SlideShare a Scribd company logo
1 of 33
Dispute and Dispute
Resolution Mechanisms
Mada Walabu
University
Construction Law
CoTM 4241
Chapter 4
College of Engineering
Construction Technology and Management Department
Instructor: Andualem Endris (M.Sc)
E-mail: andu0117@yahoo.com
What is Dispute?
CoTM 4241 2
31 July 2021
Disputes
• Dispute is a disagreement between parties
• Construction projects are generally complex, for
this reason, disputes are always present
• Involves many parties.
• When a project ends up in a dispute, the project
will fail to meet its original goals and
expectation.
CoTM 4241 3
31 July 2021
Disputes
• Clients will suffer from high legal fees, delayed
completion and occupation and general dissatisfaction.
• The contractor’s profits will diminish and to these will be
added additional legal fees.
• No winners under these circumstances
CoTM 4241 4
31 July 2021
Causes of Disputes
CoTM 4241 5
31 July 2021
Causes of Disputes
• May arise on a construction project for a number
of reasons:
 Late or non-payment for works satisfactorily
completed when payment is due.
 Inaccurate valuation of variations and works in
progress.
 Delays in the supply of general construction
information
CoTM 4241 6
31 July 2021
Causes of Disputes …Cont’d
 Late issue of instruction varying some sections of the
works, which disrupts the contractor’s progress and
program of works.
 Shortcomings, omissions and errors in contract
documentation giving rise to ambiguities in contract
requirements.
 Failure of contractor to construct the works diligently and
to program.
CoTM 4241 7
31 July 2021
Causes of Disputes …Cont’d
 Increase in scope of work (changes, extras and errors)
without proper consideration for extension of production
time.
 Acceleration to complete within original program without
proper agreement over the payment.
 Poor workmanship and failure to use specified materials,
skilled operatives and recognized methods.
 Failure to inspect works in progress regularly and
condemning only when works are completed.
CoTM 4241 8
31 July 2021
Causes of Disputes …Cont’d
• It can be deduced from the above list that the main areas
of construction disputes revolve around:
payments
contract documentation
Time and cost overruns
Construction information and site supervision
• Owing to their diverse status, the view points of the
project participants towards disputes areas vary.
CoTM 4241 9
31 July 2021
Alternative Dispute Resolution
Mechanisms (ADR)
CoTM 4241 10
31 July 2021
Dispute Resolution Mechanisms
• An introductory survey of the construction
industry’s commonly used dispute resolution
mechanisms.
• Negotiation
• Mediation
• Conciliation
• Dispute Review Boards
• Arbitration
• Litigation
11
CoTM 4241
31 July 2021
Negotiation
• Dispute resolution between the parties involving
only the parties
• Informal
– Conversations, emails, texts, phone calls
• Formal
– Meetings, documentation, presentations
• Resolution
– Regardless of how you got there:
Put it in writing
12
CoTM 4241
31 July 2021
Elevating the Negotiation
• Can’t settle at the jobsite level?
• Push the dispute “upstairs”
• Again, only the parties are involved
• May be multiple meetings
• Resolution must be written
13
CoTM 4241
31 July 2021
Mediation
• Mediation: Bringing in a respected, neutral,
uninvolved person to help everyone reach a
mutually acceptable resolution
– The mediator DOES NOT decide
– Mediation may not resolve a dispute
• Key Points
– Voluntary
– The resolution is binding, but the process is not
– You set the rules
14
CoTM 4241
31 July 2021
Mediation
• The Parties must agree to mediate
• The Parties must select a mediator
• The Contract may define mediation terms,
procedures, maybe even the mediator
• Select a mediator with whom you are
comfortable and who you believe will also be
credible with the other parties
• The mediator proposes several possible
solutions to the dispute.
15
CoTM 4241
31 July 2021
Mediation – The Process
• Parties provide the Mediator with information to
understand the dispute
• The Mediator chooses to meet individually with the
parties, or to call all parties together in a “joint
session”
• After a sufficient exchange of information, the
Mediator breaks the parties apart and begins shuttle
diplomacy
• The Mediator works for you – make the Mediator
work, not just shuffle back and forth
16
CoTM 4241
31 July 2021
Mediation – The Resolution
• Mediators DO NOT Decide
– The Parties decide
• The Mediator’s Proposal
– Not always offered
– May be requested
– NOT binding until all parties
accept
– The process is still voluntary
17
CoTM 4241
31 July 2021
Conciliation
31 July 2021 CoTM 4241 18
• Conciliation is a voluntary proceeding
• It requires that the parties be subject to a third
person (neutral or conciliator).
• The aim is to assist with legal or technical
aspects in the matter, in order to reach a
satisfactory arrangement.
• This practice is referred to as ‘reconciling’ the
parties in an attempt to find a common
agreement.
Dispute Review Boards
• A contractually defined process
• 3 members – all are neutral:
– Contractor nominated, Owner nominated
– Those two appoint the 3rd neutral
• Typically defined in the contract
– But can be established any time the parties agree to
do so
• Regular site visits
• Conducts hearings
19
CoTM 4241
31 July 2021
Dispute Review Board Hearings
• Frequently “no attorneys”
• Parties explain their case to the DRB
• Exhibits, Calculations, Presentations
• DRB hears and receives the information
20
CoTM 4241
31 July 2021
Dispute Review Board Decisions
• Check your contract – terms vary
• Typically non-binding but admissible
• Probably the best independent evaluation
you’ll ever get for your problem
21
CoTM 4241
31 July 2021
Arbitration
• Arbitration is the submission of a dispute to one or more
impartial persons for a final and binding decision, known
as an "award."
• Awards are made in writing and are generally final and
binding on the parties in the case.
• Many times contract defined
• Always an option if all parties agree.
• Variety of associations provide, arbitration services.
22
CoTM 4241
31 July 2021
Arbitrator Selection
• Big Benefit: You “choose” your Judge
• Must be confirmed independent and unrelated
• Look for folks who will understand your situation,
but without bringing too much bias and pre-
conceived resolutions
• Consider the expediency of a single arbitrator
versus the combined wisdom of a three-party
panel
23
CoTM 4241
31 July 2021
The Hearings
• NO Ex Parte communications
• Arbitrator sets schedule
• Proceedings are formalized through rules
• Evidence is presented through sworn testimony
• Arbitrator may question the witnesses and the
attorneys
• Arbitrator sets, with party input, closing briefs,
submission timelines, and form of decision
24
CoTM 4241
31 July 2021
The Decision
• The Final Decision is Final
• There are very few accepted ways to overturn a
Decision:
– The Arbitrator failed to hear evidence
– The Arbitrator was on the take, misbehavior
– The Arbitrator exceeded the powers granted to the
Arbitrator
• Other than winning an appeal using one or more of
those conditions – you are stuck with the Decision.
25
CoTM 4241
31 July 2021
Litigation
• May be a Federal or State Agency Court
– For example: Board of Contract Appeals,
• In a courtroom, you get to choose
– Judge: “Bench Trial”
• Yesterday, the Judge sentenced a rapist to life, today, the Judge
is hearing you argue about money and time
– Jury: Your “Peers”
• Check that jury pool – do any of them really understand the
nuances of a construction project?
26
CoTM 4241
31 July 2021
Litigation
• Getting There
– Many times contract defined
– Any party can initiate: “I’m gonna sue you!”
• Adjudicator Selection
– The Judge is assigned
– You may be able to choose a jury
• Hearings
– Strict rules of evidence
– The Court’s schedule – your schedule just doesn’t
matter.
27
CoTM 4241
31 July 2021
Litigation - Process
• Tedious
• Discovery – produce Everything
• Motions, Legal Positioning
• Pre-Trial Hearings
• Finally, the Hearing itself
28
CoTM 4241
31 July 2021
Litigation - Frustration
• Cancel your vacation, you’re scheduled to be in
Court
• But the Court will delay, as you are “trailing”
• When you do arrive, plan on lots of vacant times
• Remember the money you are paying your team
to be there.
29
CoTM 4241
31 July 2021
Litigation – The Decision
• Likely one party won’t like the Decision
• That party will then file for appeal
– Frequently used to encourage the “winner” to accept
an immediate but smaller resolution
• After years in Trial Court, now years of Appeals
– And you may be sent back for a new trial
30
CoTM 4241
31 July 2021
Litigation Closure
I’m just so glad,
I won…
31
CoTM 4241
31 July 2021
Assignment 2
31 July 2021 CoTM 4241 32
• Briefly discuss the difference between
‘Conciliation’ and ‘Mediation’
• Differentiate between ‘Judge, and
‘Jury’.
Submission Date: January 09, 2020
33
CoTM 4241
31 July 2021
Thank You!

More Related Content

What's hot

SWOT ANALYSIS OF ARBITRATION AWARDS IN INDIAN CONSTRUCTION CONTRACTS
SWOT ANALYSIS OF ARBITRATION AWARDS IN INDIAN CONSTRUCTION CONTRACTSSWOT ANALYSIS OF ARBITRATION AWARDS IN INDIAN CONSTRUCTION CONTRACTS
SWOT ANALYSIS OF ARBITRATION AWARDS IN INDIAN CONSTRUCTION CONTRACTSIAEME Publication
 
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...Rae Davies
 
CFW NEC Management of change under the NEC3
CFW NEC  Management of change under the NEC3 CFW NEC  Management of change under the NEC3
CFW NEC Management of change under the NEC3 Rae Davies
 
Managing Risks and Changes under NEC4
Managing Risks and Changes under NEC4Managing Risks and Changes under NEC4
Managing Risks and Changes under NEC4Sarah Fox
 
"Types and Causes of Construction Claims"
"Types and Causes of Construction Claims""Types and Causes of Construction Claims"
"Types and Causes of Construction Claims"Abhishek Shah
 
"Ranking of Causes of Disputes and Use of Dispute Resolution Methods for Cons...
"Ranking of Causes of Disputes and Use of Dispute Resolution Methods for Cons..."Ranking of Causes of Disputes and Use of Dispute Resolution Methods for Cons...
"Ranking of Causes of Disputes and Use of Dispute Resolution Methods for Cons...Abhishek Shah
 
CONSTRUCTION DISPUTES IN CONSTRUCTION WORK SITES AND THEIR PROBABLE SOLUTIONS
CONSTRUCTION DISPUTES IN CONSTRUCTION WORK SITES AND THEIR PROBABLE SOLUTIONSCONSTRUCTION DISPUTES IN CONSTRUCTION WORK SITES AND THEIR PROBABLE SOLUTIONS
CONSTRUCTION DISPUTES IN CONSTRUCTION WORK SITES AND THEIR PROBABLE SOLUTIONSIAEME Publication
 
Assignment - FIDIC Contract
Assignment - FIDIC ContractAssignment - FIDIC Contract
Assignment - FIDIC ContractKai Yun Pang
 
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...Rae Davies
 
Design & Build contracts - key points for a main contractor with technology a...
Design & Build contracts - key points for a main contractor with technology a...Design & Build contracts - key points for a main contractor with technology a...
Design & Build contracts - key points for a main contractor with technology a...Bhalindra Bath - projects & M&A law
 
Issues In Dispute Resolution Procedures and Practice
Issues In Dispute Resolution Procedures and PracticeIssues In Dispute Resolution Procedures and Practice
Issues In Dispute Resolution Procedures and PracticePalecek & Palecek, PLLC
 
NEC4 overview: key changes and impacts - Birmingham, September 2017
NEC4 overview: key changes and impacts - Birmingham, September 2017NEC4 overview: key changes and impacts - Birmingham, September 2017
NEC4 overview: key changes and impacts - Birmingham, September 2017Browne Jacobson LLP
 
07 cl-assignment-syafiq-qy-macy-huiyong-deric
07 cl-assignment-syafiq-qy-macy-huiyong-deric07 cl-assignment-syafiq-qy-macy-huiyong-deric
07 cl-assignment-syafiq-qy-macy-huiyong-dericSyafiq Zariful
 

What's hot (20)

SWOT ANALYSIS OF ARBITRATION AWARDS IN INDIAN CONSTRUCTION CONTRACTS
SWOT ANALYSIS OF ARBITRATION AWARDS IN INDIAN CONSTRUCTION CONTRACTSSWOT ANALYSIS OF ARBITRATION AWARDS IN INDIAN CONSTRUCTION CONTRACTS
SWOT ANALYSIS OF ARBITRATION AWARDS IN INDIAN CONSTRUCTION CONTRACTS
 
Construction contract
Construction contractConstruction contract
Construction contract
 
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
 
CFW NEC Management of change under the NEC3
CFW NEC  Management of change under the NEC3 CFW NEC  Management of change under the NEC3
CFW NEC Management of change under the NEC3
 
Chapter 2 [compatibility mode]
Chapter 2 [compatibility mode]Chapter 2 [compatibility mode]
Chapter 2 [compatibility mode]
 
Managing Risks and Changes under NEC4
Managing Risks and Changes under NEC4Managing Risks and Changes under NEC4
Managing Risks and Changes under NEC4
 
"Types and Causes of Construction Claims"
"Types and Causes of Construction Claims""Types and Causes of Construction Claims"
"Types and Causes of Construction Claims"
 
"Ranking of Causes of Disputes and Use of Dispute Resolution Methods for Cons...
"Ranking of Causes of Disputes and Use of Dispute Resolution Methods for Cons..."Ranking of Causes of Disputes and Use of Dispute Resolution Methods for Cons...
"Ranking of Causes of Disputes and Use of Dispute Resolution Methods for Cons...
 
CONSTRUCTION DISPUTES IN CONSTRUCTION WORK SITES AND THEIR PROBABLE SOLUTIONS
CONSTRUCTION DISPUTES IN CONSTRUCTION WORK SITES AND THEIR PROBABLE SOLUTIONSCONSTRUCTION DISPUTES IN CONSTRUCTION WORK SITES AND THEIR PROBABLE SOLUTIONS
CONSTRUCTION DISPUTES IN CONSTRUCTION WORK SITES AND THEIR PROBABLE SOLUTIONS
 
Assignment - FIDIC Contract
Assignment - FIDIC ContractAssignment - FIDIC Contract
Assignment - FIDIC Contract
 
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...
 
Fidic
FidicFidic
Fidic
 
FIDIC intro author eng. mohammed fadlalla
FIDIC intro  author eng. mohammed fadlallaFIDIC intro  author eng. mohammed fadlalla
FIDIC intro author eng. mohammed fadlalla
 
NEC Contracts - Programmes under ECC and PSC webinar
NEC Contracts - Programmes under ECC and PSC webinarNEC Contracts - Programmes under ECC and PSC webinar
NEC Contracts - Programmes under ECC and PSC webinar
 
Fidic Form of Contract.
Fidic Form of Contract.Fidic Form of Contract.
Fidic Form of Contract.
 
NEC3 to NE4 webinar
NEC3 to NE4 webinarNEC3 to NE4 webinar
NEC3 to NE4 webinar
 
Design & Build contracts - key points for a main contractor with technology a...
Design & Build contracts - key points for a main contractor with technology a...Design & Build contracts - key points for a main contractor with technology a...
Design & Build contracts - key points for a main contractor with technology a...
 
Issues In Dispute Resolution Procedures and Practice
Issues In Dispute Resolution Procedures and PracticeIssues In Dispute Resolution Procedures and Practice
Issues In Dispute Resolution Procedures and Practice
 
NEC4 overview: key changes and impacts - Birmingham, September 2017
NEC4 overview: key changes and impacts - Birmingham, September 2017NEC4 overview: key changes and impacts - Birmingham, September 2017
NEC4 overview: key changes and impacts - Birmingham, September 2017
 
07 cl-assignment-syafiq-qy-macy-huiyong-deric
07 cl-assignment-syafiq-qy-macy-huiyong-deric07 cl-assignment-syafiq-qy-macy-huiyong-deric
07 cl-assignment-syafiq-qy-macy-huiyong-deric
 

Similar to Chapter 4

Early Dispute Resolution in the Construction Industry
Early Dispute Resolution in the Construction IndustryEarly Dispute Resolution in the Construction Industry
Early Dispute Resolution in the Construction IndustryFrancis Ho
 
ALTERNATIVE DISPUTE RESOLUTION 2022_ Handling the Arbitration
ALTERNATIVE DISPUTE RESOLUTION 2022_ Handling the ArbitrationALTERNATIVE DISPUTE RESOLUTION 2022_ Handling the Arbitration
ALTERNATIVE DISPUTE RESOLUTION 2022_ Handling the ArbitrationFinancial Poise
 
Preparing for an Arbitration
Preparing for an ArbitrationPreparing for an Arbitration
Preparing for an ArbitrationFinancial Poise
 
DISPUTE REVIEW BOARDS -REASONS-NEED-METHODS-RESPONSIBILITIES-PROCESFUNCTIONS-...
DISPUTE REVIEW BOARDS -REASONS-NEED-METHODS-RESPONSIBILITIES-PROCESFUNCTIONS-...DISPUTE REVIEW BOARDS -REASONS-NEED-METHODS-RESPONSIBILITIES-PROCESFUNCTIONS-...
DISPUTE REVIEW BOARDS -REASONS-NEED-METHODS-RESPONSIBILITIES-PROCESFUNCTIONS-...Surya Bhai
 
Dealing with conflict in project management
Dealing with conflict in project managementDealing with conflict in project management
Dealing with conflict in project managementpmb25
 
Civil engineering practice (lec 5)
Civil engineering practice (lec 5)Civil engineering practice (lec 5)
Civil engineering practice (lec 5)Muhammad Khan
 
Lecture 2 - ADR vs Litigation.pdf
Lecture 2 - ADR vs Litigation.pdfLecture 2 - ADR vs Litigation.pdf
Lecture 2 - ADR vs Litigation.pdfjonathan539518
 
Overview of Patent Litigation in the United States - Knobbe Practice Webinar...
 Overview of Patent Litigation in the United States - Knobbe Practice Webinar... Overview of Patent Litigation in the United States - Knobbe Practice Webinar...
Overview of Patent Litigation in the United States - Knobbe Practice Webinar...Knobbe Martens - Intellectual Property Law
 
Adjudication: Tips, Traps and Tactics
Adjudication: Tips, Traps and TacticsAdjudication: Tips, Traps and Tactics
Adjudication: Tips, Traps and TacticsFrancis Ho
 
Alternative Dispute Resolution (ADR)
Alternative Dispute Resolution (ADR)Alternative Dispute Resolution (ADR)
Alternative Dispute Resolution (ADR)Shyam Anandjiwala
 
Adjudication: Challenging the Adjudicator's Jurisdiction
Adjudication: Challenging the Adjudicator's JurisdictionAdjudication: Challenging the Adjudicator's Jurisdiction
Adjudication: Challenging the Adjudicator's JurisdictionFrancis Ho
 
techniques of ADR- With Polls.pptx
techniques of ADR- With Polls.pptxtechniques of ADR- With Polls.pptx
techniques of ADR- With Polls.pptxssuserdf29f0
 
The Procedural Pre-nup: How to Leverage Arbitration Effectively for your Busi...
The Procedural Pre-nup: How to Leverage Arbitration Effectively for your Busi...The Procedural Pre-nup: How to Leverage Arbitration Effectively for your Busi...
The Procedural Pre-nup: How to Leverage Arbitration Effectively for your Busi...Osler, Hoskin & Harcourt LLP
 
Ceca adjudication the process - january 2013
Ceca   adjudication  the process - january 2013Ceca   adjudication  the process - january 2013
Ceca adjudication the process - january 2013watsonburton
 

Similar to Chapter 4 (20)

Chapter 4 [compatibility mode]
Chapter 4 [compatibility mode]Chapter 4 [compatibility mode]
Chapter 4 [compatibility mode]
 
Chapter 4 [compatibility mode]
Chapter 4 [compatibility mode]Chapter 4 [compatibility mode]
Chapter 4 [compatibility mode]
 
Early Dispute Resolution in the Construction Industry
Early Dispute Resolution in the Construction IndustryEarly Dispute Resolution in the Construction Industry
Early Dispute Resolution in the Construction Industry
 
Construction disputes
Construction disputesConstruction disputes
Construction disputes
 
ALTERNATIVE DISPUTE RESOLUTION 2022_ Handling the Arbitration
ALTERNATIVE DISPUTE RESOLUTION 2022_ Handling the ArbitrationALTERNATIVE DISPUTE RESOLUTION 2022_ Handling the Arbitration
ALTERNATIVE DISPUTE RESOLUTION 2022_ Handling the Arbitration
 
Litigation v Arbitration v Mediation
Litigation v Arbitration v MediationLitigation v Arbitration v Mediation
Litigation v Arbitration v Mediation
 
Preparing for an Arbitration
Preparing for an ArbitrationPreparing for an Arbitration
Preparing for an Arbitration
 
DISPUTE REVIEW BOARDS -REASONS-NEED-METHODS-RESPONSIBILITIES-PROCESFUNCTIONS-...
DISPUTE REVIEW BOARDS -REASONS-NEED-METHODS-RESPONSIBILITIES-PROCESFUNCTIONS-...DISPUTE REVIEW BOARDS -REASONS-NEED-METHODS-RESPONSIBILITIES-PROCESFUNCTIONS-...
DISPUTE REVIEW BOARDS -REASONS-NEED-METHODS-RESPONSIBILITIES-PROCESFUNCTIONS-...
 
CCDC 2 Dispute Resolution
CCDC 2 Dispute ResolutionCCDC 2 Dispute Resolution
CCDC 2 Dispute Resolution
 
Dealing with conflict in project management
Dealing with conflict in project managementDealing with conflict in project management
Dealing with conflict in project management
 
Civil engineering practice (lec 5)
Civil engineering practice (lec 5)Civil engineering practice (lec 5)
Civil engineering practice (lec 5)
 
Lecture 2 - ADR vs Litigation.pdf
Lecture 2 - ADR vs Litigation.pdfLecture 2 - ADR vs Litigation.pdf
Lecture 2 - ADR vs Litigation.pdf
 
Overview of Patent Litigation in the United States - Knobbe Practice Webinar...
 Overview of Patent Litigation in the United States - Knobbe Practice Webinar... Overview of Patent Litigation in the United States - Knobbe Practice Webinar...
Overview of Patent Litigation in the United States - Knobbe Practice Webinar...
 
Adjudication: Tips, Traps and Tactics
Adjudication: Tips, Traps and TacticsAdjudication: Tips, Traps and Tactics
Adjudication: Tips, Traps and Tactics
 
Litigation 2
Litigation 2Litigation 2
Litigation 2
 
Alternative Dispute Resolution (ADR)
Alternative Dispute Resolution (ADR)Alternative Dispute Resolution (ADR)
Alternative Dispute Resolution (ADR)
 
Adjudication: Challenging the Adjudicator's Jurisdiction
Adjudication: Challenging the Adjudicator's JurisdictionAdjudication: Challenging the Adjudicator's Jurisdiction
Adjudication: Challenging the Adjudicator's Jurisdiction
 
techniques of ADR- With Polls.pptx
techniques of ADR- With Polls.pptxtechniques of ADR- With Polls.pptx
techniques of ADR- With Polls.pptx
 
The Procedural Pre-nup: How to Leverage Arbitration Effectively for your Busi...
The Procedural Pre-nup: How to Leverage Arbitration Effectively for your Busi...The Procedural Pre-nup: How to Leverage Arbitration Effectively for your Busi...
The Procedural Pre-nup: How to Leverage Arbitration Effectively for your Busi...
 
Ceca adjudication the process - january 2013
Ceca   adjudication  the process - january 2013Ceca   adjudication  the process - january 2013
Ceca adjudication the process - january 2013
 

More from Delhi Technological University

More from Delhi Technological University (20)

Chapter 3- Contract Management
Chapter 3- Contract ManagementChapter 3- Contract Management
Chapter 3- Contract Management
 
Chapter 2- Contract Management
Chapter 2- Contract ManagementChapter 2- Contract Management
Chapter 2- Contract Management
 
Chapter 5- Lecture
Chapter 5- LectureChapter 5- Lecture
Chapter 5- Lecture
 
Chapter 4- Lecture
Chapter 4- LectureChapter 4- Lecture
Chapter 4- Lecture
 
Chapter 3- Lecture
Chapter 3- LectureChapter 3- Lecture
Chapter 3- Lecture
 
Chapter 2- Lecture
Chapter 2- LectureChapter 2- Lecture
Chapter 2- Lecture
 
Chapter 1- Lecture
Chapter 1- LectureChapter 1- Lecture
Chapter 1- Lecture
 
Construction equipment management chapter 5
Construction equipment management chapter 5Construction equipment management chapter 5
Construction equipment management chapter 5
 
Construction equipment management chapter 4
Construction equipment management chapter 4Construction equipment management chapter 4
Construction equipment management chapter 4
 
Construction equipment management chapter 3
Construction equipment management chapter 3Construction equipment management chapter 3
Construction equipment management chapter 3
 
Construction equipment management chapter 2
Construction equipment management chapter 2Construction equipment management chapter 2
Construction equipment management chapter 2
 
Construction equipment management chapter 1pdf
Construction equipment management chapter 1pdfConstruction equipment management chapter 1pdf
Construction equipment management chapter 1pdf
 
Chapter 5 [compatibility mode]
Chapter 5 [compatibility mode]Chapter 5 [compatibility mode]
Chapter 5 [compatibility mode]
 
Chapter 4 [compatibility mode]
Chapter 4 [compatibility mode]Chapter 4 [compatibility mode]
Chapter 4 [compatibility mode]
 
Chapter 3 [compatibility mode]
Chapter 3 [compatibility mode]Chapter 3 [compatibility mode]
Chapter 3 [compatibility mode]
 
Chapter 2 [compatibility mode]
Chapter 2 [compatibility mode]Chapter 2 [compatibility mode]
Chapter 2 [compatibility mode]
 
Chapter 1 [compatibility mode]
Chapter 1 [compatibility mode]Chapter 1 [compatibility mode]
Chapter 1 [compatibility mode]
 
Construction contract
Construction contractConstruction contract
Construction contract
 
Chapter 2 [compatibility mode]
Chapter 2 [compatibility mode]Chapter 2 [compatibility mode]
Chapter 2 [compatibility mode]
 
Chapter 1 [compatibility mode]
Chapter 1 [compatibility mode]Chapter 1 [compatibility mode]
Chapter 1 [compatibility mode]
 

Recently uploaded

INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 

Recently uploaded (20)

INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 

Chapter 4

  • 1. Dispute and Dispute Resolution Mechanisms Mada Walabu University Construction Law CoTM 4241 Chapter 4 College of Engineering Construction Technology and Management Department Instructor: Andualem Endris (M.Sc) E-mail: andu0117@yahoo.com
  • 2. What is Dispute? CoTM 4241 2 31 July 2021
  • 3. Disputes • Dispute is a disagreement between parties • Construction projects are generally complex, for this reason, disputes are always present • Involves many parties. • When a project ends up in a dispute, the project will fail to meet its original goals and expectation. CoTM 4241 3 31 July 2021
  • 4. Disputes • Clients will suffer from high legal fees, delayed completion and occupation and general dissatisfaction. • The contractor’s profits will diminish and to these will be added additional legal fees. • No winners under these circumstances CoTM 4241 4 31 July 2021
  • 5. Causes of Disputes CoTM 4241 5 31 July 2021
  • 6. Causes of Disputes • May arise on a construction project for a number of reasons:  Late or non-payment for works satisfactorily completed when payment is due.  Inaccurate valuation of variations and works in progress.  Delays in the supply of general construction information CoTM 4241 6 31 July 2021
  • 7. Causes of Disputes …Cont’d  Late issue of instruction varying some sections of the works, which disrupts the contractor’s progress and program of works.  Shortcomings, omissions and errors in contract documentation giving rise to ambiguities in contract requirements.  Failure of contractor to construct the works diligently and to program. CoTM 4241 7 31 July 2021
  • 8. Causes of Disputes …Cont’d  Increase in scope of work (changes, extras and errors) without proper consideration for extension of production time.  Acceleration to complete within original program without proper agreement over the payment.  Poor workmanship and failure to use specified materials, skilled operatives and recognized methods.  Failure to inspect works in progress regularly and condemning only when works are completed. CoTM 4241 8 31 July 2021
  • 9. Causes of Disputes …Cont’d • It can be deduced from the above list that the main areas of construction disputes revolve around: payments contract documentation Time and cost overruns Construction information and site supervision • Owing to their diverse status, the view points of the project participants towards disputes areas vary. CoTM 4241 9 31 July 2021
  • 10. Alternative Dispute Resolution Mechanisms (ADR) CoTM 4241 10 31 July 2021
  • 11. Dispute Resolution Mechanisms • An introductory survey of the construction industry’s commonly used dispute resolution mechanisms. • Negotiation • Mediation • Conciliation • Dispute Review Boards • Arbitration • Litigation 11 CoTM 4241 31 July 2021
  • 12. Negotiation • Dispute resolution between the parties involving only the parties • Informal – Conversations, emails, texts, phone calls • Formal – Meetings, documentation, presentations • Resolution – Regardless of how you got there: Put it in writing 12 CoTM 4241 31 July 2021
  • 13. Elevating the Negotiation • Can’t settle at the jobsite level? • Push the dispute “upstairs” • Again, only the parties are involved • May be multiple meetings • Resolution must be written 13 CoTM 4241 31 July 2021
  • 14. Mediation • Mediation: Bringing in a respected, neutral, uninvolved person to help everyone reach a mutually acceptable resolution – The mediator DOES NOT decide – Mediation may not resolve a dispute • Key Points – Voluntary – The resolution is binding, but the process is not – You set the rules 14 CoTM 4241 31 July 2021
  • 15. Mediation • The Parties must agree to mediate • The Parties must select a mediator • The Contract may define mediation terms, procedures, maybe even the mediator • Select a mediator with whom you are comfortable and who you believe will also be credible with the other parties • The mediator proposes several possible solutions to the dispute. 15 CoTM 4241 31 July 2021
  • 16. Mediation – The Process • Parties provide the Mediator with information to understand the dispute • The Mediator chooses to meet individually with the parties, or to call all parties together in a “joint session” • After a sufficient exchange of information, the Mediator breaks the parties apart and begins shuttle diplomacy • The Mediator works for you – make the Mediator work, not just shuffle back and forth 16 CoTM 4241 31 July 2021
  • 17. Mediation – The Resolution • Mediators DO NOT Decide – The Parties decide • The Mediator’s Proposal – Not always offered – May be requested – NOT binding until all parties accept – The process is still voluntary 17 CoTM 4241 31 July 2021
  • 18. Conciliation 31 July 2021 CoTM 4241 18 • Conciliation is a voluntary proceeding • It requires that the parties be subject to a third person (neutral or conciliator). • The aim is to assist with legal or technical aspects in the matter, in order to reach a satisfactory arrangement. • This practice is referred to as ‘reconciling’ the parties in an attempt to find a common agreement.
  • 19. Dispute Review Boards • A contractually defined process • 3 members – all are neutral: – Contractor nominated, Owner nominated – Those two appoint the 3rd neutral • Typically defined in the contract – But can be established any time the parties agree to do so • Regular site visits • Conducts hearings 19 CoTM 4241 31 July 2021
  • 20. Dispute Review Board Hearings • Frequently “no attorneys” • Parties explain their case to the DRB • Exhibits, Calculations, Presentations • DRB hears and receives the information 20 CoTM 4241 31 July 2021
  • 21. Dispute Review Board Decisions • Check your contract – terms vary • Typically non-binding but admissible • Probably the best independent evaluation you’ll ever get for your problem 21 CoTM 4241 31 July 2021
  • 22. Arbitration • Arbitration is the submission of a dispute to one or more impartial persons for a final and binding decision, known as an "award." • Awards are made in writing and are generally final and binding on the parties in the case. • Many times contract defined • Always an option if all parties agree. • Variety of associations provide, arbitration services. 22 CoTM 4241 31 July 2021
  • 23. Arbitrator Selection • Big Benefit: You “choose” your Judge • Must be confirmed independent and unrelated • Look for folks who will understand your situation, but without bringing too much bias and pre- conceived resolutions • Consider the expediency of a single arbitrator versus the combined wisdom of a three-party panel 23 CoTM 4241 31 July 2021
  • 24. The Hearings • NO Ex Parte communications • Arbitrator sets schedule • Proceedings are formalized through rules • Evidence is presented through sworn testimony • Arbitrator may question the witnesses and the attorneys • Arbitrator sets, with party input, closing briefs, submission timelines, and form of decision 24 CoTM 4241 31 July 2021
  • 25. The Decision • The Final Decision is Final • There are very few accepted ways to overturn a Decision: – The Arbitrator failed to hear evidence – The Arbitrator was on the take, misbehavior – The Arbitrator exceeded the powers granted to the Arbitrator • Other than winning an appeal using one or more of those conditions – you are stuck with the Decision. 25 CoTM 4241 31 July 2021
  • 26. Litigation • May be a Federal or State Agency Court – For example: Board of Contract Appeals, • In a courtroom, you get to choose – Judge: “Bench Trial” • Yesterday, the Judge sentenced a rapist to life, today, the Judge is hearing you argue about money and time – Jury: Your “Peers” • Check that jury pool – do any of them really understand the nuances of a construction project? 26 CoTM 4241 31 July 2021
  • 27. Litigation • Getting There – Many times contract defined – Any party can initiate: “I’m gonna sue you!” • Adjudicator Selection – The Judge is assigned – You may be able to choose a jury • Hearings – Strict rules of evidence – The Court’s schedule – your schedule just doesn’t matter. 27 CoTM 4241 31 July 2021
  • 28. Litigation - Process • Tedious • Discovery – produce Everything • Motions, Legal Positioning • Pre-Trial Hearings • Finally, the Hearing itself 28 CoTM 4241 31 July 2021
  • 29. Litigation - Frustration • Cancel your vacation, you’re scheduled to be in Court • But the Court will delay, as you are “trailing” • When you do arrive, plan on lots of vacant times • Remember the money you are paying your team to be there. 29 CoTM 4241 31 July 2021
  • 30. Litigation – The Decision • Likely one party won’t like the Decision • That party will then file for appeal – Frequently used to encourage the “winner” to accept an immediate but smaller resolution • After years in Trial Court, now years of Appeals – And you may be sent back for a new trial 30 CoTM 4241 31 July 2021
  • 31. Litigation Closure I’m just so glad, I won… 31 CoTM 4241 31 July 2021
  • 32. Assignment 2 31 July 2021 CoTM 4241 32 • Briefly discuss the difference between ‘Conciliation’ and ‘Mediation’ • Differentiate between ‘Judge, and ‘Jury’. Submission Date: January 09, 2020
  • 33. 33 CoTM 4241 31 July 2021 Thank You!