SlideShare a Scribd company logo
6–1
Chapter 6 - Developing a Project Plan
6–2
Developing the Project Plan
• The Project Network
–A flow chart that graphically depicts the sequence,
interdependencies, and start and finish times of the
project job plan of activities that is the critical path
through the network.
• Provides the basis for scheduling labor and equipment.
• Enhances communication among project participants.
• Provides an estimate of the project’s duration.
• Provides a basis for budgeting cash flow.
• Identifies activities that are critical.
• Highlights activities that are “critical” and can not be delayed.
• Help managers get and stay on plan.
6–3
Constructing a Project Network
• Terminology
–Activity: an element of the
project that requires time.
–Merge Activity: an activity that
has two or more preceding
activities on which it depends.
–Parallel (Concurrent) Activities:
Activities that can occur
independently and, if desired,
not at the same time.
A
C
D
B
6–4
Constructing a Project Network (cont’d)
• Terminology
–Path: a sequence of connected, dependent activities.
–Critical path: the longest path through the activity
network that allows for the completion of all project-
related activities; the shortest expected time in which
the entire project can be completed. Delays on the
critical path will delay completion of the entire project.
A B D
(Assumes that minimum of A + B > minimum of C in length of times to complete activities.)
C
6–5
Constructing a Project Network (cont’d)
• Terminology
–Event: a point in time when an activity is started
or completed. It does not consume time.
–Burst Activity: an activity that has more than one
activity immediately following it (more than one
dependency arrow flowing from it).
• Two Approaches
–Activity-on-Node (AON)
• Uses a node to depict an activity.
–Activity-on-Arrow (AOA)
• Uses an arrow to depict an activity.
B
D
A C
6–6
Basic Rules to Follow in Developing
Project Networks
1. Networks typically flow from left to right.
2. An activity cannot begin until all preceding
connected activities are complete.
3. Arrows indicate precedence and flow
and can cross over each other.
4. Each activity must have a unique identify number
that is greater than any of its predecessor activities.
5. Looping is not allowed.
6. Conditional statements are not allowed.
7. Use common start and stop nodes.
6–7
Activity-on-Node Fundamentals
FIGURE 6.2
6–8
Activity-on-Node Fundamentals (cont’d)
FIGURE 6.2 (cont’d)
6–9
Network Information
TABLE 6.1
6–10
Koll Business Center—Partial Network
FIGURE 6.3
6–11
Koll Business Center—Complete Network
FIGURE 6.4
6–12
Network Computation Process
• Forward Pass—Earliest Times
–How soon can the activity start? (early start—ES)
–How soon can the activity finish? (early finish—EF)
–How soon can the project finish? (expected time—ET)
• Backward Pass—Latest Times
–How late can the activity start? (late start—LS)
–How late can the activity finish? (late finish—LF)
–Which activities represent the critical path?
–How long can activity be delayed? (slack or float—SL)
6–13
Network Information
TABLE 6.2
6–14
Activity-on-Node Network
FIGURE 6.5
6–15
Activity-on-Node Network Forward Pass
FIGURE 6.6
6–16
Forward Pass Computation
• Add activity times along each path in the
network (ES + Duration = EF).
• Carry the early finish (EF) to the next activity
where it becomes its early start (ES) unless…
• The next succeeding activity is a merge activity,
in which case the largest EF of all preceding
activities is selected.
6–17
Activity-on-Node Network Backward Pass
FIGURE 6.7
6–18
Backward Pass Computation
• Subtract activity times along each path in the
network (LF - Duration = LS).
• Carry the late start (LS) to the next activity
where it becomes its late finish (LF) unless
• The next succeeding activity is a burst activity, in
which case the smallest LF of all preceding
activities is selected.
6–19
Determining Free Slack (or Float)
• Free Slack (or Float)
–Is the amount of time an activity can be delayed after
the start of a longer parallel activity or activities.
–Is how long an activity can exceed its early finish date
without affecting early start dates of any successor(s).
–Allows flexibility in scheduling scarce resources.
• Sensitivity
–The likelihood the original critical path(s) will change
once the project is initiated.
–The critical path is the network path(s) that has (have)
the least slack in common.
6–20
Activity-on-Node Network with Slack
FIGURE 6.8
6–21
Free Slack Example
FIGURE 6.9
6–22
Illogical Loop
FIGURE 6.10
6–23
Extended Network Techniques
to Come Close to Reality
• Laddering
–Activities are broken into segments so the following
activity can begin sooner and not delay the work.
6–24
Example of Laddering Using
Finish-to-Start Relationship
FIGURE 6.13
6–25
Activity-on-Arrow Network Building Blocks
FIGURE A6.1
6–26
Activity-on-Arrow Network Fundamentals
FIGURE A6.2

More Related Content

What's hot

Critical path method(cpm)
Critical path method(cpm)Critical path method(cpm)
Critical path method(cpm)
chandkec
 
Project management
Project managementProject management
Project management
Satish Yadavalli
 
Chap 4 Defining A Project
Chap 4 Defining A ProjectChap 4 Defining A Project
Chap 4 Defining A Project
project management
 
Project Management PPT
Project Management PPTProject Management PPT
Project Management PPTbletindia
 
Effective project management skills
Effective project management skillsEffective project management skills
Effective project management skills
Charles Cotter, PhD
 
Project Management The Managerial Process 5th Edition Larson Solutions Manual
Project Management The Managerial Process 5th Edition Larson Solutions ManualProject Management The Managerial Process 5th Edition Larson Solutions Manual
Project Management The Managerial Process 5th Edition Larson Solutions Manual
Kemppe
 
(AOA) and (AON) Network construction and critical path calculations (using fo...
(AOA) and (AON) Network construction and critical path calculations (using fo...(AOA) and (AON) Network construction and critical path calculations (using fo...
(AOA) and (AON) Network construction and critical path calculations (using fo...
Dr. Mahmoud Al-Naimi
 
Termination.project management
Termination.project managementTermination.project management
Termination.project management
Marius Miron
 
Project planning
Project planning Project planning
Project planning
Dipnarayan Thakur
 
Critical Path Analysis
Critical Path AnalysisCritical Path Analysis
Critical Path Analysis
North Warwickshie & Hinckley college
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan Development
Glen Alleman
 
WBS and OBS
WBS and OBSWBS and OBS
WBS and OBS
MuzammalMatyana
 
What is forward and backward scheduling
What is forward and backward schedulingWhat is forward and backward scheduling
What is forward and backward schedulingNaresh Gupta
 
Chap008
Chap008Chap008
8.project management chapter 8
8.project management chapter 88.project management chapter 8
8.project management chapter 8
Warui Maina
 
Tools and Techniques for Project Management
Tools and Techniques for Project Management Tools and Techniques for Project Management
Tools and Techniques for Project Management
Teresa Lawrence, Ph.D., PMP
 
Practical Project Management - full course
Practical Project Management - full coursePractical Project Management - full course
Practical Project Management - full course
Marten Schoonman
 
Chap 1 Modern Project Management
Chap 1 Modern Project ManagementChap 1 Modern Project Management
Chap 1 Modern Project Management
project management
 

What's hot (20)

Critical path method(cpm)
Critical path method(cpm)Critical path method(cpm)
Critical path method(cpm)
 
Project management
Project managementProject management
Project management
 
Chap 4 Defining A Project
Chap 4 Defining A ProjectChap 4 Defining A Project
Chap 4 Defining A Project
 
Project Management PPT
Project Management PPTProject Management PPT
Project Management PPT
 
Effective project management skills
Effective project management skillsEffective project management skills
Effective project management skills
 
Project Management The Managerial Process 5th Edition Larson Solutions Manual
Project Management The Managerial Process 5th Edition Larson Solutions ManualProject Management The Managerial Process 5th Edition Larson Solutions Manual
Project Management The Managerial Process 5th Edition Larson Solutions Manual
 
(AOA) and (AON) Network construction and critical path calculations (using fo...
(AOA) and (AON) Network construction and critical path calculations (using fo...(AOA) and (AON) Network construction and critical path calculations (using fo...
(AOA) and (AON) Network construction and critical path calculations (using fo...
 
Termination.project management
Termination.project managementTermination.project management
Termination.project management
 
Project planning
Project planning Project planning
Project planning
 
Pert & Cpm
Pert & CpmPert & Cpm
Pert & Cpm
 
Critical Path Analysis
Critical Path AnalysisCritical Path Analysis
Critical Path Analysis
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan Development
 
WBS and OBS
WBS and OBSWBS and OBS
WBS and OBS
 
What is forward and backward scheduling
What is forward and backward schedulingWhat is forward and backward scheduling
What is forward and backward scheduling
 
Work Breakdown Structure
Work Breakdown StructureWork Breakdown Structure
Work Breakdown Structure
 
Chap008
Chap008Chap008
Chap008
 
8.project management chapter 8
8.project management chapter 88.project management chapter 8
8.project management chapter 8
 
Tools and Techniques for Project Management
Tools and Techniques for Project Management Tools and Techniques for Project Management
Tools and Techniques for Project Management
 
Practical Project Management - full course
Practical Project Management - full coursePractical Project Management - full course
Practical Project Management - full course
 
Chap 1 Modern Project Management
Chap 1 Modern Project ManagementChap 1 Modern Project Management
Chap 1 Modern Project Management
 

Similar to Chapter 6 - Developing a Project Plan.pdf

PM Session 5
PM Session 5PM Session 5
PM Session 5
dmdk12
 
Session 9 - Project scheduling-PERT-CPM-Network diagram.pptx
Session 9 - Project scheduling-PERT-CPM-Network diagram.pptxSession 9 - Project scheduling-PERT-CPM-Network diagram.pptx
Session 9 - Project scheduling-PERT-CPM-Network diagram.pptx
AlRashedinKawser2
 
Focus on CPM and Resp Matrix
Focus on CPM and Resp MatrixFocus on CPM and Resp Matrix
Focus on CPM and Resp Matrix
dmdk12
 
6. Developing Project Plan.pptx
6. Developing Project Plan.pptx6. Developing Project Plan.pptx
6. Developing Project Plan.pptx
AbdulKhaliqueSolangi1
 
CHAPTER 6.pptx
CHAPTER 6.pptxCHAPTER 6.pptx
CHAPTER 6.pptx
KristleJoyDimayuga
 
Lec 09 network scheduling_techniques
Lec 09 network scheduling_techniquesLec 09 network scheduling_techniques
Lec 09 network scheduling_techniques
SAJID ALI RUK
 
08. Project Time Management Upload
08. Project Time Management Upload08. Project Time Management Upload
08. Project Time Management Upload
BhuWan Khadka
 
02-Key Definitions .pdf
02-Key Definitions .pdf02-Key Definitions .pdf
02-Key Definitions .pdf
abdelazizfarag1
 
ch08 (1).pptttttttttttttttþtttttttttttttt
ch08 (1).pptttttttttttttttþttttttttttttttch08 (1).pptttttttttttttttþtttttttttttttt
ch08 (1).pptttttttttttttttþtttttttttttttt
AbdisalamMohamud5
 
module-1 CME NETWORK ANALYSIS.pptx
module-1 CME NETWORK ANALYSIS.pptxmodule-1 CME NETWORK ANALYSIS.pptx
module-1 CME NETWORK ANALYSIS.pptx
surekha1287
 
PMP Project Management Basics Tutorial For Beginners
PMP Project Management Basics Tutorial For BeginnersPMP Project Management Basics Tutorial For Beginners
PMP Project Management Basics Tutorial For Beginners
IIMSE Edu
 
Project Management.pptx
Project Management.pptxProject Management.pptx
Project Management.pptx
NaimishKishor
 
المحاضرة السادسة: إعداد جدول المشروع
المحاضرة السادسة: إعداد جدول المشروعالمحاضرة السادسة: إعداد جدول المشروع
المحاضرة السادسة: إعداد جدول المشروع
Egypt Scholars Inc.
 
Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)Debanjan15
 
L2_Project_Management.pdf
L2_Project_Management.pdfL2_Project_Management.pdf
L2_Project_Management.pdf
JerryHung19
 
Pertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOLPertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOL
Siddanna Balapgol
 
Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02
kongara
 
12 lecture project scheduling 4
12 lecture project scheduling 412 lecture project scheduling 4
12 lecture project scheduling 4Ahmad Basim Hamza
 
Qabd 13
Qabd 13Qabd 13

Similar to Chapter 6 - Developing a Project Plan.pdf (20)

PM Session 5
PM Session 5PM Session 5
PM Session 5
 
Session 9 - Project scheduling-PERT-CPM-Network diagram.pptx
Session 9 - Project scheduling-PERT-CPM-Network diagram.pptxSession 9 - Project scheduling-PERT-CPM-Network diagram.pptx
Session 9 - Project scheduling-PERT-CPM-Network diagram.pptx
 
Focus on CPM and Resp Matrix
Focus on CPM and Resp MatrixFocus on CPM and Resp Matrix
Focus on CPM and Resp Matrix
 
6. Developing Project Plan.pptx
6. Developing Project Plan.pptx6. Developing Project Plan.pptx
6. Developing Project Plan.pptx
 
CHAPTER 6.pptx
CHAPTER 6.pptxCHAPTER 6.pptx
CHAPTER 6.pptx
 
Lec 09 network scheduling_techniques
Lec 09 network scheduling_techniquesLec 09 network scheduling_techniques
Lec 09 network scheduling_techniques
 
08. Project Time Management Upload
08. Project Time Management Upload08. Project Time Management Upload
08. Project Time Management Upload
 
Ch 5.pptx
Ch 5.pptxCh 5.pptx
Ch 5.pptx
 
02-Key Definitions .pdf
02-Key Definitions .pdf02-Key Definitions .pdf
02-Key Definitions .pdf
 
ch08 (1).pptttttttttttttttþtttttttttttttt
ch08 (1).pptttttttttttttttþttttttttttttttch08 (1).pptttttttttttttttþtttttttttttttt
ch08 (1).pptttttttttttttttþtttttttttttttt
 
module-1 CME NETWORK ANALYSIS.pptx
module-1 CME NETWORK ANALYSIS.pptxmodule-1 CME NETWORK ANALYSIS.pptx
module-1 CME NETWORK ANALYSIS.pptx
 
PMP Project Management Basics Tutorial For Beginners
PMP Project Management Basics Tutorial For BeginnersPMP Project Management Basics Tutorial For Beginners
PMP Project Management Basics Tutorial For Beginners
 
Project Management.pptx
Project Management.pptxProject Management.pptx
Project Management.pptx
 
المحاضرة السادسة: إعداد جدول المشروع
المحاضرة السادسة: إعداد جدول المشروعالمحاضرة السادسة: إعداد جدول المشروع
المحاضرة السادسة: إعداد جدول المشروع
 
Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)
 
L2_Project_Management.pdf
L2_Project_Management.pdfL2_Project_Management.pdf
L2_Project_Management.pdf
 
Pertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOLPertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOL
 
Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02
 
12 lecture project scheduling 4
12 lecture project scheduling 412 lecture project scheduling 4
12 lecture project scheduling 4
 
Qabd 13
Qabd 13Qabd 13
Qabd 13
 

Recently uploaded

What is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdfWhat is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdf
seoforlegalpillers
 
Exploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social DreamingExploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social Dreaming
Nicola Wreford-Howard
 
Kseniya Leshchenko: Shared development support service model as the way to ma...
Kseniya Leshchenko: Shared development support service model as the way to ma...Kseniya Leshchenko: Shared development support service model as the way to ma...
Kseniya Leshchenko: Shared development support service model as the way to ma...
Lviv Startup Club
 
Premium MEAN Stack Development Solutions for Modern Businesses
Premium MEAN Stack Development Solutions for Modern BusinessesPremium MEAN Stack Development Solutions for Modern Businesses
Premium MEAN Stack Development Solutions for Modern Businesses
SynapseIndia
 
Memorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.pptMemorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.ppt
seri bangash
 
Business Valuation Principles for Entrepreneurs
Business Valuation Principles for EntrepreneursBusiness Valuation Principles for Entrepreneurs
Business Valuation Principles for Entrepreneurs
Ben Wann
 
VAT Registration Outlined In UAE: Benefits and Requirements
VAT Registration Outlined In UAE: Benefits and RequirementsVAT Registration Outlined In UAE: Benefits and Requirements
VAT Registration Outlined In UAE: Benefits and Requirements
uae taxgpt
 
Buy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star ReviewsBuy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star Reviews
usawebmarket
 
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdfMeas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
dylandmeas
 
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
BBPMedia1
 
FINAL PRESENTATION.pptx12143241324134134
FINAL PRESENTATION.pptx12143241324134134FINAL PRESENTATION.pptx12143241324134134
FINAL PRESENTATION.pptx12143241324134134
LR1709MUSIC
 
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBdCree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
creerey
 
Discover the innovative and creative projects that highlight my journey throu...
Discover the innovative and creative projects that highlight my journey throu...Discover the innovative and creative projects that highlight my journey throu...
Discover the innovative and creative projects that highlight my journey throu...
dylandmeas
 
BeMetals Presentation_May_22_2024 .pdf
BeMetals Presentation_May_22_2024   .pdfBeMetals Presentation_May_22_2024   .pdf
BeMetals Presentation_May_22_2024 .pdf
DerekIwanaka1
 
Enterprise Excellence is Inclusive Excellence.pdf
Enterprise Excellence is Inclusive Excellence.pdfEnterprise Excellence is Inclusive Excellence.pdf
Enterprise Excellence is Inclusive Excellence.pdf
KaiNexus
 
Tata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s Dholera
Tata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s DholeraTata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s Dholera
Tata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s Dholera
Avirahi City Dholera
 
Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)
Lviv Startup Club
 
Cracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptxCracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptx
Workforce Group
 
Skye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto AirportSkye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto Airport
marketingjdass
 
The-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic managementThe-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic management
Bojamma2
 

Recently uploaded (20)

What is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdfWhat is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdf
 
Exploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social DreamingExploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social Dreaming
 
Kseniya Leshchenko: Shared development support service model as the way to ma...
Kseniya Leshchenko: Shared development support service model as the way to ma...Kseniya Leshchenko: Shared development support service model as the way to ma...
Kseniya Leshchenko: Shared development support service model as the way to ma...
 
Premium MEAN Stack Development Solutions for Modern Businesses
Premium MEAN Stack Development Solutions for Modern BusinessesPremium MEAN Stack Development Solutions for Modern Businesses
Premium MEAN Stack Development Solutions for Modern Businesses
 
Memorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.pptMemorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.ppt
 
Business Valuation Principles for Entrepreneurs
Business Valuation Principles for EntrepreneursBusiness Valuation Principles for Entrepreneurs
Business Valuation Principles for Entrepreneurs
 
VAT Registration Outlined In UAE: Benefits and Requirements
VAT Registration Outlined In UAE: Benefits and RequirementsVAT Registration Outlined In UAE: Benefits and Requirements
VAT Registration Outlined In UAE: Benefits and Requirements
 
Buy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star ReviewsBuy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star Reviews
 
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdfMeas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
 
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
 
FINAL PRESENTATION.pptx12143241324134134
FINAL PRESENTATION.pptx12143241324134134FINAL PRESENTATION.pptx12143241324134134
FINAL PRESENTATION.pptx12143241324134134
 
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBdCree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
 
Discover the innovative and creative projects that highlight my journey throu...
Discover the innovative and creative projects that highlight my journey throu...Discover the innovative and creative projects that highlight my journey throu...
Discover the innovative and creative projects that highlight my journey throu...
 
BeMetals Presentation_May_22_2024 .pdf
BeMetals Presentation_May_22_2024   .pdfBeMetals Presentation_May_22_2024   .pdf
BeMetals Presentation_May_22_2024 .pdf
 
Enterprise Excellence is Inclusive Excellence.pdf
Enterprise Excellence is Inclusive Excellence.pdfEnterprise Excellence is Inclusive Excellence.pdf
Enterprise Excellence is Inclusive Excellence.pdf
 
Tata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s Dholera
Tata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s DholeraTata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s Dholera
Tata Group Dials Taiwan for Its Chipmaking Ambition in Gujarat’s Dholera
 
Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)Maksym Vyshnivetskyi: PMO Quality Management (UA)
Maksym Vyshnivetskyi: PMO Quality Management (UA)
 
Cracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptxCracking the Workplace Discipline Code Main.pptx
Cracking the Workplace Discipline Code Main.pptx
 
Skye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto AirportSkye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto Airport
 
The-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic managementThe-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic management
 

Chapter 6 - Developing a Project Plan.pdf

  • 1. 6–1 Chapter 6 - Developing a Project Plan
  • 2. 6–2 Developing the Project Plan • The Project Network –A flow chart that graphically depicts the sequence, interdependencies, and start and finish times of the project job plan of activities that is the critical path through the network. • Provides the basis for scheduling labor and equipment. • Enhances communication among project participants. • Provides an estimate of the project’s duration. • Provides a basis for budgeting cash flow. • Identifies activities that are critical. • Highlights activities that are “critical” and can not be delayed. • Help managers get and stay on plan.
  • 3. 6–3 Constructing a Project Network • Terminology –Activity: an element of the project that requires time. –Merge Activity: an activity that has two or more preceding activities on which it depends. –Parallel (Concurrent) Activities: Activities that can occur independently and, if desired, not at the same time. A C D B
  • 4. 6–4 Constructing a Project Network (cont’d) • Terminology –Path: a sequence of connected, dependent activities. –Critical path: the longest path through the activity network that allows for the completion of all project- related activities; the shortest expected time in which the entire project can be completed. Delays on the critical path will delay completion of the entire project. A B D (Assumes that minimum of A + B > minimum of C in length of times to complete activities.) C
  • 5. 6–5 Constructing a Project Network (cont’d) • Terminology –Event: a point in time when an activity is started or completed. It does not consume time. –Burst Activity: an activity that has more than one activity immediately following it (more than one dependency arrow flowing from it). • Two Approaches –Activity-on-Node (AON) • Uses a node to depict an activity. –Activity-on-Arrow (AOA) • Uses an arrow to depict an activity. B D A C
  • 6. 6–6 Basic Rules to Follow in Developing Project Networks 1. Networks typically flow from left to right. 2. An activity cannot begin until all preceding connected activities are complete. 3. Arrows indicate precedence and flow and can cross over each other. 4. Each activity must have a unique identify number that is greater than any of its predecessor activities. 5. Looping is not allowed. 6. Conditional statements are not allowed. 7. Use common start and stop nodes.
  • 12. 6–12 Network Computation Process • Forward Pass—Earliest Times –How soon can the activity start? (early start—ES) –How soon can the activity finish? (early finish—EF) –How soon can the project finish? (expected time—ET) • Backward Pass—Latest Times –How late can the activity start? (late start—LS) –How late can the activity finish? (late finish—LF) –Which activities represent the critical path? –How long can activity be delayed? (slack or float—SL)
  • 16. 6–16 Forward Pass Computation • Add activity times along each path in the network (ES + Duration = EF). • Carry the early finish (EF) to the next activity where it becomes its early start (ES) unless… • The next succeeding activity is a merge activity, in which case the largest EF of all preceding activities is selected.
  • 18. 6–18 Backward Pass Computation • Subtract activity times along each path in the network (LF - Duration = LS). • Carry the late start (LS) to the next activity where it becomes its late finish (LF) unless • The next succeeding activity is a burst activity, in which case the smallest LF of all preceding activities is selected.
  • 19. 6–19 Determining Free Slack (or Float) • Free Slack (or Float) –Is the amount of time an activity can be delayed after the start of a longer parallel activity or activities. –Is how long an activity can exceed its early finish date without affecting early start dates of any successor(s). –Allows flexibility in scheduling scarce resources. • Sensitivity –The likelihood the original critical path(s) will change once the project is initiated. –The critical path is the network path(s) that has (have) the least slack in common.
  • 23. 6–23 Extended Network Techniques to Come Close to Reality • Laddering –Activities are broken into segments so the following activity can begin sooner and not delay the work.
  • 24. 6–24 Example of Laddering Using Finish-to-Start Relationship FIGURE 6.13