SlideShare a Scribd company logo
CN2114- CONTRACT LAWS AND REGULATIONS
SRM UNIVERSITY
Kattankulathur, Chennai – 603203
A presentation on
DISPUTE REVIEW BOARDS
By
T.Surya Prakash reddy - RA1612002010030
CONTACT NO 8008916165
REASONS FOR ALTERNATE DISPUTE
RESOLUTION
1. Variation in the quantities of work
2. Payment of rates for the excess/ extra quantities
3. Interpretation of the contract drawings and designs
4. Sub soil classification
5. Quantum of de-watering during excavation
6. Quality of work and workmanship
7. Time of performance and extensions
8. Delays in performance of the contract due to faults of the
owner/engineer
9. Delay in the performance due to faults on the part of the
contractor
10. Delay in getting possession of the site work and its actual
release
11. Delay in making due payment to the contractor
12. Decisions as regards the delay falling within the scope
13. Refund and failure of security deposit
14. Quality of materials used
NEED OF ADR
• The number of litigation in civil is rising at an
alarming rate.
• The resources to deal with cases in the courts are
also very limited.
• The number of judges and court rooms are also
not sufficient.
• We have to spend a considerable portion of funds
to meet with the costs of litigation and for
payment to lawyers.
• The procedure is cumbersome and involves loss of
time.
• Money spent on fighting court cases and paying
fees to lawyers can be utilized for the best
interests of the beneficiaries of developmental
activities.
NEED OF ADR…….Contd
• It is therefore, high time, that some systems and
methods of alternative dispute resolution are
developed, so that the disputes can be decided during
process of the execution of the work/project by way,
of mutual understanding and necessarily not after the
disputes are placed before the arbitrator.
METHODS OF ALTERNATE DISPUTE
RESOLUTION
1. Advisory Arbitration
2. Dispute review boards (DRB)
3. Conciliation
4. Executive tribunal
5. Expert appraisal
6. Negotiations
AIM/RESPONSIBILITIES OF DRB
• Reduction in court over crowding.
• Lowering of barriers to access.
• Achievement of superior resolution.
• Injecting power into local communities to
handle their own disputes.
• Reduction of costs.
• Production of a less contentious society by
adopting a process of resolution by effective
use of mediation, arbitration and various
composite techniques.
DISPUTE REVIEW BOARDS
• The DRB method of dispute resolution was developed by the
committee on contracting practices of the underground technology
research council of ASCE.
• For major engineering projects, the method of dispute review and
resolution boards sounds to be the most appropriate method.
• This consists of appointing a high level body, consisting of the
representatives of the owner/engineer as well the contracting
agency.
• The board also includes the Project managers of different
professions concerned with the implementation of the project as
well as representative of the contractor.
• Professional and legal experts who are not a part of the project
organization, can also be made member of the dispute resolution
board(DRB).
• The DRB should be appointed right at the time of the commencement of
the project and award of contracts.
• A specific clause should be prescribed in the contract stating all disputes
relating to the contract shall be put up to the DRB and the decision of the
board shall be final and binding to all the parties to a contract.
• The DRB comprises three members: one selected by the owner, one by the
contractor, and a third selected by the first two.
• All DRB members are impartial and experienced in construction. They are
appointed soon after the contract is awarded
• DRB members are sent progress reports and visit the project periodically.
• The DRB is not used for routine claims or differences of opinion, but for
the resolution of major problems.
• The recommendations of the DRB are not legally binding, but are not
likely to be reversed in litigation.
PROCESS OF DRB
• The DRB operates under rules specified in the contract. Usually these rules
are the rules of a nominating authority such as the National Technology
Dispute Centre.
• At the commencement of the project, the DRB meets and is provided with
sufficient project documentation to enable them to become familiar with the
project deliverables, schedules, budgets, risks and issues. The DRB meets on
a regular basis, usually on site and usually with representatives from the
parties’ project teams.
• When a dispute or issue is referred to the DRB, the DRB considers the
dispute and makes a recommendation. Unless a party objects within a set
period of time, the recommendation becomes binding under the contract.
• If a party objects the dispute may be referred to other resolution mechanisms,
usually litigation. The recommendations of a DRB are usually “with
prejudice”. That is, the recommendations can be used by a party during
litigation.
COST OF DRB
• There are two costs associated with a DRB.
• The first is the initial set up cost. This provides the
parties with the structure within which to establish the
DRB. The set up cost includes a license to use the DRB
Rules, the clauses to add into a contract and a
nominating authority to appoint members if the parties
can not.
• The second cost is the monthly retainer for each DRB
member. For most large projects this is equivalent to 2-
3 man days for each member per month. For smaller
projects it can be as low as 1 man day for each member
per month.
FUNCTIONS OF DRB
• The primary function of a Dispute Board is to assist the parties to avoid disputes if possible
by facilitating and improving communication and encouraging the resolution of
contentious issues by the parties at the job level before they become disputes, or if not, to
assist them to resolve disputes quickly and cost effectively without the need for arbitration
or litigation.
• The DRB shall serve as an advisory body to assist in the resolution of disputes between
the State and the Contractor, hereinafter referred to as the "parties."
• The DRB can be made to meet at regular periodical intervals to review the activities
relating to the contracts and also discuss and decide the issues which are likely to result
into disputes.
• This would help in solving the problems before the actual disputes, both the parties i.e the
Engineer in charge and the contractor can put up their views and claims before the DRB.
• The board, after hearing the views put up by both parties and its own evaluation and
examination of relevant materials on record, can take a final decision leading to the
resolution of dispute.
In case of government and public sector organizations DRB’s can be
constituted at various levels.
1.For small projects at district level
a) District collector – Chairman
b)Concerned executive engineer – Member
c) Other executive engineer – Member
d) Representative of the contractor – Member
2.For medium and regional level projects
a) Concerned Chief engineer – Chairman
b)Concerned superintending engineer – Member
c) One other superintending engineer – Member
d) One outside expert – Member
d) Representative of the contractor – Member
3.At state level and for major projects
a) Chief executive of the organization – Chairman
b)Financial advisor/controller – Member
c) Engineer in chief – Member
d) Two senior outside experts – Members
(one to be nominated by contractor)
d) Representative of the contractor – Member
ADVANTAGES OF DISPUTES REVIEW BOARDS
• The DRB hears disputes on an informal basis and can provide
recommendations for their timely resolution before parties
adopt hard positions leading to litigation.
• The parties are comfortable with the recommendations of the
DRB since the selection of the DRB members is controlled by
the owner and the contractor.
• Because they meet periodically and they are sent progress
reports, the DRB members are familiar with the elements of the
project.
• Although the DRB recommendations are not binding on either
party, there is strong motivation to accept the findings
DISADVANTAGES OF DISPUTES REVIEW
BOARDS
• The impartiality and conflict-of- interest portion of the
DRB specification is so tough that sometimes there are
not enough qualified people for the DRB.
• The project must be large enough, and the probability of
the occurrence of disputes throughout the course of the
project must be high enough to justify the expense of
retaining the services of the DRB members for the entire
duration of the project.
LIMITATIONS OF DISPUTE REVIEW BOARDS
•DRBs add expense but not add value to the project
•presence of bias or lack of qualifications in Board
members
•DRBs impose personal equity rather than contract
provisions
•presence of a DRB will promote claims
•DRBs are unreliable because they lack the formalities of
legal proceedings
•historical culture of “power & control”
•expectation of a binding decision
•in high value disputes, losing party motivated to try
litigation
•parties may undermine the DRB process
CONCLUSION
• Alternate dispute resolution mechanism
will relieve us from the tedious court
procedures and defects of arbitration.
• It would save both National time and
National costs.
DISPUTE REVIEW BOARDS -REASONS-NEED-METHODS-RESPONSIBILITIES-PROCESFUNCTIONS- ADVANTAGES AND DIS ADVANTAGES

More Related Content

What's hot

Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
AYM1979
 
BIDDING-TENDER-CONTRACT
BIDDING-TENDER-CONTRACTBIDDING-TENDER-CONTRACT
BIDDING-TENDER-CONTRACT
VISHNU VIJAYAN
 
Construction Project Management
Construction Project Management Construction Project Management
Construction Project Management
Rajat Nainwal
 
Tender procedure slide
Tender procedure slideTender procedure slide
Tender procedure slide
politeknik malaysia
 
Construction Claims
Construction ClaimsConstruction Claims
Construction Claims
Rajesh Sharma
 
QUANTITY SURVEYING
QUANTITY SURVEYINGQUANTITY SURVEYING
QUANTITY SURVEYING
lizwi nyandu
 
Module 4 lecture 1
Module  4 lecture 1Module  4 lecture 1
Module 4 lecture 1
Shashi Kumara
 
Construction Claims Explained
Construction Claims ExplainedConstruction Claims Explained
Construction Claims Explained
claimsconsultancy
 
Types of contract
Types of contractTypes of contract
Types of contract
HarshalNarkhede7
 
Construction tender process
Construction tender processConstruction tender process
FIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshopFIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshop
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Types of Contract in Construction Management
Types of Contract in Construction ManagementTypes of Contract in Construction Management
Types of Contract in Construction Management
Shahin MB
 
Fidic Form of Contract.
Fidic Form of Contract.Fidic Form of Contract.
Fidic Form of Contract.
Shantanu Kumar Behera
 
Types of contracts
Types of contractsTypes of contracts
Types of contracts
Tulsi Pokhrel
 
Tendering documentation
Tendering documentationTendering documentation
Tendering documentation
nipuna_bopage
 
Conditions Of Contract
Conditions Of ContractConditions Of Contract
Conditions Of Contract
guestdb5e498
 
Contracts and-tenders
Contracts and-tendersContracts and-tenders
Contracts and-tenders
Archistudent Portal
 
Build,Operate,Own,Transfer (BOOT)
Build,Operate,Own,Transfer (BOOT)Build,Operate,Own,Transfer (BOOT)
Build,Operate,Own,Transfer (BOOT)
Mohd. Ikhwan
 
The Basics of Tendering & Bidding
The Basics of Tendering & BiddingThe Basics of Tendering & Bidding
The Basics of Tendering & Bidding
Moatasem Mabrouk
 
Fidic law1
Fidic law1Fidic law1
Fidic law1
dhiraj.gaur
 

What's hot (20)

Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
 
BIDDING-TENDER-CONTRACT
BIDDING-TENDER-CONTRACTBIDDING-TENDER-CONTRACT
BIDDING-TENDER-CONTRACT
 
Construction Project Management
Construction Project Management Construction Project Management
Construction Project Management
 
Tender procedure slide
Tender procedure slideTender procedure slide
Tender procedure slide
 
Construction Claims
Construction ClaimsConstruction Claims
Construction Claims
 
QUANTITY SURVEYING
QUANTITY SURVEYINGQUANTITY SURVEYING
QUANTITY SURVEYING
 
Module 4 lecture 1
Module  4 lecture 1Module  4 lecture 1
Module 4 lecture 1
 
Construction Claims Explained
Construction Claims ExplainedConstruction Claims Explained
Construction Claims Explained
 
Types of contract
Types of contractTypes of contract
Types of contract
 
Construction tender process
Construction tender processConstruction tender process
Construction tender process
 
FIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshopFIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshop
 
Types of Contract in Construction Management
Types of Contract in Construction ManagementTypes of Contract in Construction Management
Types of Contract in Construction Management
 
Fidic Form of Contract.
Fidic Form of Contract.Fidic Form of Contract.
Fidic Form of Contract.
 
Types of contracts
Types of contractsTypes of contracts
Types of contracts
 
Tendering documentation
Tendering documentationTendering documentation
Tendering documentation
 
Conditions Of Contract
Conditions Of ContractConditions Of Contract
Conditions Of Contract
 
Contracts and-tenders
Contracts and-tendersContracts and-tenders
Contracts and-tenders
 
Build,Operate,Own,Transfer (BOOT)
Build,Operate,Own,Transfer (BOOT)Build,Operate,Own,Transfer (BOOT)
Build,Operate,Own,Transfer (BOOT)
 
The Basics of Tendering & Bidding
The Basics of Tendering & BiddingThe Basics of Tendering & Bidding
The Basics of Tendering & Bidding
 
Fidic law1
Fidic law1Fidic law1
Fidic law1
 

Similar to DISPUTE REVIEW BOARDS -REASONS-NEED-METHODS-RESPONSIBILITIES-PROCESFUNCTIONS- ADVANTAGES AND DIS ADVANTAGES

Construction disputes
Construction disputesConstruction disputes
Construction disputes
gayathrysatheesan1
 
Civil engineering practice (lec 5)
Civil engineering practice (lec 5)Civil engineering practice (lec 5)
Civil engineering practice (lec 5)
Muhammad Khan
 
Early Dispute Resolution in the Construction Industry
Early Dispute Resolution in the Construction IndustryEarly Dispute Resolution in the Construction Industry
Early Dispute Resolution in the Construction Industry
Francis Ho
 
Dispute Resolution Boards (DRBs): Effective Resolution in the Construction In...
Dispute Resolution Boards (DRBs): Effective Resolution in the Construction In...Dispute Resolution Boards (DRBs): Effective Resolution in the Construction In...
Dispute Resolution Boards (DRBs): Effective Resolution in the Construction In...
Association for Conflict Resolution (ACR)
 
Peer Review and "53 G"
Peer Review and "53 G"Peer Review and "53 G"
Chapter_2-Procurement and Contract management.pptx
Chapter_2-Procurement and Contract management.pptxChapter_2-Procurement and Contract management.pptx
Chapter_2-Procurement and Contract management.pptx
ssuserc0bf9b
 
Construction management contract management dispute
Construction management  contract management  disputeConstruction management  contract management  dispute
Construction management contract management dispute
JanakrajJoshi12
 
Unit V - Contracts.pptx
Unit V - Contracts.pptxUnit V - Contracts.pptx
Unit V - Contracts.pptx
jairam131
 
PECDisputeResolution25102018.pptx
PECDisputeResolution25102018.pptxPECDisputeResolution25102018.pptx
PECDisputeResolution25102018.pptx
IrfanAwan25
 
01 drbf event almaty 2018 adriana eng
01 drbf event almaty 2018 adriana eng01 drbf event almaty 2018 adriana eng
01 drbf event almaty 2018 adriana eng
Andrey Artyushenko
 
CCDC 2 Dispute Resolution
CCDC 2 Dispute ResolutionCCDC 2 Dispute Resolution
CCDC 2 Dispute Resolution
Gerald R. (Jerry) Genge
 
Chapter 4 [compatibility mode]
Chapter 4 [compatibility mode]Chapter 4 [compatibility mode]
Chapter 4 [compatibility mode]
Delhi Technological University
 
Professional Practice for Architecture II
Professional Practice for Architecture IIProfessional Practice for Architecture II
Professional Practice for Architecture II
Ar. Mukunda K.S
 
Muckle LLP - Which contract should I be using?
Muckle LLP - Which contract should I be using?Muckle LLP - Which contract should I be using?
Muckle LLP - Which contract should I be using?
Association for Project Management
 
Lecture 1.pptx
Lecture 1.pptxLecture 1.pptx
Lecture 1.pptx
Abadit Tadesse
 
Contracting strategies for_terminal_construction
Contracting strategies for_terminal_constructionContracting strategies for_terminal_construction
Contracting strategies for_terminal_construction
drs. ing. George van Bommel MBE, BSc
 
Contracting strategies for_terminal_construction
Contracting strategies for_terminal_constructionContracting strategies for_terminal_construction
Contracting strategies for_terminal_construction
drs. ing. George van Bommel MBE, BSc
 
Waste Contracts Administration and Performance Monitoring
Waste Contracts Administration and Performance MonitoringWaste Contracts Administration and Performance Monitoring
Waste Contracts Administration and Performance Monitoring
Circular Economy Asia
 
Effective contract administration may 2014
Effective contract administration may 2014Effective contract administration may 2014
Effective contract administration may 2014
SHKLaw
 
CONTRACT ADMINISTRATION Updated.pptx
CONTRACT ADMINISTRATION Updated.pptxCONTRACT ADMINISTRATION Updated.pptx
CONTRACT ADMINISTRATION Updated.pptx
Aditya Mane
 

Similar to DISPUTE REVIEW BOARDS -REASONS-NEED-METHODS-RESPONSIBILITIES-PROCESFUNCTIONS- ADVANTAGES AND DIS ADVANTAGES (20)

Construction disputes
Construction disputesConstruction disputes
Construction disputes
 
Civil engineering practice (lec 5)
Civil engineering practice (lec 5)Civil engineering practice (lec 5)
Civil engineering practice (lec 5)
 
Early Dispute Resolution in the Construction Industry
Early Dispute Resolution in the Construction IndustryEarly Dispute Resolution in the Construction Industry
Early Dispute Resolution in the Construction Industry
 
Dispute Resolution Boards (DRBs): Effective Resolution in the Construction In...
Dispute Resolution Boards (DRBs): Effective Resolution in the Construction In...Dispute Resolution Boards (DRBs): Effective Resolution in the Construction In...
Dispute Resolution Boards (DRBs): Effective Resolution in the Construction In...
 
Peer Review and "53 G"
Peer Review and "53 G"Peer Review and "53 G"
Peer Review and "53 G"
 
Chapter_2-Procurement and Contract management.pptx
Chapter_2-Procurement and Contract management.pptxChapter_2-Procurement and Contract management.pptx
Chapter_2-Procurement and Contract management.pptx
 
Construction management contract management dispute
Construction management  contract management  disputeConstruction management  contract management  dispute
Construction management contract management dispute
 
Unit V - Contracts.pptx
Unit V - Contracts.pptxUnit V - Contracts.pptx
Unit V - Contracts.pptx
 
PECDisputeResolution25102018.pptx
PECDisputeResolution25102018.pptxPECDisputeResolution25102018.pptx
PECDisputeResolution25102018.pptx
 
01 drbf event almaty 2018 adriana eng
01 drbf event almaty 2018 adriana eng01 drbf event almaty 2018 adriana eng
01 drbf event almaty 2018 adriana eng
 
CCDC 2 Dispute Resolution
CCDC 2 Dispute ResolutionCCDC 2 Dispute Resolution
CCDC 2 Dispute Resolution
 
Chapter 4 [compatibility mode]
Chapter 4 [compatibility mode]Chapter 4 [compatibility mode]
Chapter 4 [compatibility mode]
 
Professional Practice for Architecture II
Professional Practice for Architecture IIProfessional Practice for Architecture II
Professional Practice for Architecture II
 
Muckle LLP - Which contract should I be using?
Muckle LLP - Which contract should I be using?Muckle LLP - Which contract should I be using?
Muckle LLP - Which contract should I be using?
 
Lecture 1.pptx
Lecture 1.pptxLecture 1.pptx
Lecture 1.pptx
 
Contracting strategies for_terminal_construction
Contracting strategies for_terminal_constructionContracting strategies for_terminal_construction
Contracting strategies for_terminal_construction
 
Contracting strategies for_terminal_construction
Contracting strategies for_terminal_constructionContracting strategies for_terminal_construction
Contracting strategies for_terminal_construction
 
Waste Contracts Administration and Performance Monitoring
Waste Contracts Administration and Performance MonitoringWaste Contracts Administration and Performance Monitoring
Waste Contracts Administration and Performance Monitoring
 
Effective contract administration may 2014
Effective contract administration may 2014Effective contract administration may 2014
Effective contract administration may 2014
 
CONTRACT ADMINISTRATION Updated.pptx
CONTRACT ADMINISTRATION Updated.pptxCONTRACT ADMINISTRATION Updated.pptx
CONTRACT ADMINISTRATION Updated.pptx
 

Recently uploaded

BRAIN TUMOR DETECTION for seminar ppt.pdf
BRAIN TUMOR DETECTION for seminar ppt.pdfBRAIN TUMOR DETECTION for seminar ppt.pdf
BRAIN TUMOR DETECTION for seminar ppt.pdf
LAXMAREDDY22
 
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by AnantLLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
Anant Corporation
 
Curve Fitting in Numerical Methods Regression
Curve Fitting in Numerical Methods RegressionCurve Fitting in Numerical Methods Regression
Curve Fitting in Numerical Methods Regression
Nada Hikmah
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
IJECEIAES
 
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
Yasser Mahgoub
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
Victor Morales
 
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have oneISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
Las Vegas Warehouse
 
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
shadow0702a
 
UNLOCKING HEALTHCARE 4.0: NAVIGATING CRITICAL SUCCESS FACTORS FOR EFFECTIVE I...
UNLOCKING HEALTHCARE 4.0: NAVIGATING CRITICAL SUCCESS FACTORS FOR EFFECTIVE I...UNLOCKING HEALTHCARE 4.0: NAVIGATING CRITICAL SUCCESS FACTORS FOR EFFECTIVE I...
UNLOCKING HEALTHCARE 4.0: NAVIGATING CRITICAL SUCCESS FACTORS FOR EFFECTIVE I...
amsjournal
 
Engineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdfEngineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdf
abbyasa1014
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
jpsjournal1
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
MDSABBIROJJAMANPAYEL
 
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
ecqow
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
gerogepatton
 
Transformers design and coooling methods
Transformers design and coooling methodsTransformers design and coooling methods
Transformers design and coooling methods
Roger Rozario
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
kandramariana6
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
Dr Ramhari Poudyal
 
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
MIGUELANGEL966976
 
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
171ticu
 
Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
IJECEIAES
 

Recently uploaded (20)

BRAIN TUMOR DETECTION for seminar ppt.pdf
BRAIN TUMOR DETECTION for seminar ppt.pdfBRAIN TUMOR DETECTION for seminar ppt.pdf
BRAIN TUMOR DETECTION for seminar ppt.pdf
 
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by AnantLLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
 
Curve Fitting in Numerical Methods Regression
Curve Fitting in Numerical Methods RegressionCurve Fitting in Numerical Methods Regression
Curve Fitting in Numerical Methods Regression
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
 
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
 
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have oneISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
 
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
 
UNLOCKING HEALTHCARE 4.0: NAVIGATING CRITICAL SUCCESS FACTORS FOR EFFECTIVE I...
UNLOCKING HEALTHCARE 4.0: NAVIGATING CRITICAL SUCCESS FACTORS FOR EFFECTIVE I...UNLOCKING HEALTHCARE 4.0: NAVIGATING CRITICAL SUCCESS FACTORS FOR EFFECTIVE I...
UNLOCKING HEALTHCARE 4.0: NAVIGATING CRITICAL SUCCESS FACTORS FOR EFFECTIVE I...
 
Engineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdfEngineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdf
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
 
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
 
Transformers design and coooling methods
Transformers design and coooling methodsTransformers design and coooling methods
Transformers design and coooling methods
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
 
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
 
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
 
Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
 

DISPUTE REVIEW BOARDS -REASONS-NEED-METHODS-RESPONSIBILITIES-PROCESFUNCTIONS- ADVANTAGES AND DIS ADVANTAGES

  • 1. CN2114- CONTRACT LAWS AND REGULATIONS SRM UNIVERSITY Kattankulathur, Chennai – 603203 A presentation on DISPUTE REVIEW BOARDS By T.Surya Prakash reddy - RA1612002010030 CONTACT NO 8008916165
  • 2. REASONS FOR ALTERNATE DISPUTE RESOLUTION 1. Variation in the quantities of work 2. Payment of rates for the excess/ extra quantities 3. Interpretation of the contract drawings and designs 4. Sub soil classification 5. Quantum of de-watering during excavation 6. Quality of work and workmanship 7. Time of performance and extensions 8. Delays in performance of the contract due to faults of the owner/engineer 9. Delay in the performance due to faults on the part of the contractor 10. Delay in getting possession of the site work and its actual release 11. Delay in making due payment to the contractor 12. Decisions as regards the delay falling within the scope 13. Refund and failure of security deposit 14. Quality of materials used
  • 3. NEED OF ADR • The number of litigation in civil is rising at an alarming rate. • The resources to deal with cases in the courts are also very limited. • The number of judges and court rooms are also not sufficient. • We have to spend a considerable portion of funds to meet with the costs of litigation and for payment to lawyers. • The procedure is cumbersome and involves loss of time. • Money spent on fighting court cases and paying fees to lawyers can be utilized for the best interests of the beneficiaries of developmental activities.
  • 4. NEED OF ADR…….Contd • It is therefore, high time, that some systems and methods of alternative dispute resolution are developed, so that the disputes can be decided during process of the execution of the work/project by way, of mutual understanding and necessarily not after the disputes are placed before the arbitrator.
  • 5. METHODS OF ALTERNATE DISPUTE RESOLUTION 1. Advisory Arbitration 2. Dispute review boards (DRB) 3. Conciliation 4. Executive tribunal 5. Expert appraisal 6. Negotiations
  • 6. AIM/RESPONSIBILITIES OF DRB • Reduction in court over crowding. • Lowering of barriers to access. • Achievement of superior resolution. • Injecting power into local communities to handle their own disputes. • Reduction of costs. • Production of a less contentious society by adopting a process of resolution by effective use of mediation, arbitration and various composite techniques.
  • 7. DISPUTE REVIEW BOARDS • The DRB method of dispute resolution was developed by the committee on contracting practices of the underground technology research council of ASCE. • For major engineering projects, the method of dispute review and resolution boards sounds to be the most appropriate method. • This consists of appointing a high level body, consisting of the representatives of the owner/engineer as well the contracting agency. • The board also includes the Project managers of different professions concerned with the implementation of the project as well as representative of the contractor. • Professional and legal experts who are not a part of the project organization, can also be made member of the dispute resolution board(DRB).
  • 8. • The DRB should be appointed right at the time of the commencement of the project and award of contracts. • A specific clause should be prescribed in the contract stating all disputes relating to the contract shall be put up to the DRB and the decision of the board shall be final and binding to all the parties to a contract. • The DRB comprises three members: one selected by the owner, one by the contractor, and a third selected by the first two. • All DRB members are impartial and experienced in construction. They are appointed soon after the contract is awarded • DRB members are sent progress reports and visit the project periodically. • The DRB is not used for routine claims or differences of opinion, but for the resolution of major problems. • The recommendations of the DRB are not legally binding, but are not likely to be reversed in litigation.
  • 9. PROCESS OF DRB • The DRB operates under rules specified in the contract. Usually these rules are the rules of a nominating authority such as the National Technology Dispute Centre. • At the commencement of the project, the DRB meets and is provided with sufficient project documentation to enable them to become familiar with the project deliverables, schedules, budgets, risks and issues. The DRB meets on a regular basis, usually on site and usually with representatives from the parties’ project teams. • When a dispute or issue is referred to the DRB, the DRB considers the dispute and makes a recommendation. Unless a party objects within a set period of time, the recommendation becomes binding under the contract. • If a party objects the dispute may be referred to other resolution mechanisms, usually litigation. The recommendations of a DRB are usually “with prejudice”. That is, the recommendations can be used by a party during litigation.
  • 10. COST OF DRB • There are two costs associated with a DRB. • The first is the initial set up cost. This provides the parties with the structure within which to establish the DRB. The set up cost includes a license to use the DRB Rules, the clauses to add into a contract and a nominating authority to appoint members if the parties can not. • The second cost is the monthly retainer for each DRB member. For most large projects this is equivalent to 2- 3 man days for each member per month. For smaller projects it can be as low as 1 man day for each member per month.
  • 11. FUNCTIONS OF DRB • The primary function of a Dispute Board is to assist the parties to avoid disputes if possible by facilitating and improving communication and encouraging the resolution of contentious issues by the parties at the job level before they become disputes, or if not, to assist them to resolve disputes quickly and cost effectively without the need for arbitration or litigation. • The DRB shall serve as an advisory body to assist in the resolution of disputes between the State and the Contractor, hereinafter referred to as the "parties." • The DRB can be made to meet at regular periodical intervals to review the activities relating to the contracts and also discuss and decide the issues which are likely to result into disputes. • This would help in solving the problems before the actual disputes, both the parties i.e the Engineer in charge and the contractor can put up their views and claims before the DRB. • The board, after hearing the views put up by both parties and its own evaluation and examination of relevant materials on record, can take a final decision leading to the resolution of dispute.
  • 12. In case of government and public sector organizations DRB’s can be constituted at various levels. 1.For small projects at district level a) District collector – Chairman b)Concerned executive engineer – Member c) Other executive engineer – Member d) Representative of the contractor – Member 2.For medium and regional level projects a) Concerned Chief engineer – Chairman b)Concerned superintending engineer – Member c) One other superintending engineer – Member d) One outside expert – Member d) Representative of the contractor – Member 3.At state level and for major projects a) Chief executive of the organization – Chairman b)Financial advisor/controller – Member c) Engineer in chief – Member d) Two senior outside experts – Members (one to be nominated by contractor) d) Representative of the contractor – Member
  • 13. ADVANTAGES OF DISPUTES REVIEW BOARDS • The DRB hears disputes on an informal basis and can provide recommendations for their timely resolution before parties adopt hard positions leading to litigation. • The parties are comfortable with the recommendations of the DRB since the selection of the DRB members is controlled by the owner and the contractor. • Because they meet periodically and they are sent progress reports, the DRB members are familiar with the elements of the project. • Although the DRB recommendations are not binding on either party, there is strong motivation to accept the findings
  • 14. DISADVANTAGES OF DISPUTES REVIEW BOARDS • The impartiality and conflict-of- interest portion of the DRB specification is so tough that sometimes there are not enough qualified people for the DRB. • The project must be large enough, and the probability of the occurrence of disputes throughout the course of the project must be high enough to justify the expense of retaining the services of the DRB members for the entire duration of the project.
  • 15. LIMITATIONS OF DISPUTE REVIEW BOARDS •DRBs add expense but not add value to the project •presence of bias or lack of qualifications in Board members •DRBs impose personal equity rather than contract provisions •presence of a DRB will promote claims •DRBs are unreliable because they lack the formalities of legal proceedings •historical culture of “power & control” •expectation of a binding decision •in high value disputes, losing party motivated to try litigation •parties may undermine the DRB process
  • 16. CONCLUSION • Alternate dispute resolution mechanism will relieve us from the tedious court procedures and defects of arbitration. • It would save both National time and National costs.