This document discusses corrosion management and the implementation of IMO standards on floating storage and offloading (FSO) and floating production storage and offloading (FPSO) vessels in Indonesia. It provides an overview of Indonesia's offshore oil and gas operations, detailing the types and numbers of marine vessels used. It then focuses on corrosion management systems for FSOs/FPSOs, outlining the objectives and basic processes. Challenges in corrosion management are also discussed. Finally, it touches on implementing the IMO's Performance Standard for Protective Coatings on these vessels.
Supply chain management of rig & fpso- floating production,storage and offloa...Tochukwu Ben Anozie
Lack of clarity relating to contract responsibilities leads to unwanted surprises
Quantify delays, cost overruns and examine the reasons behind the ailing fpso supply chain
Role of the oil companies, development complexity, regulation and conflicts of interest within the value chain
Supply chain management of rig & fpso- floating production,storage and offloa...Tochukwu Ben Anozie
Lack of clarity relating to contract responsibilities leads to unwanted surprises
Quantify delays, cost overruns and examine the reasons behind the ailing fpso supply chain
Role of the oil companies, development complexity, regulation and conflicts of interest within the value chain
ANNEX V MARPOL 73/78 MERUPAKAN PERATURAN PENCEGAHAN PENCEMARAN SAMPAH DARI KAPAL
BANYAK KAPAL-KAPAL YANG LALAI MEMENUHI ATURAN INI, MUNGKIN KARENA BELUM MENGERTI ATURAN INI, ATAU MEMANG SENGAJA MENGABAIKANNYA, SEHINGGA LAUT, PANTAI, SUNGAI DAN DANAU TERCEMAR OLEH SAMPAH, KHUSUSNYA SAMPAH PLASTIC.
MUDAH-MUDAHAN SLIDE INI DAPAT MENAMBAH WAWASAN BAGI PELAUT PEMULA, CADETS DAN PERWIRA JUNIOR.
CLEAN SHIP, CLEAN SEAS.
WASALAM !
follow me on youtube:
http://www.youtube.com/channel/UC793T-JDti4aDAa_tf5aQIA
Decoding SOLAS (Safety of Life at Sea) by SHM ShipcareSHM Shipcare
105 years ago, on the same day - April 15th, the World witnessed the most disastrous shipping accident of all times - The Titanic. Legendary in every sense, RMS Titanic was designed by the Irish shipbuilder William Pirrie and built in Belfast, and was thought to be the world’s fastest ship. It spanned 883 feet from stern to bow, and its hull was divided into 16 compartments that were presumed to be watertight. Titanic was presumed to be unsinkable. But, no one had thought about the damage, an iceberg could cause. Only 10% of an iceberg is seen above the water while the rest lies below it. While in the final leg of it's journey from England to New York, the luxurious cruise liner failed to change its course and damaged its hull, causing water to flood into all the compartments, eventually leading to the ship breaking in half and a human loss of 1522 passengers. This disaster has served as a lesson for the shipping fraternity which gave birth to SOLAS and International Ice Patrol. Read more about SOLAS in our exclusive post here: http://www.shmgroup.com/blog/understanding-shipping-safety-with-solas/
INTRODUCING MY PROFILE,
DENGAN MODAL SERTIFIKAT MPT (MUALIM PELAYARAN TERBATAS) SEKARANG DISEBUT ANT-V/DECK OFFICER CLASS V, SAYA YANG LULUSAN STMN2 LULUSAN BANGUNAN, MERUBAH HALUAN JALAN HIDUP YANG TENTUNYA MERUPAKAN RANCANGAN TUHAN, MENJADI PELAUT DENGAN JABATAN DASAR YAITU SEBAGAI ORDINARY SEAMAN (OS), DAN MENINGKAT KEJABATAN YANG LEBIH TINGGI SEBAGAI ABLE BODY (AB) HINGGA AKHIRNYA MENJADI PERWIRA DAN KEPOSISI NAKHODA DENGAN IJAZAH YANG SESUAI SEBAGAIMANA TERTUANG DALAM ITRODUCING.
DEMIKIANLAH BAHWA YANG TERBERAT DIDUNIA INI HANYA SATU YAITU "KEMAUAN".
FOLLOW MY YOUTUBE CHANNEL:
https://www.youtube.com/channel/UC793T-JDti4aDAa_tf5aQlA
Belajar, Belajar dan Belajar hingga tidak bisa Belajar sama sekali.
3B = Belajar, Berubah agar Berkembang.
Sudah Belajar tidak Berubah tidak akan Berkembang.
Many Thanks,
Rob'Wild
Capt. Persobi Waldemar. M
Challenges to Deepwater West Africa DevelopmentsDylan Roberts
@Richard Luff shares an overview on whats happening offshore West Africa – discusses common challenges and potential solutions operators can implement to avoid pitfalls. Hint, local content is key.
ANNEX V MARPOL 73/78 MERUPAKAN PERATURAN PENCEGAHAN PENCEMARAN SAMPAH DARI KAPAL
BANYAK KAPAL-KAPAL YANG LALAI MEMENUHI ATURAN INI, MUNGKIN KARENA BELUM MENGERTI ATURAN INI, ATAU MEMANG SENGAJA MENGABAIKANNYA, SEHINGGA LAUT, PANTAI, SUNGAI DAN DANAU TERCEMAR OLEH SAMPAH, KHUSUSNYA SAMPAH PLASTIC.
MUDAH-MUDAHAN SLIDE INI DAPAT MENAMBAH WAWASAN BAGI PELAUT PEMULA, CADETS DAN PERWIRA JUNIOR.
CLEAN SHIP, CLEAN SEAS.
WASALAM !
follow me on youtube:
http://www.youtube.com/channel/UC793T-JDti4aDAa_tf5aQIA
Decoding SOLAS (Safety of Life at Sea) by SHM ShipcareSHM Shipcare
105 years ago, on the same day - April 15th, the World witnessed the most disastrous shipping accident of all times - The Titanic. Legendary in every sense, RMS Titanic was designed by the Irish shipbuilder William Pirrie and built in Belfast, and was thought to be the world’s fastest ship. It spanned 883 feet from stern to bow, and its hull was divided into 16 compartments that were presumed to be watertight. Titanic was presumed to be unsinkable. But, no one had thought about the damage, an iceberg could cause. Only 10% of an iceberg is seen above the water while the rest lies below it. While in the final leg of it's journey from England to New York, the luxurious cruise liner failed to change its course and damaged its hull, causing water to flood into all the compartments, eventually leading to the ship breaking in half and a human loss of 1522 passengers. This disaster has served as a lesson for the shipping fraternity which gave birth to SOLAS and International Ice Patrol. Read more about SOLAS in our exclusive post here: http://www.shmgroup.com/blog/understanding-shipping-safety-with-solas/
INTRODUCING MY PROFILE,
DENGAN MODAL SERTIFIKAT MPT (MUALIM PELAYARAN TERBATAS) SEKARANG DISEBUT ANT-V/DECK OFFICER CLASS V, SAYA YANG LULUSAN STMN2 LULUSAN BANGUNAN, MERUBAH HALUAN JALAN HIDUP YANG TENTUNYA MERUPAKAN RANCANGAN TUHAN, MENJADI PELAUT DENGAN JABATAN DASAR YAITU SEBAGAI ORDINARY SEAMAN (OS), DAN MENINGKAT KEJABATAN YANG LEBIH TINGGI SEBAGAI ABLE BODY (AB) HINGGA AKHIRNYA MENJADI PERWIRA DAN KEPOSISI NAKHODA DENGAN IJAZAH YANG SESUAI SEBAGAIMANA TERTUANG DALAM ITRODUCING.
DEMIKIANLAH BAHWA YANG TERBERAT DIDUNIA INI HANYA SATU YAITU "KEMAUAN".
FOLLOW MY YOUTUBE CHANNEL:
https://www.youtube.com/channel/UC793T-JDti4aDAa_tf5aQlA
Belajar, Belajar dan Belajar hingga tidak bisa Belajar sama sekali.
3B = Belajar, Berubah agar Berkembang.
Sudah Belajar tidak Berubah tidak akan Berkembang.
Many Thanks,
Rob'Wild
Capt. Persobi Waldemar. M
Challenges to Deepwater West Africa DevelopmentsDylan Roberts
@Richard Luff shares an overview on whats happening offshore West Africa – discusses common challenges and potential solutions operators can implement to avoid pitfalls. Hint, local content is key.
Decommissioning of Offshore InstallationsMuanisa Waras
This training course will help your team improve your decommissioning strategies to reduce your offshore liabilities. Delegates will gain an in-depth understanding of the Asia Pacific market to prepare your company for decommissioning projects in the coming years. Your team will have an overview of the future challenges for the decommissioning market for operators and contractors and the strategies that need to be implemented to move projects forward. You will be able to formulate an effective and efficient decommissioning supply chain of experienced contractors to remove
offshore installations.
FPSO / Floating Production Technology for Offshore Oil & Gas ProductionWalter Lee
The aim of the course is to introduce interested parties to the technology of FPSOs and other Floating Production hosts, and illustrate their use as part of a full Field Development. The course includes many Field Development examples, including several of the most recent additions to the worldwide fleet.
A feature of the course is the incorporation and inclusion of a large number of videos and animations to support the slide presentations. This multimedia mix makes the course
appropriate to professional engineers seeking to extend their knowledge with the latest information; but also makes it accessible to “non-experts” who are seeking a general
overview of such activities.
Oil and Liquefied Gas Tanker Operations is a comprehensive separately bookable course designed to provide participants with a technical perspective of shipping operations. The 4 day course will cover technical designs and features of tankers, operational execution based on charterparty terms, port, cargo and ballasting operations, tank cleaning, safety assessment and procedures, all broken down and discussed in detail. In addition, tanker owners, managers, operators and charterers will learn how to best minimize any operational claims and disputes due to accidents either out at sea or berthing at ports.
INTRODUCTION TO OFFSHORE DRILLING AND PRODUCTION FACILITIESpetroEDGE
This 4 day (separately bookable) intensive training course will cover the details of drilling rigs and how they operate, especially for deepwater activities. Current drilling rigs are highly automated and efficient. These advances will be illustrated with animations and videos. The relationship between drilling and production will be explored with examples of current field developments
This course will concentrate on Offshore Marine Operations and will cover Operational and Managerial requirements for Loadout; Barge Transportation; Towing of Offshore Facilities; Lifting; Steel Jackets; Gravity-Based Structures; Lift-Off, Transportation and Inshore Mating of Topsides; Offshore Pipelines; Marine Operations Overview; Special Topics, and other essential topics related to Export/Import Oil & Gas.
Final project report on grocery store management system..pdfKamal Acharya
In today’s fast-changing business environment, it’s extremely important to be able to respond to client needs in the most effective and timely manner. If your customers wish to see your business online and have instant access to your products or services.
Online Grocery Store is an e-commerce website, which retails various grocery products. This project allows viewing various products available enables registered users to purchase desired products instantly using Paytm, UPI payment processor (Instant Pay) and also can place order by using Cash on Delivery (Pay Later) option. This project provides an easy access to Administrators and Managers to view orders placed using Pay Later and Instant Pay options.
In order to develop an e-commerce website, a number of Technologies must be studied and understood. These include multi-tiered architecture, server and client-side scripting techniques, implementation technologies, programming language (such as PHP, HTML, CSS, JavaScript) and MySQL relational databases. This is a project with the objective to develop a basic website where a consumer is provided with a shopping cart website and also to know about the technologies used to develop such a website.
This document will discuss each of the underlying technologies to create and implement an e- commerce website.
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)MdTanvirMahtab2
This presentation is about the working procedure of Shahjalal Fertilizer Company Limited (SFCL). A Govt. owned Company of Bangladesh Chemical Industries Corporation under Ministry of Industries.
Explore the innovative world of trenchless pipe repair with our comprehensive guide, "The Benefits and Techniques of Trenchless Pipe Repair." This document delves into the modern methods of repairing underground pipes without the need for extensive excavation, highlighting the numerous advantages and the latest techniques used in the industry.
Learn about the cost savings, reduced environmental impact, and minimal disruption associated with trenchless technology. Discover detailed explanations of popular techniques such as pipe bursting, cured-in-place pipe (CIPP) lining, and directional drilling. Understand how these methods can be applied to various types of infrastructure, from residential plumbing to large-scale municipal systems.
Ideal for homeowners, contractors, engineers, and anyone interested in modern plumbing solutions, this guide provides valuable insights into why trenchless pipe repair is becoming the preferred choice for pipe rehabilitation. Stay informed about the latest advancements and best practices in the field.
Immunizing Image Classifiers Against Localized Adversary Attacksgerogepatton
This paper addresses the vulnerability of deep learning models, particularly convolutional neural networks
(CNN)s, to adversarial attacks and presents a proactive training technique designed to counter them. We
introduce a novel volumization algorithm, which transforms 2D images into 3D volumetric representations.
When combined with 3D convolution and deep curriculum learning optimization (CLO), itsignificantly improves
the immunity of models against localized universal attacks by up to 40%. We evaluate our proposed approach
using contemporary CNN architectures and the modified Canadian Institute for Advanced Research (CIFAR-10
and CIFAR-100) and ImageNet Large Scale Visual Recognition Challenge (ILSVRC12) datasets, showcasing
accuracy improvements over previous techniques. The results indicate that the combination of the volumetric
input and curriculum learning holds significant promise for mitigating adversarial attacks without necessitating
adversary training.
Immunizing Image Classifiers Against Localized Adversary Attacks
Corrosion Management System and Implementation of IMO PSPC on FPSO
1. SATUAN KERJA KHUSUS
PELAKSANA KEGIATAN USAHA HULU MINYAK DAN GAS BUMI
(SKK Migas)
PRIVATE AND CONFIDENTIAL
Corrosion Management System &
Implementation of IMO PSPC on FSO/FPSO
By Putu Indra Mahatrisna
NACE CIP Level 3 – Certified
Dept. of Marine & Transportation SKK Migas
2. 2PRIVATE AND CONFIDENTIAL
Agenda:
1. Indonesia Upstream Oil & Gas Marine Operation Overview
2. Corrosion Management System on FSO/FPSO
3. Implementation IMO PSPC on FSO/FPSO
4. Working Area Based on Water Depth
- 0 – 100 m = 204 Working Area
- 100 – 500 m = 26 Working Area
- 500 – 1500 m = 31 Working Area
- > 1500 m = 15 Working Area
Source: Ditjen Migas
Indonesia Oil and Gas Future is... OFFSHORE
5. PRIVATE AND CONFIDENTIAL 5
Daily Marine Fleet Controlled by SKK Migas
Total Fleet Operates in Upstream Oil and Gas Activity 2016 around 620 ships
0 20 40 60 80 100 120 140 160
AHT / AHTS
Flat Top Barge
Diving Support Vessel
FSO/FPSO/MOPU
Hopper Barge
Tug Boat / Terminal Tug / Harbour Tug
Sea Truck / Speed Boat / Fifi Sea Truck
LCT
Multipurpose Vessel / Utility Vessel
Oil Barge / Tanker
PSV / Supply vessel
Accomodation Barge/ Crane Barge
Crewboat, RIV, & Others
Jumlah
6. 6PRIVATE AND CONFIDENTIAL
Marine Daily & Annual Operation Expenditure (OPEX)
Note :
• Average Shipping Opex is USD 2,280,360,- /day atau USD 824,331,400,- /year,
includes Tangguh LNG Fleet with “Cost of Sales” mechanism.
• Above shipping opex exclude fuel cost, drilling ship opex, ship to support
EPCI, and survey seismic vessel or G&G.
8. PRIVATE AND CONFIDENTIAL 8
• Year Built : 1972
• Length : 142,5 m
• Breadth : 48.2 m
• Depth : 26,45 m
• Capacity : 30,000 BOPD
• Operator : PHE ONWJ
FSO ARCO ARDJUNA
• Year Built : 1972;
• Recondition : 1989
• Capacity : 1,000,000 BBLS
• Length : 183.6 m
• Breadth : 40.5 m
• Depth : 24.9 m
• Operator : JOB Pertamina
Petrochina East Java
FSO CINTA NATOMAS
SKK Migas FSO, FPSO, & FPU Own Fleet (1)
9. PRIVATE AND CONFIDENTIAL 9
• Year Built : 1975,
• Rebuild : 1985
• Length : 272.0 m
• Breadth : 43.4 m
• Depth : 20.6 m
• Field Location : South Cina Sea
• Operator : Star Energy (Kakap) Ltd
FPSO KAKAP NATUNA
• Year Built : 1990
• Capacity : 400,000 BBLS
• Processing Cap : 25,000 BOPD
• Length : 166 m
• Breadth : 39 m
• Depth : 21.4 m
• Operator : Premier Oil Natuna Sea
FSO ANOA NATUNA
SKK Migas FSO, FPSO, & FPU Own Fleet (2)
10. 22/04/2016 10PRIVATE AND CONFIDENTIAL 10
It was the first Deep Water Development in
Indonesia
• Water Depth: 2,400 - 3,400ft
• Start Production: 2003
• Design capacity: 60,000 BOPD
Crude Oil, 150 MMSCFD Gas,
• Hull build in PT PAL and Topside Fabrication
at Hyundai, South Korea.
• Operated by Chevron Indonesia Company
FPU WEST SENO
• Field Location: South Cina Sea
• PSC : ConocoPhillips Indonesia
• Production: Oil 40.000 BOPD; Gas
440 MMSCFD
• Condensate Prod. : 4,800 stbbls/day
• Cargo tank cap : 1,187,000 bbls
FPSO BELANAK NATUNA
SKK Migas FSO, FPSO, & FPU Own Fleet (3)
11. 22/04/2016 11PRIVATE AND CONFIDENTIAL 11
FSO GAGAK RIMANG
• Year Built : 1993,
• Rebuild : 2013
• Length : 327 m
• Breadth : 58 m
• Depth : 22.9 m
• Field Location : Java Sea
• Operator : ExxonMobil Cepu
Ltd.
SKK Migas FSO, FPSO, & FPU Own Fleet (4)
Number of FSO. FPSO, and FPU that operate in Indonesia are 23 units, with total
capacity around 15 MMBBLS Oil and Condensate.
13. 13PRIVATE AND CONFIDENTIAL
Definition:
“Corrosion management is that part of
the overall management system, which
is concerned with the development,
implementation, review and
maintenance of the corrosion policy.”
(UK Health and Safety Executive (HSE),
2004)
Corrosion Management System
Objective:
• Reducing the number of corrosion related hydrocarbon
releases and other safety related and environmentally
damaging outcomes;
• Identifying good practices for setting up an optimal corrosion
management scheme, and
• Providing an overview of the top corrosion threats.
14. 14PRIVATE AND CONFIDENTIAL
• Statutory or Corporate compliance with Safety, Health and Environmental
Policies ----> Cert. of Safety Costruction, Class, SKPI, SKPP, etc.
• Reduction in leaks
• Increased plant availability
• Reduction in unplanned maintenance
• Reduction in deferment costs
Why Manage Corrosion?
Organise and operate successfull
of Corrosion management
system depend on:
• Design
• Stage in Life Cycle
• Process Conditions
• Operational History
15. 15PRIVATE AND CONFIDENTIAL
Yes
No
Basic Corrosion Management Process
• Leak and emissions targets
• Unscheduled shutdown targets
• Annual reduction targets
• Assess skills and competence
• Define roles & responsibilities
• Ensure co-operation & communication
• Identify hazards & assess risks
• Agree targets, processes & systems
• Set standards for measuring performance
• Proactive, measurement using regular
checks to show controls are working
• Reactive, measurement identifies why
performance was substandard
• Review activities & trends
• Check for compliance
• Learn from experience & make
changes
Source:
UK Health and Safety Executive (HSE) Report
16. 22/04/2016 16PRIVATE AND CONFIDENTIAL 16
FSO Lentera Bangsa – (Sept. 2011)
• Explosion in the Engine Room
• Casualties : 1 Person, several
injured
• Oil Spilled on the spot
• Location : Java Sea
• Loss of Production : 18.000 BOPD
FSO Gagasan Perak – (Aug. 2010)
• Explosion in the Slop tank
• Casualties : 1 Person, several
injured
• Oil Spilled on the spot
• Location : Java Sea
• Loss of production : 1.200 –
1.700 BOPD
Major Accident History
18. 22/04/2016 18PRIVATE AND CONFIDENTIAL 18
SKK Migas PMS Audit for FSO & FPSO
1. Ship Particular
2. Ship Certificate & Documentation
3. Ship Operation Manual
4. Hull Components
5. Machinery Components
6. Other Components
1. Electrical Components
2. Navigation Equipments
3. Life Saving Appliance (LSA)
4. Mooring System
Objective :
Continues Improvement on effectiveness, safety, and reliability FSO & FPSO operation to
minimize unplanned shutdown.
Scope:
Working Plan, Operation Management, Safety, Maintenance, Rule and Regulation
Implementation on FSO & FPSO
19. 19PRIVATE AND CONFIDENTIAL
Common Observation Result
Heavy Corrosion on Deck Heavy Corrosion on
Structural
Heavy Corrosion on Piping
Broken Insulation Weathertight
Door/Openings Corroded
Corrosion on access
20. 20PRIVATE AND CONFIDENTIAL
Major Observation Result
Leaks on Cargo Tank/ Hull Cracks on Hull Leakage on Engine Room
Corrosion Leakage on Boiler Corrosion on Life Appliance Mechanical Damage
21. 21PRIVATE AND CONFIDENTIAL
Challenges
1. Marine corrosion is one of the leading causes of structural and
mechanical failures in the floating production facilities, but the right
measures to protect these assets can ensure they operate safely,
efficiently and profitably.
2. As the price of oil continues to fall, Facility owners may be looking to
cut budgets, which could affect corrosion control providers
3. Poor understanding of the corrosion management concept and its
practical applications.
4. Increased expectations from the public for safety, stricter
governmental regulations and, perhaps more than anything, a
shortage of experienced personnel.
5. Aging infrastructure, particularly as it relates to marine coatings, is
another major concern in the industry
22. 22PRIVATE AND CONFIDENTIAL
How to Improve Asset Corrosion Management
1. Companies should have a policy statement that clearly addresses the
organization’s objectives for the corrosion management system
2. Companies must continue to train, certify and provide opportunity to
their corrosion control personnel to ensure the program is being
properly maintained.
3. Marine corrosion control starts with the proper design and
installation of the infrastructure. If a company takes the time to
develop, implement and maintain a proper program, these assets
will operate safely, while protecting the environment and providing a
profitable system to the owner.
4. There’s not just one methodology for controlling marine corrosion.
Coating, cathodic protection, electrical isolation and proper
maintenance all play a role.
5. Government can ensure that legislation and regulations relevant to
the industry includes language that supports proper corrosion
control planning and the use of qualified personnel
24. 24PRIVATE AND CONFIDENTIAL
The Performance Standard fo Protective Coating (PSPC)
IMO PSPC for Water Ballast Tanks
IMO MSC.215(82) Performance Standard for Protective Coatings for Water Ballast Tanks
(2006)
• A standard designed to achieve a target coating lifetime of 15 years in dedicated
seawater ballast tanks and double side-skin spaces of bulk carriers.
• The regulatory amendment is: SOLAS Regulation II-1/3-2
• Entry Into Force
• The building contract was placed on or after 1st July 2008
• The keel was laid on or after 1st January 2009
• The delivery is on or after 1st July 2012
IMO PSPC for Cargo Oil Tanks
The IMO MSC.291(87) Performance Standard for Protective Coatings for Cargo Oil
Tanks of Crude Oil Tankers (2012)
• Designed to achieve a target coating lifetime of 15 years to ensure the longevity of
cargo oil tanks.
• The regulatory amendment is: SOLAS regulation II-1/3-11
• Entry Into Force:
• The building contract is placed on or after 1st January 2013 or
• The keels of which are laid or which are at a similar stage of construction on or
after 1st July 2013
• Or the delivery of which is on or after 1st January 2016
25. 25PRIVATE AND CONFIDENTIAL
SOLAS Regulation II-1/3-2, Clause No. 4:
• Maintenance of the protective coating system shall be included in the
overall ship's maintenance scheme.
• The effectiveness of the protective coating system shall be verified
during the life of a ship by the Administration or an organization
recognized by the Administration, based on the guidelines developed
by the Organization.*
Main Element of PSPC
Main Elements of the PSPC
• Design of a specification and coating system
• Coating System approval
• Definition of inspection procedures
• Production of a Coating Technical File (CTF) which records all aspects of
the process
• Verification of compliance
• IMO PSPC requires that the CTF should be completed by the shipyard and
reviewed by the flag State (usually a Class society acting as an RO) before
the related certificate is issued.
28. 28PRIVATE AND CONFIDENTIAL
Ballast Tank Dehumidifier – FSO Gagak Rimang
• OEM: Munters Pte Ltd.
• Type unit: Desiccant
Dehumidification MT-10000E
• Process Air: Rated air flow:
10000 m3/h;
• Reactivation air: Rated air flow:
3330 m3/h;
29. 29PRIVATE AND CONFIDENTIAL
Implementation of PSPC, Challenges:
• Greater demand for education in coating management
• New technology solutions for “equivalent” coating system
• More systematic approach to inspection with objectivity
• Better data recording and control of process
• True additional cost on New Build as yet not verified
• Today the surface preparation and
coating process is considered by most
shipyards as a ‘bottleneck’ in the process.
• Genuine shortage of trained coating
inspectors
• Coating Process predictable, but not an
exact science (weather, drying times,
access to surface).
30. 30PRIVATE AND CONFIDENTIAL
1. To reach the goal of 15 years useful coating life in GOOD condition from
initial coating application, these initial efforts during the new construction in
the shipyard is critical element include:
a) The clearly defined tripartite agreement on specification and
inspection procedures,
b) The selection of qualified and certified coating inspector(s),
c) Carrying out IMO PSPC-compliant surface preparation and coating
application,
d) Quality inspection and comprehensive CTF documentation.
2. The standardization of shipyard new construction processes to meet the
PSPC requirements not only has the potential for improving the quality of
coating, but also provides an opportunity for better controlling costs
during construction and throughout the service life of the vessel.
Summary
31. S C C E S S
THERE WILL BE No Success without “U”
We need your supports
32.
33. About Presenter
• Name : Putu Indra Mahatrisna
• Date of Birth : 1st May 1979
• Education :
• Bachelor degree in Department of Marine Engineering, Faculty of
Maritime Technology, ITS Surabaya
• Now is continuing Master degree majoring in Gas Management,
Department of Chemical Engineering, Faculty of Engineering,
University of Indonesia
• Experience :
• Marine Engineer at BPMIGAS/ SKK Migas (2009 to date)
• Lead Production Engineer & Subject Matter Expert (SME) for Coating & Passive
Fire Proofing at J. Ray McDermott (Batam yard) (2005-2009), project included:
• Chevron Platong Gas II CPP Topside Construction & HUC
• North Belut CPP Topside Construction & HUC
• Woodside LNG Train, Phase V Expansion Project
• Technical Service Advisor at PT. Jotun Indonesia (2003-2005)
• Certification:
• NACE CIP Level 3
• IMO OPRC (Oil Pollution Preparedness, Response, and Cooperation Convention)
- Level 2
• NEBOSH International Technical Certificate in Oil and Gas Operational Safety