CURRICULUM VITAE
Name : Kothur Chennakesavulu
Profession : Civil Engineer
Date of Birth : 20
th
May, 1956
Years with Firm / Entity : Available for the assignment Nationality : Indian
Membership of : Nil
Professional Societies
Education :
B. Tech. in Civil Engineering from Sree Venkateswara University, Tirupathi in 1979.
Other Training:
1. Undergone training programmes conducted by the Department from time to time on various
subjects like Quality Assurance, Executive Development programme etc.,
2. Continuing Education programme on “HIGHWAY CONSTRUCTION AND MANAGEMENT”
conducted by IIT Madras.
3. Attended Workshop on “QUALITY CONTROL ASPECTS FOR HIGHWAY AND BRIDGE
PROJECTS” by Indian Roads congress.
Awards/Recognition
 Best Engineer Award in 15-09-2013 by Institute of Engineers India, Kadapa
Training Imparted:
 NIL
Technical Paper / Published:
 IMPROPER CURING Journal of Kurnool District Technical Forum, Vol.6 and No.1
September 2005
Employment Record:
June 2011-may 2014, Executive Engineer, Roads & Buildings Dept., Nandyal, Kurnool District, Govt. of
Andhra Pradesh
 Construction of ROB in lieu of LC No. 183 at Railway Km 258/0-1 of Nandyal Panyam section and km
0/0-6 of Nandyal – Atmakur road in Kurnool District, Lane: double, length: 1.1 km, Cost: 39 Crores
 Construction of High level Bridge in Km 75/10 & 76/2 of peapally- Banaganapally-Gajulapally road
(NDL) in Kurnool district with estimate cost of rs. 4.00 crores
 Construction of High level Bridge in Km 8/2 of Nandyal-Atmakur road in Kurnool district with estimate
cost Rs. 2.50 Crores
 Construction of HLB at KM 54/2-6 of chgalamarri-Mahadevapuram road in Kurnool district with
estimate cost Rs. 3.10 crores.
 output and performance based Road contract for the maintenance of package-22 Roads in Kurnool
.District of Andhra Pradesh Lane: Double Length: 124 Km, Cost: INR 35.00 Cr.
 output and performance based Road contract for the maintenance of package-39 Roads in Kurnool
.District of Andhra Pradesh Lane: Double Length: 134 Km, Cost: INR 35.00 Cr.
 Widening and strengthening from Km 35/2 to 52/246 of Nandyal-Atmakur Road in Kurnool district, Lane:
Double, Length: 15.246 Km, Cost: Rs. 12.00 Crores
 Widening and Strengthening from Km 3/0 to 6/0 of Koilakuntla-Allagadda Road in Kurnool district, Lane:
Double, Length: 3.00 Km, Cost: Rs. 2.00 Crores
2/4
 Widening and Strengthening from Km 3/0 to 6/0 of Koilakuntla-Allagadda Road in Kurnool district, Lane:
Double, Length: 6.20 Km, Cost: Rs. 7.65 Crores
 Widening and from Km 15/0 to 21/6 & 23/0 to 36/4 of Nandyal-Thimmanayunipeta Road in Kurnool
district, Lane: Double, Length: 20.00 Km, Cost: Rs. 20.00 Crores
 Widening and Strengthening From Km 29/0 to 25/0 & 41/6 to 47/8 of PBG Road, Lane: Double, Length:
12.00 Km, Cost: Rs. 10.00 Crores
 Widening From Km 41/0 to 46/0 Nandyal-Thimmanayunipeta Road, Lane: Double, Length: 5.00 Km,
Cost: Rs. 4.00 Crores
 Widening and Strengthening From Km 0/0 to 13/509 of Koilakuntla-Banaganapally Road (CRF), Lane:
Double, Length: 13.50 Km, Cost: Rs. 14.00 Crores
 Under NABARD the rural roads are improved to a length of 18.16 Km with a tune of Rs. 13.00
crores
 Under APRDF scheme the rural roads are improved to a length of 14.9 Km with a tune of Rs. 16.8
crores
 Under Special repairs programme 65 Km length of the road is improved with a tune of Rs. 22.3
Crores
 Under 13 th finance commission the Black top roads are improved to a length of 110 Km with
estimate cost of Rs. 16.8 crores
As Executive Engineer, was overall responsible for execution/supervision of widening, improvements and
heavy periodical maintenance for Roads and Highways and Bridge projects, ROB's, Approval of working
drawings, contractors work plan, procedures, Implementation of QC assurance plans and monitoring the
processing of work ,cost control and approval of payment certificate etc., Involved in design review and
modifications as per site conditions, approval of working drawings, approval of contractor’s work plan,
procedures, method statements, plants and equipments, Implementation of Quality Assurance Plans,
Interpretation of contractual obligations, contract administration; monitoring progress of works using latest
project management techniques and safety measures, traffic management, cost control and approval of
Payment certificates; preparing monthly and other project progress reports. Sanctioning of Minor works and
special repairs and urgent repairs costing Rs. 10.00 Lakhs and below and further scrutiny of tenders and
concluding the agreements.
Sept 2006- May 2011; Deputy Executive Engineer; Adoni, Kurnool District of Andhra Pradesh.
The following major works were executed in addition to the annual maintenance and special repair works for a
length of 330 Kms:
 Bypass Road formation to Adoni km 0/0 to 2/1 and Km 5/4 to 10.895 Lane: 2, Length: 7.596 Km, Cost:
9.00 Crores.
 Railway Over Bridge For LC no 198 at Railway Km 500/8-9 of Guntakal -wadi section Lane: 2, Length:
1.00 km Cost: 15.00 Crores
 Widening & Strengthening Km 93/0 to 126/7 Kurnool - Bellary Road (under CRF) Lane: 2, Length: 5.00
km Cost: 2.00 Crores
 Widening & strengthening from Km 3/0 to 26/7 Adoni-siruguppa Road (CRF) with estimate cost of Rs.
2.00 Crores
 Under NABARD rural roads are improved to a length of 43.00 Kms with estimate cost of Rs 8.00
crores
 Under APRDF the rural roads are strengthened to a length of 7 Km with an estimate cost of Rs.
4.00 Crores
 Under 12 th finance commission 6.00 Km are improved with a tune of Rs. 1.50 Crores
Supervision of Road maintenance works, Special repair works for a length of 330 km pertaining to R & B Sub
division Jurisdiction including NABARD, ROB and PLAN works. As Deputy Executive Engineer, was
responsible for geotechnical investigations including pit test, DCP test, field density test, soil testing, field
testing and independent testing of construction material, collection of geotechnical data, compilation, analysis,
prescribe parameters for design of embankments, bridge foundation, etc., also responsible for assisting in
3/4
drafting Quality assurance program, reconnaissance & Identification of borrow areas and quarries, framing
guidelines for testing of soil and other construction materials, analysis, tabulation and interpretation of test
results; stipulating conditions for setting up of site laboratories; formulating test procedures and quality control
measures to ensure adoption of required standard in all construction activities of the project, pavement
investigation, condition surveys, Pavement option study and detailed design of pavement crust as per IRC,
ASHTO Specifications.
Aug 2003 to Aug 2006; Deputy Executive Engineer, Roads & Buildings Dept., Yemmiganur, Kurnool
District, Govt. of Andhra Pradesh
 Widening and Strengthening from Km 10/0 to 15/0 of Yemmiganur-Mantralyam Road andkm 0/0 to
14/0 of Tungabhadra RS to Mantralayam, Lane: 2, Length: 19 kms, Cost: 5.00 Crores
 Widening and Strengthening of the road Km 84/0 to 101/2 of Guntakal-Tungabhadra Road in
Kurnool district with estimate cost of rs. 5.00 crores for a length of 17.2 km
 Construction of HLB at Km 9/2 of Thungabadhra RS to Mantralayam in Kurnool district with
estimate cost of Rs 1.00 crore
 Construction of HLB at Km 4/6 of Yemmiganur- Mantralayam road in Kurnool district with estimate
cost of Rs 50.00 Lakhs
 Construction of HLB at Km 8/2 of Yemmiganur-Mantralayam road in Kurnool district with estimate
cost of Rs. 50.00 Lakhs
Supervision of Road maintenance works, Special repair works for a length of 330 km pertaining to R & B
Jurisdiction including NABARD, ROB and PLAN works. As Deputy Executive Engineer, was responsible for
geotechnical investigations including pit test, DCP test, field density test, soil testing, field testing and
independent testing of construction material, collection of geotechnical data, compilation, analysis, prescribe
parameters for design of embankments, bridge foundation, etc., also responsible for assisting in drafting
Quality assurance program, reconnaissance & Identification of borrow areas and quarries, framing guidelines
for testing of soil and other construction materials, analysis, tabulation and interpretation of test results;
stipulating conditions for setting up of site laboratories; formulating test procedures and quality control
measures to ensure adoption of required standard in all construction activities of the project, pavement
investigation, condition surveys, Pavement option study and detailed design of pavement crust as per IRC,
ASHTO Specifications.
April 2000 to Aug 2003; Assistant Executive Engineer, E-N-C Office, Hyderabad, Govt. of Andhra
Pradesh
Worked as Assistant Executive Engineer in Roads & buildings, Designs wing in the office of E-N-C,
Hyderabad. Involved in scrutiny of estimates and designs and according Administrative approval and
Technical sanction of Road and Bridge works costing Rs. 100 Lakhs and above, such as crust design of
pavement, fixing of longitudinal and cross sectional profile of new roads to minimize the earthwork component
in embankments and cross checking of designs of Bridges and ROBs.
May 1997-March 2003; Assistant Executive Engineer on Deputation with Director of Technical
Education, Hyderabad
World Bank is funded for upgradation of 44 number of Polytechnic Colleges in Andhra Pradesh. For this SPIU
(Special Project implimentation unit) unit has been formed in director of technical Education in Hyderabad to
monitor with the executive agencies and world bank including reimbursement and QC assurance.
July 1993 to April 1997; Assistant Executive Engineer, R&B Section, Tadpatri, anantapur District,
Andhra Pradesh
The following works are excuted apart from annual mainance and special repair woks
 Formation of Bypass Road to Tadpatri town in Anantapur district with estimate cost of Rs. 50.00
Lakhs
 Construction of Degree College building at Tadpatri with estimate cost of Rs. 60.00 Lakhs.
 Construction of Shaadi Khana at Tadpatri with estimate cost of Rs. 20.00 Lakhs
June 1991 - July 1993; Assistant Executive Engineer; Roads & Bilding Dept.,Kadiri,anantapur district
Govt. of Andhra Pradesh
4/4
 Supervision of Annual Maintenance and Special repair works for a length of 120 Km.
As Assistant Executive engineer responsible for Road condition survey, collection of data for Road
network improvements and preparation of improvement and new alignment project designing and
preparation of feasibility reports. Maintenance of Road infrastructure in Kadiri, Anantapur District of
Andhra Pradesh
April 1987-May 1991; Assistant Executive Engineer; Roads & Buildings Dept.,Madakasira anatapur
distrit. Govt. of Andhra Pradesh
 Supervision of Annual Maintenance and Special repair works for a length of 212 Km.
May 1986 - March 1987; Assistant Executive Engineer; Roads & Buildings Dept., Tirupati, Chittoor
District, Govt. of Andhra Pradesh
 Incharge for the Medical College Buildings, annual Maintenance of Buildings and special
repair works. Apart from this the following Special assignment projects are executed:
1. Contruction of Leprosy training centre with estimate cost of Rs. 60.00 Lakhs
2. Contruction of Cardiology block with estimate cost of Rs. 40.00 Lakhs
June 1984 - May 1986; Assistant Executive Engineer; Roads & Buildings Dept.Pulivendula, Kadapa
District, Govt. of Andhra Pradesh
 Supervision of Annual Maintenance and Special repair works for a length of 156 Km
June 1983- May 1984; Assistant Executive Engineer; Roads & Buildings Dept., Proddatur, Kadapa
District, Govt. of Andhra Pradesh
The following major works are executed with well foundation on the major River Kundu:
 Construction of HLB across Kundu river at Km 165/0 to0/8 of Nellore- Bellary - Bombay Road
in Kadapa Lane: 2, Length: 0.80 Km, Cost: 1.00 Crore
April 1981- May 1983; Assistant Executive Engineer; Roads & Buildings Dept., Pourumamilla, Kadapa
District, Govt. of Andhra Pradesh
 Supervision of Annual Maintenance and Special repair works for a length of 120 Km
As Assistant Executive engineer responsible for Road condition survey, collection of data for Road
network improvements and preparation of improvement and new alignment project designing and
preparation of feasibility reports. Maintenance of Road infrastructure in Pourumamilla, Kadapa District of
Andhra Pradesh
Sept 1979 - March 1981; Assistant Executive Engineer; Roads & Buildings Dept., Guntur, Guntur
Disrict, Govt. of Andhra Pradesh
 Investigation & Survey work Including Preparation of land plans for Aqusition of Commamded
Area development Roads including Design of Bridges, culvers and other Geometrical features
and preparation of Detailed Estimate for Administrative sanction
Languages Speaking Reading Writing
English Excellent Excellent Excellent
Telugu Excellent Excellent Excellent

More Related Content

What's hot

most final report of industrial training for college
most final report of industrial training for collegemost final report of industrial training for college
most final report of industrial training for college
indrajeet kumar
 
Highway Engineer
Highway EngineerHighway Engineer
Highway Engineer
hemanth kumar
 
Internship report by Muhammad Kamal Ud Din Anwar
Internship report by Muhammad Kamal Ud Din AnwarInternship report by Muhammad Kamal Ud Din Anwar
Internship report by Muhammad Kamal Ud Din Anwar
Kamal787
 
CURRICULUM_VITAE__NHAI_latest
CURRICULUM_VITAE__NHAI_latestCURRICULUM_VITAE__NHAI_latest
CURRICULUM_VITAE__NHAI_latest
venkata satyanarayana
 
Internship Report
Internship ReportInternship Report
Internship Report
prathagarg
 
resume_ajaysingh2926_rediffmail.com_-1__2_new__1_
resume_ajaysingh2926_rediffmail.com_-1__2_new__1_resume_ajaysingh2926_rediffmail.com_-1__2_new__1_
resume_ajaysingh2926_rediffmail.com_-1__2_new__1_
Ajay singh
 
Curriculum Vitae-Zuber
Curriculum Vitae-ZuberCurriculum Vitae-Zuber
Curriculum Vitae-Zuber
Mohammed Zuber Inamdar
 
Central Public Works Department (CPWD) summer training report
Central Public Works Department (CPWD) summer training reportCentral Public Works Department (CPWD) summer training report
Central Public Works Department (CPWD) summer training report
Aman Gupta
 
CV Partha
CV ParthaCV Partha
CV Partha
Partha Mukherjee
 
Summer Internship Report of Civil Engineering in Construction Site
Summer Internship Report of Civil Engineering in Construction SiteSummer Internship Report of Civil Engineering in Construction Site
Summer Internship Report of Civil Engineering in Construction Site
RAVI KUMAR
 
Resume
ResumeResume
TABLE OF CONTENTS
TABLE OF CONTENTSTABLE OF CONTENTS
TABLE OF CONTENTS
Revanth chandra
 
well foundation of six lane new ganga bridge near kacchi dargah in district P...
well foundation of six lane new ganga bridge near kacchi dargah in district P...well foundation of six lane new ganga bridge near kacchi dargah in district P...
well foundation of six lane new ganga bridge near kacchi dargah in district P...
Arman Hashmi
 
CV Suresh44UIC
CV Suresh44UICCV Suresh44UIC
CV Suresh44UIC
Sureshb21 Fasttrack
 
CURRICULAM DKS1
CURRICULAM DKS1CURRICULAM DKS1
CURRICULAM DKS1
Dharmendra Srivastava
 
Resume of Ashwani Tyagi
Resume of Ashwani TyagiResume of Ashwani Tyagi
Resume of Ashwani Tyagi
Ashwani Tyagi
 
Industrial Summer Training Report at Construction Site of CPWD
Industrial Summer Training Report at Construction Site of CPWD Industrial Summer Training Report at Construction Site of CPWD
Industrial Summer Training Report at Construction Site of CPWD
Alok Mishra
 
LVS Varma
LVS VarmaLVS Varma
LVS Varma
lokesh varma
 
road construction project
road construction projectroad construction project
road construction project
nishant singh
 

What's hot (19)

most final report of industrial training for college
most final report of industrial training for collegemost final report of industrial training for college
most final report of industrial training for college
 
Highway Engineer
Highway EngineerHighway Engineer
Highway Engineer
 
Internship report by Muhammad Kamal Ud Din Anwar
Internship report by Muhammad Kamal Ud Din AnwarInternship report by Muhammad Kamal Ud Din Anwar
Internship report by Muhammad Kamal Ud Din Anwar
 
CURRICULUM_VITAE__NHAI_latest
CURRICULUM_VITAE__NHAI_latestCURRICULUM_VITAE__NHAI_latest
CURRICULUM_VITAE__NHAI_latest
 
Internship Report
Internship ReportInternship Report
Internship Report
 
resume_ajaysingh2926_rediffmail.com_-1__2_new__1_
resume_ajaysingh2926_rediffmail.com_-1__2_new__1_resume_ajaysingh2926_rediffmail.com_-1__2_new__1_
resume_ajaysingh2926_rediffmail.com_-1__2_new__1_
 
Curriculum Vitae-Zuber
Curriculum Vitae-ZuberCurriculum Vitae-Zuber
Curriculum Vitae-Zuber
 
Central Public Works Department (CPWD) summer training report
Central Public Works Department (CPWD) summer training reportCentral Public Works Department (CPWD) summer training report
Central Public Works Department (CPWD) summer training report
 
CV Partha
CV ParthaCV Partha
CV Partha
 
Summer Internship Report of Civil Engineering in Construction Site
Summer Internship Report of Civil Engineering in Construction SiteSummer Internship Report of Civil Engineering in Construction Site
Summer Internship Report of Civil Engineering in Construction Site
 
Resume
ResumeResume
Resume
 
TABLE OF CONTENTS
TABLE OF CONTENTSTABLE OF CONTENTS
TABLE OF CONTENTS
 
well foundation of six lane new ganga bridge near kacchi dargah in district P...
well foundation of six lane new ganga bridge near kacchi dargah in district P...well foundation of six lane new ganga bridge near kacchi dargah in district P...
well foundation of six lane new ganga bridge near kacchi dargah in district P...
 
CV Suresh44UIC
CV Suresh44UICCV Suresh44UIC
CV Suresh44UIC
 
CURRICULAM DKS1
CURRICULAM DKS1CURRICULAM DKS1
CURRICULAM DKS1
 
Resume of Ashwani Tyagi
Resume of Ashwani TyagiResume of Ashwani Tyagi
Resume of Ashwani Tyagi
 
Industrial Summer Training Report at Construction Site of CPWD
Industrial Summer Training Report at Construction Site of CPWD Industrial Summer Training Report at Construction Site of CPWD
Industrial Summer Training Report at Construction Site of CPWD
 
LVS Varma
LVS VarmaLVS Varma
LVS Varma
 
road construction project
road construction projectroad construction project
road construction project
 

Viewers also liked

CV new 2015
CV new 2015CV new 2015
CV new 2015
ashraf telbany
 
Hedayatullah CV
Hedayatullah CVHedayatullah CV
Hedayatullah CV
Hedayat Shaikh
 
CURRICULUM VITAE 4 for bidding-nest
CURRICULUM VITAE 4 for bidding-nestCURRICULUM VITAE 4 for bidding-nest
CURRICULUM VITAE 4 for bidding-nest
Emeka Nweke
 
Costing Engineer Job Ref 1210 17
Costing Engineer Job Ref 1210 17Costing Engineer Job Ref 1210 17
Costing Engineer Job Ref 1210 17
Sean Durrant
 
19.2 CV M. Arteaga updated on August, 2015_engl version
19.2 CV M. Arteaga updated on August, 2015_engl version19.2 CV M. Arteaga updated on August, 2015_engl version
19.2 CV M. Arteaga updated on August, 2015_engl version
Mario Arteaga
 
Cr klb oil&gas proposal engineer
Cr klb oil&gas   proposal engineerCr klb oil&gas   proposal engineer
Cr klb oil&gas proposal engineer
omcsdd
 
PSP.PERERA CV
PSP.PERERA CVPSP.PERERA CV
PSP.PERERA CV
shihan perera
 
Imthiyaz cvs
Imthiyaz cvsImthiyaz cvs
Imthiyaz cvs
Mohamed Imthiyaz
 
Kosinski, Andy - CV
Kosinski, Andy - CVKosinski, Andy - CV
Kosinski, Andy - CV
akosinski
 
Bid manager
Bid managerBid manager
Bid manager
Kelvin Campbell
 
Engr. Asim Mahmood CV
Engr. Asim Mahmood CVEngr. Asim Mahmood CV
Engr. Asim Mahmood CV
Engr.Asim Mahmood
 
Resume
ResumeResume
Resume
Banumathi M
 
Mallikarjuna Update CV (2)
Mallikarjuna Update CV (2)Mallikarjuna Update CV (2)
Mallikarjuna Update CV (2)
krofta engineering ltd
 
CV_ Sayantan Ghosh_B.Tech_Electrical
CV_ Sayantan Ghosh_B.Tech_ElectricalCV_ Sayantan Ghosh_B.Tech_Electrical
CV_ Sayantan Ghosh_B.Tech_Electrical
SAYANTAN GHOSH
 
Girish BG - CV
Girish BG - CVGirish BG - CV
Girish BG - CV
Girish BG
 
Kamaldeep Singh (Manager Tenders & Project)
Kamaldeep Singh (Manager Tenders & Project)Kamaldeep Singh (Manager Tenders & Project)
Kamaldeep Singh (Manager Tenders & Project)
Kamaldeep Singh
 

Viewers also liked (16)

CV new 2015
CV new 2015CV new 2015
CV new 2015
 
Hedayatullah CV
Hedayatullah CVHedayatullah CV
Hedayatullah CV
 
CURRICULUM VITAE 4 for bidding-nest
CURRICULUM VITAE 4 for bidding-nestCURRICULUM VITAE 4 for bidding-nest
CURRICULUM VITAE 4 for bidding-nest
 
Costing Engineer Job Ref 1210 17
Costing Engineer Job Ref 1210 17Costing Engineer Job Ref 1210 17
Costing Engineer Job Ref 1210 17
 
19.2 CV M. Arteaga updated on August, 2015_engl version
19.2 CV M. Arteaga updated on August, 2015_engl version19.2 CV M. Arteaga updated on August, 2015_engl version
19.2 CV M. Arteaga updated on August, 2015_engl version
 
Cr klb oil&gas proposal engineer
Cr klb oil&gas   proposal engineerCr klb oil&gas   proposal engineer
Cr klb oil&gas proposal engineer
 
PSP.PERERA CV
PSP.PERERA CVPSP.PERERA CV
PSP.PERERA CV
 
Imthiyaz cvs
Imthiyaz cvsImthiyaz cvs
Imthiyaz cvs
 
Kosinski, Andy - CV
Kosinski, Andy - CVKosinski, Andy - CV
Kosinski, Andy - CV
 
Bid manager
Bid managerBid manager
Bid manager
 
Engr. Asim Mahmood CV
Engr. Asim Mahmood CVEngr. Asim Mahmood CV
Engr. Asim Mahmood CV
 
Resume
ResumeResume
Resume
 
Mallikarjuna Update CV (2)
Mallikarjuna Update CV (2)Mallikarjuna Update CV (2)
Mallikarjuna Update CV (2)
 
CV_ Sayantan Ghosh_B.Tech_Electrical
CV_ Sayantan Ghosh_B.Tech_ElectricalCV_ Sayantan Ghosh_B.Tech_Electrical
CV_ Sayantan Ghosh_B.Tech_Electrical
 
Girish BG - CV
Girish BG - CVGirish BG - CV
Girish BG - CV
 
Kamaldeep Singh (Manager Tenders & Project)
Kamaldeep Singh (Manager Tenders & Project)Kamaldeep Singh (Manager Tenders & Project)
Kamaldeep Singh (Manager Tenders & Project)
 

Similar to Chennakesavulu CV tendering format

Road construction report
Road construction reportRoad construction report
Road construction report
mohammad danish anwar
 
Improvement and Asphalting of State Highway and Major District Road of Koppal...
Improvement and Asphalting of State Highway and Major District Road of Koppal...Improvement and Asphalting of State Highway and Major District Road of Koppal...
Improvement and Asphalting of State Highway and Major District Road of Koppal...
IRJET Journal
 
CHVR CV
CHVR CVCHVR CV
PK_Thakore_New_CV
PK_Thakore_New_CVPK_Thakore_New_CV
PK_Thakore_New_CV
pritam thakore
 
Eia mumbai metro
Eia mumbai metroEia mumbai metro
Eia mumbai metro
1392pramod
 
JITENDER CV
JITENDER CVJITENDER CV
JITENDER CV
Jitender Kumar
 
Naresh Cherukuri_CV_May-2016
Naresh Cherukuri_CV_May-2016Naresh Cherukuri_CV_May-2016
Naresh Cherukuri_CV_May-2016
Cherukuri Naresh Chowdary
 
CV SUJINLAL
CV SUJINLALCV SUJINLAL
CV SUJINLAL
Sujin Lal
 
Eia Karachi Thatta Dual Carriageway Project
Eia Karachi Thatta Dual Carriageway ProjectEia Karachi Thatta Dual Carriageway Project
Eia Karachi Thatta Dual Carriageway Project
zubeditufail
 
GM CV-Nov16
GM CV-Nov16 GM CV-Nov16
GM CV-Nov16
Babu Mama
 
Prashant - CV simple format
Prashant - CV  simple formatPrashant - CV  simple format
Prashant - CV simple format
Prashant Gajbhiye
 
Rajkumar cv
Rajkumar cvRajkumar cv
Rajkumar cv
Rajkumar Singh
 
Detailsh.pdf
Detailsh.pdfDetailsh.pdf
Detailsh.pdf
YAGUVALLAVenkat320
 
ProjectReport.pdf
ProjectReport.pdfProjectReport.pdf
ProjectReport.pdf
ParveenMalik26
 
GDRPL Company Profile - .pptx
GDRPL Company Profile - .pptxGDRPL Company Profile - .pptx
GDRPL Company Profile - .pptx
NilayGandhi14
 
vino journal.docx
vino journal.docxvino journal.docx
vino journal.docx
Vinoshri1
 
highway main
highway mainhighway main
highway main
v.d sharma
 
CV_Debajit
CV_DebajitCV_Debajit
CV_Debajit
Debajit Dhar
 
Biswajit Das_Resume
Biswajit Das_ResumeBiswajit Das_Resume
Biswajit Das_Resume
Biswajit 9810983924
 
RETIRED--CV-RESUME OF Self - Copy
RETIRED--CV-RESUME OF Self - CopyRETIRED--CV-RESUME OF Self - Copy
RETIRED--CV-RESUME OF Self - Copy
subodh kumar jain
 

Similar to Chennakesavulu CV tendering format (20)

Road construction report
Road construction reportRoad construction report
Road construction report
 
Improvement and Asphalting of State Highway and Major District Road of Koppal...
Improvement and Asphalting of State Highway and Major District Road of Koppal...Improvement and Asphalting of State Highway and Major District Road of Koppal...
Improvement and Asphalting of State Highway and Major District Road of Koppal...
 
CHVR CV
CHVR CVCHVR CV
CHVR CV
 
PK_Thakore_New_CV
PK_Thakore_New_CVPK_Thakore_New_CV
PK_Thakore_New_CV
 
Eia mumbai metro
Eia mumbai metroEia mumbai metro
Eia mumbai metro
 
JITENDER CV
JITENDER CVJITENDER CV
JITENDER CV
 
Naresh Cherukuri_CV_May-2016
Naresh Cherukuri_CV_May-2016Naresh Cherukuri_CV_May-2016
Naresh Cherukuri_CV_May-2016
 
CV SUJINLAL
CV SUJINLALCV SUJINLAL
CV SUJINLAL
 
Eia Karachi Thatta Dual Carriageway Project
Eia Karachi Thatta Dual Carriageway ProjectEia Karachi Thatta Dual Carriageway Project
Eia Karachi Thatta Dual Carriageway Project
 
GM CV-Nov16
GM CV-Nov16 GM CV-Nov16
GM CV-Nov16
 
Prashant - CV simple format
Prashant - CV  simple formatPrashant - CV  simple format
Prashant - CV simple format
 
Rajkumar cv
Rajkumar cvRajkumar cv
Rajkumar cv
 
Detailsh.pdf
Detailsh.pdfDetailsh.pdf
Detailsh.pdf
 
ProjectReport.pdf
ProjectReport.pdfProjectReport.pdf
ProjectReport.pdf
 
GDRPL Company Profile - .pptx
GDRPL Company Profile - .pptxGDRPL Company Profile - .pptx
GDRPL Company Profile - .pptx
 
vino journal.docx
vino journal.docxvino journal.docx
vino journal.docx
 
highway main
highway mainhighway main
highway main
 
CV_Debajit
CV_DebajitCV_Debajit
CV_Debajit
 
Biswajit Das_Resume
Biswajit Das_ResumeBiswajit Das_Resume
Biswajit Das_Resume
 
RETIRED--CV-RESUME OF Self - Copy
RETIRED--CV-RESUME OF Self - CopyRETIRED--CV-RESUME OF Self - Copy
RETIRED--CV-RESUME OF Self - Copy
 

Chennakesavulu CV tendering format

  • 1. 1/4 CURRICULUM VITAE Name : Kothur Chennakesavulu Profession : Civil Engineer Date of Birth : 20 th May, 1956 Years with Firm / Entity : Available for the assignment Nationality : Indian Membership of : Nil Professional Societies Education : B. Tech. in Civil Engineering from Sree Venkateswara University, Tirupathi in 1979. Other Training: 1. Undergone training programmes conducted by the Department from time to time on various subjects like Quality Assurance, Executive Development programme etc., 2. Continuing Education programme on “HIGHWAY CONSTRUCTION AND MANAGEMENT” conducted by IIT Madras. 3. Attended Workshop on “QUALITY CONTROL ASPECTS FOR HIGHWAY AND BRIDGE PROJECTS” by Indian Roads congress. Awards/Recognition  Best Engineer Award in 15-09-2013 by Institute of Engineers India, Kadapa Training Imparted:  NIL Technical Paper / Published:  IMPROPER CURING Journal of Kurnool District Technical Forum, Vol.6 and No.1 September 2005 Employment Record: June 2011-may 2014, Executive Engineer, Roads & Buildings Dept., Nandyal, Kurnool District, Govt. of Andhra Pradesh  Construction of ROB in lieu of LC No. 183 at Railway Km 258/0-1 of Nandyal Panyam section and km 0/0-6 of Nandyal – Atmakur road in Kurnool District, Lane: double, length: 1.1 km, Cost: 39 Crores  Construction of High level Bridge in Km 75/10 & 76/2 of peapally- Banaganapally-Gajulapally road (NDL) in Kurnool district with estimate cost of rs. 4.00 crores  Construction of High level Bridge in Km 8/2 of Nandyal-Atmakur road in Kurnool district with estimate cost Rs. 2.50 Crores  Construction of HLB at KM 54/2-6 of chgalamarri-Mahadevapuram road in Kurnool district with estimate cost Rs. 3.10 crores.  output and performance based Road contract for the maintenance of package-22 Roads in Kurnool .District of Andhra Pradesh Lane: Double Length: 124 Km, Cost: INR 35.00 Cr.  output and performance based Road contract for the maintenance of package-39 Roads in Kurnool .District of Andhra Pradesh Lane: Double Length: 134 Km, Cost: INR 35.00 Cr.  Widening and strengthening from Km 35/2 to 52/246 of Nandyal-Atmakur Road in Kurnool district, Lane: Double, Length: 15.246 Km, Cost: Rs. 12.00 Crores  Widening and Strengthening from Km 3/0 to 6/0 of Koilakuntla-Allagadda Road in Kurnool district, Lane: Double, Length: 3.00 Km, Cost: Rs. 2.00 Crores
  • 2. 2/4  Widening and Strengthening from Km 3/0 to 6/0 of Koilakuntla-Allagadda Road in Kurnool district, Lane: Double, Length: 6.20 Km, Cost: Rs. 7.65 Crores  Widening and from Km 15/0 to 21/6 & 23/0 to 36/4 of Nandyal-Thimmanayunipeta Road in Kurnool district, Lane: Double, Length: 20.00 Km, Cost: Rs. 20.00 Crores  Widening and Strengthening From Km 29/0 to 25/0 & 41/6 to 47/8 of PBG Road, Lane: Double, Length: 12.00 Km, Cost: Rs. 10.00 Crores  Widening From Km 41/0 to 46/0 Nandyal-Thimmanayunipeta Road, Lane: Double, Length: 5.00 Km, Cost: Rs. 4.00 Crores  Widening and Strengthening From Km 0/0 to 13/509 of Koilakuntla-Banaganapally Road (CRF), Lane: Double, Length: 13.50 Km, Cost: Rs. 14.00 Crores  Under NABARD the rural roads are improved to a length of 18.16 Km with a tune of Rs. 13.00 crores  Under APRDF scheme the rural roads are improved to a length of 14.9 Km with a tune of Rs. 16.8 crores  Under Special repairs programme 65 Km length of the road is improved with a tune of Rs. 22.3 Crores  Under 13 th finance commission the Black top roads are improved to a length of 110 Km with estimate cost of Rs. 16.8 crores As Executive Engineer, was overall responsible for execution/supervision of widening, improvements and heavy periodical maintenance for Roads and Highways and Bridge projects, ROB's, Approval of working drawings, contractors work plan, procedures, Implementation of QC assurance plans and monitoring the processing of work ,cost control and approval of payment certificate etc., Involved in design review and modifications as per site conditions, approval of working drawings, approval of contractor’s work plan, procedures, method statements, plants and equipments, Implementation of Quality Assurance Plans, Interpretation of contractual obligations, contract administration; monitoring progress of works using latest project management techniques and safety measures, traffic management, cost control and approval of Payment certificates; preparing monthly and other project progress reports. Sanctioning of Minor works and special repairs and urgent repairs costing Rs. 10.00 Lakhs and below and further scrutiny of tenders and concluding the agreements. Sept 2006- May 2011; Deputy Executive Engineer; Adoni, Kurnool District of Andhra Pradesh. The following major works were executed in addition to the annual maintenance and special repair works for a length of 330 Kms:  Bypass Road formation to Adoni km 0/0 to 2/1 and Km 5/4 to 10.895 Lane: 2, Length: 7.596 Km, Cost: 9.00 Crores.  Railway Over Bridge For LC no 198 at Railway Km 500/8-9 of Guntakal -wadi section Lane: 2, Length: 1.00 km Cost: 15.00 Crores  Widening & Strengthening Km 93/0 to 126/7 Kurnool - Bellary Road (under CRF) Lane: 2, Length: 5.00 km Cost: 2.00 Crores  Widening & strengthening from Km 3/0 to 26/7 Adoni-siruguppa Road (CRF) with estimate cost of Rs. 2.00 Crores  Under NABARD rural roads are improved to a length of 43.00 Kms with estimate cost of Rs 8.00 crores  Under APRDF the rural roads are strengthened to a length of 7 Km with an estimate cost of Rs. 4.00 Crores  Under 12 th finance commission 6.00 Km are improved with a tune of Rs. 1.50 Crores Supervision of Road maintenance works, Special repair works for a length of 330 km pertaining to R & B Sub division Jurisdiction including NABARD, ROB and PLAN works. As Deputy Executive Engineer, was responsible for geotechnical investigations including pit test, DCP test, field density test, soil testing, field testing and independent testing of construction material, collection of geotechnical data, compilation, analysis, prescribe parameters for design of embankments, bridge foundation, etc., also responsible for assisting in
  • 3. 3/4 drafting Quality assurance program, reconnaissance & Identification of borrow areas and quarries, framing guidelines for testing of soil and other construction materials, analysis, tabulation and interpretation of test results; stipulating conditions for setting up of site laboratories; formulating test procedures and quality control measures to ensure adoption of required standard in all construction activities of the project, pavement investigation, condition surveys, Pavement option study and detailed design of pavement crust as per IRC, ASHTO Specifications. Aug 2003 to Aug 2006; Deputy Executive Engineer, Roads & Buildings Dept., Yemmiganur, Kurnool District, Govt. of Andhra Pradesh  Widening and Strengthening from Km 10/0 to 15/0 of Yemmiganur-Mantralyam Road andkm 0/0 to 14/0 of Tungabhadra RS to Mantralayam, Lane: 2, Length: 19 kms, Cost: 5.00 Crores  Widening and Strengthening of the road Km 84/0 to 101/2 of Guntakal-Tungabhadra Road in Kurnool district with estimate cost of rs. 5.00 crores for a length of 17.2 km  Construction of HLB at Km 9/2 of Thungabadhra RS to Mantralayam in Kurnool district with estimate cost of Rs 1.00 crore  Construction of HLB at Km 4/6 of Yemmiganur- Mantralayam road in Kurnool district with estimate cost of Rs 50.00 Lakhs  Construction of HLB at Km 8/2 of Yemmiganur-Mantralayam road in Kurnool district with estimate cost of Rs. 50.00 Lakhs Supervision of Road maintenance works, Special repair works for a length of 330 km pertaining to R & B Jurisdiction including NABARD, ROB and PLAN works. As Deputy Executive Engineer, was responsible for geotechnical investigations including pit test, DCP test, field density test, soil testing, field testing and independent testing of construction material, collection of geotechnical data, compilation, analysis, prescribe parameters for design of embankments, bridge foundation, etc., also responsible for assisting in drafting Quality assurance program, reconnaissance & Identification of borrow areas and quarries, framing guidelines for testing of soil and other construction materials, analysis, tabulation and interpretation of test results; stipulating conditions for setting up of site laboratories; formulating test procedures and quality control measures to ensure adoption of required standard in all construction activities of the project, pavement investigation, condition surveys, Pavement option study and detailed design of pavement crust as per IRC, ASHTO Specifications. April 2000 to Aug 2003; Assistant Executive Engineer, E-N-C Office, Hyderabad, Govt. of Andhra Pradesh Worked as Assistant Executive Engineer in Roads & buildings, Designs wing in the office of E-N-C, Hyderabad. Involved in scrutiny of estimates and designs and according Administrative approval and Technical sanction of Road and Bridge works costing Rs. 100 Lakhs and above, such as crust design of pavement, fixing of longitudinal and cross sectional profile of new roads to minimize the earthwork component in embankments and cross checking of designs of Bridges and ROBs. May 1997-March 2003; Assistant Executive Engineer on Deputation with Director of Technical Education, Hyderabad World Bank is funded for upgradation of 44 number of Polytechnic Colleges in Andhra Pradesh. For this SPIU (Special Project implimentation unit) unit has been formed in director of technical Education in Hyderabad to monitor with the executive agencies and world bank including reimbursement and QC assurance. July 1993 to April 1997; Assistant Executive Engineer, R&B Section, Tadpatri, anantapur District, Andhra Pradesh The following works are excuted apart from annual mainance and special repair woks  Formation of Bypass Road to Tadpatri town in Anantapur district with estimate cost of Rs. 50.00 Lakhs  Construction of Degree College building at Tadpatri with estimate cost of Rs. 60.00 Lakhs.  Construction of Shaadi Khana at Tadpatri with estimate cost of Rs. 20.00 Lakhs June 1991 - July 1993; Assistant Executive Engineer; Roads & Bilding Dept.,Kadiri,anantapur district Govt. of Andhra Pradesh
  • 4. 4/4  Supervision of Annual Maintenance and Special repair works for a length of 120 Km. As Assistant Executive engineer responsible for Road condition survey, collection of data for Road network improvements and preparation of improvement and new alignment project designing and preparation of feasibility reports. Maintenance of Road infrastructure in Kadiri, Anantapur District of Andhra Pradesh April 1987-May 1991; Assistant Executive Engineer; Roads & Buildings Dept.,Madakasira anatapur distrit. Govt. of Andhra Pradesh  Supervision of Annual Maintenance and Special repair works for a length of 212 Km. May 1986 - March 1987; Assistant Executive Engineer; Roads & Buildings Dept., Tirupati, Chittoor District, Govt. of Andhra Pradesh  Incharge for the Medical College Buildings, annual Maintenance of Buildings and special repair works. Apart from this the following Special assignment projects are executed: 1. Contruction of Leprosy training centre with estimate cost of Rs. 60.00 Lakhs 2. Contruction of Cardiology block with estimate cost of Rs. 40.00 Lakhs June 1984 - May 1986; Assistant Executive Engineer; Roads & Buildings Dept.Pulivendula, Kadapa District, Govt. of Andhra Pradesh  Supervision of Annual Maintenance and Special repair works for a length of 156 Km June 1983- May 1984; Assistant Executive Engineer; Roads & Buildings Dept., Proddatur, Kadapa District, Govt. of Andhra Pradesh The following major works are executed with well foundation on the major River Kundu:  Construction of HLB across Kundu river at Km 165/0 to0/8 of Nellore- Bellary - Bombay Road in Kadapa Lane: 2, Length: 0.80 Km, Cost: 1.00 Crore April 1981- May 1983; Assistant Executive Engineer; Roads & Buildings Dept., Pourumamilla, Kadapa District, Govt. of Andhra Pradesh  Supervision of Annual Maintenance and Special repair works for a length of 120 Km As Assistant Executive engineer responsible for Road condition survey, collection of data for Road network improvements and preparation of improvement and new alignment project designing and preparation of feasibility reports. Maintenance of Road infrastructure in Pourumamilla, Kadapa District of Andhra Pradesh Sept 1979 - March 1981; Assistant Executive Engineer; Roads & Buildings Dept., Guntur, Guntur Disrict, Govt. of Andhra Pradesh  Investigation & Survey work Including Preparation of land plans for Aqusition of Commamded Area development Roads including Design of Bridges, culvers and other Geometrical features and preparation of Detailed Estimate for Administrative sanction Languages Speaking Reading Writing English Excellent Excellent Excellent Telugu Excellent Excellent Excellent