SlideShare a Scribd company logo
Journal of Civil Engineering Inter Disciplinaries
Volume 1 | Issue 2
Open Access
https://journalofcivilengg.com 26
Case Report
Deep Dynamic Compaction and Rapid Impact Compaction Adopted to Treat
Loose Soil Formations and Fill Compaction for Large Structures and Roads -
Case Study
Khan A1
, Ahmad J1
, Alshokur H1
, Spyropoulos E2*
1
Soil Improvement Contracting Co., Dammam 32232, Kingdom of Saudi Arabia.
2
Saudi Aramco, Dhahran 31311, Kingdom of Saudi Arabia.
Received Date: 26 September, 2020; Accepted Date: 09 October, 2020; Published Date: 13 October,2020
Abstract
The current case study is concerning a facility located near Dammam, Saudi Arabia. The project consisted of three main categories
of design criteria to be achieved. It included nine Bearing Capacity and Settlement criteria for infinite, combined and isolated
foundations, Relative Density (Rd) criterion for Road/Open Areas and Liquefaction Risk Mitigation criterion for the entire site, which
encompassed an area of approximately 180,000m2
. The allotted time for soil improvement works was limited to 6 months, due to the
project being of fast-track category. The soil profile was composed largely of granular material and the depth of improvement went
as deep as 10m. Both Dynamic Compaction and Rapid Impact Compaction are popular techniques in compacting granular material,
due to their high efficiency in achieving the design criteria and fast rate of improvement. The techniques are also cost-effective and
clean, in terms not requiring water nor electricity for operations compared to Vibro-Improvement counter techniques, proving to be
value-engineered options. The improvement area was segregated into three regions based on existing loose soils and fill compaction
requirements, wherein the techniques would be implemented independently or in combination with one another. The production
works lasted around 4.5 months. Post-Improvement Quality Control tests indicated the achievement of Design Criteria by a substantial
margin, exemplifying the efficiency of Deep Dynamic Compaction and Rapid Impact Compaction techniques in terms of achieving the
design criteria and a fast rate of production in operations.
*Corresponding author: Spyropoulos E, Saudi Aramco, Dhahran 31311, Kingdom of Saudi Arabia.
Email : emmanouil.spyropoulos@aramco.com
Citation: Spyropoulos E (2020) Deep Dynamic Compaction and Rapid Impact Compaction Adopted to Treat Loose Soil Formations
and Fill Compaction for Large Structures and Roads - Case Study. J Civil Engg ID 1(2): 26-35.
Introduction
The project location is situated in the northeast of Dammam,
KSA. The project consisted of structures, parking areas and roads,
for a total area of 180,000m2
. The scope of work included existing
soil improvement and fill compaction works. The soil composition
was mainly granular with presence of stiff fine-grained layers. The
project was fast track and required optimized improvement and
compaction strategy to meet a 6-month deadline. With the same
constrained requirement, roller compaction would prove difficult
and an expensive option. The same constraint motivated the need
for value-engineered alternatives.
The current paper consists of the following abbreviations as
defined in Table 1.
Table 1: List of Abbreviations
Abbreviation Description
KSA Kingdom of Saudi Arabia
DC Dynamic Compaction
DR Dynamic Replacement
VC Vibro Compaction
VR Vibro Replacement
CPTu Piezocone Penetration Test
Rd
Relative Density
qc
Cone Tip Resistance
Ic
Soil Behavior Type Index
Journal of Civil Engineering Inter Disciplinaries
https://journalofcivilengg.com
Helics Group
27
Background
Two soil investigation campaigns were conducted prior to
improvement-compaction works. The campaigns will hereafter
be referred to as SI(A) and SI(B). Both investigations were carried
out mostly at the structures locations. As per investigation works
conducted by SI(A), the following profile displayed in Figure 1 can
be used as a summary of geological conditions.
Figure 1: Soil Profile as per SI(A)
Two profiles assessed by SI(B) are presented in the Figure 2
(a & b).
a b
Figure 2: Soil Profiles as determined by SI(B)
Although a variation was observed in the two campaigns, a
basic knowledge of the profile was attained, that mainly the sub-
surface profile consisted of granular material with lenses of fine
soils, which required compaction. This granular layer had thickness
varying from 4m until 7m. The sub-stratum was typically a stiffer
material and ranged from granular to cohesive material with little
or no soft cohesive materials predicted in the profile.
It is typical for investigations to produce slightly varying
results. However, by instilling an adequate Front-End Engineering
Design, unexpected conditions may be avoided and a preliminary
understanding of the soil conditions in the project can attained
prior (Spyropoulos & Khan, 2020).
Problem Statement
Takingintoaccountthesoilconditions,earthworkrequirements
and constrained schedule, optimized strategy for soil improvement
and fill compaction requirement was identified. Removal and
replacement, followed by conventional layer-by-layer roller
compaction would prove expensive and prevent meeting the time
schedule.
Observing the soil suitability recommendations by Braiek
(2017) and Han (2015), two prominent techniques may be
implemented as shown in Figures 5 & 6:
1.	 Rapid Impact Compaction
2.	 Dynamic Compaction
A brief description with the principle of both techniques is
given as follows:
Rapid Impact Compaction: Rapid Impact Compaction is a
cheaper and faster alternative to conventional roller compaction,
typically implemented for shallow compaction of soil within a
thickness of 5m. The technique is implemented on granular or
coarse-grained soils, however, it may be implemented for soil
types with fine content up to 20%. The principle of Rapid Impact
Compaction involves compaction of soil, as a result of energy
transferred by the repeated free fall of a hammer, on a set grid
spacing. The number of blows, height of fall and the set grid are
optimized in real-time, as a function of the behaviour of the ground
reaction and penetration, to deliver the most optimum results. A
work sequence of the Rapid Impact Compaction technique is shown
in Figure 3.
Figure 3: Rapid Impact Compaction Work Sequence
Dynamic Compaction: Dynamic Compaction is a cheaper and
faster alternative to Vibro-Compaction (VC), typically implemented
for treatment of soils within a thickness of 8-10m. The technique
is implemented on granular or coarse grained soils, however, it
may be implemented for soil types with fine content up to 30%.
The principle of Dynamic Compaction involves compaction of
soil, as a result of energy transferred by the repeated free fall of a
Heavy Pounder, on a set grid spacing. The number of blows, height
of fall and the set grid are optimized in real-time, as a function of
the behaviour of the ground reaction and penetration, to deliver
Journal of Civil Engineering Inter Disciplinaries
https://journalofcivilengg.com
Helics Group
28
the most optimum results. A work sequence of the Dynamic
Compaction method is shown in Figure 4.
Figure 4: Dynamic Compaction Work Sequence
Figure 5: Improvement technique suggestion based on soil type
and depth of improvement (Braiek, 2017)
Figure 6: Compatibility of techniques based on soil type (Han,
2015)
In an attempt to meet the short project duration, an optimized
strategy had to be defined. The project design consisting of the fol-
lowing criteria to be achieved by soil improvement works.
Settlement and Bearing Capacity Criteria
An embedment of 1.3m was to be considered for the following foun-
dation designs shown in Table 2.
Table 2: Foundations considered for Analysis
Type of Footing Footing Size AllowableBearing
Capacity(kPa)
Allowable
Settlement
(mm)
Isolated/
Spread
1.0 x 1.0 m2
250 25
1.5 x 1.5 m2
180
2.0 x 2.0 m2
145
2.5 x 2.5 m2
125
3.0 x 3.0 m2
110
Strip Width 0.7m 240
Width 1.0m 185
Width 1.5m 143
Width 2.0 m 125
Liquefaction
The following liquefaction criteria was to be achieved after soil im-
provement works.
• Minimum Factor of Safety against Liquefaction: 1.2
• Peak Ground Acceleration (PGA): 0.07g
• Magnitude (M): 4.0
The assessment of Liquefaction Risk Potential was to be carried
out implementing Youd et al. (2001). Within the summary report
by Youd et al. (2001), it is explained how the Cyclic Stress Ratio is
determined (implementing average shear stress and stress reduc-
tion factor by Seed and Idriss (1971) and Blake (1996), both cited
in Youd et al. (2001)). Following which Cyclic Resistance Ratio is
calculated for a 7.5 magnitude earthquake (using Rauch (1998) as
cited in Youd et al. (2001)). A Magnitude Scaling Factor (after Youd
et al. (2001)) is applied to the applicable design and the Factor of
Safety is assessed, where resistance is larger than the stress pre-
dicted.
Fill Compaction – Performance Line
The compacted fill was to meet required density based on project
specifications. Minimum relative density of 85% after fill compac-
tion works was required (fill thickness of 3m).
Relative density is estimated by reverse calculating the required
degree of relative density (Rd) to cone tip resistance (qc) values
based on a standard, thereby creating performance lines and com-
paring them to the post compaction cone resistance values. For the
proposed improvement strategy explained herein, a performance
Journal of Civil Engineering Inter Disciplinaries
https://journalofcivilengg.com
Helics Group
29
line for qc values has been developed according to three correlation
formulas for relative density of 85% as shown in Figures 7 & 8.
Figure 7: Design Standards considered for Relative Density
Assessment
Figure 8: Target Performance Lines (Rd = 85%) for cone tip resis-
tance (qc) as minimum
Technique Parameter Range Citation
Dynamic
Compaction
Energy 235.25 – 329.35 kJ/m3
(Hussin, 2006)
General Parameters
Diameter of Tamper: 2.2-2.5m
Tamper Weight:
10-40 Tons
Grid Spacing:
1.5 -2.5x (Tamper Diameter)
Height of Drop:
10-25m
•	 Rouaiguia and
Al-Zahrani (2002)
•	 Lukas (1995)
Energy Estimation Lukas (1995)
Rapid
Impact
Compaction
Energy 150 kJ/m3
(Han, 2015)
General Parameters
Diameter of Hammer: 1.5-2.0m
Tamper Weight:
9-16 Tons
Grid Spacing:
Primary: 6 x 6m2
Tertiary: 3 x 3m2
(adjusted based on soil conditions,
tamper weight and trial, preliminary
grid size shall be assessed
empirically)
Height of Drop:
Up to 1.2m (depending on equipment)
•	 Chu et al. (2009)
•	 Braiek (2017)
•	 Han (2015)
Energy Estimation Please refer Eq. (1) Lukas (1995)
2
( )
N W H P
E
grid spacing
× × ×
=
(1)
Hypothesis
In the current hypothesis section, the authors detail the prelimi-
nary scenario, predicted duration and closing to meet the 6-month
time duration.
Reviewing data from previous studies, Table 3 summarizes general
parameters for both techniques.
Table 3: Dynamic Compaction and Rapid Impact Compaction
General Production Parameters
Note:
−	 Energy = (drop height x weight x number of drops) / soil
volume expecting compacted.
−	 Number of passes should be kept as less as possible,
preferably two, but can exceed based on soil conditions
(Lukas, 1995).
−	 The depth of improvement assessment of Dynamic
Compaction cannot be applied to Rapid Impact Compaction,
instead categorical depth of improvement based on soil type
and energy applied should be considered (Han, 2015).
The aim was to attain a minimum of 1,154m2
of working days (26
days per month) production, with the added time allotted for earth-
work filling works.
Equipment were in vicinity of the site and the mobilization and
set up task could be completed in one working week. As per Khan
(2019), the rate of production for both techniques may be assumed
as follows,
•	 Rapid Impact Compaction: 75,000 m2
/ month (per rig under
one shift per day)
•	 Dynamic Compaction: 35,000 m2
/ month (per rig under one
shift per day)
Duration was to be slightly adjusted further for site conditions, soil
conditions and other supplementary factors.
In attempt to provide a value engineered design, supplementary
pre-investigation works were required. The same would then be
reviewed along with the earthwork design, to effectively segregate
areas where either technique would be applicable. In addition to
the same, where applicable, the techniques would be designed in
combination with one another, to boost production and provide a
value engineered design.
Method – Ground Improvement
The designed testing regime consisted of varying frequency of
Piezocone Penetration tests (CPTu) with respect to the areas desig-
nated either for structures or for roads. To simplify the same, a fre-
quency of 4,000m2
can be considered for each Pre-CPTu as shown
in Figure 9.
Journal of Civil Engineering Inter Disciplinaries
https://journalofcivilengg.com
Helics Group
30
Figures 9 & 10 aid in understanding the segregation of areas based
on expected soil improvement to be carried out.
Figure 9: Pre-Investigation CPTu Campaign and Segregated Area
Figure 10: Priority Zones and Other Areas of the Project
Journal of Civil Engineering Inter Disciplinaries
https://journalofcivilengg.com
Helics Group
31
Based on the results of the pre-investigation campaign by the soil
improvement contractor and the earthworks design, the entire
project area was segregated into the following soil improvement
scenarios as given in Figure 11.
Stage 1: Dynamic Compaction from Existing Ground Level
Stage 2: Rapid Impact Compaction after Fill Works
Figure 11: Soil Improvement Scenarios Chart
Note: The chart above represents cross-sections of improvement methodology deployed during actual works. The elevations mentioned,
are related to the cross-sections with respect to the existing ground level considered 0.0 for the sake of easier understanding. The Final
Ground Level on the project ranged from +7.0m to +10.5m.
Journal of Civil Engineering Inter Disciplinaries
https://journalofcivilengg.com
Helics Group
32
The estimated quantities of the scenarios mentioned in Figures 10
& 11 were as follows:
•	 Dynamic Compaction after fill placement: 104,000m2
•	 Rapid Impact Compaction after fill placement: 76,000m2
•	 Dynamic Compaction and Rapid Impact Compaction in
Combination
Stage 1: Dynamic Compaction to improve existing soil – 16,000m2
Stage 2: Rapid Impact Compaction for fill compaction – 16,000m2
A preliminary project duration analysis was conducted in-line with
the production details previously mentioned, which were further
adjusted to site conditions and supplementary factors. The project
duration was limited to 6 months as required and a Gannt Chart for
the same is presented in Figure 12.
Figure 12: Preliminary production duration analysis GANNT Chart
Based on the results of the project duration analysis, it was deter-
mined, implementing both Rapid Impact Compaction and Dynamic
Compaction, independently and in combination with one another,
with just one rig for each technique, the project could successfully
be complemented in a little under 5 months. Taking a safe estima-
tion of two working weeks for Calibration Works, the preliminary
project duration was assumed to be 5.2 months which was in-line
with the fast-track 6-months project requirement.
The basis of designing operation parameters for Dynamic Compac-
tion and Rapid Impact Compaction techniques are detailed in Table
3. Based on the same, the following were deduced (subject to ad-
justment and further calibration during Trial Works).
In the exercise, general parameters based on soil type, expected
soil behavior and required depth of influence were assumed, while
trying to meet energy requirement for both techniques based on
minimum energy required, as mentioned in Table 3.
Dynamic Compaction
( )
( )
15 20.87 15 2
260.89 2
2
6
× × ×
=
Using a 23 Ton pounder, with 15m height of drop, over a 6 x 6 m2
grid spacing, for a total of 15 blows and 2 passes (discounting the
ironing pass), the required energy can be attained. Dynamic Com-
paction works were further calibrated during Trials with parame-
ters in a similar range.
Rapid Impact Compaction
( )
( )
60 14.51 1.1 2
150 3
2
3.5
× × ×
=
Using a 16 Ton Hammer, with 1.1m height of drop, over a 3.5 x 3.5
m2
grid spacing, for a total of 60 blows and 2 passes (discounting
the ironing pass), the required energy can be attained. Rapid Im-
pact Compaction works were further calibrated during Trials with
parameters in similar ranges.
Results and Discussion
Calibration works were carried out for both techniques considered
in the study. Three grid spacing were considered for the trials of
both techniques as follows,
Journal of Civil Engineering Inter Disciplinaries
https://journalofcivilengg.com
Helics Group
33
•	 Dynamic Compaction
•	 Grid A : 5.0 x 5.0 m2
•	 Grid B : 5.5 x 5.5 m2
•	 Grid C : 6.0 x 6.0 m2
•	 Rapid Impact Compaction
•	 Grid A : 3.5 x 3.5 m2
•	 Grid B : 4.0 x 4.0 m2
•	 Grid C : 4.5 x 4.5 m2
Successful completion of calibration works identified optimum
production parameters shown in Table 4, i.e. parameter with which
the required soil improvement can be achieved while avoiding
overdesign of operations.
Table 4: Operation parameters adopted for general production
works
Technique Production Parameters
Dynamic Compaction
Grid C: 6 x 6 m2
Weight of Pounder: 23 Ton
Height of Drops: 15m
Number of Blows: 15
Rapid Impact Compaction
Grid C: 4.5 x 4.5 m2
Weight of Hammer: 16 Ton
Height of Drops: 0.9m
Number of Blows: 60
Note: General production parameters may vary based on soil
conditions and soil behavior during actual soil improvement
works
Figure 13 (a & b) illustrate the efficiency of applied improvement
works during calibration works for both techniques considered.
Figure 13: Pre & Post CPTu at Trial Areas (a) Dynamic
Compaction (b) Rapid Impact Compaction
Soil Improvement works lasted 4.5 month. Verification of design
criteria (as mentioned in section 3) were performed following
guideline references as mentioned below:
•	 Bearing Capacity Assessment: Eslaamizaad and Robertson
(1996).
•	 Settlement Assessment: Schmertmann et al. (1978).
•	 Relative Density: As mentioned in section 3.
•	 Liquefaction Risk Assessment: Based on the summary report on
evaluation of the liquefaction resistance of soils by Youd et al.
(2001) as briefly described in section 3.
The achievement of design criteria is shown in Figures 14 to 16.
Figure 14: Strip foundation bearing capacity and settlement assessment
Journal of Civil Engineering Inter Disciplinaries
https://journalofcivilengg.com
Helics Group
34
Figure 16: Liquefaction Risk Assessment
Figure 15: Isolated foundation bearing capacity and settlement assessment
Journal of Civil Engineering Inter Disciplinaries
https://journalofcivilengg.com
Helics Group
35
Following soil improvement works, all design criteria requirements
were met by all performed Post CPTu’s, proving the value engi-
neered design of combination of Dynamic Compaction and Rapid
Impact Compaction for the current project, a success in terms of
both, the efficiency in improving the soil and a time efficient strat-
egy.
Future Research
Similar to the chart attached in Figure 5 (Braiek, 2017), the authors
devised a similar chart to determine value engineering soil im-
provement technique based on applicable soil conditions as shown
in Figure 17.
Figure 17: Selection of soil improvement technique based in value
engineering
Figure 17 includes the inclusion of High Energy Impact Compac-
tion (HEIC) and Rapid Impact Compaction (RIC) to the pre-existing
chart as cost-effective solutions to granular soils. In terms of future
studies, the authors suggest research into a new technique, which
may be called Rapid Impact Replacement (RIR). The aim of the RIR
technique is to provide a cost-effective solution to the treatment of
soft cohesive soils to shallower depths, compared to existing tech-
niques in the industry today. The authors envision an evolution of
the technique from Rapid Impact Compaction, similar to the evolu-
tion of Dynamic Compaction to Dynamic Replacement.
Conclusion
In the current paper, a case study was presented for a fast-track
project, which required the application of soil improvement works
and fill compaction works in combination. Although a number of
techniques exist in the market, in an attempt to meet the strict time
duration constraint, the authors devised a value engineered strat-
egy, involving the combination of Dynamic Compaction and Rapid
Impact Compaction techniques. A review of the strategy, the design
and the project duration analysis was presented in the paper. Fol-
lowing the same, the results of the campaign were provided, verify-
ing the design of the strategy wherein, the project duration require-
ment was met, and the required design criteria was achieved
References
1.	 Baldi G, Bellotti VN, Ghionna N, Jamiolkowski M and Pasqual-
ini E. Interpretation of CPT’s and CPTU’s – 2nd part: Drained
penetration of sands. Proceedings of the 4th International
Geotechnical Seminar Field Instrumentation and in-situ Mea-
surements, Nanyang Technological Institute, Singapore, 25–27
November 1986;143–156.
2.	 Braiek A. Cost effective solution for improving highly heteroge-
neous soil. In: 19th International Conference on Soil Mechan-
ics and Geotechnical Engineering. Seoul. 2017.
3.	 Chu J, Varaksin S, Klotz U, Menge P. Construction processes. In
Proceedings of the International Conference on Soil Mechanics
and Geotechnical Engineering, Alexandria, Egypt. 2009.
4.	 Slaamizaad S, Robertson PK. Cone penetration test to evaluate
bearing capacity of foundation in sands. In Proceedings of the
49th Canadian Geotechnical Conference.1996;429-438.
5.	 Han, J. Principles and Practice of Ground Improvement. Hobo-
ken: Wiley.2015.
6.	 Hussin, James D. “Methods of Soft Ground Improvement.” The
Foundation Engineering Handbook. 2006;529-565.
7.	 Jamiolkowski M, Lo Presti DCF, Manassero M. Evaluation of rel-
ative density and shear strength of sands from CPT and DMT.
In Soil behavior and soft ground construction.2003;201-238.
8.	 KHAN A. Ground Improvement for Ring Beam Tank Founda-
tion compared between Vibro Replacement against combina-
tion of Dynamic Techniques with Numerical Models (MENG
dissertation, Universiti Teknologi Malaysia). 2019.
9.	 Lukas RG. Geotechnical Engineering Circular No. 1: Dynam-
ic Compaction. Washington: U.S. Department of transporta-
tion.1995.
10.	 Rouaiguia A and Al-Zahrani R. Simulation of Soil Dynamic Com-
paction. In: The 6th Saudi Engineering Conference. 2002;223-
231.
11.	 Schmertmann JH. Guidelines for Cone Penetration Test, Perfor-
mance and Design. Federal Highway Administration, Washing-
ton, DC, USA. Report FHWA-TS-78–209. 1978;145.
12.	 Schmertmann JH, Hartman JP , Brown PR. Improved strain in-
fluence factor diagrams. Journal of Geotechnical Engineering
Division, ASCE. 1978;104(8):1131-1135.
13.	 Spyropoulos E, Khan A. Differences between the Geotech-
nical Campaigns at Front-End Engineering Design (FEED)
and Detailed Design—A Case Study. World Journal Of Engi-
neering And Technology. 2020;08(4):590-604. doi: 10.4236/
wjet.2020.84041
14.	 Youd TL, Idriss IM. Liquefaction resistance of soils: sum-
mary report from the 1996 NCEER and 1998 NCEER/NSF
workshops on evaluation of liquefaction resistance of soils.
Journal of geotechnical and geoenvironmental engineering.
2001;127(4):297-313.

More Related Content

What's hot

Ground improvement techniques
Ground improvement techniquesGround improvement techniques
Ground improvement techniques
Rakesh Reddy
 
Rock Mechanics and Rock Cavern Design_ICE HKA
Rock Mechanics and Rock Cavern Design_ICE HKARock Mechanics and Rock Cavern Design_ICE HKA
Rock Mechanics and Rock Cavern Design_ICE HKAKeith Kong
 
Stone column
Stone columnStone column
Stone column
GEOMIND
 
Ground improvement using rapid impact compaction
Ground improvement using rapid impact compactionGround improvement using rapid impact compaction
Ground improvement using rapid impact compaction
Begum Emte Ajom
 
Bearing capacity of shallow foundations by abhishek sharma
Bearing capacity of shallow foundations by abhishek sharma Bearing capacity of shallow foundations by abhishek sharma
Bearing capacity of shallow foundations by abhishek sharma
ABHISHEK SHARMA
 
Stabilization of soil using bitumenous emulsions
Stabilization of soil using bitumenous emulsionsStabilization of soil using bitumenous emulsions
Stabilization of soil using bitumenous emulsions
prashanth kumar
 
Slope stability analysis
Slope stability analysisSlope stability analysis
Slope stability analysis
saurabh kumar
 
Shear Strength of Soils ( Soil Mechanics )
Shear Strength of Soils ( Soil Mechanics )Shear Strength of Soils ( Soil Mechanics )
Shear Strength of Soils ( Soil Mechanics )
pankajdrolia
 
Sub soil exploration
Sub soil explorationSub soil exploration
Sub soil exploration
Surpal Zala
 
Plate load test and its interpretations
Plate load test and its interpretationsPlate load test and its interpretations
Plate load test and its interpretations
Satyartha Saxena
 
Shear Strength of Soil
Shear Strength of SoilShear Strength of Soil
Shear Strength of Soil
Umang Parmar
 
Slope stability
Slope stabilitySlope stability
Slope stability
Dr. Pallavi Badry
 
Cone Penetration Test
Cone Penetration TestCone Penetration Test
Cone Penetration Test
Muftah Aljoat
 
cone Penetration test
cone Penetration testcone Penetration test
cone Penetration test
INDRANIL BANERJEE
 
OpenSees: Seismic stability of nailed soil slopes
OpenSees: Seismic stability of nailed soil slopesOpenSees: Seismic stability of nailed soil slopes
OpenSees: Seismic stability of nailed soil slopes
Dhanaji Chavan
 
Tunnelling & underground design (Topic6-sequential excavation & squeezing)
Tunnelling & underground design (Topic6-sequential excavation & squeezing)Tunnelling & underground design (Topic6-sequential excavation & squeezing)
Tunnelling & underground design (Topic6-sequential excavation & squeezing)
Hamed Zarei
 
CBR Test
CBR TestCBR Test
CBR Test
Priyansh Singh
 
Dynamic Soil Properties
Dynamic Soil PropertiesDynamic Soil Properties
Dynamic Soil Properties
Cristian Soriano-Camelo
 
Geotechnical Engineering-II [Lec #15 & 16: Schmertmann Method]
Geotechnical Engineering-II [Lec #15 & 16: Schmertmann Method]Geotechnical Engineering-II [Lec #15 & 16: Schmertmann Method]
Geotechnical Engineering-II [Lec #15 & 16: Schmertmann Method]
Muhammad Irfan
 
SOIL DYNAMICS - THEORY OF VIBRATIONS
SOIL DYNAMICS - THEORY OF VIBRATIONSSOIL DYNAMICS - THEORY OF VIBRATIONS
SOIL DYNAMICS - THEORY OF VIBRATIONS
Sanjay Thakare
 

What's hot (20)

Ground improvement techniques
Ground improvement techniquesGround improvement techniques
Ground improvement techniques
 
Rock Mechanics and Rock Cavern Design_ICE HKA
Rock Mechanics and Rock Cavern Design_ICE HKARock Mechanics and Rock Cavern Design_ICE HKA
Rock Mechanics and Rock Cavern Design_ICE HKA
 
Stone column
Stone columnStone column
Stone column
 
Ground improvement using rapid impact compaction
Ground improvement using rapid impact compactionGround improvement using rapid impact compaction
Ground improvement using rapid impact compaction
 
Bearing capacity of shallow foundations by abhishek sharma
Bearing capacity of shallow foundations by abhishek sharma Bearing capacity of shallow foundations by abhishek sharma
Bearing capacity of shallow foundations by abhishek sharma
 
Stabilization of soil using bitumenous emulsions
Stabilization of soil using bitumenous emulsionsStabilization of soil using bitumenous emulsions
Stabilization of soil using bitumenous emulsions
 
Slope stability analysis
Slope stability analysisSlope stability analysis
Slope stability analysis
 
Shear Strength of Soils ( Soil Mechanics )
Shear Strength of Soils ( Soil Mechanics )Shear Strength of Soils ( Soil Mechanics )
Shear Strength of Soils ( Soil Mechanics )
 
Sub soil exploration
Sub soil explorationSub soil exploration
Sub soil exploration
 
Plate load test and its interpretations
Plate load test and its interpretationsPlate load test and its interpretations
Plate load test and its interpretations
 
Shear Strength of Soil
Shear Strength of SoilShear Strength of Soil
Shear Strength of Soil
 
Slope stability
Slope stabilitySlope stability
Slope stability
 
Cone Penetration Test
Cone Penetration TestCone Penetration Test
Cone Penetration Test
 
cone Penetration test
cone Penetration testcone Penetration test
cone Penetration test
 
OpenSees: Seismic stability of nailed soil slopes
OpenSees: Seismic stability of nailed soil slopesOpenSees: Seismic stability of nailed soil slopes
OpenSees: Seismic stability of nailed soil slopes
 
Tunnelling & underground design (Topic6-sequential excavation & squeezing)
Tunnelling & underground design (Topic6-sequential excavation & squeezing)Tunnelling & underground design (Topic6-sequential excavation & squeezing)
Tunnelling & underground design (Topic6-sequential excavation & squeezing)
 
CBR Test
CBR TestCBR Test
CBR Test
 
Dynamic Soil Properties
Dynamic Soil PropertiesDynamic Soil Properties
Dynamic Soil Properties
 
Geotechnical Engineering-II [Lec #15 & 16: Schmertmann Method]
Geotechnical Engineering-II [Lec #15 & 16: Schmertmann Method]Geotechnical Engineering-II [Lec #15 & 16: Schmertmann Method]
Geotechnical Engineering-II [Lec #15 & 16: Schmertmann Method]
 
SOIL DYNAMICS - THEORY OF VIBRATIONS
SOIL DYNAMICS - THEORY OF VIBRATIONSSOIL DYNAMICS - THEORY OF VIBRATIONS
SOIL DYNAMICS - THEORY OF VIBRATIONS
 

Similar to Deep Dynamic Compaction and Rapid Impact Compaction Adopted to Treat Loose Soil Formations and Fill Compaction for Large Structures and Roads - Case Study

Mathematical approach-to-simulate-soil-behavior-under-shallow-compaction
Mathematical approach-to-simulate-soil-behavior-under-shallow-compactionMathematical approach-to-simulate-soil-behavior-under-shallow-compaction
Mathematical approach-to-simulate-soil-behavior-under-shallow-compaction
Ahmed Ebid
 
Stone columns as a remedial solution to a compromised roller compaction activ...
Stone columns as a remedial solution to a compromised roller compaction activ...Stone columns as a remedial solution to a compromised roller compaction activ...
Stone columns as a remedial solution to a compromised roller compaction activ...
Hsuain
 
Ijciet 10 01_049
Ijciet 10 01_049Ijciet 10 01_049
Ijciet 10 01_049
IAEME Publication
 
AN INVESTIGATION ON SEISMIC STABILITY OF MINE OVERBURDEN DUMP SLOPE
AN INVESTIGATION ON SEISMIC STABILITY OF MINE OVERBURDEN DUMP SLOPEAN INVESTIGATION ON SEISMIC STABILITY OF MINE OVERBURDEN DUMP SLOPE
AN INVESTIGATION ON SEISMIC STABILITY OF MINE OVERBURDEN DUMP SLOPE
IRJET Journal
 
Stabilization of Lithomargic Soil by Using Different Additives
Stabilization of Lithomargic Soil by Using Different AdditivesStabilization of Lithomargic Soil by Using Different Additives
Stabilization of Lithomargic Soil by Using Different Additives
IRJET Journal
 
4.IS-10262-2019-New-Mix-design.pdf
4.IS-10262-2019-New-Mix-design.pdf4.IS-10262-2019-New-Mix-design.pdf
4.IS-10262-2019-New-Mix-design.pdf
Prasadnb55
 
Is 10262 2019 latest
Is 10262  2019 latestIs 10262  2019 latest
Is 10262 2019 latest
balaji chikkam
 
A Building Frame Experimental Study Supported On Piles
A Building Frame Experimental Study Supported On PilesA Building Frame Experimental Study Supported On Piles
A Building Frame Experimental Study Supported On Piles
IRJET Journal
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and Development
IJERD Editor
 
B1080817
B1080817B1080817
B1080817
IJERD Editor
 
"Real-time Validation of Driven Cast-In-Situ Piles"
"Real-time Validation of Driven Cast-In-Situ Piles""Real-time Validation of Driven Cast-In-Situ Piles"
"Real-time Validation of Driven Cast-In-Situ Piles"
Remedy Geotechnics Ltd
 
Practical Application of GI Technique Rev 0 HAKI pdf
Practical Application of GI Technique Rev 0 HAKI pdfPractical Application of GI Technique Rev 0 HAKI pdf
Practical Application of GI Technique Rev 0 HAKI pdfKeat Wei, Gavin Chung
 
Evaluating 2D numerical simulations of granular columns in level and gently s...
Evaluating 2D numerical simulations of granular columns in level and gently s...Evaluating 2D numerical simulations of granular columns in level and gently s...
Evaluating 2D numerical simulations of granular columns in level and gently s...
Mahir Badanagki, Ph.D.
 
AN INVESTIGATION ON MINE OVERBURDEN DUMP SLOPE STABILITY
AN INVESTIGATION ON MINE OVERBURDEN DUMP SLOPE STABILITYAN INVESTIGATION ON MINE OVERBURDEN DUMP SLOPE STABILITY
AN INVESTIGATION ON MINE OVERBURDEN DUMP SLOPE STABILITY
IRJET Journal
 
CBR Method of Design a Flexible pavement
CBR Method of Design a Flexible pavementCBR Method of Design a Flexible pavement
CBR Method of Design a Flexible pavement
BinayalalPatra
 
Application of Geosynthetics in Pavement Design
Application of Geosynthetics in Pavement DesignApplication of Geosynthetics in Pavement Design
Application of Geosynthetics in Pavement Design
IRJET Journal
 
Stabilizing Slopes using Wastes from Industries
Stabilizing Slopes using Wastes from IndustriesStabilizing Slopes using Wastes from Industries
Stabilizing Slopes using Wastes from Industries
IRJET Journal
 
Performance evaluation of dense bituminous macadam mix a refusal density ap...
Performance evaluation of dense bituminous macadam mix   a refusal density ap...Performance evaluation of dense bituminous macadam mix   a refusal density ap...
Performance evaluation of dense bituminous macadam mix a refusal density ap...
eSAT Journals
 
Performance evaluation of dense bituminous macadam
Performance evaluation of dense bituminous macadamPerformance evaluation of dense bituminous macadam
Performance evaluation of dense bituminous macadam
eSAT Publishing House
 

Similar to Deep Dynamic Compaction and Rapid Impact Compaction Adopted to Treat Loose Soil Formations and Fill Compaction for Large Structures and Roads - Case Study (20)

Mathematical approach-to-simulate-soil-behavior-under-shallow-compaction
Mathematical approach-to-simulate-soil-behavior-under-shallow-compactionMathematical approach-to-simulate-soil-behavior-under-shallow-compaction
Mathematical approach-to-simulate-soil-behavior-under-shallow-compaction
 
Stone columns as a remedial solution to a compromised roller compaction activ...
Stone columns as a remedial solution to a compromised roller compaction activ...Stone columns as a remedial solution to a compromised roller compaction activ...
Stone columns as a remedial solution to a compromised roller compaction activ...
 
Ijciet 10 01_049
Ijciet 10 01_049Ijciet 10 01_049
Ijciet 10 01_049
 
AN INVESTIGATION ON SEISMIC STABILITY OF MINE OVERBURDEN DUMP SLOPE
AN INVESTIGATION ON SEISMIC STABILITY OF MINE OVERBURDEN DUMP SLOPEAN INVESTIGATION ON SEISMIC STABILITY OF MINE OVERBURDEN DUMP SLOPE
AN INVESTIGATION ON SEISMIC STABILITY OF MINE OVERBURDEN DUMP SLOPE
 
Stabilization of Lithomargic Soil by Using Different Additives
Stabilization of Lithomargic Soil by Using Different AdditivesStabilization of Lithomargic Soil by Using Different Additives
Stabilization of Lithomargic Soil by Using Different Additives
 
4.IS-10262-2019-New-Mix-design.pdf
4.IS-10262-2019-New-Mix-design.pdf4.IS-10262-2019-New-Mix-design.pdf
4.IS-10262-2019-New-Mix-design.pdf
 
Is 10262 2019 latest
Is 10262  2019 latestIs 10262  2019 latest
Is 10262 2019 latest
 
A Building Frame Experimental Study Supported On Piles
A Building Frame Experimental Study Supported On PilesA Building Frame Experimental Study Supported On Piles
A Building Frame Experimental Study Supported On Piles
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and Development
 
B1080817
B1080817B1080817
B1080817
 
"Real-time Validation of Driven Cast-In-Situ Piles"
"Real-time Validation of Driven Cast-In-Situ Piles""Real-time Validation of Driven Cast-In-Situ Piles"
"Real-time Validation of Driven Cast-In-Situ Piles"
 
Practical Application of GI Technique Rev 0 HAKI pdf
Practical Application of GI Technique Rev 0 HAKI pdfPractical Application of GI Technique Rev 0 HAKI pdf
Practical Application of GI Technique Rev 0 HAKI pdf
 
International Journal of Engineering Inventions (IJEI), www.ijeijournal.com,c...
International Journal of Engineering Inventions (IJEI), www.ijeijournal.com,c...International Journal of Engineering Inventions (IJEI), www.ijeijournal.com,c...
International Journal of Engineering Inventions (IJEI), www.ijeijournal.com,c...
 
Evaluating 2D numerical simulations of granular columns in level and gently s...
Evaluating 2D numerical simulations of granular columns in level and gently s...Evaluating 2D numerical simulations of granular columns in level and gently s...
Evaluating 2D numerical simulations of granular columns in level and gently s...
 
AN INVESTIGATION ON MINE OVERBURDEN DUMP SLOPE STABILITY
AN INVESTIGATION ON MINE OVERBURDEN DUMP SLOPE STABILITYAN INVESTIGATION ON MINE OVERBURDEN DUMP SLOPE STABILITY
AN INVESTIGATION ON MINE OVERBURDEN DUMP SLOPE STABILITY
 
CBR Method of Design a Flexible pavement
CBR Method of Design a Flexible pavementCBR Method of Design a Flexible pavement
CBR Method of Design a Flexible pavement
 
Application of Geosynthetics in Pavement Design
Application of Geosynthetics in Pavement DesignApplication of Geosynthetics in Pavement Design
Application of Geosynthetics in Pavement Design
 
Stabilizing Slopes using Wastes from Industries
Stabilizing Slopes using Wastes from IndustriesStabilizing Slopes using Wastes from Industries
Stabilizing Slopes using Wastes from Industries
 
Performance evaluation of dense bituminous macadam mix a refusal density ap...
Performance evaluation of dense bituminous macadam mix   a refusal density ap...Performance evaluation of dense bituminous macadam mix   a refusal density ap...
Performance evaluation of dense bituminous macadam mix a refusal density ap...
 
Performance evaluation of dense bituminous macadam
Performance evaluation of dense bituminous macadamPerformance evaluation of dense bituminous macadam
Performance evaluation of dense bituminous macadam
 

Recently uploaded

The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
Kamal Acharya
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
ssuser9bd3ba
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
Kamal Acharya
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
Kamal Acharya
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 

Recently uploaded (20)

The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 

Deep Dynamic Compaction and Rapid Impact Compaction Adopted to Treat Loose Soil Formations and Fill Compaction for Large Structures and Roads - Case Study

  • 1. Journal of Civil Engineering Inter Disciplinaries Volume 1 | Issue 2 Open Access https://journalofcivilengg.com 26 Case Report Deep Dynamic Compaction and Rapid Impact Compaction Adopted to Treat Loose Soil Formations and Fill Compaction for Large Structures and Roads - Case Study Khan A1 , Ahmad J1 , Alshokur H1 , Spyropoulos E2* 1 Soil Improvement Contracting Co., Dammam 32232, Kingdom of Saudi Arabia. 2 Saudi Aramco, Dhahran 31311, Kingdom of Saudi Arabia. Received Date: 26 September, 2020; Accepted Date: 09 October, 2020; Published Date: 13 October,2020 Abstract The current case study is concerning a facility located near Dammam, Saudi Arabia. The project consisted of three main categories of design criteria to be achieved. It included nine Bearing Capacity and Settlement criteria for infinite, combined and isolated foundations, Relative Density (Rd) criterion for Road/Open Areas and Liquefaction Risk Mitigation criterion for the entire site, which encompassed an area of approximately 180,000m2 . The allotted time for soil improvement works was limited to 6 months, due to the project being of fast-track category. The soil profile was composed largely of granular material and the depth of improvement went as deep as 10m. Both Dynamic Compaction and Rapid Impact Compaction are popular techniques in compacting granular material, due to their high efficiency in achieving the design criteria and fast rate of improvement. The techniques are also cost-effective and clean, in terms not requiring water nor electricity for operations compared to Vibro-Improvement counter techniques, proving to be value-engineered options. The improvement area was segregated into three regions based on existing loose soils and fill compaction requirements, wherein the techniques would be implemented independently or in combination with one another. The production works lasted around 4.5 months. Post-Improvement Quality Control tests indicated the achievement of Design Criteria by a substantial margin, exemplifying the efficiency of Deep Dynamic Compaction and Rapid Impact Compaction techniques in terms of achieving the design criteria and a fast rate of production in operations. *Corresponding author: Spyropoulos E, Saudi Aramco, Dhahran 31311, Kingdom of Saudi Arabia. Email : emmanouil.spyropoulos@aramco.com Citation: Spyropoulos E (2020) Deep Dynamic Compaction and Rapid Impact Compaction Adopted to Treat Loose Soil Formations and Fill Compaction for Large Structures and Roads - Case Study. J Civil Engg ID 1(2): 26-35. Introduction The project location is situated in the northeast of Dammam, KSA. The project consisted of structures, parking areas and roads, for a total area of 180,000m2 . The scope of work included existing soil improvement and fill compaction works. The soil composition was mainly granular with presence of stiff fine-grained layers. The project was fast track and required optimized improvement and compaction strategy to meet a 6-month deadline. With the same constrained requirement, roller compaction would prove difficult and an expensive option. The same constraint motivated the need for value-engineered alternatives. The current paper consists of the following abbreviations as defined in Table 1. Table 1: List of Abbreviations Abbreviation Description KSA Kingdom of Saudi Arabia DC Dynamic Compaction DR Dynamic Replacement VC Vibro Compaction VR Vibro Replacement CPTu Piezocone Penetration Test Rd Relative Density qc Cone Tip Resistance Ic Soil Behavior Type Index
  • 2. Journal of Civil Engineering Inter Disciplinaries https://journalofcivilengg.com Helics Group 27 Background Two soil investigation campaigns were conducted prior to improvement-compaction works. The campaigns will hereafter be referred to as SI(A) and SI(B). Both investigations were carried out mostly at the structures locations. As per investigation works conducted by SI(A), the following profile displayed in Figure 1 can be used as a summary of geological conditions. Figure 1: Soil Profile as per SI(A) Two profiles assessed by SI(B) are presented in the Figure 2 (a & b). a b Figure 2: Soil Profiles as determined by SI(B) Although a variation was observed in the two campaigns, a basic knowledge of the profile was attained, that mainly the sub- surface profile consisted of granular material with lenses of fine soils, which required compaction. This granular layer had thickness varying from 4m until 7m. The sub-stratum was typically a stiffer material and ranged from granular to cohesive material with little or no soft cohesive materials predicted in the profile. It is typical for investigations to produce slightly varying results. However, by instilling an adequate Front-End Engineering Design, unexpected conditions may be avoided and a preliminary understanding of the soil conditions in the project can attained prior (Spyropoulos & Khan, 2020). Problem Statement Takingintoaccountthesoilconditions,earthworkrequirements and constrained schedule, optimized strategy for soil improvement and fill compaction requirement was identified. Removal and replacement, followed by conventional layer-by-layer roller compaction would prove expensive and prevent meeting the time schedule. Observing the soil suitability recommendations by Braiek (2017) and Han (2015), two prominent techniques may be implemented as shown in Figures 5 & 6: 1. Rapid Impact Compaction 2. Dynamic Compaction A brief description with the principle of both techniques is given as follows: Rapid Impact Compaction: Rapid Impact Compaction is a cheaper and faster alternative to conventional roller compaction, typically implemented for shallow compaction of soil within a thickness of 5m. The technique is implemented on granular or coarse-grained soils, however, it may be implemented for soil types with fine content up to 20%. The principle of Rapid Impact Compaction involves compaction of soil, as a result of energy transferred by the repeated free fall of a hammer, on a set grid spacing. The number of blows, height of fall and the set grid are optimized in real-time, as a function of the behaviour of the ground reaction and penetration, to deliver the most optimum results. A work sequence of the Rapid Impact Compaction technique is shown in Figure 3. Figure 3: Rapid Impact Compaction Work Sequence Dynamic Compaction: Dynamic Compaction is a cheaper and faster alternative to Vibro-Compaction (VC), typically implemented for treatment of soils within a thickness of 8-10m. The technique is implemented on granular or coarse grained soils, however, it may be implemented for soil types with fine content up to 30%. The principle of Dynamic Compaction involves compaction of soil, as a result of energy transferred by the repeated free fall of a Heavy Pounder, on a set grid spacing. The number of blows, height of fall and the set grid are optimized in real-time, as a function of the behaviour of the ground reaction and penetration, to deliver
  • 3. Journal of Civil Engineering Inter Disciplinaries https://journalofcivilengg.com Helics Group 28 the most optimum results. A work sequence of the Dynamic Compaction method is shown in Figure 4. Figure 4: Dynamic Compaction Work Sequence Figure 5: Improvement technique suggestion based on soil type and depth of improvement (Braiek, 2017) Figure 6: Compatibility of techniques based on soil type (Han, 2015) In an attempt to meet the short project duration, an optimized strategy had to be defined. The project design consisting of the fol- lowing criteria to be achieved by soil improvement works. Settlement and Bearing Capacity Criteria An embedment of 1.3m was to be considered for the following foun- dation designs shown in Table 2. Table 2: Foundations considered for Analysis Type of Footing Footing Size AllowableBearing Capacity(kPa) Allowable Settlement (mm) Isolated/ Spread 1.0 x 1.0 m2 250 25 1.5 x 1.5 m2 180 2.0 x 2.0 m2 145 2.5 x 2.5 m2 125 3.0 x 3.0 m2 110 Strip Width 0.7m 240 Width 1.0m 185 Width 1.5m 143 Width 2.0 m 125 Liquefaction The following liquefaction criteria was to be achieved after soil im- provement works. • Minimum Factor of Safety against Liquefaction: 1.2 • Peak Ground Acceleration (PGA): 0.07g • Magnitude (M): 4.0 The assessment of Liquefaction Risk Potential was to be carried out implementing Youd et al. (2001). Within the summary report by Youd et al. (2001), it is explained how the Cyclic Stress Ratio is determined (implementing average shear stress and stress reduc- tion factor by Seed and Idriss (1971) and Blake (1996), both cited in Youd et al. (2001)). Following which Cyclic Resistance Ratio is calculated for a 7.5 magnitude earthquake (using Rauch (1998) as cited in Youd et al. (2001)). A Magnitude Scaling Factor (after Youd et al. (2001)) is applied to the applicable design and the Factor of Safety is assessed, where resistance is larger than the stress pre- dicted. Fill Compaction – Performance Line The compacted fill was to meet required density based on project specifications. Minimum relative density of 85% after fill compac- tion works was required (fill thickness of 3m). Relative density is estimated by reverse calculating the required degree of relative density (Rd) to cone tip resistance (qc) values based on a standard, thereby creating performance lines and com- paring them to the post compaction cone resistance values. For the proposed improvement strategy explained herein, a performance
  • 4. Journal of Civil Engineering Inter Disciplinaries https://journalofcivilengg.com Helics Group 29 line for qc values has been developed according to three correlation formulas for relative density of 85% as shown in Figures 7 & 8. Figure 7: Design Standards considered for Relative Density Assessment Figure 8: Target Performance Lines (Rd = 85%) for cone tip resis- tance (qc) as minimum Technique Parameter Range Citation Dynamic Compaction Energy 235.25 – 329.35 kJ/m3 (Hussin, 2006) General Parameters Diameter of Tamper: 2.2-2.5m Tamper Weight: 10-40 Tons Grid Spacing: 1.5 -2.5x (Tamper Diameter) Height of Drop: 10-25m • Rouaiguia and Al-Zahrani (2002) • Lukas (1995) Energy Estimation Lukas (1995) Rapid Impact Compaction Energy 150 kJ/m3 (Han, 2015) General Parameters Diameter of Hammer: 1.5-2.0m Tamper Weight: 9-16 Tons Grid Spacing: Primary: 6 x 6m2 Tertiary: 3 x 3m2 (adjusted based on soil conditions, tamper weight and trial, preliminary grid size shall be assessed empirically) Height of Drop: Up to 1.2m (depending on equipment) • Chu et al. (2009) • Braiek (2017) • Han (2015) Energy Estimation Please refer Eq. (1) Lukas (1995) 2 ( ) N W H P E grid spacing × × × = (1) Hypothesis In the current hypothesis section, the authors detail the prelimi- nary scenario, predicted duration and closing to meet the 6-month time duration. Reviewing data from previous studies, Table 3 summarizes general parameters for both techniques. Table 3: Dynamic Compaction and Rapid Impact Compaction General Production Parameters Note: − Energy = (drop height x weight x number of drops) / soil volume expecting compacted. − Number of passes should be kept as less as possible, preferably two, but can exceed based on soil conditions (Lukas, 1995). − The depth of improvement assessment of Dynamic Compaction cannot be applied to Rapid Impact Compaction, instead categorical depth of improvement based on soil type and energy applied should be considered (Han, 2015). The aim was to attain a minimum of 1,154m2 of working days (26 days per month) production, with the added time allotted for earth- work filling works. Equipment were in vicinity of the site and the mobilization and set up task could be completed in one working week. As per Khan (2019), the rate of production for both techniques may be assumed as follows, • Rapid Impact Compaction: 75,000 m2 / month (per rig under one shift per day) • Dynamic Compaction: 35,000 m2 / month (per rig under one shift per day) Duration was to be slightly adjusted further for site conditions, soil conditions and other supplementary factors. In attempt to provide a value engineered design, supplementary pre-investigation works were required. The same would then be reviewed along with the earthwork design, to effectively segregate areas where either technique would be applicable. In addition to the same, where applicable, the techniques would be designed in combination with one another, to boost production and provide a value engineered design. Method – Ground Improvement The designed testing regime consisted of varying frequency of Piezocone Penetration tests (CPTu) with respect to the areas desig- nated either for structures or for roads. To simplify the same, a fre- quency of 4,000m2 can be considered for each Pre-CPTu as shown in Figure 9.
  • 5. Journal of Civil Engineering Inter Disciplinaries https://journalofcivilengg.com Helics Group 30 Figures 9 & 10 aid in understanding the segregation of areas based on expected soil improvement to be carried out. Figure 9: Pre-Investigation CPTu Campaign and Segregated Area Figure 10: Priority Zones and Other Areas of the Project
  • 6. Journal of Civil Engineering Inter Disciplinaries https://journalofcivilengg.com Helics Group 31 Based on the results of the pre-investigation campaign by the soil improvement contractor and the earthworks design, the entire project area was segregated into the following soil improvement scenarios as given in Figure 11. Stage 1: Dynamic Compaction from Existing Ground Level Stage 2: Rapid Impact Compaction after Fill Works Figure 11: Soil Improvement Scenarios Chart Note: The chart above represents cross-sections of improvement methodology deployed during actual works. The elevations mentioned, are related to the cross-sections with respect to the existing ground level considered 0.0 for the sake of easier understanding. The Final Ground Level on the project ranged from +7.0m to +10.5m.
  • 7. Journal of Civil Engineering Inter Disciplinaries https://journalofcivilengg.com Helics Group 32 The estimated quantities of the scenarios mentioned in Figures 10 & 11 were as follows: • Dynamic Compaction after fill placement: 104,000m2 • Rapid Impact Compaction after fill placement: 76,000m2 • Dynamic Compaction and Rapid Impact Compaction in Combination Stage 1: Dynamic Compaction to improve existing soil – 16,000m2 Stage 2: Rapid Impact Compaction for fill compaction – 16,000m2 A preliminary project duration analysis was conducted in-line with the production details previously mentioned, which were further adjusted to site conditions and supplementary factors. The project duration was limited to 6 months as required and a Gannt Chart for the same is presented in Figure 12. Figure 12: Preliminary production duration analysis GANNT Chart Based on the results of the project duration analysis, it was deter- mined, implementing both Rapid Impact Compaction and Dynamic Compaction, independently and in combination with one another, with just one rig for each technique, the project could successfully be complemented in a little under 5 months. Taking a safe estima- tion of two working weeks for Calibration Works, the preliminary project duration was assumed to be 5.2 months which was in-line with the fast-track 6-months project requirement. The basis of designing operation parameters for Dynamic Compac- tion and Rapid Impact Compaction techniques are detailed in Table 3. Based on the same, the following were deduced (subject to ad- justment and further calibration during Trial Works). In the exercise, general parameters based on soil type, expected soil behavior and required depth of influence were assumed, while trying to meet energy requirement for both techniques based on minimum energy required, as mentioned in Table 3. Dynamic Compaction ( ) ( ) 15 20.87 15 2 260.89 2 2 6 × × × = Using a 23 Ton pounder, with 15m height of drop, over a 6 x 6 m2 grid spacing, for a total of 15 blows and 2 passes (discounting the ironing pass), the required energy can be attained. Dynamic Com- paction works were further calibrated during Trials with parame- ters in a similar range. Rapid Impact Compaction ( ) ( ) 60 14.51 1.1 2 150 3 2 3.5 × × × = Using a 16 Ton Hammer, with 1.1m height of drop, over a 3.5 x 3.5 m2 grid spacing, for a total of 60 blows and 2 passes (discounting the ironing pass), the required energy can be attained. Rapid Im- pact Compaction works were further calibrated during Trials with parameters in similar ranges. Results and Discussion Calibration works were carried out for both techniques considered in the study. Three grid spacing were considered for the trials of both techniques as follows,
  • 8. Journal of Civil Engineering Inter Disciplinaries https://journalofcivilengg.com Helics Group 33 • Dynamic Compaction • Grid A : 5.0 x 5.0 m2 • Grid B : 5.5 x 5.5 m2 • Grid C : 6.0 x 6.0 m2 • Rapid Impact Compaction • Grid A : 3.5 x 3.5 m2 • Grid B : 4.0 x 4.0 m2 • Grid C : 4.5 x 4.5 m2 Successful completion of calibration works identified optimum production parameters shown in Table 4, i.e. parameter with which the required soil improvement can be achieved while avoiding overdesign of operations. Table 4: Operation parameters adopted for general production works Technique Production Parameters Dynamic Compaction Grid C: 6 x 6 m2 Weight of Pounder: 23 Ton Height of Drops: 15m Number of Blows: 15 Rapid Impact Compaction Grid C: 4.5 x 4.5 m2 Weight of Hammer: 16 Ton Height of Drops: 0.9m Number of Blows: 60 Note: General production parameters may vary based on soil conditions and soil behavior during actual soil improvement works Figure 13 (a & b) illustrate the efficiency of applied improvement works during calibration works for both techniques considered. Figure 13: Pre & Post CPTu at Trial Areas (a) Dynamic Compaction (b) Rapid Impact Compaction Soil Improvement works lasted 4.5 month. Verification of design criteria (as mentioned in section 3) were performed following guideline references as mentioned below: • Bearing Capacity Assessment: Eslaamizaad and Robertson (1996). • Settlement Assessment: Schmertmann et al. (1978). • Relative Density: As mentioned in section 3. • Liquefaction Risk Assessment: Based on the summary report on evaluation of the liquefaction resistance of soils by Youd et al. (2001) as briefly described in section 3. The achievement of design criteria is shown in Figures 14 to 16. Figure 14: Strip foundation bearing capacity and settlement assessment
  • 9. Journal of Civil Engineering Inter Disciplinaries https://journalofcivilengg.com Helics Group 34 Figure 16: Liquefaction Risk Assessment Figure 15: Isolated foundation bearing capacity and settlement assessment
  • 10. Journal of Civil Engineering Inter Disciplinaries https://journalofcivilengg.com Helics Group 35 Following soil improvement works, all design criteria requirements were met by all performed Post CPTu’s, proving the value engi- neered design of combination of Dynamic Compaction and Rapid Impact Compaction for the current project, a success in terms of both, the efficiency in improving the soil and a time efficient strat- egy. Future Research Similar to the chart attached in Figure 5 (Braiek, 2017), the authors devised a similar chart to determine value engineering soil im- provement technique based on applicable soil conditions as shown in Figure 17. Figure 17: Selection of soil improvement technique based in value engineering Figure 17 includes the inclusion of High Energy Impact Compac- tion (HEIC) and Rapid Impact Compaction (RIC) to the pre-existing chart as cost-effective solutions to granular soils. In terms of future studies, the authors suggest research into a new technique, which may be called Rapid Impact Replacement (RIR). The aim of the RIR technique is to provide a cost-effective solution to the treatment of soft cohesive soils to shallower depths, compared to existing tech- niques in the industry today. The authors envision an evolution of the technique from Rapid Impact Compaction, similar to the evolu- tion of Dynamic Compaction to Dynamic Replacement. Conclusion In the current paper, a case study was presented for a fast-track project, which required the application of soil improvement works and fill compaction works in combination. Although a number of techniques exist in the market, in an attempt to meet the strict time duration constraint, the authors devised a value engineered strat- egy, involving the combination of Dynamic Compaction and Rapid Impact Compaction techniques. A review of the strategy, the design and the project duration analysis was presented in the paper. Fol- lowing the same, the results of the campaign were provided, verify- ing the design of the strategy wherein, the project duration require- ment was met, and the required design criteria was achieved References 1. Baldi G, Bellotti VN, Ghionna N, Jamiolkowski M and Pasqual- ini E. Interpretation of CPT’s and CPTU’s – 2nd part: Drained penetration of sands. Proceedings of the 4th International Geotechnical Seminar Field Instrumentation and in-situ Mea- surements, Nanyang Technological Institute, Singapore, 25–27 November 1986;143–156. 2. Braiek A. Cost effective solution for improving highly heteroge- neous soil. In: 19th International Conference on Soil Mechan- ics and Geotechnical Engineering. Seoul. 2017. 3. Chu J, Varaksin S, Klotz U, Menge P. Construction processes. In Proceedings of the International Conference on Soil Mechanics and Geotechnical Engineering, Alexandria, Egypt. 2009. 4. Slaamizaad S, Robertson PK. Cone penetration test to evaluate bearing capacity of foundation in sands. In Proceedings of the 49th Canadian Geotechnical Conference.1996;429-438. 5. Han, J. Principles and Practice of Ground Improvement. Hobo- ken: Wiley.2015. 6. Hussin, James D. “Methods of Soft Ground Improvement.” The Foundation Engineering Handbook. 2006;529-565. 7. Jamiolkowski M, Lo Presti DCF, Manassero M. Evaluation of rel- ative density and shear strength of sands from CPT and DMT. In Soil behavior and soft ground construction.2003;201-238. 8. KHAN A. Ground Improvement for Ring Beam Tank Founda- tion compared between Vibro Replacement against combina- tion of Dynamic Techniques with Numerical Models (MENG dissertation, Universiti Teknologi Malaysia). 2019. 9. Lukas RG. Geotechnical Engineering Circular No. 1: Dynam- ic Compaction. Washington: U.S. Department of transporta- tion.1995. 10. Rouaiguia A and Al-Zahrani R. Simulation of Soil Dynamic Com- paction. In: The 6th Saudi Engineering Conference. 2002;223- 231. 11. Schmertmann JH. Guidelines for Cone Penetration Test, Perfor- mance and Design. Federal Highway Administration, Washing- ton, DC, USA. Report FHWA-TS-78–209. 1978;145. 12. Schmertmann JH, Hartman JP , Brown PR. Improved strain in- fluence factor diagrams. Journal of Geotechnical Engineering Division, ASCE. 1978;104(8):1131-1135. 13. Spyropoulos E, Khan A. Differences between the Geotech- nical Campaigns at Front-End Engineering Design (FEED) and Detailed Design—A Case Study. World Journal Of Engi- neering And Technology. 2020;08(4):590-604. doi: 10.4236/ wjet.2020.84041 14. Youd TL, Idriss IM. Liquefaction resistance of soils: sum- mary report from the 1996 NCEER and 1998 NCEER/NSF workshops on evaluation of liquefaction resistance of soils. Journal of geotechnical and geoenvironmental engineering. 2001;127(4):297-313.