SlideShare a Scribd company logo
NEC4 overview: key changes and impacts
Nottingham, September 2017
Today Martin Cannon of Browne Jacobson and Eugene
Lenehan of Driver Trett will be speaking on:
(i) Changes to the NEC Structure (Contract and
Suite);
(ii) Changes in Approach following the change to the
structure; and
(iii)The introduction of 2 new contracts to the Suite
(the “DBO” and “Alliancing” contracts).
NEC4 – What’s new?
Overview and new contracts
Martin Cannon
Partner, construction team
NEC4 – What was the key focus?
• “Evolution” not “Revolution”.
• To provide greater stimulus to good management;
• Support new approaches to procurement which
improve contract management; and
• Inspire increased use of NEC in new markets and
sectors.
New additions to the NEC Suite
• Following the NEC4 Suite having been published
and the objective of supporting new approaches to
procurement we have seen the introduction of:
(i) NEC4 Design, Build, and Operate contract;
and
(ii) NEC4 Alliance Contract
NEC4 Suite structure
• The NEC4 Suite retains:
(a) Engineering and Construction Contract
(b) Framework Contract
(c) Professional Service Contract
(d) Supply Contract
(e) Term Service Contract
• The previous NEC3 Adjudicator’s Contract has been replaced by
the NEC4 Dispute Resolution Contract
Structure
• The key model sections of the NEC3 have been
retained (with the uniform change in language
across the suite), namely the:
(a) Core Clauses;
(b) Secondary Option Clauses; and
(c) X and Y Clauses.
A change in process…
• New provisions confirming that the programme is deemed as
accepted in the event that the Project Manager fails to respond
within the necessary time period.
• Change to the payment regime where the contractor is to submit
an application for payment prior to the “assessment date”,
together with a final payment mechanism.
• Changes to the CE mechanism – allowance for an additional CE
where the Contractor has priced for a proposed instruction and it
is not accepted, provision in the Contract Data to include further
bespoke CE’s.
A change in process…
• Changes to the dispute resolution procedure within the contract,
the introduction of a new tiered process.
• Changes in terminology with the introduction of gender neutral
wording, “client” instead of “employer”, change from “Risk
Register” to “Early Warning Register”, and the introduction of
“Scope” instead of “Works Information”/”Service Information”.
• Changes to include clauses dealing with the transfer of benefits
(i.e. assignment), confidentiality and publicity, and bribery and
corruption.
Design, Build, and Operate Contract
• Broadly the overall structure of the contract is the same as the
NEC4 model retaining the key core and secondary clauses.
• A number of the “X” clauses have, however, been removed
(options X1, X2, X5 – 7, X11 – 12, X15- 17 and X19 – 22 are not
used).
• In very broad terms the contract is similar to the PFI model as it
governs both the construction of the building and the subsequent
operational phase once the works have been completed.
Structure: a “walkthrough"
The contract follows the standard structure of the NEC4 model (albeit
in a shortened form). Key provisions to note as follows:
• Definitions:- some key terms;
• Design;
• The “Service”; and
• Time.
Definitions: some key terms
• There is a “Service Manager” (in lieu of the “Project Manager” as
referred to in the ECC).
• The “Service Period” is the period during which the Service is
carried out (this includes both the construction and operational
phase).
• The Contractor is to carry out the “Service” as defined in the
“Scope” for the “Service Period”.
Design
• The Contractor has design responsibility – the Contractor is to carry
out the design necessary for the provision of the “Service”.
• The Contractor is required to submit the “particulars of its design”
for approval to the Service Manager.
• The Contractor cannot proceed with its works unless and to the
extent that the Service Manager has accepted the design.
The Service
• The Service is set out in the Scope.
• Similar to the PFI model the Contractor is to operate a quality
management system.
• Within the period stated in the Contract Data the Contractor is to
provide to the Service Manager a “Quality Plan” and “Quality
Policy Statement”.
• Any instruction from the Service Manager to correct a failure to
comply with the Quality Plan does not operate as a CE under the
Contract.
Time
• Where a plan has not been identified in the Contract Data, the
Contractor submits a first plan to the Service Manager for
acceptance within the period stated in the Contract Data.
• Within 2 weeks of the Contractor submitting a plan for acceptance,
the Service Manager notifies the Contractor of the acceptance of
the Plan or the reasons for not accepting it.
• If the Service Manager does not notify acceptance or non –
acceptance within the time allowed the Contractor notifies the
Service Manager of the failure. If the failure continues for one
week after the notification the plan is deemed accepted.
Time: The Plan
The Plan includes provisions for:
(i) float, time risk allowances, H&S
requirements;
(ii) access dates, dates for (a) acceptances,
(b) Plant and Materials, (c) information; and
(iii) details of how each operation is to be
carried out (including dates, equipment,
resources to be used).
Conclusion
The NEC says that “The Design Build and Operate
Contract allows for a much more integrated method
of procurement”.
Alliance Contract
• The Alliance Contract has initially been published in consultation
form and can be downloaded only at present from the NEC Website
by request.
• The Alliance Contract is a multi – party contract with a risk and
reward model “built in”.
• The liabilities are shared/managed by the Alliance (save in
circumstances where there has been a wilful default by one of the
alliance partners).
Management of the Contract
• The Contract is managed by the Alliance Manager (who leads the
Alliance delivery team).
• All decisions under the contract are to be taken by the Alliance
Board (made up of representatives from each of the Alliance
members and the client). The decisions of the Alliance Board have
to be unanimous and bind all the parties that make up the
Alliance.
• The Alliance Manager reports to the Alliance Board.
Payment
• The basis of payment is Defined cost plus Fee (the same as Option
E of the NEC4 ECC). Payment is to be made via a Project Bank
Account.
• The Alliance Manager assesses the amount due and the Client’s
representative certifies.
• Alliance Objectives form the basis of the performance targets
against which the Alliance will be incentivised, this means that
work allocation will be based around what’s best for the project
(this should have the effect of reducing the likelihood of the
partners seeking to hold onto one or more of the works packages).
Compensation Events/Disputes
• Alliance Manager assesses CE’s and the Alliance Board assesses the
quotations.
• Where there is no unanimous decision of the Alliance Board the
matter is referred to the named senior representatives under the
contract.
• The Contract can be found at www.neccontract.com.
NEC4 – What’s new?
Core clauses, main options and
secondary options
Eugene Lenehan, Driver Trett
New terminology
NEC3 NEC4
Employer Client
Works Information Scope
Risk Register Early Warning Register
Section 4 (Testing and Defects) Section 4 (Quality Management)
Section 8 (Risks and Insurance) Section 8 (Liabilities and Insurance)
He / his It / its
X4 – Parent Company Guarantee X4 – Ultimate Holding Guarantee
X12 - Partnering X12 – Multiparty collaboration
New terminology
• New definition of Subcontractor (11.1(19))
• Excludes labour suppliers
Contractors proposals
• Clause 16 – Contractor proposes changes to scope “to reduce the
amount the Client pays…For Providing the Works”.
• Reduced by multiplying the assessed effect of CE by the value
engineering percentage.
• Clause 36 – Contractor can now propose acceleration
• Option X21
Other Core Clause 1 changes
• Clause 10.0 now split in two
• PM rejections “in sufficient detail to enable the Contractor to
correct the matter” (clause 13.4)
• New clause 18: the Contractor does not do a Corrupt Act. Client
may terminate (clause 91.8)
• Prevention event – must stop “the whole of” the works (clause 19)
Confidentiality
• New clause 29 – “disclosure”
• Restrictions on disclosing information
• Contractor needs Client’s agreement to publicise
the works
Programme – deemed acceptance
• Clause 31.3 amended
• If PM fails to respond within 2 weeks Contractor
can issue a reminder
• If PM continues not to respond for 1 week the
programme is deemed accepted
Updating the programme
• Clause 32 amended
• “Implemented compensation events” deleted
Quality management
• New requirement for a quality management system (Clause 40)
• QMS to comply with the Scope
• Contractor submits for acceptance a quality policy statement and
quality plan
• Contractor can change quality plan with PM’s acceptance
Payment applications
• Contractor submits application for payment (clause
50.2)
• “In the form stated in the Scope”
• If no application issued before the assessment date the
amount due is the lesser of
– Amount PM assess as due; and
– Amount as previous assessment date
Review of Defined Costs (options C, D, E & F)
• New clause 50.9
• Contractor can instigate review & acceptance of its
Defined Cost by PM
• If PM does not respond within 13 weeks (or four
weeks of providing further information)
Contractor’s Defined Costs and Disallowed Cost are
treated as accepted
Final assessment
• New clause 53
• PM obliged to issue final assessment within four weeks of Defects
Certificate (clause 53.1)
• If PM fails to do this, Contractor may issues its own assessment
• Final assessment becomes conclusive if not challenged by either
party referring it to dispute resolution within four weeks
SCC and Fee
• Schedule of Cost Components
– Subcontract costs moved to SCC. Payment of them
made consistent across all Options.
– ‘Working Areas overheads’ removed from SCC.
– ‘Design overheads’ and ‘manufacturing and
fabrication overheads’ also removed
• The Fee
– Now only one fee percentage
Defined Cost and Disallowed Cost
• Options A & B
– Cost of preparing quotations is no longer excluded
• Options C, D, E & F
– New type of Disallowed Cost – adjudication costs
between Contractor and Subcontractor where
Contractor did not notify PM
Compensation Events
• Clause 60.1(20): Quotation for proposed instruction that is not
accepted
• Clause 60.1(21): Additional compensation events can be included
• Clause 63.1: “dividing date” for forecast/actual costs
• Clause 63.5: Delay based on Accepted Programme “current at the
dividing date”
Core Clause 8
• Liabilities and insurance
• Clause 81: Contractor’s liabilities now expressly stated
• Recovery of costs
• Clause 84.2: Waiver of subrogation rights against
Parties
Amendments to secondary options
• X4 – Ultimate holding company guarantees
• X12 – Multi Party Collaboration
• X15 – Contractor’s design
New secondary options
• X8 – Undertakings to the Client or Others
• X9 – Transfer of Rights
• X10 – Information Modelling
• X11 – Termination by Client
• X21 – Whole Life Cost
• X22 – Early Contractor Involvement (C&E)
Any questions?
Martin Cannon
E: martin.cannon@brownejacobson.com
T: +44 (0)121 296 0710
Eugene Lenehan
E: eugene.lenehan@drivertrett.com
T: +44 (0)2476 697 977
All information correct at time of production.
The information and opinions expressed within this document are
no substitute for full legal advice. It is for guidance only and
illustrates the law as at the published date. If in doubt, please
telephone us on 0370 270 6000.
© Browne Jacobson LLP 2017 – The information contained within
this document is and shall remain the property of Browne
Jacobson. This document may not be reproduced without the prior
consent of Browne Jacobson.
41

More Related Content

What's hot

Managing Risks and Changes under NEC4
Managing Risks and Changes under NEC4Managing Risks and Changes under NEC4
Managing Risks and Changes under NEC4
Sarah Fox
 
CFW An Introduction to Building Information Modelling
CFW An Introduction to Building Information Modelling CFW An Introduction to Building Information Modelling
CFW An Introduction to Building Information Modelling
Rae Davies
 
Planning and development club - May 2017, Nottingham
Planning and development club - May 2017, NottinghamPlanning and development club - May 2017, Nottingham
Planning and development club - May 2017, Nottingham
Browne Jacobson LLP
 
CFW Supply Chain Development
CFW Supply Chain DevelopmentCFW Supply Chain Development
CFW Supply Chain Development
Rae Davies
 
NEC Contracts - Programmes under ECC and PSC webinar
NEC Contracts - Programmes under ECC and PSC webinarNEC Contracts - Programmes under ECC and PSC webinar
NEC Contracts - Programmes under ECC and PSC webinar
Association for Project Management
 
M4 - Making Target Cost Contracts Work, under NEC3
M4 - Making Target Cost Contracts Work, under NEC3M4 - Making Target Cost Contracts Work, under NEC3
M4 - Making Target Cost Contracts Work, under NEC3
Project Controls Expo
 
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
Project Controls Expo
 
Construction Futures Wales - Project Bank Accounts
Construction Futures Wales - Project Bank AccountsConstruction Futures Wales - Project Bank Accounts
Construction Futures Wales - Project Bank Accounts
Rae Davies
 
NEC4: The good, the bad, and the ugly, Part 1: Contract strategy changes webi...
NEC4: The good, the bad, and the ugly, Part 1: Contract strategy changes webi...NEC4: The good, the bad, and the ugly, Part 1: Contract strategy changes webi...
NEC4: The good, the bad, and the ugly, Part 1: Contract strategy changes webi...
Association for Project Management
 
NEC3 to NE4 webinar
NEC3 to NE4 webinarNEC3 to NE4 webinar
NEC FIDIC JBCC Contracts Workshop 2012
NEC FIDIC JBCC Contracts Workshop 2012NEC FIDIC JBCC Contracts Workshop 2012
NEC FIDIC JBCC Contracts Workshop 2012Ola Odejayi
 
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16Arvind Solanki
 
Muckle LLP - Which contract should I be using?
Muckle LLP - Which contract should I be using?Muckle LLP - Which contract should I be using?
Muckle LLP - Which contract should I be using?
Association for Project Management
 
Collaborative contracting strategies and the use of the NEC3 family of contracts
Collaborative contracting strategies and the use of the NEC3 family of contractsCollaborative contracting strategies and the use of the NEC3 family of contracts
Collaborative contracting strategies and the use of the NEC3 family of contracts
Association for Project Management
 
NEC Contracts - The Risk Register/Early Warning Register and risk allocation ...
NEC Contracts - The Risk Register/Early Warning Register and risk allocation ...NEC Contracts - The Risk Register/Early Warning Register and risk allocation ...
NEC Contracts - The Risk Register/Early Warning Register and risk allocation ...
Association for Project Management
 
What is NEC3? by Dr Jon Broome, with industry examples by John Rayner, 21st A...
What is NEC3? by Dr Jon Broome, with industry examples by John Rayner, 21st A...What is NEC3? by Dr Jon Broome, with industry examples by John Rayner, 21st A...
What is NEC3? by Dr Jon Broome, with industry examples by John Rayner, 21st A...
Association for Project Management
 
NEC Engineering and Construction Contract (ECC) - compensation events webinar
NEC Engineering and Construction Contract (ECC) -  compensation events webinarNEC Engineering and Construction Contract (ECC) -  compensation events webinar
NEC Engineering and Construction Contract (ECC) - compensation events webinar
Association for Project Management
 
M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...
M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...
M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...
Project Controls Expo
 
NEC Engineering and Construction Contract (ECC) -The Supervisor's roles and r...
NEC Engineering and Construction Contract (ECC) -The Supervisor's roles and r...NEC Engineering and Construction Contract (ECC) -The Supervisor's roles and r...
NEC Engineering and Construction Contract (ECC) -The Supervisor's roles and r...
Association for Project Management
 
Why does an eot not automatically entitle a contractor to prolongation costs ...
Why does an eot not automatically entitle a contractor to prolongation costs ...Why does an eot not automatically entitle a contractor to prolongation costs ...
Why does an eot not automatically entitle a contractor to prolongation costs ...
Iffat Al Gharbi
 

What's hot (20)

Managing Risks and Changes under NEC4
Managing Risks and Changes under NEC4Managing Risks and Changes under NEC4
Managing Risks and Changes under NEC4
 
CFW An Introduction to Building Information Modelling
CFW An Introduction to Building Information Modelling CFW An Introduction to Building Information Modelling
CFW An Introduction to Building Information Modelling
 
Planning and development club - May 2017, Nottingham
Planning and development club - May 2017, NottinghamPlanning and development club - May 2017, Nottingham
Planning and development club - May 2017, Nottingham
 
CFW Supply Chain Development
CFW Supply Chain DevelopmentCFW Supply Chain Development
CFW Supply Chain Development
 
NEC Contracts - Programmes under ECC and PSC webinar
NEC Contracts - Programmes under ECC and PSC webinarNEC Contracts - Programmes under ECC and PSC webinar
NEC Contracts - Programmes under ECC and PSC webinar
 
M4 - Making Target Cost Contracts Work, under NEC3
M4 - Making Target Cost Contracts Work, under NEC3M4 - Making Target Cost Contracts Work, under NEC3
M4 - Making Target Cost Contracts Work, under NEC3
 
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
 
Construction Futures Wales - Project Bank Accounts
Construction Futures Wales - Project Bank AccountsConstruction Futures Wales - Project Bank Accounts
Construction Futures Wales - Project Bank Accounts
 
NEC4: The good, the bad, and the ugly, Part 1: Contract strategy changes webi...
NEC4: The good, the bad, and the ugly, Part 1: Contract strategy changes webi...NEC4: The good, the bad, and the ugly, Part 1: Contract strategy changes webi...
NEC4: The good, the bad, and the ugly, Part 1: Contract strategy changes webi...
 
NEC3 to NE4 webinar
NEC3 to NE4 webinarNEC3 to NE4 webinar
NEC3 to NE4 webinar
 
NEC FIDIC JBCC Contracts Workshop 2012
NEC FIDIC JBCC Contracts Workshop 2012NEC FIDIC JBCC Contracts Workshop 2012
NEC FIDIC JBCC Contracts Workshop 2012
 
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
 
Muckle LLP - Which contract should I be using?
Muckle LLP - Which contract should I be using?Muckle LLP - Which contract should I be using?
Muckle LLP - Which contract should I be using?
 
Collaborative contracting strategies and the use of the NEC3 family of contracts
Collaborative contracting strategies and the use of the NEC3 family of contractsCollaborative contracting strategies and the use of the NEC3 family of contracts
Collaborative contracting strategies and the use of the NEC3 family of contracts
 
NEC Contracts - The Risk Register/Early Warning Register and risk allocation ...
NEC Contracts - The Risk Register/Early Warning Register and risk allocation ...NEC Contracts - The Risk Register/Early Warning Register and risk allocation ...
NEC Contracts - The Risk Register/Early Warning Register and risk allocation ...
 
What is NEC3? by Dr Jon Broome, with industry examples by John Rayner, 21st A...
What is NEC3? by Dr Jon Broome, with industry examples by John Rayner, 21st A...What is NEC3? by Dr Jon Broome, with industry examples by John Rayner, 21st A...
What is NEC3? by Dr Jon Broome, with industry examples by John Rayner, 21st A...
 
NEC Engineering and Construction Contract (ECC) - compensation events webinar
NEC Engineering and Construction Contract (ECC) -  compensation events webinarNEC Engineering and Construction Contract (ECC) -  compensation events webinar
NEC Engineering and Construction Contract (ECC) - compensation events webinar
 
M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...
M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...
M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...
 
NEC Engineering and Construction Contract (ECC) -The Supervisor's roles and r...
NEC Engineering and Construction Contract (ECC) -The Supervisor's roles and r...NEC Engineering and Construction Contract (ECC) -The Supervisor's roles and r...
NEC Engineering and Construction Contract (ECC) -The Supervisor's roles and r...
 
Why does an eot not automatically entitle a contractor to prolongation costs ...
Why does an eot not automatically entitle a contractor to prolongation costs ...Why does an eot not automatically entitle a contractor to prolongation costs ...
Why does an eot not automatically entitle a contractor to prolongation costs ...
 

Similar to NEC4 overview: key changes and impacts - Nottingham, September 2017

From NEC3 to NEC4 ECC
From NEC3 to NEC4 ECCFrom NEC3 to NEC4 ECC
From NEC3 to NEC4 ECC
Ir Albert YEU FCIArb MICE
 
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Rae Davies
 
Chapter_2-Procurement and Contract management.pptx
Chapter_2-Procurement and Contract management.pptxChapter_2-Procurement and Contract management.pptx
Chapter_2-Procurement and Contract management.pptx
ssuserc0bf9b
 
Construction contract_Existing and Proposed Accounting Standards
Construction contract_Existing and Proposed Accounting StandardsConstruction contract_Existing and Proposed Accounting Standards
Construction contract_Existing and Proposed Accounting Standards
Adi Iskandar Iliyas
 
Health system ITO contract restructuring : A case study
Health system ITO contract restructuring :  A case studyHealth system ITO contract restructuring :  A case study
Health system ITO contract restructuring : A case study
Damo Consulting Inc.
 
Cl presentation
Cl presentationCl presentation
Cl presentation
lucaschinsheng
 
Effective contract administration may 2014
Effective contract administration may 2014Effective contract administration may 2014
Effective contract administration may 2014
SHKLaw
 
contract_management.ppt
contract_management.pptcontract_management.ppt
contract_management.ppt
ssuser32da691
 
Core_Services_White Papers Oracle Service PUR.pdf
Core_Services_White Papers Oracle Service PUR.pdfCore_Services_White Papers Oracle Service PUR.pdf
Core_Services_White Papers Oracle Service PUR.pdf
TarigTaha3
 
Study on Procurement Method Selection Procedure in Construction Industry
Study on Procurement Method Selection Procedure in Construction IndustryStudy on Procurement Method Selection Procedure in Construction Industry
Study on Procurement Method Selection Procedure in Construction Industry
IRJET Journal
 
Revenue Recognition for Contractors - NECA NOW Conference
Revenue Recognition for Contractors - NECA NOW Conference Revenue Recognition for Contractors - NECA NOW Conference
Revenue Recognition for Contractors - NECA NOW Conference
CBIZ, Inc.
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variation
Vj NiroSh
 
TUDARCO-PROCUREMENT ISSUES IN OIL AND GAS CONTRACTS
TUDARCO-PROCUREMENT ISSUES IN OIL AND GAS CONTRACTSTUDARCO-PROCUREMENT ISSUES IN OIL AND GAS CONTRACTS
TUDARCO-PROCUREMENT ISSUES IN OIL AND GAS CONTRACTSProf Handley Mpoki Mafwenga
 
Mall management Process Overview
Mall management Process OverviewMall management Process Overview
Mall management Process Overview
Jaladhi Bhatt
 
05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION
ByishimoBTCChef
 
Ak contract management
Ak contract managementAk contract management
Ak contract management
ManaliChitranshi
 
PROJECT CONTRACTS.pptx
PROJECT CONTRACTS.pptxPROJECT CONTRACTS.pptx
PROJECT CONTRACTS.pptx
MeenalKulkarni12
 
Construction contract
Construction contract Construction contract
Construction contract
Rakshith Reddy
 

Similar to NEC4 overview: key changes and impacts - Nottingham, September 2017 (20)

From NEC3 to NEC4 ECC
From NEC3 to NEC4 ECCFrom NEC3 to NEC4 ECC
From NEC3 to NEC4 ECC
 
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
 
Chapter_2-Procurement and Contract management.pptx
Chapter_2-Procurement and Contract management.pptxChapter_2-Procurement and Contract management.pptx
Chapter_2-Procurement and Contract management.pptx
 
Construction contract_Existing and Proposed Accounting Standards
Construction contract_Existing and Proposed Accounting StandardsConstruction contract_Existing and Proposed Accounting Standards
Construction contract_Existing and Proposed Accounting Standards
 
Health system ITO contract restructuring : A case study
Health system ITO contract restructuring :  A case studyHealth system ITO contract restructuring :  A case study
Health system ITO contract restructuring : A case study
 
Cl presentation
Cl presentationCl presentation
Cl presentation
 
Effective contract administration may 2014
Effective contract administration may 2014Effective contract administration may 2014
Effective contract administration may 2014
 
contract_management.ppt
contract_management.pptcontract_management.ppt
contract_management.ppt
 
Core_Services_White Papers Oracle Service PUR.pdf
Core_Services_White Papers Oracle Service PUR.pdfCore_Services_White Papers Oracle Service PUR.pdf
Core_Services_White Papers Oracle Service PUR.pdf
 
contract procedure
contract procedurecontract procedure
contract procedure
 
Study on Procurement Method Selection Procedure in Construction Industry
Study on Procurement Method Selection Procedure in Construction IndustryStudy on Procurement Method Selection Procedure in Construction Industry
Study on Procurement Method Selection Procedure in Construction Industry
 
Revenue Recognition for Contractors - NECA NOW Conference
Revenue Recognition for Contractors - NECA NOW Conference Revenue Recognition for Contractors - NECA NOW Conference
Revenue Recognition for Contractors - NECA NOW Conference
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variation
 
TUDARCO-PROCUREMENT ISSUES IN OIL AND GAS CONTRACTS
TUDARCO-PROCUREMENT ISSUES IN OIL AND GAS CONTRACTSTUDARCO-PROCUREMENT ISSUES IN OIL AND GAS CONTRACTS
TUDARCO-PROCUREMENT ISSUES IN OIL AND GAS CONTRACTS
 
Mall management Process Overview
Mall management Process OverviewMall management Process Overview
Mall management Process Overview
 
Bkozlowski wpa
Bkozlowski wpaBkozlowski wpa
Bkozlowski wpa
 
05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION
 
Ak contract management
Ak contract managementAk contract management
Ak contract management
 
PROJECT CONTRACTS.pptx
PROJECT CONTRACTS.pptxPROJECT CONTRACTS.pptx
PROJECT CONTRACTS.pptx
 
Construction contract
Construction contract Construction contract
Construction contract
 

More from Browne Jacobson LLP

Employment law update - Browne Jacobson Exeter - 06 February 2020
Employment law update - Browne Jacobson Exeter - 06 February 2020Employment law update - Browne Jacobson Exeter - 06 February 2020
Employment law update - Browne Jacobson Exeter - 06 February 2020
Browne Jacobson LLP
 
Exclusions: keeping you informed
Exclusions: keeping you informed Exclusions: keeping you informed
Exclusions: keeping you informed
Browne Jacobson LLP
 
Procurement workshop training slides - Birmingham session
Procurement workshop training slides - Birmingham sessionProcurement workshop training slides - Birmingham session
Procurement workshop training slides - Birmingham session
Browne Jacobson LLP
 
Local authority acquisition and disposal of land - July 2019
Local authority acquisition and disposal of land - July 2019Local authority acquisition and disposal of land - July 2019
Local authority acquisition and disposal of land - July 2019
Browne Jacobson LLP
 
Your employees, their future employers, and your intellectual property - July...
Your employees, their future employers, and your intellectual property - July...Your employees, their future employers, and your intellectual property - July...
Your employees, their future employers, and your intellectual property - July...
Browne Jacobson LLP
 
Public Sector Planning Club - 4 July 2019
Public Sector Planning Club - 4 July 2019Public Sector Planning Club - 4 July 2019
Public Sector Planning Club - 4 July 2019
Browne Jacobson LLP
 
Health tech slides 12 june 2019
Health tech slides   12 june 2019Health tech slides   12 june 2019
Health tech slides 12 june 2019
Browne Jacobson LLP
 
Education Law Conference Manchester - Monday 10 June 2019
Education Law Conference Manchester - Monday 10 June 2019Education Law Conference Manchester - Monday 10 June 2019
Education Law Conference Manchester - Monday 10 June 2019
Browne Jacobson LLP
 
Education Law Conference Exeter - Thursday 6 June 2019
Education Law Conference Exeter - Thursday 6 June 2019Education Law Conference Exeter - Thursday 6 June 2019
Education Law Conference Exeter - Thursday 6 June 2019
Browne Jacobson LLP
 
Redress Schemes for Abuse and Misconduct, March 2019
Redress Schemes for Abuse and Misconduct, March 2019Redress Schemes for Abuse and Misconduct, March 2019
Redress Schemes for Abuse and Misconduct, March 2019
Browne Jacobson LLP
 
Claims Club - March 2019 - Birmingham
Claims Club - March 2019 - BirminghamClaims Club - March 2019 - Birmingham
Claims Club - March 2019 - Birmingham
Browne Jacobson LLP
 
Claims Club - March 2019 - London
Claims Club - March 2019 - London Claims Club - March 2019 - London
Claims Club - March 2019 - London
Browne Jacobson LLP
 
Admin and Public Law - April 2019 - London
Admin and Public Law - April 2019 - London Admin and Public Law - April 2019 - London
Admin and Public Law - April 2019 - London
Browne Jacobson LLP
 
State aid and IP in R&D agreements, March 2019
State aid and IP in R&D agreements, March 2019 State aid and IP in R&D agreements, March 2019
State aid and IP in R&D agreements, March 2019
Browne Jacobson LLP
 
In House Lawyers, March 2019
In House Lawyers, March 2019In House Lawyers, March 2019
In House Lawyers, March 2019
Browne Jacobson LLP
 
Privileged communications webinar, March 2019
Privileged communications webinar, March 2019 Privileged communications webinar, March 2019
Privileged communications webinar, March 2019
Browne Jacobson LLP
 
Social care forum, March 2019, Manchester
Social care forum, March 2019, ManchesterSocial care forum, March 2019, Manchester
Social care forum, March 2019, Manchester
Browne Jacobson LLP
 
Public sector breakfast club, February 2019, Exeter
Public sector breakfast club, February 2019, Exeter Public sector breakfast club, February 2019, Exeter
Public sector breakfast club, February 2019, Exeter
Browne Jacobson LLP
 
Public sector planning club, February 2019, Nottingham
Public sector planning club, February 2019, NottinghamPublic sector planning club, February 2019, Nottingham
Public sector planning club, February 2019, Nottingham
Browne Jacobson LLP
 
Mental health, capacity and deprivation of liberty case law update, February ...
Mental health, capacity and deprivation of liberty case law update, February ...Mental health, capacity and deprivation of liberty case law update, February ...
Mental health, capacity and deprivation of liberty case law update, February ...
Browne Jacobson LLP
 

More from Browne Jacobson LLP (20)

Employment law update - Browne Jacobson Exeter - 06 February 2020
Employment law update - Browne Jacobson Exeter - 06 February 2020Employment law update - Browne Jacobson Exeter - 06 February 2020
Employment law update - Browne Jacobson Exeter - 06 February 2020
 
Exclusions: keeping you informed
Exclusions: keeping you informed Exclusions: keeping you informed
Exclusions: keeping you informed
 
Procurement workshop training slides - Birmingham session
Procurement workshop training slides - Birmingham sessionProcurement workshop training slides - Birmingham session
Procurement workshop training slides - Birmingham session
 
Local authority acquisition and disposal of land - July 2019
Local authority acquisition and disposal of land - July 2019Local authority acquisition and disposal of land - July 2019
Local authority acquisition and disposal of land - July 2019
 
Your employees, their future employers, and your intellectual property - July...
Your employees, their future employers, and your intellectual property - July...Your employees, their future employers, and your intellectual property - July...
Your employees, their future employers, and your intellectual property - July...
 
Public Sector Planning Club - 4 July 2019
Public Sector Planning Club - 4 July 2019Public Sector Planning Club - 4 July 2019
Public Sector Planning Club - 4 July 2019
 
Health tech slides 12 june 2019
Health tech slides   12 june 2019Health tech slides   12 june 2019
Health tech slides 12 june 2019
 
Education Law Conference Manchester - Monday 10 June 2019
Education Law Conference Manchester - Monday 10 June 2019Education Law Conference Manchester - Monday 10 June 2019
Education Law Conference Manchester - Monday 10 June 2019
 
Education Law Conference Exeter - Thursday 6 June 2019
Education Law Conference Exeter - Thursday 6 June 2019Education Law Conference Exeter - Thursday 6 June 2019
Education Law Conference Exeter - Thursday 6 June 2019
 
Redress Schemes for Abuse and Misconduct, March 2019
Redress Schemes for Abuse and Misconduct, March 2019Redress Schemes for Abuse and Misconduct, March 2019
Redress Schemes for Abuse and Misconduct, March 2019
 
Claims Club - March 2019 - Birmingham
Claims Club - March 2019 - BirminghamClaims Club - March 2019 - Birmingham
Claims Club - March 2019 - Birmingham
 
Claims Club - March 2019 - London
Claims Club - March 2019 - London Claims Club - March 2019 - London
Claims Club - March 2019 - London
 
Admin and Public Law - April 2019 - London
Admin and Public Law - April 2019 - London Admin and Public Law - April 2019 - London
Admin and Public Law - April 2019 - London
 
State aid and IP in R&D agreements, March 2019
State aid and IP in R&D agreements, March 2019 State aid and IP in R&D agreements, March 2019
State aid and IP in R&D agreements, March 2019
 
In House Lawyers, March 2019
In House Lawyers, March 2019In House Lawyers, March 2019
In House Lawyers, March 2019
 
Privileged communications webinar, March 2019
Privileged communications webinar, March 2019 Privileged communications webinar, March 2019
Privileged communications webinar, March 2019
 
Social care forum, March 2019, Manchester
Social care forum, March 2019, ManchesterSocial care forum, March 2019, Manchester
Social care forum, March 2019, Manchester
 
Public sector breakfast club, February 2019, Exeter
Public sector breakfast club, February 2019, Exeter Public sector breakfast club, February 2019, Exeter
Public sector breakfast club, February 2019, Exeter
 
Public sector planning club, February 2019, Nottingham
Public sector planning club, February 2019, NottinghamPublic sector planning club, February 2019, Nottingham
Public sector planning club, February 2019, Nottingham
 
Mental health, capacity and deprivation of liberty case law update, February ...
Mental health, capacity and deprivation of liberty case law update, February ...Mental health, capacity and deprivation of liberty case law update, February ...
Mental health, capacity and deprivation of liberty case law update, February ...
 

Recently uploaded

Synopsis On Annual General Meeting/Extra Ordinary General Meeting With Ordina...
Synopsis On Annual General Meeting/Extra Ordinary General Meeting With Ordina...Synopsis On Annual General Meeting/Extra Ordinary General Meeting With Ordina...
Synopsis On Annual General Meeting/Extra Ordinary General Meeting With Ordina...
Syed Muhammad Humza Hussain
 
Matthew Professional CV experienced Government Liaison
Matthew Professional CV experienced Government LiaisonMatthew Professional CV experienced Government Liaison
Matthew Professional CV experienced Government Liaison
MattGardner52
 
怎么购买(massey毕业证书)新西兰梅西大学毕业证学位证书注册证明信原版一模一样
怎么购买(massey毕业证书)新西兰梅西大学毕业证学位证书注册证明信原版一模一样怎么购买(massey毕业证书)新西兰梅西大学毕业证学位证书注册证明信原版一模一样
怎么购买(massey毕业证书)新西兰梅西大学毕业证学位证书注册证明信原版一模一样
9ib5wiwt
 
XYZ-v.-state-of-Maharashtra-Bombay-HC-Writ-Petition-6340-2023.pdf
XYZ-v.-state-of-Maharashtra-Bombay-HC-Writ-Petition-6340-2023.pdfXYZ-v.-state-of-Maharashtra-Bombay-HC-Writ-Petition-6340-2023.pdf
XYZ-v.-state-of-Maharashtra-Bombay-HC-Writ-Petition-6340-2023.pdf
bhavenpr
 
Understanding about ITR-1 and Documentation
Understanding about ITR-1 and DocumentationUnderstanding about ITR-1 and Documentation
Understanding about ITR-1 and Documentation
CAAJAYKUMAR4
 
2015pmkemenhub163.pdf. 2015pmkemenhub163.pdf
2015pmkemenhub163.pdf. 2015pmkemenhub163.pdf2015pmkemenhub163.pdf. 2015pmkemenhub163.pdf
2015pmkemenhub163.pdf. 2015pmkemenhub163.pdf
CIkumparan
 
办理(waikato毕业证书)新西兰怀卡托大学毕业证双学位证书原版一模一样
办理(waikato毕业证书)新西兰怀卡托大学毕业证双学位证书原版一模一样办理(waikato毕业证书)新西兰怀卡托大学毕业证双学位证书原版一模一样
办理(waikato毕业证书)新西兰怀卡托大学毕业证双学位证书原版一模一样
9ib5wiwt
 
Lifting the Corporate Veil. Power Point Presentation
Lifting the Corporate Veil. Power Point PresentationLifting the Corporate Veil. Power Point Presentation
Lifting the Corporate Veil. Power Point Presentation
seri bangash
 
一比一原版麻省理工学院毕业证(MIT毕业证)成绩单如何办理
一比一原版麻省理工学院毕业证(MIT毕业证)成绩单如何办理一比一原版麻省理工学院毕业证(MIT毕业证)成绩单如何办理
一比一原版麻省理工学院毕业证(MIT毕业证)成绩单如何办理
o6ov5dqmf
 
Car Accident Injury Do I Have a Case....
Car Accident Injury Do I Have a Case....Car Accident Injury Do I Have a Case....
Car Accident Injury Do I Have a Case....
Knowyourright
 
定制(nus毕业证书)新加坡国立大学毕业证学位证书实拍图原版一模一样
定制(nus毕业证书)新加坡国立大学毕业证学位证书实拍图原版一模一样定制(nus毕业证书)新加坡国立大学毕业证学位证书实拍图原版一模一样
定制(nus毕业证书)新加坡国立大学毕业证学位证书实拍图原版一模一样
9ib5wiwt
 
Highlights_of_Bhartiya_Nyaya_Sanhita.pptx
Highlights_of_Bhartiya_Nyaya_Sanhita.pptxHighlights_of_Bhartiya_Nyaya_Sanhita.pptx
Highlights_of_Bhartiya_Nyaya_Sanhita.pptx
anjalidixit21
 
原版仿制(aut毕业证书)新西兰奥克兰理工大学毕业证文凭毕业证雅思成绩单原版一模一样
原版仿制(aut毕业证书)新西兰奥克兰理工大学毕业证文凭毕业证雅思成绩单原版一模一样原版仿制(aut毕业证书)新西兰奥克兰理工大学毕业证文凭毕业证雅思成绩单原版一模一样
原版仿制(aut毕业证书)新西兰奥克兰理工大学毕业证文凭毕业证雅思成绩单原版一模一样
9ib5wiwt
 
原版制作(PSU毕业证书)宾州州立大学公园分校毕业证学历证书一模一样
原版制作(PSU毕业证书)宾州州立大学公园分校毕业证学历证书一模一样原版制作(PSU毕业证书)宾州州立大学公园分校毕业证学历证书一模一样
原版制作(PSU毕业证书)宾州州立大学公园分校毕业证学历证书一模一样
osenwakm
 
Bharatiya Nagarik Suraksha Sanhita power.pptx
Bharatiya Nagarik Suraksha Sanhita power.pptxBharatiya Nagarik Suraksha Sanhita power.pptx
Bharatiya Nagarik Suraksha Sanhita power.pptx
ShivkumarIyer18
 
在线办理(SU毕业证书)美国雪城大学毕业证成绩单一模一样
在线办理(SU毕业证书)美国雪城大学毕业证成绩单一模一样在线办理(SU毕业证书)美国雪城大学毕业证成绩单一模一样
在线办理(SU毕业证书)美国雪城大学毕业证成绩单一模一样
osenwakm
 
1比1制作(swansea毕业证书)英国斯旺西大学毕业证学位证书托业成绩单原版一模一样
1比1制作(swansea毕业证书)英国斯旺西大学毕业证学位证书托业成绩单原版一模一样1比1制作(swansea毕业证书)英国斯旺西大学毕业证学位证书托业成绩单原版一模一样
1比1制作(swansea毕业证书)英国斯旺西大学毕业证学位证书托业成绩单原版一模一样
9ib5wiwt
 
Patenting_Innovations_in_3D_Printing_Prosthetics.pptx
Patenting_Innovations_in_3D_Printing_Prosthetics.pptxPatenting_Innovations_in_3D_Printing_Prosthetics.pptx
Patenting_Innovations_in_3D_Printing_Prosthetics.pptx
ssuser559494
 
Tax Law Notes on taxation law tax law for 10th sem
Tax Law Notes on taxation law tax law for 10th semTax Law Notes on taxation law tax law for 10th sem
Tax Law Notes on taxation law tax law for 10th sem
azizurrahaman17
 
Guide on the use of Artificial Intelligence-based tools by lawyers and law fi...
Guide on the use of Artificial Intelligence-based tools by lawyers and law fi...Guide on the use of Artificial Intelligence-based tools by lawyers and law fi...
Guide on the use of Artificial Intelligence-based tools by lawyers and law fi...
Massimo Talia
 

Recently uploaded (20)

Synopsis On Annual General Meeting/Extra Ordinary General Meeting With Ordina...
Synopsis On Annual General Meeting/Extra Ordinary General Meeting With Ordina...Synopsis On Annual General Meeting/Extra Ordinary General Meeting With Ordina...
Synopsis On Annual General Meeting/Extra Ordinary General Meeting With Ordina...
 
Matthew Professional CV experienced Government Liaison
Matthew Professional CV experienced Government LiaisonMatthew Professional CV experienced Government Liaison
Matthew Professional CV experienced Government Liaison
 
怎么购买(massey毕业证书)新西兰梅西大学毕业证学位证书注册证明信原版一模一样
怎么购买(massey毕业证书)新西兰梅西大学毕业证学位证书注册证明信原版一模一样怎么购买(massey毕业证书)新西兰梅西大学毕业证学位证书注册证明信原版一模一样
怎么购买(massey毕业证书)新西兰梅西大学毕业证学位证书注册证明信原版一模一样
 
XYZ-v.-state-of-Maharashtra-Bombay-HC-Writ-Petition-6340-2023.pdf
XYZ-v.-state-of-Maharashtra-Bombay-HC-Writ-Petition-6340-2023.pdfXYZ-v.-state-of-Maharashtra-Bombay-HC-Writ-Petition-6340-2023.pdf
XYZ-v.-state-of-Maharashtra-Bombay-HC-Writ-Petition-6340-2023.pdf
 
Understanding about ITR-1 and Documentation
Understanding about ITR-1 and DocumentationUnderstanding about ITR-1 and Documentation
Understanding about ITR-1 and Documentation
 
2015pmkemenhub163.pdf. 2015pmkemenhub163.pdf
2015pmkemenhub163.pdf. 2015pmkemenhub163.pdf2015pmkemenhub163.pdf. 2015pmkemenhub163.pdf
2015pmkemenhub163.pdf. 2015pmkemenhub163.pdf
 
办理(waikato毕业证书)新西兰怀卡托大学毕业证双学位证书原版一模一样
办理(waikato毕业证书)新西兰怀卡托大学毕业证双学位证书原版一模一样办理(waikato毕业证书)新西兰怀卡托大学毕业证双学位证书原版一模一样
办理(waikato毕业证书)新西兰怀卡托大学毕业证双学位证书原版一模一样
 
Lifting the Corporate Veil. Power Point Presentation
Lifting the Corporate Veil. Power Point PresentationLifting the Corporate Veil. Power Point Presentation
Lifting the Corporate Veil. Power Point Presentation
 
一比一原版麻省理工学院毕业证(MIT毕业证)成绩单如何办理
一比一原版麻省理工学院毕业证(MIT毕业证)成绩单如何办理一比一原版麻省理工学院毕业证(MIT毕业证)成绩单如何办理
一比一原版麻省理工学院毕业证(MIT毕业证)成绩单如何办理
 
Car Accident Injury Do I Have a Case....
Car Accident Injury Do I Have a Case....Car Accident Injury Do I Have a Case....
Car Accident Injury Do I Have a Case....
 
定制(nus毕业证书)新加坡国立大学毕业证学位证书实拍图原版一模一样
定制(nus毕业证书)新加坡国立大学毕业证学位证书实拍图原版一模一样定制(nus毕业证书)新加坡国立大学毕业证学位证书实拍图原版一模一样
定制(nus毕业证书)新加坡国立大学毕业证学位证书实拍图原版一模一样
 
Highlights_of_Bhartiya_Nyaya_Sanhita.pptx
Highlights_of_Bhartiya_Nyaya_Sanhita.pptxHighlights_of_Bhartiya_Nyaya_Sanhita.pptx
Highlights_of_Bhartiya_Nyaya_Sanhita.pptx
 
原版仿制(aut毕业证书)新西兰奥克兰理工大学毕业证文凭毕业证雅思成绩单原版一模一样
原版仿制(aut毕业证书)新西兰奥克兰理工大学毕业证文凭毕业证雅思成绩单原版一模一样原版仿制(aut毕业证书)新西兰奥克兰理工大学毕业证文凭毕业证雅思成绩单原版一模一样
原版仿制(aut毕业证书)新西兰奥克兰理工大学毕业证文凭毕业证雅思成绩单原版一模一样
 
原版制作(PSU毕业证书)宾州州立大学公园分校毕业证学历证书一模一样
原版制作(PSU毕业证书)宾州州立大学公园分校毕业证学历证书一模一样原版制作(PSU毕业证书)宾州州立大学公园分校毕业证学历证书一模一样
原版制作(PSU毕业证书)宾州州立大学公园分校毕业证学历证书一模一样
 
Bharatiya Nagarik Suraksha Sanhita power.pptx
Bharatiya Nagarik Suraksha Sanhita power.pptxBharatiya Nagarik Suraksha Sanhita power.pptx
Bharatiya Nagarik Suraksha Sanhita power.pptx
 
在线办理(SU毕业证书)美国雪城大学毕业证成绩单一模一样
在线办理(SU毕业证书)美国雪城大学毕业证成绩单一模一样在线办理(SU毕业证书)美国雪城大学毕业证成绩单一模一样
在线办理(SU毕业证书)美国雪城大学毕业证成绩单一模一样
 
1比1制作(swansea毕业证书)英国斯旺西大学毕业证学位证书托业成绩单原版一模一样
1比1制作(swansea毕业证书)英国斯旺西大学毕业证学位证书托业成绩单原版一模一样1比1制作(swansea毕业证书)英国斯旺西大学毕业证学位证书托业成绩单原版一模一样
1比1制作(swansea毕业证书)英国斯旺西大学毕业证学位证书托业成绩单原版一模一样
 
Patenting_Innovations_in_3D_Printing_Prosthetics.pptx
Patenting_Innovations_in_3D_Printing_Prosthetics.pptxPatenting_Innovations_in_3D_Printing_Prosthetics.pptx
Patenting_Innovations_in_3D_Printing_Prosthetics.pptx
 
Tax Law Notes on taxation law tax law for 10th sem
Tax Law Notes on taxation law tax law for 10th semTax Law Notes on taxation law tax law for 10th sem
Tax Law Notes on taxation law tax law for 10th sem
 
Guide on the use of Artificial Intelligence-based tools by lawyers and law fi...
Guide on the use of Artificial Intelligence-based tools by lawyers and law fi...Guide on the use of Artificial Intelligence-based tools by lawyers and law fi...
Guide on the use of Artificial Intelligence-based tools by lawyers and law fi...
 

NEC4 overview: key changes and impacts - Nottingham, September 2017

  • 1. NEC4 overview: key changes and impacts Nottingham, September 2017
  • 2. Today Martin Cannon of Browne Jacobson and Eugene Lenehan of Driver Trett will be speaking on: (i) Changes to the NEC Structure (Contract and Suite); (ii) Changes in Approach following the change to the structure; and (iii)The introduction of 2 new contracts to the Suite (the “DBO” and “Alliancing” contracts).
  • 3. NEC4 – What’s new? Overview and new contracts Martin Cannon Partner, construction team
  • 4. NEC4 – What was the key focus? • “Evolution” not “Revolution”. • To provide greater stimulus to good management; • Support new approaches to procurement which improve contract management; and • Inspire increased use of NEC in new markets and sectors.
  • 5. New additions to the NEC Suite • Following the NEC4 Suite having been published and the objective of supporting new approaches to procurement we have seen the introduction of: (i) NEC4 Design, Build, and Operate contract; and (ii) NEC4 Alliance Contract
  • 6. NEC4 Suite structure • The NEC4 Suite retains: (a) Engineering and Construction Contract (b) Framework Contract (c) Professional Service Contract (d) Supply Contract (e) Term Service Contract • The previous NEC3 Adjudicator’s Contract has been replaced by the NEC4 Dispute Resolution Contract
  • 7. Structure • The key model sections of the NEC3 have been retained (with the uniform change in language across the suite), namely the: (a) Core Clauses; (b) Secondary Option Clauses; and (c) X and Y Clauses.
  • 8. A change in process… • New provisions confirming that the programme is deemed as accepted in the event that the Project Manager fails to respond within the necessary time period. • Change to the payment regime where the contractor is to submit an application for payment prior to the “assessment date”, together with a final payment mechanism. • Changes to the CE mechanism – allowance for an additional CE where the Contractor has priced for a proposed instruction and it is not accepted, provision in the Contract Data to include further bespoke CE’s.
  • 9. A change in process… • Changes to the dispute resolution procedure within the contract, the introduction of a new tiered process. • Changes in terminology with the introduction of gender neutral wording, “client” instead of “employer”, change from “Risk Register” to “Early Warning Register”, and the introduction of “Scope” instead of “Works Information”/”Service Information”. • Changes to include clauses dealing with the transfer of benefits (i.e. assignment), confidentiality and publicity, and bribery and corruption.
  • 10. Design, Build, and Operate Contract • Broadly the overall structure of the contract is the same as the NEC4 model retaining the key core and secondary clauses. • A number of the “X” clauses have, however, been removed (options X1, X2, X5 – 7, X11 – 12, X15- 17 and X19 – 22 are not used). • In very broad terms the contract is similar to the PFI model as it governs both the construction of the building and the subsequent operational phase once the works have been completed.
  • 11. Structure: a “walkthrough" The contract follows the standard structure of the NEC4 model (albeit in a shortened form). Key provisions to note as follows: • Definitions:- some key terms; • Design; • The “Service”; and • Time.
  • 12. Definitions: some key terms • There is a “Service Manager” (in lieu of the “Project Manager” as referred to in the ECC). • The “Service Period” is the period during which the Service is carried out (this includes both the construction and operational phase). • The Contractor is to carry out the “Service” as defined in the “Scope” for the “Service Period”.
  • 13. Design • The Contractor has design responsibility – the Contractor is to carry out the design necessary for the provision of the “Service”. • The Contractor is required to submit the “particulars of its design” for approval to the Service Manager. • The Contractor cannot proceed with its works unless and to the extent that the Service Manager has accepted the design.
  • 14. The Service • The Service is set out in the Scope. • Similar to the PFI model the Contractor is to operate a quality management system. • Within the period stated in the Contract Data the Contractor is to provide to the Service Manager a “Quality Plan” and “Quality Policy Statement”. • Any instruction from the Service Manager to correct a failure to comply with the Quality Plan does not operate as a CE under the Contract.
  • 15. Time • Where a plan has not been identified in the Contract Data, the Contractor submits a first plan to the Service Manager for acceptance within the period stated in the Contract Data. • Within 2 weeks of the Contractor submitting a plan for acceptance, the Service Manager notifies the Contractor of the acceptance of the Plan or the reasons for not accepting it. • If the Service Manager does not notify acceptance or non – acceptance within the time allowed the Contractor notifies the Service Manager of the failure. If the failure continues for one week after the notification the plan is deemed accepted.
  • 16. Time: The Plan The Plan includes provisions for: (i) float, time risk allowances, H&S requirements; (ii) access dates, dates for (a) acceptances, (b) Plant and Materials, (c) information; and (iii) details of how each operation is to be carried out (including dates, equipment, resources to be used).
  • 17. Conclusion The NEC says that “The Design Build and Operate Contract allows for a much more integrated method of procurement”.
  • 18. Alliance Contract • The Alliance Contract has initially been published in consultation form and can be downloaded only at present from the NEC Website by request. • The Alliance Contract is a multi – party contract with a risk and reward model “built in”. • The liabilities are shared/managed by the Alliance (save in circumstances where there has been a wilful default by one of the alliance partners).
  • 19. Management of the Contract • The Contract is managed by the Alliance Manager (who leads the Alliance delivery team). • All decisions under the contract are to be taken by the Alliance Board (made up of representatives from each of the Alliance members and the client). The decisions of the Alliance Board have to be unanimous and bind all the parties that make up the Alliance. • The Alliance Manager reports to the Alliance Board.
  • 20. Payment • The basis of payment is Defined cost plus Fee (the same as Option E of the NEC4 ECC). Payment is to be made via a Project Bank Account. • The Alliance Manager assesses the amount due and the Client’s representative certifies. • Alliance Objectives form the basis of the performance targets against which the Alliance will be incentivised, this means that work allocation will be based around what’s best for the project (this should have the effect of reducing the likelihood of the partners seeking to hold onto one or more of the works packages).
  • 21. Compensation Events/Disputes • Alliance Manager assesses CE’s and the Alliance Board assesses the quotations. • Where there is no unanimous decision of the Alliance Board the matter is referred to the named senior representatives under the contract. • The Contract can be found at www.neccontract.com.
  • 22. NEC4 – What’s new? Core clauses, main options and secondary options Eugene Lenehan, Driver Trett
  • 23. New terminology NEC3 NEC4 Employer Client Works Information Scope Risk Register Early Warning Register Section 4 (Testing and Defects) Section 4 (Quality Management) Section 8 (Risks and Insurance) Section 8 (Liabilities and Insurance) He / his It / its X4 – Parent Company Guarantee X4 – Ultimate Holding Guarantee X12 - Partnering X12 – Multiparty collaboration
  • 24. New terminology • New definition of Subcontractor (11.1(19)) • Excludes labour suppliers
  • 25. Contractors proposals • Clause 16 – Contractor proposes changes to scope “to reduce the amount the Client pays…For Providing the Works”. • Reduced by multiplying the assessed effect of CE by the value engineering percentage. • Clause 36 – Contractor can now propose acceleration • Option X21
  • 26. Other Core Clause 1 changes • Clause 10.0 now split in two • PM rejections “in sufficient detail to enable the Contractor to correct the matter” (clause 13.4) • New clause 18: the Contractor does not do a Corrupt Act. Client may terminate (clause 91.8) • Prevention event – must stop “the whole of” the works (clause 19)
  • 27. Confidentiality • New clause 29 – “disclosure” • Restrictions on disclosing information • Contractor needs Client’s agreement to publicise the works
  • 28. Programme – deemed acceptance • Clause 31.3 amended • If PM fails to respond within 2 weeks Contractor can issue a reminder • If PM continues not to respond for 1 week the programme is deemed accepted
  • 29. Updating the programme • Clause 32 amended • “Implemented compensation events” deleted
  • 30. Quality management • New requirement for a quality management system (Clause 40) • QMS to comply with the Scope • Contractor submits for acceptance a quality policy statement and quality plan • Contractor can change quality plan with PM’s acceptance
  • 31. Payment applications • Contractor submits application for payment (clause 50.2) • “In the form stated in the Scope” • If no application issued before the assessment date the amount due is the lesser of – Amount PM assess as due; and – Amount as previous assessment date
  • 32. Review of Defined Costs (options C, D, E & F) • New clause 50.9 • Contractor can instigate review & acceptance of its Defined Cost by PM • If PM does not respond within 13 weeks (or four weeks of providing further information) Contractor’s Defined Costs and Disallowed Cost are treated as accepted
  • 33. Final assessment • New clause 53 • PM obliged to issue final assessment within four weeks of Defects Certificate (clause 53.1) • If PM fails to do this, Contractor may issues its own assessment • Final assessment becomes conclusive if not challenged by either party referring it to dispute resolution within four weeks
  • 34. SCC and Fee • Schedule of Cost Components – Subcontract costs moved to SCC. Payment of them made consistent across all Options. – ‘Working Areas overheads’ removed from SCC. – ‘Design overheads’ and ‘manufacturing and fabrication overheads’ also removed • The Fee – Now only one fee percentage
  • 35. Defined Cost and Disallowed Cost • Options A & B – Cost of preparing quotations is no longer excluded • Options C, D, E & F – New type of Disallowed Cost – adjudication costs between Contractor and Subcontractor where Contractor did not notify PM
  • 36. Compensation Events • Clause 60.1(20): Quotation for proposed instruction that is not accepted • Clause 60.1(21): Additional compensation events can be included • Clause 63.1: “dividing date” for forecast/actual costs • Clause 63.5: Delay based on Accepted Programme “current at the dividing date”
  • 37. Core Clause 8 • Liabilities and insurance • Clause 81: Contractor’s liabilities now expressly stated • Recovery of costs • Clause 84.2: Waiver of subrogation rights against Parties
  • 38. Amendments to secondary options • X4 – Ultimate holding company guarantees • X12 – Multi Party Collaboration • X15 – Contractor’s design
  • 39. New secondary options • X8 – Undertakings to the Client or Others • X9 – Transfer of Rights • X10 – Information Modelling • X11 – Termination by Client • X21 – Whole Life Cost • X22 – Early Contractor Involvement (C&E)
  • 40. Any questions? Martin Cannon E: martin.cannon@brownejacobson.com T: +44 (0)121 296 0710 Eugene Lenehan E: eugene.lenehan@drivertrett.com T: +44 (0)2476 697 977
  • 41. All information correct at time of production. The information and opinions expressed within this document are no substitute for full legal advice. It is for guidance only and illustrates the law as at the published date. If in doubt, please telephone us on 0370 270 6000. © Browne Jacobson LLP 2017 – The information contained within this document is and shall remain the property of Browne Jacobson. This document may not be reproduced without the prior consent of Browne Jacobson. 41