SlideShare a Scribd company logo
Madawalabu
Madawalabu
University
University
Construction Equipment and Plant Management
COTM 4202
General
 Estimating and planning involves
the judicious selection of
equipment, the careful scheduling
of time and resources, and the
accurate determination of
expected system output and cost.
Definition
 It is the number of units and the
size of equipment that would
permit the constructor to
accomplish the activity with a
duration resulting in the lowest
cost.
2 February 2019 2
COTM 4202
 Haul unit horsepower
 Haul road rolling resistance
 Haul road grades
 Haul unit loaded and empty weight
 Haul unit transmission characteristics
 Haul unit loading time
 Haul unit travel time
 Haul unit delay time
 Altitude of the project site
 Haul unit horsepower
 Haul road rolling resistance
 Haul road grades
 Haul unit loaded and empty weight
 Haul unit transmission characteristics
 Haul unit loading time
 Haul unit travel time
 Haul unit delay time
 Altitude of the project site
2 February 2019
COTM 4202 3
 Total power that an engine is capable of
generating is expressed as its horsepower.
 Available horsepower is power that is
available to perform work after taking into
account losses and consumption in other
machine functions.
 Rimpull is defined as the tractive force
between the driving wheels and the surface
on which they travel.( V is velocity in mph)
 Total power that an engine is capable of
generating is expressed as its horsepower.
 Available horsepower is power that is
available to perform work after taking into
account losses and consumption in other
machine functions.
 Rimpull is defined as the tractive force
between the driving wheels and the surface
on which they travel.( V is velocity in mph)
2 February 2019
COTM 4202 4
Power generated by engine
2 February 2019
COTM 4202 5
Drawbar Pull
Rolling Resistance
Rimpull
 Rolling resistance is resistance offered to movement of
materials on a plain surface; often expressed in pounds
per ton of materials.
 Rolling Resistance depends upon:
2 February 2019
COTM 4202 6
2 February 2019
COTM 4202 7
 The force-opposing movement of a machine up a
frictionless slope is grade resistance.
 The effect of gravitational force in aiding movement of a
vehicle down a slope is grade assistance.
2 February 2019
COTM 4202 8
F= 20 lbs/ G% per Ton
 The cycle capacity C of a piece of equipment
is defined as the number of output units per
cycle of operation under standard work
conditions.
 The standard production rate R of a piece of
construction equipment is defined as the
number of output units per unit time.
 The cycle time T refers to units of time per
cycle of operation.
 The cycle capacity C of a piece of equipment
is defined as the number of output units per
cycle of operation under standard work
conditions.
 The standard production rate R of a piece of
construction equipment is defined as the
number of output units per unit time.
 The cycle time T refers to units of time per
cycle of operation.
2 February 2019
COTM 4202 9
 Time to load a mover for load shifting will
determine loads that can be transferred.
Longer loading time lesser will be
productivity.
 To is loading time
 Te is cycle time for loader/excavator
 Ch is capacity of a hauler (dump truck)
 Ce loading rate/capacity of loader
 Time to load a mover for load shifting will
determine loads that can be transferred.
Longer loading time lesser will be
productivity.
 To is loading time
 Te is cycle time for loader/excavator
 Ch is capacity of a hauler (dump truck)
 Ce loading rate/capacity of loader
2 February 2019
COTM 4202 10
 It is time for moving load from production site to
disposal site. Longer time will reduce productivity.
 To determine the productivity of a hauler,
› Let: D be the distance from source to a dump site, S
be the average speed of the hauler, Tt be the travel
time for the round trip to the dump site, To be the
loading time,Td be the dumping time plus other
delays.
 Then the travel time for the round trip is given by:
 It is time for moving load from production site to
disposal site. Longer time will reduce productivity.
 To determine the productivity of a hauler,
› Let: D be the distance from source to a dump site, S
be the average speed of the hauler, Tt be the travel
time for the round trip to the dump site, To be the
loading time,Td be the dumping time plus other
delays.
 Then the travel time for the round trip is given by:
2 February 2019
COTM 4202 11
 Human and machine system suffer from
inherent delays due to reaction time and
capacity, say Td.
2 February 2019
COTM 4202 12
 For a given dumping time Td, the total cycle
time Th of the hauler is the sum of loading
time, travel time and damping time given
by:
 For a given dumping time Td, the total cycle
time Th of the hauler is the sum of loading
time, travel time and damping time given
by:
2 February 2019
COTM 4202 13
 Optimum number of haul units (N) is
determined by:
 NB: Rounding down will maximize haul unit
productivity.
 Optimum number of haul units (N) is
determined by:
 NB: Rounding down will maximize haul unit
productivity.
2 February 2019
COTM 4202 14
 An 16 cubic meter dump truck has a
loading time of 3 min, a travel time of 7 min,
and the dumping and delay times of 5 min.
Calculate the cycle time of the hauler and
optimum number of hauling units.
 An 16 cubic meter dump truck has a
loading time of 3 min, a travel time of 7 min,
and the dumping and delay times of 5 min.
Calculate the cycle time of the hauler and
optimum number of hauling units.
2 February 2019
COTM 4202 15
 The daily standard production rate Pe of an
excavator is is given by:
 He is the operating hours per day
 Ce is the cycle capacity (in units of volume) of the
excavator
 Te is the cycle time (in hours) of the excavator
 The daily standard production rate Pe of an
excavator is is given by:
 He is the operating hours per day
 Ce is the cycle capacity (in units of volume) of the
excavator
 Te is the cycle time (in hours) of the excavator
2 February 2019
COTM 4202 16
 The daily standard production rate Ph of a
hauler is given by:
 Rh is standard production rate
 Hh is the number of operating hours per day
 The daily standard production rate Ph of a
hauler is given by:
 Rh is standard production rate
 Hh is the number of operating hours per day
2 February 2019
COTM 4202 17
 A 1.5 cubic meter front-end loader is going to
load dump trucks with a capacity of 9.0 cubic
meter. The loader takes 0.4 min to fill and load
one bucket. The travel time in the haul is 4.0 min.
Dump and delay times are 2.5 min combined.
Calculate:
 The loading time,
 The cycle time of hauler,
 Number of trucks,
 The hourly production rate of haul units, and
 The hourly production of loader
 A 1.5 cubic meter front-end loader is going to
load dump trucks with a capacity of 9.0 cubic
meter. The loader takes 0.4 min to fill and load
one bucket. The travel time in the haul is 4.0 min.
Dump and delay times are 2.5 min combined.
Calculate:
 The loading time,
 The cycle time of hauler,
 Number of trucks,
 The hourly production rate of haul units, and
 The hourly production of loader
2 February 2019
COTM 4202 18
 A power shovel with a dipper of one cubic
meter capacity has a standard operating
cycle time of 30 seconds. Find the daily
standard production rate of the shovel.
Ce = 1 cu. mtr., Te = 30 sec. and He = 8
hours.
 A power shovel with a dipper of one cubic
meter capacity has a standard operating
cycle time of 30 seconds. Find the daily
standard production rate of the shovel.
Ce = 1 cu. mtr., Te = 30 sec. and He = 8
hours.
2 February 2019
COTM 4202 19
 A dump truck with a capacity of 6 cubic meter
is used to dispose of excavated materials at a
dump site 4 km away. The average speed of
the dump truck is 30 mph and the dumping
time is 30 seconds. Find the daily standard
production rate of the truck. If a fleet of dump
trucks of 9 cubic meter capacity is used to
dispose of the excavated materials for 8 hours
per day, determine the number of trucks
needed daily.
 A dump truck with a capacity of 6 cubic meter
is used to dispose of excavated materials at a
dump site 4 km away. The average speed of
the dump truck is 30 mph and the dumping
time is 30 seconds. Find the daily standard
production rate of the truck. If a fleet of dump
trucks of 9 cubic meter capacity is used to
dispose of the excavated materials for 8 hours
per day, determine the number of trucks
needed daily.
2 February 2019
COTM 4202 20
 Material properties have a direct effect on the ease or
difficulty of handling the material, on the selection of
equipment, and on equipment production rates.
 Quantities are often measured in volume units.
 Volume of material under different conditions varies
appreciably.
 Material properties have a direct effect on the ease or
difficulty of handling the material, on the selection of
equipment, and on equipment production rates.
 Quantities are often measured in volume units.
 Volume of material under different conditions varies
appreciably.
2 February 2019
COTM 4202 21
 Bank: Material in its natural state. Also called
in-place or in-situ. Measurement: BCM (Bank
Cubic Meter)
 Lose: material that has been excavated or
loaded. Measurement: LCM (Lose Cubic
Meter)
 Compacted: Material after compaction:
Measurement: CCM (Compacted Cubic
Meter)
2 February 2019
COTM 4202 22
 Bank: Material in its natural state. Also called
in-place or in-situ. Measurement: BCM (Bank
Cubic Meter)
 Lose: material that has been excavated or
loaded. Measurement: LCM (Lose Cubic
Meter)
 Compacted: Material after compaction:
Measurement: CCM (Compacted Cubic
Meter)
Swell
Factor
Shrinkage
Factor
 The swell factor is the ratio of the loose dry
weight per unit volume to the bank dry weight
per unit volume.
Loose dry unit weight
Swell Factor (w) = _____________________
Bank dry unit weight
Swell% = ( 1/w – 1 )x100
 The shrinkage factor is the ratio of the compacted dry
weight per unit volume to the bank dry weight per unit
volume:
Compacted dry unit weight
Shrinkage Factor = _________________________
Bank dry unit weight
Shrinkage % = ( SrF – 1 )x100
Shrinkage
Factor
 The shrinkage factor is the ratio of the compacted dry
weight per unit volume to the bank dry weight per unit
volume:
Compacted dry unit weight
Shrinkage Factor = _________________________
Bank dry unit weight
Shrinkage % = ( SrF – 1 )x100
2 February 2019
COTM 4202 23
2 February 2019
COTM 4202 24
 Let w denote the swell factor of the soil
 wPe denote the daily volume of loose
excavated materials.
 Then the approximate number of haulers
required to dispose of the excavated
materials is given by:
 Let w denote the swell factor of the soil
 wPe denote the daily volume of loose
excavated materials.
 Then the approximate number of haulers
required to dispose of the excavated
materials is given by:
2 February 2019
COTM 4202 25
 Equipment productivities at job sites are
influenced by actual work conditions and a
variety of inefficiencies and work stoppages.
 Let F1, F2, ..., Fn, denote factors that lower
productivity, each of which is smaller than 1,
 Then the actual equipment productivity R' at the
job site can be related to the standard
production rate R as follows:
 Equipment productivities at job sites are
influenced by actual work conditions and a
variety of inefficiencies and work stoppages.
 Let F1, F2, ..., Fn, denote factors that lower
productivity, each of which is smaller than 1,
 Then the actual equipment productivity R' at the
job site can be related to the standard
production rate R as follows:
2 February 2019
COTM 4202 26
 The actual cycle time T' at the job site is
related to the standard cycle time T as:
2 February 2019
COTM 4202 27
 A power shovel with a dipper of 1.2 cubic meter
capacity has a standard production rate of 960
cubic meter for an 8-hour day. 4min is consumed
to fill and load. Determine the job site
productivity and the actual cycle time of this
shovel under the work conditions at the site that
affects its productivity as shown below:
 Work Conditions at the Site Factors
Bulk composition 0.954
Soil properties and water content 0.983
Equipment idle time for worker breaks 0.8
Management efficiency 0.7
 A power shovel with a dipper of 1.2 cubic meter
capacity has a standard production rate of 960
cubic meter for an 8-hour day. 4min is consumed
to fill and load. Determine the job site
productivity and the actual cycle time of this
shovel under the work conditions at the site that
affects its productivity as shown below:
 Work Conditions at the Site Factors
Bulk composition 0.954
Soil properties and water content 0.983
Equipment idle time for worker breaks 0.8
Management efficiency 0.7
2 February 2019
COTM 4202 28
 A dump truck with a capacity of 6 cubic meter is used
to dispose of excavated materials. The distance from
the dump site is 4km and the average speed of the
dump truck is 30 kph. The job site productivity of the
power shovel per day is 504 cubic meter, which will
be modified by a swell factor of 1.1. The only factors
affecting the job site productivity of the dump truck in
addition to those affecting the power shovel are 0.80
for equipment idle time and 0.70 for management
efficiency. Determine the job site productivity of the
dump truck. If a fleet of such trucks is used to haul the
excavated material, find the number of trucks needed
daily.
 A dump truck with a capacity of 6 cubic meter is used
to dispose of excavated materials. The distance from
the dump site is 4km and the average speed of the
dump truck is 30 kph. The job site productivity of the
power shovel per day is 504 cubic meter, which will
be modified by a swell factor of 1.1. The only factors
affecting the job site productivity of the dump truck in
addition to those affecting the power shovel are 0.80
for equipment idle time and 0.70 for management
efficiency. Determine the job site productivity of the
dump truck. If a fleet of such trucks is used to haul the
excavated material, find the number of trucks needed
daily.
2 February 2019
COTM 4202 29
 A front-end loader loads a fleet of dump trucks
(capacity 18 loose cubic meter each), which haul the
earth to a fill where it is compacted with a shrinkage
factor of 10%. The earth has a percent swell of 20%.
The job requires a volume of 18,000 compacted cubic
meter. Distance between quarry and project site is
5miles connected with dirt track.
 How many hours will be required to excavate and haul
the material to the fill.
 A front-end loader loads a fleet of dump trucks
(capacity 18 loose cubic meter each), which haul the
earth to a fill where it is compacted with a shrinkage
factor of 10%. The earth has a percent swell of 20%.
The job requires a volume of 18,000 compacted cubic
meter. Distance between quarry and project site is
5miles connected with dirt track.
 How many hours will be required to excavate and haul
the material to the fill.
2 February 2019
COTM 4202 30
THANK YOU!
THANK YOU!
31
THANK YOU!
THANK YOU!
2 February 2019
COTM 4202

More Related Content

What's hot

Construction equipments
Construction equipmentsConstruction equipments
Construction equipmentsAshish Parihar
 
Trucks & wagons
Trucks & wagonsTrucks & wagons
Trucks & wagons
Aditya Khanolkar
 
Scraper
ScraperScraper
Scraper
Karan Patel
 
construction equipment
construction equipment construction equipment
construction equipment
Purav Patel
 
Rigid pavements
Rigid pavements Rigid pavements
Rigid pavements
pradip dangar
 
Heavy Construction Equipment Productivity
Heavy Construction Equipment Productivity Heavy Construction Equipment Productivity
Heavy Construction Equipment Productivity
SSudhaVelan
 
Chapter 8 introduction to construction equipments
Chapter 8 introduction to construction equipmentsChapter 8 introduction to construction equipments
Chapter 8 introduction to construction equipments
KHUSHBU SHAH
 
Power shovel
Power shovelPower shovel
Power shovel
Ashi gupta
 
Construction equipment (earth work)
Construction equipment (earth work)Construction equipment (earth work)
Construction equipment (earth work)
Suhaa Chine
 
Dredging equipment
Dredging equipmentDredging equipment
Dredging equipmentSwarna Rajan
 
Railway track:An Introduction
Railway track:An IntroductionRailway track:An Introduction
Railway track:An Introduction
Prem Prakash Kumar
 
Trucks and Hauling Equipment
Trucks and Hauling EquipmentTrucks and Hauling Equipment
Trucks and Hauling Equipment
Construction Tech. and Mgmt., VNIT Nagpur
 
Defects in rails. Railway Engineering
Defects in rails. Railway EngineeringDefects in rails. Railway Engineering
Defects in rails. Railway Engineering
Irfan Nasir
 
Scraper
ScraperScraper
Road construction equipment.pptx 2
Road construction equipment.pptx 2Road construction equipment.pptx 2
Road construction equipment.pptx 2AhmedZL
 
Box Pushing Technique
Box Pushing TechniqueBox Pushing Technique
Box Pushing Technique
Seminar Links
 
L1 Planning for Earthwork Construction
L1 Planning for Earthwork ConstructionL1 Planning for Earthwork Construction
L1 Planning for Earthwork ConstructionDon W. Lewis
 
Tractor, bulldozer, scraper, ripper_Advanced Construction Technology (Semeste...
Tractor, bulldozer, scraper, ripper_Advanced Construction Technology (Semeste...Tractor, bulldozer, scraper, ripper_Advanced Construction Technology (Semeste...
Tractor, bulldozer, scraper, ripper_Advanced Construction Technology (Semeste...
A Makwana
 
Heavy construction equipment
Heavy construction equipmentHeavy construction equipment
Heavy construction equipment
Pritesh Parmar
 
Highway Geometric Design control and criteria-2
Highway Geometric Design control and criteria-2Highway Geometric Design control and criteria-2
Highway Geometric Design control and criteria-2
Muhammad Faisal
 

What's hot (20)

Construction equipments
Construction equipmentsConstruction equipments
Construction equipments
 
Trucks & wagons
Trucks & wagonsTrucks & wagons
Trucks & wagons
 
Scraper
ScraperScraper
Scraper
 
construction equipment
construction equipment construction equipment
construction equipment
 
Rigid pavements
Rigid pavements Rigid pavements
Rigid pavements
 
Heavy Construction Equipment Productivity
Heavy Construction Equipment Productivity Heavy Construction Equipment Productivity
Heavy Construction Equipment Productivity
 
Chapter 8 introduction to construction equipments
Chapter 8 introduction to construction equipmentsChapter 8 introduction to construction equipments
Chapter 8 introduction to construction equipments
 
Power shovel
Power shovelPower shovel
Power shovel
 
Construction equipment (earth work)
Construction equipment (earth work)Construction equipment (earth work)
Construction equipment (earth work)
 
Dredging equipment
Dredging equipmentDredging equipment
Dredging equipment
 
Railway track:An Introduction
Railway track:An IntroductionRailway track:An Introduction
Railway track:An Introduction
 
Trucks and Hauling Equipment
Trucks and Hauling EquipmentTrucks and Hauling Equipment
Trucks and Hauling Equipment
 
Defects in rails. Railway Engineering
Defects in rails. Railway EngineeringDefects in rails. Railway Engineering
Defects in rails. Railway Engineering
 
Scraper
ScraperScraper
Scraper
 
Road construction equipment.pptx 2
Road construction equipment.pptx 2Road construction equipment.pptx 2
Road construction equipment.pptx 2
 
Box Pushing Technique
Box Pushing TechniqueBox Pushing Technique
Box Pushing Technique
 
L1 Planning for Earthwork Construction
L1 Planning for Earthwork ConstructionL1 Planning for Earthwork Construction
L1 Planning for Earthwork Construction
 
Tractor, bulldozer, scraper, ripper_Advanced Construction Technology (Semeste...
Tractor, bulldozer, scraper, ripper_Advanced Construction Technology (Semeste...Tractor, bulldozer, scraper, ripper_Advanced Construction Technology (Semeste...
Tractor, bulldozer, scraper, ripper_Advanced Construction Technology (Semeste...
 
Heavy construction equipment
Heavy construction equipmentHeavy construction equipment
Heavy construction equipment
 
Highway Geometric Design control and criteria-2
Highway Geometric Design control and criteria-2Highway Geometric Design control and criteria-2
Highway Geometric Design control and criteria-2
 

Similar to Construction equipment management chapter 3

Chapter 3- Lecture
Chapter 3- LectureChapter 3- Lecture
Chapter 3- Lecture
Delhi Technological University
 
Construction Equipments.ppt
Construction Equipments.pptConstruction Equipments.ppt
Construction Equipments.ppt
VinayakNaik80
 
Construction equipment management chapter 2
Construction equipment management chapter 2Construction equipment management chapter 2
Construction equipment management chapter 2
Delhi Technological University
 
Project Greenland Cost Report - Initial Draft
Project Greenland Cost Report - Initial DraftProject Greenland Cost Report - Initial Draft
Project Greenland Cost Report - Initial DraftRupak Parekh
 
Design, Development, and Fabrication of a Mini-Hovercraft
Design, Development, and Fabrication of a Mini-HovercraftDesign, Development, and Fabrication of a Mini-Hovercraft
Design, Development, and Fabrication of a Mini-Hovercraft
IRJET Journal
 
Construction Equipment Fleet Management
Construction Equipment Fleet ManagementConstruction Equipment Fleet Management
Construction Equipment Fleet Management
IJMER
 
D012311522
D012311522D012311522
D012311522
IOSR Journals
 
@ETCONp Construction Exam 8 .DOCX
@ETCONp Construction Exam 8  .DOCX@ETCONp Construction Exam 8  .DOCX
@ETCONp Construction Exam 8 .DOCX
MekonnenAyal
 
construction equpment Chapter 2.pdf
construction equpment Chapter 2.pdfconstruction equpment Chapter 2.pdf
construction equpment Chapter 2.pdf
example43
 
Construction equipment management chapter 4
Construction equipment management chapter 4Construction equipment management chapter 4
Construction equipment management chapter 4
Delhi Technological University
 
A CASE STUDY ON COCHIN PORT TRUST
A CASE STUDY ON COCHIN PORT TRUSTA CASE STUDY ON COCHIN PORT TRUST
A CASE STUDY ON COCHIN PORT TRUSTpaneer4
 
AN INVESTIGATION ON SEISMIC STABILITY OF MINE OVERBURDEN DUMP SLOPE
AN INVESTIGATION ON SEISMIC STABILITY OF MINE OVERBURDEN DUMP SLOPEAN INVESTIGATION ON SEISMIC STABILITY OF MINE OVERBURDEN DUMP SLOPE
AN INVESTIGATION ON SEISMIC STABILITY OF MINE OVERBURDEN DUMP SLOPE
IRJET Journal
 
Appendix 11 analysis of rates - balsio shp phase ii - 28032014
Appendix 11   analysis of rates - balsio shp phase ii - 28032014Appendix 11   analysis of rates - balsio shp phase ii - 28032014
Appendix 11 analysis of rates - balsio shp phase ii - 28032014
Nikhil Jaipurkar
 
Best cement-handbook-final-pdf
Best cement-handbook-final-pdfBest cement-handbook-final-pdf
Best cement-handbook-final-pdf
mkpq pasha
 
E05622428
E05622428E05622428
E05622428
IOSR-JEN
 
CL 380_Unit-1 (1).pptx
CL 380_Unit-1 (1).pptxCL 380_Unit-1 (1).pptx
CL 380_Unit-1 (1).pptx
megha desai
 
Site visit report of Raikela & Tantra Iron.pptx
Site visit report of Raikela & Tantra Iron.pptxSite visit report of Raikela & Tantra Iron.pptx
Site visit report of Raikela & Tantra Iron.pptx
ssuser9d0ede
 
Download-manuals-surface water-manual-surfacewatero&m-norms
 Download-manuals-surface water-manual-surfacewatero&m-norms Download-manuals-surface water-manual-surfacewatero&m-norms
Download-manuals-surface water-manual-surfacewatero&m-normshydrologyproject0
 
Download-manuals-surface water-manual-surfacewatero&m-norms
 Download-manuals-surface water-manual-surfacewatero&m-norms Download-manuals-surface water-manual-surfacewatero&m-norms
Download-manuals-surface water-manual-surfacewatero&m-normshydrologywebsite1
 
Design and Fabrication of Multi-purpose Agriculture Machine
Design and Fabrication of Multi-purpose Agriculture MachineDesign and Fabrication of Multi-purpose Agriculture Machine
Design and Fabrication of Multi-purpose Agriculture Machine
IRJET Journal
 

Similar to Construction equipment management chapter 3 (20)

Chapter 3- Lecture
Chapter 3- LectureChapter 3- Lecture
Chapter 3- Lecture
 
Construction Equipments.ppt
Construction Equipments.pptConstruction Equipments.ppt
Construction Equipments.ppt
 
Construction equipment management chapter 2
Construction equipment management chapter 2Construction equipment management chapter 2
Construction equipment management chapter 2
 
Project Greenland Cost Report - Initial Draft
Project Greenland Cost Report - Initial DraftProject Greenland Cost Report - Initial Draft
Project Greenland Cost Report - Initial Draft
 
Design, Development, and Fabrication of a Mini-Hovercraft
Design, Development, and Fabrication of a Mini-HovercraftDesign, Development, and Fabrication of a Mini-Hovercraft
Design, Development, and Fabrication of a Mini-Hovercraft
 
Construction Equipment Fleet Management
Construction Equipment Fleet ManagementConstruction Equipment Fleet Management
Construction Equipment Fleet Management
 
D012311522
D012311522D012311522
D012311522
 
@ETCONp Construction Exam 8 .DOCX
@ETCONp Construction Exam 8  .DOCX@ETCONp Construction Exam 8  .DOCX
@ETCONp Construction Exam 8 .DOCX
 
construction equpment Chapter 2.pdf
construction equpment Chapter 2.pdfconstruction equpment Chapter 2.pdf
construction equpment Chapter 2.pdf
 
Construction equipment management chapter 4
Construction equipment management chapter 4Construction equipment management chapter 4
Construction equipment management chapter 4
 
A CASE STUDY ON COCHIN PORT TRUST
A CASE STUDY ON COCHIN PORT TRUSTA CASE STUDY ON COCHIN PORT TRUST
A CASE STUDY ON COCHIN PORT TRUST
 
AN INVESTIGATION ON SEISMIC STABILITY OF MINE OVERBURDEN DUMP SLOPE
AN INVESTIGATION ON SEISMIC STABILITY OF MINE OVERBURDEN DUMP SLOPEAN INVESTIGATION ON SEISMIC STABILITY OF MINE OVERBURDEN DUMP SLOPE
AN INVESTIGATION ON SEISMIC STABILITY OF MINE OVERBURDEN DUMP SLOPE
 
Appendix 11 analysis of rates - balsio shp phase ii - 28032014
Appendix 11   analysis of rates - balsio shp phase ii - 28032014Appendix 11   analysis of rates - balsio shp phase ii - 28032014
Appendix 11 analysis of rates - balsio shp phase ii - 28032014
 
Best cement-handbook-final-pdf
Best cement-handbook-final-pdfBest cement-handbook-final-pdf
Best cement-handbook-final-pdf
 
E05622428
E05622428E05622428
E05622428
 
CL 380_Unit-1 (1).pptx
CL 380_Unit-1 (1).pptxCL 380_Unit-1 (1).pptx
CL 380_Unit-1 (1).pptx
 
Site visit report of Raikela & Tantra Iron.pptx
Site visit report of Raikela & Tantra Iron.pptxSite visit report of Raikela & Tantra Iron.pptx
Site visit report of Raikela & Tantra Iron.pptx
 
Download-manuals-surface water-manual-surfacewatero&m-norms
 Download-manuals-surface water-manual-surfacewatero&m-norms Download-manuals-surface water-manual-surfacewatero&m-norms
Download-manuals-surface water-manual-surfacewatero&m-norms
 
Download-manuals-surface water-manual-surfacewatero&m-norms
 Download-manuals-surface water-manual-surfacewatero&m-norms Download-manuals-surface water-manual-surfacewatero&m-norms
Download-manuals-surface water-manual-surfacewatero&m-norms
 
Design and Fabrication of Multi-purpose Agriculture Machine
Design and Fabrication of Multi-purpose Agriculture MachineDesign and Fabrication of Multi-purpose Agriculture Machine
Design and Fabrication of Multi-purpose Agriculture Machine
 

More from Delhi Technological University

Chapter 6- Contract Management
Chapter 6- Contract ManagementChapter 6- Contract Management
Chapter 6- Contract Management
Delhi Technological University
 
Chapter 5- Contract Management
Chapter 5- Contract ManagementChapter 5- Contract Management
Chapter 5- Contract Management
Delhi Technological University
 
Chapter 4- Contract Management
Chapter 4- Contract ManagementChapter 4- Contract Management
Chapter 4- Contract Management
Delhi Technological University
 
Chapter 3- Contract Management
Chapter 3- Contract ManagementChapter 3- Contract Management
Chapter 3- Contract Management
Delhi Technological University
 
Chapter 2- Contract Management
Chapter 2- Contract ManagementChapter 2- Contract Management
Chapter 2- Contract Management
Delhi Technological University
 
Chapter 1- Procurement management
Chapter 1- Procurement managementChapter 1- Procurement management
Chapter 1- Procurement management
Delhi Technological University
 
Chapter 4
Chapter 4Chapter 4
Chapter 3- Construction Law
Chapter 3- Construction Law Chapter 3- Construction Law
Chapter 3- Construction Law
Delhi Technological University
 
Chapter 2- Construction Law
Chapter 2- Construction Law Chapter 2- Construction Law
Chapter 2- Construction Law
Delhi Technological University
 
Chapter 1-Construction Law
Chapter 1-Construction Law Chapter 1-Construction Law
Chapter 1-Construction Law
Delhi Technological University
 
Chapter 5- Lecture
Chapter 5- LectureChapter 5- Lecture
Chapter 5- Lecture
Delhi Technological University
 
Chapter 4- Lecture
Chapter 4- LectureChapter 4- Lecture
Chapter 4- Lecture
Delhi Technological University
 
Chapter 2- Lecture
Chapter 2- LectureChapter 2- Lecture
Chapter 2- Lecture
Delhi Technological University
 
Chapter 1- Lecture
Chapter 1- LectureChapter 1- Lecture
Chapter 1- Lecture
Delhi Technological University
 
Construction equipment management chapter 5
Construction equipment management chapter 5Construction equipment management chapter 5
Construction equipment management chapter 5
Delhi Technological University
 
Construction equipment management chapter 1pdf
Construction equipment management chapter 1pdfConstruction equipment management chapter 1pdf
Construction equipment management chapter 1pdf
Delhi Technological University
 
Chapter 5 [compatibility mode]
Chapter 5 [compatibility mode]Chapter 5 [compatibility mode]
Chapter 5 [compatibility mode]
Delhi Technological University
 
Chapter 4 [compatibility mode]
Chapter 4 [compatibility mode]Chapter 4 [compatibility mode]
Chapter 4 [compatibility mode]
Delhi Technological University
 
Chapter 3 [compatibility mode]
Chapter 3 [compatibility mode]Chapter 3 [compatibility mode]
Chapter 3 [compatibility mode]
Delhi Technological University
 
Chapter 2 [compatibility mode]
Chapter 2 [compatibility mode]Chapter 2 [compatibility mode]
Chapter 2 [compatibility mode]
Delhi Technological University
 

More from Delhi Technological University (20)

Chapter 6- Contract Management
Chapter 6- Contract ManagementChapter 6- Contract Management
Chapter 6- Contract Management
 
Chapter 5- Contract Management
Chapter 5- Contract ManagementChapter 5- Contract Management
Chapter 5- Contract Management
 
Chapter 4- Contract Management
Chapter 4- Contract ManagementChapter 4- Contract Management
Chapter 4- Contract Management
 
Chapter 3- Contract Management
Chapter 3- Contract ManagementChapter 3- Contract Management
Chapter 3- Contract Management
 
Chapter 2- Contract Management
Chapter 2- Contract ManagementChapter 2- Contract Management
Chapter 2- Contract Management
 
Chapter 1- Procurement management
Chapter 1- Procurement managementChapter 1- Procurement management
Chapter 1- Procurement management
 
Chapter 4
Chapter 4Chapter 4
Chapter 4
 
Chapter 3- Construction Law
Chapter 3- Construction Law Chapter 3- Construction Law
Chapter 3- Construction Law
 
Chapter 2- Construction Law
Chapter 2- Construction Law Chapter 2- Construction Law
Chapter 2- Construction Law
 
Chapter 1-Construction Law
Chapter 1-Construction Law Chapter 1-Construction Law
Chapter 1-Construction Law
 
Chapter 5- Lecture
Chapter 5- LectureChapter 5- Lecture
Chapter 5- Lecture
 
Chapter 4- Lecture
Chapter 4- LectureChapter 4- Lecture
Chapter 4- Lecture
 
Chapter 2- Lecture
Chapter 2- LectureChapter 2- Lecture
Chapter 2- Lecture
 
Chapter 1- Lecture
Chapter 1- LectureChapter 1- Lecture
Chapter 1- Lecture
 
Construction equipment management chapter 5
Construction equipment management chapter 5Construction equipment management chapter 5
Construction equipment management chapter 5
 
Construction equipment management chapter 1pdf
Construction equipment management chapter 1pdfConstruction equipment management chapter 1pdf
Construction equipment management chapter 1pdf
 
Chapter 5 [compatibility mode]
Chapter 5 [compatibility mode]Chapter 5 [compatibility mode]
Chapter 5 [compatibility mode]
 
Chapter 4 [compatibility mode]
Chapter 4 [compatibility mode]Chapter 4 [compatibility mode]
Chapter 4 [compatibility mode]
 
Chapter 3 [compatibility mode]
Chapter 3 [compatibility mode]Chapter 3 [compatibility mode]
Chapter 3 [compatibility mode]
 
Chapter 2 [compatibility mode]
Chapter 2 [compatibility mode]Chapter 2 [compatibility mode]
Chapter 2 [compatibility mode]
 

Recently uploaded

HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
SupreethSP4
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
ongomchris
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 

Recently uploaded (20)

HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 

Construction equipment management chapter 3

  • 2. General  Estimating and planning involves the judicious selection of equipment, the careful scheduling of time and resources, and the accurate determination of expected system output and cost. Definition  It is the number of units and the size of equipment that would permit the constructor to accomplish the activity with a duration resulting in the lowest cost. 2 February 2019 2 COTM 4202
  • 3.  Haul unit horsepower  Haul road rolling resistance  Haul road grades  Haul unit loaded and empty weight  Haul unit transmission characteristics  Haul unit loading time  Haul unit travel time  Haul unit delay time  Altitude of the project site  Haul unit horsepower  Haul road rolling resistance  Haul road grades  Haul unit loaded and empty weight  Haul unit transmission characteristics  Haul unit loading time  Haul unit travel time  Haul unit delay time  Altitude of the project site 2 February 2019 COTM 4202 3
  • 4.  Total power that an engine is capable of generating is expressed as its horsepower.  Available horsepower is power that is available to perform work after taking into account losses and consumption in other machine functions.  Rimpull is defined as the tractive force between the driving wheels and the surface on which they travel.( V is velocity in mph)  Total power that an engine is capable of generating is expressed as its horsepower.  Available horsepower is power that is available to perform work after taking into account losses and consumption in other machine functions.  Rimpull is defined as the tractive force between the driving wheels and the surface on which they travel.( V is velocity in mph) 2 February 2019 COTM 4202 4
  • 5. Power generated by engine 2 February 2019 COTM 4202 5 Drawbar Pull Rolling Resistance Rimpull
  • 6.  Rolling resistance is resistance offered to movement of materials on a plain surface; often expressed in pounds per ton of materials.  Rolling Resistance depends upon: 2 February 2019 COTM 4202 6
  • 8.  The force-opposing movement of a machine up a frictionless slope is grade resistance.  The effect of gravitational force in aiding movement of a vehicle down a slope is grade assistance. 2 February 2019 COTM 4202 8 F= 20 lbs/ G% per Ton
  • 9.  The cycle capacity C of a piece of equipment is defined as the number of output units per cycle of operation under standard work conditions.  The standard production rate R of a piece of construction equipment is defined as the number of output units per unit time.  The cycle time T refers to units of time per cycle of operation.  The cycle capacity C of a piece of equipment is defined as the number of output units per cycle of operation under standard work conditions.  The standard production rate R of a piece of construction equipment is defined as the number of output units per unit time.  The cycle time T refers to units of time per cycle of operation. 2 February 2019 COTM 4202 9
  • 10.  Time to load a mover for load shifting will determine loads that can be transferred. Longer loading time lesser will be productivity.  To is loading time  Te is cycle time for loader/excavator  Ch is capacity of a hauler (dump truck)  Ce loading rate/capacity of loader  Time to load a mover for load shifting will determine loads that can be transferred. Longer loading time lesser will be productivity.  To is loading time  Te is cycle time for loader/excavator  Ch is capacity of a hauler (dump truck)  Ce loading rate/capacity of loader 2 February 2019 COTM 4202 10
  • 11.  It is time for moving load from production site to disposal site. Longer time will reduce productivity.  To determine the productivity of a hauler, › Let: D be the distance from source to a dump site, S be the average speed of the hauler, Tt be the travel time for the round trip to the dump site, To be the loading time,Td be the dumping time plus other delays.  Then the travel time for the round trip is given by:  It is time for moving load from production site to disposal site. Longer time will reduce productivity.  To determine the productivity of a hauler, › Let: D be the distance from source to a dump site, S be the average speed of the hauler, Tt be the travel time for the round trip to the dump site, To be the loading time,Td be the dumping time plus other delays.  Then the travel time for the round trip is given by: 2 February 2019 COTM 4202 11
  • 12.  Human and machine system suffer from inherent delays due to reaction time and capacity, say Td. 2 February 2019 COTM 4202 12
  • 13.  For a given dumping time Td, the total cycle time Th of the hauler is the sum of loading time, travel time and damping time given by:  For a given dumping time Td, the total cycle time Th of the hauler is the sum of loading time, travel time and damping time given by: 2 February 2019 COTM 4202 13
  • 14.  Optimum number of haul units (N) is determined by:  NB: Rounding down will maximize haul unit productivity.  Optimum number of haul units (N) is determined by:  NB: Rounding down will maximize haul unit productivity. 2 February 2019 COTM 4202 14
  • 15.  An 16 cubic meter dump truck has a loading time of 3 min, a travel time of 7 min, and the dumping and delay times of 5 min. Calculate the cycle time of the hauler and optimum number of hauling units.  An 16 cubic meter dump truck has a loading time of 3 min, a travel time of 7 min, and the dumping and delay times of 5 min. Calculate the cycle time of the hauler and optimum number of hauling units. 2 February 2019 COTM 4202 15
  • 16.  The daily standard production rate Pe of an excavator is is given by:  He is the operating hours per day  Ce is the cycle capacity (in units of volume) of the excavator  Te is the cycle time (in hours) of the excavator  The daily standard production rate Pe of an excavator is is given by:  He is the operating hours per day  Ce is the cycle capacity (in units of volume) of the excavator  Te is the cycle time (in hours) of the excavator 2 February 2019 COTM 4202 16
  • 17.  The daily standard production rate Ph of a hauler is given by:  Rh is standard production rate  Hh is the number of operating hours per day  The daily standard production rate Ph of a hauler is given by:  Rh is standard production rate  Hh is the number of operating hours per day 2 February 2019 COTM 4202 17
  • 18.  A 1.5 cubic meter front-end loader is going to load dump trucks with a capacity of 9.0 cubic meter. The loader takes 0.4 min to fill and load one bucket. The travel time in the haul is 4.0 min. Dump and delay times are 2.5 min combined. Calculate:  The loading time,  The cycle time of hauler,  Number of trucks,  The hourly production rate of haul units, and  The hourly production of loader  A 1.5 cubic meter front-end loader is going to load dump trucks with a capacity of 9.0 cubic meter. The loader takes 0.4 min to fill and load one bucket. The travel time in the haul is 4.0 min. Dump and delay times are 2.5 min combined. Calculate:  The loading time,  The cycle time of hauler,  Number of trucks,  The hourly production rate of haul units, and  The hourly production of loader 2 February 2019 COTM 4202 18
  • 19.  A power shovel with a dipper of one cubic meter capacity has a standard operating cycle time of 30 seconds. Find the daily standard production rate of the shovel. Ce = 1 cu. mtr., Te = 30 sec. and He = 8 hours.  A power shovel with a dipper of one cubic meter capacity has a standard operating cycle time of 30 seconds. Find the daily standard production rate of the shovel. Ce = 1 cu. mtr., Te = 30 sec. and He = 8 hours. 2 February 2019 COTM 4202 19
  • 20.  A dump truck with a capacity of 6 cubic meter is used to dispose of excavated materials at a dump site 4 km away. The average speed of the dump truck is 30 mph and the dumping time is 30 seconds. Find the daily standard production rate of the truck. If a fleet of dump trucks of 9 cubic meter capacity is used to dispose of the excavated materials for 8 hours per day, determine the number of trucks needed daily.  A dump truck with a capacity of 6 cubic meter is used to dispose of excavated materials at a dump site 4 km away. The average speed of the dump truck is 30 mph and the dumping time is 30 seconds. Find the daily standard production rate of the truck. If a fleet of dump trucks of 9 cubic meter capacity is used to dispose of the excavated materials for 8 hours per day, determine the number of trucks needed daily. 2 February 2019 COTM 4202 20
  • 21.  Material properties have a direct effect on the ease or difficulty of handling the material, on the selection of equipment, and on equipment production rates.  Quantities are often measured in volume units.  Volume of material under different conditions varies appreciably.  Material properties have a direct effect on the ease or difficulty of handling the material, on the selection of equipment, and on equipment production rates.  Quantities are often measured in volume units.  Volume of material under different conditions varies appreciably. 2 February 2019 COTM 4202 21
  • 22.  Bank: Material in its natural state. Also called in-place or in-situ. Measurement: BCM (Bank Cubic Meter)  Lose: material that has been excavated or loaded. Measurement: LCM (Lose Cubic Meter)  Compacted: Material after compaction: Measurement: CCM (Compacted Cubic Meter) 2 February 2019 COTM 4202 22  Bank: Material in its natural state. Also called in-place or in-situ. Measurement: BCM (Bank Cubic Meter)  Lose: material that has been excavated or loaded. Measurement: LCM (Lose Cubic Meter)  Compacted: Material after compaction: Measurement: CCM (Compacted Cubic Meter)
  • 23. Swell Factor Shrinkage Factor  The swell factor is the ratio of the loose dry weight per unit volume to the bank dry weight per unit volume. Loose dry unit weight Swell Factor (w) = _____________________ Bank dry unit weight Swell% = ( 1/w – 1 )x100  The shrinkage factor is the ratio of the compacted dry weight per unit volume to the bank dry weight per unit volume: Compacted dry unit weight Shrinkage Factor = _________________________ Bank dry unit weight Shrinkage % = ( SrF – 1 )x100 Shrinkage Factor  The shrinkage factor is the ratio of the compacted dry weight per unit volume to the bank dry weight per unit volume: Compacted dry unit weight Shrinkage Factor = _________________________ Bank dry unit weight Shrinkage % = ( SrF – 1 )x100 2 February 2019 COTM 4202 23
  • 25.  Let w denote the swell factor of the soil  wPe denote the daily volume of loose excavated materials.  Then the approximate number of haulers required to dispose of the excavated materials is given by:  Let w denote the swell factor of the soil  wPe denote the daily volume of loose excavated materials.  Then the approximate number of haulers required to dispose of the excavated materials is given by: 2 February 2019 COTM 4202 25
  • 26.  Equipment productivities at job sites are influenced by actual work conditions and a variety of inefficiencies and work stoppages.  Let F1, F2, ..., Fn, denote factors that lower productivity, each of which is smaller than 1,  Then the actual equipment productivity R' at the job site can be related to the standard production rate R as follows:  Equipment productivities at job sites are influenced by actual work conditions and a variety of inefficiencies and work stoppages.  Let F1, F2, ..., Fn, denote factors that lower productivity, each of which is smaller than 1,  Then the actual equipment productivity R' at the job site can be related to the standard production rate R as follows: 2 February 2019 COTM 4202 26
  • 27.  The actual cycle time T' at the job site is related to the standard cycle time T as: 2 February 2019 COTM 4202 27
  • 28.  A power shovel with a dipper of 1.2 cubic meter capacity has a standard production rate of 960 cubic meter for an 8-hour day. 4min is consumed to fill and load. Determine the job site productivity and the actual cycle time of this shovel under the work conditions at the site that affects its productivity as shown below:  Work Conditions at the Site Factors Bulk composition 0.954 Soil properties and water content 0.983 Equipment idle time for worker breaks 0.8 Management efficiency 0.7  A power shovel with a dipper of 1.2 cubic meter capacity has a standard production rate of 960 cubic meter for an 8-hour day. 4min is consumed to fill and load. Determine the job site productivity and the actual cycle time of this shovel under the work conditions at the site that affects its productivity as shown below:  Work Conditions at the Site Factors Bulk composition 0.954 Soil properties and water content 0.983 Equipment idle time for worker breaks 0.8 Management efficiency 0.7 2 February 2019 COTM 4202 28
  • 29.  A dump truck with a capacity of 6 cubic meter is used to dispose of excavated materials. The distance from the dump site is 4km and the average speed of the dump truck is 30 kph. The job site productivity of the power shovel per day is 504 cubic meter, which will be modified by a swell factor of 1.1. The only factors affecting the job site productivity of the dump truck in addition to those affecting the power shovel are 0.80 for equipment idle time and 0.70 for management efficiency. Determine the job site productivity of the dump truck. If a fleet of such trucks is used to haul the excavated material, find the number of trucks needed daily.  A dump truck with a capacity of 6 cubic meter is used to dispose of excavated materials. The distance from the dump site is 4km and the average speed of the dump truck is 30 kph. The job site productivity of the power shovel per day is 504 cubic meter, which will be modified by a swell factor of 1.1. The only factors affecting the job site productivity of the dump truck in addition to those affecting the power shovel are 0.80 for equipment idle time and 0.70 for management efficiency. Determine the job site productivity of the dump truck. If a fleet of such trucks is used to haul the excavated material, find the number of trucks needed daily. 2 February 2019 COTM 4202 29
  • 30.  A front-end loader loads a fleet of dump trucks (capacity 18 loose cubic meter each), which haul the earth to a fill where it is compacted with a shrinkage factor of 10%. The earth has a percent swell of 20%. The job requires a volume of 18,000 compacted cubic meter. Distance between quarry and project site is 5miles connected with dirt track.  How many hours will be required to excavate and haul the material to the fill.  A front-end loader loads a fleet of dump trucks (capacity 18 loose cubic meter each), which haul the earth to a fill where it is compacted with a shrinkage factor of 10%. The earth has a percent swell of 20%. The job requires a volume of 18,000 compacted cubic meter. Distance between quarry and project site is 5miles connected with dirt track.  How many hours will be required to excavate and haul the material to the fill. 2 February 2019 COTM 4202 30
  • 31. THANK YOU! THANK YOU! 31 THANK YOU! THANK YOU! 2 February 2019 COTM 4202