The Door Testing and Certification Guide
Project Planning to Labeling in 10 Simple Steps




                  www.intertek-etlsemko.com
Door Testing and Certification:
Project Planning to Labeling in 10 Simple Steps

From project planning and test assembly preparation to certification planning and factory
audit preparation you’ll learn the simple steps you can take to speed the testing and
certification process. Our whitepaper details the door testing and certification process
including technical and regulatory requirements, project timelines, and test setup
procedures for Fire Testing, Windstorm Resistance, and Tornado Resistance projects.


What are the 10 steps of door testing and certification?

•   Step 1: Project Planning
•   Step 2: Project Proposal
•   Step 3: Initial Product Review
•   Step 4: Pre-Test Inspection (For Certification Test Only)
•   Step 5: Test Assembly Preparation
•   Step 6: Testing (Fire, Windstorm / Tornado Resistance)
•   Step 7: Reporting
•   Step 8: Certification Planning
•   Step 9: Initial Factory Audit
•   Step 10: Labeling

Step 1: Project Planning

•   Client identifies product(s) for qualification
•   Client supplies product information – construction and application drawings
•   Client identifies target markets for sale or distribution
•   Client identifies which ratings or standards will need to be met

•   Timeline: Dependent on client delivery of project information

Step 2: Project Proposal

•   Client supplies information collected in Step 1 as noted above
•   Intertek prepares and delivers project proposal – often attached are credit
    applications and client information forms for expediency.
•   Client completes and returns the proposal or suggests revisions as necessary. A
    deposit for the subtotal amount may be required at this stage.
•   A copy of the signed proposal is forwarded to Intertek’s certification department

•   Timeline: Intertek’s proposal is delivered within 48 hours




                             www.intertek-etlsemko.com
Step 3: Initial Product Review

•   Intertek evaluates product information, drawings, etc. and advises on any areas of
    concern.
            o At this point the client may need to address concerns before making test
               samples.

•   Timeline: Projects are opened within 2-4 days of receipt of signed paperwork. The
    review begins within 3-4 days after the project has been opened. The review time
    may vary depending on curing time and product.

Step 4: Pre-Test Inspection (For Certification Test Only)

•   An Intertek representative will:
            o Witness and document construction of test sample
            o Review component and assembly drawings, material type, size and
               dimension
            o Prepare a “Pre-Test Inspection Report” and send to Intertek lab
            o Sign the test sample/package to be opened only at the test lab
•   The client will:
            o Seal and package the test sample
            o If the sample requires custom clearance, it is advised to mark “Test
               Samples for Destructive Testing, Commercial Value is Zero” on the
               package and send to the Intertek lab designated in proposal

•   Timeline:
           o Domestic: Pretest sampling - up to 2 weeks. Doors are usually allowed
              up to 28 days for adhesive conditioning then trimmed to test frame size.
              Delivery to the lab is usually 1 week thereafter.
           o International: Pretest sampling - up to 3 weeks. Delivery of the prepared
              samples to the test lab may take 4-6 weeks depending on client’s
              selected shipping method.

Step 5: Test Assembly Preparation

•   Option 1 – Client prehangs the doors for test and ships to Intertek to be installed in
    test setup.
•   Option 2 – Client sends the doors to Intertek for machining and installation in test
    setup.
•   Upon receipt, technicians will inspect the samples. If all match the Pre-Test
    Inspection Report, construction of the test assemblies will begin.
•   Test assemblies are built in accordance with the test plan including all assembly
    components.

•   Timeline: Test plans are based on client preference and availability. Test assemblies
    can be prepared in as few as 2 days if all materials have been supplied. Where
    cementitious materials are used a cure time of 7 days is normally required.

                              www.intertek-etlsemko.com
Step 6a: Fire Testing

•   Conducted under positive or neutral pressure following standard time vs.
    temperature curves.
•   Doors must meet temperature rise criteria (when applicable), resist the passage of
    fire, and stay securely in the opening through the test period.
•   Test methods include but are not limited to:
            o US & Canada: NFPA 252, UL 10 (B/C), UBC 7-2 (1994/1997), CAN4
                S104
            o International: BS 476, parts 21 & 22 and ISO 3008.

•   Timeline: Ranges from 20 minutes to 3 hours depending on product construction and
    requirements of standard

Step 6a: Fire Testing Test Setup

•   Research Scale or Pilot Scale: Provides data prior to larger scale tests. Used to
    qualify a variable in the assembly and components (Example: Adhesives).
•   Mid-Scale: Used when single swing doors are required.
•   Full-Scale: Used for multiple doors or a pair in a test wall.

Step 6b: Windstorm Resistance Testing

•   Testing of hurricane-resistant products
           o Required for State of Florida, and may be required in IRC and IBC from
               the Gulf coast up the Eastern seaboard.
•   Test standards include:
           o Door assemblies: ASTM E330, ASTM E1886, ASTM E1996
           o Door assemblies: TAS 201, TAS 202, TAS 203 for Miami Dade County
           o Individual components: ANSI A250.13

•   Timeline: Tests typically range from 3 to 7 days depending on size and/or
    configuration, and number of rating options needed.

Step 6b: Windstorm Resistance Test Setup

•   Several approaches
            o Assembly tests to High Velocity Hurricane Zone requirements for South
               Florida (Miami Dade) approval (TAS 201,202, 203); also requires
               notification of upcoming test via Miami Dade submittal
            o Component testing per ANSI A250.13
            o Assembly tests per ASTM E1886/E1996
            o Combination component and assembly testing to Miami Dade
               requirements, ANSI A250.13 and ASTM E1886/E1996
•   Product design must be documented and verified by a pre-test inspection, or post-
    test examination of cut sections.


                             www.intertek-etlsemko.com
•   Client must specify target design load (DL)…….enhanced protection, etc). If client is
    unsure of what his product's DL may be, an R & D test project will be conducted to
    establish the appropriate DL.)
•   Structural performance testing is conducted first at 1.5 times the DL. If Miami-Dade
    requirements are also required, the water penetration, air infiltration and forced entry
    tests will be conducted within this first series of tests.
•   Impact testing is then conducted, with the cyclic load tests conducted following.
    Doors must remain closed, and prevent penetration of the missile(s).
•   Variations in the assembly (i.e., anchorage, hardware options, etc) will be considered,
    and may be included in the 3 assemblies required for the impact and cyclic load tests.
    These variations should be discussed with your project manager prior to the start of
    testing.
•   Glazed doors and/or frames with sidelights and/or transoms require separate tests.
•   Tests are conducted on the largest size to be certified.

Step 6c: Tornado Resistance Testing

•   Testing of tornado-resistant products including static load and impact
•   Test methods include:
           o FEMA 320 - Taking Shelter from the Storm – Building a Safe Room in
                Your House
           o FEMA 361 - Design and Construction Guidance for Community Shelter
           o National Storm Shelter Association requirements

•   Note: Work is currently being done to develop a formal ANSI test method.

•   Timeline: Tornado resistance testing can be completed in 1 day.

Step 6c: Tornado Resistance Test Setup

•   Testing is assembly based
•   Installed in simulated wall – typically wood framing, concrete or CMU with specified
    anchorage
•   Impact test with 15 pound 2x4 at 100 miles per hour (5,014 foot-pounds)
•   Impact at multiple locations including near latch and hinge points
•   Static load tests (positive and negative) at 250 PSF on separate (unimpacted)
    assembly
•   Assemblies must prevent missile penetration, remain closed and limit dynamic
    deflection to 3” or less

Step 7: Reporting

•   Upon successful test results Intertek will issue:
          o Test Report or Engineering Evaluation Report (Listing Report for
             Certification) to the client and Intertek Certification department
          o Draft Listing and Authorization to Mark (ATM) to the Intertek Certification
             department.

                             www.intertek-etlsemko.com
Step 8: Certification Planning

•   Intertek sends the client a “Certification & Listing Agreement”.
            o The client signs and returns the document along with a deposit (if
               applicable) to Intertek.
            o The client receives a signed copy for records.

•   Note: Not all products require a physical label as some only need to be “Listed”. For
    those products that do require a label, presence of an authorized label, such as
    Intertek’s WH Mark, is the only legal proof that a third party has certified the product.

•   Timeline: Once the listing report has been accepted a certification agreement is
    prepared.

Step 9: Initial Factory Audit (IFA)

•   An Intertek inspector will visit your factory:
           o Review flow chart of production process and in-house quality control
               during production
           o Review training records of critical personnel
           o Conduct raw material inspection & QC done by factory
           o Witness a representative layup
           o Complete final inspection after production is completed (prior to shipping)
           o Secure arrangements and certification label controller
           o If the IFA is successful, the inspector will provide the Authorization to
               Mark (ATM).

•   Timeline: Domestic – 10 days, International – 14 days

Step 10: Labeling

•   The client may apply certification labels to the product, packaging, or both
    (recommended).
•   An Intertek inspector will conduct unannounced, quarterly inspections to verify all
    processes identified during the IFA are being followed.
•   Non-conformances are immediately reported to the client and Intertek.
            o The client is required to resolve immediately and communicate evidence
               of resolution to Intertek.
            o Delay / failure to resolve can result in suspension or termination of
               certification.




                              www.intertek-etlsemko.com
Additional Resources

How can I further accelerate the process?

•   Using our proprietary web-based tool you can:
           o Initiate projects online and track project status
           o Access listings and specs via a secure site - 24/7/365
           o Distribute notifications of product updates, listings to customers
           o Replace paper delivery and 3-ring binder system
           o Educate customers by mapping marketing literature, installation
               instructions, etc. to a product listing
           o Print your own labels

… Get the product information you need sooner so you can manufacture and market
your products faster.

Are their any quick hints to be aware of?

•   Once the Listing Report has been accepted a Certification Agreement is prepared…
    sign and return agreement on that day and it can be finalized by Intertek within 1-2
    days.

•   The Certification Agreement can be issued when the signed proposal is returned.
    Once Intertek has a signed agreement and an accepted Listing Report, only the
    Factory Audit is remaining.

•   Subscribe to SpecDirect and speed the entire process. The SpecDirect contract can
    be offered along with the testing program proposal.




                             www.intertek-etlsemko.com
About Intertek

Intertek is recognized by all major code bodies throughout the world. We are a Nationally
Recognized Testing Laboratory (NRTL) by OSHA; recognized by Standards Council of
Canada (SCC); and A2LA, APLAC, and ILAC accredited for Asia and other parts of the
world. In North America we are recognized by the International Codes Council Evaluation
Service (ICC-ES) and serve as an administrator for multiple Builders Hardware
Manufacturers Association (BHMA) certification programs.

What testing, certification, and evaluation services does Intertek offer?

•   WH Mark for North America
•   Performance evaluations; durability and product comparison
•   Environmental testing
•   Flammability, flame spread, and fire resistance testing
•   Structural, physical and mechanical evaluations

What specific accreditations does Intertek hold?

•   ICC-International Accreditation Services (IAS) for testing and certification of building
    materials
•   American Association of Laboratory Accreditation (A2LA)
•   American National Standards Institute (ANSI)
•   Department of Housing and Urban Development (HUD)
•   Recognized by the Occupational Safety and Health Administration (OSHA) as a
    Nationally Recognized Testing Laboratory (NRTL)
•   Standards Council of Canada (SCC)
•   Testing Laboratory accredited to ISO/IEC 17025
•   Inspection Agency accredited to ISO/IEC 17020
•   Certification Organization accredited to ISO Guide 65




For more information on Intertek’s door testing and certification capabilities or to
                start a project right away, call 1-800-967-5352,
       email icenter@intertek.com, or visit www.intertek-etlsemko.com.




                              www.intertek-etlsemko.com

More Related Content

What's hot

Quality Control & Quality Assurance of MS pipeline
Quality Control & Quality Assurance of MS pipelineQuality Control & Quality Assurance of MS pipeline
Quality Control & Quality Assurance of MS pipeline
IEI GSC
 
MD.NAFISUL HAQUE_original
MD.NAFISUL HAQUE_originalMD.NAFISUL HAQUE_original
MD.NAFISUL HAQUE_originalM.Nafis Haque
 
Qc
QcQc
MADHAN RESUME - UPDATED
MADHAN RESUME - UPDATEDMADHAN RESUME - UPDATED
MADHAN RESUME - UPDATEDMadan Kumar
 
Rajasekaran CV-updated
Rajasekaran CV-updatedRajasekaran CV-updated
Rajasekaran CV-updatedRaja Sekhar
 
Rajesh kannan -BGAS level 2 CV
Rajesh kannan -BGAS level 2 CVRajesh kannan -BGAS level 2 CV
Rajesh kannan -BGAS level 2 CVRajesh kannan
 
Quality assurance-for-ms-pipe itp-------------------------
Quality assurance-for-ms-pipe itp-------------------------Quality assurance-for-ms-pipe itp-------------------------
Quality assurance-for-ms-pipe itp-------------------------
Pratap Biswas
 
senthilkumar CV
senthilkumar CVsenthilkumar CV
senthilkumar CV
senthil kumar
 
10 steps blast_certification
10 steps blast_certification10 steps blast_certification
10 steps blast_certificationIntertek CE
 
Complete March 2015 CV-2
Complete March 2015 CV-2Complete March 2015 CV-2
Complete March 2015 CV-2Tim Jones
 
Quality
QualityQuality
Multidispline Inspector - DEEPAK RAI
Multidispline Inspector - DEEPAK RAIMultidispline Inspector - DEEPAK RAI
Multidispline Inspector - DEEPAK RAIDeepak Rai
 
Muhammad Imran QAQC (Welding Inspector)CSWIP
Muhammad Imran QAQC (Welding Inspector)CSWIPMuhammad Imran QAQC (Welding Inspector)CSWIP
Muhammad Imran QAQC (Welding Inspector)CSWIPMuhammad Imran
 
Resume_Chintan_Gohil_
Resume_Chintan_Gohil_Resume_Chintan_Gohil_
Resume_Chintan_Gohil_Chintan Gohil
 
site visit presentation
site visit presentationsite visit presentation
site visit presentationDominic Egan
 

What's hot (20)

Quality Control & Quality Assurance of MS pipeline
Quality Control & Quality Assurance of MS pipelineQuality Control & Quality Assurance of MS pipeline
Quality Control & Quality Assurance of MS pipeline
 
MD.NAFISUL HAQUE_original
MD.NAFISUL HAQUE_originalMD.NAFISUL HAQUE_original
MD.NAFISUL HAQUE_original
 
Qc
QcQc
Qc
 
cv3 of Magripa Tulepova
cv3  of Magripa Tulepovacv3  of Magripa Tulepova
cv3 of Magripa Tulepova
 
MADHAN RESUME - UPDATED
MADHAN RESUME - UPDATEDMADHAN RESUME - UPDATED
MADHAN RESUME - UPDATED
 
MWI CV3
MWI CV3MWI CV3
MWI CV3
 
Rajasekaran CV-updated
Rajasekaran CV-updatedRajasekaran CV-updated
Rajasekaran CV-updated
 
Rajesh kannan -BGAS level 2 CV
Rajesh kannan -BGAS level 2 CVRajesh kannan -BGAS level 2 CV
Rajesh kannan -BGAS level 2 CV
 
Quality assurance-for-ms-pipe itp-------------------------
Quality assurance-for-ms-pipe itp-------------------------Quality assurance-for-ms-pipe itp-------------------------
Quality assurance-for-ms-pipe itp-------------------------
 
senthilkumar CV
senthilkumar CVsenthilkumar CV
senthilkumar CV
 
10 steps blast_certification
10 steps blast_certification10 steps blast_certification
10 steps blast_certification
 
ars resume
ars resumears resume
ars resume
 
Complete March 2015 CV-2
Complete March 2015 CV-2Complete March 2015 CV-2
Complete March 2015 CV-2
 
Quality
QualityQuality
Quality
 
Multidispline Inspector - DEEPAK RAI
Multidispline Inspector - DEEPAK RAIMultidispline Inspector - DEEPAK RAI
Multidispline Inspector - DEEPAK RAI
 
Muhammed Riswan-QC rev1
Muhammed Riswan-QC rev1Muhammed Riswan-QC rev1
Muhammed Riswan-QC rev1
 
Muhammad Imran QAQC (Welding Inspector)CSWIP
Muhammad Imran QAQC (Welding Inspector)CSWIPMuhammad Imran QAQC (Welding Inspector)CSWIP
Muhammad Imran QAQC (Welding Inspector)CSWIP
 
Ikram _CV.
Ikram _CV.Ikram _CV.
Ikram _CV.
 
Resume_Chintan_Gohil_
Resume_Chintan_Gohil_Resume_Chintan_Gohil_
Resume_Chintan_Gohil_
 
site visit presentation
site visit presentationsite visit presentation
site visit presentation
 

Similar to Door testing 10_steps

UL Understanding the Importance of Air and Water Field Testing of Installed F...
UL Understanding the Importance of Air and Water Field Testing of Installed F...UL Understanding the Importance of Air and Water Field Testing of Installed F...
UL Understanding the Importance of Air and Water Field Testing of Installed F...
Ausrine Rakauskaite
 
API-936 exam preperation.pdf
API-936 exam preperation.pdfAPI-936 exam preperation.pdf
API-936 exam preperation.pdf
KarthikeyanP288430
 
INDERPAL SINGH CV AS QC
INDERPAL SINGH CV AS QCINDERPAL SINGH CV AS QC
INDERPAL SINGH CV AS QCInder Singh
 
Practical Assessment 1 - Install horizontal weatherboards
Practical Assessment 1 - Install horizontal weatherboardsPractical Assessment 1 - Install horizontal weatherboards
Practical Assessment 1 - Install horizontal weatherboards
Canberra Institute of technology
 
Practical assessment 2 - Install horizontal weatherboards to internal corner
Practical assessment 2 - Install horizontal weatherboards to internal cornerPractical assessment 2 - Install horizontal weatherboards to internal corner
Practical assessment 2 - Install horizontal weatherboards to internal corner
Canberra Institute of technology
 
Battery Pack Development Timeline and Expectations
Battery Pack Development Timeline and ExpectationsBattery Pack Development Timeline and Expectations
Battery Pack Development Timeline and Expectations
Epec Engineered Technologies
 
Practical assessment 3 - Install horizontal and vertical sheet panels
Practical assessment 3 - Install horizontal and vertical sheet panels Practical assessment 3 - Install horizontal and vertical sheet panels
Practical assessment 3 - Install horizontal and vertical sheet panels
Canberra Institute of technology
 
FACTORY ACCEPTANCE TEST
FACTORY ACCEPTANCE TEST FACTORY ACCEPTANCE TEST
En-Waleed Ibrahim Sr. Construction Piping Engineer cv
En-Waleed Ibrahim Sr. Construction Piping Engineer     cvEn-Waleed Ibrahim Sr. Construction Piping Engineer     cv
En-Waleed Ibrahim Sr. Construction Piping Engineer cvwaleed ibrahim
 
CURRICULAM_VITAE_QC
CURRICULAM_VITAE_QCCURRICULAM_VITAE_QC
CURRICULAM_VITAE_QCAnil Singh
 
Packaging Solutions that Improve Time to Market
Packaging Solutions that Improve Time to MarketPackaging Solutions that Improve Time to Market
Packaging Solutions that Improve Time to Market
April Bright
 
Insulation
InsulationInsulation
Insulation
Insulation2
 
COATING/ INSULATION/ PASSIVE FIRE PROTECTION /SUPERVISOR
COATING/ INSULATION/ PASSIVE FIRE PROTECTION /SUPERVISORCOATING/ INSULATION/ PASSIVE FIRE PROTECTION /SUPERVISOR
COATING/ INSULATION/ PASSIVE FIRE PROTECTION /SUPERVISOR
Artem Velychko
 
Electronic product design and development -2
Electronic product design and development -2Electronic product design and development -2
Electronic product design and development -2
Vinayak Bairagi
 
Standard Operating Procedures SOP for Prestressed Concrete Members facility.pdf
Standard Operating Procedures SOP for Prestressed Concrete Members facility.pdfStandard Operating Procedures SOP for Prestressed Concrete Members facility.pdf
Standard Operating Procedures SOP for Prestressed Concrete Members facility.pdf
ParmeshworVetwal1
 
Offshore Rig Productivity using AFT Xtegra Manifold Curtain Containment System
Offshore Rig Productivity using AFT Xtegra Manifold Curtain Containment SystemOffshore Rig Productivity using AFT Xtegra Manifold Curtain Containment System
Offshore Rig Productivity using AFT Xtegra Manifold Curtain Containment System
Jay Nowlin
 
Episode 22 : PROJECT EXECUTION
Episode 22 : PROJECT EXECUTION Episode 22 : PROJECT EXECUTION
Episode 22 : PROJECT EXECUTION
SAJJAD KHUDHUR ABBAS
 
Practical Assessment 2 cavity slider
Practical Assessment 2 cavity sliderPractical Assessment 2 cavity slider
Practical Assessment 2 cavity slider
Canberra Institute of technology
 

Similar to Door testing 10_steps (20)

UL Understanding the Importance of Air and Water Field Testing of Installed F...
UL Understanding the Importance of Air and Water Field Testing of Installed F...UL Understanding the Importance of Air and Water Field Testing of Installed F...
UL Understanding the Importance of Air and Water Field Testing of Installed F...
 
API-936 exam preperation.pdf
API-936 exam preperation.pdfAPI-936 exam preperation.pdf
API-936 exam preperation.pdf
 
INDERPAL SINGH CV AS QC
INDERPAL SINGH CV AS QCINDERPAL SINGH CV AS QC
INDERPAL SINGH CV AS QC
 
Practical Assessment 1 - Install horizontal weatherboards
Practical Assessment 1 - Install horizontal weatherboardsPractical Assessment 1 - Install horizontal weatherboards
Practical Assessment 1 - Install horizontal weatherboards
 
Practical assessment 2 - Install horizontal weatherboards to internal corner
Practical assessment 2 - Install horizontal weatherboards to internal cornerPractical assessment 2 - Install horizontal weatherboards to internal corner
Practical assessment 2 - Install horizontal weatherboards to internal corner
 
Battery Pack Development Timeline and Expectations
Battery Pack Development Timeline and ExpectationsBattery Pack Development Timeline and Expectations
Battery Pack Development Timeline and Expectations
 
Practical assessment 3 - Install horizontal and vertical sheet panels
Practical assessment 3 - Install horizontal and vertical sheet panels Practical assessment 3 - Install horizontal and vertical sheet panels
Practical assessment 3 - Install horizontal and vertical sheet panels
 
FACTORY ACCEPTANCE TEST
FACTORY ACCEPTANCE TEST FACTORY ACCEPTANCE TEST
FACTORY ACCEPTANCE TEST
 
kiruba new resume
kiruba new resumekiruba new resume
kiruba new resume
 
En-Waleed Ibrahim Sr. Construction Piping Engineer cv
En-Waleed Ibrahim Sr. Construction Piping Engineer     cvEn-Waleed Ibrahim Sr. Construction Piping Engineer     cv
En-Waleed Ibrahim Sr. Construction Piping Engineer cv
 
CURRICULAM_VITAE_QC
CURRICULAM_VITAE_QCCURRICULAM_VITAE_QC
CURRICULAM_VITAE_QC
 
Packaging Solutions that Improve Time to Market
Packaging Solutions that Improve Time to MarketPackaging Solutions that Improve Time to Market
Packaging Solutions that Improve Time to Market
 
Quality Check in Building
Quality Check in BuildingQuality Check in Building
Quality Check in Building
 
Insulation
InsulationInsulation
Insulation
 
COATING/ INSULATION/ PASSIVE FIRE PROTECTION /SUPERVISOR
COATING/ INSULATION/ PASSIVE FIRE PROTECTION /SUPERVISORCOATING/ INSULATION/ PASSIVE FIRE PROTECTION /SUPERVISOR
COATING/ INSULATION/ PASSIVE FIRE PROTECTION /SUPERVISOR
 
Electronic product design and development -2
Electronic product design and development -2Electronic product design and development -2
Electronic product design and development -2
 
Standard Operating Procedures SOP for Prestressed Concrete Members facility.pdf
Standard Operating Procedures SOP for Prestressed Concrete Members facility.pdfStandard Operating Procedures SOP for Prestressed Concrete Members facility.pdf
Standard Operating Procedures SOP for Prestressed Concrete Members facility.pdf
 
Offshore Rig Productivity using AFT Xtegra Manifold Curtain Containment System
Offshore Rig Productivity using AFT Xtegra Manifold Curtain Containment SystemOffshore Rig Productivity using AFT Xtegra Manifold Curtain Containment System
Offshore Rig Productivity using AFT Xtegra Manifold Curtain Containment System
 
Episode 22 : PROJECT EXECUTION
Episode 22 : PROJECT EXECUTION Episode 22 : PROJECT EXECUTION
Episode 22 : PROJECT EXECUTION
 
Practical Assessment 2 cavity slider
Practical Assessment 2 cavity sliderPractical Assessment 2 cavity slider
Practical Assessment 2 cavity slider
 

More from Intertek CE

CE Presentation
CE Presentation CE Presentation
CE Presentation Intertek CE
 
EMC Testing brochure
EMC Testing brochureEMC Testing brochure
EMC Testing brochure
Intertek CE
 
Intertek emc capabilities
Intertek emc capabilitiesIntertek emc capabilities
Intertek emc capabilitiesIntertek CE
 
Emc testing-brochure
Emc testing-brochureEmc testing-brochure
Emc testing-brochureIntertek CE
 
ETL Mark Fact-sheet
ETL Mark Fact-sheetETL Mark Fact-sheet
ETL Mark Fact-sheet
Intertek CE
 
Hvac single-sheet-brochure
Hvac single-sheet-brochureHvac single-sheet-brochure
Hvac single-sheet-brochureIntertek CE
 
Intertek emc capabilities
Intertek emc capabilitiesIntertek emc capabilities
Intertek emc capabilitiesIntertek CE
 
E uv usexplosiveareas
E uv usexplosiveareasE uv usexplosiveareas
E uv usexplosiveareasIntertek CE
 
Eu p power_supplies_im_final
Eu p power_supplies_im_finalEu p power_supplies_im_final
Eu p power_supplies_im_finalIntertek CE
 
Er p directive-televisions
Er p directive-televisionsEr p directive-televisions
Er p directive-televisionsIntertek CE
 
Ems pre reg_tips
Ems pre reg_tipsEms pre reg_tips
Ems pre reg_tipsIntertek CE
 
Emc compliance-for-renewable-resource-power-systems
Emc compliance-for-renewable-resource-power-systemsEmc compliance-for-renewable-resource-power-systems
Emc compliance-for-renewable-resource-power-systemsIntertek CE
 
Effects of emc_on_smart_appliance_designs
Effects of emc_on_smart_appliance_designsEffects of emc_on_smart_appliance_designs
Effects of emc_on_smart_appliance_designsIntertek CE
 
Eco design directive
Eco design directiveEco design directive
Eco design directiveIntertek CE
 

More from Intertek CE (20)

CE Presentation
CE Presentation CE Presentation
CE Presentation
 
EMC Testing brochure
EMC Testing brochureEMC Testing brochure
EMC Testing brochure
 
Intertek emc capabilities
Intertek emc capabilitiesIntertek emc capabilities
Intertek emc capabilities
 
Emc testing-brochure
Emc testing-brochureEmc testing-brochure
Emc testing-brochure
 
ETL Mark Fact-sheet
ETL Mark Fact-sheetETL Mark Fact-sheet
ETL Mark Fact-sheet
 
Hvac single-sheet-brochure
Hvac single-sheet-brochureHvac single-sheet-brochure
Hvac single-sheet-brochure
 
Hvac brochure
Hvac brochureHvac brochure
Hvac brochure
 
Intertek emc capabilities
Intertek emc capabilitiesIntertek emc capabilities
Intertek emc capabilities
 
S mark-en
S mark-enS mark-en
S mark-en
 
Intertek gs en
Intertek gs enIntertek gs en
Intertek gs en
 
Etl vs-ul-chart
Etl vs-ul-chartEtl vs-ul-chart
Etl vs-ul-chart
 
Wh mark
Wh markWh mark
Wh mark
 
E uv usexplosiveareas
E uv usexplosiveareasE uv usexplosiveareas
E uv usexplosiveareas
 
Eu p power_supplies_im_final
Eu p power_supplies_im_finalEu p power_supplies_im_final
Eu p power_supplies_im_final
 
Er p directive-televisions
Er p directive-televisionsEr p directive-televisions
Er p directive-televisions
 
Ems pre reg_tips
Ems pre reg_tipsEms pre reg_tips
Ems pre reg_tips
 
Emc compliance-for-renewable-resource-power-systems
Emc compliance-for-renewable-resource-power-systemsEmc compliance-for-renewable-resource-power-systems
Emc compliance-for-renewable-resource-power-systems
 
Emc safety
Emc safetyEmc safety
Emc safety
 
Effects of emc_on_smart_appliance_designs
Effects of emc_on_smart_appliance_designsEffects of emc_on_smart_appliance_designs
Effects of emc_on_smart_appliance_designs
 
Eco design directive
Eco design directiveEco design directive
Eco design directive
 

Recently uploaded

Cree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBdCree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
creerey
 
anas about venice for grade 6f about venice
anas about venice for grade 6f about veniceanas about venice for grade 6f about venice
anas about venice for grade 6f about venice
anasabutalha2013
 
What is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdfWhat is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdf
seoforlegalpillers
 
Digital Transformation in PLM - WHAT and HOW - for distribution.pdf
Digital Transformation in PLM - WHAT and HOW - for distribution.pdfDigital Transformation in PLM - WHAT and HOW - for distribution.pdf
Digital Transformation in PLM - WHAT and HOW - for distribution.pdf
Jos Voskuil
 
Exploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social DreamingExploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social Dreaming
Nicola Wreford-Howard
 
Affordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n PrintAffordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n Print
Navpack & Print
 
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
BBPMedia1
 
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
BBPMedia1
 
Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111
zoyaansari11365
 
5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer
ofm712785
 
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdfMeas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
dylandmeas
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
Cynthia Clay
 
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
taqyed
 
Taurus Zodiac Sign_ Personality Traits and Sign Dates.pptx
Taurus Zodiac Sign_ Personality Traits and Sign Dates.pptxTaurus Zodiac Sign_ Personality Traits and Sign Dates.pptx
Taurus Zodiac Sign_ Personality Traits and Sign Dates.pptx
my Pandit
 
Discover the innovative and creative projects that highlight my journey throu...
Discover the innovative and creative projects that highlight my journey throu...Discover the innovative and creative projects that highlight my journey throu...
Discover the innovative and creative projects that highlight my journey throu...
dylandmeas
 
Global Interconnection Group Joint Venture[960] (1).pdf
Global Interconnection Group Joint Venture[960] (1).pdfGlobal Interconnection Group Joint Venture[960] (1).pdf
Global Interconnection Group Joint Venture[960] (1).pdf
Henry Tapper
 
Improving profitability for small business
Improving profitability for small businessImproving profitability for small business
Improving profitability for small business
Ben Wann
 
Role of Remote Sensing and Monitoring in Mining
Role of Remote Sensing and Monitoring in MiningRole of Remote Sensing and Monitoring in Mining
Role of Remote Sensing and Monitoring in Mining
Naaraayani Minerals Pvt.Ltd
 
20240425_ TJ Communications Credentials_compressed.pdf
20240425_ TJ Communications Credentials_compressed.pdf20240425_ TJ Communications Credentials_compressed.pdf
20240425_ TJ Communications Credentials_compressed.pdf
tjcomstrang
 
India Orthopedic Devices Market: Unlocking Growth Secrets, Trends and Develop...
India Orthopedic Devices Market: Unlocking Growth Secrets, Trends and Develop...India Orthopedic Devices Market: Unlocking Growth Secrets, Trends and Develop...
India Orthopedic Devices Market: Unlocking Growth Secrets, Trends and Develop...
Kumar Satyam
 

Recently uploaded (20)

Cree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBdCree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
 
anas about venice for grade 6f about venice
anas about venice for grade 6f about veniceanas about venice for grade 6f about venice
anas about venice for grade 6f about venice
 
What is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdfWhat is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdf
 
Digital Transformation in PLM - WHAT and HOW - for distribution.pdf
Digital Transformation in PLM - WHAT and HOW - for distribution.pdfDigital Transformation in PLM - WHAT and HOW - for distribution.pdf
Digital Transformation in PLM - WHAT and HOW - for distribution.pdf
 
Exploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social DreamingExploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social Dreaming
 
Affordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n PrintAffordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n Print
 
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
 
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
 
Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111
 
5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer
 
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdfMeas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
 
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
 
Taurus Zodiac Sign_ Personality Traits and Sign Dates.pptx
Taurus Zodiac Sign_ Personality Traits and Sign Dates.pptxTaurus Zodiac Sign_ Personality Traits and Sign Dates.pptx
Taurus Zodiac Sign_ Personality Traits and Sign Dates.pptx
 
Discover the innovative and creative projects that highlight my journey throu...
Discover the innovative and creative projects that highlight my journey throu...Discover the innovative and creative projects that highlight my journey throu...
Discover the innovative and creative projects that highlight my journey throu...
 
Global Interconnection Group Joint Venture[960] (1).pdf
Global Interconnection Group Joint Venture[960] (1).pdfGlobal Interconnection Group Joint Venture[960] (1).pdf
Global Interconnection Group Joint Venture[960] (1).pdf
 
Improving profitability for small business
Improving profitability for small businessImproving profitability for small business
Improving profitability for small business
 
Role of Remote Sensing and Monitoring in Mining
Role of Remote Sensing and Monitoring in MiningRole of Remote Sensing and Monitoring in Mining
Role of Remote Sensing and Monitoring in Mining
 
20240425_ TJ Communications Credentials_compressed.pdf
20240425_ TJ Communications Credentials_compressed.pdf20240425_ TJ Communications Credentials_compressed.pdf
20240425_ TJ Communications Credentials_compressed.pdf
 
India Orthopedic Devices Market: Unlocking Growth Secrets, Trends and Develop...
India Orthopedic Devices Market: Unlocking Growth Secrets, Trends and Develop...India Orthopedic Devices Market: Unlocking Growth Secrets, Trends and Develop...
India Orthopedic Devices Market: Unlocking Growth Secrets, Trends and Develop...
 

Door testing 10_steps

  • 1. The Door Testing and Certification Guide Project Planning to Labeling in 10 Simple Steps www.intertek-etlsemko.com
  • 2. Door Testing and Certification: Project Planning to Labeling in 10 Simple Steps From project planning and test assembly preparation to certification planning and factory audit preparation you’ll learn the simple steps you can take to speed the testing and certification process. Our whitepaper details the door testing and certification process including technical and regulatory requirements, project timelines, and test setup procedures for Fire Testing, Windstorm Resistance, and Tornado Resistance projects. What are the 10 steps of door testing and certification? • Step 1: Project Planning • Step 2: Project Proposal • Step 3: Initial Product Review • Step 4: Pre-Test Inspection (For Certification Test Only) • Step 5: Test Assembly Preparation • Step 6: Testing (Fire, Windstorm / Tornado Resistance) • Step 7: Reporting • Step 8: Certification Planning • Step 9: Initial Factory Audit • Step 10: Labeling Step 1: Project Planning • Client identifies product(s) for qualification • Client supplies product information – construction and application drawings • Client identifies target markets for sale or distribution • Client identifies which ratings or standards will need to be met • Timeline: Dependent on client delivery of project information Step 2: Project Proposal • Client supplies information collected in Step 1 as noted above • Intertek prepares and delivers project proposal – often attached are credit applications and client information forms for expediency. • Client completes and returns the proposal or suggests revisions as necessary. A deposit for the subtotal amount may be required at this stage. • A copy of the signed proposal is forwarded to Intertek’s certification department • Timeline: Intertek’s proposal is delivered within 48 hours www.intertek-etlsemko.com
  • 3. Step 3: Initial Product Review • Intertek evaluates product information, drawings, etc. and advises on any areas of concern. o At this point the client may need to address concerns before making test samples. • Timeline: Projects are opened within 2-4 days of receipt of signed paperwork. The review begins within 3-4 days after the project has been opened. The review time may vary depending on curing time and product. Step 4: Pre-Test Inspection (For Certification Test Only) • An Intertek representative will: o Witness and document construction of test sample o Review component and assembly drawings, material type, size and dimension o Prepare a “Pre-Test Inspection Report” and send to Intertek lab o Sign the test sample/package to be opened only at the test lab • The client will: o Seal and package the test sample o If the sample requires custom clearance, it is advised to mark “Test Samples for Destructive Testing, Commercial Value is Zero” on the package and send to the Intertek lab designated in proposal • Timeline: o Domestic: Pretest sampling - up to 2 weeks. Doors are usually allowed up to 28 days for adhesive conditioning then trimmed to test frame size. Delivery to the lab is usually 1 week thereafter. o International: Pretest sampling - up to 3 weeks. Delivery of the prepared samples to the test lab may take 4-6 weeks depending on client’s selected shipping method. Step 5: Test Assembly Preparation • Option 1 – Client prehangs the doors for test and ships to Intertek to be installed in test setup. • Option 2 – Client sends the doors to Intertek for machining and installation in test setup. • Upon receipt, technicians will inspect the samples. If all match the Pre-Test Inspection Report, construction of the test assemblies will begin. • Test assemblies are built in accordance with the test plan including all assembly components. • Timeline: Test plans are based on client preference and availability. Test assemblies can be prepared in as few as 2 days if all materials have been supplied. Where cementitious materials are used a cure time of 7 days is normally required. www.intertek-etlsemko.com
  • 4. Step 6a: Fire Testing • Conducted under positive or neutral pressure following standard time vs. temperature curves. • Doors must meet temperature rise criteria (when applicable), resist the passage of fire, and stay securely in the opening through the test period. • Test methods include but are not limited to: o US & Canada: NFPA 252, UL 10 (B/C), UBC 7-2 (1994/1997), CAN4 S104 o International: BS 476, parts 21 & 22 and ISO 3008. • Timeline: Ranges from 20 minutes to 3 hours depending on product construction and requirements of standard Step 6a: Fire Testing Test Setup • Research Scale or Pilot Scale: Provides data prior to larger scale tests. Used to qualify a variable in the assembly and components (Example: Adhesives). • Mid-Scale: Used when single swing doors are required. • Full-Scale: Used for multiple doors or a pair in a test wall. Step 6b: Windstorm Resistance Testing • Testing of hurricane-resistant products o Required for State of Florida, and may be required in IRC and IBC from the Gulf coast up the Eastern seaboard. • Test standards include: o Door assemblies: ASTM E330, ASTM E1886, ASTM E1996 o Door assemblies: TAS 201, TAS 202, TAS 203 for Miami Dade County o Individual components: ANSI A250.13 • Timeline: Tests typically range from 3 to 7 days depending on size and/or configuration, and number of rating options needed. Step 6b: Windstorm Resistance Test Setup • Several approaches o Assembly tests to High Velocity Hurricane Zone requirements for South Florida (Miami Dade) approval (TAS 201,202, 203); also requires notification of upcoming test via Miami Dade submittal o Component testing per ANSI A250.13 o Assembly tests per ASTM E1886/E1996 o Combination component and assembly testing to Miami Dade requirements, ANSI A250.13 and ASTM E1886/E1996 • Product design must be documented and verified by a pre-test inspection, or post- test examination of cut sections. www.intertek-etlsemko.com
  • 5. Client must specify target design load (DL)…….enhanced protection, etc). If client is unsure of what his product's DL may be, an R & D test project will be conducted to establish the appropriate DL.) • Structural performance testing is conducted first at 1.5 times the DL. If Miami-Dade requirements are also required, the water penetration, air infiltration and forced entry tests will be conducted within this first series of tests. • Impact testing is then conducted, with the cyclic load tests conducted following. Doors must remain closed, and prevent penetration of the missile(s). • Variations in the assembly (i.e., anchorage, hardware options, etc) will be considered, and may be included in the 3 assemblies required for the impact and cyclic load tests. These variations should be discussed with your project manager prior to the start of testing. • Glazed doors and/or frames with sidelights and/or transoms require separate tests. • Tests are conducted on the largest size to be certified. Step 6c: Tornado Resistance Testing • Testing of tornado-resistant products including static load and impact • Test methods include: o FEMA 320 - Taking Shelter from the Storm – Building a Safe Room in Your House o FEMA 361 - Design and Construction Guidance for Community Shelter o National Storm Shelter Association requirements • Note: Work is currently being done to develop a formal ANSI test method. • Timeline: Tornado resistance testing can be completed in 1 day. Step 6c: Tornado Resistance Test Setup • Testing is assembly based • Installed in simulated wall – typically wood framing, concrete or CMU with specified anchorage • Impact test with 15 pound 2x4 at 100 miles per hour (5,014 foot-pounds) • Impact at multiple locations including near latch and hinge points • Static load tests (positive and negative) at 250 PSF on separate (unimpacted) assembly • Assemblies must prevent missile penetration, remain closed and limit dynamic deflection to 3” or less Step 7: Reporting • Upon successful test results Intertek will issue: o Test Report or Engineering Evaluation Report (Listing Report for Certification) to the client and Intertek Certification department o Draft Listing and Authorization to Mark (ATM) to the Intertek Certification department. www.intertek-etlsemko.com
  • 6. Step 8: Certification Planning • Intertek sends the client a “Certification & Listing Agreement”. o The client signs and returns the document along with a deposit (if applicable) to Intertek. o The client receives a signed copy for records. • Note: Not all products require a physical label as some only need to be “Listed”. For those products that do require a label, presence of an authorized label, such as Intertek’s WH Mark, is the only legal proof that a third party has certified the product. • Timeline: Once the listing report has been accepted a certification agreement is prepared. Step 9: Initial Factory Audit (IFA) • An Intertek inspector will visit your factory: o Review flow chart of production process and in-house quality control during production o Review training records of critical personnel o Conduct raw material inspection & QC done by factory o Witness a representative layup o Complete final inspection after production is completed (prior to shipping) o Secure arrangements and certification label controller o If the IFA is successful, the inspector will provide the Authorization to Mark (ATM). • Timeline: Domestic – 10 days, International – 14 days Step 10: Labeling • The client may apply certification labels to the product, packaging, or both (recommended). • An Intertek inspector will conduct unannounced, quarterly inspections to verify all processes identified during the IFA are being followed. • Non-conformances are immediately reported to the client and Intertek. o The client is required to resolve immediately and communicate evidence of resolution to Intertek. o Delay / failure to resolve can result in suspension or termination of certification. www.intertek-etlsemko.com
  • 7. Additional Resources How can I further accelerate the process? • Using our proprietary web-based tool you can: o Initiate projects online and track project status o Access listings and specs via a secure site - 24/7/365 o Distribute notifications of product updates, listings to customers o Replace paper delivery and 3-ring binder system o Educate customers by mapping marketing literature, installation instructions, etc. to a product listing o Print your own labels … Get the product information you need sooner so you can manufacture and market your products faster. Are their any quick hints to be aware of? • Once the Listing Report has been accepted a Certification Agreement is prepared… sign and return agreement on that day and it can be finalized by Intertek within 1-2 days. • The Certification Agreement can be issued when the signed proposal is returned. Once Intertek has a signed agreement and an accepted Listing Report, only the Factory Audit is remaining. • Subscribe to SpecDirect and speed the entire process. The SpecDirect contract can be offered along with the testing program proposal. www.intertek-etlsemko.com
  • 8. About Intertek Intertek is recognized by all major code bodies throughout the world. We are a Nationally Recognized Testing Laboratory (NRTL) by OSHA; recognized by Standards Council of Canada (SCC); and A2LA, APLAC, and ILAC accredited for Asia and other parts of the world. In North America we are recognized by the International Codes Council Evaluation Service (ICC-ES) and serve as an administrator for multiple Builders Hardware Manufacturers Association (BHMA) certification programs. What testing, certification, and evaluation services does Intertek offer? • WH Mark for North America • Performance evaluations; durability and product comparison • Environmental testing • Flammability, flame spread, and fire resistance testing • Structural, physical and mechanical evaluations What specific accreditations does Intertek hold? • ICC-International Accreditation Services (IAS) for testing and certification of building materials • American Association of Laboratory Accreditation (A2LA) • American National Standards Institute (ANSI) • Department of Housing and Urban Development (HUD) • Recognized by the Occupational Safety and Health Administration (OSHA) as a Nationally Recognized Testing Laboratory (NRTL) • Standards Council of Canada (SCC) • Testing Laboratory accredited to ISO/IEC 17025 • Inspection Agency accredited to ISO/IEC 17020 • Certification Organization accredited to ISO Guide 65 For more information on Intertek’s door testing and certification capabilities or to start a project right away, call 1-800-967-5352, email icenter@intertek.com, or visit www.intertek-etlsemko.com. www.intertek-etlsemko.com