SlideShare a Scribd company logo
1 of 8
Download to read offline
ALLAN BLOCK INSTALLATION GUIDE
ALLAN BLOCK
InstallationGuide
This installation guide outlines how to construct
AB retaining wall systems. It should be noted that
these are only guidelines. Ensure that all local
building codes are complied with.
01: Getting Started
Determine if your Wall Requires Reinforcement
For wall heights less than or equal to those listed in
Table 1, a non reinforced gravity retaining wall may be built.
For walls that exceed the maximum values listed in Table 1,
or where loads exist, the wall will need reinforcement.
Refer to the C&M Allan Block brochure (ref. CM.AB0505)
or a C&M representative for guidelines to designing for
geogrid reinforced retaining walls.
02: Order Materials
Blocks
A) Length of Wall x Total Height of Wall = Wall Area.
B) Total Height of Wall.
C) Wall Area x Number of Blocks /m2
= Blocks Required.
Convert all dimensions to metres before calculating.
To calculate total wall height:
add buried block + above ground wall height.
For walls under 1m, 100mm of block must be buried.
For walls 1-3m, one block must be buried.
Leveling Pad & Drainage Zone
Use a well graded aggregate, 12mm to 20mm free draining
material for the drainage zone within the block cores.
Check your local aggregate sources for availability.
Drainage Zone
The drainage material includes the material in the block cores
plus a 300mm layer behind the blocks.
A simple way to calculate this material in cubic metres is:
Wall Height x Wall Length x 0.5 (block + 300mm) = Cubic Metres
of drainage material.
Note: C&M takes no responsibility for quantity of material ordered.
Base
The typical base for an AB retaining wall is 600mm
wide x 150mm deep.
Geogrid
If geogrid is required, contact C&M or your AB distributor for
specifications and assistance.
The wall must first have been designed by a suitably
qualified engineer.
For walls that exceed the heights shown in the following table
(table 1), please refer to the Commercial Installation section.
Figure 1: Calculated Materials
Wall Height
Wall Length
Drain Field
Geogrid
Zone
Base
Figure 2: Start Wall at Lowest Elevation
Stepped BaseSloping Grade
Start Here
Figure 3: Excavate the Base Trench
Width = 600mm
Depth = 150mm for base
plus embedment required
as per step 2.
03: Excavate Base Trench and Geogrid Zone
Excavate base trench at the wall location. Make sure the trench is level and to the
proper depth (Figure 3).
Walls built on a sloping grade will require a stepped base (Figure 2).
Begin excavation at the lowest point and dig a level trench into the slope until
it is deep enough to accommodate the 150mm Base Material and the recommended
depth of block embedment.
Step up the height of one block and repeat.
For geogrid walls, excavate behind the wall far enough to fit the geogrid length,
and a safe buffer beyond this zone.
04: Install Base Material
Place 150mm base material in the base trench and rake smooth.
Compact with a mechanical plate compacter (Figure 4).
Check the entire length for level and adjust as needed.
05: Install Base Course
Begin at the lowest wall elevation (Figure 2).
Place the first row of AB blocks on the Base Material with the raised front lip
facing up and forward to the front of the wall.
Check and adjust the level and alignment of all blocks. Check levels frequently,
side-to-side and front-to-back. Verify the proper position of all blocks by examining
a straight line across the back of the blocks or the back of the lips (Figure 5).
Make minor adjustments by tapping the block with a rubber mallet or by placing small
amounts of coarse sand underneath.
Irregularities in the base course become larger as the wall stacks up. Careful
attention to a straight and level base course will ensure a quality finished wall.
1
4
5 kPa
Poor Soils (25˚)
Including sands, gravelly clays,
sandy clays & silt clays
Average Soils (30˚)
Including well graded sands
& gravelly sands
Good Soils (35˚)
Including gravels, sandy gravels
& crushed sandstone
Poor Soils (25˚)
Including sands, gravelly clays,
sandy clays & silt clays
Average Soils (30˚)
Including well graded sands
& gravelly sands
Good Soils (35˚)
Including gravels, sandy gravels
& crushed sandstone
Poor Soils (25˚)
Including sands, gravelly clays,
sandy clays & silt clays
Average Soils (30˚)
Including well graded sands
& gravelly sands
Good Soils (35˚)
Including gravels, sandy gravels
& crushed sandstone
Backfill Friction Angle, φ
600 600 800 800 1000
AB Junior AB Aussie AB Vertical AB Classic AB Stones
800 800 800 1000 1400*
800 800 1000 1200 1500*
400 400 400 400 400
600 600 600 600 800
600 600 800 800 800
400 400 400 400 600
400 400 600 600 800
800 800 800 800 1000
Job Site
Level Above Wall
Surcharge of 5 kPa
(Driveway)
Slope Above Wall in Excess of
1 in 4 & Surcharge of 1.5 kPa
Slope Above Wall
*Wall Heights achieved by replacing granular fill (in drainage zone) with ‘No Fines’ concrete
Table 1: Maximum Heights(mm) for Allan Block - without grid
Allan Block Gravity Walls only up to 1.5m maximum height in accordance with AS4678-2002
Figure 4: Compact Base Material
Compact
Base Material
Level
06: Install Drainage Material
Place an agricultural pipe at the bottom rear of the drainage field with appropriate fall
to designated drainage point.
Fill the AB hollow cores and the 300mm drain field behind the wall with drainage material.
Proper placement of drainage material serves three important purposes. First, the material
creates a positive interlock between the blocks. Second, it increases structural stability.
Finally, it permits the release of water pressure from behind the wall.
07: Backfill and Compact
Compaction of the material behind the wall is critical for a quality wall installation.
Use select backfill behind the drain field. Heavy clays and organic materials
are not recommended due to their water holding properties.
Use a plate compacter to consolidate the aggregate in the block cores and lock the
base course in place. The first pass of the plate compacter should be directly over the
top of the block cores (Figure 7).
After running the plate compacter on top of the base course and drain field, compact
the backfill material immediately behind the wall. Compact in a path parallel to the wall,
working from the front of the wall to the back of the backfill material (Figure 7).
Compact in 200mm lifts. Use only light weight equipment within 1.2m of the wall face.
Check the base course for level and adjust as necessary.
08: Install Second & Subsequent Courses
Remove all excess drainage material and stone from the top surface of the blocks.
This prepares a smooth surface for placement of the next course of AB.
Stack the next row of block with the vertical joints offset from the block below.
Sight down the wall line to check for a straight wall. Block may be adjusted to form
straight lines and smooth curves.
Check for level before installing drainage and backfill materials. Adjust as necessary.
Repeat steps 6 to 8, installing drainage and backfill material and compacting parallel
to the wall face from front to back.
For non reinforced gravity walls, repeat steps 6 to 8 to the top of the wall then proceed
to step 12. For walls needing reinforcement, follow the steps below.
09: Install First Layer of Geogrid
Cut sections of geogrid to specified length. The wall must first have been designed
by a suitably qualified engineer. Check manufacturer’s grid specifications for strength
or machine direction of the geogrid.
Place geogrid behind the block lip with the machine direction extending
back into the slope (Figure 8).
Place next course of blocks on top of the geogrid.
Pull on the back of the grid to remove any slack.
Stake in place before installing drainage and backfill material (Figure 9).
Figure 8: Determining Geogrid Direction
Figure 5: Install Base Course
String line
Adjust with
a rubber
mallet
Level
Figure 6: Install Drainage Material & Backfill Soils
Drainage Material
Figure 7: Compact Drainage Material & Backfill Soils
Infill soils
Fill void in
front of block
Compact
parallel
to wall
Machine Direction
Figure 12: Ending & Topping Walls
CapMulch
Lawn
Filter Fabric Filter Fabric
Filter Fabric
10: Backfill & Compact
Place drainage material in blocks and 300mm behind the blocks. Place a 200mm layer
of backfill soil on top of the geogrid. All drainage material in the drain field and infill soils
within 1m of the wall must be properly compacted using a walk behind plate compacter.
Compact in maximum 200mm lifts, starting on the wall and working in a path
that runs parallel to the wall towards the back of the reinforced zone (Figure 10).
Never operate compacting equipment directly on geogrid.
All heavy equipment must be kept at least 1.2m from the wall face (figure 11).
11: Install Additional Courses
Repeat steps 7 through 10.
Each lift of drainage and backfill material should be installed in the same manner.
Compact in lifts of 200mm, the height of one AB unit (Figure 10).
Check block for level after compacting each lift, and adjust as needed.
12: Ending and Topping Walls
AB's patented raised front lip provides a built-in edging for landscape rock, mulch,
grass, soil or AB Cappers (Figure 12). Place filter fabric between the drainage zone
and landscaped zone.
Walls with step down can be easily finished by turning the ends back into the
hillside (Figure 13), or using a cornerstone with a split end as the last unit before
step down.
13: Grading and Water Management
Grade backfill to ensure that water drainage from the entire site flows away from
the wall. A drainage swale can also be incorporated above the wall to divert water
away from the top of the wall.
Erosion at the end of the wall can be prevented by rolling the end of the wall
into the bank (Figure 13). As a general rule bury 500mm of block into the hillside
to prevent potential problems.
For projects where excessive water run off above the wall is a factor (parking lots,
roof drains, etc.) the top of the wall must be finished off to prevent the penetration
of water. To ensure that water run off from above the retaining wall does not saturate
the soil behind it, a 150mm (min.) layer of impermeable fill should be placed on top of
the entire run off area.
Install an agricultural drain pipe at the bottom of the drainage field and vent away
from wall to remove excess water.
Figure 9: Install First Layer of Geogrid
Figure 10: Compact in 200mm Lifts
Figure 11: Keep Heavy Equipment 1.2m from
the wall face
Figure 13: Final Grading & Topping Off the Wall Options
Set second course
on top of Geogrid
Keep heavy
equipment
1.2m from
the wall face
Compact in
200mm lifts
Pull back Geogrid
and stake in place
Place cut edge
of grid flight
against lip
Flowing turn-in of wall For a step-down that doubles as a planter, turn the wall in
2 or 3 blocks after the AB Cornerstone.
For a natural flow into the landscape, curve the wall back
into the hillside.
14: Curves
Curves and serpentine walls are easy to build. Walls designed with curves complement
natural landscape forms and are easy to build. To create outside curves, simply remove
the 'wings' from the back of the Allan Block units and tighten the radius of the curve.
For setback walls a slight coning will occur on curved walls. Design curved walls so
the radius at the top of the wall is at least 1.2m. Refer to the table below to find the
minimum recommended radius at the wall base while maintaining a 1.2m radius at the
top of the wall.
15: Terraces
In some cases it is preferable to terrace a site rather than construct a single wall
as this allows for garden beds and stairs between levels to be incorporated into
the landscape design. Although terracing improves the look of the landscape,
it is important to consider the pressure of the upper wall on the lower wall.
The distance between the walls must be greater than 1.5 times the height of the
lower wall to ensure the top terrace does not apply loads to the lower wall.
This does not take into account global stability issues which need to be considered.
Terraced hillsides may require engineering assistance. Contact C&M or your local
distributor for more information.
Wall Height
1.43m 1.52m 1.6m 1.7m
1.2m 1.8m 2.4m 3.0m
1.55m 1.66m 1.8m 1.9m
1.67m 1.8m 2.0m 2.1m
Figure 14: Remove wings for outside curves
H2
D
H1
Figure 15: Terraced Walls - No Reinforcement
Required (if walls are below heights shown in Table 1).
Keep the front
of the blocks
tight together
Inside Curve
Outide Curve
Consistent
spacing
Setback
3˚
6˚
12˚
Use this chart to find the minimum recommended radius at base of wall.
Table 2: AB Radius Chart
Figure 16: Outside Corners
Figure 17: Outside Corners
16: Corners
When building corners, start from the corners and build away.
Soft corners are easier to build than angles.
Always avoid small block cuts at the corners.
Outside Corners
Outside corners are formed by reversing the directions for each course of cornerstone.
They must be ordered as right hand or left hand units.
Inside Corners
Inside corners are easily constructed by modifying Allan Block units (figure 17).
Remove half of the raised front lip.
They can be chiselled off, but a masonry saw works best.
Lay the modified block perpendicular to another Allan Block unit with the lips lined up.
Remove the opposite half of the lip of another AB unit and position it over the right
angle corner.
On each successive row, simply reverse the position of the modified block to obtain
an interlocked corner.
Step 1
Step 1
Step 1
Ensure base is level
going both directions
Remove notch
to form corner
Area of
front lip
removed
Blocks with
part of lip
removed
Step 1 Step 2
Remove part of
front lip so next
course will seat
properly
Figure 23: Step Tread Options
17: Steps
Always check local code requirements before building an type of step application.
The steps (figures 18 - 22, left) are general guidelines for building steps.
By understanding the basic installation elements, steps can be easily incorporated
into the wall installation.
Before excavation can begin, the rise and run of the step treads must be determined
and code requirements must be met. With that information, the entire base trench
can then be excavated. Some examples of different step tread options are illustrated
below (figure 23).
Our example (figures 18 - 22, left) uses a base trench of 150mm and a step tread
of AB cappers and pavers.
Excavate to the necessary depth and width for each step riser (figure 18)
and thoroughly compact the entire area with a mechanical plate compactor.
Check for level.
Starting at the first step, fill the base trench with 150mm of drainage material.
Rake smooth.
Compact and check for level. Steps need extra compaction to avoid any settling
later. Better compaction is achieved by backfilling and compacting in 100mm
lifts or less when able.
Install blocks on the base material. Allow for a space of at least 150mm behind
the blocks for drainage material (figure 19).
Adjust for level and alignment of each block as it’s installed.
Install drainage material in the block cores, fill any space in front of and behind
the block. When backfilling behind the blocks, fill the entire area that was earlier
excavated to create the base for the next step riser. This should produce a level
base for the next set of risers. We recommend backfilling and compacting behind
the block in 100mm lifts to achieve better compaction when able.
Rake drainage material smooth and compact with the first pass of the compactor
directly on the tops of the block and then working in a path that runs parallel
to the block (figure 20).
Repeat this process for each additional course of steps needed (figures 21 & 22).
AB Cappers AB Cappers
& Pavers
Pavers Concrete
Figure 18: Step 1
Figure 19: Step 2
Figure 20: Step 3
Figure 21: Step 4
Figure 22: Step 5
Rise
Base
Trench
Run
150mm
Excavate for steps and compact
Install and level blocks on
base material
Backfill block cores and behind
block with drainage material &
compact
Install next step course
150mm Step tread depth
Continue for each new step
150mm Step tread depth
Next step
Install cappers and
paver treads. Use sand
under the pavers to
level with AB Cappers
ALLAN BLOCK
Installation Guide - Ref: CM.ABIN0905
Important:
Please consult with the appropriate council for local design and construction of a
retaining wall. Councils in general require that retaining walls be designed and certified
by a suitably qualified engineer where the wall is over 500mm in height and/or where
there is a load such as a road, driveway, house, building or hydrostatic pressure.
Patents:
Allan Block Retaining Wall Systems are protected by the Australian patent numbers
682394 and 133306
CM0504_K4027
Melbourne - Essendon (Head Office)
264 Keilor Road North Essendon, VIC 3041
phone: 03) 9375 8500 I fax: 03) 9374 4736
C&M Brick Pty Ltd
ABN: 14 055 701 034
www.cmbrick.com.au
Bendigo
69 Collins Street Kangaroo Flat, VIC 3555
phone: 03) 5447 8866 I fax: 03) 5447 0399
Canberra
6 Tennant Street Fyshwick, ACT 2609
phone: 02) 6239 1255 I fax: 02) 6280 7284
Melbourne - Campbellfield
194 Northbourne Road Campbellfield, VIC 3061
phone: 03) 9305 0900 I fax: 03) 9303 9035
Newcastle
Old Maitland Road Sandgate, NSW 2304
phone: 02) 4967 3611 I fax: 02) 4960 1187
Nowra
270-274 Princes Hwy South Nowra, NSW 2541
phone: 02) 4421 3500 I fax: 02) 4421 3082
Queensland
5 Demand Avenue Arundel, QLD 4211
phone: 07) 5571 6644 I fax: 07) 5571 6644
South Australia
Cnr Grand Junction & Blakeney Rds Ottoway, SA 5013
phone: 08) 8304 2323 I fax: 08) 8341 1101
Sydney - Moorebank
20 Kelso Crescent Moorebank, NSW 2170
phone: 02) 9822 6822 I fax: 02) 9601 7446

More Related Content

What's hot

Cpt by h.a.akbar
Cpt by h.a.akbarCpt by h.a.akbar
Cpt by h.a.akbarRASULUET
 
Engineering properties of soil
Engineering properties of soilEngineering properties of soil
Engineering properties of soilRakesh Reddy
 
Influence of geological condition on foundation and design of building
Influence of geological condition on  foundation and design of buildingInfluence of geological condition on  foundation and design of building
Influence of geological condition on foundation and design of buildingDarshan Darji
 
Slope Stability Analysis Using Graphical Method تبسيط الطريقة البيانية في تحل...
Slope Stability Analysis Using Graphical Method تبسيط الطريقة البيانية في تحل...Slope Stability Analysis Using Graphical Method تبسيط الطريقة البيانية في تحل...
Slope Stability Analysis Using Graphical Method تبسيط الطريقة البيانية في تحل...Ali A. Alzahrani
 
Shake table analysis and modelling introduction
Shake table analysis and modelling introduction Shake table analysis and modelling introduction
Shake table analysis and modelling introduction waiseee
 
MAT/RAFT foundation presentation- Details of Construction
MAT/RAFT foundation presentation- Details of Construction MAT/RAFT foundation presentation- Details of Construction
MAT/RAFT foundation presentation- Details of Construction Tahey Bin Mainur
 
Pull off test for concrete
Pull off test for concretePull off test for concrete
Pull off test for concreteAyaz khan
 
Piles in liquefiable soil
Piles in liquefiable soilPiles in liquefiable soil
Piles in liquefiable soilNabam Budh
 
Percussion drilling
Percussion drillingPercussion drilling
Percussion drillingshaxee ali
 
How to reduce Earthquake Effects on Buildings?
How to reduce Earthquake Effects on Buildings?How to reduce Earthquake Effects on Buildings?
How to reduce Earthquake Effects on Buildings?Abhinav Verma
 
Plaxis Presentation
Plaxis PresentationPlaxis Presentation
Plaxis Presentationselvem
 

What's hot (20)

Cpt by h.a.akbar
Cpt by h.a.akbarCpt by h.a.akbar
Cpt by h.a.akbar
 
Engineering properties of soil
Engineering properties of soilEngineering properties of soil
Engineering properties of soil
 
Standard Penetration Test
Standard Penetration TestStandard Penetration Test
Standard Penetration Test
 
Influence of geological condition on foundation and design of building
Influence of geological condition on  foundation and design of buildingInfluence of geological condition on  foundation and design of building
Influence of geological condition on foundation and design of building
 
Geology mcq
Geology mcqGeology mcq
Geology mcq
 
Slope Stability Analysis Using Graphical Method تبسيط الطريقة البيانية في تحل...
Slope Stability Analysis Using Graphical Method تبسيط الطريقة البيانية في تحل...Slope Stability Analysis Using Graphical Method تبسيط الطريقة البيانية في تحل...
Slope Stability Analysis Using Graphical Method تبسيط الطريقة البيانية في تحل...
 
Micropile
MicropileMicropile
Micropile
 
benkle(DS)...pptx
benkle(DS)...pptxbenkle(DS)...pptx
benkle(DS)...pptx
 
Pile Foundations
Pile FoundationsPile Foundations
Pile Foundations
 
Shake table analysis and modelling introduction
Shake table analysis and modelling introduction Shake table analysis and modelling introduction
Shake table analysis and modelling introduction
 
Caissons
Caissons Caissons
Caissons
 
Geology of Dams
Geology of DamsGeology of Dams
Geology of Dams
 
MAT/RAFT foundation presentation- Details of Construction
MAT/RAFT foundation presentation- Details of Construction MAT/RAFT foundation presentation- Details of Construction
MAT/RAFT foundation presentation- Details of Construction
 
Dampers
DampersDampers
Dampers
 
Pull off test for concrete
Pull off test for concretePull off test for concrete
Pull off test for concrete
 
Piles in liquefiable soil
Piles in liquefiable soilPiles in liquefiable soil
Piles in liquefiable soil
 
Percussion drilling
Percussion drillingPercussion drilling
Percussion drilling
 
M10l24
M10l24M10l24
M10l24
 
How to reduce Earthquake Effects on Buildings?
How to reduce Earthquake Effects on Buildings?How to reduce Earthquake Effects on Buildings?
How to reduce Earthquake Effects on Buildings?
 
Plaxis Presentation
Plaxis PresentationPlaxis Presentation
Plaxis Presentation
 

Similar to Allan block Installation guide

Allan block Commercial brochure
Allan block Commercial brochureAllan block Commercial brochure
Allan block Commercial brochurekristenjames
 
Easy steps to build a besser block wall
Easy steps to build a besser block wallEasy steps to build a besser block wall
Easy steps to build a besser block wallkristenjames
 
How to build a besser block wall - APC
How to build a besser block wall - APCHow to build a besser block wall - APC
How to build a besser block wall - APCkristenjames
 
How to build a besser block wall
How to build a besser block wallHow to build a besser block wall
How to build a besser block wallkristenjames
 
Bolderstone brochure
Bolderstone brochureBolderstone brochure
Bolderstone brochurekristenjames
 
Bolderstone brochure
Bolderstone brochureBolderstone brochure
Bolderstone brochurekristenjames
 
REINFORCED CONCRETE PRECAST TWIN WALLS
REINFORCED CONCRETE PRECAST TWIN WALLSREINFORCED CONCRETE PRECAST TWIN WALLS
REINFORCED CONCRETE PRECAST TWIN WALLSGuy Pomphrey
 
Repair,Retrofitting and Rehabilitation
Repair,Retrofitting and RehabilitationRepair,Retrofitting and Rehabilitation
Repair,Retrofitting and RehabilitationIshwar Chauhan
 
Construction Sequence.pptx
Construction Sequence.pptxConstruction Sequence.pptx
Construction Sequence.pptxssuser480182
 
Retaining wall/level backfill
Retaining wall/level backfillRetaining wall/level backfill
Retaining wall/level backfillTimóteo Rocha
 
Slope Stability Measure For Basement Excavation, A Case Study on Office Build...
Slope Stability Measure For Basement Excavation, A Case Study on Office Build...Slope Stability Measure For Basement Excavation, A Case Study on Office Build...
Slope Stability Measure For Basement Excavation, A Case Study on Office Build...Andy Sugianto
 
Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)AJAY SHAHU
 
EARTHQUAKE SAFE CONSTRUCTION OF MASONRY BUILDINGS
EARTHQUAKE SAFE CONSTRUCTION OF MASONRY BUILDINGSEARTHQUAKE SAFE CONSTRUCTION OF MASONRY BUILDINGS
EARTHQUAKE SAFE CONSTRUCTION OF MASONRY BUILDINGSMohd Danish
 
Retaing wall
Retaing wallRetaing wall
Retaing wallsaibabu48
 
Agilia horizontal datasheet_final_2012_lo_res
Agilia horizontal datasheet_final_2012_lo_resAgilia horizontal datasheet_final_2012_lo_res
Agilia horizontal datasheet_final_2012_lo_resgunalan7
 
Versaloc - very easy, very quick
Versaloc - very easy, very quickVersaloc - very easy, very quick
Versaloc - very easy, very quickkristenjames
 

Similar to Allan block Installation guide (20)

Allan block Commercial brochure
Allan block Commercial brochureAllan block Commercial brochure
Allan block Commercial brochure
 
Easy steps to build a besser block wall
Easy steps to build a besser block wallEasy steps to build a besser block wall
Easy steps to build a besser block wall
 
How to build a besser block wall - APC
How to build a besser block wall - APCHow to build a besser block wall - APC
How to build a besser block wall - APC
 
How to build a besser block wall
How to build a besser block wallHow to build a besser block wall
How to build a besser block wall
 
Bolderstone brochure
Bolderstone brochureBolderstone brochure
Bolderstone brochure
 
Bolderstone brochure
Bolderstone brochureBolderstone brochure
Bolderstone brochure
 
Work check list
Work check listWork check list
Work check list
 
REINFORCED CONCRETE PRECAST TWIN WALLS
REINFORCED CONCRETE PRECAST TWIN WALLSREINFORCED CONCRETE PRECAST TWIN WALLS
REINFORCED CONCRETE PRECAST TWIN WALLS
 
Repair,Retrofitting and Rehabilitation
Repair,Retrofitting and RehabilitationRepair,Retrofitting and Rehabilitation
Repair,Retrofitting and Rehabilitation
 
Construction Sequence.pptx
Construction Sequence.pptxConstruction Sequence.pptx
Construction Sequence.pptx
 
Retaining wall/level backfill
Retaining wall/level backfillRetaining wall/level backfill
Retaining wall/level backfill
 
Slope Stability Measure For Basement Excavation, A Case Study on Office Build...
Slope Stability Measure For Basement Excavation, A Case Study on Office Build...Slope Stability Measure For Basement Excavation, A Case Study on Office Build...
Slope Stability Measure For Basement Excavation, A Case Study on Office Build...
 
Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)
 
INSTRUCT_Print
INSTRUCT_PrintINSTRUCT_Print
INSTRUCT_Print
 
Top Down Construction Presentation.
Top Down Construction Presentation.Top Down Construction Presentation.
Top Down Construction Presentation.
 
EARTHQUAKE SAFE CONSTRUCTION OF MASONRY BUILDINGS
EARTHQUAKE SAFE CONSTRUCTION OF MASONRY BUILDINGSEARTHQUAKE SAFE CONSTRUCTION OF MASONRY BUILDINGS
EARTHQUAKE SAFE CONSTRUCTION OF MASONRY BUILDINGS
 
Retaing wall
Retaing wallRetaing wall
Retaing wall
 
Agilia horizontal datasheet_final_2012_lo_res
Agilia horizontal datasheet_final_2012_lo_resAgilia horizontal datasheet_final_2012_lo_res
Agilia horizontal datasheet_final_2012_lo_res
 
Versaloc - very easy, very quick
Versaloc - very easy, very quickVersaloc - very easy, very quick
Versaloc - very easy, very quick
 
Versaloc
VersalocVersaloc
Versaloc
 

More from kristenjames

Yin and sound Immersion
Yin and sound ImmersionYin and sound Immersion
Yin and sound Immersionkristenjames
 
Melbourne boat hire proposal cruises
Melbourne boat hire proposal cruisesMelbourne boat hire proposal cruises
Melbourne boat hire proposal cruiseskristenjames
 
Residential Energy Audits
Residential Energy AuditsResidential Energy Audits
Residential Energy Auditskristenjames
 
Melbourne boat hire birrarung
Melbourne boat hire birrarungMelbourne boat hire birrarung
Melbourne boat hire birrarungkristenjames
 
Melbourne boat-hire-brochure-august-2018 (1)
Melbourne boat-hire-brochure-august-2018 (1)Melbourne boat-hire-brochure-august-2018 (1)
Melbourne boat-hire-brochure-august-2018 (1)kristenjames
 
Melbourne boat hire photography cruise flyer
Melbourne boat hire photography cruise flyerMelbourne boat hire photography cruise flyer
Melbourne boat hire photography cruise flyerkristenjames
 
HOW TO SET VIDEO ALARMS ON THE CONNECT APP
HOW TO SET VIDEO ALARMS ON THE CONNECT APPHOW TO SET VIDEO ALARMS ON THE CONNECT APP
HOW TO SET VIDEO ALARMS ON THE CONNECT APPkristenjames
 
The Present - Yoga Teacher Training
The	Present - Yoga Teacher TrainingThe	Present - Yoga Teacher Training
The Present - Yoga Teacher Trainingkristenjames
 
Yarra River Skippered Cruises and Private Boat Charter
Yarra River Skippered Cruises and Private Boat CharterYarra River Skippered Cruises and Private Boat Charter
Yarra River Skippered Cruises and Private Boat Charterkristenjames
 
Sound immersion on 22nd-December 2019 at UpDog Yoga
Sound immersion on 22nd-December 2019 at UpDog YogaSound immersion on 22nd-December 2019 at UpDog Yoga
Sound immersion on 22nd-December 2019 at UpDog Yogakristenjames
 
Vinyasa unlocked - UpDog Yoga
Vinyasa unlocked - UpDog YogaVinyasa unlocked - UpDog Yoga
Vinyasa unlocked - UpDog Yogakristenjames
 
Movement as medicine - UpDog Yoga
Movement as medicine - UpDog YogaMovement as medicine - UpDog Yoga
Movement as medicine - UpDog Yogakristenjames
 
Yoga studios melbourne updog yoga
Yoga studios melbourne  updog yogaYoga studios melbourne  updog yoga
Yoga studios melbourne updog yogakristenjames
 
Melbourne boat-hire-photography-cruise-flyer
Melbourne boat-hire-photography-cruise-flyerMelbourne boat-hire-photography-cruise-flyer
Melbourne boat-hire-photography-cruise-flyerkristenjames
 
Erectarack long span shelving-3
Erectarack long span shelving-3Erectarack long span shelving-3
Erectarack long span shelving-3kristenjames
 
Erectarack Raised Storage Areas
Erectarack Raised Storage Areas Erectarack Raised Storage Areas
Erectarack Raised Storage Areas kristenjames
 
Erectarack mezzanine Floor
Erectarack mezzanine FloorErectarack mezzanine Floor
Erectarack mezzanine Floorkristenjames
 
Banker and Jeweller Safes - CMI Premier
Banker and Jeweller Safes - CMI PremierBanker and Jeweller Safes - CMI Premier
Banker and Jeweller Safes - CMI Premierkristenjames
 
Ironguard Domestic Security Safe
Ironguard Domestic Security Safe Ironguard Domestic Security Safe
Ironguard Domestic Security Safe kristenjames
 

More from kristenjames (20)

Yin and sound Immersion
Yin and sound ImmersionYin and sound Immersion
Yin and sound Immersion
 
Melbourne boat hire proposal cruises
Melbourne boat hire proposal cruisesMelbourne boat hire proposal cruises
Melbourne boat hire proposal cruises
 
Residential Energy Audits
Residential Energy AuditsResidential Energy Audits
Residential Energy Audits
 
Melbourne boat hire birrarung
Melbourne boat hire birrarungMelbourne boat hire birrarung
Melbourne boat hire birrarung
 
Melbourne boat-hire-brochure-august-2018 (1)
Melbourne boat-hire-brochure-august-2018 (1)Melbourne boat-hire-brochure-august-2018 (1)
Melbourne boat-hire-brochure-august-2018 (1)
 
Melbourne boat hire photography cruise flyer
Melbourne boat hire photography cruise flyerMelbourne boat hire photography cruise flyer
Melbourne boat hire photography cruise flyer
 
HOW TO SET VIDEO ALARMS ON THE CONNECT APP
HOW TO SET VIDEO ALARMS ON THE CONNECT APPHOW TO SET VIDEO ALARMS ON THE CONNECT APP
HOW TO SET VIDEO ALARMS ON THE CONNECT APP
 
The Present - Yoga Teacher Training
The	Present - Yoga Teacher TrainingThe	Present - Yoga Teacher Training
The Present - Yoga Teacher Training
 
Yarra River Skippered Cruises and Private Boat Charter
Yarra River Skippered Cruises and Private Boat CharterYarra River Skippered Cruises and Private Boat Charter
Yarra River Skippered Cruises and Private Boat Charter
 
Sound immersion on 22nd-December 2019 at UpDog Yoga
Sound immersion on 22nd-December 2019 at UpDog YogaSound immersion on 22nd-December 2019 at UpDog Yoga
Sound immersion on 22nd-December 2019 at UpDog Yoga
 
Sound immersion
Sound immersionSound immersion
Sound immersion
 
Vinyasa unlocked - UpDog Yoga
Vinyasa unlocked - UpDog YogaVinyasa unlocked - UpDog Yoga
Vinyasa unlocked - UpDog Yoga
 
Movement as medicine - UpDog Yoga
Movement as medicine - UpDog YogaMovement as medicine - UpDog Yoga
Movement as medicine - UpDog Yoga
 
Yoga studios melbourne updog yoga
Yoga studios melbourne  updog yogaYoga studios melbourne  updog yoga
Yoga studios melbourne updog yoga
 
Melbourne boat-hire-photography-cruise-flyer
Melbourne boat-hire-photography-cruise-flyerMelbourne boat-hire-photography-cruise-flyer
Melbourne boat-hire-photography-cruise-flyer
 
Erectarack long span shelving-3
Erectarack long span shelving-3Erectarack long span shelving-3
Erectarack long span shelving-3
 
Erectarack Raised Storage Areas
Erectarack Raised Storage Areas Erectarack Raised Storage Areas
Erectarack Raised Storage Areas
 
Erectarack mezzanine Floor
Erectarack mezzanine FloorErectarack mezzanine Floor
Erectarack mezzanine Floor
 
Banker and Jeweller Safes - CMI Premier
Banker and Jeweller Safes - CMI PremierBanker and Jeweller Safes - CMI Premier
Banker and Jeweller Safes - CMI Premier
 
Ironguard Domestic Security Safe
Ironguard Domestic Security Safe Ironguard Domestic Security Safe
Ironguard Domestic Security Safe
 

Recently uploaded

Case study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailCase study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailAriel592675
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst SummitHolger Mueller
 
(8264348440) 🔝 Call Girls In Hauz Khas 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Hauz Khas 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Hauz Khas 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Hauz Khas 🔝 Delhi NCRsoniya singh
 
Islamabad Escorts | Call 03274100048 | Escort Service in Islamabad
Islamabad Escorts | Call 03274100048 | Escort Service in IslamabadIslamabad Escorts | Call 03274100048 | Escort Service in Islamabad
Islamabad Escorts | Call 03274100048 | Escort Service in IslamabadAyesha Khan
 
The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024christinemoorman
 
RE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechRE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechNewman George Leech
 
Lean: From Theory to Practice — One City’s (and Library’s) Lean Story… Abridged
Lean: From Theory to Practice — One City’s (and Library’s) Lean Story… AbridgedLean: From Theory to Practice — One City’s (and Library’s) Lean Story… Abridged
Lean: From Theory to Practice — One City’s (and Library’s) Lean Story… AbridgedKaiNexus
 
Call Girls In Kishangarh Delhi ❤️8860477959 Good Looking Escorts In 24/7 Delh...
Call Girls In Kishangarh Delhi ❤️8860477959 Good Looking Escorts In 24/7 Delh...Call Girls In Kishangarh Delhi ❤️8860477959 Good Looking Escorts In 24/7 Delh...
Call Girls In Kishangarh Delhi ❤️8860477959 Good Looking Escorts In 24/7 Delh...lizamodels9
 
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth MarketingShawn Pang
 
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts ServiceVip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Serviceankitnayak356677
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation SlidesKeppelCorporation
 
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / NcrCall Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncrdollysharma2066
 
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessSales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessAggregage
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.Aaiza Hassan
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfpollardmorgan
 
CATALOG cáp điện Goldcup (bảng giá) 1.4.2024.PDF
CATALOG cáp điện Goldcup (bảng giá) 1.4.2024.PDFCATALOG cáp điện Goldcup (bảng giá) 1.4.2024.PDF
CATALOG cáp điện Goldcup (bảng giá) 1.4.2024.PDFOrient Homes
 
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...lizamodels9
 
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service DewasVip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewasmakika9823
 

Recently uploaded (20)

Case study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailCase study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detail
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst Summit
 
(8264348440) 🔝 Call Girls In Hauz Khas 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Hauz Khas 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Hauz Khas 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Hauz Khas 🔝 Delhi NCR
 
Islamabad Escorts | Call 03274100048 | Escort Service in Islamabad
Islamabad Escorts | Call 03274100048 | Escort Service in IslamabadIslamabad Escorts | Call 03274100048 | Escort Service in Islamabad
Islamabad Escorts | Call 03274100048 | Escort Service in Islamabad
 
The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024
 
RE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechRE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman Leech
 
Lean: From Theory to Practice — One City’s (and Library’s) Lean Story… Abridged
Lean: From Theory to Practice — One City’s (and Library’s) Lean Story… AbridgedLean: From Theory to Practice — One City’s (and Library’s) Lean Story… Abridged
Lean: From Theory to Practice — One City’s (and Library’s) Lean Story… Abridged
 
KestrelPro Flyer Japan IT Week 2024 (English)
KestrelPro Flyer Japan IT Week 2024 (English)KestrelPro Flyer Japan IT Week 2024 (English)
KestrelPro Flyer Japan IT Week 2024 (English)
 
Call Girls In Kishangarh Delhi ❤️8860477959 Good Looking Escorts In 24/7 Delh...
Call Girls In Kishangarh Delhi ❤️8860477959 Good Looking Escorts In 24/7 Delh...Call Girls In Kishangarh Delhi ❤️8860477959 Good Looking Escorts In 24/7 Delh...
Call Girls In Kishangarh Delhi ❤️8860477959 Good Looking Escorts In 24/7 Delh...
 
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
 
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCREnjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
 
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts ServiceVip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Service
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
 
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / NcrCall Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
 
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessSales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for Success
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
 
CATALOG cáp điện Goldcup (bảng giá) 1.4.2024.PDF
CATALOG cáp điện Goldcup (bảng giá) 1.4.2024.PDFCATALOG cáp điện Goldcup (bảng giá) 1.4.2024.PDF
CATALOG cáp điện Goldcup (bảng giá) 1.4.2024.PDF
 
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
 
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service DewasVip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
 

Allan block Installation guide

  • 1. ALLAN BLOCK INSTALLATION GUIDE ALLAN BLOCK InstallationGuide This installation guide outlines how to construct AB retaining wall systems. It should be noted that these are only guidelines. Ensure that all local building codes are complied with. 01: Getting Started Determine if your Wall Requires Reinforcement For wall heights less than or equal to those listed in Table 1, a non reinforced gravity retaining wall may be built. For walls that exceed the maximum values listed in Table 1, or where loads exist, the wall will need reinforcement. Refer to the C&M Allan Block brochure (ref. CM.AB0505) or a C&M representative for guidelines to designing for geogrid reinforced retaining walls. 02: Order Materials Blocks A) Length of Wall x Total Height of Wall = Wall Area. B) Total Height of Wall. C) Wall Area x Number of Blocks /m2 = Blocks Required. Convert all dimensions to metres before calculating. To calculate total wall height: add buried block + above ground wall height. For walls under 1m, 100mm of block must be buried. For walls 1-3m, one block must be buried. Leveling Pad & Drainage Zone Use a well graded aggregate, 12mm to 20mm free draining material for the drainage zone within the block cores. Check your local aggregate sources for availability. Drainage Zone The drainage material includes the material in the block cores plus a 300mm layer behind the blocks. A simple way to calculate this material in cubic metres is: Wall Height x Wall Length x 0.5 (block + 300mm) = Cubic Metres of drainage material. Note: C&M takes no responsibility for quantity of material ordered. Base The typical base for an AB retaining wall is 600mm wide x 150mm deep. Geogrid If geogrid is required, contact C&M or your AB distributor for specifications and assistance. The wall must first have been designed by a suitably qualified engineer. For walls that exceed the heights shown in the following table (table 1), please refer to the Commercial Installation section. Figure 1: Calculated Materials Wall Height Wall Length Drain Field Geogrid Zone Base
  • 2. Figure 2: Start Wall at Lowest Elevation Stepped BaseSloping Grade Start Here Figure 3: Excavate the Base Trench Width = 600mm Depth = 150mm for base plus embedment required as per step 2. 03: Excavate Base Trench and Geogrid Zone Excavate base trench at the wall location. Make sure the trench is level and to the proper depth (Figure 3). Walls built on a sloping grade will require a stepped base (Figure 2). Begin excavation at the lowest point and dig a level trench into the slope until it is deep enough to accommodate the 150mm Base Material and the recommended depth of block embedment. Step up the height of one block and repeat. For geogrid walls, excavate behind the wall far enough to fit the geogrid length, and a safe buffer beyond this zone. 04: Install Base Material Place 150mm base material in the base trench and rake smooth. Compact with a mechanical plate compacter (Figure 4). Check the entire length for level and adjust as needed. 05: Install Base Course Begin at the lowest wall elevation (Figure 2). Place the first row of AB blocks on the Base Material with the raised front lip facing up and forward to the front of the wall. Check and adjust the level and alignment of all blocks. Check levels frequently, side-to-side and front-to-back. Verify the proper position of all blocks by examining a straight line across the back of the blocks or the back of the lips (Figure 5). Make minor adjustments by tapping the block with a rubber mallet or by placing small amounts of coarse sand underneath. Irregularities in the base course become larger as the wall stacks up. Careful attention to a straight and level base course will ensure a quality finished wall. 1 4 5 kPa Poor Soils (25˚) Including sands, gravelly clays, sandy clays & silt clays Average Soils (30˚) Including well graded sands & gravelly sands Good Soils (35˚) Including gravels, sandy gravels & crushed sandstone Poor Soils (25˚) Including sands, gravelly clays, sandy clays & silt clays Average Soils (30˚) Including well graded sands & gravelly sands Good Soils (35˚) Including gravels, sandy gravels & crushed sandstone Poor Soils (25˚) Including sands, gravelly clays, sandy clays & silt clays Average Soils (30˚) Including well graded sands & gravelly sands Good Soils (35˚) Including gravels, sandy gravels & crushed sandstone Backfill Friction Angle, φ 600 600 800 800 1000 AB Junior AB Aussie AB Vertical AB Classic AB Stones 800 800 800 1000 1400* 800 800 1000 1200 1500* 400 400 400 400 400 600 600 600 600 800 600 600 800 800 800 400 400 400 400 600 400 400 600 600 800 800 800 800 800 1000 Job Site Level Above Wall Surcharge of 5 kPa (Driveway) Slope Above Wall in Excess of 1 in 4 & Surcharge of 1.5 kPa Slope Above Wall *Wall Heights achieved by replacing granular fill (in drainage zone) with ‘No Fines’ concrete Table 1: Maximum Heights(mm) for Allan Block - without grid Allan Block Gravity Walls only up to 1.5m maximum height in accordance with AS4678-2002 Figure 4: Compact Base Material Compact Base Material Level
  • 3. 06: Install Drainage Material Place an agricultural pipe at the bottom rear of the drainage field with appropriate fall to designated drainage point. Fill the AB hollow cores and the 300mm drain field behind the wall with drainage material. Proper placement of drainage material serves three important purposes. First, the material creates a positive interlock between the blocks. Second, it increases structural stability. Finally, it permits the release of water pressure from behind the wall. 07: Backfill and Compact Compaction of the material behind the wall is critical for a quality wall installation. Use select backfill behind the drain field. Heavy clays and organic materials are not recommended due to their water holding properties. Use a plate compacter to consolidate the aggregate in the block cores and lock the base course in place. The first pass of the plate compacter should be directly over the top of the block cores (Figure 7). After running the plate compacter on top of the base course and drain field, compact the backfill material immediately behind the wall. Compact in a path parallel to the wall, working from the front of the wall to the back of the backfill material (Figure 7). Compact in 200mm lifts. Use only light weight equipment within 1.2m of the wall face. Check the base course for level and adjust as necessary. 08: Install Second & Subsequent Courses Remove all excess drainage material and stone from the top surface of the blocks. This prepares a smooth surface for placement of the next course of AB. Stack the next row of block with the vertical joints offset from the block below. Sight down the wall line to check for a straight wall. Block may be adjusted to form straight lines and smooth curves. Check for level before installing drainage and backfill materials. Adjust as necessary. Repeat steps 6 to 8, installing drainage and backfill material and compacting parallel to the wall face from front to back. For non reinforced gravity walls, repeat steps 6 to 8 to the top of the wall then proceed to step 12. For walls needing reinforcement, follow the steps below. 09: Install First Layer of Geogrid Cut sections of geogrid to specified length. The wall must first have been designed by a suitably qualified engineer. Check manufacturer’s grid specifications for strength or machine direction of the geogrid. Place geogrid behind the block lip with the machine direction extending back into the slope (Figure 8). Place next course of blocks on top of the geogrid. Pull on the back of the grid to remove any slack. Stake in place before installing drainage and backfill material (Figure 9). Figure 8: Determining Geogrid Direction Figure 5: Install Base Course String line Adjust with a rubber mallet Level Figure 6: Install Drainage Material & Backfill Soils Drainage Material Figure 7: Compact Drainage Material & Backfill Soils Infill soils Fill void in front of block Compact parallel to wall Machine Direction
  • 4. Figure 12: Ending & Topping Walls CapMulch Lawn Filter Fabric Filter Fabric Filter Fabric 10: Backfill & Compact Place drainage material in blocks and 300mm behind the blocks. Place a 200mm layer of backfill soil on top of the geogrid. All drainage material in the drain field and infill soils within 1m of the wall must be properly compacted using a walk behind plate compacter. Compact in maximum 200mm lifts, starting on the wall and working in a path that runs parallel to the wall towards the back of the reinforced zone (Figure 10). Never operate compacting equipment directly on geogrid. All heavy equipment must be kept at least 1.2m from the wall face (figure 11). 11: Install Additional Courses Repeat steps 7 through 10. Each lift of drainage and backfill material should be installed in the same manner. Compact in lifts of 200mm, the height of one AB unit (Figure 10). Check block for level after compacting each lift, and adjust as needed. 12: Ending and Topping Walls AB's patented raised front lip provides a built-in edging for landscape rock, mulch, grass, soil or AB Cappers (Figure 12). Place filter fabric between the drainage zone and landscaped zone. Walls with step down can be easily finished by turning the ends back into the hillside (Figure 13), or using a cornerstone with a split end as the last unit before step down. 13: Grading and Water Management Grade backfill to ensure that water drainage from the entire site flows away from the wall. A drainage swale can also be incorporated above the wall to divert water away from the top of the wall. Erosion at the end of the wall can be prevented by rolling the end of the wall into the bank (Figure 13). As a general rule bury 500mm of block into the hillside to prevent potential problems. For projects where excessive water run off above the wall is a factor (parking lots, roof drains, etc.) the top of the wall must be finished off to prevent the penetration of water. To ensure that water run off from above the retaining wall does not saturate the soil behind it, a 150mm (min.) layer of impermeable fill should be placed on top of the entire run off area. Install an agricultural drain pipe at the bottom of the drainage field and vent away from wall to remove excess water. Figure 9: Install First Layer of Geogrid Figure 10: Compact in 200mm Lifts Figure 11: Keep Heavy Equipment 1.2m from the wall face Figure 13: Final Grading & Topping Off the Wall Options Set second course on top of Geogrid Keep heavy equipment 1.2m from the wall face Compact in 200mm lifts Pull back Geogrid and stake in place Place cut edge of grid flight against lip Flowing turn-in of wall For a step-down that doubles as a planter, turn the wall in 2 or 3 blocks after the AB Cornerstone. For a natural flow into the landscape, curve the wall back into the hillside.
  • 5. 14: Curves Curves and serpentine walls are easy to build. Walls designed with curves complement natural landscape forms and are easy to build. To create outside curves, simply remove the 'wings' from the back of the Allan Block units and tighten the radius of the curve. For setback walls a slight coning will occur on curved walls. Design curved walls so the radius at the top of the wall is at least 1.2m. Refer to the table below to find the minimum recommended radius at the wall base while maintaining a 1.2m radius at the top of the wall. 15: Terraces In some cases it is preferable to terrace a site rather than construct a single wall as this allows for garden beds and stairs between levels to be incorporated into the landscape design. Although terracing improves the look of the landscape, it is important to consider the pressure of the upper wall on the lower wall. The distance between the walls must be greater than 1.5 times the height of the lower wall to ensure the top terrace does not apply loads to the lower wall. This does not take into account global stability issues which need to be considered. Terraced hillsides may require engineering assistance. Contact C&M or your local distributor for more information. Wall Height 1.43m 1.52m 1.6m 1.7m 1.2m 1.8m 2.4m 3.0m 1.55m 1.66m 1.8m 1.9m 1.67m 1.8m 2.0m 2.1m Figure 14: Remove wings for outside curves H2 D H1 Figure 15: Terraced Walls - No Reinforcement Required (if walls are below heights shown in Table 1). Keep the front of the blocks tight together Inside Curve Outide Curve Consistent spacing Setback 3˚ 6˚ 12˚ Use this chart to find the minimum recommended radius at base of wall. Table 2: AB Radius Chart
  • 6. Figure 16: Outside Corners Figure 17: Outside Corners 16: Corners When building corners, start from the corners and build away. Soft corners are easier to build than angles. Always avoid small block cuts at the corners. Outside Corners Outside corners are formed by reversing the directions for each course of cornerstone. They must be ordered as right hand or left hand units. Inside Corners Inside corners are easily constructed by modifying Allan Block units (figure 17). Remove half of the raised front lip. They can be chiselled off, but a masonry saw works best. Lay the modified block perpendicular to another Allan Block unit with the lips lined up. Remove the opposite half of the lip of another AB unit and position it over the right angle corner. On each successive row, simply reverse the position of the modified block to obtain an interlocked corner. Step 1 Step 1 Step 1 Ensure base is level going both directions Remove notch to form corner Area of front lip removed Blocks with part of lip removed Step 1 Step 2 Remove part of front lip so next course will seat properly
  • 7. Figure 23: Step Tread Options 17: Steps Always check local code requirements before building an type of step application. The steps (figures 18 - 22, left) are general guidelines for building steps. By understanding the basic installation elements, steps can be easily incorporated into the wall installation. Before excavation can begin, the rise and run of the step treads must be determined and code requirements must be met. With that information, the entire base trench can then be excavated. Some examples of different step tread options are illustrated below (figure 23). Our example (figures 18 - 22, left) uses a base trench of 150mm and a step tread of AB cappers and pavers. Excavate to the necessary depth and width for each step riser (figure 18) and thoroughly compact the entire area with a mechanical plate compactor. Check for level. Starting at the first step, fill the base trench with 150mm of drainage material. Rake smooth. Compact and check for level. Steps need extra compaction to avoid any settling later. Better compaction is achieved by backfilling and compacting in 100mm lifts or less when able. Install blocks on the base material. Allow for a space of at least 150mm behind the blocks for drainage material (figure 19). Adjust for level and alignment of each block as it’s installed. Install drainage material in the block cores, fill any space in front of and behind the block. When backfilling behind the blocks, fill the entire area that was earlier excavated to create the base for the next step riser. This should produce a level base for the next set of risers. We recommend backfilling and compacting behind the block in 100mm lifts to achieve better compaction when able. Rake drainage material smooth and compact with the first pass of the compactor directly on the tops of the block and then working in a path that runs parallel to the block (figure 20). Repeat this process for each additional course of steps needed (figures 21 & 22). AB Cappers AB Cappers & Pavers Pavers Concrete Figure 18: Step 1 Figure 19: Step 2 Figure 20: Step 3 Figure 21: Step 4 Figure 22: Step 5 Rise Base Trench Run 150mm Excavate for steps and compact Install and level blocks on base material Backfill block cores and behind block with drainage material & compact Install next step course 150mm Step tread depth Continue for each new step 150mm Step tread depth Next step Install cappers and paver treads. Use sand under the pavers to level with AB Cappers
  • 8. ALLAN BLOCK Installation Guide - Ref: CM.ABIN0905 Important: Please consult with the appropriate council for local design and construction of a retaining wall. Councils in general require that retaining walls be designed and certified by a suitably qualified engineer where the wall is over 500mm in height and/or where there is a load such as a road, driveway, house, building or hydrostatic pressure. Patents: Allan Block Retaining Wall Systems are protected by the Australian patent numbers 682394 and 133306 CM0504_K4027 Melbourne - Essendon (Head Office) 264 Keilor Road North Essendon, VIC 3041 phone: 03) 9375 8500 I fax: 03) 9374 4736 C&M Brick Pty Ltd ABN: 14 055 701 034 www.cmbrick.com.au Bendigo 69 Collins Street Kangaroo Flat, VIC 3555 phone: 03) 5447 8866 I fax: 03) 5447 0399 Canberra 6 Tennant Street Fyshwick, ACT 2609 phone: 02) 6239 1255 I fax: 02) 6280 7284 Melbourne - Campbellfield 194 Northbourne Road Campbellfield, VIC 3061 phone: 03) 9305 0900 I fax: 03) 9303 9035 Newcastle Old Maitland Road Sandgate, NSW 2304 phone: 02) 4967 3611 I fax: 02) 4960 1187 Nowra 270-274 Princes Hwy South Nowra, NSW 2541 phone: 02) 4421 3500 I fax: 02) 4421 3082 Queensland 5 Demand Avenue Arundel, QLD 4211 phone: 07) 5571 6644 I fax: 07) 5571 6644 South Australia Cnr Grand Junction & Blakeney Rds Ottoway, SA 5013 phone: 08) 8304 2323 I fax: 08) 8341 1101 Sydney - Moorebank 20 Kelso Crescent Moorebank, NSW 2170 phone: 02) 9822 6822 I fax: 02) 9601 7446