Construction claims, disputes and project closuresrinivas2036
This document discusses construction claims, disputes, and project closure. It begins by explaining that during project execution, issues often arise between parties that cannot be resolved, resulting in claims from contractors for time extensions or cost reimbursements. These claims can be settled amicably or become disputes if the owner does not agree. Common sources of claims include defects in contracts, site conditions differing from descriptions, scope changes, and payment delays. The document provides guidance on claim management, notification, substantiation, and resolution procedures. It also discusses mechanisms for dispute avoidance and resolution such as negotiation, mediation, arbitration, and their advantages over legal proceedings.
This document discusses variations and deviations that may occur during contract execution. It defines variations as changes to the scope of work, while deviations refer specifically to changes in quantities, items, or conditions from what is specified in the bill of quantities. The reasons for variations and deviations include errors in estimating, design changes, unavailable materials, and client/contractor revisions. Extra items not included in the original bill are also addressed. The document outlines how rates for quantity deviations, extra items, and substituted items are typically determined in the contract or through other agreed methods. Implications like time and cost overruns and potential disputes are also noted.
FIDIC is an international federation of consulting engineers established in 1913. It publishes standard form construction contracts known by the color of their covers, such as the Red Book. The document discusses the history and evolution of FIDIC contracts, describing various contract forms like the Red Book, Yellow Book, and Silver Book. It also discusses the roles of consulting engineers and the Consulting Engineers Association of India, the Indian affiliate of FIDIC.
Tendering Bidding & Award of Contract Final DraftMuneesh Methwani
The document discusses various aspects of tendering and bidding processes for construction projects. It covers:
- Types of tenders including lumpsum, item rate, percentage rate, cost plus, package deal, standing offer, labour contract, and supply of materials tenders.
- Tendering steps such as finalizing procurement strategy, preparing tender documents, inviting tenders, bid evaluation, negotiation and award of contract.
- Key tender documents including notice inviting tenders, instructions to bidders, contract conditions, specifications, drawings and formats.
- Modes of inviting tenders including negotiated, limited competition and open competition.
- Bidding methods like single-stage single-envelope, single-
Construction Project Management is an important subject to learn in Civil Engineering.
Significance • As construction involves various activities starting from the design and planning to project completion and quality check, there is a exorbitant need for Management of construction. • Construction Industry plays a crucial role in the economy and development of a nation.
4. Objectives To complete the project in specified time and with allocated budget. To Plan and schedule the work and distribute between various departments. Deployment of personnel in Different tasks. To achieve High quality workmanship. Creating an organisation that works as a team. Using the limited available resources and producing maximum output. Providing safe and satisfactory working conditions for all personnel and workers.
5. Functions: Planning & Scheduling Organizing Staffing Directing Controlling & Co-ordinating
6. Stages of construction Briefing Designing Tendering Construction Commissioning
7. 1) Briefing Stage • This stage consists of framework required for the construction work to take a shape from the ideology of client and feasibility of Project which involves architects, engineers and project manager.
Objectives Developing Alternatives Feasible Solution ? Evaluation of Alternatives Report & Recommendation Technical and non technical Investigations
8. 2) Designing or planning Stage Prepare construction schedule Prepare final cost estimate Prepare Working Drawings and specificati ons Prepare scheme and detailed designs Soil investigations, Topographic investigation, material supply and market surveys etc Carry out Technical Investigations Final adoption of the most suitable summary Finalize Project Summary
The document discusses various aspects of civil tenders and contracts processes in the Indian Railways. It defines civil tenders as the process where governments and institutions invite bids for project execution within a deadline. It notes that a contract is a defined legal agreement between the tendering authority and successful bidder. It also describes the different types of tenders like open, limited, special limited, and single tenders. Additionally, it provides details on tendering processes like notice inviting tenders, publication of tenders, tender committee formation, and earnest money deposits.
Presentation is trying to define the intent , content, methods and scope of arbitration and tendering and its implications for the architectural practice.
The document discusses various types of construction contracts including: lump sum contracts where the owner pays a specified amount upon completion; cost plus contracts where the owner pays the contractor's documented costs plus an additional fee; and integrated contracts where a single contractor is responsible for design and construction like design-build or turnkey contracts. Management contracts involve appointing a contractor to coordinate other subcontractors. Measurable and item rate contracts establish payment based on physical measurements or rates for units of work.
Construction claims, disputes and project closuresrinivas2036
This document discusses construction claims, disputes, and project closure. It begins by explaining that during project execution, issues often arise between parties that cannot be resolved, resulting in claims from contractors for time extensions or cost reimbursements. These claims can be settled amicably or become disputes if the owner does not agree. Common sources of claims include defects in contracts, site conditions differing from descriptions, scope changes, and payment delays. The document provides guidance on claim management, notification, substantiation, and resolution procedures. It also discusses mechanisms for dispute avoidance and resolution such as negotiation, mediation, arbitration, and their advantages over legal proceedings.
This document discusses variations and deviations that may occur during contract execution. It defines variations as changes to the scope of work, while deviations refer specifically to changes in quantities, items, or conditions from what is specified in the bill of quantities. The reasons for variations and deviations include errors in estimating, design changes, unavailable materials, and client/contractor revisions. Extra items not included in the original bill are also addressed. The document outlines how rates for quantity deviations, extra items, and substituted items are typically determined in the contract or through other agreed methods. Implications like time and cost overruns and potential disputes are also noted.
FIDIC is an international federation of consulting engineers established in 1913. It publishes standard form construction contracts known by the color of their covers, such as the Red Book. The document discusses the history and evolution of FIDIC contracts, describing various contract forms like the Red Book, Yellow Book, and Silver Book. It also discusses the roles of consulting engineers and the Consulting Engineers Association of India, the Indian affiliate of FIDIC.
Tendering Bidding & Award of Contract Final DraftMuneesh Methwani
The document discusses various aspects of tendering and bidding processes for construction projects. It covers:
- Types of tenders including lumpsum, item rate, percentage rate, cost plus, package deal, standing offer, labour contract, and supply of materials tenders.
- Tendering steps such as finalizing procurement strategy, preparing tender documents, inviting tenders, bid evaluation, negotiation and award of contract.
- Key tender documents including notice inviting tenders, instructions to bidders, contract conditions, specifications, drawings and formats.
- Modes of inviting tenders including negotiated, limited competition and open competition.
- Bidding methods like single-stage single-envelope, single-
Construction Project Management is an important subject to learn in Civil Engineering.
Significance • As construction involves various activities starting from the design and planning to project completion and quality check, there is a exorbitant need for Management of construction. • Construction Industry plays a crucial role in the economy and development of a nation.
4. Objectives To complete the project in specified time and with allocated budget. To Plan and schedule the work and distribute between various departments. Deployment of personnel in Different tasks. To achieve High quality workmanship. Creating an organisation that works as a team. Using the limited available resources and producing maximum output. Providing safe and satisfactory working conditions for all personnel and workers.
5. Functions: Planning & Scheduling Organizing Staffing Directing Controlling & Co-ordinating
6. Stages of construction Briefing Designing Tendering Construction Commissioning
7. 1) Briefing Stage • This stage consists of framework required for the construction work to take a shape from the ideology of client and feasibility of Project which involves architects, engineers and project manager.
Objectives Developing Alternatives Feasible Solution ? Evaluation of Alternatives Report & Recommendation Technical and non technical Investigations
8. 2) Designing or planning Stage Prepare construction schedule Prepare final cost estimate Prepare Working Drawings and specificati ons Prepare scheme and detailed designs Soil investigations, Topographic investigation, material supply and market surveys etc Carry out Technical Investigations Final adoption of the most suitable summary Finalize Project Summary
The document discusses various aspects of civil tenders and contracts processes in the Indian Railways. It defines civil tenders as the process where governments and institutions invite bids for project execution within a deadline. It notes that a contract is a defined legal agreement between the tendering authority and successful bidder. It also describes the different types of tenders like open, limited, special limited, and single tenders. Additionally, it provides details on tendering processes like notice inviting tenders, publication of tenders, tender committee formation, and earnest money deposits.
Presentation is trying to define the intent , content, methods and scope of arbitration and tendering and its implications for the architectural practice.
The document discusses various types of construction contracts including: lump sum contracts where the owner pays a specified amount upon completion; cost plus contracts where the owner pays the contractor's documented costs plus an additional fee; and integrated contracts where a single contractor is responsible for design and construction like design-build or turnkey contracts. Management contracts involve appointing a contractor to coordinate other subcontractors. Measurable and item rate contracts establish payment based on physical measurements or rates for units of work.
This document provides an overview of construction contracting methods and contract types. It discusses the traditional Design-Bid-Build approach, as well as Design-Build, Turnkey, and Construction Management delivery methods. The major contract types covered are Lump Sum, Unit Price, Cost Plus, and variations like Cost Plus Fixed Fee and Cost Plus with a Guaranteed Maximum Price. For each, the document outlines the key characteristics, advantages, and disadvantages. The course appears to cover construction documents, contracting, bidding processes, and contract conditions over multiple lectures.
BIDDING-TENDER-CONTRACT
TENDERING PROCEDURE – AWARD OF TENDERS
ESSENTIAL ELEMENTS OF CONTRACTS
Types of contracts
MEASUREMENT BOOK
Security deposit
CONTRACT DOCUMENT
Earnest money deposit (EMD)
Qualification of contractors
IMPORTANT CLAUSES IN CONSTRUCTION CONTRACTS
This document discusses project management principles and techniques. It covers topics like organizing and managing projects, planning projects, review procedures, reporting, and project termination. It describes various project management functions including defining project scope, deciding how activities will be executed, developing suitable project organizations, preparing implementation plans, and monitoring and controlling progress. It also discusses techniques for project planning like network analysis, bar charts, work breakdown structures, critical path method, and time/resource analysis.
The document discusses the tender process for construction projects. It involves project definition, selecting tenderers, issuing tender documentation, criteria for selection, calling for tenders, tender meetings, amendments, submission and closing, tender analysis of work experience, price, company finances and personnel, ongoing projects, and conformity to conditions. Selection criteria include conformity, capability, innovation, price and construction period. Tenders can be rejected for noncompliance, incomplete details, too high or low prices, too much work in progress, insufficient finances, or unsatisfactory records.
The document discusses various types of claims that can arise in construction contracts, including contractual claims, extra contractual claims, quantum merit claims, ex-gratia claims, and counter claims. It emphasizes the importance of properly preparing and presenting claims by outlining the burden of proof, establishing the legal basis, and providing supporting evidence and facts. Claims must be substantiated with documentation like correspondence, meeting records, site diaries, programs and payment records.
The document provides an introduction to the role of quantity surveyors in construction projects. It discusses that quantity surveyors are responsible for financial aspects of construction and provide various services throughout a project, including preparing initial budgets and cost estimates, tender documents, valuations of work, and final accounts. It also describes the different stages of a project where quantity surveyors are involved, such as pre-tender, tender, and post-tender stages, and the tasks performed during each stage.
The document discusses the tendering process and key elements of a tender. It defines a tender as an offer to complete a project for a specified price and time. The main stages of the tendering process are preparation, approval, documentation, invitation, processing, and contract award. Key elements of tender documents include drawings, specifications, bill of quantities, conditions of contract, forms of tender and agreement, and performance bonds.
Construction Claims generally comes up between two parties of the construction contracts, and there can be several reasons which result in a claim such as a delay in the project, uninformed changes, misinformation, unforeseen circumstances and general conflicts. In UAE, as the constructions are on the rise, so the disputes are. Professional construction claims consultants Dubai offering services protecting the values of both the clients and the contractors.
Contracts provide a legally-enforceable framework for guiding any and every type of business relationship, from employment agreements to orders for parts and supplies. While these agreements are key to guiding business relationships and ventures across all sectors, getting contracts right is especially important within construction, where the ability to complete a build on time, on budget and to code hinges upon all vendor arrangements going as expected. From the builder’s perspective, contracts are also important for preventing scope creep and to reducing the risk of cost overruns they may unexpectedly have to absorb.
Construction management contracts encompass the work and/or materials required for a building project. Typically, they will address:
1)Project/deliverable specifications
2)Labor and material requirements
3)Timelines for completion/delivery
4)Compensation formula and amounts
While construction management agreements will typically include the above, they can be structured differently, with numerous types of contracts that are designed to best meet the needs of all parties under all sorts of different scenarios. Familiarizing yourself with the types of contracts that are typically in play within building projects is an important first step to optimizing all contract-related processes within construction management.
The document outlines the construction tender process between clients, contractors, and subcontractors. It discusses the various stages a contractor goes through when submitting a tender, including reviewing project details, conducting site surveys, developing cost estimates and bills of quantities, considering available resources and equipment, and ultimately submitting a bid package. The tender process depends on the type of tender (open or selective) and involves the contractor strategically planning and scrutinizing all available tender documents.
Types of Contract in Construction ManagementShahin MB
This document describes several types of construction contracts: lump-sum, cost plus fixed fee, cost plus bid fee, guaranteed maximum, negotiated, unit-price, design-build, and turn-key. Lump-sum contracts establish a fixed total price upfront, while cost plus contracts reimburse the contractor's costs plus a fixed or percentage-based fee. Guaranteed maximum contracts set a ceiling on costs. Negotiated, unit-price, design-build, and turn-key contracts vary in responsibilities and payment structures.
FIDIC is an international federation of consulting engineers that publishes standard forms of contract. It was founded in 1913 and is headquartered in Geneva. Some of FIDIC's most well-known standard forms include the Red, Yellow, and Silver Books. The Red Book covers construction projects, the Yellow Book covers electrical and mechanical works, and the Silver Book covers EPC/turnkey projects. FIDIC contracts establish important procedures like priority of contract documents, the engineer's role, extensions of time, insurance requirements, and dispute resolution processes involving negotiation, mediation, and arbitration.
This document discusses various aspects of contract management for construction projects including methods of work execution, types of contracts, and the tendering process. It describes executing work through amanat (directly by the owner) or through contracts. It outlines various types of contracts like lump sum, unit price, cost reimbursable, design-build, and BOOT/BOT. Finally, it explains the tendering process which involves preparation, tender notice, tender document, conditions of contract, prequalification, evaluation, and selection/award.
The document is the tender and contract conditions for the construction of a building in Liwan, Dubai. It includes instructions to tenderers on submitting the tender, requirements for site visits, and clarification of contract documents. The tender must include supporting documents such as proof of a site visit and a tender bond. The employer reserves the right to accept or reject any part of the tender. The tenderer is responsible for understanding all project requirements and conditions. No changes can be made to the tender documents except for filling in blanks.
Contracts and Tenders
When two or more persons have common intention communicated to each other to create same obligation between them there is said to be an agreement. An agreement which is enforceable by law is a Contract.
A Tenders is called upon for executing certain specified work, or supplying specified materials; subjected to certain terms and conditions like rates, time limit, etc. It is an offer in written form: Legally speaking, it is an offer to receive an offer for the work, within the specified financial limits.
Check for more presentations at - www.archistudent.net
The document discusses Build-Own-Operate-Transfer (BOOT) projects as a type of public-private partnership procurement strategy. In a BOOT project, a private company builds and operates a facility, such as a toll road, on behalf of the public sector for a set period of time. The case study examines Malaysia's North-South Expressway, which was developed as a BOOT project where a consortium designed, constructed, financed, and operated the expressway over a 30-year concession period.
The document provides an overview of the tendering and bidding process. It defines key terms like tender, bid, proposal, and procurement methods. The tender process involves several steps - pre-tender activities, issuing the tender, tender evaluation, and awarding the contract. The bidding process map outlines various stages from announcement to awarding. The evaluation process consists of opening bids, examining them, requesting clarifications, evaluating and comparing bids, post-qualification, and recommending a winner. Key points of evaluation include checking for completeness, computational errors, and applying criteria to determine the lowest bidder.
The document discusses FIDIC, an international organization for consulting engineers. It was founded in 1913 and now has over 60 member countries. FIDIC is best known for publishing standard contract conditions used around the world for construction projects. The document discusses the new editions of FIDIC's standard contracts, including the Red Book for construction, Yellow Book for plant design/build, and Silver Book for EPC turnkey projects. It provides details on the applicability of each book under different project delivery systems. The document also discusses improvements made in the new editions to address issues like back payments, financial arrangements, and contractor-financed projects.
Construction disputes arise from environmental and behavioural factors. There are many different causes of disputes in the construction industry. Disputes waste money, therefore drain profits and destroy the relationship and it takes energy away from projects.
construction dispute cases
construction dispute lawyer
construction disputes statistics
construction dispute letter
causes of disputes in construction
construction disputes attorney
construction dispute resolution services llc
homeowner vs contractor disputes
building construction ppt
construction ppt presentations
This document discusses various techniques for resolving construction contract disputes, including litigation, negotiation, arbitration, mediation, expert determination, dispute review boards, and rent-a-judge. It provides details on claims that commonly arise in construction projects and against owners or contractors. The best practices for preventing and resolving disputes involve using alternative dispute resolution methods like mediation early on and having a predetermined dispute resolution plan.
This document provides an overview of construction contracting methods and contract types. It discusses the traditional Design-Bid-Build approach, as well as Design-Build, Turnkey, and Construction Management delivery methods. The major contract types covered are Lump Sum, Unit Price, Cost Plus, and variations like Cost Plus Fixed Fee and Cost Plus with a Guaranteed Maximum Price. For each, the document outlines the key characteristics, advantages, and disadvantages. The course appears to cover construction documents, contracting, bidding processes, and contract conditions over multiple lectures.
BIDDING-TENDER-CONTRACT
TENDERING PROCEDURE – AWARD OF TENDERS
ESSENTIAL ELEMENTS OF CONTRACTS
Types of contracts
MEASUREMENT BOOK
Security deposit
CONTRACT DOCUMENT
Earnest money deposit (EMD)
Qualification of contractors
IMPORTANT CLAUSES IN CONSTRUCTION CONTRACTS
This document discusses project management principles and techniques. It covers topics like organizing and managing projects, planning projects, review procedures, reporting, and project termination. It describes various project management functions including defining project scope, deciding how activities will be executed, developing suitable project organizations, preparing implementation plans, and monitoring and controlling progress. It also discusses techniques for project planning like network analysis, bar charts, work breakdown structures, critical path method, and time/resource analysis.
The document discusses the tender process for construction projects. It involves project definition, selecting tenderers, issuing tender documentation, criteria for selection, calling for tenders, tender meetings, amendments, submission and closing, tender analysis of work experience, price, company finances and personnel, ongoing projects, and conformity to conditions. Selection criteria include conformity, capability, innovation, price and construction period. Tenders can be rejected for noncompliance, incomplete details, too high or low prices, too much work in progress, insufficient finances, or unsatisfactory records.
The document discusses various types of claims that can arise in construction contracts, including contractual claims, extra contractual claims, quantum merit claims, ex-gratia claims, and counter claims. It emphasizes the importance of properly preparing and presenting claims by outlining the burden of proof, establishing the legal basis, and providing supporting evidence and facts. Claims must be substantiated with documentation like correspondence, meeting records, site diaries, programs and payment records.
The document provides an introduction to the role of quantity surveyors in construction projects. It discusses that quantity surveyors are responsible for financial aspects of construction and provide various services throughout a project, including preparing initial budgets and cost estimates, tender documents, valuations of work, and final accounts. It also describes the different stages of a project where quantity surveyors are involved, such as pre-tender, tender, and post-tender stages, and the tasks performed during each stage.
The document discusses the tendering process and key elements of a tender. It defines a tender as an offer to complete a project for a specified price and time. The main stages of the tendering process are preparation, approval, documentation, invitation, processing, and contract award. Key elements of tender documents include drawings, specifications, bill of quantities, conditions of contract, forms of tender and agreement, and performance bonds.
Construction Claims generally comes up between two parties of the construction contracts, and there can be several reasons which result in a claim such as a delay in the project, uninformed changes, misinformation, unforeseen circumstances and general conflicts. In UAE, as the constructions are on the rise, so the disputes are. Professional construction claims consultants Dubai offering services protecting the values of both the clients and the contractors.
Contracts provide a legally-enforceable framework for guiding any and every type of business relationship, from employment agreements to orders for parts and supplies. While these agreements are key to guiding business relationships and ventures across all sectors, getting contracts right is especially important within construction, where the ability to complete a build on time, on budget and to code hinges upon all vendor arrangements going as expected. From the builder’s perspective, contracts are also important for preventing scope creep and to reducing the risk of cost overruns they may unexpectedly have to absorb.
Construction management contracts encompass the work and/or materials required for a building project. Typically, they will address:
1)Project/deliverable specifications
2)Labor and material requirements
3)Timelines for completion/delivery
4)Compensation formula and amounts
While construction management agreements will typically include the above, they can be structured differently, with numerous types of contracts that are designed to best meet the needs of all parties under all sorts of different scenarios. Familiarizing yourself with the types of contracts that are typically in play within building projects is an important first step to optimizing all contract-related processes within construction management.
The document outlines the construction tender process between clients, contractors, and subcontractors. It discusses the various stages a contractor goes through when submitting a tender, including reviewing project details, conducting site surveys, developing cost estimates and bills of quantities, considering available resources and equipment, and ultimately submitting a bid package. The tender process depends on the type of tender (open or selective) and involves the contractor strategically planning and scrutinizing all available tender documents.
Types of Contract in Construction ManagementShahin MB
This document describes several types of construction contracts: lump-sum, cost plus fixed fee, cost plus bid fee, guaranteed maximum, negotiated, unit-price, design-build, and turn-key. Lump-sum contracts establish a fixed total price upfront, while cost plus contracts reimburse the contractor's costs plus a fixed or percentage-based fee. Guaranteed maximum contracts set a ceiling on costs. Negotiated, unit-price, design-build, and turn-key contracts vary in responsibilities and payment structures.
FIDIC is an international federation of consulting engineers that publishes standard forms of contract. It was founded in 1913 and is headquartered in Geneva. Some of FIDIC's most well-known standard forms include the Red, Yellow, and Silver Books. The Red Book covers construction projects, the Yellow Book covers electrical and mechanical works, and the Silver Book covers EPC/turnkey projects. FIDIC contracts establish important procedures like priority of contract documents, the engineer's role, extensions of time, insurance requirements, and dispute resolution processes involving negotiation, mediation, and arbitration.
This document discusses various aspects of contract management for construction projects including methods of work execution, types of contracts, and the tendering process. It describes executing work through amanat (directly by the owner) or through contracts. It outlines various types of contracts like lump sum, unit price, cost reimbursable, design-build, and BOOT/BOT. Finally, it explains the tendering process which involves preparation, tender notice, tender document, conditions of contract, prequalification, evaluation, and selection/award.
The document is the tender and contract conditions for the construction of a building in Liwan, Dubai. It includes instructions to tenderers on submitting the tender, requirements for site visits, and clarification of contract documents. The tender must include supporting documents such as proof of a site visit and a tender bond. The employer reserves the right to accept or reject any part of the tender. The tenderer is responsible for understanding all project requirements and conditions. No changes can be made to the tender documents except for filling in blanks.
Contracts and Tenders
When two or more persons have common intention communicated to each other to create same obligation between them there is said to be an agreement. An agreement which is enforceable by law is a Contract.
A Tenders is called upon for executing certain specified work, or supplying specified materials; subjected to certain terms and conditions like rates, time limit, etc. It is an offer in written form: Legally speaking, it is an offer to receive an offer for the work, within the specified financial limits.
Check for more presentations at - www.archistudent.net
The document discusses Build-Own-Operate-Transfer (BOOT) projects as a type of public-private partnership procurement strategy. In a BOOT project, a private company builds and operates a facility, such as a toll road, on behalf of the public sector for a set period of time. The case study examines Malaysia's North-South Expressway, which was developed as a BOOT project where a consortium designed, constructed, financed, and operated the expressway over a 30-year concession period.
The document provides an overview of the tendering and bidding process. It defines key terms like tender, bid, proposal, and procurement methods. The tender process involves several steps - pre-tender activities, issuing the tender, tender evaluation, and awarding the contract. The bidding process map outlines various stages from announcement to awarding. The evaluation process consists of opening bids, examining them, requesting clarifications, evaluating and comparing bids, post-qualification, and recommending a winner. Key points of evaluation include checking for completeness, computational errors, and applying criteria to determine the lowest bidder.
The document discusses FIDIC, an international organization for consulting engineers. It was founded in 1913 and now has over 60 member countries. FIDIC is best known for publishing standard contract conditions used around the world for construction projects. The document discusses the new editions of FIDIC's standard contracts, including the Red Book for construction, Yellow Book for plant design/build, and Silver Book for EPC turnkey projects. It provides details on the applicability of each book under different project delivery systems. The document also discusses improvements made in the new editions to address issues like back payments, financial arrangements, and contractor-financed projects.
Construction disputes arise from environmental and behavioural factors. There are many different causes of disputes in the construction industry. Disputes waste money, therefore drain profits and destroy the relationship and it takes energy away from projects.
construction dispute cases
construction dispute lawyer
construction disputes statistics
construction dispute letter
causes of disputes in construction
construction disputes attorney
construction dispute resolution services llc
homeowner vs contractor disputes
building construction ppt
construction ppt presentations
This document discusses various techniques for resolving construction contract disputes, including litigation, negotiation, arbitration, mediation, expert determination, dispute review boards, and rent-a-judge. It provides details on claims that commonly arise in construction projects and against owners or contractors. The best practices for preventing and resolving disputes involve using alternative dispute resolution methods like mediation early on and having a predetermined dispute resolution plan.
Early Dispute Resolution in the Construction IndustryFrancis Ho
The document discusses various alternative dispute resolution (ADR) methods for resolving construction disputes more efficiently than litigation. It describes problem-solving hierarchies, expert determination, dispute boards, and highlights advantages and disadvantages of each method. Problem-solving hierarchies allow issues to be referred to increasingly senior individuals until resolved, while expert determination and dispute boards utilize neutral experts to resolve technical or specialized issues more quickly than courts. However, no single ADR method is suitable for every dispute type.
Dispute Resolution Boards have proven highly effective (greater than 98% success rate) in resolving disputes in segments of the construction industry and preventing claims from going to arbitration or litigation. While more successful than all other non-binding alternatives, their use has been concentrated in specific project types and limited regions. Dispute and construction professionals will benefit from exploring the principles leading to success, and the practice will benefit from broader dissemination of this exciting method.
This document provides an overview of peer review for municipal planning projects. It defines peer review as evaluation of work by others in the same field to enhance quality. Reasons for hiring peer review consultants include lack of in-house expertise. Massachusetts General Law Chapter 44 Section 53G allows municipalities to use revolving funds from applicant fees to hire outside consultants. The document outlines best practices for engaging consultants, developing review processes and schedules, and the role and responsibilities of peer review consultants in reviewing documents and providing supplemental feedback. It also discusses relevant case law and tricks of the trade to conduct effective peer reviews.
Chapter_2-Procurement and Contract management.pptxssuserc0bf9b
The document discusses procurement and contract management. It defines procurement as the purchase of goods, services, or works at the best price, delivery date, and legal terms through a competitive bidding process. Contract management involves contract planning, procurement management, and contract administration. It aims to ensure fair competition and fair distribution of obligations and rights among stakeholders. The document outlines different types of procurement and contract delivery systems including force account, design-bid-build, and design-build. It provides details on the processes, roles, advantages, and disadvantages of each type.
The document discusses various types of construction contracts and tenders. It describes key elements like:
1. The main types of construction contracts include item rate contracts, lumpsum contracts, cost plus contracts, unit pricing contracts, and turnkey contracts.
2. Tenders can be open, selective, term or single tenders. The tendering process involves pre-tender planning, advertisement, submission, evaluation and awarding the tender.
3. Construction contracts are important documents that outline the scope of work, responsibilities, costs and timelines for projects. Key elements of valid contracts include agreement, consideration, competent parties and legal purpose.
Disputes can arise on construction projects from uncertainties, contractual issues, and behaviors. Common causes of disputes include delays, design errors, differing site conditions, and changes in requirements. Standard contracts provide dispute resolution processes that typically involve the engineer making a decision first, followed by negotiations, adjudication, and possibly arbitration. The best practices for resolving disputes emphasize preventing disputes, being flexible, intervening early, and using alternative dispute resolution methods.
Adriana Spassova presentation. Networking that was made jointly by DRBF and Artyushenko & Partners law firm (Kazakhstan) in Almaty (Kazakhstan) - DAB in Construction, April 25, 2018. Details are here https://a-p.legal/en/2018/05/01/report-on-our-networking-on-april-25-2018/
The staple of most construction contracts has embedded dispute resolution provisions. Learn what these are and how to apply these to expedite resolution of your dispute.
This document provides an overview of dispute resolution mechanisms in construction projects. It begins by defining what a dispute is and noting that disputes can cause projects to fail and for all parties to incur losses. The main causes of disputes are then outlined, including issues with payments, contract documentation, time and cost overruns, and construction information and supervision. Alternative dispute resolution mechanisms are introduced, including negotiation, mediation, dispute review boards, arbitration, and litigation. Each of these options is then described in one to three paragraphs detailing the key aspects and processes involved.
Architects are responsible for providing oversight during construction projects through site visits and meetings. They issue instructions to contractors to coordinate work, remedy issues, and authorize changes. Contractors must comply with written instructions from architects, but can object if they believe an instruction is invalid. Instructions may require variations that warrant cost estimates. Proper documentation of instructions helps avoid disputes over contractor responsibilities.
This was a presentation delivered by Robert Langley, partner and head of the construction and engineering team at Muckle LLP, on Tuesday 7th October. The event was organised and hosted by the APM North East branch and was entitled 'Project contracts and how they support collaborative working'. It was held at the Radisson Blu hotel in Durham.
The construction industry is a major employer that builds infrastructure through both public and private works using various financing methods. Projects involve owners, engineers/architects, and contractors related through contracts that can be delivered through design-bid-build, design-build, or turnkey approaches. The total cost of construction includes direct costs, overhead costs, and contractor profit that must be considered in selecting the appropriate construction method.
The document discusses various contracting strategies for terminal construction projects. It describes client managed construction, engineering procurement and construction (EPC) contracts with a single contractor, and using multiple package unit contracts. EPC contracts can be lump-sum turn-key, design and construct, or unit rates. Package units require more interfaces but allow negotiation. Engineering, procurement, and construction management is also discussed. Key factors in choosing a strategy include project complexity, risk allocation, budget and schedule certainty, and client influence.
The document discusses various contracting strategies for terminal construction projects. It describes client managed construction, engineering procurement and construction (EPC) contracts with a single contractor, and using multiple package unit contracts. EPC contracts can be lump-sum turn-key, design and construct, or unit rates. Package units require more interfaces but allow negotiation. EPC management is also discussed. Choosing a strategy depends on project size, complexity, budget risk tolerance, and design influence desired.
Tips for effective administration of a construction contract and for reducing the risk of delay and change orders. Interplay between the contractors, the consultant and an owner.
The document discusses contract administration processes and common issues that can lead to disputes such as deviations, claims, and breaches. It emphasizes the importance of clear documentation, communication, and dispute avoidance strategies. The document then outlines various alternative dispute resolution methods like negotiation, mediation, conciliation, and arbitration that can be used to resolve disputes without litigation. It provides details on the procedures, roles
Similar to DISPUTE REVIEW BOARDS -REASONS-NEED-METHODS-RESPONSIBILITIES-PROCESFUNCTIONS- ADVANTAGES AND DIS ADVANTAGES (20)
Embedded machine learning-based road conditions and driving behavior monitoringIJECEIAES
Car accident rates have increased in recent years, resulting in losses in human lives, properties, and other financial costs. An embedded machine learning-based system is developed to address this critical issue. The system can monitor road conditions, detect driving patterns, and identify aggressive driving behaviors. The system is based on neural networks trained on a comprehensive dataset of driving events, driving styles, and road conditions. The system effectively detects potential risks and helps mitigate the frequency and impact of accidents. The primary goal is to ensure the safety of drivers and vehicles. Collecting data involved gathering information on three key road events: normal street and normal drive, speed bumps, circular yellow speed bumps, and three aggressive driving actions: sudden start, sudden stop, and sudden entry. The gathered data is processed and analyzed using a machine learning system designed for limited power and memory devices. The developed system resulted in 91.9% accuracy, 93.6% precision, and 92% recall. The achieved inference time on an Arduino Nano 33 BLE Sense with a 32-bit CPU running at 64 MHz is 34 ms and requires 2.6 kB peak RAM and 139.9 kB program flash memory, making it suitable for resource-constrained embedded systems.
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsVictor Morales
K8sGPT is a tool that analyzes and diagnoses Kubernetes clusters. This presentation was used to share the requirements and dependencies to deploy K8sGPT in a local environment.
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...shadow0702a
This document serves as a comprehensive step-by-step guide on how to effectively use PyCharm for remote debugging of the Windows Subsystem for Linux (WSL) on a local Windows machine. It meticulously outlines several critical steps in the process, starting with the crucial task of enabling permissions, followed by the installation and configuration of WSL.
The guide then proceeds to explain how to set up the SSH service within the WSL environment, an integral part of the process. Alongside this, it also provides detailed instructions on how to modify the inbound rules of the Windows firewall to facilitate the process, ensuring that there are no connectivity issues that could potentially hinder the debugging process.
The document further emphasizes on the importance of checking the connection between the Windows and WSL environments, providing instructions on how to ensure that the connection is optimal and ready for remote debugging.
It also offers an in-depth guide on how to configure the WSL interpreter and files within the PyCharm environment. This is essential for ensuring that the debugging process is set up correctly and that the program can be run effectively within the WSL terminal.
Additionally, the document provides guidance on how to set up breakpoints for debugging, a fundamental aspect of the debugging process which allows the developer to stop the execution of their code at certain points and inspect their program at those stages.
Finally, the document concludes by providing a link to a reference blog. This blog offers additional information and guidance on configuring the remote Python interpreter in PyCharm, providing the reader with a well-rounded understanding of the process.
UNLOCKING HEALTHCARE 4.0: NAVIGATING CRITICAL SUCCESS FACTORS FOR EFFECTIVE I...amsjournal
The Fourth Industrial Revolution is transforming industries, including healthcare, by integrating digital,
physical, and biological technologies. This study examines the integration of 4.0 technologies into
healthcare, identifying success factors and challenges through interviews with 70 stakeholders from 33
countries. Healthcare is evolving significantly, with varied objectives across nations aiming to improve
population health. The study explores stakeholders' perceptions on critical success factors, identifying
challenges such as insufficiently trained personnel, organizational silos, and structural barriers to data
exchange. Facilitators for integration include cost reduction initiatives and interoperability policies.
Technologies like IoT, Big Data, AI, Machine Learning, and robotics enhance diagnostics, treatment
precision, and real-time monitoring, reducing errors and optimizing resource utilization. Automation
improves employee satisfaction and patient care, while Blockchain and telemedicine drive cost reductions.
Successful integration requires skilled professionals and supportive policies, promising efficient resource
use, lower error rates, and accelerated processes, leading to optimized global healthcare outcomes.
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTjpsjournal1
The rivalry between prominent international actors for dominance over Central Asia's hydrocarbon
reserves and the ancient silk trade route, along with China's diplomatic endeavours in the area, has been
referred to as the "New Great Game." This research centres on the power struggle, considering
geopolitical, geostrategic, and geoeconomic variables. Topics including trade, political hegemony, oil
politics, and conventional and nontraditional security are all explored and explained by the researcher.
Using Mackinder's Heartland, Spykman Rimland, and Hegemonic Stability theories, examines China's role
in Central Asia. This study adheres to the empirical epistemological method and has taken care of
objectivity. This study analyze primary and secondary research documents critically to elaborate role of
china’s geo economic outreach in central Asian countries and its future prospect. China is thriving in trade,
pipeline politics, and winning states, according to this study, thanks to important instruments like the
Shanghai Cooperation Organisation and the Belt and Road Economic Initiative. According to this study,
China is seeing significant success in commerce, pipeline politics, and gaining influence on other
governments. This success may be attributed to the effective utilisation of key tools such as the Shanghai
Cooperation Organisation and the Belt and Road Economic Initiative.
International Conference on NLP, Artificial Intelligence, Machine Learning an...gerogepatton
International Conference on NLP, Artificial Intelligence, Machine Learning and Applications (NLAIM 2024) offers a premier global platform for exchanging insights and findings in the theory, methodology, and applications of NLP, Artificial Intelligence, Machine Learning, and their applications. The conference seeks substantial contributions across all key domains of NLP, Artificial Intelligence, Machine Learning, and their practical applications, aiming to foster both theoretical advancements and real-world implementations. With a focus on facilitating collaboration between researchers and practitioners from academia and industry, the conference serves as a nexus for sharing the latest developments in the field.
Literature Review Basics and Understanding Reference Management.pptxDr Ramhari Poudyal
Three-day training on academic research focuses on analytical tools at United Technical College, supported by the University Grant Commission, Nepal. 24-26 May 2024
Advanced control scheme of doubly fed induction generator for wind turbine us...IJECEIAES
This paper describes a speed control device for generating electrical energy on an electricity network based on the doubly fed induction generator (DFIG) used for wind power conversion systems. At first, a double-fed induction generator model was constructed. A control law is formulated to govern the flow of energy between the stator of a DFIG and the energy network using three types of controllers: proportional integral (PI), sliding mode controller (SMC) and second order sliding mode controller (SOSMC). Their different results in terms of power reference tracking, reaction to unexpected speed fluctuations, sensitivity to perturbations, and resilience against machine parameter alterations are compared. MATLAB/Simulink was used to conduct the simulations for the preceding study. Multiple simulations have shown very satisfying results, and the investigations demonstrate the efficacy and power-enhancing capabilities of the suggested control system.
Advanced control scheme of doubly fed induction generator for wind turbine us...
DISPUTE REVIEW BOARDS -REASONS-NEED-METHODS-RESPONSIBILITIES-PROCESFUNCTIONS- ADVANTAGES AND DIS ADVANTAGES
1. CN2114- CONTRACT LAWS AND REGULATIONS
SRM UNIVERSITY
Kattankulathur, Chennai – 603203
A presentation on
DISPUTE REVIEW BOARDS
By
T.Surya Prakash reddy - RA1612002010030
CONTACT NO 8008916165
2. REASONS FOR ALTERNATE DISPUTE
RESOLUTION
1. Variation in the quantities of work
2. Payment of rates for the excess/ extra quantities
3. Interpretation of the contract drawings and designs
4. Sub soil classification
5. Quantum of de-watering during excavation
6. Quality of work and workmanship
7. Time of performance and extensions
8. Delays in performance of the contract due to faults of the
owner/engineer
9. Delay in the performance due to faults on the part of the
contractor
10. Delay in getting possession of the site work and its actual
release
11. Delay in making due payment to the contractor
12. Decisions as regards the delay falling within the scope
13. Refund and failure of security deposit
14. Quality of materials used
3. NEED OF ADR
• The number of litigation in civil is rising at an
alarming rate.
• The resources to deal with cases in the courts are
also very limited.
• The number of judges and court rooms are also
not sufficient.
• We have to spend a considerable portion of funds
to meet with the costs of litigation and for
payment to lawyers.
• The procedure is cumbersome and involves loss of
time.
• Money spent on fighting court cases and paying
fees to lawyers can be utilized for the best
interests of the beneficiaries of developmental
activities.
4. NEED OF ADR…….Contd
• It is therefore, high time, that some systems and
methods of alternative dispute resolution are
developed, so that the disputes can be decided during
process of the execution of the work/project by way,
of mutual understanding and necessarily not after the
disputes are placed before the arbitrator.
6. AIM/RESPONSIBILITIES OF DRB
• Reduction in court over crowding.
• Lowering of barriers to access.
• Achievement of superior resolution.
• Injecting power into local communities to
handle their own disputes.
• Reduction of costs.
• Production of a less contentious society by
adopting a process of resolution by effective
use of mediation, arbitration and various
composite techniques.
7. DISPUTE REVIEW BOARDS
• The DRB method of dispute resolution was developed by the
committee on contracting practices of the underground technology
research council of ASCE.
• For major engineering projects, the method of dispute review and
resolution boards sounds to be the most appropriate method.
• This consists of appointing a high level body, consisting of the
representatives of the owner/engineer as well the contracting
agency.
• The board also includes the Project managers of different
professions concerned with the implementation of the project as
well as representative of the contractor.
• Professional and legal experts who are not a part of the project
organization, can also be made member of the dispute resolution
board(DRB).
8. • The DRB should be appointed right at the time of the commencement of
the project and award of contracts.
• A specific clause should be prescribed in the contract stating all disputes
relating to the contract shall be put up to the DRB and the decision of the
board shall be final and binding to all the parties to a contract.
• The DRB comprises three members: one selected by the owner, one by the
contractor, and a third selected by the first two.
• All DRB members are impartial and experienced in construction. They are
appointed soon after the contract is awarded
• DRB members are sent progress reports and visit the project periodically.
• The DRB is not used for routine claims or differences of opinion, but for
the resolution of major problems.
• The recommendations of the DRB are not legally binding, but are not
likely to be reversed in litigation.
9. PROCESS OF DRB
• The DRB operates under rules specified in the contract. Usually these rules
are the rules of a nominating authority such as the National Technology
Dispute Centre.
• At the commencement of the project, the DRB meets and is provided with
sufficient project documentation to enable them to become familiar with the
project deliverables, schedules, budgets, risks and issues. The DRB meets on
a regular basis, usually on site and usually with representatives from the
parties’ project teams.
• When a dispute or issue is referred to the DRB, the DRB considers the
dispute and makes a recommendation. Unless a party objects within a set
period of time, the recommendation becomes binding under the contract.
• If a party objects the dispute may be referred to other resolution mechanisms,
usually litigation. The recommendations of a DRB are usually “with
prejudice”. That is, the recommendations can be used by a party during
litigation.
10. COST OF DRB
• There are two costs associated with a DRB.
• The first is the initial set up cost. This provides the
parties with the structure within which to establish the
DRB. The set up cost includes a license to use the DRB
Rules, the clauses to add into a contract and a
nominating authority to appoint members if the parties
can not.
• The second cost is the monthly retainer for each DRB
member. For most large projects this is equivalent to 2-
3 man days for each member per month. For smaller
projects it can be as low as 1 man day for each member
per month.
11. FUNCTIONS OF DRB
• The primary function of a Dispute Board is to assist the parties to avoid disputes if possible
by facilitating and improving communication and encouraging the resolution of
contentious issues by the parties at the job level before they become disputes, or if not, to
assist them to resolve disputes quickly and cost effectively without the need for arbitration
or litigation.
• The DRB shall serve as an advisory body to assist in the resolution of disputes between
the State and the Contractor, hereinafter referred to as the "parties."
• The DRB can be made to meet at regular periodical intervals to review the activities
relating to the contracts and also discuss and decide the issues which are likely to result
into disputes.
• This would help in solving the problems before the actual disputes, both the parties i.e the
Engineer in charge and the contractor can put up their views and claims before the DRB.
• The board, after hearing the views put up by both parties and its own evaluation and
examination of relevant materials on record, can take a final decision leading to the
resolution of dispute.
12. In case of government and public sector organizations DRB’s can be
constituted at various levels.
1.For small projects at district level
a) District collector – Chairman
b)Concerned executive engineer – Member
c) Other executive engineer – Member
d) Representative of the contractor – Member
2.For medium and regional level projects
a) Concerned Chief engineer – Chairman
b)Concerned superintending engineer – Member
c) One other superintending engineer – Member
d) One outside expert – Member
d) Representative of the contractor – Member
3.At state level and for major projects
a) Chief executive of the organization – Chairman
b)Financial advisor/controller – Member
c) Engineer in chief – Member
d) Two senior outside experts – Members
(one to be nominated by contractor)
d) Representative of the contractor – Member
13. ADVANTAGES OF DISPUTES REVIEW BOARDS
• The DRB hears disputes on an informal basis and can provide
recommendations for their timely resolution before parties
adopt hard positions leading to litigation.
• The parties are comfortable with the recommendations of the
DRB since the selection of the DRB members is controlled by
the owner and the contractor.
• Because they meet periodically and they are sent progress
reports, the DRB members are familiar with the elements of the
project.
• Although the DRB recommendations are not binding on either
party, there is strong motivation to accept the findings
14. DISADVANTAGES OF DISPUTES REVIEW
BOARDS
• The impartiality and conflict-of- interest portion of the
DRB specification is so tough that sometimes there are
not enough qualified people for the DRB.
• The project must be large enough, and the probability of
the occurrence of disputes throughout the course of the
project must be high enough to justify the expense of
retaining the services of the DRB members for the entire
duration of the project.
15. LIMITATIONS OF DISPUTE REVIEW BOARDS
•DRBs add expense but not add value to the project
•presence of bias or lack of qualifications in Board
members
•DRBs impose personal equity rather than contract
provisions
•presence of a DRB will promote claims
•DRBs are unreliable because they lack the formalities of
legal proceedings
•historical culture of “power & control”
•expectation of a binding decision
•in high value disputes, losing party motivated to try
litigation
•parties may undermine the DRB process
16. CONCLUSION
• Alternate dispute resolution mechanism
will relieve us from the tedious court
procedures and defects of arbitration.
• It would save both National time and
National costs.