SlideShare a Scribd company logo
1 of 22
Download to read offline
Civil Engineering Department Saad.bilbas@epu.edu.iq 77
Civil Engineering Department Saad.bilbas@epu.edu.iq 78
Earthworks or Groundworks
o Earthworks
An embankment or other construction made of earth; especially one used as a field
fortification ,or the operations connected with excavations and embankments of earth, or a
work of art consisting of a portion of land modified by an artist as shown in Figure 8.
o Site investigation
To select a foundation from tables, or to design a foundation, it is necessary to calculate the
loads on the foundation and determine the nature of the subsoil, its bearing capacity.
Where the nature of the subsoil is known from geological surveys, adjacent building
work or trial pits or borings.
Figure 8: Earth Work
Civil Engineering Department Saad.bilbas@epu.edu.iq 79
o Site visit:
A visit to the site and its surroundings should always be made to record everything relevant
from a careful examination of the nature of the subsoil, vegetation, evidence of marshy
ground, signs of ground water, and flooding.
o Top Soil:
This layer of top soil, which is about 100 to 300 mm deep, is some times referred to as
vegetable top soil. It is loosely compacted, supports growing plant life and is unsatisfactory
as a foundation. It should be stripped from the site of buildings because of its poor bearing
strengths and its ability to retain moisture and support vegetation which might adversely
affect the health of occupants of buildings as presented in Figure 9
Figure 9: Top Soil
Civil Engineering Department Saad.bilbas@epu.edu.iq 80
o Sub Soil:
Subsoil is the general term for soil below the top soil. It is unusual for a subsoil to consist of
gravel, sand or clay by itself as shown in Figure 10
Figure 10: Sub Soil
Civil Engineering Department Saad.bilbas@epu.edu.iq 81
o Excavation
As shown in Figure 10, after the site has been cleared and the approximate location of the
corners of the building have been established , excavation can be begun depending on the soil
type, slope, complexity of the building, the availability of equipment, a number of machines,
ranging from road grader to backhoe to bulldozer, may be used. If the house is to be built on a
rocky site, a blasting contractor might also be employed. The excavator first removes from the
surface all soil containing organic matter with in footprint of the house. This mixture of top
soil and plant material (grass and small roots) is stockpiled for future use a backfill.
Figure 10: Excavation Work
Civil Engineering Department Saad.bilbas@epu.edu.iq 82
o Volume of H:
• H > 0.25m (avoiding top soil) as presented in Figure 11
• Bearing: the foundation should bear on natural soil.
• At depth near, so offer from frost action (H>=0.5m).
o Bearing:
• B.C = 10 --- 15 Ton/m2
(KPa)
• If the soil volume under the foundation is changed uniformly so that no damage would be
caused to the building.
• But after raining seasons, the soil at top tends to become much water than the soil under
foundation. Therefore, after raining the soil at exterior expanded more than at the under
foundation and thus when the sun shines the soil at exterior dries out more quickly and
shrinks more than the soil at under foundation
• The concrete foundation tiles slightly.
• Cracking will be happened on walls as shown in Figure 12
Figure 11: Typical Foundation
Figure 12:
Wall cracking
Civil Engineering Department Saad.bilbas@epu.edu.iq 83
o Bulk Fill
It is all that material placed in the fill, from the ground surface after clearing and removing of
top soil as presented in Figure 13
.
Figure 13: Bulk Fill Earthwork
Civil Engineering Department Saad.bilbas@epu.edu.iq 84
o Borrow
It is excavation and importing from outside the construction batter limits as shown in
Figure 14
.
Figure 14: Borrow Earthworks
o Rock
It is any igneous, sedimentary, or metamorphic stone which is solidly bonded or cemented
together and which occurs in masses, ledges, seams or layers as presented in Figure 15
Figure 15: Borrow Earthworks
Civil Engineering Department Saad.bilbas@epu.edu.iq 85
o Cut
It is excavation within the construction scope as exhibited in Figure 16.
Figure 16: Cutting Earthworks
Civil Engineering Department Saad.bilbas@epu.edu.iq 86
o Granular Fill Material
It is material which has been placed in the fill and which contains less than 35% passing a
75μm sieve and has a sand equivalent greater than no. 20 as shown in Figure 17
Figure 17: Filling Earthworks
Civil Engineering Department Saad.bilbas@epu.edu.iq 87
o Overbreak
It is the excavated material removed by contracting operations from outside the construction
properties, but not authorized as a borrow such as explained in Figure 18
o Side Drain
It is an open drainage excavation often at the toe of a fill earthwork as discovered in Figure 19
Figure 18: Filling Earthworks
Figure 19: Side drain Earthworks
Civil Engineering Department Saad.bilbas@epu.edu.iq 88
o Subgrade
It is defined as that layer of material at the top 1.0 m of the construction measured down from
the underside of the sub-base course. It may be filled or insitue material as mentioned in Figure
20
o Surface Water Channel
It is a water channel formed at the subgrade surface at the edge of the road as shown in Figure
21.
Figure 20: Subgrade Earthworks
Figure 21: surface Water Channel
Civil Engineering Department Saad.bilbas@epu.edu.iq 89
Nominal Maximum Particle Size Maximum Layer Thickness
Up to 100 mm 200 mm
100 mm to 200 mm 1.5 times the 85 percentile size
Over 200 mm Refer contract documents where applicable
In term of Layer thickness, the maximum thickness of each layer of fill before
compaction shall be in accordance with Tables 1 below unless field trials show, to the
satisfaction of the Engineer that the specified compaction is obtained with thicker
layers.
Table 1: Bulk Fill
Civil Engineering Department Saad.bilbas@epu.edu.iq 90
o Shoring and Timbering
The length, breadth and depth of trench should be as per drawing and design given in the
map. Where the soil is wet or cohesion less the side slopes are supported by the use of cross
bars and side shutters (planks) in order to prevent the collapse of the trench. This is called
shoring and timbering. The details of shoring and timbering are given in Figures 23 and 24.
Figure 22: Loose Timbering
Civil Engineering Department Saad.bilbas@epu.edu.iq 91
Figure 23: Close timbering
o Unit of measurement of Earthwork
The unit of measurement of earth work is cubic meter (meter3). If the length of trench = 1 m,
breadth 1 m and depth 1 m then the total earthwork is 1 m × 1 m × 1 m = 1 cub meter.
Vol. of earth work (length × breadth × depth)
If the shape of the trench is trapezoidal
Vol. of earth work =
𝑩𝟏 𝑩𝟐
𝟐
x Height x Length
Civil Engineering Department Saad.bilbas@epu.edu.iq 92
o Frost action:
• Evasion of the soil due to freezing of the water in the soil near the natural ground level.
• Compact granular subsoil does not suffer volume change.
• The water in soil more than (0.5m) below N.G.L. does not usually freeze.
• Freezing of the water in the soil near the natural ground level.
• Granular subsoil does not suffer volume change.
o Temporary timber support:
It is used to uphold the sides of the excavation to avoid collapse of the trenches sides‘. Also,
nature of the soil being excavated will allocate at what depth of the trench timber support to
the sides should use.
• Soft granular soil readily crumbles and the sides of trenches in such soil may have to be
supported for the full depth of the trenches.
• Clay soil does not usually require support up to 1.5m (dry weather).
Case (1):
Deep Trenches in Clay Soil.
Civil Engineering Department Saad.bilbas@epu.edu.iq 93
Case 2:
Soft Soil (Loam).
Case 3:
Dry Granular Soil (sand)
Civil Engineering Department Saad.bilbas@epu.edu.iq 94
o Base of the Trench
• The base of the trench should be made flat and all loose soil should be removed from
it.
• If by mistake the depth of the trench becomes more than the required depth, it should
not be filled by loose soil rather it should be filled with lean concrete such as 1:3:6 or
1: 4 : 8 or 1 : 5: 10 and made flat.
• If it is required to construct a soil embankment, at least 10% more soil should be
added for instance; if the designed height of the embankment is 6.0 m, the
embankment of 6.6 m height should be constructed initially to allow for the
settlement of soil at later stage.
so, embankment height = 6+0.6
= 6.6m
• In case of deep cutting or filling a side slope of 1 : 1 or 1 : 2 (i.e. 1 vertical and 2
horizontal) is usually maintained.
• If it is required to put new soil over old soil, Benching is required to be done so that a
perfect bonding between old and new soil is achieved. Benching means construction
of steps.
• Grass should be planted on the slope to check the soil erosion; in order to maintain
the slope of the embankment.
Figure 25: Trench Side Slope
Civil Engineering Department Saad.bilbas@epu.edu.iq 95
Figure 26: Lean Concrete Trench Base
Figure 27: Grass planted on the side slope to check the soil erosion
Figure 28: Stabilization and benching of Cover Soil
Figure 29: Stabilization and benching of Cover Soil
Civil Engineering Department Saad.bilbas@epu.edu.iq 96
Also, apart from the above earthwork is required to be carried out in the construction of roads.
During construction of roads two types of situation can arise i.e. it may require either cutting
or filling. During excavation we may get different types of soil layers. For this a reformed line
is required to be made for controlling the soil texture and depth of the road/embankment as
presented in Figures 30.
Figure 30: Embankment Construction Layers
Civil Engineering Department Saad.bilbas@epu.edu.iq 97
Furthermore; Figure 31 above aids in explaining the cutting or filling which has been done
as per the drawing. Catch water drains are made on the sides of the cutting which takes out
and run off water from road surface.
Figure 31: Cross section of a road
Civil Engineering Department Saad.bilbas@epu.edu.iq 98
o WBM Road
It is coming from Water Bound Macadam. The word Macadam comes from the name of
Scottish Engineer JOHN L. MACADAM. So, the WBM is the pavement base course made of
crushed or broken aggregates which they are mechanically interlocked by rolling, and voids
filled by screening and binding material with the assistance of water as shown in Figure 32
below.
o Materials to be used in WBN road
• Crushed trap rock – most suitable
• Crushed slag
• Burnt Brick bats
• Aggregate
• Laterite
• Screenings to be used as filler material
o Salient Features of WBM Roads
• Low cost
• Thickness range: 8cm to 30cm
• Camber: 2.5% to 3% or 1:36 to 1:48
• Surface is better than earthen road, but rough as compared to bituminous or
concrete roads
• Can be used as a Base Course for Bituminous or concrete roads

More Related Content

What's hot

Proctor compaction test
Proctor compaction testProctor compaction test
Proctor compaction testFaizan Tanoli
 
Seal coat,prime coat and tack coat
Seal coat,prime coat and tack coatSeal coat,prime coat and tack coat
Seal coat,prime coat and tack coatMuhammadArif856
 
Internship report on rcc road
Internship report on rcc roadInternship report on rcc road
Internship report on rcc roaddeepak athwal
 
Chapter 4 earth work and quantities new
Chapter 4 earth work and quantities newChapter 4 earth work and quantities new
Chapter 4 earth work and quantities newBashaFayissa1
 
Cone Penetration Test
Cone Penetration TestCone Penetration Test
Cone Penetration TestMuftah Aljoat
 
Group index method
Group index methodGroup index method
Group index methodUsama Aslam
 
Introduction to highway engineering
Introduction to highway engineeringIntroduction to highway engineering
Introduction to highway engineeringAavani Thampi
 
Construction of flexible pavements
Construction of flexible pavementsConstruction of flexible pavements
Construction of flexible pavementspradip dangar
 
Bearing capacity of shallow foundations by abhishek sharma
Bearing capacity of shallow foundations by abhishek sharma Bearing capacity of shallow foundations by abhishek sharma
Bearing capacity of shallow foundations by abhishek sharma ABHISHEK SHARMA
 
Geometric design of highways
Geometric design of highways Geometric design of highways
Geometric design of highways akshaydesai76
 
SPECIFIC GRAVITY TEST ON BITUMINOUS MATERIALS.
SPECIFIC GRAVITY TEST ON BITUMINOUS MATERIALS.SPECIFIC GRAVITY TEST ON BITUMINOUS MATERIALS.
SPECIFIC GRAVITY TEST ON BITUMINOUS MATERIALS.Sayed Sajid H.Zidani
 
Unit 1 sheet pile-converted
Unit 1   sheet pile-convertedUnit 1   sheet pile-converted
Unit 1 sheet pile-convertedNigitha rajan
 
Determination of Immediate Settlement
Determination of Immediate Settlement Determination of Immediate Settlement
Determination of Immediate Settlement Suez Halder
 
pavement analysis
pavement analysis pavement analysis
pavement analysis Saeed Badeli
 
3. Highway Drainage.pdf
3. Highway Drainage.pdf3. Highway Drainage.pdf
3. Highway Drainage.pdfRoshani Shahi
 
Pavement thickness design
Pavement thickness designPavement thickness design
Pavement thickness designSohail Khan
 

What's hot (20)

Proctor compaction test
Proctor compaction testProctor compaction test
Proctor compaction test
 
Seal coat,prime coat and tack coat
Seal coat,prime coat and tack coatSeal coat,prime coat and tack coat
Seal coat,prime coat and tack coat
 
Internship report on rcc road
Internship report on rcc roadInternship report on rcc road
Internship report on rcc road
 
Chapter 4 earth work and quantities new
Chapter 4 earth work and quantities newChapter 4 earth work and quantities new
Chapter 4 earth work and quantities new
 
Cone Penetration Test
Cone Penetration TestCone Penetration Test
Cone Penetration Test
 
CBR Test
CBR TestCBR Test
CBR Test
 
Group index method
Group index methodGroup index method
Group index method
 
Introduction to highway engineering
Introduction to highway engineeringIntroduction to highway engineering
Introduction to highway engineering
 
Construction of flexible pavements
Construction of flexible pavementsConstruction of flexible pavements
Construction of flexible pavements
 
Bearing capacity of shallow foundations by abhishek sharma
Bearing capacity of shallow foundations by abhishek sharma Bearing capacity of shallow foundations by abhishek sharma
Bearing capacity of shallow foundations by abhishek sharma
 
Drawing And Report
Drawing And Report Drawing And Report
Drawing And Report
 
Geometric design of highways
Geometric design of highways Geometric design of highways
Geometric design of highways
 
SPECIFIC GRAVITY TEST ON BITUMINOUS MATERIALS.
SPECIFIC GRAVITY TEST ON BITUMINOUS MATERIALS.SPECIFIC GRAVITY TEST ON BITUMINOUS MATERIALS.
SPECIFIC GRAVITY TEST ON BITUMINOUS MATERIALS.
 
Design of rigid pavements
Design of rigid pavementsDesign of rigid pavements
Design of rigid pavements
 
Unit 1 sheet pile-converted
Unit 1   sheet pile-convertedUnit 1   sheet pile-converted
Unit 1 sheet pile-converted
 
Determination of Immediate Settlement
Determination of Immediate Settlement Determination of Immediate Settlement
Determination of Immediate Settlement
 
pavement analysis
pavement analysis pavement analysis
pavement analysis
 
3. Highway Drainage.pdf
3. Highway Drainage.pdf3. Highway Drainage.pdf
3. Highway Drainage.pdf
 
Grouting Methods
Grouting Methods Grouting Methods
Grouting Methods
 
Pavement thickness design
Pavement thickness designPavement thickness design
Pavement thickness design
 

Similar to Earthworks or Groundworks

Mat Foundation-Nirvik-34-Sec-B
Mat Foundation-Nirvik-34-Sec-BMat Foundation-Nirvik-34-Sec-B
Mat Foundation-Nirvik-34-Sec-BArif Abdullah
 
Water proofing treatement
Water proofing treatementWater proofing treatement
Water proofing treatementRajiva Gupta
 
CH_3-Road_Construction_Technology_1658041305[1].ppt
CH_3-Road_Construction_Technology_1658041305[1].pptCH_3-Road_Construction_Technology_1658041305[1].ppt
CH_3-Road_Construction_Technology_1658041305[1].pptRamchandraYadav20
 
Soil Bearing Capacity and Case study of Black Cotton Soil
Soil Bearing Capacity and Case study of Black Cotton SoilSoil Bearing Capacity and Case study of Black Cotton Soil
Soil Bearing Capacity and Case study of Black Cotton SoilPraveen S.K
 
Excavation and filling - Execution, QC & Equipment 101
Excavation and filling - Execution, QC & Equipment 101Excavation and filling - Execution, QC & Equipment 101
Excavation and filling - Execution, QC & Equipment 101SHAZEBALIKHAN1
 
Specifications of rcc foundation
Specifications of rcc foundation Specifications of rcc foundation
Specifications of rcc foundation Prabhat chhirolya
 
2 1 excavation_basementconstruction
2 1 excavation_basementconstruction2 1 excavation_basementconstruction
2 1 excavation_basementconstructionvietcgxd
 
(2010) - Yates M, Krzeminski M, Berthier D, Hamidi B - The Application of Jet...
(2010) - Yates M, Krzeminski M, Berthier D, Hamidi B - The Application of Jet...(2010) - Yates M, Krzeminski M, Berthier D, Hamidi B - The Application of Jet...
(2010) - Yates M, Krzeminski M, Berthier D, Hamidi B - The Application of Jet...Michal Krzeminski
 
Mat foundation
Mat foundationMat foundation
Mat foundationshuvo293
 
Allan block Installation guide
Allan block Installation guideAllan block Installation guide
Allan block Installation guidekristenjames
 
Construction methode ash yard
Construction methode   ash yardConstruction methode   ash yard
Construction methode ash yardranow
 
Construction methode ash yard
Construction methode   ash yardConstruction methode   ash yard
Construction methode ash yardranow
 
Bearing capacity
Bearing capacityBearing capacity
Bearing capacityBhanu Ojha
 
Construction of Dams.pptx
Construction of Dams.pptxConstruction of Dams.pptx
Construction of Dams.pptxKhawarSakhani
 
Effect of Replacement Layers on Bearing Capacity of Silty Clay Layer
Effect of Replacement Layers on Bearing Capacity of Silty Clay LayerEffect of Replacement Layers on Bearing Capacity of Silty Clay Layer
Effect of Replacement Layers on Bearing Capacity of Silty Clay LayerIJAEMSJORNAL
 

Similar to Earthworks or Groundworks (20)

Mat Foundation-Nirvik-34-Sec-B
Mat Foundation-Nirvik-34-Sec-BMat Foundation-Nirvik-34-Sec-B
Mat Foundation-Nirvik-34-Sec-B
 
Water proofing treatement
Water proofing treatementWater proofing treatement
Water proofing treatement
 
CH_3-Road_Construction_Technology_1658041305[1].ppt
CH_3-Road_Construction_Technology_1658041305[1].pptCH_3-Road_Construction_Technology_1658041305[1].ppt
CH_3-Road_Construction_Technology_1658041305[1].ppt
 
Ay 2020 2021 fe supply key
Ay 2020 2021 fe supply keyAy 2020 2021 fe supply key
Ay 2020 2021 fe supply key
 
Soil Bearing Capacity and Case study of Black Cotton Soil
Soil Bearing Capacity and Case study of Black Cotton SoilSoil Bearing Capacity and Case study of Black Cotton Soil
Soil Bearing Capacity and Case study of Black Cotton Soil
 
Combined Footing
Combined FootingCombined Footing
Combined Footing
 
Excavation and filling - Execution, QC & Equipment 101
Excavation and filling - Execution, QC & Equipment 101Excavation and filling - Execution, QC & Equipment 101
Excavation and filling - Execution, QC & Equipment 101
 
Specifications of rcc foundation
Specifications of rcc foundation Specifications of rcc foundation
Specifications of rcc foundation
 
Interlocking pavement
Interlocking pavementInterlocking pavement
Interlocking pavement
 
2 1 excavation_basementconstruction
2 1 excavation_basementconstruction2 1 excavation_basementconstruction
2 1 excavation_basementconstruction
 
Work check list
Work check listWork check list
Work check list
 
(2010) - Yates M, Krzeminski M, Berthier D, Hamidi B - The Application of Jet...
(2010) - Yates M, Krzeminski M, Berthier D, Hamidi B - The Application of Jet...(2010) - Yates M, Krzeminski M, Berthier D, Hamidi B - The Application of Jet...
(2010) - Yates M, Krzeminski M, Berthier D, Hamidi B - The Application of Jet...
 
Mat foundation
Mat foundationMat foundation
Mat foundation
 
Allan block Installation guide
Allan block Installation guideAllan block Installation guide
Allan block Installation guide
 
Construction methode ash yard
Construction methode   ash yardConstruction methode   ash yard
Construction methode ash yard
 
Construction methode ash yard
Construction methode   ash yardConstruction methode   ash yard
Construction methode ash yard
 
Bearing capacity
Bearing capacityBearing capacity
Bearing capacity
 
Mat Foundation
Mat FoundationMat Foundation
Mat Foundation
 
Construction of Dams.pptx
Construction of Dams.pptxConstruction of Dams.pptx
Construction of Dams.pptx
 
Effect of Replacement Layers on Bearing Capacity of Silty Clay Layer
Effect of Replacement Layers on Bearing Capacity of Silty Clay LayerEffect of Replacement Layers on Bearing Capacity of Silty Clay Layer
Effect of Replacement Layers on Bearing Capacity of Silty Clay Layer
 

More from Bahzad5

دليل تجارب الاسفلت المختبرية - Asphalt Experiments Guide Laboratory
دليل تجارب الاسفلت المختبرية - Asphalt Experiments Guide Laboratoryدليل تجارب الاسفلت المختبرية - Asphalt Experiments Guide Laboratory
دليل تجارب الاسفلت المختبرية - Asphalt Experiments Guide LaboratoryBahzad5
 
2013 (Total Station & Civil 3D) فێرکاری
2013  (Total Station & Civil 3D) فێرکاری2013  (Total Station & Civil 3D) فێرکاری
2013 (Total Station & Civil 3D) فێرکاریBahzad5
 
Engineering field knowledge -زانیاری بواری ئەندازیاری
Engineering field knowledge -زانیاری بواری ئەندازیاریEngineering field knowledge -زانیاری بواری ئەندازیاری
Engineering field knowledge -زانیاری بواری ئەندازیاریBahzad5
 
(atmosphere correction) زانیاری دەربارەی
(atmosphere correction) زانیاری دەربارەی(atmosphere correction) زانیاری دەربارەی
(atmosphere correction) زانیاری دەربارەیBahzad5
 
(Building Permit Guidelines ) ڕێنماییەکانی مۆڵەتی بینا
(Building Permit Guidelines ) ڕێنماییەکانی مۆڵەتی بینا(Building Permit Guidelines ) ڕێنماییەکانی مۆڵەتی بینا
(Building Permit Guidelines ) ڕێنماییەکانی مۆڵەتی بیناBahzad5
 
المبادئ التوجيهية البلدية - ڕێنامەی شارەوانی (Municipal guidelines)
المبادئ التوجيهية البلدية - ڕێنامەی شارەوانی  (Municipal guidelines)المبادئ التوجيهية البلدية - ڕێنامەی شارەوانی  (Municipal guidelines)
المبادئ التوجيهية البلدية - ڕێنامەی شارەوانی (Municipal guidelines)Bahzad5
 
CONDITIONS OF CONTRACT FOR WORKS OF CIVIL ENGINEERING CONSTRUCTION
CONDITIONS OF CONTRACT  FOR WORKS OF CIVIL  ENGINEERING CONSTRUCTIONCONDITIONS OF CONTRACT  FOR WORKS OF CIVIL  ENGINEERING CONSTRUCTION
CONDITIONS OF CONTRACT FOR WORKS OF CIVIL ENGINEERING CONSTRUCTIONBahzad5
 
Lecture 1: Basics of trigonometry (surveying)
Lecture 1: Basics of trigonometry (surveying)Lecture 1: Basics of trigonometry (surveying)
Lecture 1: Basics of trigonometry (surveying)Bahzad5
 
الشروط العامة لمقاولات اعمال الهندسة المدنية
الشروط العامة لمقاولات اعمال الهندسة المدنيةالشروط العامة لمقاولات اعمال الهندسة المدنية
الشروط العامة لمقاولات اعمال الهندسة المدنيةBahzad5
 
GENERAL CONDITIONS FOR CONTRACTS OF CIVIL ENGINEERING WORKS
GENERAL CONDITIONS  FOR  CONTRACTS OF CIVIL ENGINEERING WORKS GENERAL CONDITIONS  FOR  CONTRACTS OF CIVIL ENGINEERING WORKS
GENERAL CONDITIONS FOR CONTRACTS OF CIVIL ENGINEERING WORKS Bahzad5
 
2 سەرەتاکانی دیزاین
2 سەرەتاکانی دیزاین2 سەرەتاکانی دیزاین
2 سەرەتاکانی دیزاینBahzad5
 
Soil Mechanics (Problems & solutions)
Soil Mechanics (Problems & solutions)Soil Mechanics (Problems & solutions)
Soil Mechanics (Problems & solutions)Bahzad5
 
ڕێبەری بەشە ئەندازیارییەکان
ڕێبەری بەشە ئەندازیارییەکانڕێبەری بەشە ئەندازیارییەکان
ڕێبەری بەشە ئەندازیارییەکانBahzad5
 
سەرەتاکانی دیزاین
سەرەتاکانی دیزاینسەرەتاکانی دیزاین
سەرەتاکانی دیزاینBahzad5
 
ڕێبەری بەشەئەندازیارییەكانی زانكۆی كۆیە
ڕێبەری بەشەئەندازیارییەكانی زانكۆی كۆیەڕێبەری بەشەئەندازیارییەكانی زانكۆی كۆیە
ڕێبەری بەشەئەندازیارییەكانی زانكۆی كۆیەBahzad5
 
پرۆژەی ناساندنی ئەندازیاری
پرۆژەی ناساندنی ئەندازیاریپرۆژەی ناساندنی ئەندازیاری
پرۆژەی ناساندنی ئەندازیاریBahzad5
 
بناغە و بنەپایە Footing and Foundation
بناغە و بنەپایە Footing and Foundationبناغە و بنەپایە Footing and Foundation
بناغە و بنەپایە Footing and FoundationBahzad5
 
slump test سڵەمپ تێست
slump test سڵەمپ تێستslump test سڵەمپ تێست
slump test سڵەمپ تێستBahzad5
 
Design of Storm Sewer System
Design of Storm Sewer SystemDesign of Storm Sewer System
Design of Storm Sewer SystemBahzad5
 
ڕۆنی بزوێنەر
ڕۆنی بزوێنەرڕۆنی بزوێنەر
ڕۆنی بزوێنەرBahzad5
 

More from Bahzad5 (20)

دليل تجارب الاسفلت المختبرية - Asphalt Experiments Guide Laboratory
دليل تجارب الاسفلت المختبرية - Asphalt Experiments Guide Laboratoryدليل تجارب الاسفلت المختبرية - Asphalt Experiments Guide Laboratory
دليل تجارب الاسفلت المختبرية - Asphalt Experiments Guide Laboratory
 
2013 (Total Station & Civil 3D) فێرکاری
2013  (Total Station & Civil 3D) فێرکاری2013  (Total Station & Civil 3D) فێرکاری
2013 (Total Station & Civil 3D) فێرکاری
 
Engineering field knowledge -زانیاری بواری ئەندازیاری
Engineering field knowledge -زانیاری بواری ئەندازیاریEngineering field knowledge -زانیاری بواری ئەندازیاری
Engineering field knowledge -زانیاری بواری ئەندازیاری
 
(atmosphere correction) زانیاری دەربارەی
(atmosphere correction) زانیاری دەربارەی(atmosphere correction) زانیاری دەربارەی
(atmosphere correction) زانیاری دەربارەی
 
(Building Permit Guidelines ) ڕێنماییەکانی مۆڵەتی بینا
(Building Permit Guidelines ) ڕێنماییەکانی مۆڵەتی بینا(Building Permit Guidelines ) ڕێنماییەکانی مۆڵەتی بینا
(Building Permit Guidelines ) ڕێنماییەکانی مۆڵەتی بینا
 
المبادئ التوجيهية البلدية - ڕێنامەی شارەوانی (Municipal guidelines)
المبادئ التوجيهية البلدية - ڕێنامەی شارەوانی  (Municipal guidelines)المبادئ التوجيهية البلدية - ڕێنامەی شارەوانی  (Municipal guidelines)
المبادئ التوجيهية البلدية - ڕێنامەی شارەوانی (Municipal guidelines)
 
CONDITIONS OF CONTRACT FOR WORKS OF CIVIL ENGINEERING CONSTRUCTION
CONDITIONS OF CONTRACT  FOR WORKS OF CIVIL  ENGINEERING CONSTRUCTIONCONDITIONS OF CONTRACT  FOR WORKS OF CIVIL  ENGINEERING CONSTRUCTION
CONDITIONS OF CONTRACT FOR WORKS OF CIVIL ENGINEERING CONSTRUCTION
 
Lecture 1: Basics of trigonometry (surveying)
Lecture 1: Basics of trigonometry (surveying)Lecture 1: Basics of trigonometry (surveying)
Lecture 1: Basics of trigonometry (surveying)
 
الشروط العامة لمقاولات اعمال الهندسة المدنية
الشروط العامة لمقاولات اعمال الهندسة المدنيةالشروط العامة لمقاولات اعمال الهندسة المدنية
الشروط العامة لمقاولات اعمال الهندسة المدنية
 
GENERAL CONDITIONS FOR CONTRACTS OF CIVIL ENGINEERING WORKS
GENERAL CONDITIONS  FOR  CONTRACTS OF CIVIL ENGINEERING WORKS GENERAL CONDITIONS  FOR  CONTRACTS OF CIVIL ENGINEERING WORKS
GENERAL CONDITIONS FOR CONTRACTS OF CIVIL ENGINEERING WORKS
 
2 سەرەتاکانی دیزاین
2 سەرەتاکانی دیزاین2 سەرەتاکانی دیزاین
2 سەرەتاکانی دیزاین
 
Soil Mechanics (Problems & solutions)
Soil Mechanics (Problems & solutions)Soil Mechanics (Problems & solutions)
Soil Mechanics (Problems & solutions)
 
ڕێبەری بەشە ئەندازیارییەکان
ڕێبەری بەشە ئەندازیارییەکانڕێبەری بەشە ئەندازیارییەکان
ڕێبەری بەشە ئەندازیارییەکان
 
سەرەتاکانی دیزاین
سەرەتاکانی دیزاینسەرەتاکانی دیزاین
سەرەتاکانی دیزاین
 
ڕێبەری بەشەئەندازیارییەكانی زانكۆی كۆیە
ڕێبەری بەشەئەندازیارییەكانی زانكۆی كۆیەڕێبەری بەشەئەندازیارییەكانی زانكۆی كۆیە
ڕێبەری بەشەئەندازیارییەكانی زانكۆی كۆیە
 
پرۆژەی ناساندنی ئەندازیاری
پرۆژەی ناساندنی ئەندازیاریپرۆژەی ناساندنی ئەندازیاری
پرۆژەی ناساندنی ئەندازیاری
 
بناغە و بنەپایە Footing and Foundation
بناغە و بنەپایە Footing and Foundationبناغە و بنەپایە Footing and Foundation
بناغە و بنەپایە Footing and Foundation
 
slump test سڵەمپ تێست
slump test سڵەمپ تێستslump test سڵەمپ تێست
slump test سڵەمپ تێست
 
Design of Storm Sewer System
Design of Storm Sewer SystemDesign of Storm Sewer System
Design of Storm Sewer System
 
ڕۆنی بزوێنەر
ڕۆنی بزوێنەرڕۆنی بزوێنەر
ڕۆنی بزوێنەر
 

Recently uploaded

SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 

Recently uploaded (20)

SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 

Earthworks or Groundworks

  • 1. Civil Engineering Department Saad.bilbas@epu.edu.iq 77
  • 2. Civil Engineering Department Saad.bilbas@epu.edu.iq 78 Earthworks or Groundworks o Earthworks An embankment or other construction made of earth; especially one used as a field fortification ,or the operations connected with excavations and embankments of earth, or a work of art consisting of a portion of land modified by an artist as shown in Figure 8. o Site investigation To select a foundation from tables, or to design a foundation, it is necessary to calculate the loads on the foundation and determine the nature of the subsoil, its bearing capacity. Where the nature of the subsoil is known from geological surveys, adjacent building work or trial pits or borings. Figure 8: Earth Work
  • 3. Civil Engineering Department Saad.bilbas@epu.edu.iq 79 o Site visit: A visit to the site and its surroundings should always be made to record everything relevant from a careful examination of the nature of the subsoil, vegetation, evidence of marshy ground, signs of ground water, and flooding. o Top Soil: This layer of top soil, which is about 100 to 300 mm deep, is some times referred to as vegetable top soil. It is loosely compacted, supports growing plant life and is unsatisfactory as a foundation. It should be stripped from the site of buildings because of its poor bearing strengths and its ability to retain moisture and support vegetation which might adversely affect the health of occupants of buildings as presented in Figure 9 Figure 9: Top Soil
  • 4. Civil Engineering Department Saad.bilbas@epu.edu.iq 80 o Sub Soil: Subsoil is the general term for soil below the top soil. It is unusual for a subsoil to consist of gravel, sand or clay by itself as shown in Figure 10 Figure 10: Sub Soil
  • 5. Civil Engineering Department Saad.bilbas@epu.edu.iq 81 o Excavation As shown in Figure 10, after the site has been cleared and the approximate location of the corners of the building have been established , excavation can be begun depending on the soil type, slope, complexity of the building, the availability of equipment, a number of machines, ranging from road grader to backhoe to bulldozer, may be used. If the house is to be built on a rocky site, a blasting contractor might also be employed. The excavator first removes from the surface all soil containing organic matter with in footprint of the house. This mixture of top soil and plant material (grass and small roots) is stockpiled for future use a backfill. Figure 10: Excavation Work
  • 6. Civil Engineering Department Saad.bilbas@epu.edu.iq 82 o Volume of H: • H > 0.25m (avoiding top soil) as presented in Figure 11 • Bearing: the foundation should bear on natural soil. • At depth near, so offer from frost action (H>=0.5m). o Bearing: • B.C = 10 --- 15 Ton/m2 (KPa) • If the soil volume under the foundation is changed uniformly so that no damage would be caused to the building. • But after raining seasons, the soil at top tends to become much water than the soil under foundation. Therefore, after raining the soil at exterior expanded more than at the under foundation and thus when the sun shines the soil at exterior dries out more quickly and shrinks more than the soil at under foundation • The concrete foundation tiles slightly. • Cracking will be happened on walls as shown in Figure 12 Figure 11: Typical Foundation Figure 12: Wall cracking
  • 7. Civil Engineering Department Saad.bilbas@epu.edu.iq 83 o Bulk Fill It is all that material placed in the fill, from the ground surface after clearing and removing of top soil as presented in Figure 13 . Figure 13: Bulk Fill Earthwork
  • 8. Civil Engineering Department Saad.bilbas@epu.edu.iq 84 o Borrow It is excavation and importing from outside the construction batter limits as shown in Figure 14 . Figure 14: Borrow Earthworks o Rock It is any igneous, sedimentary, or metamorphic stone which is solidly bonded or cemented together and which occurs in masses, ledges, seams or layers as presented in Figure 15 Figure 15: Borrow Earthworks
  • 9. Civil Engineering Department Saad.bilbas@epu.edu.iq 85 o Cut It is excavation within the construction scope as exhibited in Figure 16. Figure 16: Cutting Earthworks
  • 10. Civil Engineering Department Saad.bilbas@epu.edu.iq 86 o Granular Fill Material It is material which has been placed in the fill and which contains less than 35% passing a 75μm sieve and has a sand equivalent greater than no. 20 as shown in Figure 17 Figure 17: Filling Earthworks
  • 11. Civil Engineering Department Saad.bilbas@epu.edu.iq 87 o Overbreak It is the excavated material removed by contracting operations from outside the construction properties, but not authorized as a borrow such as explained in Figure 18 o Side Drain It is an open drainage excavation often at the toe of a fill earthwork as discovered in Figure 19 Figure 18: Filling Earthworks Figure 19: Side drain Earthworks
  • 12. Civil Engineering Department Saad.bilbas@epu.edu.iq 88 o Subgrade It is defined as that layer of material at the top 1.0 m of the construction measured down from the underside of the sub-base course. It may be filled or insitue material as mentioned in Figure 20 o Surface Water Channel It is a water channel formed at the subgrade surface at the edge of the road as shown in Figure 21. Figure 20: Subgrade Earthworks Figure 21: surface Water Channel
  • 13. Civil Engineering Department Saad.bilbas@epu.edu.iq 89 Nominal Maximum Particle Size Maximum Layer Thickness Up to 100 mm 200 mm 100 mm to 200 mm 1.5 times the 85 percentile size Over 200 mm Refer contract documents where applicable In term of Layer thickness, the maximum thickness of each layer of fill before compaction shall be in accordance with Tables 1 below unless field trials show, to the satisfaction of the Engineer that the specified compaction is obtained with thicker layers. Table 1: Bulk Fill
  • 14. Civil Engineering Department Saad.bilbas@epu.edu.iq 90 o Shoring and Timbering The length, breadth and depth of trench should be as per drawing and design given in the map. Where the soil is wet or cohesion less the side slopes are supported by the use of cross bars and side shutters (planks) in order to prevent the collapse of the trench. This is called shoring and timbering. The details of shoring and timbering are given in Figures 23 and 24. Figure 22: Loose Timbering
  • 15. Civil Engineering Department Saad.bilbas@epu.edu.iq 91 Figure 23: Close timbering o Unit of measurement of Earthwork The unit of measurement of earth work is cubic meter (meter3). If the length of trench = 1 m, breadth 1 m and depth 1 m then the total earthwork is 1 m × 1 m × 1 m = 1 cub meter. Vol. of earth work (length × breadth × depth) If the shape of the trench is trapezoidal Vol. of earth work = 𝑩𝟏 𝑩𝟐 𝟐 x Height x Length
  • 16. Civil Engineering Department Saad.bilbas@epu.edu.iq 92 o Frost action: • Evasion of the soil due to freezing of the water in the soil near the natural ground level. • Compact granular subsoil does not suffer volume change. • The water in soil more than (0.5m) below N.G.L. does not usually freeze. • Freezing of the water in the soil near the natural ground level. • Granular subsoil does not suffer volume change. o Temporary timber support: It is used to uphold the sides of the excavation to avoid collapse of the trenches sides‘. Also, nature of the soil being excavated will allocate at what depth of the trench timber support to the sides should use. • Soft granular soil readily crumbles and the sides of trenches in such soil may have to be supported for the full depth of the trenches. • Clay soil does not usually require support up to 1.5m (dry weather). Case (1): Deep Trenches in Clay Soil.
  • 17. Civil Engineering Department Saad.bilbas@epu.edu.iq 93 Case 2: Soft Soil (Loam). Case 3: Dry Granular Soil (sand)
  • 18. Civil Engineering Department Saad.bilbas@epu.edu.iq 94 o Base of the Trench • The base of the trench should be made flat and all loose soil should be removed from it. • If by mistake the depth of the trench becomes more than the required depth, it should not be filled by loose soil rather it should be filled with lean concrete such as 1:3:6 or 1: 4 : 8 or 1 : 5: 10 and made flat. • If it is required to construct a soil embankment, at least 10% more soil should be added for instance; if the designed height of the embankment is 6.0 m, the embankment of 6.6 m height should be constructed initially to allow for the settlement of soil at later stage. so, embankment height = 6+0.6 = 6.6m • In case of deep cutting or filling a side slope of 1 : 1 or 1 : 2 (i.e. 1 vertical and 2 horizontal) is usually maintained. • If it is required to put new soil over old soil, Benching is required to be done so that a perfect bonding between old and new soil is achieved. Benching means construction of steps. • Grass should be planted on the slope to check the soil erosion; in order to maintain the slope of the embankment. Figure 25: Trench Side Slope
  • 19. Civil Engineering Department Saad.bilbas@epu.edu.iq 95 Figure 26: Lean Concrete Trench Base Figure 27: Grass planted on the side slope to check the soil erosion Figure 28: Stabilization and benching of Cover Soil Figure 29: Stabilization and benching of Cover Soil
  • 20. Civil Engineering Department Saad.bilbas@epu.edu.iq 96 Also, apart from the above earthwork is required to be carried out in the construction of roads. During construction of roads two types of situation can arise i.e. it may require either cutting or filling. During excavation we may get different types of soil layers. For this a reformed line is required to be made for controlling the soil texture and depth of the road/embankment as presented in Figures 30. Figure 30: Embankment Construction Layers
  • 21. Civil Engineering Department Saad.bilbas@epu.edu.iq 97 Furthermore; Figure 31 above aids in explaining the cutting or filling which has been done as per the drawing. Catch water drains are made on the sides of the cutting which takes out and run off water from road surface. Figure 31: Cross section of a road
  • 22. Civil Engineering Department Saad.bilbas@epu.edu.iq 98 o WBM Road It is coming from Water Bound Macadam. The word Macadam comes from the name of Scottish Engineer JOHN L. MACADAM. So, the WBM is the pavement base course made of crushed or broken aggregates which they are mechanically interlocked by rolling, and voids filled by screening and binding material with the assistance of water as shown in Figure 32 below. o Materials to be used in WBN road • Crushed trap rock – most suitable • Crushed slag • Burnt Brick bats • Aggregate • Laterite • Screenings to be used as filler material o Salient Features of WBM Roads • Low cost • Thickness range: 8cm to 30cm • Camber: 2.5% to 3% or 1:36 to 1:48 • Surface is better than earthen road, but rough as compared to bituminous or concrete roads • Can be used as a Base Course for Bituminous or concrete roads