SlideShare a Scribd company logo
1 of 6
ASSIGNMENT - 101
Table ; Cost/Time Data
Activity Normal
Duration
Weeks
Normal Cost
per Week Rs.
Crashed
Duration
Weeks
Crashed Cost
per Week Rs.
1 - 2 5 4000 3 7000
1 - 3 5 3000 1 8000
2 - 4 10 4000 5 7000
3 - 4 7 4000 2 15000
2 - 6 6 3000 2 10000
4 - 6 11 6000 5 9000
4 - 5 6 3000 4 6000
6 – 7 5 2000 1 12000
5 - 7 4 2000 1 9000
Answers
a)
Activity Normal Duration
Weeks
Crashed Duration
Weeks
Duration after Crash
weeks (Normal
Duration-Crashed
Duration)
1 - 2 5 3 2
1 - 3 5 1 4
2 - 4 10 5 5
3 - 4 7 2 5
2 - 6 6 2 4
4 - 6 11 5 6
4 - 5 6 4 2
6 – 7 5 1 4
5 - 7 4 1 3
Net work Diagram for crashed case scenarios
EF=2 ES=2 4 EF=6 ES=15 4 EF=19
LF=19
2 5 EF=7 6 ES=9 3
4 ES=4 2
ES=0 5 EF=9 ES=9 ES=11
Net work Diagram for normal case scenarios
ES=5 6 EF=11 ES=26 5 EF=31
LF=31
5 10 EF=15 11ES=15
4
5 ES=5 ES=15 6
ES=0 7 EF=12 ES=21
Answer ( b) crashed case scenarios
Activity Duration ES EF(ES+Du) LS(LF-Du) LF TF(LF-ES-D) FF
1 - 2 2 0 2 2 4 2 0
1 - 3 4 0 4 0 4 0 0
2 - 4 5 2 7 4 9 2 2
3 - 4 5 4 9 4 9 0 0
2 - 6 4 2 6 11 15 7 9
4 - 6 6 9 15 9 15 0 0
4 - 5 2 9 11 14 16 5 0
6 – 7 4 15 19 15 19 0 0
5 - 7 3 11 14 16 19 5 5
1
2
3
4
6
5
7
1
2
3
4
6
5
7
2 Answer ( b) Normal case scenarios
Activity Duration ES EF(ES+Du) LS(LF-Du) LF TF(LF-ES-D) FF
1 - 2 5 0 5 0 5 0 0
1 - 3 5 0 5 3 8 3 0
2 - 4 10 5 15 5 15 0 0
3 - 4 7 4 11 8 15 4 3
2 - 6 6 5 11 20 26 15 15
4 - 6 11 15 26 15 26 0 0
4 - 5 6 15 21 21 27 6 0
6 – 7 5 26 31 26 31 0 0
5 - 7 4 21 25 10 31 6 6
Answer ( c)
Project Cost
crashed case scenarios
Activity Duration
Weeks
(After
crashed)
Normal
Cost per
Week Rs.
Normal
cost
Crashed
Duration
Weeks
Crashed
Cost per
Week Rs.
Crashed cost
1 - 2 2 4000 8000 3 7000 21000
1 - 3 4 3000 12000 1 8000 8000
2 - 4 5 4000 20000 5 7000 35000
3 - 4 5 4000 20000 2 15000 30000
2 - 6 4 3000 12000 2 10000 20000
4 - 6 6 6000 36000 5 9000 45000
4 - 5 2 3000 6000 4 6000 24000
6 – 7 4 2000 8000 1 12000 12000
5 - 7 3 2000 6000 1 9000 9000
Total 128,000.00 204,000.00
Total Project Cost = Normal cost +Crashed cost
= 128,000.00 + 204,000.00
= 332,000.00
Normal Case scenarios
Activity Normal
Duration
Weeks
Normal Cost
per Week Rs.
Normal cost
1 - 2 5 4000 20,000.00
1 - 3 5 3000 15,000.00
2 - 4 10 4000 40,000.00
3 - 4 7 4000 28,000.00
2 - 6 6 3000 18,000.00
4 - 6 11 6000 66,000.00
4 - 5 6 3000 18,000.00
6 – 7 5 2000 10,000.00
5 - 7 4 2000 8,000.00
Total =223,000.00
Total Project Cost = Normal cost
= 223,000.00
Answer d) Least cost scenario
By considering Net work Diagram for crashed case scenarios
EF=2 ES=2 4 EF=6 ES=15 4 EF=19
LF=19
2 5 EF=7 6 ES=9 3
4 ES=4 2
ES=0 5 EF=9 ES=9 ES=11
Critical Path
Without affecting critical path ,the activity 1 -2 can be done less crashed duration (1 week)
,the following activities can be done without crashed
Activity 2 -6 = 6 Weeks , 4 -5 =6 Weeks , 5 – 7 = 4 weeks
1
2
3
4
6
5
7
1 3 4 6 7
Least Cost Calculation
Activity Duration
Weeks
(After
crashed)
Normal
Cost per
Week Rs.
Normal
cost Rs
Crashed
Duration
Weeks
Crashed
Cost per
Week Rs.
Crashed cost Rs
1 - 2 4 4000 16000 1 7000 7000
1 - 3 4 3000 12000 1 8000 8000
2 - 4 5 4000 20000 5 7000 35000
3 - 4 5 4000 20000 2 15000 30000
2 - 6 6 3000 18000 - - -
4 - 6 6 6000 36000 5 9000 45000
4 - 5 6 3000 18000
6 – 7 4 2000 8000 1 12000 12000
5 - 7 4 2000 8000
Total = 156,000.00 137,000.00
Total Project Cost = Normal cost +Crashed cost
= 156,000.00 + 137,000.00
= 293,000.00
Method of Duration Total no of weeks Project Cost
Normal 31 223,000.00
Crashed 19 332,000.00
Normal + Crashed 19 293,000.00
By considering above option 3 is considered as least cost scenarios because It is within crashed
duration period less cost .
Total Project least Cost = 293,000.00
Answer e)
Activity Duration ES EF(ES+Du) LS(LF-Du) LF TF(LF-ES-D) FF
1 - 2 4 0 4 0 4 0 0
1 - 3 4 0 4 0 4 0 0
2 - 4 5 4 9 4 9 0 0
3 - 4 5 4 9 4 9 0 0
2 - 6 6 4 10 9 15 5 5
4 - 6 6 9 15 9 15 0 0
4 - 5 6 9 15 9 15 0 0
6 – 7 4 15 19 15 19 0 0
5 - 7 4 15 19 15 19 0 0
Assignment 101

More Related Content

What's hot (12)

2SC4051(SPICE MODEL)
2SC4051(SPICE MODEL)2SC4051(SPICE MODEL)
2SC4051(SPICE MODEL)
 
Z mega product
Z mega productZ mega product
Z mega product
 
Z mega product
Z mega productZ mega product
Z mega product
 
EE201_Assignment2
EE201_Assignment2EE201_Assignment2
EE201_Assignment2
 
Assembly line balancing
Assembly line balancingAssembly line balancing
Assembly line balancing
 
Pert
PertPert
Pert
 
Presentation on eco
Presentation on ecoPresentation on eco
Presentation on eco
 
Dam31303 lab sheet 4
Dam31303 lab sheet 4Dam31303 lab sheet 4
Dam31303 lab sheet 4
 
Canadian Solar
Canadian SolarCanadian Solar
Canadian Solar
 
Svelte
SvelteSvelte
Svelte
 
HOW TO < 今日
HOW TO < 今日HOW TO < 今日
HOW TO < 今日
 
함정의 초기단계 설계영역탐색(design space exploration)의 효과적 적용
함정의 초기단계 설계영역탐색(design space exploration)의 효과적 적용함정의 초기단계 설계영역탐색(design space exploration)의 효과적 적용
함정의 초기단계 설계영역탐색(design space exploration)의 효과적 적용
 

Viewers also liked

Research Blast: A new study on luxury consumers and digital
Research Blast: A new study on luxury consumers and digitalResearch Blast: A new study on luxury consumers and digital
Research Blast: A new study on luxury consumers and digitalBranded Ltd
 
Parapetto anticaduta mh18_maxi
Parapetto anticaduta mh18_maxiParapetto anticaduta mh18_maxi
Parapetto anticaduta mh18_maxiDavide Piscopiello
 
Digital Matters & Music Matters 2012 Wrap Report
Digital Matters & Music Matters 2012 Wrap ReportDigital Matters & Music Matters 2012 Wrap Report
Digital Matters & Music Matters 2012 Wrap ReportBranded Ltd
 
Bamboo sector development+standardization presentation inbar wk 2014 11
Bamboo sector development+standardization presentation inbar wk 2014 11Bamboo sector development+standardization presentation inbar wk 2014 11
Bamboo sector development+standardization presentation inbar wk 2014 11Werner Kosemund
 
GfKs "Asian Sponsorship Survey"
GfKs "Asian Sponsorship Survey"GfKs "Asian Sponsorship Survey"
GfKs "Asian Sponsorship Survey"Branded Ltd
 
Nissan Global Media Center: Brand as Content Creator: The Why’s and the How’s...
Nissan Global Media Center: Brand as Content Creator: The Why’s and the How’s...Nissan Global Media Center: Brand as Content Creator: The Why’s and the How’s...
Nissan Global Media Center: Brand as Content Creator: The Why’s and the How’s...Branded Ltd
 
Platform presentation: Key developments in LINE's collaborations with brands
Platform presentation: Key developments in LINE's collaborations with brandsPlatform presentation: Key developments in LINE's collaborations with brands
Platform presentation: Key developments in LINE's collaborations with brandsBranded Ltd
 
Platform interview: How Sina Weibo builds brands
Platform interview: How Sina Weibo builds brands Platform interview: How Sina Weibo builds brands
Platform interview: How Sina Weibo builds brands Branded Ltd
 

Viewers also liked (16)

Parapetti provvisori mh18
Parapetti provvisori mh18Parapetti provvisori mh18
Parapetti provvisori mh18
 
Parapetto mh100
Parapetto mh100Parapetto mh100
Parapetto mh100
 
Parapetto montante mh011_eco
Parapetto montante mh011_ecoParapetto montante mh011_eco
Parapetto montante mh011_eco
 
Research Blast: A new study on luxury consumers and digital
Research Blast: A new study on luxury consumers and digitalResearch Blast: A new study on luxury consumers and digital
Research Blast: A new study on luxury consumers and digital
 
365반찬
365반찬365반찬
365반찬
 
Parapetto anticaduta mh18_maxi
Parapetto anticaduta mh18_maxiParapetto anticaduta mh18_maxi
Parapetto anticaduta mh18_maxi
 
Parapetti di protezione_mh15
Parapetti di protezione_mh15Parapetti di protezione_mh15
Parapetti di protezione_mh15
 
Parapetto sicurezza mh12
Parapetto sicurezza mh12Parapetto sicurezza mh12
Parapetto sicurezza mh12
 
Digital Matters & Music Matters 2012 Wrap Report
Digital Matters & Music Matters 2012 Wrap ReportDigital Matters & Music Matters 2012 Wrap Report
Digital Matters & Music Matters 2012 Wrap Report
 
Parapetto anticaduta mh78
Parapetto anticaduta mh78Parapetto anticaduta mh78
Parapetto anticaduta mh78
 
Parapetti anticaduta mh 60 it
Parapetti anticaduta mh 60 itParapetti anticaduta mh 60 it
Parapetti anticaduta mh 60 it
 
Bamboo sector development+standardization presentation inbar wk 2014 11
Bamboo sector development+standardization presentation inbar wk 2014 11Bamboo sector development+standardization presentation inbar wk 2014 11
Bamboo sector development+standardization presentation inbar wk 2014 11
 
GfKs "Asian Sponsorship Survey"
GfKs "Asian Sponsorship Survey"GfKs "Asian Sponsorship Survey"
GfKs "Asian Sponsorship Survey"
 
Nissan Global Media Center: Brand as Content Creator: The Why’s and the How’s...
Nissan Global Media Center: Brand as Content Creator: The Why’s and the How’s...Nissan Global Media Center: Brand as Content Creator: The Why’s and the How’s...
Nissan Global Media Center: Brand as Content Creator: The Why’s and the How’s...
 
Platform presentation: Key developments in LINE's collaborations with brands
Platform presentation: Key developments in LINE's collaborations with brandsPlatform presentation: Key developments in LINE's collaborations with brands
Platform presentation: Key developments in LINE's collaborations with brands
 
Platform interview: How Sina Weibo builds brands
Platform interview: How Sina Weibo builds brands Platform interview: How Sina Weibo builds brands
Platform interview: How Sina Weibo builds brands
 

Similar to Assignment 101

construction resource optimization 1.pptx
construction resource optimization 1.pptxconstruction resource optimization 1.pptx
construction resource optimization 1.pptxkimkov119
 
Lecture7_2021_v2.pdf
Lecture7_2021_v2.pdfLecture7_2021_v2.pdf
Lecture7_2021_v2.pdfssuserc9da59
 
Push And Pull Production Systems Chap7 Ppt)
Push And Pull Production Systems   Chap7 Ppt)Push And Pull Production Systems   Chap7 Ppt)
Push And Pull Production Systems Chap7 Ppt)3abooodi
 
Costing assignment.docx
Costing assignment.docxCosting assignment.docx
Costing assignment.docxssuserdcbf4e
 
Projectproposalon10mwsolarpvpowerplant 160312085340 (2)
Projectproposalon10mwsolarpvpowerplant 160312085340 (2)Projectproposalon10mwsolarpvpowerplant 160312085340 (2)
Projectproposalon10mwsolarpvpowerplant 160312085340 (2)Muzaffar Ahmad
 
Project Proposal on 10 MW Solar PV Power Plant
Project Proposal on 10 MW Solar PV Power PlantProject Proposal on 10 MW Solar PV Power Plant
Project Proposal on 10 MW Solar PV Power PlantVignesh Sekar
 
Part 3 Residuals.pdf
Part 3 Residuals.pdfPart 3 Residuals.pdf
Part 3 Residuals.pdfSajawalNawaz5
 
ACC 422 Education Organization / snaptutorial.com
ACC 422  Education Organization / snaptutorial.comACC 422  Education Organization / snaptutorial.com
ACC 422 Education Organization / snaptutorial.comdonaldzs171
 
Pushandpullproductionsystems chap7-ppt-100210005527-phpapp01[1]
Pushandpullproductionsystems chap7-ppt-100210005527-phpapp01[1]Pushandpullproductionsystems chap7-ppt-100210005527-phpapp01[1]
Pushandpullproductionsystems chap7-ppt-100210005527-phpapp01[1]Pankaj Rathod
 
Replacement theory
Replacement theoryReplacement theory
Replacement theoryR A Shah
 
Acc 422 Enhance teaching-snaptutorial.com
Acc 422 Enhance teaching-snaptutorial.comAcc 422 Enhance teaching-snaptutorial.com
Acc 422 Enhance teaching-snaptutorial.comrobertleew1
 
Applied Operation Research (AOR) Replacement Theory
Applied Operation Research (AOR) Replacement TheoryApplied Operation Research (AOR) Replacement Theory
Applied Operation Research (AOR) Replacement TheoryRekha Rani
 
2.-Replacement-and-Retention.pdf
2.-Replacement-and-Retention.pdf2.-Replacement-and-Retention.pdf
2.-Replacement-and-Retention.pdf18010YeashRahman
 

Similar to Assignment 101 (20)

construction resource optimization 1.pptx
construction resource optimization 1.pptxconstruction resource optimization 1.pptx
construction resource optimization 1.pptx
 
Lecture7_2021_v2.pdf
Lecture7_2021_v2.pdfLecture7_2021_v2.pdf
Lecture7_2021_v2.pdf
 
Push And Pull Production Systems Chap7 Ppt)
Push And Pull Production Systems   Chap7 Ppt)Push And Pull Production Systems   Chap7 Ppt)
Push And Pull Production Systems Chap7 Ppt)
 
Costing assignment.docx
Costing assignment.docxCosting assignment.docx
Costing assignment.docx
 
Projectproposalon10mwsolarpvpowerplant 160312085340 (2)
Projectproposalon10mwsolarpvpowerplant 160312085340 (2)Projectproposalon10mwsolarpvpowerplant 160312085340 (2)
Projectproposalon10mwsolarpvpowerplant 160312085340 (2)
 
Project Proposal on 10 MW Solar PV Power Plant
Project Proposal on 10 MW Solar PV Power PlantProject Proposal on 10 MW Solar PV Power Plant
Project Proposal on 10 MW Solar PV Power Plant
 
Part 3 Residuals.pdf
Part 3 Residuals.pdfPart 3 Residuals.pdf
Part 3 Residuals.pdf
 
ACC 422 Education Organization / snaptutorial.com
ACC 422  Education Organization / snaptutorial.comACC 422  Education Organization / snaptutorial.com
ACC 422 Education Organization / snaptutorial.com
 
Pushandpullproductionsystems chap7-ppt-100210005527-phpapp01[1]
Pushandpullproductionsystems chap7-ppt-100210005527-phpapp01[1]Pushandpullproductionsystems chap7-ppt-100210005527-phpapp01[1]
Pushandpullproductionsystems chap7-ppt-100210005527-phpapp01[1]
 
Crashing
CrashingCrashing
Crashing
 
Log11 uitwerking opdrachten
Log11 uitwerking opdrachtenLog11 uitwerking opdrachten
Log11 uitwerking opdrachten
 
Unit 2 prodn
Unit 2 prodnUnit 2 prodn
Unit 2 prodn
 
Replacement theory
Replacement theoryReplacement theory
Replacement theory
 
Acc 422 Enhance teaching-snaptutorial.com
Acc 422 Enhance teaching-snaptutorial.comAcc 422 Enhance teaching-snaptutorial.com
Acc 422 Enhance teaching-snaptutorial.com
 
project designa.docx
project designa.docxproject designa.docx
project designa.docx
 
Applied Operation Research (AOR) Replacement Theory
Applied Operation Research (AOR) Replacement TheoryApplied Operation Research (AOR) Replacement Theory
Applied Operation Research (AOR) Replacement Theory
 
Time-Cost Tradeoff by Examples
Time-Cost Tradeoff by ExamplesTime-Cost Tradeoff by Examples
Time-Cost Tradeoff by Examples
 
Engineering Economy Final review-2011
Engineering Economy Final review-2011Engineering Economy Final review-2011
Engineering Economy Final review-2011
 
Theory of cost
Theory of costTheory of cost
Theory of cost
 
2.-Replacement-and-Retention.pdf
2.-Replacement-and-Retention.pdf2.-Replacement-and-Retention.pdf
2.-Replacement-and-Retention.pdf
 

Assignment 101

  • 1. ASSIGNMENT - 101 Table ; Cost/Time Data Activity Normal Duration Weeks Normal Cost per Week Rs. Crashed Duration Weeks Crashed Cost per Week Rs. 1 - 2 5 4000 3 7000 1 - 3 5 3000 1 8000 2 - 4 10 4000 5 7000 3 - 4 7 4000 2 15000 2 - 6 6 3000 2 10000 4 - 6 11 6000 5 9000 4 - 5 6 3000 4 6000 6 – 7 5 2000 1 12000 5 - 7 4 2000 1 9000 Answers a) Activity Normal Duration Weeks Crashed Duration Weeks Duration after Crash weeks (Normal Duration-Crashed Duration) 1 - 2 5 3 2 1 - 3 5 1 4 2 - 4 10 5 5 3 - 4 7 2 5 2 - 6 6 2 4 4 - 6 11 5 6 4 - 5 6 4 2 6 – 7 5 1 4 5 - 7 4 1 3
  • 2. Net work Diagram for crashed case scenarios EF=2 ES=2 4 EF=6 ES=15 4 EF=19 LF=19 2 5 EF=7 6 ES=9 3 4 ES=4 2 ES=0 5 EF=9 ES=9 ES=11 Net work Diagram for normal case scenarios ES=5 6 EF=11 ES=26 5 EF=31 LF=31 5 10 EF=15 11ES=15 4 5 ES=5 ES=15 6 ES=0 7 EF=12 ES=21 Answer ( b) crashed case scenarios Activity Duration ES EF(ES+Du) LS(LF-Du) LF TF(LF-ES-D) FF 1 - 2 2 0 2 2 4 2 0 1 - 3 4 0 4 0 4 0 0 2 - 4 5 2 7 4 9 2 2 3 - 4 5 4 9 4 9 0 0 2 - 6 4 2 6 11 15 7 9 4 - 6 6 9 15 9 15 0 0 4 - 5 2 9 11 14 16 5 0 6 – 7 4 15 19 15 19 0 0 5 - 7 3 11 14 16 19 5 5 1 2 3 4 6 5 7 1 2 3 4 6 5 7
  • 3. 2 Answer ( b) Normal case scenarios Activity Duration ES EF(ES+Du) LS(LF-Du) LF TF(LF-ES-D) FF 1 - 2 5 0 5 0 5 0 0 1 - 3 5 0 5 3 8 3 0 2 - 4 10 5 15 5 15 0 0 3 - 4 7 4 11 8 15 4 3 2 - 6 6 5 11 20 26 15 15 4 - 6 11 15 26 15 26 0 0 4 - 5 6 15 21 21 27 6 0 6 – 7 5 26 31 26 31 0 0 5 - 7 4 21 25 10 31 6 6 Answer ( c) Project Cost crashed case scenarios Activity Duration Weeks (After crashed) Normal Cost per Week Rs. Normal cost Crashed Duration Weeks Crashed Cost per Week Rs. Crashed cost 1 - 2 2 4000 8000 3 7000 21000 1 - 3 4 3000 12000 1 8000 8000 2 - 4 5 4000 20000 5 7000 35000 3 - 4 5 4000 20000 2 15000 30000 2 - 6 4 3000 12000 2 10000 20000 4 - 6 6 6000 36000 5 9000 45000 4 - 5 2 3000 6000 4 6000 24000 6 – 7 4 2000 8000 1 12000 12000 5 - 7 3 2000 6000 1 9000 9000 Total 128,000.00 204,000.00 Total Project Cost = Normal cost +Crashed cost = 128,000.00 + 204,000.00 = 332,000.00
  • 4. Normal Case scenarios Activity Normal Duration Weeks Normal Cost per Week Rs. Normal cost 1 - 2 5 4000 20,000.00 1 - 3 5 3000 15,000.00 2 - 4 10 4000 40,000.00 3 - 4 7 4000 28,000.00 2 - 6 6 3000 18,000.00 4 - 6 11 6000 66,000.00 4 - 5 6 3000 18,000.00 6 – 7 5 2000 10,000.00 5 - 7 4 2000 8,000.00 Total =223,000.00 Total Project Cost = Normal cost = 223,000.00 Answer d) Least cost scenario By considering Net work Diagram for crashed case scenarios EF=2 ES=2 4 EF=6 ES=15 4 EF=19 LF=19 2 5 EF=7 6 ES=9 3 4 ES=4 2 ES=0 5 EF=9 ES=9 ES=11 Critical Path Without affecting critical path ,the activity 1 -2 can be done less crashed duration (1 week) ,the following activities can be done without crashed Activity 2 -6 = 6 Weeks , 4 -5 =6 Weeks , 5 – 7 = 4 weeks 1 2 3 4 6 5 7 1 3 4 6 7
  • 5. Least Cost Calculation Activity Duration Weeks (After crashed) Normal Cost per Week Rs. Normal cost Rs Crashed Duration Weeks Crashed Cost per Week Rs. Crashed cost Rs 1 - 2 4 4000 16000 1 7000 7000 1 - 3 4 3000 12000 1 8000 8000 2 - 4 5 4000 20000 5 7000 35000 3 - 4 5 4000 20000 2 15000 30000 2 - 6 6 3000 18000 - - - 4 - 6 6 6000 36000 5 9000 45000 4 - 5 6 3000 18000 6 – 7 4 2000 8000 1 12000 12000 5 - 7 4 2000 8000 Total = 156,000.00 137,000.00 Total Project Cost = Normal cost +Crashed cost = 156,000.00 + 137,000.00 = 293,000.00 Method of Duration Total no of weeks Project Cost Normal 31 223,000.00 Crashed 19 332,000.00 Normal + Crashed 19 293,000.00 By considering above option 3 is considered as least cost scenarios because It is within crashed duration period less cost . Total Project least Cost = 293,000.00 Answer e) Activity Duration ES EF(ES+Du) LS(LF-Du) LF TF(LF-ES-D) FF 1 - 2 4 0 4 0 4 0 0 1 - 3 4 0 4 0 4 0 0 2 - 4 5 4 9 4 9 0 0 3 - 4 5 4 9 4 9 0 0 2 - 6 6 4 10 9 15 5 5 4 - 6 6 9 15 9 15 0 0 4 - 5 6 9 15 9 15 0 0 6 – 7 4 15 19 15 19 0 0 5 - 7 4 15 19 15 19 0 0