MECHANICAL ENGINEER:- 7 YEARS 5 MONTHS EXPERIENCE IN CONSTRUCTION OF POWER PLANTS, REFINERY &CEMENT
PLANT.
Professionally accomplished Mechanical Engineering,with qualitative and valuable experience in contract management, costing & site
coordination in mechanical construction, with a flair for adopting modern construction methodologies in compliance with quality standards.
EDUCATIONAL CREDENTIALS
Diploma in Mechanical Engineering 2005  H.K.E.S Polytechnic, RAICHUR (Karnataka)
Computer Proficiency: AutoCAD - 2000, M.S.Office.
PROFESSIONAL EXPERIENCE
HAPBCO
Project. Manager March-2012 to till date
My Duties:-
 Fabrication and erection of pelletizing unit.
 Erection of ball mill equipment and grinding mill equipment.
 Sequential erection of kiln with shell and motors.
 Attending weekly meeting with client and pmc.
 MEETINGS WITH DIFFERENT AREA MANAGER ON DAILY BASIS FOR THEIR REQUIRMENT TO COMPLETE THE
PROJECT.
 HANDLEING SITE PURCHASING, PROGRESS, ACCOUNTS, ETC.
 DEAL WITH CLIENT HAVING GOOD COMMUNICATION AND CORESSPONDENT SKILLS.
 COST CONTROLLING AND MONITORING PROGRESS AND COST & REPORTING..
 MANAGING SITE RESOURCES LIKE MANPOWER AND MACHINERY AND SITE REQUIRMENTS.
PROJECT: - ULTRA TECH CEMENT –RAWAN, CHATTISGARH
BHUSHAN STEEL &POWER LTD-JHARSUGUDA, ORISSA
UB ENGINEERINGLTD.
Asst.Resident.Engineer Aug-2011 to March-2012
 Sequational erection of boiler structure, pressure parts, ducting, girders&boiler drum.
 Interacting with clients to understand their specific requirements and execute projects accordingly.
 Supervising all construction activities including providing technical inputs for methodologies of construction & coordinating about site
management activities.
 Detail knowledge of boiler structure work along with pressure parts.
 Participated from the beginning in the commissioning activities of the complete plant with a generation capacity of 660 MW &600 MW .
 Project Handled: - 660 MWJINDAL & SON,DARANG,TALCHER ORISSA
IOT ENGINEERING PROJECTS LTD, MUMBAI
EXE.ENGINEER Aug 2009 to Aug-2011
 Drawing up detailed project plan, estimates, cost-benefit analysis Contractor’s bill certification, fabrication and site execution for
various units of ACC plant-2, Wadi construction such as
 T.A.Duct support structure & Duct. Clinker silo, DPC Erection& Fabrication
 Administering construction of mechanical works according to drawing & specifications and coordinating with contractor to assure
smooth functioning of work
 Accountable for planning, supervising sites against the planned construction schedules and administering the timely completion of
projects
 Interacting with clients to understand their specific requirements and execute projects accordingly.
 Supervising all construction activities including providing technical inputs for methodologies of construction & coordinating about site
management activities.
 T.A.Duct fabrication of 600 MT, along with manpower supply of 100 heads for shut down work at ACC Wadi Site.
 IOCL Paradip site, VGO Site total pre assembly, erection &Commissioning of VGO unit. Of 2000 MT structure, 27000 IM piping along
with ducting, &stack.
Project Handled
Title: - IOCL Paradeep, DHDT, VGO HEATERS.
Client:-IOCL
Title: - Construction of ACC Plant-2, WADI
Client:-ACC
PETRON ENGINEERING CONSTRUCTION LTD, Mumbai
Asst.Engineer, Sr.Asst.Engineer, , Trainee. Engineer Nov 2005 to Aug 2009
Planning, Coordination, Project Control, Communication, Personnel.
 Supervising all construction activities including providing technical inputs for method of construction & coordinating about site
management activities.
 Interacting with clients to understand their specific requirements and execute projects accordingly.
 Planning, monitoring & controlling all site activities including manpower planning, resource planning & material planning for the
erection.
 Attending site coordination meeting as required with client along with site-in-charge for resolving problems associated with area of
work.
 Coordination with site store for management of various materials associated with area of work.
 Control on site activities for erection progress and resolving site discrepancy reports with engineering.
 Erection of equipments –rotary &static with erection planning and methods of erection.
Project Handled
CLIENT: - NTPC, BHEL, RAMCO, RELIANCE, INDIANOIL.
Title:- Construction of Project – Power Plant, Cement Plant, Refinery, Steel Plant.
Languages:-
Languages English, Hindi, Oriya, Marathi, Kannada.
Primary Language English, Hindi, Oriya
Nationality INDIAN
Salary requirement:-
Current CTC GROSS: - 7.2 Lakhs /annum
Expected CTC GROSS: - 7.5 Lakhs /annum
I HEREBY DECLARE THAT THE ABOVE WRITTEN PARTICULARS ARE TRUE TO THE BEST OF MY KNOWLEDGE AND BELIEF.
MOHD.FEROZ

Resume

  • 1.
    RESUME MOHD.FEROZ Email: -iqbalferoz99@gmail.com H.NO-345, Charta Road Mobile-09637545725 Ankush Nagar, Balepir Pass Port No: - H4354298 Nagar Road, Beed Maharashtra -431122 MECHANICAL ENGINEER:- 7 YEARS 5 MONTHS EXPERIENCE IN CONSTRUCTION OF POWER PLANTS, REFINERY &CEMENT PLANT. Professionally accomplished Mechanical Engineering,with qualitative and valuable experience in contract management, costing & site coordination in mechanical construction, with a flair for adopting modern construction methodologies in compliance with quality standards. EDUCATIONAL CREDENTIALS Diploma in Mechanical Engineering 2005  H.K.E.S Polytechnic, RAICHUR (Karnataka) Computer Proficiency: AutoCAD - 2000, M.S.Office. PROFESSIONAL EXPERIENCE HAPBCO Project. Manager March-2012 to till date My Duties:-  Fabrication and erection of pelletizing unit.  Erection of ball mill equipment and grinding mill equipment.  Sequential erection of kiln with shell and motors.  Attending weekly meeting with client and pmc.  MEETINGS WITH DIFFERENT AREA MANAGER ON DAILY BASIS FOR THEIR REQUIRMENT TO COMPLETE THE PROJECT.  HANDLEING SITE PURCHASING, PROGRESS, ACCOUNTS, ETC.  DEAL WITH CLIENT HAVING GOOD COMMUNICATION AND CORESSPONDENT SKILLS.  COST CONTROLLING AND MONITORING PROGRESS AND COST & REPORTING..  MANAGING SITE RESOURCES LIKE MANPOWER AND MACHINERY AND SITE REQUIRMENTS. PROJECT: - ULTRA TECH CEMENT –RAWAN, CHATTISGARH BHUSHAN STEEL &POWER LTD-JHARSUGUDA, ORISSA UB ENGINEERINGLTD. Asst.Resident.Engineer Aug-2011 to March-2012  Sequational erection of boiler structure, pressure parts, ducting, girders&boiler drum.  Interacting with clients to understand their specific requirements and execute projects accordingly.  Supervising all construction activities including providing technical inputs for methodologies of construction & coordinating about site management activities.  Detail knowledge of boiler structure work along with pressure parts.  Participated from the beginning in the commissioning activities of the complete plant with a generation capacity of 660 MW &600 MW .  Project Handled: - 660 MWJINDAL & SON,DARANG,TALCHER ORISSA IOT ENGINEERING PROJECTS LTD, MUMBAI EXE.ENGINEER Aug 2009 to Aug-2011
  • 2.
     Drawing updetailed project plan, estimates, cost-benefit analysis Contractor’s bill certification, fabrication and site execution for various units of ACC plant-2, Wadi construction such as  T.A.Duct support structure & Duct. Clinker silo, DPC Erection& Fabrication  Administering construction of mechanical works according to drawing & specifications and coordinating with contractor to assure smooth functioning of work  Accountable for planning, supervising sites against the planned construction schedules and administering the timely completion of projects  Interacting with clients to understand their specific requirements and execute projects accordingly.  Supervising all construction activities including providing technical inputs for methodologies of construction & coordinating about site management activities.  T.A.Duct fabrication of 600 MT, along with manpower supply of 100 heads for shut down work at ACC Wadi Site.  IOCL Paradip site, VGO Site total pre assembly, erection &Commissioning of VGO unit. Of 2000 MT structure, 27000 IM piping along with ducting, &stack. Project Handled Title: - IOCL Paradeep, DHDT, VGO HEATERS. Client:-IOCL Title: - Construction of ACC Plant-2, WADI Client:-ACC PETRON ENGINEERING CONSTRUCTION LTD, Mumbai Asst.Engineer, Sr.Asst.Engineer, , Trainee. Engineer Nov 2005 to Aug 2009 Planning, Coordination, Project Control, Communication, Personnel.  Supervising all construction activities including providing technical inputs for method of construction & coordinating about site management activities.  Interacting with clients to understand their specific requirements and execute projects accordingly.  Planning, monitoring & controlling all site activities including manpower planning, resource planning & material planning for the erection.  Attending site coordination meeting as required with client along with site-in-charge for resolving problems associated with area of work.  Coordination with site store for management of various materials associated with area of work.  Control on site activities for erection progress and resolving site discrepancy reports with engineering.  Erection of equipments –rotary &static with erection planning and methods of erection. Project Handled CLIENT: - NTPC, BHEL, RAMCO, RELIANCE, INDIANOIL. Title:- Construction of Project – Power Plant, Cement Plant, Refinery, Steel Plant. Languages:- Languages English, Hindi, Oriya, Marathi, Kannada. Primary Language English, Hindi, Oriya Nationality INDIAN Salary requirement:- Current CTC GROSS: - 7.2 Lakhs /annum
  • 3.
    Expected CTC GROSS:- 7.5 Lakhs /annum I HEREBY DECLARE THAT THE ABOVE WRITTEN PARTICULARS ARE TRUE TO THE BEST OF MY KNOWLEDGE AND BELIEF. MOHD.FEROZ