Call Girls Delhi {Jodhpur} 9711199012 high profile service
Chapter 5- Lecture
1. Chapter 5
Equipment Operation
Instructor: Andualem Endris (M.Sc)
andu0117@yahoo.com
School of Engineering,
Construction Technology & Management Department
A. Safety
Madawalabu
University
2. Signs and symbols
Visible at all times
Danger signs
Caution signs
1a
July 31, 2021 2
COTM 4202
3. Exit signs
Legible red letters
Or red background with legible
white letters
2a
CLOSED CLOSED
July 31, 2021 3
COTM 4202
14. Inspect for:
Lights
Fire extinguishers
Reflectors
Other
equipment
12f
July 31, 2021
14
COTM 4202
15. Correct all defects
Before equipment is placed in
service
12h
July 31, 2021 15
COTM 4202
16. Operating equipment in
reverse: Do if
The equipment has a reverse
signal alarm distinguishable
from the surrounding noise
level, or
An employee signals that it is
safe to do so
13a
July 31, 2021 16
COTM 4202
18. B. Equipment Utilization
Utilization is working time
duration, not calendar duration
Utilization data are:
• Work load
• Speed
• Environment
(See Chapter 3: Productivity)
July 31, 2021 COTM 4202 18
19. C. Technology
Automation of Equipment
• The introduction of new mechanized equipment
in construction has had a profound effect on the
cost and productivity of construction as well as
the methods used for construction itself.
• An exciting example of innovation in this regard
is the introduction of computer microprocessors
on tools and equipment. As a result, the
performance and activity of equipment can be
continually monitored and adjusted for
improvement.
July 31, 2021 COTM 4202 19