Analisi delle normative militari concernenti la compatibilità elettromagnetica e, in particolare, i Data Item EMC relativi alle procedure di prova, alle procedure di controllo ed alla stesura dei report. Pubblicata in occasione del seminario MIL nel 2017.
This document provides design criteria and a checklist for instrumentation documentation. It outlines requirements for various documentation deliverables including instrument indexes, loop diagrams, specifications, calculations, installation details, location drawings, purchase documents, software and hardware documentation, and vendor documentation. It also provides guidance on general instrumentation including required control systems, signal levels and indications, tagging, and electrical classifications. The overall purpose is to ensure consistent and complete documentation is developed to support construction, startup, and long-term maintenance of the facility's instrumentation and control systems.
The document describes a control, navigation, and telecommunications system for unmanned airships. The system allows for automatic and remote control of airship flight along a given path or hovering in an area. It consists of ground and airborne units connected by radio. The airborne unit includes a navigation system, environmental sensors, onboard computer, and telecommunications terminals. The ground control station allows operators to control takeoff and landing from up to 2 km away. Technical specifications of the system components are provided. The developing organization has experience creating similar systems for airships.
This document provides standards and guidelines for the design of transmission lines in SEC's system. It outlines parameters like frequency, voltage levels, insulation requirements. It describes design aspects like circuit configuration, phase designation, short circuit ratings. It also provides details on structural supports, insulators, hardware and environmental considerations that must be taken into account in transmission line design. The document is intended to guide SEC engineers and other agencies involved in transmission line design projects.
This document summarizes the scope of work for a project to design, supply materials for, erect, test and commission a 220kV transmission line on a turnkey basis. The scope includes overall project management, surveys, fabrication drawings, supplying towers, conductor and other materials, excavation, tower erection, stringing conductor and optical fiber ground wires, testing and commissioning. It describes the technical requirements for the transmission line, towers, conductor, earthwire, insulators and accessories. It also outlines the contractor qualification requirements, bidding process, bid evaluation process and procedures to ensure quality of work.
The document discusses various types of documentation used for aircraft maintenance, including manufacturer's documentation, regulatory documentation, and airline generated documentation. It describes documentation such as the maintenance manual, fault isolation manual, illustrated parts catalogue, wiring diagram manual, minimum equipment list, and more. It explains that proper documentation is essential for safely performing maintenance and troubleshooting aircraft systems.
This site survey will evaluate the physical infrastructure of a data center, including thermal management, power distribution, racks, cabling, pathways, grounding and bonding, and labeling. An on-site evaluation will be conducted to inspect these systems and provide a detailed report on findings and recommendations for improvement based on relevant industry standards. The client will provide information and access to the data center to enable the partner to thoroughly assess the current state of the physical infrastructure.
Analisi della filosofia si cui si è basato lo sviluppo della norma MIL-STD-461 dalla sua nascita fino alla versione attuale -461G. Pubblicata in occasione del seminario MIL nel 2017.
This document provides a summary of UFC 3-110-03, which establishes unified facilities criteria for roofing design for the Department of Defense (DoD). It updates and cancels several previous roofing design documents. The UFC includes general design requirements for both low-slope and steep-slope roof systems. For low-slope roofs, it provides criteria for roof decks, insulation, cover boards, and various membrane types. The UFC aims to coordinate roofing design with current industry standards to provide familiar and up-to-date criteria for designers and contractors, while continuing to rely on commercial standards to minimize future revisions.
This document provides design criteria and a checklist for instrumentation documentation. It outlines requirements for various documentation deliverables including instrument indexes, loop diagrams, specifications, calculations, installation details, location drawings, purchase documents, software and hardware documentation, and vendor documentation. It also provides guidance on general instrumentation including required control systems, signal levels and indications, tagging, and electrical classifications. The overall purpose is to ensure consistent and complete documentation is developed to support construction, startup, and long-term maintenance of the facility's instrumentation and control systems.
The document describes a control, navigation, and telecommunications system for unmanned airships. The system allows for automatic and remote control of airship flight along a given path or hovering in an area. It consists of ground and airborne units connected by radio. The airborne unit includes a navigation system, environmental sensors, onboard computer, and telecommunications terminals. The ground control station allows operators to control takeoff and landing from up to 2 km away. Technical specifications of the system components are provided. The developing organization has experience creating similar systems for airships.
This document provides standards and guidelines for the design of transmission lines in SEC's system. It outlines parameters like frequency, voltage levels, insulation requirements. It describes design aspects like circuit configuration, phase designation, short circuit ratings. It also provides details on structural supports, insulators, hardware and environmental considerations that must be taken into account in transmission line design. The document is intended to guide SEC engineers and other agencies involved in transmission line design projects.
This document summarizes the scope of work for a project to design, supply materials for, erect, test and commission a 220kV transmission line on a turnkey basis. The scope includes overall project management, surveys, fabrication drawings, supplying towers, conductor and other materials, excavation, tower erection, stringing conductor and optical fiber ground wires, testing and commissioning. It describes the technical requirements for the transmission line, towers, conductor, earthwire, insulators and accessories. It also outlines the contractor qualification requirements, bidding process, bid evaluation process and procedures to ensure quality of work.
The document discusses various types of documentation used for aircraft maintenance, including manufacturer's documentation, regulatory documentation, and airline generated documentation. It describes documentation such as the maintenance manual, fault isolation manual, illustrated parts catalogue, wiring diagram manual, minimum equipment list, and more. It explains that proper documentation is essential for safely performing maintenance and troubleshooting aircraft systems.
This site survey will evaluate the physical infrastructure of a data center, including thermal management, power distribution, racks, cabling, pathways, grounding and bonding, and labeling. An on-site evaluation will be conducted to inspect these systems and provide a detailed report on findings and recommendations for improvement based on relevant industry standards. The client will provide information and access to the data center to enable the partner to thoroughly assess the current state of the physical infrastructure.
Analisi della filosofia si cui si è basato lo sviluppo della norma MIL-STD-461 dalla sua nascita fino alla versione attuale -461G. Pubblicata in occasione del seminario MIL nel 2017.
This document provides a summary of UFC 3-110-03, which establishes unified facilities criteria for roofing design for the Department of Defense (DoD). It updates and cancels several previous roofing design documents. The UFC includes general design requirements for both low-slope and steep-slope roof systems. For low-slope roofs, it provides criteria for roof decks, insulation, cover boards, and various membrane types. The UFC aims to coordinate roofing design with current industry standards to provide familiar and up-to-date criteria for designers and contractors, while continuing to rely on commercial standards to minimize future revisions.
The primary goal of the checklist is to make it useful and as a trusted guide for IT Auditors,Security Consultant in Network Architecture Review assignments.The checklist is drawn from numerous resources referred and my experience in network architecture reviews.Though the essentially doesn't essentially cover all elements of a network architecture review,I have tried to bring in aspects of the security element in a network architecture
Piping and instrumentation diagrams (P&IDs) are complex diagrams that show the piping, instrumentation, and process flow in chemical plants. The presentation discusses P&IDs in detail, including:
1. The purpose of P&IDs in understanding chemical processes, operations, and maintenance.
2. The various standards and symbols used to represent equipment, piping, instruments, and their interconnectivity.
3. How P&IDs are developed through various stages and used by different engineering departments and industries for design and operations.
4. Examples of software that can be used to create detailed P&IDs.
This document outlines the skills, knowledge, and behaviors required to install circuit breakers in substations. It details three categories for assessment: 1) transmission circuit breakers, 2) primary circuit breakers, and 3) distribution circuit breakers up to 20kV. For each category, candidates must demonstrate installation procedures and testing for specific circuit breaker types and components according to safety standards and company procedures. The document specifies performance criteria, tasks, and required technical knowledge for competent installation of circuit breakers across all three categories.
The document provides guidance on building an ideal maintenance program with four phases: 1) Planning and preparation which includes developing a coding system to organize assets, gathering machine information, and building a database. 2) Getting organized by creating shadow boards and tool crib organization. 3) Maintenance tracking and metrics such as work orders and site maps. 4) Continuous improvement through standardization, training, and enforcement of the maintenance program.
Requirements documentation standards ieee830Abdul Basit
The document discusses requirements specification documents and the IEEE 830 standard. It provides an overview of the requirements specification document and its purpose. It also describes the key sections and contents of the IEEE 830 standard, including the structure and templates for software requirements specifications. The standard provides guidance on producing high-quality requirements documents and the relationship between IEEE 830 and the ISO/IEC 12207 standard. Example requirements and diagrams are also presented.
This document discusses hardware design verification and testing techniques. It covers emulation architectures like FPGA-based and processor-based systems. It also discusses formal property verification methods, software formal verification, design for test objectives, chip-level DFT techniques, automatic test pattern generation, and testing techniques for analog/mixed-signal circuits like ADCs, PLLs and oscillators.
CSI Master Format Specification 271005 Structured Cabling for Voice and DataMETZ CONNECT USA Inc.
Product specifications written in the Construction Specification Institute Master Format style. Structured cabling systems for industrial Ethernet, voice and data, audio and visual networks.
This document outlines specifications and requirements for personal computers in India. It provides:
1) General requirements for PC components like the microprocessor, memory, interfaces, display, keyboard, and power supply.
2) Safety, EMC, and performance requirements for PCs to ensure quality, reliability, and electromagnetic compatibility.
3) Requirements for marking, user manuals, and testing including type tests, routine tests, and acceptance tests.
4) Environmental tests to ensure PCs can withstand vibration, temperature extremes, humidity, and mechanical stresses.
This supplemental agenda provides details for an upcoming ASME BTH Standards Committee meeting on May 26, 2021. The agenda includes a new business item to discuss the NRC's draft regulatory guide 1.244, which proposes to endorse parts of ASME BTH-1 for controlling heavy loads at nuclear facilities. The agenda also includes reviewing a membership application from Jon Alberson. The secretary of the committee, Elijah Dominguez, respectfully submitted the supplemental agenda with these details for committee review and action.
The document discusses the typical documentation used to illustrate process control and field instrumentation for a plant. It describes four types of common drawings: plot plans, process flow diagrams, piping and instrumentation diagrams, and control narratives. Plot plans show the physical layout of equipment in the plant. Process flow diagrams show the major equipment and expected operating conditions. Piping and instrumentation diagrams provide detailed piping and instrumentation information. Control narratives describe the control system configuration and strategies. Documentation standards like those from ISA are often followed to maintain consistency.
This document summarizes guidelines for determining short circuit current rating (SCCR) for electrical equipment. It discusses:
- Upcoming 2017 NEC changes that will require marking or documenting the available fault current where equipment is installed.
- Methods for determining equipment SCCR, including considering the ratings of components, overcurrent devices, and whether current-limiting devices can increase component ratings.
- Basic guidelines for using current-limiting devices to increase SCCR, such as only being able to raise branch component SCCR, not feeder components or overcurrent device ratings.
- A 4-step process to calculate equipment SCCR by determining component and overcurrent device ratings and identifying the lowest rating.
This document outlines the skills, knowledge, and behaviors required to install electricity switchgear at different voltage levels. Candidates can be assessed for installation of transmission, primary, or distribution switchgear. Specific requirements include carrying out installation procedures and testing on various switchgear components according to manufacturers' specifications and company procedures. Candidates must also demonstrate safety practices and an understanding of switchgear operating principles and hazards.
Presentacion asme seccion viii division 2 2013leo040490
This document outlines steps for developing a quality control system manual (QCSM) to meet ASME Section VIII Division 2 regulations for pressure vessel certification. The key steps include:
1. Applying to ASME and the National Board for certification.
2. Developing detailed design calculations, drawings, materials specifications, and fabrication and inspection procedures meeting code requirements.
3. Implementing the QCSM in the shop and warehouses, and distributing it to all relevant personnel, to ensure all code requirements are met during construction.
4. Scheduling audits by the Authorized Inspector to confirm readiness for joint review and certification.
This document is a material requisition for slurry storage tank agitators for a bauxite pipeline project in Paragominas, Brazil. It includes 6 agitators to be provided - 4 for mine site storage tanks and 2 for terminal site tanks. The scope of work includes design, fabrication, testing and delivery of the agitators. Drawings, manuals and other documentation are required to be submitted. Quality surveillance of the agitator manufacturing is also specified, requiring the supplier to allow access to their facilities for inspection. Technical specifications for aspects like painting, gearboxes and instruments are referenced.
Wiring design for commercial and industrial buildingsducusin_kevin07
This document discusses wiring design and installation practices for commercial and industrial buildings. It covers various topics such as basic installation rules and inspection requirements, different wiring methods including types of raceways and cable assemblies, types of conductors and their applications, types of circuits, overcurrent protection, low-voltage busway systems, protective grounding, and interior wiring distribution systems. The document provides information on National Electrical Code compliance and safety standards that must be followed for commercial and industrial wiring installations.
This document provides testing procedures for switchgear and controlgear. It outlines dielectric tests on the main circuit to check insulation as well as tests on auxiliary and control circuits. Visual inspections are also specified to check components, wiring, and that no conductors can be damaged. Separate tests are required if the equipment is not fully assembled during transport.
Presentazione di base relativa ai concetti della Compatibilità Elettromagnetica (EMC). Nello scritto si trovano informazioni sulle normative iEC, sugli ambienti e sulla loro struttura, sulle prove irradiate e sulle prove condotte.
The primary goal of the checklist is to make it useful and as a trusted guide for IT Auditors,Security Consultant in Network Architecture Review assignments.The checklist is drawn from numerous resources referred and my experience in network architecture reviews.Though the essentially doesn't essentially cover all elements of a network architecture review,I have tried to bring in aspects of the security element in a network architecture
Piping and instrumentation diagrams (P&IDs) are complex diagrams that show the piping, instrumentation, and process flow in chemical plants. The presentation discusses P&IDs in detail, including:
1. The purpose of P&IDs in understanding chemical processes, operations, and maintenance.
2. The various standards and symbols used to represent equipment, piping, instruments, and their interconnectivity.
3. How P&IDs are developed through various stages and used by different engineering departments and industries for design and operations.
4. Examples of software that can be used to create detailed P&IDs.
This document outlines the skills, knowledge, and behaviors required to install circuit breakers in substations. It details three categories for assessment: 1) transmission circuit breakers, 2) primary circuit breakers, and 3) distribution circuit breakers up to 20kV. For each category, candidates must demonstrate installation procedures and testing for specific circuit breaker types and components according to safety standards and company procedures. The document specifies performance criteria, tasks, and required technical knowledge for competent installation of circuit breakers across all three categories.
The document provides guidance on building an ideal maintenance program with four phases: 1) Planning and preparation which includes developing a coding system to organize assets, gathering machine information, and building a database. 2) Getting organized by creating shadow boards and tool crib organization. 3) Maintenance tracking and metrics such as work orders and site maps. 4) Continuous improvement through standardization, training, and enforcement of the maintenance program.
Requirements documentation standards ieee830Abdul Basit
The document discusses requirements specification documents and the IEEE 830 standard. It provides an overview of the requirements specification document and its purpose. It also describes the key sections and contents of the IEEE 830 standard, including the structure and templates for software requirements specifications. The standard provides guidance on producing high-quality requirements documents and the relationship between IEEE 830 and the ISO/IEC 12207 standard. Example requirements and diagrams are also presented.
This document discusses hardware design verification and testing techniques. It covers emulation architectures like FPGA-based and processor-based systems. It also discusses formal property verification methods, software formal verification, design for test objectives, chip-level DFT techniques, automatic test pattern generation, and testing techniques for analog/mixed-signal circuits like ADCs, PLLs and oscillators.
CSI Master Format Specification 271005 Structured Cabling for Voice and DataMETZ CONNECT USA Inc.
Product specifications written in the Construction Specification Institute Master Format style. Structured cabling systems for industrial Ethernet, voice and data, audio and visual networks.
This document outlines specifications and requirements for personal computers in India. It provides:
1) General requirements for PC components like the microprocessor, memory, interfaces, display, keyboard, and power supply.
2) Safety, EMC, and performance requirements for PCs to ensure quality, reliability, and electromagnetic compatibility.
3) Requirements for marking, user manuals, and testing including type tests, routine tests, and acceptance tests.
4) Environmental tests to ensure PCs can withstand vibration, temperature extremes, humidity, and mechanical stresses.
This supplemental agenda provides details for an upcoming ASME BTH Standards Committee meeting on May 26, 2021. The agenda includes a new business item to discuss the NRC's draft regulatory guide 1.244, which proposes to endorse parts of ASME BTH-1 for controlling heavy loads at nuclear facilities. The agenda also includes reviewing a membership application from Jon Alberson. The secretary of the committee, Elijah Dominguez, respectfully submitted the supplemental agenda with these details for committee review and action.
The document discusses the typical documentation used to illustrate process control and field instrumentation for a plant. It describes four types of common drawings: plot plans, process flow diagrams, piping and instrumentation diagrams, and control narratives. Plot plans show the physical layout of equipment in the plant. Process flow diagrams show the major equipment and expected operating conditions. Piping and instrumentation diagrams provide detailed piping and instrumentation information. Control narratives describe the control system configuration and strategies. Documentation standards like those from ISA are often followed to maintain consistency.
This document summarizes guidelines for determining short circuit current rating (SCCR) for electrical equipment. It discusses:
- Upcoming 2017 NEC changes that will require marking or documenting the available fault current where equipment is installed.
- Methods for determining equipment SCCR, including considering the ratings of components, overcurrent devices, and whether current-limiting devices can increase component ratings.
- Basic guidelines for using current-limiting devices to increase SCCR, such as only being able to raise branch component SCCR, not feeder components or overcurrent device ratings.
- A 4-step process to calculate equipment SCCR by determining component and overcurrent device ratings and identifying the lowest rating.
This document outlines the skills, knowledge, and behaviors required to install electricity switchgear at different voltage levels. Candidates can be assessed for installation of transmission, primary, or distribution switchgear. Specific requirements include carrying out installation procedures and testing on various switchgear components according to manufacturers' specifications and company procedures. Candidates must also demonstrate safety practices and an understanding of switchgear operating principles and hazards.
Presentacion asme seccion viii division 2 2013leo040490
This document outlines steps for developing a quality control system manual (QCSM) to meet ASME Section VIII Division 2 regulations for pressure vessel certification. The key steps include:
1. Applying to ASME and the National Board for certification.
2. Developing detailed design calculations, drawings, materials specifications, and fabrication and inspection procedures meeting code requirements.
3. Implementing the QCSM in the shop and warehouses, and distributing it to all relevant personnel, to ensure all code requirements are met during construction.
4. Scheduling audits by the Authorized Inspector to confirm readiness for joint review and certification.
This document is a material requisition for slurry storage tank agitators for a bauxite pipeline project in Paragominas, Brazil. It includes 6 agitators to be provided - 4 for mine site storage tanks and 2 for terminal site tanks. The scope of work includes design, fabrication, testing and delivery of the agitators. Drawings, manuals and other documentation are required to be submitted. Quality surveillance of the agitator manufacturing is also specified, requiring the supplier to allow access to their facilities for inspection. Technical specifications for aspects like painting, gearboxes and instruments are referenced.
Wiring design for commercial and industrial buildingsducusin_kevin07
This document discusses wiring design and installation practices for commercial and industrial buildings. It covers various topics such as basic installation rules and inspection requirements, different wiring methods including types of raceways and cable assemblies, types of conductors and their applications, types of circuits, overcurrent protection, low-voltage busway systems, protective grounding, and interior wiring distribution systems. The document provides information on National Electrical Code compliance and safety standards that must be followed for commercial and industrial wiring installations.
This document provides testing procedures for switchgear and controlgear. It outlines dielectric tests on the main circuit to check insulation as well as tests on auxiliary and control circuits. Visual inspections are also specified to check components, wiring, and that no conductors can be damaged. Separate tests are required if the equipment is not fully assembled during transport.
Similar to DI-EMCS - Contro procedures, test procedures e test report (20)
Presentazione di base relativa ai concetti della Compatibilità Elettromagnetica (EMC). Nello scritto si trovano informazioni sulle normative iEC, sugli ambienti e sulla loro struttura, sulle prove irradiate e sulle prove condotte.
Analisi delle prove di misura di emissioni condotte nell'ambito della norma MIL-STD-461G e paragone con le normative precedenti. Pubblicata in occasione del seminario MIL nel 2017.
Analisi delle strutture per prove di suscettività irradiata nell'ambito della sezione RS105 della norma MIL-STD-461G. Pubblicata in occasione del seminario MIL nel 2017.
This document discusses radiated susceptibility testing standards and procedures. It provides an overview of various radiated susceptibility test methods (RS101, RS103, RS105) defined in MIL-STD-461G, including applicable frequency ranges and equipment. It also compares these test methods to relevant IEC commercial standards. The document outlines the specific test setup, equipment, and procedures required to perform radiated susceptibility integrity checks and testing according to MIL-STD-461G for equipment under test.
Analisi delle prove di misura di emissioni irradiate nell'ambito della norma MIL-STD-461G e paragone con le normative precedenti. Pubblicata in occasione del seminario MIL nel 2017.
Analisi delle prove di suscettibilità condotta nell'ambito della norma MIL-STD-461G e paragone con le normative precedenti. Pubblicata in occasione del seminario MIL nel 2017.
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024Sinan KOZAK
Sinan from the Delivery Hero mobile infrastructure engineering team shares a deep dive into performance acceleration with Gradle build cache optimizations. Sinan shares their journey into solving complex build-cache problems that affect Gradle builds. By understanding the challenges and solutions found in our journey, we aim to demonstrate the possibilities for faster builds. The case study reveals how overlapping outputs and cache misconfigurations led to significant increases in build times, especially as the project scaled up with numerous modules using Paparazzi tests. The journey from diagnosing to defeating cache issues offers invaluable lessons on maintaining cache integrity without sacrificing functionality.
Null Bangalore | Pentesters Approach to AWS IAMDivyanshu
#Abstract:
- Learn more about the real-world methods for auditing AWS IAM (Identity and Access Management) as a pentester. So let us proceed with a brief discussion of IAM as well as some typical misconfigurations and their potential exploits in order to reinforce the understanding of IAM security best practices.
- Gain actionable insights into AWS IAM policies and roles, using hands on approach.
#Prerequisites:
- Basic understanding of AWS services and architecture
- Familiarity with cloud security concepts
- Experience using the AWS Management Console or AWS CLI.
- For hands on lab create account on [killercoda.com](https://killercoda.com/cloudsecurity-scenario/)
# Scenario Covered:
- Basics of IAM in AWS
- Implementing IAM Policies with Least Privilege to Manage S3 Bucket
- Objective: Create an S3 bucket with least privilege IAM policy and validate access.
- Steps:
- Create S3 bucket.
- Attach least privilege policy to IAM user.
- Validate access.
- Exploiting IAM PassRole Misconfiguration
-Allows a user to pass a specific IAM role to an AWS service (ec2), typically used for service access delegation. Then exploit PassRole Misconfiguration granting unauthorized access to sensitive resources.
- Objective: Demonstrate how a PassRole misconfiguration can grant unauthorized access.
- Steps:
- Allow user to pass IAM role to EC2.
- Exploit misconfiguration for unauthorized access.
- Access sensitive resources.
- Exploiting IAM AssumeRole Misconfiguration with Overly Permissive Role
- An overly permissive IAM role configuration can lead to privilege escalation by creating a role with administrative privileges and allow a user to assume this role.
- Objective: Show how overly permissive IAM roles can lead to privilege escalation.
- Steps:
- Create role with administrative privileges.
- Allow user to assume the role.
- Perform administrative actions.
- Differentiation between PassRole vs AssumeRole
Try at [killercoda.com](https://killercoda.com/cloudsecurity-scenario/)
Batteries -Introduction – Types of Batteries – discharging and charging of battery - characteristics of battery –battery rating- various tests on battery- – Primary battery: silver button cell- Secondary battery :Ni-Cd battery-modern battery: lithium ion battery-maintenance of batteries-choices of batteries for electric vehicle applications.
Fuel Cells: Introduction- importance and classification of fuel cells - description, principle, components, applications of fuel cells: H2-O2 fuel cell, alkaline fuel cell, molten carbonate fuel cell and direct methanol fuel cells.
Software Engineering and Project Management - Introduction, Modeling Concepts...Prakhyath Rai
Introduction, Modeling Concepts and Class Modeling: What is Object orientation? What is OO development? OO Themes; Evidence for usefulness of OO development; OO modeling history. Modeling
as Design technique: Modeling, abstraction, The Three models. Class Modeling: Object and Class Concept, Link and associations concepts, Generalization and Inheritance, A sample class model, Navigation of class models, and UML diagrams
Building the Analysis Models: Requirement Analysis, Analysis Model Approaches, Data modeling Concepts, Object Oriented Analysis, Scenario-Based Modeling, Flow-Oriented Modeling, class Based Modeling, Creating a Behavioral Model.
An improved modulation technique suitable for a three level flying capacitor ...IJECEIAES
This research paper introduces an innovative modulation technique for controlling a 3-level flying capacitor multilevel inverter (FCMLI), aiming to streamline the modulation process in contrast to conventional methods. The proposed
simplified modulation technique paves the way for more straightforward and
efficient control of multilevel inverters, enabling their widespread adoption and
integration into modern power electronic systems. Through the amalgamation of
sinusoidal pulse width modulation (SPWM) with a high-frequency square wave
pulse, this controlling technique attains energy equilibrium across the coupling
capacitor. The modulation scheme incorporates a simplified switching pattern
and a decreased count of voltage references, thereby simplifying the control
algorithm.
2. • MIL-STD-461G 6.3 – Associated Data Item Descriptions
(DIDs)
– This standard has been assigned an Acquisition Management
Systems Control (AMSC) number authorizing it as the source
document for the following DIDs. When it is necessary to
obtain the data, the applicable DIDs must be listed on the
Contract Data Requirements List (DD Form 1423).
– The above DIDs were current as of the date of this standard.
The ASSIST database should be researched at
http://quicksearch.dla.mil/ to ensure that only current and
approved DIDs are cited on the DD Form 1423.
MIL-STD-461G
DID Number DID Title
DI-EMCS-80199 Electromagnetic Interference Control Procedures (EMICP)
DI-EMCS-80201 Electromagnetic Interference Test Procedures (EMITP)
DI-EMCS-80200 Electromagnetic Interference Test Report (EMITR)
3. • Il DD Form 1423 è utilizzato per specificare e tracciare i
requirements di contratti e sub-contratti governativi. Se
usato per specificare un contratto, è definito CDRL
(Contract Data Requirements List) ed è una lista dei
requirements per dati autorizzati per approvvigionamento
specifico parte di un contratto.
• Si può avere un singolo DD Form 1423 o una serie di DD
Form 1423 individuali che contengono le informazioni di
riferimento da consegnare per specifica.
• Subpart 215.470 di DFARS richiede espressamente l’utilizzo
di CDRL nelle istanze in cui si chieda fornitura di dati. Le
CDRL dovrebbero essere associate direttamente ai SOW e
gestite dal Program office data manager.
• Il fine delle CDRL è di fornire un metodo standardizzato per
definire in modo chiaro e non ambiguo le necessità minime
di dati richiesti.
DD Form 1423
http://www.acq.osd.mil/dpap/dars/dfars/html/current/215_4.htm#215.470
5. • DoD 5010.12-M – Procedures for the
acquisition and management of technical data
– C3.1.2: All data requirements shall be consistent
with the data acquisition documents and tasking
requirements imposed by the contract and shall be
tailored, as appropriate, to ensure that only
essential data is acquired. Data acquisition
documents are defined as only those DIDs,
specifications, and standards listed in DoD
5010.12-L (reference (a)), or one-time DIDs
prepared in accordance with DoD-STD-963
(reference (g)) that provides the authorized format
and content of all data requirements listed on DD
Form 1423. [...]
DoD 5010.12-M
6. • DoD 5010.12-M C3.3 – DD FORM
1423, CONTRACT DATA
REQUIREMENTS LIST (CDRL)
• Il capitolo specifica e spiega in modo
dettagliato come compilare un CDRL
su DD Form 1423.
DoD 5010.12-M
7. • MIL-STD-461: 1967 e -461A: 1968
fanno riferimento nella norma
• MIL-STD-461B: 1980 fa riferimento a
DI-R-7061, DI-R-7063 e DI-R-7062
• Da MIL-STD-461C: 1986 si fa
riferimento a DI-EMCS-80199,
DI-EMCS-80201 e DI-EMCS-80201
MIL-STD-461
8. • DI-EMCS-80199: 1986
• DI-EMCS-80199A: 1993
– Su DD Form 1664, necessità eliminata
da MIL-STD-963B 4.3 (1997)
• DI-EMCS-80199B: 1999
• DI-EMCS-80199C: 2007
• DI-EMCS definisce le procedure di
controllo (EMICP)
DI-EMCS-80199 - EMICP
http://www.dtic.mil/whs/directives/forms/forminfo/forminfopage2175.html
9. • 1. Reference documents. The applicable issue of the documents cited
herein, including their approval dates and dates of any applicable
amendments, notices, and revisions, shall be as specified in the contract.
• 2. Format. Contractor format is acceptable.
• 3. Content. The EMICP shall contain the following:
– 3.1. Management. The EMICP shall address the following management areas:
• a. Specific organizational responsibilities, lines of authority and control, and program
planning, including milestones and schedules.
• b. Detailed EMI requirements imposed on subcontractors.
• c. Role in program of Government Furnished Equipment and subcontractor items.
• d. Description of the equipment or subsystem, its function, characteristics, and intended
installation.
• e. Plans and procedures for identifying and resolving potential EMI problems,
implementing solutions, and verifying solutions through analysis and testing.
• f. Point of contact for EMI technical issues.
DI-EMCS-80199 - EMICP
10. – 3.2. Design techniques and procedures. The EMICP shall describe the specific
design techniques and procedures used to meet each emission and susceptibility
requirement, including the following:
• a. Spectrum management techniques.
• b. EMI mechanical design, including the following:
– (1) Type of metals, casting, finishes, and hardware employed in the design.
– (2) Construction techniques, such as isolated compartments; filter mounting, isolation of other
parts; treatment of openings (ventilation ports, access hatches, windows, metal faces and control
shafts), and attenuation characteristics of Radio Frequency (RF) gaskets used on mating surfaces.
– (3) Shielding provisions and techniques used for determining shielding effectiveness.
– (4) Corrosion control procedures.
– (5) Methods of bonding mating surfaces, such as surface preparation and gaskets.
• c. Electrical wiring design, including cable types or characteristics, cable routing, cable
separation, grounding philosophy, and cable shielding types and termination methods.
• d. Electrical and electronic circuit design, including the following:
– (1) Filtering techniques, technical reasons for selecting types of filters, and associated filter
characteristics, including attenuation and line-to-ground capacitance values of AC and DC power
line filters.
– (2) Part location and separation for reducing EMI.
– (3) Location, shielding, and isolation of critical circuits.
DI-EMCS-80199 - EMICP
11. – 3.3. Analysis. The EMICP shall provide analysis results demonstrating how each
applicable requirement is going to be met.
– 3.4. Developmental testing. The EMICP shall include a discussion of testing to be
performed during development (such as evaluations of breadboards, prototypes,
and engineering models).
DI-EMCS-80199 - EMICP
12. • DI-EMCS-80201: 1986
• DI-EMCS-80201A: 1993
– Su DD Form 1664, necessità eliminata
da MIL-STD-963B 4.3 (1997)
• DI-EMCS-80201B: 1999
• DI-EMCS-80201C: 2007
• DI-EMCS definisce le procedure di
test (EMITP)
DI-EMCS-80201 - EMITP
http://www.dtic.mil/whs/directives/forms/forminfo/forminfopage2175.html
13. • 1. Reference documents. The applicable issue of the documents cited
herein, including their approval dates and dates of any applicable
amendments, notices, and revisions, shall be as specified in the contract.
• 2. Format. Contractor format is acceptable.
• 3. Content. The EMITP shall contain the following:
– 3.1. Introduction. The introduction of the EMITP shall include the following:
• a. A table describing all the tests to be performed, the applicable section within the EMITP, and the
corresponding test procedure from MIL-STD-461.
• b. Description of the Equipment Under Test (EUT), including its function, characteristics,
intended installation, and power usage.
• c. Approved exceptions or deviations from contractual test requirements, if any.
– 3.2. Applicable documents. Applicable documents shall be listed as follows:
• a. Military (such as standards and specifications).
• b. Company (such as in-house documents used for calibration or quality assurance).
• c. Other Government or industry standards, specifications, and documents.
– 3.3. Test site. A description of the test site shall be provided covering the
following:
• a. Test facility and shielded enclosure or anechoic chamber, including size, characteristics, and
placement of radio frequency (RF) absorbers.
• b. Ground plane (size and type) and methods of grounding or bonding the EUT to the ground plane to
simulate actual equipment installation.
• c. Implementation of test precautions required by 4.3.7 of MIL-STD-461.
DI-EMCS-80201 - EMITP
14. – 3.4. Test instrumentation. Test instrumentation to be used shall be described as
follows:
• a. Equipment nomenclature.
• b. Characteristics of coupling transformers and band-reject filters.
• c. Antenna factors of specified antennas, transfer impedances of current probes, and impedance of
Line Impedance Stabilization Networks (LISN).
• d. Description of the operations being directed by software for computer-controlled instrumentation,
the verification techniques used to demonstrate proper performance of the software, and the specific
versions of the software to be used. In addition, sweep times, correction factors and how are
they used, how final data are determined and presented, and an audit trail that provides
details on what part of the software controls each function shall be described.
• e. Bandwidth (resolution and video) and scanning speeds of measurement receivers.
• f. Modulation characteristics and scan rates of the susceptibility test signals.
– 3.5. EUT setup. A description of the EUT test setup for each test shall cover
the following:
• a. Physical layout of the cables and EUT.
• b. Cable types, characteristics, and construction details (see 4.3.8.6 of MIL-STD-461)
• c. Position of the line impedance stabilization networks on the ground plane.
• d. Use of bond straps and loads.
• e. Test simulation and monitoring equipment.
DI-EMCS-80201 - EMITP
15. – 3.6. EUT operation. A description of the EUT operation shall cover the following:
• a. Modes of operation for each test, including operating frequencies (where applicable), and rationale for
selection.
• b. Control settings on the EUT.
• c. Control settings on any test stimulation and monitoring equipment and characteristics of input signals.
• d. Operating frequencies (such as oscillator and clock frequencies) which may be expected to approach
limits.
• e. Performance checks initiated to designate the equipment as meeting minimal working standard
requirements.
• f. Enumeration of circuits, outputs, or displays to be monitored during susceptibility testing, as well as the
criteria for monitoring degradation of performance.
– 3.7. Measurements. The following shall be described for each test.
• a. Block diagram depicting test setup, including all pertinent dimensions.
• b. Step-by-step procedures.
• c. Test equipment used in performance of the test and the methods of grounding, bonding, or
achieving electrical isolation of the measurement instrumentation.
• d. Selection of measurement frequencies.
• e. Information to be recorded during the test, including frequency and units of recorded information.
Sample data sheets, test logs and graphs, including test limits, may be shown.
DI-EMCS-80201 - EMITP
16. • DI-EMCS-80200: 1986
• DI-EMCS-80200A: 1993
– Su DD Form 1664, necessità eliminata
da MIL-STD-963B 4.3 (1997)
• DI-EMCS-80200B: 1999
• DI-EMCS-80200C: 2007
• DI-EMCS definisce i test report
(EMITR)
DI-EMCS-80200 - EMITR
http://www.dtic.mil/whs/directives/forms/forminfo/forminfopage2175.html
17. • 1. Reference documents. The applicable issue of the documents cited
herein, including their approval dates and dates of any applicable
amendments, notices, and revisions, shall be as specified in the contract.
• 2. Format. Contractor format is acceptable.
• 3. Content. The EMITR shall contain the following:
– 3.1 Administrative data. The EMITR shall contain an administrative section
covering the following:
• a. Contract number.
• b. Authentication and certification of performance of the tests by a qualified
representative of the procuring activity.
• c. Disposition of the Equipment Under Test (EUT).
• d. Description of the EUT, including its function, characteristics, intended installation,
actual cable types (characteristics and construction details - see 4.3.8.6 of MIL-STD-
461), and electrical current usage on each power input line.
• e. List of tests performed with pass/fail indications.
• f. Any approved deviations from contractual test procedures or limits previously
authorized.
• g. Identification of Non-Developmental Items (NDI) and Government Furnished
Equipment (GFE) that may be part of the EUT.
• h. Traceability of test equipment calibration.
• i. A reference to the approved EMI test procedure (EMITP).
DI-EMCS-80200 - EMITR
18. – 3.2 Detailed results. A separate appendix shall be prepared for each test. If
deviations from an approved test procedure occurred during the test program,
an additional appendix shall be provided with the “as run” procedures showing
all red-lines and procuring activity concurrence. A separate appendix shall be
provided for log sheets. Each test appendix shall contain the following factual
data:
• a. Test equipment nomenclature, serial numbers, version of software used (if any), and calibration
due date.
• b. Photographs or diagrams of the actual test set up and EUT, with identification.
• c. Transfer impedance of current probes.
• d. Antenna factors.
• e. Impedance values of Line Impedance Stabilization Networks (LISN).
• f. Identification of any suppression devices used to meet the contractual requirements, including
schematics, performance data, and drawings.
• g. Sample calculations, such as conversions of measured levels for comparison against the applicable
limit.
• h. The ambient radiated and conducted electromagnetic emission profile of the test facility, when
necessary.
• i. Data, and data presentation, as specified in the “data presentation” sections of the individual test
procedures of MIL-STD-461. Emissions data cannot be provided on one single sheet (plot).
Provide a minimum frequency resolution of 1% or twice the measurement receiver
bandwidth, whichever is less stringent, and a minimum amplitude resolution of 1 dB for
each plot.
DI-EMCS-80200 - EMITR
19. – 3.2 Detailed results. A separate appendix shall be prepared for each test. If
deviations from an approved test procedure occurred during the test program,
an additional appendix shall be provided with the “as run” procedures showing
all red-lines and procuring activity concurrence. A separate appendix shall be
provided for log sheets. Each test appendix shall contain the following factual
data:
• j. Scan speeds.
• k. Measurement receiver bandwidths.
• l. Antenna polarization.
• m. Power line voltages, frequencies, and power factor.
• n. Low-noise amplifiers (LNA) compression points.
• o. Test susceptibilities and deviations from normal performance are not acceptable.
However, when susceptibility indications or deviations from normal performance are noted
in the EUT operation, a threshold level shall be determined where the susceptible condition
or deviation is no longer present. These thresholds need to be documented for further
assessment.
– 3.3 Conclusions and recommendations. Conclusions and recommendations
shall be provided, including results of the tests in brief narrative form, a
discussion of any remedial actions already initiated, and proposed corrective
measures required (if necessary) to assure compliance of the equipment or
subsystem with the contractual EMI requirements.
DI-EMCS-80200 - EMITR