2. KY EDT Working Group Members Tour Anniston EDT
18 March: Four members of the Kentucky EDT Working Group toured the
Anniston, Alabama EDT facility. Members included: Rev. Robert Blythe
(2nd from left); Leslie Kaylor (4th from left); Craig Williams (5th from left);
and, Terry House (6th from left).
3. 6 May 2014
30% Design
EDT Working Group Meeting
In attendance were the following:
Robert Blythe, CDCAB; Jeff Brubaker, BGCAPP; Joe Elliott, Blue Grass Army Depot;
Doug Hindman, Kentucky Chemical Demilitarization Citizens' Advisory Commission
(CAC)/CDCAB; Debbie Hogan, BGCAPP; Terry House, CDCAB; Scott Jackson, CDCAB;
Leslie Kaylor, CDCAB; John McArthur, Bechtel Parsons Blue Grass (BPBG); Sarah Parke,
BGCAPP; Stephanie Parrett, BGCAPP; Chester Powell, CDCAB; Kevin Roberts, BPBG;
Regina Stivers, CDCAB; Daniel Walker, Kentucky Department for Environmental
Protection (KDEP); April Webb, KDEP; Craig Williams, CAC/CDCAB; Todd Williams, Blue
Grass Chemical Activity (BGCA).
Excerpts from this briefing include
4. O2SF Outside Operations Support Facility
ESB EDT Support Building
MH Monitoring House
ESM EDT Service Magazine
EEB EDT Enclosure Building
CON Control Room
TOF Treaty Office Facility
4
EDT and OPS Facilities
6. 6
EDT Enclosure Building (EEB)
Layout is based
on the Vendor’s
Preliminary
Design and Equipment
Layout Drawings
7. 7
Note: Our Scrap Conveyor
is turned 90 degrees from
the Cool Down Conveyor
Feed
Conveyor
Munitions
Lift
Dust
Collection
Scrap
Bin
Belt
Conveyor
Secondary
Containment
Buffer Tank
EDT Process Equipment Layout
10. Reverse angle
Spray Dryer Dosing Station
Spray Dryer Waste Drum
Quench Venturi
Bag House Waste Drum
Emergency
Water Tank
Bag House Filter
Spray Dryer
Thermal
Oxidizer
Scrubbers
10
OTS Process Equipment Layout
11. Activity Date
EDT CW Operations Jan – Oct 2017
Ramp-Up Period
Full Rate Period
Regulatory Testing
Over-Pack Processing
EDT Closure and Turn-Over Nov 2017 – May 2018
Decontamination
Restoration
De-staffing
System / Facility Turn Over
Main Plant CW Operations (forecasted Start date) Jan 2018
11
EDT Schedule and Key Milestones
12. Location: Anniston BGCAPP
Description SDC 1200 CM (Chemical Mobile) SDC 1200 C (Chemical)
Transportable unit Fix Facility unit
CW Net Explosive Wt. (NEW) 2.2 lb HE / 6.61 Propellant TBD (min, 2.2 lb HE / 6.61 Propellant)
Fragment Shield: Tube Shaped (sides only) Bowl Shaped (sides with a bottom)
DC Heater: 3 on the bottom of the DC 3 on the bottom plus additional on sides
Cooling Fan for Locking Ring: None Yes (added to minimize binding at high temps.)
LC1 and LC2 Vents to THO: No Yes
(to minimize/prevent agent migration to the Process
Ventilation)
Bypass valve around off-gas No Yes orifice:
(to minimize press in the chamber to minimize agent
migration to LC2)
Off-Gas Treatment System (OTS): Has a SDC 1200 sized OTS Has a larger SDC 2000 OTS (75% larger)
Thermal Oxidizer (THO): 162 ft3 321 ft3 (98% larger)
Bleed Water Tank: No Yes (added to support 24/7 operations)
Chiller to remove Condensate: No (collection pump to recycle H2O) Yes (added after the Neutral Scrubber)
Re-Heater after Chiller: None initially – installed later Included
Carbon Filter System: IONEX CD2000 IONEX CD4000
Building Type: Sprung Structure Steel Building
Building HVAC: No - Portable AC unit added Yes
Cascading Ventilation System: Vapor containment only Yes (with Category A, B, C, and D areas)
Number of Mustard Projectiles: 2,737 CW munitions processed Approx. 16,000 munitions to be processed
Agent Types: HD and HT Mustard H Mustard (with solids and heels)
DOT Bottles: None processed Two (2) are planned
12
EDT Unit Differences
(Anniston vs. BGCAPP)
13. The preceding slides are meant to highlight certain aspects of the 30%
design discussed at the EDT meeting.
A complete set of EDT slides from the 6 May meeting is available by
contacting the Outreach Office @ 626- 8944
-----
ADDITIONAL EDT ISSUE – What is the amount and the disposal plan for
Projectile Bodies resulting from EDT processing of Mustard.
Answer: Approximately 729 tons of “clean-for-release” scrap metal will
be generated from EDT processing and will be managed under the
Kentucky Administrative Regulations scrap metals exemption and sent
to a metal recycling facility.
14. EDT PERMIT MODIFICATION
Permit Issuance Timeframe
Part B, Class 3 Permit Modification to add a Subpart X typically have a
375 day regulatory review timeframe.
Potential time to review the EDT modification is contingent upon the
number of noticed of deficiency and technical completeness
of the application
15. EDT PERMIT STATUS
Post NEPA EA/FONSI
--
EDT Application Submitted: 14 March
Public Meeting Held: 14 April
CAC/CDCAB Comments Submitted: 14 May
Current Status: Comments Under Review (30 Days)
- -
Next Milestone
DRAFT Permit Issued = Begins 45 Day Comment Period