...Comment évaluer la maturité organisationnelle en projet ? Cas d&rsquo;étude d...
Comment évaluer la maturité organisationnelle en projet ? Cas d&rsquo;étude d...
PMI-Montréal
 
PMP Training - 08 project quality management
PMP Training - 08 project quality managementPMP Training - 08 project quality management
PMP Training - 08 project quality management
ejlp12
 

What's hot (20)

PMO Performance Measurement and Metrics - Kendrick
PMO Performance Measurement and Metrics - KendrickPMO Performance Measurement and Metrics - Kendrick
PMO Performance Measurement and Metrics - Kendrick
 
Planifier projet
Planifier projetPlanifier projet
Planifier projet
 
From WBS to Integrated Master Schedule
From WBS to Integrated Master ScheduleFrom WBS to Integrated Master Schedule
From WBS to Integrated Master Schedule
 
PMP® Certification | PMP® Certification Exam Preparation | PMP® Training Vide...
PMP® Certification | PMP® Certification Exam Preparation | PMP® Training Vide...PMP® Certification | PMP® Certification Exam Preparation | PMP® Training Vide...
PMP® Certification | PMP® Certification Exam Preparation | PMP® Training Vide...
 
Comment évaluer la maturité organisationnelle en projet ? Cas d&rsquo;étude d...
Comment évaluer la maturité organisationnelle en projet ? Cas d&rsquo;étude d...Comment évaluer la maturité organisationnelle en projet ? Cas d&rsquo;étude d...
Comment évaluer la maturité organisationnelle en projet ? Cas d&rsquo;étude d...
 
ISO 21500 - Guidance on Project Management
ISO 21500 - Guidance on Project ManagementISO 21500 - Guidance on Project Management
ISO 21500 - Guidance on Project Management
 
PMP Training - 08 project quality management
PMP Training - 08 project quality managementPMP Training - 08 project quality management
PMP Training - 08 project quality management
 
Project integration management
Project integration managementProject integration management
Project integration management
 
PMP Chapter 1 of 6 introduction (Based on PMBOK 6th edition)
PMP Chapter 1 of 6  introduction (Based on PMBOK 6th edition)PMP Chapter 1 of 6  introduction (Based on PMBOK 6th edition)
PMP Chapter 1 of 6 introduction (Based on PMBOK 6th edition)
 
Qualite1
Qualite1Qualite1
Qualite1
 
Pmp presentation chapter 1 to 7
Pmp presentation chapter 1 to 7Pmp presentation chapter 1 to 7
Pmp presentation chapter 1 to 7
 
PMP PMBOK 6th
PMP PMBOK 6thPMP PMBOK 6th
PMP PMBOK 6th
 
04 management de la qualité pm bo-k v5
04 management de la qualité   pm bo-k v504 management de la qualité   pm bo-k v5
04 management de la qualité pm bo-k v5
 
Fiatech 2016 - Advanced Work Packaging: from Theory to Practice
Fiatech 2016 - Advanced Work Packaging: from Theory to PracticeFiatech 2016 - Advanced Work Packaging: from Theory to Practice
Fiatech 2016 - Advanced Work Packaging: from Theory to Practice
 
Introduction Cours Gestion de projets.pdf
Introduction Cours Gestion de projets.pdfIntroduction Cours Gestion de projets.pdf
Introduction Cours Gestion de projets.pdf
 
Back to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinarBack to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinar
 
Project Management Maturity Assessment
Project Management Maturity AssessmentProject Management Maturity Assessment
Project Management Maturity Assessment
 
Advanced Work Packaging (AWP) - Reduction to Practice
Advanced Work Packaging (AWP) - Reduction to PracticeAdvanced Work Packaging (AWP) - Reduction to Practice
Advanced Work Packaging (AWP) - Reduction to Practice
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
Support de Cours Gestion de projets (partie 2) - Tableau de bord.pdf
Support de Cours Gestion de projets (partie 2) - Tableau de bord.pdfSupport de Cours Gestion de projets (partie 2) - Tableau de bord.pdf
Support de Cours Gestion de projets (partie 2) - Tableau de bord.pdf
 

Similar to Pmp formulas pmbok6

Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
Serdar Temiz
 
Earned value management in action - A Webinar by Vivek Prakash, pmwares
Earned value management in action - A Webinar by Vivek Prakash, pmwares Earned value management in action - A Webinar by Vivek Prakash, pmwares
Earned value management in action - A Webinar by Vivek Prakash, pmwares
Vivek Prakash
 

Similar to Pmp formulas pmbok6 (20)

Cost Controlling And Forecasting of Project.pdf
Cost Controlling And Forecasting of Project.pdfCost Controlling And Forecasting of Project.pdf
Cost Controlling And Forecasting of Project.pdf
 
Evm.calculations.Summary sheet
Evm.calculations.Summary sheetEvm.calculations.Summary sheet
Evm.calculations.Summary sheet
 
Earned value management
Earned value managementEarned value management
Earned value management
 
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
Earned Value Analysis in Project Management — an Easy Cheat Sheet  🡆 http://b...Earned Value Analysis in Project Management — an Easy Cheat Sheet  🡆 http://b...
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
 
Project Health.doc
Project Health.docProject Health.doc
Project Health.doc
 
Earned value analysis - presentation
Earned value analysis  -  presentationEarned value analysis  -  presentation
Earned value analysis - presentation
 
PM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdfPM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdf
 
Track Project Performance - Earned Value Management
Track Project Performance - Earned Value ManagementTrack Project Performance - Earned Value Management
Track Project Performance - Earned Value Management
 
PMP COST FORMULAE
PMP COST FORMULAEPMP COST FORMULAE
PMP COST FORMULAE
 
Learning pmp formulas the easy way
Learning pmp formulas the easy wayLearning pmp formulas the easy way
Learning pmp formulas the easy way
 
Formulas for pmp exam
Formulas for pmp examFormulas for pmp exam
Formulas for pmp exam
 
cost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.pptcost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.ppt
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Project Cost Management - PMP preparation course
Project Cost Management - PMP preparation courseProject Cost Management - PMP preparation course
Project Cost Management - PMP preparation course
 
PMP - Math Formulas
PMP - Math FormulasPMP - Math Formulas
PMP - Math Formulas
 
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
PMP Exam Formulas To Know
PMP Exam Formulas To KnowPMP Exam Formulas To Know
PMP Exam Formulas To Know
 
Earned value analysis (1)
Earned value analysis (1)Earned value analysis (1)
Earned value analysis (1)
 
Earned value management in action - A Webinar by Vivek Prakash, pmwares
Earned value management in action - A Webinar by Vivek Prakash, pmwares Earned value management in action - A Webinar by Vivek Prakash, pmwares
Earned value management in action - A Webinar by Vivek Prakash, pmwares
 

Recently uploaded

Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Victor Rentea
 
Why Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire businessWhy Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire business
panagenda
 

Recently uploaded (20)

WSO2's API Vision: Unifying Control, Empowering Developers
WSO2's API Vision: Unifying Control, Empowering DevelopersWSO2's API Vision: Unifying Control, Empowering Developers
WSO2's API Vision: Unifying Control, Empowering Developers
 
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
 
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
 
TEST BANK For Principles of Anatomy and Physiology, 16th Edition by Gerard J....
TEST BANK For Principles of Anatomy and Physiology, 16th Edition by Gerard J....TEST BANK For Principles of Anatomy and Physiology, 16th Edition by Gerard J....
TEST BANK For Principles of Anatomy and Physiology, 16th Edition by Gerard J....
 
Six Myths about Ontologies: The Basics of Formal Ontology
Six Myths about Ontologies: The Basics of Formal OntologySix Myths about Ontologies: The Basics of Formal Ontology
Six Myths about Ontologies: The Basics of Formal Ontology
 
Polkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin WoodPolkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin Wood
 
Elevate Developer Efficiency & build GenAI Application with Amazon Q​
Elevate Developer Efficiency & build GenAI Application with Amazon Q​Elevate Developer Efficiency & build GenAI Application with Amazon Q​
Elevate Developer Efficiency & build GenAI Application with Amazon Q​
 
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot TakeoffStrategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
 
Exploring Multimodal Embeddings with Milvus
Exploring Multimodal Embeddings with MilvusExploring Multimodal Embeddings with Milvus
Exploring Multimodal Embeddings with Milvus
 
CNIC Information System with Pakdata Cf In Pakistan
CNIC Information System with Pakdata Cf In PakistanCNIC Information System with Pakdata Cf In Pakistan
CNIC Information System with Pakdata Cf In Pakistan
 
Quantum Leap in Next-Generation Computing
Quantum Leap in Next-Generation ComputingQuantum Leap in Next-Generation Computing
Quantum Leap in Next-Generation Computing
 
Corporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptxCorporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptx
 
API Governance and Monetization - The evolution of API governance
API Governance and Monetization -  The evolution of API governanceAPI Governance and Monetization -  The evolution of API governance
API Governance and Monetization - The evolution of API governance
 
Decarbonising Commercial Real Estate: The Role of Operational Performance
Decarbonising Commercial Real Estate: The Role of Operational PerformanceDecarbonising Commercial Real Estate: The Role of Operational Performance
Decarbonising Commercial Real Estate: The Role of Operational Performance
 
[BuildWithAI] Introduction to Gemini.pdf
[BuildWithAI] Introduction to Gemini.pdf[BuildWithAI] Introduction to Gemini.pdf
[BuildWithAI] Introduction to Gemini.pdf
 
Introduction to Multilingual Retrieval Augmented Generation (RAG)
Introduction to Multilingual Retrieval Augmented Generation (RAG)Introduction to Multilingual Retrieval Augmented Generation (RAG)
Introduction to Multilingual Retrieval Augmented Generation (RAG)
 
Navigating Identity and Access Management in the Modern Enterprise
Navigating Identity and Access Management in the Modern EnterpriseNavigating Identity and Access Management in the Modern Enterprise
Navigating Identity and Access Management in the Modern Enterprise
 
DBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor PresentationDBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor Presentation
 
Why Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire businessWhy Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire business
 
JohnPollard-hybrid-app-RailsConf2024.pptx
JohnPollard-hybrid-app-RailsConf2024.pptxJohnPollard-hybrid-app-RailsConf2024.pptx
JohnPollard-hybrid-app-RailsConf2024.pptx
 

Pmp formulas pmbok6

  • 1. by Edward Chung, PMP (http://edward-designer.com/web/pmp/) PMP Formulas mentioned in the PMBOK Guide 6th Edition Name (Abbreviation) Formula Interpretation No. of Communication Channels n (n-1)/2 n = number of members in the team n should include the project manager e.g. if the no. of team members increase from 4 to 5, the increase in communication channels: 5(5-1)/2 – 4(4-1)/2 = 4 Schedule Performance Index (SPI) SPI = EV/PV EV = Earned Value PV = Planned Value < 1 behind schedule = 1 on schedule > 1 ahead of schedule Cost Performance Index (CPI) CPI = EV/AC EV = Earned Value AC = Actual Cost < 1 Over budget = 1 On budget > 1 Under budget sometimes the term ‘cumulative CPI’ would be shown, which actually is the CPI up to that moment Schedule Variance (SV) SV = EV – PV EV = Earned Value PV = Planned Value < 0 Behind schedule = 0 On schedule > 0 Ahead of schedule Cost Variance (CV) CV = EV – AC EV = Earned Value AC = Actual Cost < 0 Over budget = 0 On budget > 0 Within budget Estimate at Completion (EAC) if original is flawed EAC = AC + New ETC AC = Actual Cost New ETC = New Estimate to Completion if the original estimate is based on wrong data/assumptions or circumstances have changed Estimate at Completion (EAC) if BAC remains the same EAC = AC + BAC – EV AC = Actual Cost BAC = Budget at completion EV = Earned Value the variance is caused by a one- time event and is not likely to happen again
  • 2. by Edward Chung, PMP (http://edward-designer.com/web/pmp/) Name (Abbreviation) Formula Interpretation Estimate at Completion (EAC) if CPI remains the same EAC = BAC/CPI BAC = Budget at completion CPI = Cost performance index if the CPI would remain the same till end of project, i.e. the original estimation is not accurate Estimate at Completion (EAC) if substandard performance continues EAC = AC + (BAC - EV)/(CPI*SPI) AC = Actual Cost BAC = Budget at completion EV = Earned Value CPI = Cost Performance Index SPI = Schedule Performance Index use when the question gives all the values (AC, BAC, EV, CPI and SPI), otherwise, this formula is not likely to be used To-Complete Performance Index (TCPI) TCPI = (BAC – EV) / (BAC – AC) BAC = Budget at completion EV = Earned value AC = Actual Cost TCPI = Remaining Work /Remaining Funds BAC = Budget at completion EV = Earned value CPI = Cost performance index < 1 Under budget = 1 On budget > 1 Over budget Estimate to Completion ETC = EAC -AC EAC = Estimate at Completion AC = Actual Cost
  • 3. by Edward Chung, PMP (http://edward-designer.com/web/pmp/) Name (Abbreviation) Formula Interpretation Variance at Completion VAC = BAC – EAC BAC = Budget at completion EAC = Estimate at Completion < 0 Over budget = 0 On budget > 0 Under budget PERT Estimation (O + 4M + P)/6 O= Optimistic estimate M= Most Likely estimate P= Pessimistic estimate Standard Deviation (P – O)/6 O= Optimistic estimate P= Pessimistic estimate this is a rough estimate for the standard deviation Float/Slack LS – ES LS = Late start ES = Early start LF – EF LF = Late finish EF = Early finish = 0 On critical path < 0 Behind schedule The above 17 PMP formulas are all that you’ll need for the PMP Exam. Learn them and understand their application. You will be able to solve the calculation questions in the certification exam. However, if you are still struggling with PMP® formulas or you want some more guided descriptions on how to apply them with PMP® practice questions, you are advised to explore the PM Exam Formulas Study Guide authored by Cornelius Fitchner (the same author of the acclaimed online PMP® Exam Prep course which I used to clear my PMP® exam – the PM PrepCast™).