SlideShare a Scribd company logo
In India, Engineer's day is celebrated every year on September 15.
Sir Mokshagundam Visvesvaraya (popularly known as
Sir MV) born on 15 September 1860 was a notable Indian
engineer, thus it is celebrated on this day. "Making Indian
Engineering World-class" is the theme of Engineers Day 2014.
HAPPY
ENGINEERS
DAY
Hard work performed in a disciplined manner will in
most cases keep the worker fit and also prolong his life.
To give real service, you must add something which
cannot be bought or measured with money.
The way to build a nation is to build a good citizen. The
majority of the citizens should be efficient, of good character
and possess a reasonable high sense of duty.
INSPIRATIONAL QUOTES BY
MOKSHAGUNDAM VISVESVARAYYA
WELCOME
11013-C-056 11013-C-063 11013-C-068 11013-C-412
11212-C-049 12008-C-030 12013-C-412 12215-C-019
12215-C-049 12215-C-054 12215-C-057 12215-C-059
CASE STUDIES
DEFINITION OF CASE STUDIES
IF ANY STUDY IS DONE TO GET THE
COMPLETE PICTURE OF TOPIC OR IN DEEP
RESEARCH ON A TOPIC, GROUP, PERSON & WORK
ETC., IS KNOWN AS CASE STUDIES.
CASE STUDIES
THESE CASE STUDIES CAN BE CARRIED ON A STREAM
OF ENGG.
EXAMPLES
• ECE - NETWORK ANALYSIS
• EEE - CURCUITS
• MECHANICAL - MACHINE DESIGN
• AUTO-MOBILE - AUTOMOBILE ENGINES
IN CIVIL Engineering
• BUILDING DESIGN
• CONSTRUCTION OF HEAVY STRUCTURES
• TRANSPORTATION
ROADS RAILWAYS
• STEEL STRUCTURES
OUR EXAMPLE
NOW WE ARE GOING TO PRESENT YOU THE
CASE STUDIES THAT ARE CARRIED ON ONE OF THE GREAT
CIVIL ENGG WONDER.
NOTE:- THIS IS ONLY EXAMPLE OF 5 SLIDES FOR BETTER UNDERSTANDING OF
CASE STUDIES DEFINITION.
CASE STUDIES
OF
MARMARAY TUNNEL
1. MARMARAY TUNNEL PROJECT
Marmaray is a rail transport project in the Turkish city of Istanbul. It is
an under sea rail tunnel under the Bosphorus strait, along the sea of Marmara
from Halkali on the European side to Gebze on the Asian side.
 The Marmaray project was divided in to the two main contracts. The
Bosphorus crossing (BC1) contract covers the 13.6km and remaining is surface
portion .
 The tunnel is the deepest immersed structure (55 m below the sea level) in
the world.
 Construction of Marmaray tunnel started in 2004, with an initial target
opening date of April 2009. After multiple delays it is opened on October 2013.
 The total BC1 contract there is 9.8 km of bored tunnel, 2.4 km built
using cut-and-cover methods and the remaining 1.4 km as an immersed tunnel.
The detailed picture of the Bosphorus Crossing project.
2. MARMARAY BOSPHORUS CROSSING PROJECT SURVEYING ACTIVITY AND
GEODETIC MONITORING
Various surveying works are carried out in the construction
of Bosphorus crossing project of Marmaray tunnel.
A. Hydrological Surveying and Modeling
B. Seismic Designing of Marmaray Tunnel
C. Real Time Kinematics (R.T.K) GPS technique
D. Geodetic surface network
E. Tunnels and Geodetic Underground Network
F. Deformations and Transversal Profiles Surveys
Hydrological survey is carried out to find the alignment of
tunnel at appropriate position. For this a single-beam sonar is used.
(a) Hydrological Survey and modelling
 Single beam echo sounders use one emitting and receiving “transducer”, which
releases a series of energy pulses in the form of sound waves
 It is installed under the boat and scans the under terrain of the sea weather it is
undulating or leveled, depth also can be determined by using this
Figure of Single Beam Sonar ( Echosounder)
 The primary tectonic feature affecting the project area is the Marmaray
fault system on the South side of the project area. The main Marmara fault , exhibits
features typically associated with a strike-slip fault.
(b) Seismic Designing of the marmaray tunnel
 The figure shows us the motion and direction of tectonic plates. This is done to
assess the seismic hazards. It can be done by using G.P.S. (Global Positioning System)
 G.P.S aids us in better understanding our planet by allowing us to measure
how the surface of earth moves. Much of this motions cause earthquakes.
This is the image analyzed by the G.P.S. in detecting the tectonic plate movements
 The velocity vectors shown determined as a result of Global Positioning
System (GPS) measurements and the long term seismicity indicates that this strand
is more active.
 Therefore, for this project minimum seismic design requirements are
based on a single-level earthquake.
 Both probabilistic and deterministic approaches were used to assess the
seismic hazards. The project design basis earthquake corresponds to a MW=7.5
(moment magnitude).
Real Time Kinematic (RTK) GPS technique was effectively
used in Bathymetric map production, filling works in the sea bottom, leveling,
digging and immersion of the tube.
 RTK GPS measurement technique is used in BC1 project to immerse the
tunnels in desired position by carrying the tunnel with ships.
 In practice RTK systems use as a single base station receiver and a
number of rover units.
(c) REAL TIME KINEMATICS (RTK) GPS MEASUREMENT
TECHNIQUE AND USING ON IMMERSED TUNNEL
 The ability to determine positions with accuracy in real time within the project
area is very important therefore a carrier phase-based RTK GPS system was
established.
 The Base station broadcasts the phase of the carrier that is measured from the
satellites, and the rover units compare their own phase measurements with
those received from the base station.
 During immersion of the tunnel elements are carried out by
accurately determining the position of the immersion operation vessel
using RTK GPS installed on the operation vessel.
 A multi-beam sonar is used in monitoring the element position and shape
of the sea bottom while immersing the tunnel.
 To make the final
connection between an
element already in
position, as the next
element is lowered to
bottom the distance
between the two elements,
the axial deviation, and the
orientation deviation are
measured using ultrasonic
distance measurements
sensors installed on the
opposing end surfaces of
the elements.
In BC1 project the tunnels must be positioned, in the
horizontal and vertical dimensions, to within ±100 mm (total tolerance) of
their designed locations.
In BC1 project, 44 mm of total tolerance is reserved for
surveying error with the remaining portion of the tolerance 66 mm budgeted
for TBM (Tunnel Boring Machine) variations.
(d) GEODETIC SURFACE NETWORK
For the BC1 project a high accuracy horizontal control network was
formed in 2004 to be used in constructing structures and the above mentioned
tolerance for deformation measurements.
 The horizontal control network has two levels ; primary and secondary.
 The primary control network consists of 10 pillars and the secondary
horizontal control network consists of 17 pillars.
 These control network is laid to define the local movement.
 The GPS receivers were used for the horizontal control network
measurements with the differential techniques to guarantee an accuracy
of ±4 mm for relative position of pillars.
Standard
deviation
Maximum value Minimum value Mean Value
Latitude, ϕ 0.005 0.002 0.004
Longitude, λ 0.005 0.002 0.004
Ellipsoid height, h 0.010 0.004 0.008
Table 1 Accuracy information of horizontal control network (in m)
Difference between the first and second campaign.
Position Mean value / m
Latitude, ϕ 0.016
Longitude, λ 0.022
Ellipsoid height, h 0.040
 In 2012, a new GPS observation campaign of the surface network was
executed in order to verify the local movement of the horizontal control network.
 In this way the design of the vertical surface network consists of
66 benchmarks distributed throughout the project area by using the Wild
N3 precise leveling instrument and invar rod.
Fig of Wild N3 leveling instrument and Invar rod
In urban areas, the TBM (Tunnel Boring Machine) is most
commonly used for tunnel construction. TBM tunnel consists of several typical
phases including preparatory tasks, working shaft construction, initial set up, tunnel
construction, and removal shaft construction.
The TBM dig the three bored tunnels in BC1 project.
Tunnel 1 on the European continent : 2345 m
Tube 2 on the Asian continent : 2150 m
Tube 3 on the Asian continent : 4620 m
(e) TUNNELS AND GEODETIC UNDER GROUND NETWORK
The detailed picture of the Bosphorus Crossing project.
The TBM is guided with the Tacs guidance system based
on the tunnel control network.
 The Tacs guidance system continuously define the TBM position and
compares it with the design tunnel axis.
 The Tacs system receives input measurements from a laser theodolite,
which is placed on a bracket attached to the left upper wall of the tunnel. The
guidance station bracket is incrementally moved forward as the TBM advances
In this section, the studies undertaken concerning tunnel 1 is examined in
detail.
 In order to perform redirection using the laser theodolite within the
forecast tolerance, the geodetic network within the tunnel should be very accurately
positioned.
 The effect of lateral refraction and lateral temperature gradient can produce
a severe error especially in a tunnel environment.
 Therefore geodetic underground network formed for tunnel 1 consists of a
total of 109 benchmarks, 49 benchmarks in Tube 1 and 60 in Tube 2. The
benchmarks in tunnel were located at intervals of approximately 50 m.
Leica DNA03 level
Instruments used in tunnels geodetic
underground network construction
 Leica DNA03
levels and leica TC1201
total stations were used for
the leveling and angle-
distance measurements.
 The accuracy of
the measurements is
typically ±0.3 mm/km for
precise leveling and 1” for
angles and 1 mm +2 ppm
for distances with total
stations.
Image of Leica TC 1201 Total
station.
The network adjustment was
also achieved using HANNA
software developed by the
Institute of Geodesy, University
of Hannover.
The construction and operation of tunnel projects can result in a
damage to surfaces or sub surface structures. In a metropolitan city like Istanbul
where housing and historical structures are very intensive. Hence it is very
important to determine the deformations on the surface and in the structures due to
bored tunnels.
Deformations in tunnel borings occur in two ways;
1. Deformations on the surface due to volume loss
2. Deformations due to the pressure on the tunnel perimeter applied by the mass
over the tunnel
(f) DEFORMATIONS AND TRANSVERSAL PROFILES SURVEYS
1. Deformations on the surface due to volume loss
The surface settlement trough assumes a bell-shaped curve centered on the
tunnel axis. The surface settlement is determined as follows.
 As-built surveys are prepared after the completion of a construction project. This survey
shows the as-built locations of improvements and utilities as opposed to the designed location.
The
Transversal
Profile
survey
 In this project the reference profile area was calculated as 38.046 m². According to this
information the over profile and under profile areas were determined for each transversal profile.
 The profile monitoring system consists of an optical technique using a high specification
robotic total station (Leica TCA 1201). The transversal profile survey was executed every 7.5 m of the
tunnel. The Leica TMS (Tunnel Measurement System) is used for data processing, as shown in fig.
So this is the Case Studies of Marmaray
tunnel BC1 project
After the Marmaray project Turkey is starting a new project by using
the same survey as mentioned above. It is similar to the BC1 project. It is signed
to implementation on 26 Feb 2011.
Special Thanks To R. Venu Gopal Sir

More Related Content

What's hot

Presentation about Ircon's SGEDT project in Malaysia.
Presentation about Ircon's SGEDT project in Malaysia.Presentation about Ircon's SGEDT project in Malaysia.
Presentation about Ircon's SGEDT project in Malaysia.
Hitesh Khanna
 
Tunnel’s
Tunnel’sTunnel’s
Tunnel’s
Javed Syed
 
Under ground railway
Under ground railwayUnder ground railway
Under ground railway
sandipjagdale2008
 
Effect of underground tunnelling by (TBM) on foundations of existing structures
Effect of underground tunnelling by (TBM) on foundations of existing structuresEffect of underground tunnelling by (TBM) on foundations of existing structures
Effect of underground tunnelling by (TBM) on foundations of existing structures
Kishor Ade
 
Lightening Ventiltion Dust control Safety And Safety in tunnel
Lightening Ventiltion Dust control Safety And Safety in tunnelLightening Ventiltion Dust control Safety And Safety in tunnel
Lightening Ventiltion Dust control Safety And Safety in tunnel
Abhishek Kansara
 
Tunnel example for road project by Malyar Talash
Tunnel example for road project by Malyar TalashTunnel example for road project by Malyar Talash
Tunnel example for road project by Malyar Talash
Malyar Talash
 
Michalis presentation_2015
Michalis presentation_2015Michalis presentation_2015
Michalis presentation_2015ILIAS MICHALIS
 
Site visit presentation: Kwun Tong line extension
Site visit presentation: Kwun Tong line extensionSite visit presentation: Kwun Tong line extension
Site visit presentation: Kwun Tong line extension
Association for Project Management
 
20100514 pipe arch presentation to iem may 2010
20100514 pipe arch presentation to iem   may 201020100514 pipe arch presentation to iem   may 2010
20100514 pipe arch presentation to iem may 2010forcepraxeum
 
Tunnel making methods and tunnel boring machine
Tunnel making methods and tunnel boring machine Tunnel making methods and tunnel boring machine
Tunnel making methods and tunnel boring machine mohammadsalikali
 
Tunnel boring machine
Tunnel boring machineTunnel boring machine
Tunnel boring machine
rutuldave
 
7. TUNNEL ENGINEERING
7. TUNNEL ENGINEERING7. TUNNEL ENGINEERING
7. TUNNEL ENGINEERING
VATSAL PATEL
 
Study of tunnel engineering
Study of tunnel engineeringStudy of tunnel engineering
Study of tunnel engineering
Adil Shaikh
 
Pipe Jacking
Pipe JackingPipe Jacking
Pipe Jacking
Himanshu Gupta
 
RAILWAYS,HARBOR, TUNNEL ENGINEERING
RAILWAYS,HARBOR, TUNNEL ENGINEERINGRAILWAYS,HARBOR, TUNNEL ENGINEERING
RAILWAYS,HARBOR, TUNNEL ENGINEERING
bhavin_pindoriya
 
Atal Rohtang Tunnel - construction process ,challenges and features
Atal Rohtang Tunnel - construction process ,challenges and featuresAtal Rohtang Tunnel - construction process ,challenges and features
Atal Rohtang Tunnel - construction process ,challenges and features
Bimenpreet Kaur
 
Mihalis presentation final 10092011
Mihalis presentation final 10092011Mihalis presentation final 10092011
Mihalis presentation final 10092011ILIAS MICHALIS
 
Tunneling
TunnelingTunneling
Tunneling
Avdhesh Mathur
 
Execution of 680 m long tunnel ensuring safety of the adjoining rail tunnel w...
Execution of 680 m long tunnel ensuring safety of the adjoining rail tunnel w...Execution of 680 m long tunnel ensuring safety of the adjoining rail tunnel w...
Execution of 680 m long tunnel ensuring safety of the adjoining rail tunnel w...
Rajesh Prasad
 

What's hot (20)

Presentation about Ircon's SGEDT project in Malaysia.
Presentation about Ircon's SGEDT project in Malaysia.Presentation about Ircon's SGEDT project in Malaysia.
Presentation about Ircon's SGEDT project in Malaysia.
 
Tunnel’s
Tunnel’sTunnel’s
Tunnel’s
 
Under ground railway
Under ground railwayUnder ground railway
Under ground railway
 
Effect of underground tunnelling by (TBM) on foundations of existing structures
Effect of underground tunnelling by (TBM) on foundations of existing structuresEffect of underground tunnelling by (TBM) on foundations of existing structures
Effect of underground tunnelling by (TBM) on foundations of existing structures
 
Lightening Ventiltion Dust control Safety And Safety in tunnel
Lightening Ventiltion Dust control Safety And Safety in tunnelLightening Ventiltion Dust control Safety And Safety in tunnel
Lightening Ventiltion Dust control Safety And Safety in tunnel
 
Tunnel example for road project by Malyar Talash
Tunnel example for road project by Malyar TalashTunnel example for road project by Malyar Talash
Tunnel example for road project by Malyar Talash
 
Michalis presentation_2015
Michalis presentation_2015Michalis presentation_2015
Michalis presentation_2015
 
Site visit presentation: Kwun Tong line extension
Site visit presentation: Kwun Tong line extensionSite visit presentation: Kwun Tong line extension
Site visit presentation: Kwun Tong line extension
 
20100514 pipe arch presentation to iem may 2010
20100514 pipe arch presentation to iem   may 201020100514 pipe arch presentation to iem   may 2010
20100514 pipe arch presentation to iem may 2010
 
Tunnel making methods and tunnel boring machine
Tunnel making methods and tunnel boring machine Tunnel making methods and tunnel boring machine
Tunnel making methods and tunnel boring machine
 
Tunnel boring machine
Tunnel boring machineTunnel boring machine
Tunnel boring machine
 
7. TUNNEL ENGINEERING
7. TUNNEL ENGINEERING7. TUNNEL ENGINEERING
7. TUNNEL ENGINEERING
 
Tunnel construction
Tunnel constructionTunnel construction
Tunnel construction
 
Study of tunnel engineering
Study of tunnel engineeringStudy of tunnel engineering
Study of tunnel engineering
 
Pipe Jacking
Pipe JackingPipe Jacking
Pipe Jacking
 
RAILWAYS,HARBOR, TUNNEL ENGINEERING
RAILWAYS,HARBOR, TUNNEL ENGINEERINGRAILWAYS,HARBOR, TUNNEL ENGINEERING
RAILWAYS,HARBOR, TUNNEL ENGINEERING
 
Atal Rohtang Tunnel - construction process ,challenges and features
Atal Rohtang Tunnel - construction process ,challenges and featuresAtal Rohtang Tunnel - construction process ,challenges and features
Atal Rohtang Tunnel - construction process ,challenges and features
 
Mihalis presentation final 10092011
Mihalis presentation final 10092011Mihalis presentation final 10092011
Mihalis presentation final 10092011
 
Tunneling
TunnelingTunneling
Tunneling
 
Execution of 680 m long tunnel ensuring safety of the adjoining rail tunnel w...
Execution of 680 m long tunnel ensuring safety of the adjoining rail tunnel w...Execution of 680 m long tunnel ensuring safety of the adjoining rail tunnel w...
Execution of 680 m long tunnel ensuring safety of the adjoining rail tunnel w...
 

Similar to Case studies of surveys involved in Railway Tunnel constructed under sea.

DUAL BAND GNSS ANTENNA PHASE CENTER CHARACTERIZATION FOR AUTOMOTIVE APPLICATIONS
DUAL BAND GNSS ANTENNA PHASE CENTER CHARACTERIZATION FOR AUTOMOTIVE APPLICATIONSDUAL BAND GNSS ANTENNA PHASE CENTER CHARACTERIZATION FOR AUTOMOTIVE APPLICATIONS
DUAL BAND GNSS ANTENNA PHASE CENTER CHARACTERIZATION FOR AUTOMOTIVE APPLICATIONS
jantjournal
 
DUAL BAND GNSS ANTENNA PHASE CENTER CHARACTERIZATION FOR AUTOMOTIVE APPLICATIONS
DUAL BAND GNSS ANTENNA PHASE CENTER CHARACTERIZATION FOR AUTOMOTIVE APPLICATIONSDUAL BAND GNSS ANTENNA PHASE CENTER CHARACTERIZATION FOR AUTOMOTIVE APPLICATIONS
DUAL BAND GNSS ANTENNA PHASE CENTER CHARACTERIZATION FOR AUTOMOTIVE APPLICATIONS
jantjournal
 
DUAL BAND GNSS ANTENNA PHASE CENTER CHARACTERIZATION FOR AUTOMOTIVE APPLICATIONS
DUAL BAND GNSS ANTENNA PHASE CENTER CHARACTERIZATION FOR AUTOMOTIVE APPLICATIONSDUAL BAND GNSS ANTENNA PHASE CENTER CHARACTERIZATION FOR AUTOMOTIVE APPLICATIONS
DUAL BAND GNSS ANTENNA PHASE CENTER CHARACTERIZATION FOR AUTOMOTIVE APPLICATIONS
jantjournal
 
DUAL BAND GNSS ANTENNA PHASE CENTER CHARACTERIZATION FOR AUTOMOTIVE APPLICATIONS
DUAL BAND GNSS ANTENNA PHASE CENTER CHARACTERIZATION FOR AUTOMOTIVE APPLICATIONSDUAL BAND GNSS ANTENNA PHASE CENTER CHARACTERIZATION FOR AUTOMOTIVE APPLICATIONS
DUAL BAND GNSS ANTENNA PHASE CENTER CHARACTERIZATION FOR AUTOMOTIVE APPLICATIONS
jantjournal
 
DUAL BAND GNSS ANTENNA PHASE CENTER CHARACTERIZATION FOR AUTOMOTIVE APPLICATIONS
DUAL BAND GNSS ANTENNA PHASE CENTER CHARACTERIZATION FOR AUTOMOTIVE APPLICATIONSDUAL BAND GNSS ANTENNA PHASE CENTER CHARACTERIZATION FOR AUTOMOTIVE APPLICATIONS
DUAL BAND GNSS ANTENNA PHASE CENTER CHARACTERIZATION FOR AUTOMOTIVE APPLICATIONS
jantjournal
 
DUAL BAND GNSS ANTENNA PHASE CENTER CHARACTERIZATION FOR AUTOMOTIVE APPLICATIONS
DUAL BAND GNSS ANTENNA PHASE CENTER CHARACTERIZATION FOR AUTOMOTIVE APPLICATIONSDUAL BAND GNSS ANTENNA PHASE CENTER CHARACTERIZATION FOR AUTOMOTIVE APPLICATIONS
DUAL BAND GNSS ANTENNA PHASE CENTER CHARACTERIZATION FOR AUTOMOTIVE APPLICATIONS
jantjournal
 
DUAL BAND GNSS ANTENNA PHASE CENTER CHARACTERIZATION FOR AUTOMOTIVE APPLICATIONS
DUAL BAND GNSS ANTENNA PHASE CENTER CHARACTERIZATION FOR AUTOMOTIVE APPLICATIONSDUAL BAND GNSS ANTENNA PHASE CENTER CHARACTERIZATION FOR AUTOMOTIVE APPLICATIONS
DUAL BAND GNSS ANTENNA PHASE CENTER CHARACTERIZATION FOR AUTOMOTIVE APPLICATIONS
jantjournal
 
Engineering surveying-ii
Engineering surveying-iiEngineering surveying-ii
Engineering surveying-ii
Marvin Ken
 
B04920920
B04920920B04920920
B04920920
IOSR-JEN
 
Design Methodology for Feasible Railway Alignment
Design Methodology for Feasible Railway AlignmentDesign Methodology for Feasible Railway Alignment
Design Methodology for Feasible Railway Alignment
IRJET Journal
 
group-3-a21-traverse-report.pdf
group-3-a21-traverse-report.pdfgroup-3-a21-traverse-report.pdf
group-3-a21-traverse-report.pdf
NkosiAnsari
 
A Fully Automated System for Monitoring Pit Wall Displacements
 A Fully Automated System for Monitoring Pit Wall Displacements A Fully Automated System for Monitoring Pit Wall Displacements
A Fully Automated System for Monitoring Pit Wall Displacements
JOSE ESPEJO VASQUEZ
 
Analysis of stability of rock column between cut & cover Metro Station and NA...
Analysis of stability of rock column between cut & cover Metro Station and NA...Analysis of stability of rock column between cut & cover Metro Station and NA...
Analysis of stability of rock column between cut & cover Metro Station and NA...
IRJET Journal
 
Wall Station Surveys
Wall Station SurveysWall Station Surveys
Wall Station Surveys
brett_grocock
 
microgravity REPORT@CSL LRT STN edited II_MMC-GAMUDA-signed.pdf
microgravity REPORT@CSL LRT STN edited II_MMC-GAMUDA-signed.pdfmicrogravity REPORT@CSL LRT STN edited II_MMC-GAMUDA-signed.pdf
microgravity REPORT@CSL LRT STN edited II_MMC-GAMUDA-signed.pdf
divyapriya balasubramani
 
Tower verticality for Tall Building using DGPS
Tower verticality for Tall Building using DGPSTower verticality for Tall Building using DGPS
Tower verticality for Tall Building using DGPS
AM Publications
 
Iaetsd concepts of surveying with totalstation-a latest
Iaetsd concepts of surveying with totalstation-a latestIaetsd concepts of surveying with totalstation-a latest
Iaetsd concepts of surveying with totalstation-a latest
Iaetsd Iaetsd
 
ALEEM MALIK
ALEEM MALIKALEEM MALIK
ALEEM MALIK
AbdulAleem145
 
Study of Dynamic Analysis for Immersed Tube Tunnel
Study of Dynamic Analysis for Immersed Tube TunnelStudy of Dynamic Analysis for Immersed Tube Tunnel
Study of Dynamic Analysis for Immersed Tube Tunnel
ijceronline
 
Development of Methodology for Determining Earth Work Volume Using Combined S...
Development of Methodology for Determining Earth Work Volume Using Combined S...Development of Methodology for Determining Earth Work Volume Using Combined S...
Development of Methodology for Determining Earth Work Volume Using Combined S...
IJMER
 

Similar to Case studies of surveys involved in Railway Tunnel constructed under sea. (20)

DUAL BAND GNSS ANTENNA PHASE CENTER CHARACTERIZATION FOR AUTOMOTIVE APPLICATIONS
DUAL BAND GNSS ANTENNA PHASE CENTER CHARACTERIZATION FOR AUTOMOTIVE APPLICATIONSDUAL BAND GNSS ANTENNA PHASE CENTER CHARACTERIZATION FOR AUTOMOTIVE APPLICATIONS
DUAL BAND GNSS ANTENNA PHASE CENTER CHARACTERIZATION FOR AUTOMOTIVE APPLICATIONS
 
DUAL BAND GNSS ANTENNA PHASE CENTER CHARACTERIZATION FOR AUTOMOTIVE APPLICATIONS
DUAL BAND GNSS ANTENNA PHASE CENTER CHARACTERIZATION FOR AUTOMOTIVE APPLICATIONSDUAL BAND GNSS ANTENNA PHASE CENTER CHARACTERIZATION FOR AUTOMOTIVE APPLICATIONS
DUAL BAND GNSS ANTENNA PHASE CENTER CHARACTERIZATION FOR AUTOMOTIVE APPLICATIONS
 
DUAL BAND GNSS ANTENNA PHASE CENTER CHARACTERIZATION FOR AUTOMOTIVE APPLICATIONS
DUAL BAND GNSS ANTENNA PHASE CENTER CHARACTERIZATION FOR AUTOMOTIVE APPLICATIONSDUAL BAND GNSS ANTENNA PHASE CENTER CHARACTERIZATION FOR AUTOMOTIVE APPLICATIONS
DUAL BAND GNSS ANTENNA PHASE CENTER CHARACTERIZATION FOR AUTOMOTIVE APPLICATIONS
 
DUAL BAND GNSS ANTENNA PHASE CENTER CHARACTERIZATION FOR AUTOMOTIVE APPLICATIONS
DUAL BAND GNSS ANTENNA PHASE CENTER CHARACTERIZATION FOR AUTOMOTIVE APPLICATIONSDUAL BAND GNSS ANTENNA PHASE CENTER CHARACTERIZATION FOR AUTOMOTIVE APPLICATIONS
DUAL BAND GNSS ANTENNA PHASE CENTER CHARACTERIZATION FOR AUTOMOTIVE APPLICATIONS
 
DUAL BAND GNSS ANTENNA PHASE CENTER CHARACTERIZATION FOR AUTOMOTIVE APPLICATIONS
DUAL BAND GNSS ANTENNA PHASE CENTER CHARACTERIZATION FOR AUTOMOTIVE APPLICATIONSDUAL BAND GNSS ANTENNA PHASE CENTER CHARACTERIZATION FOR AUTOMOTIVE APPLICATIONS
DUAL BAND GNSS ANTENNA PHASE CENTER CHARACTERIZATION FOR AUTOMOTIVE APPLICATIONS
 
DUAL BAND GNSS ANTENNA PHASE CENTER CHARACTERIZATION FOR AUTOMOTIVE APPLICATIONS
DUAL BAND GNSS ANTENNA PHASE CENTER CHARACTERIZATION FOR AUTOMOTIVE APPLICATIONSDUAL BAND GNSS ANTENNA PHASE CENTER CHARACTERIZATION FOR AUTOMOTIVE APPLICATIONS
DUAL BAND GNSS ANTENNA PHASE CENTER CHARACTERIZATION FOR AUTOMOTIVE APPLICATIONS
 
DUAL BAND GNSS ANTENNA PHASE CENTER CHARACTERIZATION FOR AUTOMOTIVE APPLICATIONS
DUAL BAND GNSS ANTENNA PHASE CENTER CHARACTERIZATION FOR AUTOMOTIVE APPLICATIONSDUAL BAND GNSS ANTENNA PHASE CENTER CHARACTERIZATION FOR AUTOMOTIVE APPLICATIONS
DUAL BAND GNSS ANTENNA PHASE CENTER CHARACTERIZATION FOR AUTOMOTIVE APPLICATIONS
 
Engineering surveying-ii
Engineering surveying-iiEngineering surveying-ii
Engineering surveying-ii
 
B04920920
B04920920B04920920
B04920920
 
Design Methodology for Feasible Railway Alignment
Design Methodology for Feasible Railway AlignmentDesign Methodology for Feasible Railway Alignment
Design Methodology for Feasible Railway Alignment
 
group-3-a21-traverse-report.pdf
group-3-a21-traverse-report.pdfgroup-3-a21-traverse-report.pdf
group-3-a21-traverse-report.pdf
 
A Fully Automated System for Monitoring Pit Wall Displacements
 A Fully Automated System for Monitoring Pit Wall Displacements A Fully Automated System for Monitoring Pit Wall Displacements
A Fully Automated System for Monitoring Pit Wall Displacements
 
Analysis of stability of rock column between cut & cover Metro Station and NA...
Analysis of stability of rock column between cut & cover Metro Station and NA...Analysis of stability of rock column between cut & cover Metro Station and NA...
Analysis of stability of rock column between cut & cover Metro Station and NA...
 
Wall Station Surveys
Wall Station SurveysWall Station Surveys
Wall Station Surveys
 
microgravity REPORT@CSL LRT STN edited II_MMC-GAMUDA-signed.pdf
microgravity REPORT@CSL LRT STN edited II_MMC-GAMUDA-signed.pdfmicrogravity REPORT@CSL LRT STN edited II_MMC-GAMUDA-signed.pdf
microgravity REPORT@CSL LRT STN edited II_MMC-GAMUDA-signed.pdf
 
Tower verticality for Tall Building using DGPS
Tower verticality for Tall Building using DGPSTower verticality for Tall Building using DGPS
Tower verticality for Tall Building using DGPS
 
Iaetsd concepts of surveying with totalstation-a latest
Iaetsd concepts of surveying with totalstation-a latestIaetsd concepts of surveying with totalstation-a latest
Iaetsd concepts of surveying with totalstation-a latest
 
ALEEM MALIK
ALEEM MALIKALEEM MALIK
ALEEM MALIK
 
Study of Dynamic Analysis for Immersed Tube Tunnel
Study of Dynamic Analysis for Immersed Tube TunnelStudy of Dynamic Analysis for Immersed Tube Tunnel
Study of Dynamic Analysis for Immersed Tube Tunnel
 
Development of Methodology for Determining Earth Work Volume Using Combined S...
Development of Methodology for Determining Earth Work Volume Using Combined S...Development of Methodology for Determining Earth Work Volume Using Combined S...
Development of Methodology for Determining Earth Work Volume Using Combined S...
 

Recently uploaded

Honest Reviews of Tim Han LMA Course Program.pptx
Honest Reviews of Tim Han LMA Course Program.pptxHonest Reviews of Tim Han LMA Course Program.pptx
Honest Reviews of Tim Han LMA Course Program.pptx
timhan337
 
Guidance_and_Counselling.pdf B.Ed. 4th Semester
Guidance_and_Counselling.pdf B.Ed. 4th SemesterGuidance_and_Counselling.pdf B.Ed. 4th Semester
Guidance_and_Counselling.pdf B.Ed. 4th Semester
Atul Kumar Singh
 
Operation Blue Star - Saka Neela Tara
Operation Blue Star   -  Saka Neela TaraOperation Blue Star   -  Saka Neela Tara
Operation Blue Star - Saka Neela Tara
Balvir Singh
 
Palestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptxPalestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptx
RaedMohamed3
 
Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345
beazzy04
 
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup   New Member Orientation and Q&A (May 2024).pdfWelcome to TechSoup   New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
TechSoup
 
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCECLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
BhavyaRajput3
 
Synthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptxSynthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptx
Pavel ( NSTU)
 
Embracing GenAI - A Strategic Imperative
Embracing GenAI - A Strategic ImperativeEmbracing GenAI - A Strategic Imperative
Embracing GenAI - A Strategic Imperative
Peter Windle
 
The French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free downloadThe French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free download
Vivekanand Anglo Vedic Academy
 
special B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdfspecial B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdf
Special education needs
 
Unit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdfUnit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdf
Thiyagu K
 
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
EugeneSaldivar
 
Thesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.pptThesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.ppt
EverAndrsGuerraGuerr
 
The Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptxThe Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptx
DhatriParmar
 
The Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official PublicationThe Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official Publication
Delapenabediema
 
CACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdfCACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdf
camakaiclarkmusic
 
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
Nguyen Thanh Tu Collection
 
1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx
JosvitaDsouza2
 
Francesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptxFrancesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptx
EduSkills OECD
 

Recently uploaded (20)

Honest Reviews of Tim Han LMA Course Program.pptx
Honest Reviews of Tim Han LMA Course Program.pptxHonest Reviews of Tim Han LMA Course Program.pptx
Honest Reviews of Tim Han LMA Course Program.pptx
 
Guidance_and_Counselling.pdf B.Ed. 4th Semester
Guidance_and_Counselling.pdf B.Ed. 4th SemesterGuidance_and_Counselling.pdf B.Ed. 4th Semester
Guidance_and_Counselling.pdf B.Ed. 4th Semester
 
Operation Blue Star - Saka Neela Tara
Operation Blue Star   -  Saka Neela TaraOperation Blue Star   -  Saka Neela Tara
Operation Blue Star - Saka Neela Tara
 
Palestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptxPalestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptx
 
Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345
 
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup   New Member Orientation and Q&A (May 2024).pdfWelcome to TechSoup   New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
 
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCECLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
 
Synthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptxSynthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptx
 
Embracing GenAI - A Strategic Imperative
Embracing GenAI - A Strategic ImperativeEmbracing GenAI - A Strategic Imperative
Embracing GenAI - A Strategic Imperative
 
The French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free downloadThe French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free download
 
special B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdfspecial B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdf
 
Unit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdfUnit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdf
 
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
 
Thesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.pptThesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.ppt
 
The Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptxThe Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptx
 
The Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official PublicationThe Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official Publication
 
CACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdfCACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdf
 
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
 
1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx
 
Francesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptxFrancesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptx
 

Case studies of surveys involved in Railway Tunnel constructed under sea.

  • 1. In India, Engineer's day is celebrated every year on September 15. Sir Mokshagundam Visvesvaraya (popularly known as Sir MV) born on 15 September 1860 was a notable Indian engineer, thus it is celebrated on this day. "Making Indian Engineering World-class" is the theme of Engineers Day 2014. HAPPY ENGINEERS DAY
  • 2. Hard work performed in a disciplined manner will in most cases keep the worker fit and also prolong his life. To give real service, you must add something which cannot be bought or measured with money. The way to build a nation is to build a good citizen. The majority of the citizens should be efficient, of good character and possess a reasonable high sense of duty. INSPIRATIONAL QUOTES BY MOKSHAGUNDAM VISVESVARAYYA
  • 3. WELCOME 11013-C-056 11013-C-063 11013-C-068 11013-C-412 11212-C-049 12008-C-030 12013-C-412 12215-C-019 12215-C-049 12215-C-054 12215-C-057 12215-C-059
  • 5. DEFINITION OF CASE STUDIES IF ANY STUDY IS DONE TO GET THE COMPLETE PICTURE OF TOPIC OR IN DEEP RESEARCH ON A TOPIC, GROUP, PERSON & WORK ETC., IS KNOWN AS CASE STUDIES.
  • 6. CASE STUDIES THESE CASE STUDIES CAN BE CARRIED ON A STREAM OF ENGG.
  • 7. EXAMPLES • ECE - NETWORK ANALYSIS • EEE - CURCUITS • MECHANICAL - MACHINE DESIGN • AUTO-MOBILE - AUTOMOBILE ENGINES
  • 8. IN CIVIL Engineering • BUILDING DESIGN
  • 9. • CONSTRUCTION OF HEAVY STRUCTURES
  • 12. OUR EXAMPLE NOW WE ARE GOING TO PRESENT YOU THE CASE STUDIES THAT ARE CARRIED ON ONE OF THE GREAT CIVIL ENGG WONDER. NOTE:- THIS IS ONLY EXAMPLE OF 5 SLIDES FOR BETTER UNDERSTANDING OF CASE STUDIES DEFINITION.
  • 14. 1. MARMARAY TUNNEL PROJECT Marmaray is a rail transport project in the Turkish city of Istanbul. It is an under sea rail tunnel under the Bosphorus strait, along the sea of Marmara from Halkali on the European side to Gebze on the Asian side.  The Marmaray project was divided in to the two main contracts. The Bosphorus crossing (BC1) contract covers the 13.6km and remaining is surface portion .  The tunnel is the deepest immersed structure (55 m below the sea level) in the world.  Construction of Marmaray tunnel started in 2004, with an initial target opening date of April 2009. After multiple delays it is opened on October 2013.
  • 15.  The total BC1 contract there is 9.8 km of bored tunnel, 2.4 km built using cut-and-cover methods and the remaining 1.4 km as an immersed tunnel.
  • 16. The detailed picture of the Bosphorus Crossing project.
  • 17. 2. MARMARAY BOSPHORUS CROSSING PROJECT SURVEYING ACTIVITY AND GEODETIC MONITORING Various surveying works are carried out in the construction of Bosphorus crossing project of Marmaray tunnel. A. Hydrological Surveying and Modeling B. Seismic Designing of Marmaray Tunnel C. Real Time Kinematics (R.T.K) GPS technique D. Geodetic surface network E. Tunnels and Geodetic Underground Network F. Deformations and Transversal Profiles Surveys
  • 18. Hydrological survey is carried out to find the alignment of tunnel at appropriate position. For this a single-beam sonar is used. (a) Hydrological Survey and modelling
  • 19.  Single beam echo sounders use one emitting and receiving “transducer”, which releases a series of energy pulses in the form of sound waves  It is installed under the boat and scans the under terrain of the sea weather it is undulating or leveled, depth also can be determined by using this Figure of Single Beam Sonar ( Echosounder)
  • 20.
  • 21.
  • 22.  The primary tectonic feature affecting the project area is the Marmaray fault system on the South side of the project area. The main Marmara fault , exhibits features typically associated with a strike-slip fault. (b) Seismic Designing of the marmaray tunnel
  • 23.  The figure shows us the motion and direction of tectonic plates. This is done to assess the seismic hazards. It can be done by using G.P.S. (Global Positioning System)
  • 24.  G.P.S aids us in better understanding our planet by allowing us to measure how the surface of earth moves. Much of this motions cause earthquakes. This is the image analyzed by the G.P.S. in detecting the tectonic plate movements
  • 25.  The velocity vectors shown determined as a result of Global Positioning System (GPS) measurements and the long term seismicity indicates that this strand is more active.
  • 26.  Therefore, for this project minimum seismic design requirements are based on a single-level earthquake.  Both probabilistic and deterministic approaches were used to assess the seismic hazards. The project design basis earthquake corresponds to a MW=7.5 (moment magnitude).
  • 27. Real Time Kinematic (RTK) GPS technique was effectively used in Bathymetric map production, filling works in the sea bottom, leveling, digging and immersion of the tube.  RTK GPS measurement technique is used in BC1 project to immerse the tunnels in desired position by carrying the tunnel with ships.  In practice RTK systems use as a single base station receiver and a number of rover units. (c) REAL TIME KINEMATICS (RTK) GPS MEASUREMENT TECHNIQUE AND USING ON IMMERSED TUNNEL
  • 28.  The ability to determine positions with accuracy in real time within the project area is very important therefore a carrier phase-based RTK GPS system was established.  The Base station broadcasts the phase of the carrier that is measured from the satellites, and the rover units compare their own phase measurements with those received from the base station.
  • 29.  During immersion of the tunnel elements are carried out by accurately determining the position of the immersion operation vessel using RTK GPS installed on the operation vessel.
  • 30.  A multi-beam sonar is used in monitoring the element position and shape of the sea bottom while immersing the tunnel.
  • 31.  To make the final connection between an element already in position, as the next element is lowered to bottom the distance between the two elements, the axial deviation, and the orientation deviation are measured using ultrasonic distance measurements sensors installed on the opposing end surfaces of the elements.
  • 32. In BC1 project the tunnels must be positioned, in the horizontal and vertical dimensions, to within ±100 mm (total tolerance) of their designed locations. In BC1 project, 44 mm of total tolerance is reserved for surveying error with the remaining portion of the tolerance 66 mm budgeted for TBM (Tunnel Boring Machine) variations. (d) GEODETIC SURFACE NETWORK
  • 33. For the BC1 project a high accuracy horizontal control network was formed in 2004 to be used in constructing structures and the above mentioned tolerance for deformation measurements.
  • 34.  The horizontal control network has two levels ; primary and secondary.  The primary control network consists of 10 pillars and the secondary horizontal control network consists of 17 pillars.  These control network is laid to define the local movement.  The GPS receivers were used for the horizontal control network measurements with the differential techniques to guarantee an accuracy of ±4 mm for relative position of pillars. Standard deviation Maximum value Minimum value Mean Value Latitude, ϕ 0.005 0.002 0.004 Longitude, λ 0.005 0.002 0.004 Ellipsoid height, h 0.010 0.004 0.008 Table 1 Accuracy information of horizontal control network (in m)
  • 35. Difference between the first and second campaign. Position Mean value / m Latitude, ϕ 0.016 Longitude, λ 0.022 Ellipsoid height, h 0.040  In 2012, a new GPS observation campaign of the surface network was executed in order to verify the local movement of the horizontal control network.
  • 36.  In this way the design of the vertical surface network consists of 66 benchmarks distributed throughout the project area by using the Wild N3 precise leveling instrument and invar rod. Fig of Wild N3 leveling instrument and Invar rod
  • 37. In urban areas, the TBM (Tunnel Boring Machine) is most commonly used for tunnel construction. TBM tunnel consists of several typical phases including preparatory tasks, working shaft construction, initial set up, tunnel construction, and removal shaft construction. The TBM dig the three bored tunnels in BC1 project. Tunnel 1 on the European continent : 2345 m Tube 2 on the Asian continent : 2150 m Tube 3 on the Asian continent : 4620 m (e) TUNNELS AND GEODETIC UNDER GROUND NETWORK
  • 38. The detailed picture of the Bosphorus Crossing project.
  • 39. The TBM is guided with the Tacs guidance system based on the tunnel control network.  The Tacs guidance system continuously define the TBM position and compares it with the design tunnel axis.
  • 40.  The Tacs system receives input measurements from a laser theodolite, which is placed on a bracket attached to the left upper wall of the tunnel. The guidance station bracket is incrementally moved forward as the TBM advances
  • 41. In this section, the studies undertaken concerning tunnel 1 is examined in detail.  In order to perform redirection using the laser theodolite within the forecast tolerance, the geodetic network within the tunnel should be very accurately positioned.  The effect of lateral refraction and lateral temperature gradient can produce a severe error especially in a tunnel environment.  Therefore geodetic underground network formed for tunnel 1 consists of a total of 109 benchmarks, 49 benchmarks in Tube 1 and 60 in Tube 2. The benchmarks in tunnel were located at intervals of approximately 50 m.
  • 42. Leica DNA03 level Instruments used in tunnels geodetic underground network construction  Leica DNA03 levels and leica TC1201 total stations were used for the leveling and angle- distance measurements.  The accuracy of the measurements is typically ±0.3 mm/km for precise leveling and 1” for angles and 1 mm +2 ppm for distances with total stations.
  • 43. Image of Leica TC 1201 Total station. The network adjustment was also achieved using HANNA software developed by the Institute of Geodesy, University of Hannover.
  • 44. The construction and operation of tunnel projects can result in a damage to surfaces or sub surface structures. In a metropolitan city like Istanbul where housing and historical structures are very intensive. Hence it is very important to determine the deformations on the surface and in the structures due to bored tunnels. Deformations in tunnel borings occur in two ways; 1. Deformations on the surface due to volume loss 2. Deformations due to the pressure on the tunnel perimeter applied by the mass over the tunnel (f) DEFORMATIONS AND TRANSVERSAL PROFILES SURVEYS
  • 45. 1. Deformations on the surface due to volume loss The surface settlement trough assumes a bell-shaped curve centered on the tunnel axis. The surface settlement is determined as follows.
  • 46.  As-built surveys are prepared after the completion of a construction project. This survey shows the as-built locations of improvements and utilities as opposed to the designed location. The Transversal Profile survey  In this project the reference profile area was calculated as 38.046 m². According to this information the over profile and under profile areas were determined for each transversal profile.  The profile monitoring system consists of an optical technique using a high specification robotic total station (Leica TCA 1201). The transversal profile survey was executed every 7.5 m of the tunnel. The Leica TMS (Tunnel Measurement System) is used for data processing, as shown in fig.
  • 47.
  • 48.
  • 49.
  • 50.
  • 51.
  • 52.
  • 53.
  • 54.
  • 55.
  • 56. So this is the Case Studies of Marmaray tunnel BC1 project
  • 57. After the Marmaray project Turkey is starting a new project by using the same survey as mentioned above. It is similar to the BC1 project. It is signed to implementation on 26 Feb 2011.
  • 58. Special Thanks To R. Venu Gopal Sir